You are on page 1of 287

6

Ver 2017.1

PMP and The PMI Registered Education Provider logo are registered
mark of the Project Management Institute, Inc.
1. Introduction
PMP CTP

www.qaiglobal.com

"PMP" and the PMP logo are certification marks registered in the
1
United States and other nations;
Workshop Agenda

Introduction to PMI and PMP


PM Framework
Initiating Process Group
Professional and Social Responsibilities
Integration Management
Scope Management
Schedule Management
Cost Management
Quality Management
Resource Management
Communication Management
Risk Management
Procurement Management
Stakeholder Management

"PMP" and the PMP logo are certification marks registered in the
2
United States and other nations;
Introductions

Participant introduction
Name
Organization / Department
Total years of experience
Years of experience in project management
Your expectations from the workshop

"PMP" and the PMP logo are certification marks registered in the
3
United States and other nations;
Ground Rules

Mobile Phones: Silent mode please

Questions are welcome at any time

Respect view point of others

Keep discussions brief and to the point

Please be prompt in returning from breaks

Provide feedback as to where course can be improved – it will be useful for sub-
sequent sessions

"PMP" and the PMP logo are certification marks registered in the
4
United States and other nations;
Introduction to PMI

PMI® – the leading non-profit organization devoted to project management


Profession

Has a global coverage with members from various leading organizations

Propagates multiple Services – including Research & Education, Development of


Standards,
Certifications, Conferences, Products and recognition of PM related contributions.

Has City chapters and SIGs

"PMP" and the PMP logo are certification marks registered in the
5
United States and other nations;
PMP® Certification

Project Management Professional (PMP ®) Certification is amongst the most coveted


Certifications globally.

Many organizations require PMP® as a prerequisite qualification for their Managers


executing large scale projects

Though it is industry generic, has seen lots of acceptability in IT and IT related


community

"PMP" and the PMP logo are certification marks registered in the
6
United States and other nations;
Suggested Route map for PMP® Certification

I want to acquire Have Degree Yes


PMP® Certification qualification?

No
No
Have requisite
S
PM experience?

Have Diploma
qualification?
Yes

Become a PMI® Member


Prepare for PMP® Attend PM Training
examination

Apply for PMP® Take PMP® exam from


examination from Prometric Center Maintain
PMI® and get the ATT and clear the exam PMP® credential

"PMP" and the PMP logo are certification marks registered in the
7
United States and other nations;
On the PMP® examination pattern

It’s a 4 hour test – 200 questions – mixed randomly across Process groups- as per a set
pattern

Out of 200 questions, 175 are for final marking and remaining 25 are ‘pre-test’ questions
- which are included to assess if these questions can be included in the ‘Master set’
subsequently

Questions get mixed up in various process groups

"PMP" and the PMP logo are certification marks registered in the
8
United States and other nations;
PMP Exam Fee Structure

Membership Fees
o Annual membership Fee - $129
o One Time joining Fee - $ 10
• ----------
o Total cost of membership = $ 139
o Certification Fee
o For Members - $ 405
o For Non members - $ 555
o Total Cost of Certification (Members) - $544

"PMP" and the PMP logo are certification marks registered in the
9
United States and other nations;
PMP® – Retake and Maintenance of credential

In case of failure, candidate can retake the exam at an additional fee ($ 275 for
members)

Certified PMP®s have to earn 60 PDU®s in a specified time duration through multiple
avenues as a CCR cycle- incl.:

Formal Academic education/ Giving lectures etc.


Publishing professional articles/ books on project management
Attending seminars / Undergoing additional trainings
Self directed learning
Continuance as a PM Practitioner
Volunteer activities

"PMP" and the PMP logo are certification marks registered in the
10
United States and other nations;
PMI® Application forms and Audits

For each of the projects specified in the Application form as Experience verification,
candidates need to give a contact person’s name for reference

PMI® can schedule Audits to verify the experience Verification forms

Responding to PMI® Audit requires submission of supporting documentation - like


copies of educational certificates, endorsements for the projects handled and the
copy of the Training participation certificate.

"PMP" and the PMP logo are certification marks registered in the
11
United States and other nations;
What we learnt here?

Overview of PMI®
PMP® examination – importance and structure
Keeping up the PMP® credential

"PMP" and the PMP logo are certification marks registered in the
12
United States and other nations;
2. Project Management
Framework

www.qaiglobal.com

"PMP" and the PMP logo are certification marks registered in the
1
United States and other nations;
PMBOK® and PMBOK® guide

Project Management Body of Knowledge (PMBOK®) describes knowledge unique to


the project management field

This PMBOK® Guide is different from a methodology. A methodology is a system of


practices, techniques, procedures, and rules used by those who work in a discipline.

This PMBOK® Guide is a foundation upon which organizations can build


methodologies, policies, procedures, rules, tools and techniques, and life cycle
phases needed to practice project management.

"PMP" and the PMP logo are certification marks registered in the
2
United States and other nations;
Project Management Processes

As per PMBOK ®( Sixth edition), 49 processes have been enumerated

These processes fall under five Process Groups of


Initiating
Planning
Executing
Monitoring & Controlling
Closing

Product oriented processes are different from project management processes

"PMP" and the PMP logo are certification marks registered in the
3
United States and other nations;
Project Management Process Groups

Initiation – Those processes performed to define a new project


by obtaining authorization to start the project. (Project Charter)

Planning – Those processes required to establish the scope,


refine objectives and defining the course of action required to
attain the objectives of the project (Project Management Plan) Initiation

Monitoring and Controlling


Executing – Those processes performed to complete the work
Planning
defined in the Project Plan (Deliverables)

Monitoring & Controlling – Those processes required to Execution


track, review and regulate the progress and performance of the
project (Change Requests)
Closing
Closing – Those processes required to finalize all activities
across all process groups to bring the project to an orderly end
(Lessons Learned)

"PMP" and the PMP logo are certification marks registered in the
4
United States and other nations;
Project Management Process Groups in Adaptive environments

Initiation
Adaptive projects revisit and revalidate the project charter on a frequent basis. on
each iterative cycle of an adaptive life cycle project

Adaptive projects rely heavily on a knowledgeable customer. Identification of this


stakeholder or other stakeholders at the start of the project permits frequent
interactions when performing Execution and Monitoring and Controlling processes

Planning
Adaptive life cycles, develop a set of high-level plans for the initial requirements and
progressively elaborate requirements to an appropriate level of detail for the
planning cycle

Projects navigating high degrees of complexity and uncertainty should involve as


many team members and stakeholders as possible in the planning processes

"PMP" and the PMP logo are certification marks registered in the
5
United States and other nations;
Project Management Process Groups in Adaptive environments

Execution
Work is directed through managed Iterations, which is short and fixed in duration
Work done in iteration is followed by a demonstration (retrospection). Benefits of
retrospection include:
o check progress against the plan and determines if any changes to the project
scope, schedule, or execution processes
o help manage stakeholder engagement by showing increments of work done
o allows issues with the execution approach to be identified and ideas for
improvements generated
o primary tool to manage project knowledge
While work is undertaken via short iterations, it is also tracked and managed
against longer-term project delivery. Trends such as velocity, team capacity, spends,
defect rates are extrapolated to track performance
Rather than PM selecting and sequencing work team members are empowered to
self-organize specific tasks as a group to best meet those objectives – better buy-in

"PMP" and the PMP logo are certification marks registered in the
6
United States and other nations;
Project Management Process Groups in Adaptive environments

Monitoring & Controlling


Adaptive approaches track, review, and regulate progress and performance by
maintaining a Backlog. The backlog is prioritized by a business representative
Work is pulled from the top of the backlog for the next iteration based on business
priority and team capacity
Backlog acts as a single place for stakeholders to manage and control project work,
perform change control, and validate scope
Trends, and metrics on work performed, change effort and defect rates, Team
capacity, velocity are all used to measure progress and forecast.
These metrics and projections are shared with project stakeholders via trend graphs
(information radiators) to communicate progress, share issues, drive continuous
improvement activities, and manage stakeholder expectations

"PMP" and the PMP logo are certification marks registered in the
7
United States and other nations;
Project Management Process Groups in Adaptive environments

Closing
Adaptive approaches in cases where a project is prematurely closed , there is a
thigh chance that some useful business value will already have been generated as
against predictive life cycles. This is because highest business value items are
prioritized.

"PMP" and the PMP logo are certification marks registered in the
8
United States and other nations;
What is Project?

A project is a temporary endeavour undertaken to create a unique product, service or


result’ (Reproduced from PMBOK® Guide)

What are some of the characteristics of a project?


Has a start and end date (Temporary)
Unique endeavour
Objective oriented
Usually involve Progressive Elaboration and Rolling Wave Planning
Drive Change
Create Business Value

"PMP" and the PMP logo are certification marks registered in the
9
United States and other nations;
Progressive Elaboration

Construct Home Progressing through steady


incremental steps
Location: City

Structure: Brick

3 Storeys

3 car garage

6 bedrooms

More Details

"PMP" and the PMP logo are certification marks registered in the
10
United States and other nations;
What is Project Management?

