CONSTRUCTION OF ACCESS ROAD, DRAINAGE AND SUPPORTING FACILITIES AROUND MAIN GATE OF THE CENTRAL JAVA CFPP 2 X 1000 MW
1. CC will complete Construction Drawing for MC – 0 on 21 April 2022.
2. CC will complete Method Statements as follows: a. Survey: Awaiting for PTW. It will be completed on 20 April 2022 b. Earthwork, including equipment and schedule: Awaiting for PTW 3. CC also waiting for a Periodic ID Card – Staff and Temporary ID Card - Workers from Nawakara. BPI – Security Team will support expediting the process. 4. Temporary fence will be installed on 20 April 2022. 5. Heavy Equipment, as follows: a. Excavator PC 200 (1 Unit) and Operator, including license will be provided on 20 April 2022. b. Dump Trucks 8T: partially depend on-site condition. 6. Genset 5000 Watt Contractor will coordinate with BPI – HSE Team prior to operation. 7. Color of safety helmet will be discussed with BPI – HSE Team. 8. Contractor shall revise Construction Schedule, as follows: a. Earthwork of east area b. Curb, etc shall be completed on Week 8