KURVA S COLDSTORAGE MALUKU Fix
KURVA S COLDSTORAGE MALUKU Fix
6 PEMASANGAN MESIN DAN KONDENSOR FREEZER ROOM 22,30% 7,43% 7,43% 7,43%
12 PEMASANGAN MESIN DAN KONDENSOR ABF ROOM 22,30% 7,43% 7,43% 7,43%
15 TES RUNNING FREEZER ROOM DAN ABF ROOM 0,58% 0,19% 0,19% 0,19%
JUMAH BOBOT 100,00%
I RENCANA KEMAJUAN MINGGUAN 0,58% 3,56% 4,75% 1,19% 1,19% 1,78% 1,78% 7,43% 7,43% 13,87% 8,22% 1,78% 1,19% 1,19% 2,97% 1,78% 7,43% 7,43% 7,43% 6,44% 6,44% 3,56% 0,19% 0,19% 0,19%
II RENCANA KOMULATIF MINGGUAN 0,58% 4,14% 8,89% 10,07% 11,26% 13,04% 14,82% 22,25% 29,69% 43,56% 51,78% 53,56% 54,75% 55,93% 58,90% 60,68% 68,11% 75,55% 82,98% 89,42% 95,86% 99,42% 99,61% 99,81% 100,00%
III REALISASI
IV DEVIASI
0 0