“Project Management is the application of Knowledge, Skills, Tools and Techniques to


project to meet project requirements”
(Reproduced from PMBOK® Guide)

Project Lifecycle is a part of Product Lifecycle

"PMP" and the PMP logo are certification marks registered in the
11
United States and other nations;
Managing project Constraints

Budget

Schedule Resources

Quality Risk

Scope

"PMP" and the PMP logo are certification marks registered in the
12
United States and other nations;
Related Endeavors

Portfolio - A portfolio is a collection of projects or programs and other work that are
grouped together to facilitate effective management of that work to meet strategic
business Objectives

Program – A Program is a group of related projects, managed in a coordinated way to


obtain benefits not available from managing them individually

Project

"PMP" and the PMP logo are certification marks registered in the
13
United States and other nations;
Key differences between Project/Program and Portfolio Management

Theme Project Program Portfolio


Portfolios have a
Projects have a well defined
Program’s scope is Business scope which
scope which usually gets
Scope more attuned towards change with the
progressively elaborated
Benefits Management strategy of the
during the project life cycle
Organisation
Program Managers Portfolio Managers
create the overall Plan institute necessary
Project Managers use ‘Rolling
at the program level processes and
Planning Wave’ Planning during the
and guide the communication
project life cycle
Component Project structures relative to the
Managers aggregate portfolio
Program managers Portfolio Managers
oversee the Project mostly provide direction
Project Managers manage the
Management managers/ associated and alignment to
project team
operations to provide Organisational
leadership strategies

"PMP" and the PMP logo are certification marks registered in the
14
United States and other nations;
Key differences between Project/Program and Portfolio Management

Theme Project Program Portfolio


Program managers are Portfolio Managers are
Project Manager tries to
open to changes open to changes driven
Change control keep the Changes to a
coming from Internal/ by Market and
minimum
External changes Regulatory changes
Delivery style/
Benefit realization
Success Task oriented Value oriented
oriented
measurement
Aggregate
Project objectives Benefit/ Governance
Monitoring style Performance/Value
related related
indicators driven

"PMP" and the PMP logo are certification marks registered in the
15
United States and other nations;
Organizational Project Management

OPM is defined as a framework in which portfolio, program, and project management


are integrated with organizational enablers in order to achieve strategic objectives

Each contributing in different ways:

Portfolio management aligns portfolios with organizational strategies by selecting the


right programs or projects, prioritizing the work, and providing the needed resources.
Program management harmonizes its program components and controls
interdependencies in order to realize specified benefits.
Project management enables the achievement of organizational goals and objectives.

"PMP" and the PMP logo are certification marks registered in the
16
United States and other nations;
Typical Project Lifecycle

Performing Organization/ Stakeholders

Exits
Exits

Exits
Initiation

Closure
Phase I Phase II Phase III Phase IV

a b c d

Deliverables

"PMP" and the PMP logo are certification marks registered in the
17
United States and other nations;
Project Life Cycles

Predictive - Project scope, time and cost are determined as early as possible.
Changes to project scope are carefully managed and require re-planning and formal
acceptance of the new scope

Iterative - An approach that allows feedback for unfinished work to improve and
modify that work

Incremental - An approach that provides finished deliverables that the customer may
be able to use immediately. Optimize speed of delivery

Adaptive – These are designed to address high levels of change and stakeholder
involvement. In these the iterations are very rapid and are fixed in time and cost.

Hybrid - A hybrid life cycle is a combination of a predictive and an adaptive life cycle

"PMP" and the PMP logo are certification marks registered in the
18
United States and other nations;
Comparison of Life Cycles
Predictive Iterative Incremental Agile
Requirements are defined Requirements can be Requirements are
up-front before elaborated at periodic elaborated frequently
development begins intervals during delivery during delivery
Deliver plans for the Delivery can be divided into Delivery occurs frequently
eventual deliverable. Then subsets of the overall with customer-valued
deliver only a single final product subsets of the overall
product at end of project product
Timeline
Change is constrained as Change is incorporated at Change is incorporated in
much as possible periodic Intervals real-time during delivery
Key stakeholders are Key stakeholders are Key stakeholders are
involved at specific regularly Involved continuously involved
milestones
Risk and cost are controlled Risk and cost are controlled Risk and cost are controlled
by detailed planning of by progressively elaborating as requirements and
mostly knowable the plans with new constraints Emerge
considerations information
"PMP" and the PMP logo are certification marks registered in the
United States and other nations; Project Management Institute, A
19 Guide to the Project Management Body of Knowledge, (PMBOK®
Guide) – Sixth Edition, Project Management Institute Inc., 2017,
Page 666
Tailoring PM Methodology

A PM needs to select appropriate project management processes, inputs, tools,


techniques, outputs, life cycle phases to manage a project effectively. This selection
activity is referred to as tailoring project management.

Certain considerations while tailoring would include:


o Project environment
o Organizational culture
o Stakeholder needs
o Governance level required
o Whether customer is internal or external

"PMP" and the PMP logo are certification marks registered in the
20
United States and other nations;
Project Management Business Documents

Business Case - The project business case is a documented economic feasibility


study used to establish the validity of the benefits that is used as a basis for the
authorization of further project management activities. This is used for go/no-go
decision

Benefits Management Plan - The project benefits management plan is the


document that describes how and when the benefits of the project will be delivered,
and describes the mechanisms that should be in place to measure those benefits

"PMP" and the PMP logo are certification marks registered in the
21
United States and other nations;
Business Case

Business Need:
o What triggers the action?
o Describes the business problem or opportunity
o Stakeholders affected
Analysis of the situation: Identification of organizational goals/objectives, root
cause analysis of the problem, risks, etc. Analysis could use classifying criteria as
required/ desired/optional
Options available:
o Do nothing
o Do the minimum work possible
o Do more than the minimum work possible
Recommendation: A statement of the recommended option to pursue in the project
and why
Evaluation: Statement describing the plan for measuring benefits the project will
deliver

"PMP" and the PMP logo are certification marks registered in the
22
United States and other nations;
Benefits Management Plan

o Target benefits: List of all benefits tangible/non-tangible


o Strategic alignment: How well and which business strategy is the benefits aligned to
o Timeframe : When can the benefits be realized, arranged by phases or short
term/long-term/on-going etc.
o Benefits Owner: Person accountable for the benefit
o Metrics: How will each benefit be measured
o Assumptions: Factors to be in place for the benefit to be realized
o Risks: Any threats to benefit realization

"PMP" and the PMP logo are certification marks registered in the
23
United States and other nations;
Organizational Influences - Governance

Governance is the framework within which authority is exercised in organizations.


Includes people, roles, structures and policies and requires providing direction and
oversight to projects.

A project governance framework may have guidance on:


Project success and deliverable acceptance criteria
Process to manage and escalate issues
Processes and procedures for communication
Project decision making process
Project life cycle approach
Process for stage gate reviews
Process of approval of changes to time, cost, scope and quality which are
beyond the authority of the PM
Project roles required in a project

"PMP" and the PMP logo are certification marks registered in the
24
United States and other nations;
Organizational Influences – Organization Structures

Project Manager The Organization Structure


Projectized determines the authority that the
Project Manager and Functional
Manager will have
Strong Matrix

Balanced Matrix

Weak Matrix

Functional

Functional Manager

Projects usually are part of the Organizational work and fit in the Organizational culture,
style and structures

"PMP" and the PMP logo are certification marks registered in the
25
United States and other nations;
Other Structures

Organic/Simple – Flexible with people working side by side. All authority vested
with owner/operator. Like start-ups

Multi-divisional – May replicate function for each division with little centralization.
Similar to functional organization but de-centralized

Hybrid – Mix of other types

Virtual - The virtual organization exists within a network of alliances, using the
Internet.

Network - Another modern structure, that contracts out any business function which
can be done better or more cheaply. Managers in network structures spend most
of their time coordinating and controlling external relations
Organizational Influences - Organization Structures

Balanced
Functional Weak Matrix Strong Matrix Projectized
Matrix

Project
Manager’s Low to
Little or none Limited High High to Total
Authority Moderate

Resource Low to
Little or none Limited High High to Total
Availability Moderate

Functional
Functional Project Project
Budget Control Manager Both
Manager Manager Manager

Project Part-time Part-time


Part-time Full-Time Full-time
Manager’s role

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
27 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 13
Other Organization Structures

Organic/Simple Multi-divisional Virtual Hybrid

Project Manager’s
Little or none
Authority Little or none Low to Moderate Mixed

Resource
Little or none Little or none Low to Moderate Mixed
Availability

Functional
Budget Control Owner or Operator Manager Mixed Mixed

Part-time/Full
Project Manager’s Part-time
Part-time Time Mixed
role

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
28 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 13
Organizational Influences - Types of PMOs

A project management office (PMO) is an organizational structure that standardizes


the project-related governance processes and facilitates the sharing of resources,
methodologies, tools, and techniques

There could be several types of PMOs such as:

Supportive – provide consultative role to projects; degree of control is LOW

Controlling – provide support and ensure compliance through various means;


degree of control is MODERATE

Directive – Take control of projects by directly managing the projects; degree of


control is HIGH

"PMP" and the PMP logo are certification marks registered in the
29
United States and other nations;
Organizational Influences - Enterprise Environmental Factors

Enterprise environmental factors (EEFs) refer to conditions, not under the control of
the project team, that influence, constrain, or direct the project
Internal:
Organizational/ Company structure and culture
Existing Company Infrastructure /Skill sets
Geographic distribution of facilities and resources
IT Software
Resource availability
External
Market place conditions
External factors like Political Systems
Statutory/ Industry Standards
Financial Considerations

"PMP" and the PMP logo are certification marks registered in the
30
United States and other nations;
Organizational Influences - Organizational Process Assets

These include the Organizational policies, procedures, knowledge databases, practice


etc.

These Assets can include Organizational:


Policies and Procedures
Organizational Knowledge base
Change Control procedures
Metrics and Guidelines
Historical Information/Knowledge Databases

"PMP" and the PMP logo are certification marks registered in the
31
United States and other nations;
What we learnt here?

