ASME ANDE-1 - A COMPLETELY NEW APPROACH TO PERSONNEL QUALIFICATION

Tomáš ZAVADIL Michael L. TURNBOW


ATG (Advanced Technology Group), s.r.o. Tennessee Valley Authority (Retired)
Prague, Czech Republic Hixson, TN

document, called ANDE-1 (4), represents one of the


ABSTRACT permissible qualification systems accepted by ASME Boiler
and Pressure Vessel (BPV) Code 2017 (together with SNT-TC-
ASME (American Society of Mechanical Engineers) 1A and ANSI / ASNT CP-189). For the ASME BPVC, ISO
Nondestructive Examination (NDE) and Quality Control (QC) 9712 is also acceptable, but only in limited extent.
Central Qualification and Certification Program (ANDE-1
Standard) is a new independent qualification system for NDT This article analyzes the ANDE-1 standard and compares
and QC personnel. It is the first to come with a requirement of it with other relevant qualification standards used in the EU,
performance-based experience of Nondestructive Testing especially ISO 9712. This article deals exclusively with the
(NDT) personnel on the basis of practical demonstration to NDT personnel qualification section and its conclusions
perform all required activities rather than length of experience. therefore cannot be related to QC personnel.
It also adds unflawed samples to the test sets in order to
simulate real situation in industrial practice, where decisions
about the acceptance is necessary. This article analyzes the 2 THE BACKGROUND OF CREATION
ANDE-1 Standard and compares it with other relevant
qualification standards used in the European Union (EU). The task of each qualification system without exception is
to prepare the NDT inspectors / operators to be able to carry out
1 INTRODUCTION their assigned tasks correctly and responsibly, to fully
understand their role of the NDT process and also to
The qualification of NDT personnel is, together with the comprehend their own personal roles and responsibilities and
qualification of welding personnel and welding coordination behave accordingly.
and inspection personnel, one of the most elaborate in industrial
practice. The reason is the crucial role of NDT (and welding) in However, NDT personnel often lack some of the above-
industry. Every company which delivers products to the mentioned qualities. The basic cause of most problems appears
European market is responsible for the operational safety of to be their lack of quality experience. This issue first appeared
their products. This requires skilled and experienced NDT widespread in the power industry 1982, when NDT personnel
personnel who can reliably verify the quality requirements of failed to detect intergranular stress corrosion cracking (IGSCC)
the semi-products and/or the final products. at the Nine Mile Point nuclear power plant. This leaded to a
pipe failure on March 20, 1982 and a two-year plant shutdown.
There are many of qualification systems, often distributed Even when the defects were clearly visible (the water leaking
into following two groups: independent qualification and from the pipe), NDT personnel were unable to detect those
certification and employer qualification and certification. ISO defects by the Ultrasonic Testing (UT). Subsequent assessment
9712 (1) (independent), SNT-TC-1A (2), and EN4179 / NAS (IGSCC qualification on service-removed samples) revealed
410 (3) (employer) are the most used in the EU. However, there that only ~18% of the personnel tested were able to reliably
are in fact even more qualification systems. detect >80% of the IGSCC despite the fact, that they were all
certified Level II or III (mostly according to SNT-TC-1A) and
ASME introduced in 2015 a new qualification standard, with many years of work experience.
which approaches in a brand new way to collection of
experience and requires independent verification, which is the Since 1982, there has been a growing concern about the
key weakness of most of the current qualification systems. This competence of NDT personnel. In an effort to address the

1 Copyright © 2018 ASME


qualification weaknesses, ASME published Section XI,
Appendix VIII (Performance Demonstration for Ultrasonic
Examination Systems) in 1989. Appendix VIII was
implemented as Performance Demonstration Initiative (PDI) in
1992 to evaluate NDT personnel eligibility to perform
inspections in nuclear power plants. Studies show, that “pass
rates for experienced certified personnel is rarely above 50% on
the first attempt for demonstration test that simulate field
examinations“ (6).

However, PDI only monitors the current state and does not
increase the quality of the qualification and experience. Despite
this, the industry has invested an estimated $150,000,000 USD
in performance demonstrations (5).

Recommended Practice SNT-TC-1A encourages the Figure 1 Example of JTA requirements for the UT method for
employer to modify the recommendations in the employer’s specific activities as the resulting knowledge requirements (K)
Written Practice and is one of the most common qualification and skills (S) and determination of difficulty (D), importance
systems implemented globally. However, Written Practice (I) and the appropriate frequency (F) (10).
requirements vary from employer to employer and provide the
opportunity for abuse. The multitude of variation makes it 3.1 ELIGIBILITY
essentially impossible to address weaknesses industry wide and
implement appropriate corrective action. The ASME/ANDE The primary requirement for eligibility is minimal
project team was founded in 2012 with the task of preparing a education. Qualification systems generally require basic
criteria document for the needs of pressure equipment industry. education (ability to read) with sufficient knowledge of
In 2012 this objective was re-evaluated and the required output mathematics (ISO 9712 paragraph 7.2.3). Nevertheless, training
became a completely new ASME/ANSI standard for the central centers often meet with problems of understanding basic
(independent) qualification of NDT personnel. mathematics such as simple proportion, trigonometric
functions, or single variable equations. ASME ANDE-1
The first version was released on November 18, 2015. The therefore requires from all applicants at least secondary
document was originally created as a universal one (8), but the education (paragraph 1-5.2).
pressure equipment remained an essential building component.
Training requirements, experience verification, final
3 HOW ASME ANDE-1 DIFFERS FROM OTHER examination and any other certification requirements must be
INDEPENDENT QUALIFICATION SYSTEMS based on the JTA (ANDE-1 paragraph 1-2.3). Thus, unlike ISO
9712, the certification body is not completely independent, but
Like ISO 9712, ANDE-1 qualification is divided into requirements of the SIS committee must be implemented
methods (ANDE-1 recognizes only ET, MT, PT, RT, UT, VT (ANDE-1 paragraphs 1-3.7). This approach is partly similar to
methods, i.e. methods with relevant industrial impact) and three the role of National Aerospace NDT Board (NANDTB),
qualification levels. Similar to ISO 9712 that divides the represented by primary contractors and type certificate holders,
qualification to industrial sectors, ANDE-1 recognizes who may partly enter the NDT qualification process, otherwise
industries (e.g. energy), which are further divided into sectors performed by the employer (EN4179 paragraphs 3.19 and 4.4.2
(e.g. power plants, fossil fuels, renewable sources, offshore, (3)).
etc.) and characteristic applications (e.g. production,
construction, maintenance, commissioning). ANDE-1 also demands more strict vision requirements
than most other systems. There are requirements for near as
For each combination of industry-sector-task ANDE-1 well as far vision acuity, and color differentiation / contrast.
defines method and level requirements for knowledge and When vision correction is necessary to pass the vision acuity
skills, and the corresponding need for qualification of examinations, the same vision correction device shall be worn
personnel. This includes content of classification using the Job during all testing (paragraph 1-1.6.a4). The employer is then
Task Analysis (JTA) methodology that is performed by a required to create a Written Practice or Eye Examination
Specific Industry Sector (SIS) committee (The SIS is a group of Program that defines internal vision requirements that will not
experts from industrial practice in the particular sector) (5,9). be in contradiction with this standard (paragraph 1-1.6.b1).
Therefore, it is clearly defined what abilities the operator must
possess to be able to perform in the particular sector / industry /
task.

2 Copyright © 2018 ASME


3.2 TRAINING

Training shall agree with the JTA program approved by the


Certification Authority (ASME) and SIS committee.

The training instructor is required to be a Level III


qualified in each NDT method he instructs to be eligible to
conduct the qualification of the personnel. Eligibility for
training is given either by the experience of an instructor at a
state educational institute or by an additional qualification with
a minimum of 40 hours of formal instruction including
communication skills and teaching abilities (paragraph 1-4.5).

