Professional Documents
Culture Documents
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
CONSTRUCTION
ENTREPRENEURSHIP
Profit - Tax +
Depreciation 4,30,000.00 3,36,000.00 2,80,000.00 2,49,000.00 1,99,000.00
(₹)
The initial investment of ₹ 14,00,000.00/- is likely to be received after the 6th year, i.e., four
years after the project implementation.
Cumulative Profit (4 years after implementation) = ₹ 12,95,000.00
Cumulative Profit (5 years after implementation) = ₹ 14,94,000.00
Difference = ₹ 1,99,000.00
• Profit after tax is the average annual after-tax benefit over the life of the
project.
• The entire life of the project is taken into account.
Example:
There are 3 projects, A, B & C, whose details are given below. Compare the
3 projects by ARR method select the most beneficial.
Profit after Tax
Life of the Project Project A Project B Project C
4 Years 5 Years 6 Years
1st Year ₹ 4,00,000.00 ₹ 3,00,000.00 ₹ 2,50,000.00
2nd Year ₹ 4,50,000.00 ₹ 4,50,000.00 ₹ 3,00,000.00
3rd Year ₹ 5,00,000.00 ₹ 5,00,000.00 ₹ 4,00,000.00
4th Year ₹ 4,50,000.00 ₹ 5,50,000.00 ₹ 5,00,000.00
5th Year - ₹ 5,00,000.00 ₹ 3,00,000.00
6th Year - - ₹ 2,50,000.00
₹ 18,00,000.00 ₹ 23,00,000.00 ₹ 20,00,000.00
Book Value of Investment
Life of the Project
Project A Project B Project C
1st Year ₹ 15,00,000.00 ₹ 12,00,000.00 ₹ 10,00,000.00
2nd Year ₹ 13,50,000.00 ₹ 10,80,000.00 ₹ 9,00,000.00
3rd Year ₹ 12,15,000.00 ₹ 9,72,000.00 ₹ 8,10,000.00
4th Year ₹ 10,93,500.00 ₹ 8,74,800.00 ₹7,29,000.00
5th Year - ₹ 7,87,320.00 ₹ 6,56,100.00
6th Year - - ₹ 5,90,490.00
Solution:
Project A Project B Project C
Total Profit over the
₹ 18,00,000.00 ₹ 23,00,000.00 ₹ 20,00,000.00
life of the project
[10,000.00 +
[12,00,000.00 +
[15,00,000.00 + 9,00,000.00 +
10,80,000.00 +
13,50,000.00 + 8,10,000.00 +
9,72,000.00 +
Avg. Investment 12,15,000.00 + 7,29,000.00 +
8,74,800.00 +
10,93,500.00] ÷ 4 6,56,100.00 +
7,87,320.00] ÷ 5
= ₹ 12.89.625.00 5,90,490.00] ÷ 6
= ₹ 9,82,824.00
= ₹ 7,80,932.00
Where, CF1, CF2…. Future cash inflows occurring at the end of first year, second
year…. etc.
n = life of the project in years
r = discount rate (cost of capital)
CF0 = Present Cash Outflow
NPV = 0, it indicates that the present cash outflow & the present value of future
cash inflows are equal
NPV < 1, it indicates that the present value of future cash inflows is less than
the present cash outflow
NPV > 1, it indicates that the present value of future cash inflows is more than
the present cash outflow
Example:
Compare project A & B using NPV method.
