AKL SCO PROJECT DARAIL AND TANGIR

PROGRESS REPORT
TANGIR SECTION Remarks( if any
total alignment 280
total pits done 280
total poles installed 255
poles remaining 25
total poles received 296 32 poles received from KKH pak china project
poles required NIL
DARAIL SECTION
total alignment 370 alignment issue not resolved yet .
total pits done 370
total poles installed 188
poles remaining 182
total poles received 395 3 trucks *70 , 1 truck*84, 1 truck*75+26
poles required NIL

CEMENT DETAILS
TOTAL CEMENT RECEIVED
1800 BAGS
FROM FACTORY
SHIFTED TO DARAIL BY
410
ISMAIL CONTRACTOR
CONTRACTOR FAZAL
365
DARAIL
CONTRACTOR ABDUL MALIK
818
TANGIR
RAHAT FOR PAK CHINA 40
IBRAHIM/ MIR WALI PAK
156
CHINA SHATIAL
IN STOCK 11 7 BAGS DAMAGED IN UNLOADING
TOTAL 1800