Agenda for Discussion in the Staff review Meeting

Project Objectives : Target Date


1 Commissioning of 12 PSS under ELITE NEXT 100 3/31/2017
2 Achievement of Pole Progress - 100/Day Regular
3 Handing over of 4 PSS already test charged 3/31/2017
4 Preparation of "AS BUILT" Drawings for 16 PSS 3/31/2017

Progress review : Target Date


1 Forest Clearances & ROW Issues - All PSS 3/31/2017
2 Joint Measurement Certiciation from Customer Regular
3 S/c Measurement Certification & Reconciliation 3/31/2017
4 Requirement of Material at site
5