Project A:
Investment on the project: ₹ 10,00,000.00
Life of the Project : 5 years
Cost of Capital : 15 %
Year 1 2 3 4 5
Cash
2,00,000.00 3,00,000.00 4,00,000.00 3,00,000.00 1,00,000.00
Inflow (₹)
Project B:
Investment on the project: ₹ 10,00,000.00
Life of the Project : 5 years
Cost of Capital : 13 %
Year 1 2 3 4 5
Cash
3,00,000.00 4,00,000.00 4,00,000.00 3,00,000.00 2,00,000.00
Inflow (₹)
Solution:
Project A
Present value of future cash inflows:
𝐶𝐹1 𝐶𝐹2 𝐶𝐹3 𝐶𝐹4 𝐶𝐹5
NPV = [( +( + +( +( ] − 𝐶𝐹0
1+𝑟 )1 1+𝑟 )2 (1+𝑟 )3 1+𝑟 )4 1+𝑟 )5
2,00,000 3,00,000 4,00,000 3,00,000 1,00,000
= [( +( + +( +( ]
1+0.15)1 1+0.15)2 (1+0.15)3 1+0.15)4 1+0.15)5
− 10,00,000
= - ₹ 1,14,998.00
The NPV is negative & hence the project should not be taken up.
Project B
Present value of future cash inflows:
𝐶𝐹1 𝐶𝐹2 𝐶𝐹3 𝐶𝐹4 𝐶𝐹5
NPV = [( +( + +( +( ] − 𝐶𝐹0
1+𝑟 )1 1+𝑟 )2 (1+𝑟 )3 1+𝑟 )4 1+𝑟 )5
− 10,00,000
= ₹ 1,48,506.00
Since, the NPV for project B is far better than project A, project B shall be selected
for implementation.
ROLE OF DEPRICIATION IN PAYBACK PERIOD
• All businesses need to consider depreciation within their accounting and forecasts, as
it will impact the value of goods over time.
• However, depreciation isn’t a loss of value in cash terms- you haven’t actually lost
physical money on that product you own.
• Therefore, when calculating cash flows for payback periods, we need to add
depreciation back into the equation.
Example- A laptop owned depreciates but we don’t lose physical money on that laptop.
Example- If a product costs Rs.1 Crore to build & make a profit of Rs.6,00,000 after
depreciation of 10% but before tax at 30%, the payback period would be;
Profit before tax = Rs.6,00,000 less tax = (600000*30%) = Rs.1,80,000
Profit after tax = Rs.4,20,000
Add depreciation = (1,00,00,000*10%) = Rs.10,00,000
Total cash flow = Rs.14,20,000
𝑇𝑜𝑡𝑎𝑙 𝐼𝑛𝑣𝑒𝑠𝑡𝑚𝑒𝑛𝑡
Payback Period = = 10000000/14,20,000 = 7.04 year approximately
𝑇𝑜𝑡𝑎𝑙 𝐶𝑎𝑠ℎ 𝐹𝑙𝑜𝑤
RISK MANAGEMENT IN
CONSTRUCTION
4
PROJECT RISK SOURCES
External Environment
External Environment
Internal Environment Unknown
Predictable sources
Uncertainties
5
PROJECT RISK BREAKDOWN STRUCTURE
6
TYPES OF PROJECT RISK
› Project completion Risk
Completing the project in time & within the estimated cost
itself is a major achievement.
A project that is delayed will result in time overrun resulting
into cost overrun.
› Project Scope Risk
High complexity, ill-defined project scope, frequent
changes, no analysis of changes & problems in quality
control.
7
TYPES OF PROJECT RISK
› Design & Specification Risk
Inadequate design information, inclusion of new
construction technology, unrealistic specifications, poor
design, design changes.
› Quality Risk
No quality assurance plan, poor quality materials,
absence of quality testing laboratory, poor quality control,
problems in re-working of defects during construction.
8
TYPES OF PROJECT RISK
› Time Overrun Risk
Inaccurate activity time estimates, unrealistic time
schedule, incomplete work breakdown structure, poor
resource allocation, incomplete assessment of project time,
inflexible project plans, inability to take timely corrective
action.
› Cost Overrun Risk
Inaccurate cost estimates, inadequate cost planning &
control, delay in project completion, unprecedented
changes.
9
TYPES OF PROJECT RISK
› Leadership Risk
No project vision, no team building, poor motivation of
participants, limited authority/control of project manager,
poor industrial relations, unsafe working conditions, lack of
co-ordination.