Project Management Body of Knowledge (PMBOK®)


PMBOK® Process Groups & Knowledge areas
PMBOK® Process Groups in Adaptive environment
Projects, Programs and Portfolios
Project Life cycles
Tailoring PM Methodolgy
Business Documents
Organizational Influences – EEF, OPA, PMO, Organizational structures

"PMP" and the PMP logo are certification marks registered in the
32
United States and other nations;
3. The Role of Project
Manager

www.qaiglobal.com

"PMP" and the PMP logo are certification marks registered in the
1
United States and other nations;
The Project Manager

The project manager is the person assigned by the


performing organization to lead the team that is
responsible for achieving the project objectives

Skills needed in a Project Manager – The PMI Talent Triangle®


Technical project management - The knowledge, skills,
and behaviors related to specific domains of project,
program, and portfolio management.

Leadership - The knowledge, skills, and behaviors needed


to guide, motivate, and direct a team, to help an
organization achieve its business goals.

Strategic and business management - The knowledge of


and expertise in the industry and organization.

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
2 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 57
Leader vs. Manager

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
3 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 64
Types of Power

Leadership and management are ultimately about being able to get things done. At
the root of many of these skills and qualities is the ability to deal with politics
Some forms of Power include:
o Positional
o Informational
o Referent
o Personal or Charismatic
o Expert
o Reward
o Coercive

"PMP" and the PMP logo are certification marks registered in the
4
United States and other nations;
Leadership Styles

Some of the most common leadership style includes:

o Laissez-faire - Allowing the team to make their own decisions and establish their own
goals, also referred to as taking a hands-off style)
o Transactional - Focus on goals, feedback, and accomplishment to determine
rewards
o Servant leader - Demonstrates commitment to serve and put other people first.
Focuses on other people’s growth, learning, development, autonomy, and well-being;
concentrates on relationships, community and collaboration; leadership is secondary
and emerges after service
o Transformational - Empowering followers through idealized attributes and behaviors,
inspirational motivation, encouragement for innovation and creativity, and individual
consideration
o Charismatic - Able to inspire; is high-energy, enthusiastic, self-confident; holds
strong convictions
o Interactional - A combination of transactional, transformational, and charismatic

"PMP" and the PMP logo are certification marks registered in the
5
United States and other nations;
Integration

The two facets of integration that a Project Manager needs to deal with are
o Strategic Alignment - Working with sponsor and key stakeholders to understand the
strategic objectives and aligning project to these. Also means alignment of project to
program, portfolio and business area objectives

o Project Level - Project managers are responsible for guiding the team to work
together to focus on what is really essential at the project level. This is achieved
through the integration of processes, knowledge, and people

A Project Manager needs to perform integration at all levels including process,


cognitive and context.

"PMP" and the PMP logo are certification marks registered in the
6
United States and other nations;
What we learnt here?

Project Management Process Groups

Project Management Knowledge Areas

Project Management Processes

"PMP" and the PMP logo are certification marks registered in the
7
United States and other nations;
4A. Initiating
Process Group

www.qaiglobal.com

1
Initiating Process Group - Overview

Initiating Process Group is about defining a new project or a phase of a project.

Project Charter and Stakeholder Register


are the major deliverables of this Process Group

The Initiation activities in a project are often done outside the Project Mangers
domain of control – by the Senior Management/Portfolio Manager etc.

In subsequent Phases the Initiating processes are repeated to ensure that the project
remains focussed on the business needs it was undertaken to fulfil

2
Develop Project Charter

• To authorize the project


• Authorize the Project Manager to apply Organizational resources to
perform the activities in the project

The project can be chartered by someone external to the project such as a


Sponsor, Customer, PMO and the Portfolio Steering Committee as well

It is essential that the Charter is prepared ( and signed) by an Authority


consistent with funding powers . This could be done by the Sponsor or
customer.

3
Develop Project Charter

Business Documents, Agreements,


Enterprise environmental Factors,
Organizational Process Assets

Expert Judgment, Data Gathering techniques,


Interpersonal skills, Meetings

Project Charter
Assumptions Log

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 71
Project Charter Contents

Project Charter may include the following information:

Project purpose or justification


Measurable project objectives and related success criteria
High level requirements/Key Deliverables
Summary milestones/ schedules/ budget issues
Summary Macro level risks/ Assumptions/ Constraints
Key Stakeholders
High Level risks
Project (Success) Approval requirements
Name of the Assigned Project Manager
Name of the Assigned Sponsor

Project Manager is required to share the approved


Charter with stakeholders to ensure a common
understanding of the project at the onset.

5
Cost-Benefit analysis techniques

Some commonly used Cost-Benefit analysis techniques are:

o Benefit to Cost ratio (BCR)


o Return on Investment (ROI)
o Payback period
o Net Present Value (NPV)
o Internal Rate of Return (IRR)

6
Benefit Cost Ratio

Cost – Benefit analysis involves estimating tangible and intangible costs (outlays) and
benefits (returns) of various projects and product alternatives

Helps arrive at the comparative analysis of the project’s benefits that offset the cost.

Benefit/Cost >1 – during the project lifecycle is the desired criterion

Sunk costs and benefits already realized are not taken into account in cost-benefit analysis

7
Choosing a Project to Charter - Return On Investment

ROI is also referred to as Accounting or Average Rate of Return (ARR) and provides
a way to compare the net profitability to the investment required

Most common formula to calculate ROI % is (Average Annual Profit/Total


Investment)*100

Cash Inflow Cash Return


outflow

Cash Invested 25,000


1st year result 9000 2000 7000
2nd year result 10000 2000 8000
3rd year result 16000 4000 12000

Average profit (7+8+12)/3=9 9,000


ROI= ((9000/25000)*100) 36%

8
Choosing a Project to Charter - Payback Period

Payback Period is the time taken to “break even” or pay back the initial cash outlay
on the project – Shorter the payback period the more desirable the project

Year Cash Flow Project A Cash Flow Project B

0 -100,000 -100,000

1 50,000 20,000

2 30,000 20,000

3 *20,000 20,000

4 10,000 * 40,000

5 10,000 50,000

6 - 60,000

9
Choosing a Project to Charter - NPV

Net Present Value (NPV) is the difference of discounted Cash Flows and discounted
expenses occurring over the Product’s Lifecycle:

If NPV <=0 No real profit is accruing to the project

If NPV > 0 Profitable Venture

10
NPV – An Illustration

Consider an investment with the following income-expense profile: (assumed rate of interest – 10%)

Year Expected Income Expected


( ‘000 $) Expenditure (‘000 $)

0 - 100

1 50 20

2 70 10

3 50 10

Determine if the investment is likely to be profitable by the NPV criteria.

11
Choosing a Project to Charter - IRR

IRR represents the rate of interest that will make the NPV for an investment zero

It is calculated by finding IRR internally in the equation :


Initial Outlay = Sum(Discounted Cashflows with IRR)

IRR has to be greater than the ‘Cost of Capital’ or ‘Hurdle Rrate’ for it to be taken up
for further consideration

12
Identify Stakeholders

Identifying Individuals and Organizations involved in the project, their


interests and potential impact on project.

It is imperative for the Stakeholders to be identified early in the project and


in each phase
Stakeholders might have varying levels of interest, expectations,
importance and influence on the project
The stakeholders to also be classified as per their power and interest
equations
By engaging the right people in the right way in your project, you can make
a big difference to its success

13
Identify Stakeholders

Project Charter, Business Documents,


Project Management Plan, Project
Documents

Expert Judgment, Data Gathering,


Data Analysis (Stakeholder Analysis), Meetings,
Data Representation

Stakeholder Register

Project Management Institute, A Guide to the Project Management Body


14 of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management
Institute Inc., 2017, Page 504
Stakeholder Identification

The Project Charter can contain initial list of stakeholders – but Business documents
therein gives direction for understanding of further stakeholders and their expectations

An initial Stakeholder map – representing the list of Stakeholders and their interest
areas can be prepared

It is better to group the stakeholders into multiple categories – like users/ beneficiaries,
suppliers, those who govern and influencers

The messages to be given to the diverse set of stakeholders and their expectation
management styles could be different

15
Stakeholder Mapping/Representation

Once the Project Charter is approved, the Project Manager goes about detailed
Stakeholder analysis

Stakeholders can be grouped by multiple factors like interest- influence, interest-


Impact etc

The message content, media, frequency of engagement and the level of detail can
vary with the relative needs of the stakeholders

16
Sample Stakeholder Register

Standardization of specification for Telecom Tower Roll out


Assessment of
Stakeholder Name Major Need Strategy
Influence

Share:
Top end specification
1. Reliability analysis report
Customer required High
2. Cost-benefit analysis (marginal analysis)
Cost is secondary
Involve in decision making

Low CAPEX and OPEX Clearly communicate Cost-benefit analysis


Top Management Very High
but still meeting SLAs and reliability analysis

Top end specs to


Plan User trials
O &M reduce down time. Medium
Involve in decision making
Cost secondary

Low - have less say


Circle Project Team Ease of rollout Convince by using Prototype deployment
in decision making

Off the shelf availability Low - company Float questionnaires on specs availability
Equipment vendors No need for being the biggest Involve in field trials
customization vendor Plan Lead times in procurement

17
What we learnt here?

Multiple project selection methods

Importance of Project Charter in project lifecycle

Project Charter contents and the preparation process

Preparation of Stakeholder Register

18
4B. Project Integration
Management

www.qaiglobal.com

"PMP" and the PMP logo are certification marks registered in the
1
United States and other nations;
Integration Management

Integration Management consists of the processes to integrate the actions across


Knowledge Areas and Process Groups
Also consists of actions concerning integration of
Project Scope with the Product Scope
Project work with the ongoing operations of the Performing Organization

While other Knowledge Areas may be managed by specialists like Business Analysts,
Project Accountant, Risk management expert etc. the accountability of Project
Integration Management cannot be delegated or transferred. This remains specifically
with PM.

