You are on page 1of 26

EXCAVATION

Footing
B L H No. of ftgs. Volume
F1 1.10 1.10 1.50 4.00 7.26

F2 1.40 1.40 1.50 14.00 41.16

F3 1.50 1.50 1.55 3.00 10.46

58.88 m3

Wall Footing
H W L Volume
WF1 0.70 0.40 78.00 1.00 21.84
.
21.84 m3

TOTAL VOLUME OF EXCAVATED SOIL


80.72 m3
FORMWORKS
Footing
B L sides No. of ftgs. Volume
F1 1.00 0.40 4.00 4.00 6.40

F2 1.30 0.40 4.00 14.00 7.28

F3 1.50 0.45 4.00 3.00 2.03

15.71 m2
Column
C1 0.40 5.40 2.00 7.00 30.24
0.20 5.40 2.00 7.00 15.12
UC1 0.40 1.00 2.00 4.00 3.20
0.20 1.00 2.00 4.00 1.60
C2 0.35 5.40 2.00 5.00 18.90
0.35 5.40 2.00 5.00 18.90
UC2 0.35 1.00 2.00 1.00 0.70
0.35 1.00 2.00 1.00 0.70
C3 0.35 5.40 2.00 7.00 26.46
0.35 5.40 2.00 7.00 26.46
UC3 0.35 1.00 2.00 3.00 2.10
0.35 1.00 2.00 3.00 2.10
C4 0.35 5.40 2.00 2.00 7.56

154.04 m2

Footing Tie Beam


W H L No. of sides Volume
FTB1-Bot. 0.20 0.40 137.00 1.00 27.40
FTB1-Side 0.20 0.40 137.00 2.00 109.60
137.00 m2
Roof Beam
W/H L No. of sides Volume
RB1 0.40 19.15 2.00 15.32
0.20 19.15 1.00 3.83
RB2 0.40 5.90 2.00 4.72
0.20 5.90 1.00 1.18
RB3 0.40 17.80 2.00 14.24
0.20 17.80 1.00 3.56
RB4 0.40 5.50 1.00 2.20
0.20 5.50 1.00 1.10
RB5 0.40 4.00 2.00 3.20
0.20 4.00 1.00 0.80
RB6 0.40 23.40 2.00 18.72
0.20 23.40 1.00 4.68
RB7 0.40 17.70 2.00 14.16
0.20 17.70 1.00 3.54
RB8 0.40 5.50 2.00 4.40
0.20 5.50 1.00 1.10
RB9 0.40 18.70 2.00 14.96
0.20 18.70 1.00 3.74
RB10 0.40 6.50 2.00 5.20
0.30 6.50 1.00 1.95
RB11 0.40 19.00 2.00 15.20
0.20 19.00 1.00 3.80
RB12 0.40 11.20 2.00 8.96
0.30 11.20 1.00 3.36
RB13 0.40 11.20 2.00 8.96
0.30 11.20 1.00 3.36
RB14 0.40 33.60 2.00 26.88
0.20 33.60 1.00 6.72
0.45 12.80 2.00 11.52
0.30 12.80 1.00 3.84
RB15 0.40 21.60 2.00 17.28
0.20 21.60 1.00 4.32
URB1 0.40 5.50 2.00 4.40
0.20 5.50 2.00 2.20
URB2&3 0.40 11.00 2.00 8.80
0.20 11.00 2.00 4.40
URB4 0.40 5.50 2.00 4.40
0.25 5.50 2.00 2.75
URB5 0.40 18.20 2.00 14.56
0.25 18.20 2.00 9.10
URB6 0.40 16.50 2.00 13.20
0.20 18.20 2.00 7.28
RB 0.45 0.50 2.00 0.45
0.40 0.50 2.00 0.40
308.75 m2