› Organizational Risk
Inappropriate organization network, poor allocation of
tasks & responsibilities, lack of competent persons, no
project manual/documented procedures/processes.
10
TYPES OF PROJECT RISK
› Resource & Utilization Risk
Inadequate & low quality procurement of resources, non-
availability of spare parts, transshipment delays, wastage.
Shortage of raw materials may lead to reduction in
capacity utilization & higher cost of production, which
results in profit estimates going wrong. Shortage of power,
fuel & skilled manpower will also affect the project.
› Technology Risk
Inadequate information on new technology, non-
replacement of old technology, non-availability of
competent & professional staff to use new technology, lack
of managerial skills. 11
TYPES OF PROJECT RISK
› Contractual Risk
Non-standard & inconsistent conditions of contract, delay
in site possession, no credit worthy contractor, insufficient
insurance & surety, extra work variations.
› Force Majeure & Ecological Risk
Acts of God such as earthquakes, floods, land-slides,
ecological damages, epidemics, etc.
› Exchange Rate Risk
Exchange rate risk (currency risk) is the risk arising from
currency fluctuations. Volatile exchange rates reduce cost
& profitability advantages gained over years of hard work.12
TYPES OF PROJECT RISK
› Political, Legal & Social Risk
Changes in government, policies, regulations, joint venture
rules, risks under criminal law, pollution & waste
management, bribe & corruption.
› Financial & Economic Risk
Investment risk, inflation, escalation of prices, local &
international taxes, cash flow problems.
› Safety & Health Risk
Unsafe working conditions, healthcare & environment
protection, absence of safety audit, accidents, strikes,
security, fire fighting capability & disaster preparedness.
13
TYPES OF PROJECT RISK
› Funding Failure Risk
Lenders not comfortable with project viability, high interest
rate, partners conflict, revenue shortfalls.
› Communication & Network Failure Risk
Non-availability of antivirus software to safeguard office
computer system, data loss due to network breakdown, no
back-up data available, high fluctuations in electric supply,
internet servers breakdown, non-compatibilty of software
with the hardware purchased, ineffective management
information system
14
RISK EXPOSURE EXAMPLE
New state
government may Redesigning may 0.2*Rs.1,00,000=
20%
change the cost Rs.1,00,000 Rs.20,000
regulatory policy
15
RISK ASSESSMENT APPROACH
› Risk assessment involves overall ranking of risks using
qualitative assessment approach & quantifying the risk
exposures for mitigating high exposure risks for developing
risk exposure plan.
› Risk analysis approaches vary with the purpose & the
project.
› The choice of the techniques for risk analysis is dependent
on the nature of the problem being modelled, the
amount & reliability of available information & the nature
of the output required.
› The particular needs of the client & the type of decision to
be made will determine the nature of the output that is
required. 16
RISK ASSESMENT TECHNIQUES
RISK PARAMETER RISK ASSESSMENT TECHNIQUES
17
RISK MITIGATION
› Risk mitigation measures (steps) aim at minimizing the loss,
damage or disruption in a project due to unforeseen
events. The risk mitigation measures are:
1. Risk Transfer
2. Risk Deferred
3. Risk Reduction
4. Risk Acceptance
5. Risk Avoidance
6. Risk Sharing
18
RISK MITIGATION
1. Risk Transferred
Project risks can be transferred to someone who is more
capable of dealing with such problems, such as specialized
sub-contractors, designers, material suppliers or passing the
risk to insurance firms. For example, the risk can be
transferred:
› To a contractor or designer by client
› To a sub-contractor by the contractor
› To insurance companies or banks by the client, contractor
or sub-contractor
19
RISK MITIGATION
1. Risk Transferred
Some of the construction risk protection, which insurance
companies provide cover, include, but are not limited to
the following:
▪ Property Risk- Fire, explosions, dropping of loads by tower
cranes, impact damage & collapse of plant, theft, transit
risk.
▪ Performance related- Design, landslide, collapse,
vibrations, breakdown of construction equipment.
