FORM TECH - 7 STAFFING SCHEDULE (KEY EXPERTS)

No. Name of Staff Staff Input (In the form of a Bar Chart) 43 Total Staff Week Input
1 2 3 4 5 6 7 8 9 10 11 12 Office Field Total

Foreign

1 Team Leader [Office] 1 0.5 0.5 0.5 0.5 0.5 0.5 0.5 1 5.50 7.50
[Field] 1 0.5 0.5 2.00
2 Financial Expert [Office] 1 1 1 1 0.5 0.5 1 1 7.00 11.00
[Field] 1 1 1 1 4.00
3 Technical Expert [Office] 0.5 0.5 0.5 0.5 0.5 0.5 0.5 3.50 7.50
[Field] 1 1 1 1 4.00
4 Legal Expert [Office] 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 0.5 4.50 7.50
[Field] 1 1 1 3.00

Sub-total 20.50 13.00 33.50

Total in Staff Weeks 33.50

1 Full time

0.5 Part time

Page 1 of 1