Rc Concrete Canopy
W H L No. of sides Volume
0.95 33 1 31.35
31.35 m2

Rc Concrete Gutter
W H L No. of sides Volume
0.95 58 1 55.10
55.10 m2

TOTAL AREA COVERED


701.94 m2
CONCRETING
Footing
B L H No. of ftgs. Volume
F1 1.10 1.10 0.30 4.00 1.45
F2 1.40 1.40 0.30 14.00 8.23
F3 1.50 1.50 1.55 3.00 10.46

20.15 m3

Column
C1 0.20 0.40 5.40 7.00 21.17
UC1 0.20 0.40 1.00 4.00 1.28
C2 0.35 0.35 5.40 5.00 16.54
UC2 0.35 0.35 1.00 1.00 0.61
C3 0.35 0.35 5.40 7.00 32.41
UC3 0.35 0.35 1.00 3.00 1.10
C4 0.35 0.35 5.40 2.00 2.65

75.76 m3
Footing Tie Beam
W H L Volume
FTB1 0.20 0.40 137.00 10.96
WF1 0.15 0.45 78.00 5.27
16.23 m3 135.37
285.918
Roof Beam
W H L Volume
RB1 0.20 0.40 19.15 9.19
RB2 0.20 0.40 5.90 2.83
RB3 0.20 0.40 17.80 8.54
RB4 0.20 0.40 5.50 2.64
RB5 0.20 0.40 4.00 1.92
RB6 0.20 0.40 23.40 11.23
RB7 0.20 0.40 17.70 8.50
RB8 0.20 0.40 5.50 2.64
RB9 0.20 0.40 18.70 8.98
RB10 0.30 0.40 6.50 4.68
RB11 0.20 0.40 19.00 9.12
RB12 0.30 0.40 11.20 8.06
RB13 0.30 0.40 11.20 8.06
RB14 0.20 0.40 33.60 16.13
0.30 0.45 12.80 10.37
RB15 0.20 0.40 21.60 10.37
URB1 0.25 0.40 5.50 3.30
URB2&3 0.20 0.40 11.00 5.28
URB4 0.25 0.40 5.50 3.30
URB5 0.25 0.40 18.20 10.92
URB6 0.20 0.40 16.50 7.92
RB 0.40 0.45 10.80 11.66
165.65 m3

Slab
W H THK Volume
Rc Walls 31 1 0.15 27.90
Rc Canopy 10.81
Rc Gutter 5.80

44.51 m3

TOTAL VOLUME OF CONCRETE


322.29 m3

Lean Concrete
Footing
B L H No. of ftgs. Volume
F1 1.00 1.00 0.05 4.00 0.20
F2 1.30 1.50 0.05 14.00 1.37
F3 1.50 1.50 0.05 3.00 0.34

1.90 m3

Footing Tie Beam


W H L Volume
FTB1 0.04 0.05 137.00 1.44
WF1 0.04 0.05 78.00 0.82
2.26 m3

TOTAL VOLUME OF LEAN CONCRETE


4.16 m3
REINFORCING BAR

Bottom Bar Top Bar Cutting Length


Footing No. of ftgs.
@B @L @B @L @B @L
F1 6.00 6.00 1.00 1.00 4.00
F2 8.00 8.00 1.30 1.30 14.00
F3 9.00 9.00 1.50 1.50 3.00

Sub Total Length

32mm 25mm 20mm 16mm 12mm 10mm


6.31 3.85 2.47 1.58 0.89 0.62

No. of Vertical Cutting No. of


Column bars Length (m) columns
C1 6.00 7.30 4.00
6.00 6.00 3.00
C2 8.00 7.30 1.00
8.00 6.00 4.00
C3 12.00 7.30 3.00
12.00 6.00 4.00
C4 16.00 6.00 2.00

Cutting Length
Footing Tie Beam Top Bar Bottom Bar
top bott ex top
FTB 1 3.00 3.00 - -
WF1 3.00 - -

Cutting Length
Roof Beam Top Bar Bottom Bar
top bott ex top
RB 1 2.00 2.00 - - 21.35 21.35
RB 2 2.00 2.00 7.00 7.00
RB3 2.00 2.00 21.35 21.35
RB4 2.00 3.00 7.00 7.00
RB5 2.00 2.00 7.00 7.00
RB6 2.00 2.00 25.40 25.40
RB7 2.00 2.00 21.35 21.35
RB8 2.00 2.00 6.60 6.60
RB9 2.00 2.00 21.35 21.35
RB10 2.00 2.00 7.70 7.70
RB11 2.00 2.00 20.40 20.40
RB12 2.00 2.00 18.50 18.50
2.00 2.00 12.90 12.90
RB13 2.00 2.00 12.90 12.90
RB14 2.00 2.00 21.70 21.70
2.00 2.00 21.70 21.70
2.00 2.00 6.20 6.20
2.00 2.00 10.80 10.80
RB15 2.00 2.00 23.40 23.40
RB16 2.00 2.00 33.00 33.00
URB1 to 4 2.00 2.00 27.20 27.20
URB5 2.00 2.00 18.20 18.20
URB6 2.00 2.00 26.70 26.70
RB 2.00 2.00 6.20 6.20
5.00 3.00 9.00 9.00

Stirrups :
RC Canopy & RC Parapet wall :
Length (clear) No. of Cutting
splice Length
7.5 7.32 6.00
183 0.30 6.00
5 7.32 6.00
155 0.20 6.00
Stirrups RC Gutter:
5 7.32 6.00
38 0.20 6.00

12mm
18,470.90

TOTAL WEIGHT OF REINFORCEMENT BAR


16,791.73 KGS
.
Total Length
25mm 20mm 16mm
48.00
291.20
81.00
-
-
- - 420.20 m
663.92 -
Sub Total Weight (kgs) 663.92

Lateral

Total Length Length (clear) Cutting


No. of stirrups
25mm 20mm 16mm Length
175.20 44 4.00 176.00 1.30
108.00 42 3.00 126.00 1.30
58.40 44 1.00 44.00 1.40
192.00 42 4.00 168.00 1.40
- 262.80 44 3.00 132.00 1.40
288.00 42 4.00 168.00 1.40
192.00 42 2.00 84.00 1.40

- m
- 3,151.43 1,276.40 10mm
Sub Total Weight (kgs) 3,907.26

Stirrups :
ng Length No. of pcs per Length (clear) Cutting
Total Length No. of stirrups
ex bott cut Length
164.00 984.00 164.00 1 820.00 1.40
93.60 280.80 93.60 1 312.00 0.40
Sub Total 984.00
20mm 16mm 12mm 10mm
1,554.72 172.97
Sub Total Weight (kgs) 2,747.12 12mm

Stirrups :
ng Length No. of pcs per Length (clear) Cutting
Total Length No. of stirrups
ex bott cut Length
1.00 85.40 19.15 1 95.75 1.40
4.50 1.00 32.50 6.00 1 30.00 1.40
1.00 85.40 19.15 1 95.75 1.40
1.00 35.00 6.00 1 30.00 1.40
1.00 28.00 4.40 1 22.00 1.40
1.00 101.60 23.40 1 117.00 1.40
1.00 85.40 17.70 1 88.50 1.40
1.00 26.40 6.00 1 30.00 1.40
1.00 85.40 18.70 1 93.50 1.40
9.00 1.00 39.80 6.50 1 32.50 1.60
1.00 81.60 19.05 1 95.25 1.40
12.00 1.00 86.00 17.10 1 85.50 1.40
1.00 51.60 11.50 1 57.50 1.40
1.00 51.60 11.50 1 57.50 1.40
1.00 86.80 19.50 1 97.50 1.70
1.00 86.80 19.50 1 97.50 1.70
1.00 24.80 5.00 1 25.00 1.70
1.00 43.20 9.00 1 45.00 1.70
1.00 93.60 22.00 1 110.00 1.40
1.00 132.00 31.50 1 157.50 1.40
1.00 108.80 24.80 1 124.00 1.50
1.00 72.80 18.20 1 91.00 1.50
1.00 106.80 23.10 1 115.50 1.40
1.00 24.80 4.50 1 22.50 1.80
1.00 72.00 5.10 1 25.50 1.40
Sub Total 1,632.60
25mm 20mm 16mm 95.50
4,030.89 150.89
Sub Total Weight (kgs) 5,841.87 10mm

Stirrups :
SOG :
Length (clear) Cutting
Total No. of splice
Length
329.40 46 5.00 6.00
329.40 46 5.00 6.00
219.60
186.00

219.60
45.60

1,329.60 m

1,180.68 kgs 12mm


Total

228.80
163.80
61.60
235.20
184.80
235.20
117.60
1,227.00 m

755.83 kgs

Total

1,148.00
124.80
1,148.00 m

1,019.42 kgs

97.53
Total
97.53
134.05 115.61
42.00 115.61
134.05 109.00
42.00 109.00
30.80 66.26
163.80 66.26
123.90
42.00
130.90
52.00
133.35
119.70
80.50
80.50
165.75
165.75
42.50
76.50
154.00
220.50
186.00
136.50
161.70
40.50
35.70
2,694.95 m

1,660.09 kgs

Total

1,380.00
1,380.00

2,760.00 m

2,450.88 kgs
MASONRY
h L Less(D&W) Area
Front Elev. 4.20 13.05 17.43 37.38
5.60 6.00 33.60
Rear Elev. 5.60 5.60 2.97 28.39
Rightside 4.20 16.50 16.74 52.56
Left. 5.60 18.50 16.38 87.22
Interior 313.36
Plantbox 1.75 56.00 98.00
Parapet Walls 1.40 60.00 84.00
1.00 22.00 22.00
756.51 m2 794.34

No. of Pcs.
CHB 9,456.38 pcs.

Mortar Class B
Cement 770.13 bags
Sand 638.49 m3

Plastering Class B - 20mm thick 1,513.02 m2


Cement 363.12 bags
Sand 30.26 m3

SLAB ON GRADE
490.15 0.15 73.52
73.52 m3 77.20
Gravel Bedding
490.15 0.05 24.51
24.51 m3 25.73
ESTIMATE OF STRUCTURAL STEEL FOR TAPERED SECTION
Project Name: CBEC ADMINISTRATION BUILDING
Location : ISABELA
Standard weights (kgs/m2)
40mm 32mm 30mm 25mm 21mm 16mm 12mm
314.10 235.58 235.58 196.32 164.90 125.64 94.23
C-Purlins - 175x50x2.0 - weights per l.m
4.690
computed
Structure b1 b2 L no. of pcs. Area
weights (kgs)
STEEL TRUSS TYPE
TC & BC
2L1/2X1/2x6mm 434 2 868.00 3,845.24

Web member -
2L 1/2X1/2x3.3mm 395 2 790.00 2,212.00
-
-

C-Purlins
50mmx100mmx2.0mm 631 631.00 2,069.68

Rafter
50mmx150mm Channel Bar 96.00 1,516.80
-
Roofing Panels -
main roofing 18.6 22.00 409.20
5.3 18.70 99.11
Rafter Roofing 3 8.70 52.20
Wall Flushing 89.00 88.2
-

TOTAL KILOGRAMS
1.758
10mm 1.88 1.779
78.53 1.78 1.996
1.423 1.817
1.509 1.811
Total Weights 1.366 1.776
(kgs) 1.236 1.696
66 1.362 1.639
2L4x4x6mm 54.83 9.138333 1.339 1.618
3,845.24 2L4x4x10mm 89.49 14.915 1.202 1.653
2L2 1/2x2 1/2x6mm 35.04 5.84 1.136 1.629
2L65x65x6mm 1.096 1.598
2,212.00 6mm 47.116 7.852667 1.129 1.505
1.167 1.527
1.2 1.536
1.266 1.58
1.294 1.654
2,069.68 1.333 1.733
1.366 1.751
1.383 1.786
1,516.80 1.441 1.812
1.759 1.789
1.715 1.747
1.841 1.939