▪ Financial risk- Loss or Profit margin
20
RISK MITIGATION
▪ Commercial Risk- Client not meeting obligations, delay in
settlement of claims, money & securities & performance
bond.
▪ Human Risk- Accidents, health & safety, workers
compensation, third party liability.
▪ Environment Related- Earthquakes, floods, wind, storms,
epidemics requiring personal safety & health care.
▪ Ground Related- Underground water courses, locations
with geological faults, proximity to roadways & railways,
piling processes.
▪ Professional Liability Risk- Professional errors & omissions
inclusive of defence cost from claims 21
RISK MITIGATION
2. Risk Deferred
▪ Certain projects risks can be deferred by time.
▪ Activities can be moved to a later date in the project
when the adverse effects of events may be minimized or
reduced.
▪ Example- road bitumen paving scheduled during rainy
season can be postponed to a different season in the
year, when there is less moisture.
22
RISK MITIGATION
3. Risk Reduction
▪ Project risk reduction aims to reduce either the probability
of risk occurrence or the adverse impact on the project or
a combination of both.
▪ Example- a client may cover the risk of unknown
underground soil conditions by suitably wording the
contract
23
RISK MITIGATION
4. Risk Acceptance
▪ Once the risks have been identified & their adverse
effects assessed, a contingency plan to encounter them
has to be organized, developed & implemented.
▪ Risk acceptance may arise due to, no alternative
available, cost to transfer risk is high, risk occurrence
probability is low etc.
▪ Unidentified risks fall in the category or risks accepted by
the client.
24
RISK MITIGATION
5. Risk Avoidance
▪ Risks can be avoided in some cases, by taking
appropriate action such as changing designs, materials,
technology & construction methods that may involve
additional costs.
6. Risk Sharing
▪ A risk may be taken when it is impractical for one party to
control the risk.
▪ In such cases, a risk can be managed by two or more
parties.
▪ The client can also retain a part of the risk. 25
RISK REGISTER
26
BENEFITS OF MANAGING PROJECT RISK
› The risk response development process gives an insight
into the project management process.
› A pre-planned contingency plan provides clear definition
of the specific risks associated with a project.
› A fully documented risk management process, builds up a
profile of past risk to allow better modelling for future
projects.
› Risk response decisions are supported by a thorough
analysis of available data.
› It encourages problem solving & provides innovative
solutions to the risk problems in a project.
› A risk reporting framework avoids risk shocks 27
THANK YOU!
28
BIDDING IN CONSTRUCTION
• Direct losses are the losses which are paid to the workers for compensation
& paid for medical expenses incurred on the workers.
• Direct losses are the losses which are paid to the workers for compensation
& paid for medical expenses incurred on the workers.
• Overwork/overtime by workers
• Negligence/not alertness
• Act of God
PREVENTIVE MEASURES OF SAFETY
• Safety Audit
• Safety Programme
PROJECT SAFETY MANUAL
• Project Safety Manual include a set of minimum safety standards &
guidelines to be followed for any project.
• This insurance provides insurance on all risks, i.e. on almost any sudden &
unforeseen loss or damage occurring to the property insured.
• This loss includes: fire, lightning & explosion, flood, rain, wind storm, snow
avalanche, earthquake, sand slide, rockslide, theft, burglary, bad
workmanship, lack of skill, human error.
CONTRACTORS ALL RISK INSURANCE (CAR)
• This loss does not includes: loss or damage due to war, strike, riots, loss or
damage due to willful negligence, loss or damage due to nuclear reaction,
radiation, claims due to penalty losses, replacement, rectification or repair
due to deficency in work.
MACHINERY BREAKDOWN INSURANCE
• Breakdown cover is offered on all type of installed machineries working in
fixed premises.
• Sometimes when a small but vital part of a machine fails, entire work
comes to a stand still.
• The policy may be for full machine or part thereof & it may be for a
period varying from 3 months to 12 months.
