Professional Documents
Culture Documents
The first three steps, which constitute the planning stage, are especially important.
The length of the startup period, from when the equipment is installed until it is in
stable operation, is one of the elements that increase or reduce the LCC.
Technology today is moving so fast that falling behind production schedules can
have a major impact on business. This is why MP design explicitly addresses the
challenge of reducing equipment efficiency shortfalls and commissioning control
costs arising during startup. Commissioning control is regarded not as a separate
entity, but as part of the equipment’s LCC.
The purpose of design reviews is to catch any problems that have slipped through
the MP design net so that they are not carried over to the commissioning stage.
This ensures that once the equipment has been installed, an immediate, ‘vertical’
startup can be achieved. In other words, instead of leaving the identification of
problems to the commissioning stage after installation and adjustment, thorough
design reviews are carried out before installation.
As Figure “Design Review and Startup Period” shows, the design reviews at each
stage can be ranked in descending order of importance as follows: (1) design, (2)
fabrication, (3) witnessed test-run, (4) installation. This underlines the crucial
importance of the review carried out at the design stage.
Step 1 is the crucial stage at which the equipment plan is formulated and finalized,
based on the company’s annual and mid-term business plans. In general,
companies tend to put the cart before the horse and give too much weight to the
budget framework. Estimates are made without examining the proposals
thoroughly enough, and it often proves necessary to correct the details, the amount
budgeted, the time-frame and other parameters after the budget has been decided.
To avoid this scenario, the MP design aims to achieve higher planning precision by
focusing on the following:
(1) Equipment engineers should get involved early in the product development or
improvement process (from the conceptual design stage on) and all ready make a
start on designing the equipment.
(2) To this end, the purpose and necessity of the investment should be made
explicit, as should the economic requirements the equipment must satisfy (in terms
of LCC and LCP), and more than one proposal should be considered.
(4) A design review should be carried out by knowledgeable staff from the relevant
departments. This design review should include a thorough investigation of the
appropriateness of each proposed investment, its future potential, the degree of
technical difficulty it presents, its necessity, how economical it is, the order and
schedule in which it should be carried out, and so forth. Only after all this
information has been carefully clarified should the most appropriate proposal be
selected. Prototypes fabricated on experimental equipment should then be
assessed, and technical information from internal and external sources regarding
this and similar equipment should be carefully studied to flesh out the proposal to
be implemented. Figure “A Typical Investment Proposal Comparison Table” shows
an example of a proposal comparison table prepared at this stage.
A Typical Investment Proposal Comparison Table
Once the equipment investment plan has been approved, it is time to decide on the
equipment design and fabrication specifications, based on the investment proposal
comparison table drawn up in Step 1. When this has been done, the second design
review should be used to check that none of the items in the equipment design and
fabrication specifications has been overlooked. The design and fabrication
specifications should then be incorporated into the equipment concept, improving
the precision of the design (see Figure “Detailed Flow Diagram of Action Plan”).
1. Process Diagram This clarifies the sequence and limits of each process.
2. Process QA matrix This clarifies the relationships between product quality and
process. Figure “Process QA Matrix” shows a typical QA Matrix.
3. 4-M Analysis The Process QA Matrix may show that certain processes are heavily
implicated in the generation of defectives. In this case, the 4-M Analysis will show how
these defects relate to the 4 Ms and will clarify the equipment conditions needed to
stop them from being produced. Figure “4-M Analysis” shows a typical 4-M Analysis.
4. Process FMEA The Process FMEA further quantifies the degree of risk posed by the
problems identified in the 4-M Analysis. This information is very useful in evaluating
the equipment concept. If any item fails to meet the assessment criteria, the issue
should be addressed, and a re-evaluation carried out. Figure “Process FMEA” shows
a typical Process FMEA.
5. Record of Corrections Made to the Equipment Design, and Action Taken Problems
thrown up by assessing the equipment specification concept and carrying out the
second design review should be carefully addressed in the equipment design
specifications, using a form of the type shown in Figure “Record of Corrections Made
to Equipment Design, and Action Taken”.
Process QA Matrix
4-M Analysis
Process FMEA
Record of Corrections Made to Equipment Design, and Action Taken
The design stage covers the period from receiving budget approval to just before
embarking on fabrication.
1. Formulate the basic design, based on the equipment specification, and draw up the
implementation budget. At this point, an equipment FMEA (see Figure “The Anatomy
of an MP Information Utilization System” in lesson 3.5) should be carried out to find
out how the system operation, safety, product quality, and other parameters would be
affected if a failure were to occur in an equipment system, subsystem, or section. Any
problems identified should be addressed in the design. Equipment layout
considerations should also be thought through in-depth at this stage. Typical
considerations include the format in which raw materials will arrive; where they are to
be stored and by what route they should be conveyed to the production line; how the
power and other utilities are to be supplied; and how the finished products are to be
packaged, stored and shipped out.
2. In the design review carried out after formulating the basic design, check that nothing
has been overlooked regarding the equipment’s reliability, maintainability, operability,
safety, economy, flexibility, and conceptual design requirements. The next step will be
to flesh out the basic design.
3. Building on the basic design, formulate the detailed design. At this point, an FMEA
(see Figure “Typical FMEA (for Components)”) should be carried out on the
equipment’s components. Besides improving the reliability of the parts, this process
includes examining their factory- friendliness and making any necessary changes to
the detailed design. To ensure that MP information is not overlooked, make full use of
available design standards, collections of design expertise, and common
specifications. This will help to make the design as precise as possible and eliminate
the individual differences that tend to creep in when many designers are working on a
project. This is the stage of the design process at which you will need most outside
help from construction companies and other specialist firms. It is important to conduct
the design review very thoroughly, based on a relationship of trust between all
concerned and underpinned by the knowledge and experience of all parties.
4. In the fourth design review, after the detailed design has been formulated, have the
members of staff directly involved – in the maintenance, manufacturing, safety,
environment, and technology departments – get together and work up the design,
making sure that nothing has been overlooked concerning the basic design
requirements concerning reliability, maintainability, operability, safety, and other
attributes.