Economic Analysis Summary

HDM-4
HIGHWAY DEVELOPMENT & MANAGEMENT Study Name: BEGUMGANJ - SULTANGANJ ROAD
Run Date: 30-04-2022

This report shows total economic benefits using the following:


Currency: INR (millions).
Discount rate: 12.00%.
Analysis Mode: Analysis-by-Section

Section: BEGUMGANJ - SULTANGANJ ROAD


Alternative: Upgradation vs Base Alternative

Savings in MT Savings in Net


Increase in Road Agency Costs Reduction Net
Savings in MT Travel NMT Travel Economic
in Accident Exogenous
VOC Time Costs & Operating Benefits
Capital Recurrent Special Costs Benefits
Costs (NPV)
Undiscounted 456.12 0.00 0.00 806.30 2,192.39 24.16 0.00 0.00 2,566.73
Discounted 436.57 0.00 0.00 271.96 740.04 8.58 0.00 0.00 584.00

Economic Internal Rate of Return (EIRR) = 25.8% (No. of solutions = 1)

HDM-4 Version 1.3 Page 1 of 1