You are on page 1of 3

No Uraian Pekerjaan Sat

Minggu Senin Selasa Rabu Kamis Jum'at


3 4 5 6 7 8
A INLET INTAKE
1 Galian Terowongan m
2 Steel Support set
3 Wiremesh m2
4 Shotcrete m2
5 Rockbolt titik
B OUTLET INTAKE
1 Galian Terowongan m 0.80 0.70 1.00
2 Steel Support set 1.00 1.00 1.00
3 Wiremesh m2 14.45 14.45
4 Shotcrete m2 14.45
5 Rockbolt titik
SISA GALIAN TEROWONGAN 375.00 375.00 375.00 374.20 373.50 372.50 372.50
Progres Pekerjaan
Mei
Sabtu Rata-Rata Minggu Senin Selasa Rabu Kamis Jum'at Sabtu Rata-Rata
9 Mingguan 10 11 12 13 14 15 16 Mingguan

1.00 0.88 1.50 2.00 1.75


1.00 1.00 1.00 1.00 1.00 1.00
14.45 14.45 14.45 28.91 14.45 19.27
14.45 16.50 70.22 43.36

371.50 370.00 368.00 368.00 368.00 368.00 368.00 368.00


Total Produktivitas

-
-
-
-
-

7.00 1.17
7.00 1.00
101.18 16.86
101.18 33.73
-