"PMP" and the PMP logo are certification marks registered in the
2
United States and other nations;
What goes where?
Develop Project Charter: The process develops a Charter that authorizes the project in
the organization
Develop Project Management Plan: Defining how the project will be executed,
monitored and controlled and closed

Direct and Manage Project Work: Executing the work defined in the Project
Management Plan to produce deliverables defined in the Scope

Manage Project Knowledge: Using existing knowledge and creating new knowledge
for organizational learning.

Monitor and Control Project Work: Tracking the project progress and regulating the
progress to meet the project objectives

Perform Integrated Change Control: Reviewing all Change Requests, approving


Changes and coordinating Changes to the Baselines
Close Project or Phase: To bring the project to a formal ending

"PMP" and the PMP logo are certification marks registered in the
3
United States and other nations;
Develop Project Management Plan

It defines how the project is executed, monitored/controlled and closed

Project Charter, Outputs from other


Processes

Expert Judgment, Data Gathering (Brainstorming,


Focus Groups, Checklists) Interpersonal
and Team Skills (Conflict Management, Facilitation)
Meetings

Project Management Plan

"PMP" and the PMP logo are certification marks registered in the
United States and other nations
4 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 71;
Project Management Plan contents

Project Management Lifecycle and processes selected by the Project Management


Team and the degree of rigor of their implementation for various Phases
Descriptions of Inputs, Outputs, Tools and Techniques to be used for accomplishing
these processes
A Change Management Plan and Configuration Management Plan
Also includes processes for key Management Reviews
All subsidiary plans (Scope Management Plan, Schedule Management Plan, Cost
Management Plan etc.)
Performance Measurement Baselines (scope, schedule and cost )
Milestone list,
Resource calendar

"PMP" and the PMP logo are certification marks registered in the
5
United States and other nations;
Direct and Manage Project Work

It is about performing the work defined in the project management plan to


produce the project deliverables

PM Plan, Approved Change Requests


Plan
Deliverables

Changes Execution
Expert Judgment, PMIS, Meetings
Status
Defects

Deliverables, Work Performance data, Issue Log, Change Requests and Updates
to PM Plan and Project Documents

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
6 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 71
Manage Project Knowledge

This process involves applying existing knowledge and creating new


knowledge

PM Plan, Lessons Learned Register,

Expert Judgment, Knowledge Management, Information


Management, Interpersonal and Team skills (Active Listening,
Facilitation, Leadership, Networking)

Lessons Learned Register, PM Plan updates, Organizational Process updates

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
7 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 71
Monitor and Control Project Work

This process involves tracking, reviewing and regulating the Project progress
to meet the performance objectives

PM Plan, Project Documents, Work


Performance Information

Expert Judgment, Data Analysis, Decision making, Meetings

Change Requests, Work Performance Reports, updates to PM Plan


and Project Documents

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
8 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 71
Monitor and Control Project Work

This process Involves:

Comparing the actual performance against Project Management Plan


Analyzing, tracking and monitoring project risks/identifying new risks
Proper communications management/ forecasting
Maintaining an up-to-date status of project’s product
Monitoring implementation of approved changes

"PMP" and the PMP logo are certification marks registered in the
9
United States and other nations;
Change Requests Cycle

Rec. CA

Execution Deliverables M&C Rec. PA


Rec DR

App. CRs
ICC Updates
Rej. CRs

"PMP" and the PMP logo are certification marks registered in the
10
United States and other nations;
Perform Integrated Change Control

This process concerns mainly change management activities, including


reviewing all Change Requests, approving Changes and managing Changes to
the deliverables

Change Requests, Project Management Plan

Change control tools, Data Analysis (Alternative Analysis, Cost-


benefit Analysis), Decision making, Meetings

Approved Change Requests, Change Log, Updates to PM Plan


and Project Documents

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
11 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 71
Change Control Tools

Tools used here should support configuration management and change management.
These could be manual or automated as per the needs of the project

Configuration management tool should support activities such as identification ,


record, reporting, control, verification and audit.
Change management activities would include identification, documentation of
change, decide and track changes through implementation

"PMP" and the PMP logo are certification marks registered in the
12
United States and other nations;
Project Manager’s role in Change Control

Recognize the change and assess their validity and impact

Create alternatives and rank them for presentation to Change Control Board (CCB)/
Top Management

The role of CCB is clearly spelt out in the Configuration Control and Change Control
procedures

Obtain relevant decisions , integrate them back into the Project Plan and
communicate to all concerned

Track and report results

"PMP" and the PMP logo are certification marks registered in the
13
United States and other nations;
Close Project or Phase

This process finalizes all activities across the project management process
Groups to formally complete the project or phase

PM Plan, Project Charter, Project Documents,


Business Documents, Agreements, Accepted
Deliverables

Expert Judgment, Data Analysis (Document Analysis, Trend


Analysis, Variance Analysis), Meetings

Final Product, Service or result transition, Final Report,


Organizational Process Asset Updates

"PMP" and the PMP logo are certification marks registered in the
United States and other nations;
14 Project Management Institute, A Guide to the Project
Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 71
Project Closure

Documents project results – to formalize acceptance of the product of the


project by the sponsor / customer
Confirms that the project has met all the relevant stakeholders’ requirements
and expectations
Transfers project’s product to operations or maintenance
Updates employee skills database to reflect new skills/ proficiency increases
Updates organizational asset database
Pass on Lessons learned to appropriate corporate function

Celebrate successful closure!

"PMP" and the PMP logo are certification marks registered in the
15
United States and other nations;
Final Report

Provides a summary of project performance


o To what extent were the Project objectives achieved
o Evidence that the completion criteria was met
o Quality objective achievement and reasons for any variance
o Including acceptable cost range, actual cost and reason of any variance
o Summary of validation result
o Benefits achieved to date and time frame for achieving residual benefits
o Summary of issues and risks dealt with in the project

"PMP" and the PMP logo are certification marks registered in the
16
United States and other nations;
Emerging Trends

Some emerging trends are:


Use of automated tools
Use of Visual management tools
Project knowledge management
Expanding the project manager’s responsibility
Hybrid methodologies

In an agile environment, detailed product planning and delivery is delegated to the


team. Nevertheless, Project Managers responsibility of integration doesn’t change
still. Project Managers focus is on building a collaborative decision making
environment.

"PMP" and the PMP logo are certification marks registered in the
17
United States and other nations;
What we learnt here?

Project Integration management


Project Management Plan components
Change control process
Project closure
Evolving trends in Integration management

"PMP" and the PMP logo are certification marks registered in the
18
United States and other nations;
5. Scope Management

www.qaiglobal.com

1
Project Scope Management

Define & control what is and is not included in the project


Constantly checking to make sure you are completing
all the work
Preventing extra work or gold plating
Product Scope and Project Scope are interlinked

Project Scope Product Scope


WORK FEATURES All the work and only the work

2
What goes where?

Plan Scope Management – The process of creating a scope management plan which
documents how project scope will be defined, validated and controlled

Collect Requirements – The process of defining and documenting stakeholder needs


and expectations from the project

Define Scope – Developing a detailed description of the project and the product

Create WBS – The process of subdividing project deliverables and project work into
smaller, more manageable components

Validate Scope – Formalizing acceptance of completed project deliverables

Control Scope – Monitoring the status of the project and product scope and managing
changes to the scope baseline

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
Plan Scope Management

Project Charter, Project Management Plan

Expert Judgment, Alternative Analysis, Meetings

Scope Management Plan, Requirement Management Plan

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
Collect Requirements

The process involves capturing project and product requirements of


stakeholders

Stakeholders’ needs to be understood for successful project planning and


execution
Requirements include the quantified and documented needs and
expectations of stakeholders

5
Collect requirements

Project Charter, Project Documents,


Business Documents, Agreements

Data Gathering, Data Analysis, Decision Making, Data


representation, Interpersonal skills, Prototyping

Requirement Documentation, Requirement Traceability Matrix,

Project Management Institute, A Guide to the Project Management


6 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
Requirement gathering techniques

Data Gathering – Brainstorming, Interviews, Focus group, Questionnaire & Surveys,


Benchmarking
Data Analysis: Document Analysis can be used to analyze documents such as
Agreements, Business documents, business rules, process flows, regulatory
documents, RFP etc. to elicit requirements
Decision making: Voting/Autocratic/Multi criteria decision analysis
Data Representation: Use of mind maps
Interpersonal skills: Nominal group technique, Observation/Conversation, Facilitation
Prototyping: Could be used to obtain early feedback on requirements

7
Sample Requirement Traceability Matrix
Requirement ID

Source
Requirement

Requirement
Product

Status
Requirement

HLD Section #

LLD Section #

Code Unit

UTS #

STS #

User Manual
001 Business R012 Verified 4.1 Parse 4.1.1 Read Read_Card UT 4.1.032 ST 120.020 Section 12
Rule # 1 Credit Mag Strip Card Type _Type.c UT 4.1.033 ST 120.021
card types Read_Card UT 4.1.038 ST 120.022
_Type.h UT 4.1.043

4.1.2 Verify Ver_Card UT 4.2.012 ST 120.035 Section 12


Card Type _Type.c UT 4.2.013 ST 120.036
Ver_Card UT 4.2.016 ST 120.037
_Type.h UT 4.2.031 ST 120.037
Ver_Card UT 4.2.045
_Types.dat

8
Define Scope

Project Charter, Requirement


Documentation, Scope Management Plan

Product Analysis, Alternatives


analysis

Project Scope Statement, Project


Documents updates

Project Management Institute, A Guide to the Project Management


9 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
Project Scope Statement - contents

Projects fail in the beginning, not the end - A rushed scope definition will likely cause
problems later on in the project
Project Scope statement includes the Deliverables and the ‘Work’ needed to
produce the Deliverables
Enables detailed planning, baselining and controlling the project
Major Deliverables/ Exclusions are stated
Anything not Explicitly Included is Implicitly Excluded
It includes product scope description, project deliverables, product acceptance
criteria etc
Also includes boundaries of the project, amplified set of constraints and
assumptions etc.

