(54) SELF-ANCHORED SUSPENSION BRIDGE ages land at either or both ends of the Suspension bridge span
is disclosed. The method of constructing the self-anchored
(76) Inventor: Jian Ren Tao, Sunnvyale, CA (US) Suspension bridge comprises the use of preexisting perma
Correspondence Address: nent structures solely or in combination with minimum
GLENN PATENT GROUP temporary structures to provide temporary anchor points for
3475 EDISON WAY, SUITE L main Suspension cables during construction. Once the Sus
MENLO PARK, CA 94025 (US) pension bridge span end structures are properly secured by
(21) Appl. No.: 11/292,497 a tensioning cable to the temporary structure or by a tem
porary connection to a permanent structure and the deck
(22) Filed: Dec. 1, 2005 segment of pier table is lifted into place and tied down on an
end Support, the main Suspension bridge cables are erected,
Publication Classification suspenders are then erected from the main cable, and further
(51) Int. Cl. construction of the bridge proceeds. Once the bridge deck
EOID 2L/00 (2006.01) segments are all erected and integrated with the end piers,
(52) U.S. Cl. ............................................................... 14/77.1 temporary PT bars or cables connecting end Supports to
either preexisting or temporary structures are gradually
(57) ABSTRACT released to transfer anchoring force back to the bridge deck.
A method for constructing a Suspension bridge in places The temporary PT bars, cables and the temporary structures
where it is not feasible to construct permanent earth anchor (if used) are then disassembled and removed.
Patent Application Publication Jun. 7, 2007 Sheet 1 of 3 US 2007/O124876 A1

- - - QS

- - - QS
Patent Application Publication Jun. 7, 2007 Sheet 2 of 3 US 2007/O124876 A1

- NN
N

S.
Patent Application Publication Jun. 7, 2007 Sheet 3 of 3 US 2007/O124876 A1
US 2007/01 24876 A1 Jun. 7, 2007

SELF-ANCHOREO SUSPENSION BRIDGE point have been the earth anchorages and are located at both
ends of the span across which the bridge is built. In the case
BACKGROUND OF THE INVENTION of a self-anchored Suspension bridge, such as the San
0001) 1. Technical Field Francisco-Oakland Self-Anchored Suspension Bay Bridge
(Abbreviated as SAS thereafter), cables are supposedly
0002 The invention relates to bridges. More specifically, anchored by the bridge deck carrying compressing force at
the invention relates to construction of a self-anchored
Suspension bridge. both ends. Such self-anchor mechanism, however, does not
exist until the bridge is fully assembled, because during
0003 2. Discussion of the Prior Art construction, the bridge deck segments need to be Supported
0004 Heretofore, most of the suspension bridges were by cables whereas not yet capable of providing the required
constructed using earth anchors. In Such cases, cables are anchor force for cables loaded by themselves. The broken
anchored to earth at both sides of the span over which the chain needs to be connected by auxiliary structures. A
bridge is built. straightforward solution is to construct a temporary bridge to
Support the bridge deck segments. Once the bridge segments
0005. However, it may be desirable to build a suspension are assembled and integrated with the end piers of the
bridge based on considerations of esthetic preference or site bridge, cables are erected and Suspenders are installed. Then
conditions or both, for example, where the soil condition is gravity force of the bridge deck is transferred onto cables by
not ideal for building earth anchorages economically, Such adjusting the Suspenders’ length and the temporary bridge is
as across the San Francisco-Oakland East Bay, it has been released and removed. However, in case where the bridge
decided to provide a self-anchored suspension bridge for the span is getting quite long over the deep water, Such as SAS,
navigation span of the New San Francisco-Oakland Bay constructing a temporary bridge itself become very chal
Bridge East Span.
lenging and too expensive. If there exist permanent struc
SUMMARY OF THE INVENTION tures can be utilized to provide all or part of the anchoring
force for cables during construction, such costly temporary
0006. A method for constructing a self-anchored suspen bridge can be avoided. As shown in FIGS. 1A and 1B that
sion bridge is disclosed. The method of constructing the during construction, the main cable of a self-anchored
self-anchored suspension bridge comprises the construction suspension bridge 15 can be temporarily anchored by vari
of a temporary structure, which is used to secure an end ous means. On the left hand side of the bridge 15, cables are
Support of the suspension bridge by means of a cable anchored at temporary structure 10 through temporary
therebetween. Another end support of the suspension bridge cables 12. It is relevant to point out that the foundation
is preferably secured by a preexisting structure, but may also (footing and piles) of temporary structure 10 could be used
be secured by a temporary structure. Once the Suspension afterwards to Support a permanent approach bridge span. On
bridge span end structures are properly secured by a ten the right hand side of the bridge 15 cables can be temporarily
Sioning cable to the temporary structure or by a temporary anchored using preexisting portions of the bridge, Frame 1.
connection to a permanent structure, a pier table deck In case if Frame 1 alone is not sufficient, Frame 2 can be
segment is lifted into place and tied down on an end Support. engaged using temporary connectors 17 to further provide
After that, the main Suspension bridge cables are erected, required anchor force.
suspenders are erected from the main cable, and further
construction of the bridge proceeds. Once the bridge is 0013 FIG. 2 shows a construction sequence beginning
completed, the temporary structure is disassembled. with a first step. In FIG. 2A, an elevation view is shown for
the temporary structure as well as various bridge structures,
BRIEF DESCRIPTION OF THE DRAWINGS i.e. end supports W2 and E2, and a center support T1. During
0007 FIG. 1 is a schematic diagram showing a self construction, the end supports W2 and E2, as well as the
anchored Suspension bridge according to the invention; center support T1 are built, including the pier tables for
supports W2 and E2. The temporary structure 10 is also
0008 FIG. 2 shows a first step in the construction of a constructed as shown in FIG.2B. To support t the temporary
self-anchored Suspension bridge according to the invention; structure 10, a footing 20 is required. In some cases piles or
0009 FIG. 3 shows a second step in the construction of rock sockets may be necessary to prevent the footing from
a self-anchored Suspension bridge according to the inven sliding. The structure 20 could be utilized as the foundation
tion; and for permanent approach bridge structures. The temporary
structure 10 is preferably made of pre-cast concrete blocks
0010 FIG. 4 shows a third step in the construction of a 22 that have post-tensioning tendons there through and can
self-anchored Suspension bridge according to the invention; be later easily dissembled and removed.
DETAILED DESCRIPTION OF A PREFERRED 0014 FIG. 3 shows a second step in the construction of
EMBODIMENT the self-anchored Suspension bridge. At a first part of step
0011. The invention provides an alternative method of two, one deck segment 30 of the bridge is lifted onto end
constructing a self-anchored Suspension bridge. support E2 and is secured on support E2 via a tie down 32.
The deck segment is connected with existing bridge struc
0012 FIGS. 1A and 1B are schematic elevation and plan ture Frame I using PT bars or cables 34, which can be
views of a self-anchored Suspension bridge 15 according to initially tensioned, adjusted and released. If Frame 1 alone
the invention. A key problem with the construction of is not sufficient for providing the required anchoring force,
Suspension bridges is the need to provide anchor points for the existing bridge structure Frame 2 can also be engaged by
the Suspension bridge cables. Traditionally, these anchor temporary connectors between Frame 1 and Frame 2. The
US 2007/01 24876 A1 Jun. 7, 2007

