GIS Design Procedure and Standards For FTTH Project

ITC
Prepared By: Qamar Munir

GIS Supervisor

Mob: - +966567265942
Capturing FTTH Network In GIS

1- Open ArcMap , Add GIS data and turn on Attribute Assistant tool from toolbar
2- Place FDT (ITC: Cabinet CAB-CUST-42U [Metro]) 7-10 meters from parcel line

Attributes:

1- NAME and User Label should be same LIKE(FDT004-KRADLS)

2- INSTALLATION_LOCATION (select from domain)

3-PO Number Like (10774)


4-RTP Number Like (ACC-00038)
5-District and Hay Name should be same (select from Hay Name Domain)
6-Region (should be Same for all GIS Layer)
7-City (should be Same for all GIS Layer)
8-Hay Name Arabic (should be Same for all GIS Layer)
9-Contractor Name (should be Same for all GIS Layer)
10-Asbuilt updated by (should be Same for all GIS Layer)
11-Asbuilt updated on (should be Same for all GIS Layer)
12-Rotation (Rotation is important for 4 Layers in GIS 1-FDT 2-Manhole 3-Customer_Location 4- FAT/Splice)
13- MIGRATION_STATUS should be “No” for all GIS Layer
14-Remarks this field available for all GIS Layer you can update for any feature if you have Remarks

3 - Place Manhole in GIS as per As-built civil drawing (Center point of the manhole must be on 2m offset from the parcel
line). Use codes for Manhole (MH001) / Handhole (HH001) and Mini manhole (MMH001)

Attributes:

1. Fill remaining all common attributes same as FDT.

4- Place trench in GIS (ITC: Trench 12x50mm [Metro]) as per As-built drawing and the length should match with civil
drawing and Work schedule –Civil (Offset from parcel is 2m)

Attributes:

2. Measured_Length
3. And fill remaining all common attributes same as FDT.
4. 1-From_Endpoint 2-To_Endpoint 3- From_Endpoint_Name 4- To_Endpoint_Name and USER_LABEL should be
update automatically, if not updating automatically then you need to check snapping on both ends and also
check attributes of manhole and FDT.
After draw Trench in GIS , Rotate FDT and Manholes and they should look according the below picture.

5- Drop Duct: Draw drop duct ITC: Drop Duct 2x20mm [Access] from MH to each building and Vacant lot (where civil is
existing in As-built drawing) at 2m offset from the parcel.

6- Add customer location on each end of drop duct make sure its properly snapped. And give the reference number as
per civil drawing. Fill out the following attributes

1-REF Number & Name & User label All should be same like (REF001)
2-And fill remaining all common attributes same as FDT.

3-GEOCODE (from survey sheet) (Geocode is important for 3 Layers in GIS 1-Customer_Location - 2-ODB 3-OSB)

4-Dwelling type (Single Dwelling unit or Multi Dwelling unit or Vacant Lot)
5-Enterprises type (RESIDENTIAL or COMMERCIAL or RESIDENTIAL + COMMERCIAL or UNKNOWN)
6-Street_Name (English) (Street Name is important for 3 Layers in GIS 1-Customer_Location - 2-ODB 3-OSB)
7-Street name Arabic (Street Name Arabic is important for 3 Layers in GIS 1-Customer_Location - 2-ODB 3-OSB)

8- Building_Number (Must be 4 digit) in case if it’s not 4 digits you have to add 0 in the start to make it 4 digits

( Before : 1 New: 0001)


It can be 5 digits if there is any alphabet letter like 2765A
(before: 14A New : 0014A )
9-Rotation

After draw Customer Location in GIS , Rotate Customer Location according the below picture.
7- Snap again all drop ducts with customer location. 1-From_Endpoint 2-To_Endpoint 3- From_Endpoint_Name 4-
To_Endpoint_Name and USER_LABEL should be update automatically, if not updating automatically then you need
to check snapping on both ends and also check attributes of manhole and customer location.

8- Drop Duct Attributes


After snapping add all attributes of drop duct.
1- Ref_Number REF001 and for Vacant Lot Write VL001
2- Tiles (BB034) from contractor work schedule also compare with as built drawing.
3- SPT Special Tiles (BB035) from contractor work schedule also compare with as built drawing.
4- Asphalt (from As-Built drawing) also can compare with contractor work schedule (asphalt column).
5- Measured_Length (should be equal to BB023 in Civil BOQ)
6- U-Guard (1.5 Meter) and Vacant Lot ( 0)
7- Concrete (Soil/dust or BB009 in Civil BOQ)
8- Drop Duct Number as shown in below Picture
9- Fill Remaining all common attributes (except street name English and Arabic)

9- ODB

Add ODB’s for each building (ODB location should be center point of customer location) Quantity and type should match
with as built CJD, Survey sheet, Routing Table.

Attributes:

1. ODB_NUMBER & User_Label should be same (and should match with REF number of customer location as
well). Example REF001 there should be ODB_Number ODB001
2. GEOCODE (From survey sheet)
3. Building Number (From survey sheet or Cable Drawing)
4. ODB type (4 Port or 24 Port)
5. Number of Ports (4 or 24)
6. POP name (From Feeder Schematic)
7. And fill remaining all common attributes same as customer location attributes.

10- OSB

Add OSB’s for each building (OSB location should be center point of ODB) Quantity and type should match with as built
CJD, Survey sheet, Routing Table.

Attributes:

1. OSB_NUMBER & User_Label should be same (Should match with ODB number as well). Example OSB001
there should be ODB_Number ODB001
2. GEOCODE (From survey sheet)
3. Building Number (From survey sheet or Cable Drawing)
4. OSB type (1:4 Port , 1:8 Port or 1:16 Port) (From survey sheet)
5. Number of Ports (4 ,8 or 16)
6. POP name (From Feeder Schematic)
7. And fill remaining all common attributes same as ODB attributes.

11-FAT

Add FAT inside each manhole and rotate as per manhole angel. It should properly have snapped on manhole center
point. And when you select The FAT in attribute table related MH number should appear by default.

Attributes:

1- FAT Number (FAT001, FAT002) (JC001, for any joint closure added on feeder cable)
2- User Label
3- All common attributes
4- Rotation
5- After draw FAT/Splice in GIS , Rotate FAT/Splice according the below picture.

12-Drop Cable:

From FAT to each ODB (offset must be 1 meter inside drop duct or 1 meter from parcel)

Attributes:

1- Length: (From Contractor work schedule – Cable without loop) Make sure 12F and 24 F both should be match
with BOQ. Also compare length with Cable Drawing.
2- Fiber Number: you can find fiber number from As-built cable drawing or from survey sheet, for all SDU write the
fiber number is this format (ODB001 = 1,73) (ODB002=2,74)
For All MDU (ODB003 = 3-4,75-76) in case if fibers are not used in sequence (ODB004= 5+43,77+115)
3- Remaining all common attributes must be filled as other features.
4- 1-From_Endpoint 2-To_Endpoint 3- From_Endpoint_Name 4- To_Endpoint_Name and USER_LABEL should be
update automatically, if not updating automatically then you need to check snapping on both ends and also
check attributes of FAT and ODB.
13-Main Cable (Distribution Cable – 144FOC / 288FOC)

Distribution cable starts from FDT and move to words first FAT of each cable. It should be on 0.5m offset on the outer
side of the trench and should be properly snapped on both ends (FDT and FAT)

Then from FAT001 to FAT002

When you draw the second cable it should be on 0.5m offset from first cable. And all cables should be in 5-meter area in
order to keep relationship with manhole’s from where the cables are passing.

all common attributes must be filled as other features. Update fiber number from JCD Drawing.

1-From_Endpoint 2-To_Endpoint 3- From_Endpoint_Name 4- To_Endpoint_Name and USER_LABEL should be update


automatically, if not updating automatically then you need to check snapping on both ends and also check attributes of
FDT and FAT.

14-Optical Cable Slack

After Capturing complete fiber with require Attributes, add Optical Cable Slack (LOOP) Over the Main Cable Near to
Related Manhole as mention in As-Built BOQ and Work Schedule Cable.xls

Add Optical Cable Slack In GIS as shown in below picture

15-T_DUCT (Table)
After capturing complete civil and fiber network in GIS create ducts for Trench and Drop Duct, Using this tool from

toolbar .

Attributes: -

OWNER

Super_Object if not updating by default then update “96848”

REMARK “TD” for Trench ducts and “DD” for Drop Duct

FDT Number

PO_Number

RTP

MIGRATION_STATUS if not updating by default then select “No” from domain value.

16-T_DuctCableAllocation (Table)

After Creating T_Ducts with require attributes in GIS Use this tool from toolbar to put cable inside related
duct. All drop cable put inside 1st T_duct of drop duct. For main cable 144FOC or 288FOC, fallow Duct Layout from As-
built Cable Drawing As shown in below Picture.

17-QC Report (GIS DATA MATCH WITH BOQ)

1-UPDATE QC Report (GIS DATA MATCH WITH BOQ) (Excel Format) Sample provided by ITC

18-Connectivity Sheet

1-use Connectivity Sheet (Excel Format) Sample provided by ITC

2-Fallow CJD and Routing table

3-GUID and User Label should match with GIS DATA.