10
Create WBS

Project Scope Statement, Requirements


Documentation, Scope Management Plan

Expert Judgment, Decomposition

Scope Baseline, Project Documents


updates

Project Management Institute, A Guide to the Project Management


11 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
WBS

WBS details out the project scope and subdivides the project work into smaller more
manageable pieces of work

The first level decomposition may relate to project phases, deliverables or sub-
projects

The lowest level of WBS is called the Work Package with Control
Accounts placed as required in between

The Project Manager keeps decomposing the WBS, until at the Work Package level,
desired clarity is obtained for Scope, Time and Cost as well as for Management of
Risk and Quality

What is not there in WBS is not in the scope of the project


Lower level elements in the WBS are necessary and sufficient to produce
the higher level deliverables (100% rule)

12
WBS

Activities

Resource estimation
Requirements

Cost estimation
Scope

Duration estimation
WBS

Identify Risk

Plan Quality

Work Allocation

13
WBS – Software Project

Project

Requirement Development Training & Implementation


Analysis Documentation & Support

SIT & Go Live/


Initiation Design Launch
UAT

Functional Technical
Coding Unit Testing
Specs Specs

14
WBS – Telecom Tower Set up Project

A. GBT Set up

A.1. Site Acquisition A.2 Infrastructure A.3 Quality

A.3.1 A.3.2
A 2.1 Civil
A 1.1 Electrical
Civil Work Acceptance
Site Survey Acceptance

A.2.2 A.2.3
A 1.2 Tower Erection
Electrical Work
Legal
Documentation

15
WBS Dictionary

The WBS dictionary provides detailed descriptions of the components in the WBS
including:
Description of Work
Responsible organization
List of schedule milestones
Associated activities
Resources required
Cost estimates
Quality requirements
Acceptance criteria
Technical references
Contract information

16
Validate Scope

Scope Validation connotes to formalizing Product


Acceptance

Control Quality usually precedes Validate Scope


process

17
Validate Scope

PM Plan, Requirements Documentation, Requirement Traceability matrix,


Verified Deliverables, Work Performance Data

Inspection, Decision making (Voting)

Accepted Deliverables, Change requests, Project Documents updates

Project Management Institute, A Guide to the Project Management


18 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
Control Scope

Control Scope is about protecting the project scope from


change and, when change does happen, managing those
changes

Changes are inevitable in a project environment and require proper control, to


reduce the risk of scope creep and for better project success

Triggers for Scope change could come from Multiple sources

Change Requests can relate to Scope Baseline or other Components of


PM Plan and can include Preventive or Corrective Actions or Defect Repairs

Approved Change Requests can require Updates in the PM Plan and Project
Documents

19
Control Scope

Scope Baseline, Work Performance Data, Requirements Documentation,


Requirement Traceability Matrix

Data Analysis (Variance Analysis, Trend


Analysis)

Change Requests, Work performance Information, Updates to Project


documents, PM Plan and Lessons learned register

Project Management Institute, A Guide to the Project Management


20 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 130
Emerging Trends

Some emerging trends are:


Use of Business Analysis in defining, managing and controlling requirements
management activities. Business analysis activities may start before a project is
initiated.
Projects may be assigned a Business Analyst role in which case all requirements
management responsibility will be owned by this person. However, PM needs to
ensure all requirements related work is accounted for in Project plan and conducted
on time and to budget.

"PMP" and the PMP logo are certification marks registered in the
21
United States and other nations;
Agile Considerations

The overall scope of an adaptive project will be decomposed into a set of


requirements and work to be performed, sometimes referred to as a product
backlog. The backlog continues to evolve all through the project life cycle

Agile methods deliberately spend less time trying to define and agree on scope in the
early stage of the project and spend more time establishing the process for its
ongoing discovery and refinement

During iteration planning, the three processes (Collect requirement, Define scope and
create WBS) are repeated for each iteration contrary to predictive life cycles

In Agile, the customer/sponsor is continuously (end of each iteration) engaged with


the project to review products and provide feedback. Thus ‘Validate Scope’ process is
a continuous activity in agile contrary to predictive life cycle where this happens at the
end of project (or phase)

Projects run in an agile methodology use backlogs as against scope baseline for
scope validation and control

"PMP" and the PMP logo are certification marks registered in the
22
United States and other nations;
What we learnt here?

Scope Management Life cycle

Importance of Requirements Management in Scoping

Processes for defining the Scope Statement

Importance of WBS/ WBS Dictionary

Scope Validation and Control processes

Emerging trends and agile considerations

23
6. Project Schedule
Management

www.qaiglobal.com

1
Schedule Management

The first 90 percent of a project schedule takes 90 percent of the time. The last 10 percent
takes the other 90 percent of the time.‘

Schedule Management relates to the Processes which need to be done to complete the
project within the defined schedule

Schedule and Cost Management go hand in hand

2
What goes where?

Plan Schedule Management: Establishes guidelines and method for managing the
project schedule throughout the project.

Define Activities: Definition of Activities to produce the project deliverables

Sequence Activities: Incorporating Logical dependencies amongst the defined Activities

Estimate Activity Durations: Estimating the likely durations (elapsed times) of various
activities

Develop Schedule: Combining the prior processes to produce the overall Schedule

Control Schedule: Monitoring the project and controlling changes to the Project
schedule

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 173
Plan Schedule Management

To define policies, procedures and guidelines for planning, developing,


managing and controlling the project schedule

PM Plan, Project Charter

Data Analysis (Alternate Analysis) Techniques, Meetings

Schedule Management Plan

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 174
Define Activities

Identifying all Activities needed to be performed to complete the project


successfully

Schedule Management Plan, Scope Baseline,


Organizational Process Assets

Rolling Wave Planning, Decomposition

Activity List, Activity Attributes, Milestone List

Project Management Institute, A Guide to the Project Management


5 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 174
Rolling Wave Planning

Construction
Project

Infrastructure Phase 2 Phase 3 Phase 4

Civil

Electrical
Deliverables to be determined
Tower

6
Sequence Activities

Identifying the dependencies that exist between the various activities in


the project

Schedule Management Plan, Activity List, Activity Attributes, Milestone List,


Project Scope statement

Precedence Diagramming Method (PDM), Leads and Lags, Dependency


Determination and Integration, PMIS

Project Schedule Network Diagram

Project Management Institute, A Guide to the Project Management


7 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 174
Dependency Determination– Logical Relationships

Mandatory Dependencies/Hard – Inherent in nature of work


Logic

Discretionary Dependencies/ – As per best Practices


Preferred Logic
External Dependencies – Between project and non-project activities

Internal Dependencies Precedence relationship between project


activities

8
Multiple Types of Precedence Relationships

Start to Start
Finish to Start
A A

B B
A finishes then B starts A starts then B starts

Most commonly used relationship Used sometimes


Finish to Finish

Start to Finish
A A

B
B
A starts then B finishes
A finishes then B finishes

Rarely used relationship Most rarely used relationship

9
Network Diagramming Method

Precedence Diagramming Methods (PDM)

Also called activity-on-node (AON) project network diagrams


Activities are represented by boxes
Arrows show relationships between activities
Can depict the four different types of dependencies

G H I

Start End

J K L

10
Estimate Activity Durations

Estimating the number of work periods required to perform the various activities
in the project

Activity List, Activity Attributes, Resource


Requirements, Organizational Process Assets,
Risk Register

Analogous Estimating, Parametric Estimating,


Three Point Estimates, Bottom-up, Data
Analysis (Reserve Analysis), Decision making,
Meeting

Duration Estimates, Project Documents Updates

Project Management Institute, A Guide to the Project Management


11 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 174
Develop Schedule

To complete the project in the shortest amount of time


possible

Outputs of preceding processes, Project Scope


Statement, Risk Register

Schedule network analysis, Critical Path


Method, Schedule Compression, Resource
Optimization, Leads and Lags, Data Analysis
(What-if-scenario, Simulation), PMIS, Agile
release planning

Schedule Baseline, Schedule Data, Project Calendars

Project Management Institute, A Guide to the Project Management


12 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 174
Critical Path Method

B6
C6
A2 FS+2

G5
D5

E6

F3

Activity Duration Preceder ES EF Successor LS LF Float

A 2 - 0 2 B,D,E 0 2 -
B 6 A 2 8 C+2 2 8 -
C 6 B+2 10 16 G 10 16 -
D 5 A 2 7 G 11 16 9
E 6 A 2 8 F 7 13 5
F 3 E 8 11 G 13 16 5
G 5 C,D,F 16 21 - 16 21 -

13
Critical Path Method

The critical Path is the longest path through the Network which represents the
minimum time in which the project can be completed

There can be more than one Critical Path – the more they are – more risky it is
for the Project Manager

The Critical Path can change as the project progresses.

To shorten the project, focus on Critical Path activities.