This requirement reflects the fact that not everyone who is


a certified NDT professional is also a good instructor, who can
deliver the correct content in the limited time such that the
trainee understands it, and will be able to successfully apply it
in the future (11). Request for additional training in the field of Figure 2 Example Part of Qual Card for UT personnel
communication activities is therefore absolutely relevant. (conventional ultrasound), for testing of austenitic steel welds.
Unfortunately, this requirement should also be mandatory for (12)
college professors, who often do not know how to pass on their
knowledge adequately, and this requirement sadly does not This new approach brings a fundamental change to assure
apply to them, according to ANDE-1. sufficient practical experience of NDT personnel. It is, of
course, possible that one signature of sufficient experience
3.3 EXPERIENCE based on time range will only be replaced by a large series of
signatures from professional scope. For such copying,
An important change compared to other independent Responsible Level 3 will only have to get a good "potato"
qualification systems is the demonstration of experience based stamp. However, a completely different situation occurs, if
on performance, rather than on the length of time in industry. there will be demonstrated, that the operator was not able to,
let’s say, calibrate an ultrasonic device or set the DGS curve on
Each candidate, when submitting a request for the ANDE site. In the case of ISO 9712, the demonstration of experience is
examination, must also submit a completed Qualification / not binding to the employer and his Level 3 (if he even has one)
Continuity Card (abbreviated Qual Card; paragraph 1-4.2). to ensure the ability of his personnel to perform such tasks.
This document details the individual knowledge (must However, in the case of ANDE-1, there will be a documented
understand and be able to implement) and the skills (must be record before the inspection itself, that the operator had
able to do) that the candidate must master before being properly demonstrated his abilities to the Level 3. If during the
admitted to the examination. Thus, ANDE-1 requires inspection he would not be able to replicate such knowledge,
experience prior to the examination, unlike ISO 9712, which there is irrefutable proof that the employer through his Level 3
permits the acquisition of part of the experience after the inadequately prepared his NDT operator and can thus be driven
examination and allows reduction in experience as per the to direct responsibility. Sole worry about the simple
decision of the certification body (see ISO 9712 paragraph demonstration of possible fraud can lead to an increase in
7.3.1 and 7.3.3). employers' demands on the competence of their employees.

The Qualification Card must be completed and signed by 3.4 FINAL EXAMINATION
the responsible person, which may be either an ANDE Level 3
(5) or, in selected cases, an Authorized Inspector (e.g. Nuclear The ANDE-1 examination is divided into two parts, a
Power, ANDE-1 Mandatory attachment 1, Section I-2.5). written examination and a practical demonstration of abilities.
It does not distinguish between general and specific parts, but
the knowledge of regulations, standards, specifications and
codes continues to be required (paragraph 2-2.2.c). In both
cases, 80% is required in order to pass (2-2.2.d and 2-2.3.a1c),
unlike other systems, that usually require only 70% from each
test. Additionally, the examinations shall be developed and
validated using psychometric principles.

3 Copyright © 2018 ASME


ANDE-1 requires that the content of the final examination long-term documented problems with the competence of NDT
shall be in compliance with the JTA and the SIS committee, and personnel. In spite of its nature, however, it learned from many
the questions cover the full application of the method (ISO mistakes of ISO 9712 and equivalent systems and was inspired
9712 requires only a minimal number of questions, see by the advantages of employer qualification systems, soon to
ISO9712, paragraph 8.2). Per ANDE-1, the number of create a robust system able to examine the task of NDT
questions for individual methods and their endorsements personnel to carry out their work properly and responsibly and
mandatories can be divided according to the Quality Manual of also to understand roles and responsibilities delegated to them.
the certification body (Table 2-2.2-1). The examination is
carried out without aids, norms and standards, with only In particular, the document tightens the requirements for
exception being reference materials defined by the certification collecting experience in a fundamental way, because it changes
body (paragraphs 2-2.2.b). the whole concept of the satisfaction for the experience
requirement. ANDE-1 requires each candidate to demonstrate
The Practical Demonstration test samples used shall be knowledge and skills according to a defined Qual Card model,
representative of those encountered in the performance of NDT which is obtained under the supervision of the responsible
for the SIS activities that the applicant is seeking to qualify. person. This person confirms the verification of the acquisition
Practical demonstration abilities must be presented on at least of the given knowledge and skills by signing each individual
three samples (within ASME requirement is 5 (13)), which will task and thereby assumes responsibility for the full competence
contain a maximum of 1/3 of the samples with obligatory of his trainee.
detectable defects (paragraphs 2-2.3.a2h). This represents a
major change in the practical examination, as the applicant may ANDE-1 examination concept places greater demands on
not only decide which defect is unacceptable (ISO 9712 demonstrating knowledge (minimum 80%) using psychometric
requires a reportable defect without exceptions, see paragraphs principles and requires compliance with industry, sector and
8.2.3.3 and 8.2.3.4), but whether the defect in the test sample is related activities. At the same time, it requires the inclusion of
at all. Such a practical demonstration of abilities is much closer a sufficient number of examination specimens without
to reality in industrial practice when the NDT operator is reportable defects in the examination kits so that the applicant
pushed to find all relevant defects but also to minimize has to consider the possibility that the examination specimen is
evaluation mistakes that lead to increasing scrap rate and without flaws. By this means the examination would get much
therefore increased cost. closer to the actual industrial practice.