cap beam of support W2 is tied with temporary structure 10 erecting end Supports and a center Support for said Sus
using PT bars or cables, and the cables are tensioned to the pension bridge;
required initial forces. constructing a temporary structure founded on a founda
0.015 FIG. 4 shows a third step in constructing a self tion (afterwards could be used to support a permanent
anchored Suspension bridge. The main Suspension bridge approach bridge structure) spaced away from an end
cables 40 are erected. Support of said Suspension bridge;
0016. The suspenders 42 are then erected onto the main tensioning an end Support proximate to said temporary
cables. Add temporary hangers if crossbeams are welded structure with a cable suspended therebetween:
after the erection of steel boxes (not shown).
forming temporary connections between said Support
0017. During a fourth step, the box girder segments are structure and said preexisting bridge frames;
lifted and the temporary PT bars or cables are adjusted as
necessary. To avoid damage to the preexisting permanent erecting main Suspension bridge cables;
structures, W2, E2, Frame I and Frame 2 (if engaged) have completing said bridge; and
to be kept well within elastic condition. It is then necessary
to align and make up box girder section splices, including disassembling said temporary connections and temporary
crossbeams (if welded in field), and a closure segment at Structure.
support W2. Once all segments are lifted and connected, the 2. The method of claim 1, further comprising the steps of:
temporary PT bars at support structure E2 are gradually
released from the support E2 frame I connection. Before erecting Suspenders from said main cable, adding tempo
doing this, the tie downs at Support E2 are first released so rary hangers if crossbeams are welded after erection of
that the box girder can slide longitudinally on temporary steel boxes;
bearings. The temporary PT bars or cables are then released lifting box girder segments and adjusting said temporary
and the Suspenders are adjusted to the required length. cables as necessary;
0018. At step five, the bridge furnitures are constructed aligning and making up box girder section splices, includ
and bridge construction is continued until the bridge is ing cross beams and a closure segment at an end
finished. Concurrently, the temporary structure is disas Support;
sembled and the pre-cast concrete blocks are removed.
0019. The above construction sequence has the advan once all segments are lifted and connected, gradually
tages of eliminating construction of temporary towers, releasing temporary connections at said end Support
bridges, as would be used in making a suspension bridge that structure; and
was self-anchored. This saves construction cost and time. constructing bridge furnitures.
0020. Although the invention is described herein with 3. The method of claim 2, further comprising the steps of:
reference to the preferred embodiment, one skilled in the art lifting a pier table deck segment of said Suspension bridge
will readily appreciate that other applications may be Sub
stituted for those set forth herein without departing from the onto one end Support and securing said deck segment to
spirit and scope of the present invention. Accordingly, the said Support; and
invention should only be limited by the Claims included connecting said deck segment with a preexisting Suspen
below. sion bridge frame.
1. A method for constructing a self-anchored Suspension
bridge, comprising the steps of: