F
Hydro Tasmania
Huge effort prevents
major damage at Poatina
An enormous effort by the
at Poatina has resulted in limiting
@ potentially serious incident at the
Poatina Pow
On Saturday July 2, the Poatina No 3 machine
isolating valve failed allowing high pressure
(azo0psi) penstock water to escape, causing the
alarms to sound. While the escaping water was
not enough to threaten the station with flooding,
it was a potentially dangerous situation requiring
shutting down the power station and draining the
penstock,
Station
Generating Asset Manager, Rod Vogel, said the
response process was put to the test and worked
admirably
“No one was injured and there was no
consequential damage to plant or the
environment,” Rod said. “After draining and a mot
detailed inspection it became apparent that the
failure was worse than frst thought with 20 of the
26, 7omm bolts that hold the two halves of the
body oft jogether completely severed,
“Once the situation was contained, the
investigation phase began in earnest with the
collection of broken bolts, ultra-sonie testing of
all remaining bolts on all valves and removal and
‘examination ofthe offending valve itselt
Engineers and metallurgists a
looked at numerous theories to explain this
failure, The logical and favoured culprit was
aver pressurisation but there was no evide
support this theory. The only explanation was that
ne with
Yaks hel
Leone aa et
ena 4 al
Coan
Pouce eee)
talk careers
ry
re
the bolts had failed from fatigue, possibly due to inadequate tensioning
when re-assembled in 1983,
‘With all ofthis done in remarkable time, re-filing of the penstock
commenced on 2 August,” Rod sald. “During the refill a small leak was
noticed on a pressure tapping point weld, just upstream from the No 3
penstock flange.
“More ultra-sonic testing of the other 24 pressure tappings, four per
‘machine just upstream from the penstack flange, revealed that many had
cracks already and were prone to both leakage and crack propagation.”
Wiile the remedial work was being undertaken a new
emerged as the cause of the original bolt fail
tial culprit
AAS part of the dam safety program, a selsmic recorder had been installed
near the top of the penstock and it was a recording from this device that
identified @ small but consistent vibration in the hours leading up to the
inital station alarm and this vibration appeared to cease at @ suspiciously
coincidental time to the station alarm being initiated,
With this additional information the possibility of an over pressurisation
event, a resonant oscillation in the penstock, became more likely. The seal
arrangement on this p ssociated with a phenomena
ular valve type
oe ety eta
safety commitm
Eo) a
Co ean eee
hes for energy stars
een eet ete