Is a powerful tool for top level reporting and resource requisition

Escalation of durations of non-critical activities beyond a point


may result in having additional Critical Paths.

14
Other Tools used in Scheduling

Schedule Compression
Crashing – How to obtain the greatest schedule compression with least
incremental cost, by analyzing the cost and schedule tradeoffs
– Feasible for ‘effort-driven’ activities
Fast Tracking – Doing activities in parallel by relaxing dependencies

Data Analysis Techniques


What-if Scenario Analysis: Calculating multiple project durations with
different sets of scenarios that may apply.
Simulation: Used to calculate a range of possible project duration

15
Schedule Development Tools

Leads and Lags

Task A Task B Task C

Lag adds time Lead reduce time

Leads and Lags must be considered in the Project Schedule since an abundance of Lag
time can increase the project duration. An abundance of Lead time may introduce more
risk to the project.

16
Develop Schedule - Resource Optimization Techniques

Often, Critical resources pose a problem in scheduling

Resource leveling is used:


To address the issue of shared resource ‘over-stretching’
To keep resource usage at a constant level during specific time durations

17
Resource Histogram - Leveling

Staff hours
120
110
100
Engineers
90
Resource Usage

80
70
60
50
40
30
20
10
0
8 15 22 29 6 13 20 27 6 13 20 27 3 10 17 24 1 8 15 22
Apr May Jun Jul Aug

Weekly Resource Usage in Man Days

18
Sample Gantt Chart (View from MS Project)

19
Sample Network Diagram (View from MS Project)

20
Agile Release Planning

21
Control Schedule

Monitoring the up to date status of the project and


managing and controlling schedule variations in
the project

PM Plan, Schedule Baseline, Work


Performance Data,

Data Analysis, Tools of previous process like


CPM, Compression, Leads/Lags, Resource
optimization, PMIS

Work Performance Information, Schedule Forecasts, Change Request,


Updates to PM Plan and Project Documents, Lessons learned register

Project Management Institute, A Guide to the Project Management


22 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 174
Control Schedule Techniques

Data Analysis techniques used in schedule control include:


Earned Value analysis
Iteration burndown chart
Trend analysis
Variance analysis
What-if-scenario analysis

23
Burndown Chart

24
Emerging Trends

Some emerging trends are:


Iterative scheduling: This is a form of rolling wave planning based on adaptive life
cycles. The benefit of this approach is that it welcomes changes throughout the
development life cycle

On-demand scheduling - On-demand scheduling does not rely on a schedule that


was developed previously, but rather pulls work from a backlog or intermediate queue
of work to be done immediately as resources become available

While tailoring schedule management process PM needs to consider factors such as


Lifecycle approach
Resource availability
Project dimensions
Technology support

25
What we learnt here?

Schedule Development Process


Define Activities process
Estimation techniques
Modelling Techniques
Critical path computation
Schedule Compression/ Resource optimization
techniques
Schedule Monitoring on an ongoing process

26
7. Project Cost Management

www.qaiglobal.com

1
What goes where?

Plan Cost Management: Developing the Cost Management Plan which documents
how the project costs will be planned, structured and controlled

Estimate Costs: Developing the likely costs of performing project activities

Determine Budget: The process of aggregating the costs of individual activities to


establish a Cost Baseline

Control Costs: Controlling the Variances against the Cost Baseline

Project Management Institute, A Guide to the Project Management


2 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 231
Plan Cost Management

Provides guidance and direction on how the project costs will be managed
throughout the project

Project Management Plan, Project Charter

Expert Judgment, Data Analysis, Meetings

Cost Management Plan

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 232
Estimate Costs

Estimating the cost of the resources needed to perform project activities

Cost Management Plan, Scope Baseline,


Project Schedule, Resource requirements and
Risk Register

Analogous Estimating, Bottom Up Estimating, Parametric Estimating and


Three Point Estimates, PMIS, Data Analysis (Reserve Analysis, Alternative
analysis, COQ),

Activity Cost Estimates, Basis of estimate

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 232
Determine Budget

A Budget is primarily a compilation of the individual


Costs Estimates.

Cost Management Plan, Project Schedule,


Scope Baseline, Activity Cost Estimates, Basis
of estimate, Risk Register, Business
Documents, Agreements

Cost Aggregation, Funding Limit Reconciliation,


Data Analysis (Reserve Analysis), Financing, Historical
information review
Cost Baseline, Project Funding Requirements

Project Management Institute, A Guide to the Project Management


5 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 232
Cost Baseline

Cost

Time

6
Control costs

This process monitors the status of the project and managing changes as
needed

Cost Management Plan, Cost Baseline, Project Funding


Requirements, Work Performance Data

Data analysis (Earned Value, Reserve Analysis, Variance


analysis, Trend analysis), PMIS

Work Performance Information, Cost Forecasts, Change Requests,


Project Management Plan updates

Project Management Institute, A Guide to the Project Management


7 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 232
Earned Value Management

Is a powerful tool for measurement and reporting :

It integrates scope, cost and schedule measures to help the Project Team
evaluate the project’s performance
It enables the Project Manager to know the % of completed work and the value
of the completed work
It is a quantitative technique for assessing and predicting project progress.
It is a quantitative technique for assessing and predicting project progress.

SCOPE COST

TIME

8
Earned Value Management

The Planned Value (PV)


the budgeted cost of work scheduled

The Actual Cost (AC)


the actual cost of work performed

Earned Value (EV)


the budgeted cost of work performed
– signifies the value of the work performed.

9
Earned Value: Variances

Schedule Variance (SV): SV = EV – PV


A negative variance indicates a schedule overrun condition, positive variance is
favourable to the project

Cost Variance (CV) : CV = EV – AC


A negative variance indicates a cost overrun condition, positive variance is favourable
to the project
Cost
(under) Variance

D A
(behind) (ahead)

Schedule
Variance
C B

(over)

10
Earned Value: Performance Indices

Schedule Performance Index (SPI) - SPI is an indication of the efficiency with which the
project is utilizing scheduled resources SPI = EV/PV
If SPI > 1.0 we have favourable performance. Project is ahead of schedule
If SPI < 1.0, less has been completed than what was scheduled, so project is
behind schedule.

General Interpretation – the project is progressing at -% of the schedule originally


planned

Cost Performance Index (CPI) – CPI is an indication of the efficiency with which the
project is utilizing the cost budget CPI = EV/AC
If CPI > 1.0 we have favourable performance. Productivity is more than what
was expected
If CPI < 1.0, performance is poor, productivity is less

General Interpretation - The project is realizing -% of value for every 100% of the $ spent

11
Some more EV Elements Explained…

The Budget at Completion (BAC)


Is the sum of all the budgets allocated to the Activity/ WBS component

The Estimate at Completion (EAC)


It is the new likely total cost of the project

The Estimate to Complete (ETC)


It is the likely cost of completing the remaining work in the project

Variance at Completion (VAC)


The difference between BAC and EAC

12
Estimate at Completion- Forecasting Techniques

EAC - Calculated by multiple ways – to get a range of estimates, like:

EAC = AC + ETC (judgmental)


– ‘Sunk costs’ + revised future costs

EAC = AC + (BAC- EV)- when current variances are seen to be atypical and
the Project Management expectations are that similar variances will not
occur in future.

EAC = BAC/CPI –future spending will continue in a predictable way as was


observed so far for Cost Variance

EAC = AC + (BAC-EV)/(CPI*SPI) – when future performance is expected to


be affected by both time and cost

13
To-Complete Performance Index (TCPI)Techniques

TCPI is the Target projection of the Cost Performance to be achieved on the remaining
work to meet a specific Cost objective – as a Target BAC or a Target EAC

If BAC is not a viable figure, these forecasts are better done with EAC

TCPI (based on BAC) is calculated as

TCPI = (BAC-EV)/(BAC-AC)

On the other hand, if a new EAC has been approved by Management, then

TCPI = (BAC-EV)/( EAC-AC)

14
Cost Management Concepts

Term Description Example


Capital Cost Projects requiring investment in project Buildings/ Equipment/ Servers
specific capital assets. The money spent on
assets can be treated as a depreciable
expense for the taxation purposes.

Cost of Cost of raising capital, or the cost of raising Capital raised from Banks, Funding
Capital funds via various means – through a Capital agencies etc.
budgeting process

Direct Cost Costs that are incurred specifically for a Cost for project related material,
project salary expenses associated with
subcontractors & billable staff

Indirect Cost Costs that are borne by the organization, and Salaries of Corp. Executives,
(Overhead) then shared across projects proportionately Administrative Expense, Rental,
building costs

15
Cost Management Concepts

Term Description Example


Opportunity The cost of choosing one alternative and Choosing a line of business over
Cost therefore, giving up the potential benefits of another based on business
another alternative reasons

Return On The value returned as profit from a project Profit from setting up an
Investment entertainment theme park

Sunk Cost Money irrevocably spent in a project or a cost Past costs incurred in an ongoing
that has been paid for prior to making the project/ Consultant fees reg.
decision for the projects under consideration project selection

Fixed costs Costs which are incurred irrespective Machine set up costs
of the volume of production.

Variable Costs Costs that rise directly with the size of the Hardware parts consumed in an
project/ volume of production and are related product assembly
to consumable materials used to accomplish
the project

16
Emerging Trends

Some emerging trends are:


Expansion of Earned Value Management – Earned schedule (ES) and Actual Time
(AT)
SV = ES – AT

SPI = ES/AT

While tailoring schedule management process PM needs to consider factors such as


Knowledge Management – Financial database repository
Estimating and Budgeting – Policies, procedures, guidelines
Earned Value Management - Is it used in the organization?
Use of Agile – If agile is adopted
Governance – Formal/informal audit

17
Agile Considerations

Projects with high degrees of uncertainty or those where the scope is not yet fully
defined may not benefit from detailed cost calculations due to frequent changes.
Lightweight estimation can be used to generate a fast, high-level forecast of project
labor costs, which can then be easily adjusted as changes arise. Detailed estimates
are reserved for short-term planning horizons in a just-in-time fashion

When using agile approach with high-variability projects where the budget is also
constrained, the scope and schedule are adjusted to stay within cost constraints.
Scope swapping can be opted for.