• This policy covers the actual losses suffered by the insured due to the
business interruption leading to:
1) Reduction in turnover
2) Increase in cost of working, resulting in loss of gross profit due to
breakdown.
LOSS OF PROFITS INSURANCE FOLLOWING MACHINERY
BREAKDOWN OR MACHINERY LOSS OF PROFITS POLICY
• Exclusions:
• This insurance policy do not provide coverage against loss/damage due to:
1. Electrical or mechanical breakdown
2. Normal wear & tear
3. While being tested
4. War or nuclear reaction
5. Willful negligence
• The coverage under this policy can also be extended for; third part
liability, owners surrounding property.
CONTRACTOR’S PLANT & MACHINERY INSURANCE
• While moving the equipment from one site to another, transit insurance
policy should be taken for covering losses/damages happening during
transit.
THANK YOU!
CONSTRUCTION SITE
RESOURCES
► It is also necessary that first aid kits are kept in the site engineer’s office.
Prof. Vihang Pathare
3
SITE LAYOUT
FACTORS AFFECTING SITE LAYOUT 4
2. Construction Methods:
► The construction can be either cast-in-situ or by precast elements.
► If it’s to be of precast elements, then provision for a casting yard should be included in the job
layout.
FACTORS AFFECTING SITE LAYOUT 5
► Areas for keeping the needed plant & equipment are to be chosen such that they serve the entire
project.
► Material storage areas are to be provided such that cross movements are avoided & their lead time is
the shortest.
► They should be well protected from damage due to atmospheric & weathering effects.
FACTORS AFFECTING SITE LAYOUT 6
4. Medical Facilities:
6. Temporary roads:
► To provide access from nearby road & to transport materials, manpower and machineries.
7. Other Facilities: Power Supply, Telephone connection, Drinking water, washroom etc.
ADVANTAGES OF A GOOD SITE 7
LAYOUT
► The client organization may need a small team for overall supervision & control, but the contractor,
who has been entrusted with the job of construction of project needs a larger team for controlling
labor, supervising work, timely supply & consumption of materials, co-ordination with client & local
authorities.
► The organization set-up for a construction project is temporary & ends after completion of the
project.
ORGANIZATION SET-UP 9
► The management team of the project is capable of handling the problems as they arise & its
members are experienced persons who responds speedily with changing situations & can take
immediate decisions.
CONTROLLING CONSTRUCTION PROJECT 10
► Control can be defined as management activity whereby the managers compare actual performance
against the planned one, find out the deviation & take corrective actions.
► An efficient control system improves productivity of men & materials, economizes allocation of resources,
provides yard-sticks for measuring performance, generates information for updating resource planning &
costing norms.
► This is a process which keeps the actual standard as nearly as possible to the predetermined standard
by strict supervision & control.
► It involves continuous checking & evaluation of actual results with the budget goals, thus helping in
corrective action.
CONTROL TECHNIQUES 13
3. Inventory Control:
► It is defined as the systematic location, storage & recording of goods in such a way that desired
degree of service can be made available at the minimum cost.
► The necessity of inventory control is to maintain a reserve (store) of goods that will ensure
production according to a production plan with the lowest possible ultimate cost.
CONTROL TECHNIQUES 14
► The systematic location, storage & recording of goods in such a way that desired degree of service can be
made to the operating shops (work centres) at minimum ultimate cost.
4. Quality Control:
► Quality control is defined as a management technique by means of which products of uniform acceptable
quality are produced.
► It is concerned with the making things right rather than discovering and rejecting those made wrong.
FUNCTIONS OF INVENTORY CONTROL 15
5. Lead time:
It is the time which takes the stock to reach from Recorder Point to Maximum stock Level.
STEPS IN INVENTORY CONTROL 18
Procurement Cost:
It includes,
1. Calling quotations
2. Processing quotations
3. Placing purchase orders
4. Receiving & inspecting
5. Verifying & payment of bills
6. Other incidental charges
ECONOMIC ORDERING QUANTITY 21