1 Commissioning of 12 PSS under ELITE NEXT 100 3/31/2017 2 Achievement of Pole Progress - 100/Day Regular 3 Handing over of 4 PSS already test charged 3/31/2017 4 Preparation of "AS BUILT" Drawings for 16 PSS 3/31/2017
Progress review : Target Date
1 Forest Clearances & ROW Issues - All PSS 3/31/2017 2 Joint Measurement Certiciation from Customer Regular 3 S/c Measurement Certification & Reconciliation 3/31/2017 4 Requirement of Material at site 5