33.981 1.722
67.962 41.093
596.51

82.186
9,643.72
Summary of Material Estimates

Earthworks
Excavation 80.72 m3
Hauling of Excess Materials 238.28 m3
Backfilling 319.00 m3
Compaction 319.00 m2
Gravel Bedding 26.55 m3

Formworks 702.00 m2

Concreting
f'c = 3000 psi @ 28days
Lean Concrete 4.16 m3
Footings 20.15 m3
Footing tie Beam 16.23 m3
Slab on Grade 98.56 m3

f'c = 3500 psi @ 28days


Column/Pedestal 75.76 m3
Beams 165.65 m3
Slabs 44.51 m3

Masonry
Wall Area 756.51 m2
Plastered Area 1,513.02 m2 756.51

Painting
Wall Area Paintings 1,361.14 m2
Strucural Area Paintings 324.00
Rebars 16,791.73 kgs.

Structural Steel
Equal Bar / Rafter / Purlins kgs.

Roofing
main 560.51 m2
2nd Floor, Unit B26, Banawe de Sta. Rosa Bldg., F. Reyes Road, Brgy. Balibago, City of Sta. Rosa, Laguna

ADMIN BUILDING
TABLE - 1
EARTHWORK IN EXCAVATION & BACKFILLING
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
Earthwork in excavation, backfilling and disposal as per
1 specification, drawings and as directed by engineer for the
following
Earth works in excavation of Foundation for Admin Building
1.1 Cu.m. 80.72 380.00 30,673.60

Disposal of surplus excavated earth / rock beyond an initial lead of 1 km


and up to a lead of 5 km dumping and leveling the dumped soil and
1.2 Cu.m. 238.28 200.00 47,656.00
leveling the area from where the material is transported, complete with all
lifts as specified and directed by Engineer.

Backfilling around foundation and footing tie beam to proper grade and
level with excavated materials within 1 Km lead watering and ramming in
1.3 layers of 30 cm. Thickness to 80% maximum dry density by manual / Cu.m. 319.00 380.00 121,220.00
mechanical means, compaction with mechanized compaction machine,
dressing etc. complete is including transportation.

Slab on grade soil levelling and compaction it includes the removal of


weak materials from the surface , sub grade evaluation the section of
1.4 sq.m. 319.00 50.00 15,950.00
suitable materials for use as fill , proper compaction , control moisture
and providing flat uniform surface for concrete palcement.
Supply and filling sand/boulder/gravel under floors, in foundation and
footing tie beam
cost of sand/boulder/gravel transporting for all leads, loading, unloading,
spreading in layers in 25 cm loose thickness at all depths, watering,
1.5 compaction with mechanized compaction machine or manually to Cu.m. - -
minimum 80% of relative density dressing and leveling etc complete

a)     Sand Cu.m

b)    Boulder Cu.m


c)     Gravel Bedding (thick = 50mm) Cu.m 24.51 800.00 19,608.00
SUB TOTAL Cu.m. 235,107.60

TABLE - 2
CONCRETE WORKS
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures

Providing and placing concrete work including cost of labour,


materials and equipment for handling, transportation, batching,
mixing, placing, vibrating and curing, (excluding cost of centering,
2
shuttering and reinforcement) complete at all elevations as per
drawing, specifications unless specified otherwise and as directed
by Engineer-in-charge-in-charge for the following

Plain Cement Concrete with compressive strength of 20.7 Mpa (3000psi)


2.1 Cu.m. 73.52 4,950.00 363,924.00
@ 28days for SOG, Foundation, Footing Tie Beam & Lintel Beam

Plain Cement Concrete with compressive strength of 20.7 Mpa (2500psi)


Cu.m. 4.16 3,800.00 15,808.00
@ 28days for Lean Concrete
SUB TOTAL Cu.m. 379,732.00
TABLE – 3
FORMWORK
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
Supplying, fixing and removing formwork at any elevation including
3 all labour, material, scaffolding, etc., as per specifications and as
directed by Engineer-in-charge-in-charge for the following:

Ordinary formwork below and above finished ground floor level for
3.2 columns, beams, suspended floors, roofs, lintels, cantilevers, staircases, Sq.m 702.00 1,200.00 842,400.00
landings, balconies, etc., for all heights
SUB TOTAL Sq.m 842,400.00
TABLE - 4
REINFORCEMENT
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
REINFORCEMENTS
4

All reinforcement shall be hot rolled deformed high yield bars of grade
460 of BS 4449 with characteristic tensile strength not less than 460
N/mm2.Providing, Transporting from store, straightening, cutting,
4.1 bending, placing in position of any level, binding in position of tor steel KG 16,791.73 47.50 797,607.18
reinforcements including cost of binding wire, labour transportation to &
from stores etc complete all as per specifications, drawings and as
directed by Engineer
4.2 Transportation , houling of materials cost KG 16,791.73 1.50 25,187.60

SUB TOTAL 822,794.77


TABLE - 5
FABRICATION & INSTALLATION
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
5 Structural Steel Structure
Supply, fabrication & installation of equal bar, rafters & C-purlins
5.1 KG 9,643.72 87.50 843,825.50
(roofings)
5.2 Transportation , houling of materials cost KG 9,643.72 1.50 14,465.58
5.6 Supply, Ramp railing (35 linear Meter) KG -
SUB TOTAL KG 858,291.08
TABLE - 6
CHB WORK
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
CHBWORK MASONRY INCLUDING SUPPLY OF MATERIAL, COST
OF LABOUR, SCAFFOLDING ETC COMPLETE AS PER
6
SPECIFICATIONS, DRAWING AND AS DIRECTED BY Engineer-in-
charge FOR THE FOLLOWING
Laying of 150mm thick chb for outer walls including, mortar, rebars and 239.15
6.1 Sq.m 1,300.00 310,895.00
scafolds.
Laying of 150mm thick chb for inner walls including, mortar, rebars and 313.36
6.2 Sq.m 1,300.00 407,368.00
scafolds.
Laying of 150mm thick chb for Parapet walls including, mortar, rebars 106.00
6.3 Sq.m 1,300.00 137,800.00
and scafolds.
Laying of 100mm thick chb for Plantbox walls including, mortar, rebars 98.00
6.4 Sq.m -
and scafolds.
SUB TOTAL 856,063.00

TABLE - 7
CHB WORK
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
CHBWORK MASONRY INCLUDING SUPPLY OF MATERIAL, COST
OF LABOUR, SCAFFOLDING ETC COMPLETE AS PER
7
SPECIFICATIONS, DRAWING AND AS DIRECTED BY Engineer-in-
charge FOR THE FOLLOWING
Laying of 150mm thick chb for outer walls including, mortar, rebars and 239.15
7.1 Sq.m 1,300.00 310,895.00
scafolds.
Laying of 150mm thick chb for inner walls including, mortar, rebars and 313.36
7.2 Sq.m 1,300.00 407,368.00
scafolds.
Laying of 150mm thick chb for Parapet walls including, mortar, rebars 106.00
7.3 Sq.m 1,300.00 137,800.00
and scafolds.
Laying of 100mm thick chb for Plantbox walls including, mortar, rebars 98.00
7.4 Sq.m -
and scafolds.
SUB TOTAL 856,063.00