18
What we learnt here?

Cost Management process

Various methods of Cost estimating

Various methods of Cost estimating

Application of EVM to project Cost control

19
8. Quality Management

www.qaiglobal.com

1
Project Quality Management

*Quality is the totality of characteristics of an


entity that bear on its ability to satisfy stated or
implied needs.

Project Quality Management includes processes


to ensure that the project fulfills its obligations to
satisfy the project needs

Important terms:

1) Quality vs. Grade

2) Accuracy vs. Precision

3) Quality Policy

2
What goes where?

Plan Quality Management – Determining which quality standards are relevant to the
project and finding out the best methods of achieving the same

Manage Quality – : The process of translating the quality management plan into
executable quality activities

Control Quality – Monitoring results of quality management activities to assess


performance and ensure outputs meet customer requirements

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 271
Plan Quality Management

What quality standards apply to my project?


How to satisfy them?

PM Plan, Stakeholder Register, Requirement


Documentation, Risk Register

Benchmarking, Brainstorming,
Interviews, Cost-Benefit Analysis, Cost Quality is planned in, not inspected in
of Quality (COQ), Test and Inspection
Planning

Quality Management Plan, Quality Metrics,


PM Plan updates

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 272
Plan Quality Tools and Techniques

Brainstorming: Used to creatively gather data from team or subject matter experts to
develop the Quality Management Plan adequate for the project

Benchmarking : Comparing actual or planned project practices to ‘best in class’ or


competitors
Interviews: Key stakeholders can be interviewed to gather information on required
quality expectations both implicit and explicit

Cost-Benefit Analysis : The Project Team has to balance the costs of deployment of
incremental quality vis-a-vis corresponding incremental benefits
( Marginal Benefit Analysis principle)

Cost of Quality (COQ): includes cost of Conformance and cost of Non-conformance

Test and Inspection Planning: Performed by PM and team to determine how to


test/inspect the project deliverables

5
Plan Quality Tools and Techniques - COQ

Quality

Cost of Cost of
Quality Non Quality

Cost of Cost of
Conformance Non-Conformance

Prevention Appraisal Internal External Brand Image


Failure Failure Market Share

•Quality Systems •Inspection •Defect Repair •Warranty/ Maintenance


•Training •Testing •Rework •Recall/Replacement
•Self Certification •Calibration •Scrap •Litigation

6
Manage Quality

Manage Quality mostly relates to


conformance and capability assurance
activities relating to project and product
quality

Quality Management Plan, Quality Control


Measurements, Risk Report

Checklists, Alternative Analysis,


Document Analysis, Audits, Process
Analysis, Quality Improvement Methods

Quality Reports, Test and Evaluation


Documents, Change Requests, Updates
to PM Plan

Project Management Institute, A Guide to the Project Management


7 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 272
Manage Quality

The objective of Manage Quality process include:

Design an optimal and mature product by adopting specific guidelines and processes
Build confidence that a future output will confirm to specified requirements
Confirm that the quality processes are being complied to
Improve the efficiency and effectiveness of processes and activities

8
Control Quality

Measure specific project results to


determine whether quality has been met

Quality Management Plan, Quality Metrics, Test


and Evaluation Documents, Approved Change
Requests and Deliverables

Checklist, Statistical Sampling,


Questionnaire & Surveys, Performance
reviews, Inspection and Testing/Product
Evaluations

Quality Control Measurements, Verified


Deliverables, Change Request and
updates to Test and Evaluation
Documents

Project Management Institute, A Guide to the Project Management


9 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 272
Common Tools in Quality

Checklist
Check sheets
Root cause analysis
Control chart s
Histograms
Scatter diagrams
Flowcharts
Affinity diagrams

10
Cause and Effect Diagrams (Ishikawa/ Fishbone Diagrams)

Possible
Causes

Problem
Quality Training
Attitude

Operator
Mix Raw material

Defective
piece
Voltage Setup

Machine

Environment
Maintenance
Pressure

11
Control Charts

CONTROL CHART for Machine X


Mean diameter (mm)

USL
UCL
10.
8
10.
7
10.5 MEAN
10.3 LCL
10.2 LSL
0 5 10 15
Time pints 20 25 30

MEAN Normal expected result of diameter of washers produced


USL Upper Specification Limit (nothing above this limit will be of acceptable
quality)
LSL Lower Specification Limit (nothing below this limit will be of acceptable quality)
UCL Upper Control Limit (Ideal upper acceptance limit for internal quality)
LCL Lower Control Limit (Ideal lower acceptance limit for internal quality)

12
Histograms

Can be used to organize data collected for measurements done on a product or process

Shows frequency of occurrence of items within a range of activity


Involves “grouping” of data
Shows “count” per interval

No. of samples having


defective pieces

# of defective pieces 4 5 6 7

13
Other Quality Tools

Scatter Diagrams
o Used to determine the correlations Design Complexity vs. Defect Density
relationship between independent and
dependent variables 10
o To explore cause-effect relationships
8

Errors/KLOC
Checklist 6
Series1
o A checklist is a structured tool to ensure a series 4
of steps have been performed to help ensure 2
consistency
0
o Standard checklists may be available in the 20 25 30 35
organization
Complexity

Checksheet
o Inspection includes activities to determine
whether results conform to standards at any
stage of the project lifecycle

14
Other Quality Tools

Check sheets
o Check sheets are also known as tally sheets and are used to organize facts
in a manner that will facilitate the effective collection of useful data about a
potential quality problem

15
Other Quality Tools

Flowcharts
o Also referred to as Process Maps display the sequence of steps in a
process.
o Particularly useful to analyse any redundant/non-value added steps in the
process

Affinity Diagram
o Allows large numbers of ideas to be classified into groups for review and analysis

16
Emerging Trends

Some emerging trends in Quality Management include:


Customer Satisfaction - This requires a combination of conformance to
requirements and fitness for use. In Agile environments continuous/frequent
engagement with customer ensures customer satisfaction is maintained
throughout the project
Continual Improvement - Initiatives such as PDCA, TQM, SIx sigma
Management Responsibility - Management must equip the Project Team with
the resources needed to achieve quality, although success requires participation
of all
Mutually beneficial partnership with suppliers - A shift from traditional
supplier management to partnership and cooperation model which can create
value for each other and enhance joint responses to customer needs

17
Agile considerations

Agile methods call for frequent quality and review steps built in throughout the project
rather than toward the end of the project
Recurring retrospectives regularly check on the effectiveness of the quality processes
(New approaches are tried and in subsequent retrospectives these are reviewed for
effectiveness and adjusted if required)
Focus on small batches of work (iterations) uncovering inconsistencies and quality
issues much early

18
What did we learn here?

Key concepts in Quality Management


Plan Quality Management Process
Cost of Quality
Manage Quality process
Quality Audits
Control Quality process
Tools in Quality Management

19
9. Resource
Management

www.qaiglobal.com

1
Project Resource Management

Resource Management includes the processes that identify, acquire and


manage all resources needed to complete the project

Project Resources include team members, supplies, materials, equipment,


services and facilities

The Project Management Team assists the Project Manager in Planning


onwards

2
What goes where?

Plan Resource Management: The process of defining how to estimate, acquire,


manage, and utilize physical and team resources

Estimate Activity Resources: Estimating the types and quantities of Resource


requirements of various activities

Acquire Resources: Obtaining the human resources needed for the project

Develop Project Team: Enhancing the competencies of Project Team and creating a
favourable environment conducive for effective project performance

Manage Project Team: Resolving team issues, tracking team member performance
and providing feedback

Control Resources: Ensuring availability of physical resources and monitoring


planned vs. Actual resource usage

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 307
Plan Resource Management

Project Charter, PM Plan, Project Documents

Data Representation, Organizational


Theory , Meetings

Resource Management Plan, Team


Charter

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 308
Data Representation

Three formats to document Team member Roles and Responsibilities


Hierarchical Type
Matrix – Based
Text-Oriented

5
Project Org. Chart – Hierarchical Type

6
RACI Chart (Responsibility Assignment Matrix)

Project Team Members


Activity Steve Mark Peter David John

Requirement A R I C

Design A I R C
Construct C A R C C
Testing I A I C R

7
7
Text- Based Format

Role___________________________________

Responsibilities____________________________________
__________________________________________________
__________________________________________________

Authority__________________________________________
__________________________________________________

8
8
Resource Management Plan

The Resource Management Plan can include the following:

Where are we going to acquire the team and physical resources from

Roles and responsibilities

Organization charts depicting reporting relationship

Project team resource management guidelines

Any training need for project team

Team development guidelines

Resource control – How physical resource utilization will be monitored. May also
include guidance on inventory management etc.

