Clarifier I Clarifier II

Aerotank

DS 0.5 - 1%

M M

Sludge thickener Flocculation


Sludge tank
DS 3 - 6 % tank

Filter press Belt press Decanter

Cake dryness 25-30% Cake dryness 18-22% Cake dryness 0.1 - 65 %


flow wide range flow 2.7-23 m3/hr flow : wide range
< 7 m3/hr
BELT PRESS _ CALCULATION

Dry Solid = Sludge flow x Solid content


Cake weight = Dry solid / Cake dryness
Cake Volume = Cake weight / Cake density

Sludge 3% or %DS = 3 %
Sludge flowrate = 5.2 m3/hr
Dry solid = 156 kg/hr
% solid of Cake = 18 %
Cake solid = 0.866667 ton/hr
% solid of Cake = 30 %
Cake solid = 0.52 ton/hr