You are on page 1of 1

JADWAL WAKTU PELAKSANAAN COLDSTORAGE MALUKU (KURVA "S")

WAKTU PELAKSANAAN HARI KE -


BOBOT
NO. U R A I A N Keterangan
(%) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 PERSIAPAN 0,23% 0,23%

2 PENGUKURAN ABF DAN FREEZER ROOM 0,35% 0,35%

3 PEMASANGAN PANEL SLAB FREEZER ROOM 3,56% 1,78% 1,78%

4 PEMASANGAN DINDING PANEL FREEZER ROOM 3,56% 1,19% 1,19% 1,19%

5 PEMASANGAN ATAP FREEZER ROOM 3,56% 1,78% 1,78%

6 PEMASANGAN MESIN DAN KONDENSOR FREEZER ROOM 22,30% 7,43% 7,43% 7,43%

7 PEMASANGAN EVAPORATOR FREEZER ROOM 12,88% 6,44% 6,44%

8 PEMASANGAN PINTU FREEZER ROOM 3,56% 1,78% 1,78%

9 PEMASANGAN PANEL SLAB ABF ROOM 3,56% 1,78% 1,78%

10 PEMASANGAN DINDING PANEL ABF ROOM 3,56% 1,19% 1,19% 1,19%

11 PEMASANGAN ATAP ABF ROOM 3,56% 1,78% 1,78%

12 PEMASANGAN MESIN DAN KONDENSOR ABF ROOM 22,30% 7,43% 7,43% 7,43%

13 PEMASANGAN EVAPORATOR ABF ROOM 12,88% 6,44% 6,44%

14 PEMASANGAN PINTU ABF ROOM 3,56% 3,56%

15 TES RUNNING FREEZER ROOM DAN ABF ROOM 0,58% 0,19% 0,19% 0,19%
JUMAH BOBOT 100,00%
I RENCANA KEMAJUAN MINGGUAN 0,58% 3,56% 4,75% 1,19% 1,19% 1,78% 1,78% 7,43% 7,43% 13,87% 8,22% 1,78% 1,19% 1,19% 2,97% 1,78% 7,43% 7,43% 7,43% 6,44% 6,44% 3,56% 0,19% 0,19% 0,19%
II RENCANA KOMULATIF MINGGUAN 0,58% 4,14% 8,89% 10,07% 11,26% 13,04% 14,82% 22,25% 29,69% 43,56% 51,78% 53,56% 54,75% 55,93% 58,90% 60,68% 68,11% 75,55% 82,98% 89,42% 95,86% 99,42% 99,61% 99,81% 100,00%
III REALISASI
IV DEVIASI

0 0