TABLE – 8
PLASTERING WORK
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
Sl No DESCRIPTION UNIT QTY
In Figures In Figures

CEMENT MORTAR PLASTER INCLUDING MAKING GROOVES


8 WHEREVER REQUIRED, ALL MATERIALS, SCAFFOLDING, CURING
ETC. COMPLETE AS PER SPECIFICATION, DRAWING AND AS
DIRECTED BY Engineer-in-charge FOR THE FOLLOWING
Providing of 18 mm thick plaster in two layers outside the
8.1 building/boundary wall in cement mortar 1:4 on walls, finished to a Sq.m 756.51 220.00 166,432.20
smooth finish as per specification.
Providing 12 mm thick plaster in two layers inside the building/boundary
8.2 wall in cement mortar 1:4 on walls finished to a smooth finish as per Sq.m 756.51 0
specification.
SUB TOTAL Sq.m 1,513.02 166,432.20
TABLE - 9
PAINTING WORKS
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
FINISHES, PAINTING TO CONCRETE, PLASTERED SURFACES,
SURFACE PREPARATION INCLUDING ALL MATERIALS, LABOUR,
9 SCAFFOLDING ETC. ALL COMPLETE AS PER SPECIFICATION,
DRAWING AND AS DIRECTED BY Engineer-in-charge FOR THE
FOLLOWING :
Two coats of white washing with lime to give an even shade on walls and
9.1 Sq.m 1,834.16 625.00 1,146,350.00
ceiling including priming coat of cement primer complete.

Two coats of water proofing cement paint colour wash Cold Bitumen
9.2 Paint or approved brand and manufacture & of required shade to give an Sq.m - 0
even shade on walls complete including a priming coat of cement primer.

Providing two coats of Epoxy primer paint of approved brand and


9.3 manufacture to give an thinnable approved shade and quality as per LOT 300,000.00 0
specifications.
SUB TOTAL Sq.m
TABLE - 10
FLOORING AND SKIRTING
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
FLOORING AND SKIRTING INCLUDING BASE LAYER AND ALL
MATERIALS, LABOUR, CURING, POLISHING ETC. COMPLETE IN
10 ALL RESPECTS AS SHOWN ON DRAWINGS, DESCRIBED IN
SPECIFICATIONS AND AS DIRECTED BY Engineer-in-charge FOR
THE FOLLOWING

10.1 Providing and application of Concrete Hardener - smooth finish Sq.m -

SUB TOTAL Sq.m -

TABLE - 11
RAIN WATER DOWN TAKE PIPE
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
PROVIDING AND FIXING RAIN WATER DOWN TAKE PIPES
INCLUDING 2 COATS OF APPROVED PAINT OVER A PRIMARY
11
COAT, ALL SPECIALS AND ACCESSORIES ETC COMPLETE AS
PER SPECIFICATION
Providing & laying 100mm thick chb and grouted with fine sand mix
11.1 LOT -
including well rammed, finishing the top smooth.
PVC' down take pipes of 75 mm dia with all fittings, bends, joints etc all
11.2 LM 20.00 -
complete as per specification.
RC pipes of 200 mm dia with all fittings, bends, joints etc all complete as
11.3 LM 74.00 -
per specification.
SUB TOTAL -
TABLE - 12
ROOFINGS WORKS
RATE AMOUNT
Sl No DESCRIPTION UNIT QTY
In Figures In Figures
Providing & fixing of Pre painted Rib Type Powder Coated finished-
12.1 Sq.m 560.51 1,250.00 700,637.50
0.6mm thick for Roofing
12.2 Providing & fixing of Flushing galvanized finished- 1.5mm thick . Lm. 88.20 1,450.00 127,890.00
SUBTOTAL Sq.m 828,527.50

TOTAL 4,987,120.07

Equipment Usage -
Supervision and Overhead -

GRAND TOTAL** 4,987,120.07


1513.02
546.305

9200

5,026,006.00

You might also like