3.5 CERTIFICATION AND RECERTIFICATION ANDE-1 is fully aware that once acquired knowledge will
not last forever, and therefore requires its users to demonstrate
ASME ANDE-1 is an independent qualification system for competence by annually updated Qual Cards, like Employer
NDT personnel and QC inspection personnel. Certification is qualification systems (Annual Maintenance at EN 4179 or
carried out by an independent certification body, but at present Technical Performance Review in SNT-TC-1A) and
time only ASME has exclusive permission to do so (9). accreditation according to PRI NADCAP and PRI TPG.

The certificate is granted after all the certification ASME system ANDE-1 is currently in the implementation
requirements have been met. The certificate is issued for a phase for the Nuclear Specific Industry Sector (SIS).
period of 5 years (exclusive). In order to maintain validity of Provisional Level III applications are currently being accepted.
the certificate the applicant must send an updated Qual Card The SIS requirements for the Boiler Pressure Vessel and Piping
each year to ensure that the certificate maintains all the (BPVP) NDT is soon to follow.
knowledge and skills needed for work (paragraphs 1-6.2, or (9)
respectively). This principle is in compliance with Employer The only certification body is ASME and there is a reason
qualification system principles: Annual Maintenance according to believe that it will stay that way for several more years. How
to EN 4179 (paragraph 8.6) or NAS410, respectively, and the qualification regulation will be successful depends mainly
Technical Performance Evaluation recommended by the SNT- on the ability to penetrate the international market. Time will
TC-1A (paragraph 10). tell.

Similarly to ISO 9712 the ANDE-1 does not allow a ACKNOWLEDGEMENTS


significant interruption (for more than 24 months) and a breach
of the Code of conduct (paragraph 1-6.5). This article is based on the outcome of ATG task group
discussions to mark the 25th anniversary celebration of ATG
4 SUMMARY AND CONCLUSION held in 2017 in Prague, which was attended by former ASNT
president and ANDE-1 project leader Michael L. Turnbow.
ASME ANDE-1, a new independent (central) qualification
system for NDT and QC personnel, has been created to answer

4 Copyright © 2018 ASME


REFERENCES

1. ISO 9712: 2012. Nondestructive Testing - Qualification


and Certification of NDT personnel. June 2012.

2. ASNT SNT-TC-1A: 2016. Personnel Qualification and


Certification in Nondestructive Testing. March 2016.

3. EN4179: 2017. Aerospace series - Qualification and


approval of personnel for non-destructive testing.

4. ASME ANDE-1: 2015. ASME Nondestructive


Examination and Quality Control Central Qualification
and Certification Program. November 2015.

5. ML Turnbow. ANDE-1, An ASME Nondestructive


Examination and Quality Control Qualification and
Certification Standard. Conference PVP2014, Anaheim,
California, USA. July 20-24, 2014

6. Nondestructive Evaluation: A Review of NDE


Performance Demonstrations - NDE Round Robin Report.
EPRI, Palo Alto, CA2008, 1016969.

7. NDE Performance Demonstration Test for intergranular


stress Corrosion Cracking. EPRI, Palo Alto, Accession
Number ML100140091

8. ANDE Certification Program for Non-Destructive


Examination. Resources. (cit. 09/30/2017) URL: https:
//www.asme.org/shop/certification-
accreditation/certification-personnel/ande/resources

9. ML Turnbow. ANDE-1 ASME Nondestructive


Examination and Quality Control Qualification and
Certification Standard. NDTMA 2015 Conference, Las
Vegas,2015.(cit.09/30/2017)URL:http://www.ndtma.org/
wp-content/uploads/2015/02/Turnbow.pdf

10. Skills Commons. ASME/ANDE JTAs. (cit. 201709-30)


URL:https://www.skillscommons.org/handle/taaccct/9421

11. ZAVADIL T. Quality in qualification and certification of


NDT personnel. Proceedings of NDT for Safety 2016

12. Skills Commons. ASME / ANDE NDE Qual Cards. (cit.


201709-30)
URL:https://www.skillscommons.org/handle/taaccct/9334

13. ANDE Certification Program for Non-Destructive


Examination. ANDE Application Process & Testing.
(cit.09/30/2017)
URL:https://www.asme.org/shop/certification-
accreditation/personnel-certification/ande/ande-
application-process-testing

5 Copyright © 2018 ASME