Reward and recognition for project team

9
9
Estimate Activity Resources

Estimating the type and quantities of resources needed to perform the


individual activities in the project

Resource Management Plan, Activity List,


Resource Calendars, Activity Attributes, Risk
Register, Activity Cost Estimates,
Organizational Process Asset

Bottom up Estimating , Analogous estimating,


Parametric estimating, Alternative Analysis,
PMIS

Resource Requirements, RBS

Project Management Institute, A Guide to the Project


10 Management Body of Knowledge, (PMBOK® Guide) – Sixth
Edition, Project Management Institute Inc., 2017, Page 308
Acquire Resources

The PM’s role in this process relates to Confirming


and Obtaining the Extended Team

Resource Management Plan, Procurement


Management Plan

Decision making (Multi-Criteria decision


analysis), Interpersonal skills
(Negotiation), Pre assignment, Virtual
teams

Physical Resource assignment, Team


assignments, Resource Calendars

Project Management Institute, A Guide to the Project Management


Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
11
Management Institute Inc., 2017, Page 308
11
Develop Project Team

Project Teams need development to align best to


project objectives and contribute to project
performance

Project Team Assignments, Resource


Management Plan, Team Charter

Co-Location , Virtual Teams, Communication Technology,


Interpersonal skills , Rewards and Recognitions, Training,
Team Building Activities, Ground Rules, and
Individual and Team Assessments

Team Performance Assessment,


Enterprise Environmental Factors updates

Project Management Institute, A Guide to the Project Management


12 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 308
Stages of Team Development

Adjourning

Performing

Norming

Storming

Tuckman Model
Forming

13
Manage Project Team

Project Teams require constant managing to bring


out the best in them

Resource Management Plan, Team Charter,


Team Performance Assessments ,
Issue Log, Work Performance Reports

Interpersonal and Team Skills (Conflict


Management, Emotional Intelligence,
Influencing, leadership)

Change Requests, updates to PM Plan/


Organizational Process Assets

Project Management Institute, A Guide to the Project Management


14 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 308
Control Resources

Ensuring right resource is available at the right time


and monitoring effective resource utilization

Resource Management Plan, Physical


Resource Assignment, Project Schedule,
Work Performance Data, Agreements

Data Analysis (Alternative


Analysis/Cost-benefit Analysis/Trend
Analysis) , Problem Solving,
Interpersonal skills, PMIS

Work Performance Information, Change


Requests, updates to PM Plan

Project Management Institute, A Guide to the Project Management


15 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 308
Conflict Management

Common sources of Conflict – Schedule, Budget, Priorities,


Personality issues, Tradeoffs, Administrative procedures etc.

Conflicts should be addressed early, using a direct participative


approach

Disruptive Conflicts can call for increasingly formal procedures,


including possible use of disciplinary actions.

Conflict resolution should be issue focused on current problems

16
Conflict Resolution styles

Withdrawal/Avoiding - Retreating from actual or potential disagreements and


conflict situations. Appropriate only in certain situations such as when a “cooling-off”
period is needed

Smoothing/Accommodating - De-emphasizes differences and emphasizes


commonalities. Keeps the atmosphere friendly

Compromising/Reconciling - Considers various issues and searches for solutions


which bring some degree of satisfaction to both parties. Definitive solution

Forcing/Directing - Exerts one’s view point at the potential expense of another party.
Could be of Use during emergencies or unpopular actions.

Collaborating/Problem solving - Directly addresses disagreements. Provides a


resolution but is time consuming. This is considered to be the best method for
resolving conflicts

These definitions are taken from the Glossary of Project Management


Institute, A Guide to the Project Management Body of Knowledge,
17
(PMBOK® Guide) - Fifth Edition, Project Management Institute, Inc.,
2013
Emerging Trends

Some emerging trends in resource management include:


Resource management methods – JIT, Lean management, Kaizen etc.
Emotional intelligence – Research suggests that project teams that succeed in
developing team EI are more effective and there is reduction in staff turnover
Self-organizing teams – Popular in Agile methodology where the team functions
with an absence of centralized control
Virtual teams/distributed teams - The globalization of projects has promoted
the need for virtual teams that work on the same project, but are not colocated at
the same site

18
What we learnt here?

Resource Management processes

Organization charts

Conflict Management models

Emerging trends in resource mangement

19
19
10. Communication
Management

www.qaiglobal.com

1
Project Communication Management

Project Communications Management deals with the project information


Lifecycle

Project Teams typically spend considerable amount of time in


communications

2
What goes where?

Plan Communications Management: Developing an approach/strategy for


communication in the project and identifying the Communications needs of
Stakeholders and preparation of the Communications Management Plan

Manage Communications: Distributing the information as per the Communications


Management Plan to the relevant Stakeholders

Monitor Communications: The process monitoring communications throughout the


project to ensure stakeholder’s information needs are satisfied

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 359
Project Communications

Communication mechanisms – Written, Spoken, Formal / Informal, through gestures,


through words, choice of words

Internal (within the project) or external

Upward, Downward or Horizontal

Communication Methods
Push
Pull
Interactive

4
Plan Communications Management

This process is focused on determining the project stakeholder information


needs and defining a Communication approach

Stakeholder Register, PM Plan

Communications Requirements Analysis, Communications Technology,


Communication Models, Communication Methods, Stakeholder
engagement assessment matrix

Communication Management Plan

Project Management Institute, A Guide to the Project Management


5 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 360
Factors affecting the Communications Technology

The frequency and the immediacy of information requirements of various


stakeholders

Access to Technology by the Stakeholders

Experience of the Project Team member to use the Technology

The # of communication Channels is determined by the # of persons in the Team

6
Sender-Receiver Communication Model

Noise

Feedback

Source Encoding Medium Decoding Receiver

Message Message

7
Communication channels

With N=2
1 channels With N=3
3 channels

Number of communication channels is


Calculated as n(n-1)/2

With N=4
6 channels

8
Communication Management Plan

What information needs to be collected from which Stakeholders and when and who
needs this information?
Reason for the distribution of that information
Methods used to gather and store information
Confidentiality to be applied
Description of the information to be distributed (including formats) and schedules/
Security related issues
Escalation processes including timeframes for decisions
Method for updating and refining the communications management plan as the
project progresses
Glossary of common terminology

9
Communication Matrix

Communication Frequency Information Person Distribution Escalation


Requirement Format Responsible List
What needs to be How often – Presentation, Where is the The person The person
communicate, monthly, Email , Word information of group for to be
like status report, daily, document, generated or whom the escalated to
meetings, project weekly….. excel sheet . who can information in the lack
review, Also Should also provide the is intended communicati
presentations mention contain the required on
when the structure of information
communicat information
ion has be
stopped
(when the
need is
over

10
Manage Communications

During project execution, the Information gets distributed to concerned


Stakeholders as per the Communications Management Plan

Communications Management Plan, Work


Performance Reports

Communication Technology, Communication Methods, PMIS,


Performance Reporting, Communication skills

Project Communications, Lessons Learned Register and


Organizational Process Assets get updated

Project Management Institute, A Guide to the Project Management


11 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 360
Performance Reports

Performance Reports provide the Status , Progress and Forecasts

They can show the following :

Analysis of past performance and current status of risks and issues


Work completed during the current period and forecast to be done in the
next period
Results of variance Analysis
Summary of Changes approved in the reporting period
Forecasted project completion

12
Monitor Communications

Right information to the right person at the right time

PM Plan, Project Communications, Issue Log,

PMIS, Stakeholder Engagement Assessment Matrix, Meetings

Work Performance Information, Change


Requests, PM Plan updates

Project Management Institute, A Guide to the Project Management


13 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 360
Obstacles to Intercultural Communication

Language
Non-verbal
Perceptions
Tendency to evaluate
High anxiety

14
Emerging Trends

Some emerging trends in project communications include:


Inclusion of stakeholders in project reviews - An effective communication strategy
requires regular and timely reviews of the stakeholder community, changes in in its
membership and attitudes
Inclusion of stakeholders in project meetings – Stakeholders from outside of
project (at times organization) are made to participate in project meetings.
Increased use of social computing
Multifaceted approaches to communication

In Agile methodologies
There is a need to communicate evolving and emerging details more frequently and
quickly
Posting project artifacts in a transparent fashion
Holding regular stakeholder reviews

15
What we learnt here?

Communications Management Plan

Sender Receiver Communications Models

Managing Communications and reporting performance

Monitor Communications

Cross cultural communication

16
11. Risk Management

www.qaiglobal.com

1
Risk Management

*A project Risk is an uncertain event or condition that can


have a positive or negative impact on the project

Risk Management is concerned with conducting Risk


Management Planning, Identification, Analysis and
response planning, response implementation and
monitoring risks on a project.

The objective of Risk Management is to increase the


likelihood/impact of positive risks and decrease the
likelihood/ impact of negative risks

Risk exists at two levels within every project


Individual project risk
Overall project risk

Project Management Institute, A Guide to the Project Management


2 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 395
What goes where?
Plan Risk Management – Preparing the Roadmap for the Risk
Management Lifecycle

Identify Risks– Identification of risks which might affect the project

Perform Qualitative Risk Analysis – Prioritizing risks for further analysis

Perform Quantitative Risk Analysis – Numerically analyzing the effect of prioritized


risks on overall project objectives

Plan Risk Responses – Developing options and actions to enhance opportunities


and reduce threats to project objectives

Implement Risk Responses – Implementing planned responses

Monitor Risks– Tracking identified risks, monitoring residual risks, identifying new
risks, executing risk response plans throughout the project life cycle

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 395
Plan Risk Management

The Process of Planning enables giving sufficient


consideration/ budgets and timeframes required for
Risk Management

PM Plan, Project Charter, Stakeholder Register

Data Analysis (Stakeholder Analysis) ,


Meetings

Risk Management Plan

Project Management Institute, A Guide to the Project Management


4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Risk Management Plan Contents

The key components of Risk Management (RM) Plan include:


Methodology – approaches, tools and data sources to be used for RM
Roles and Responsibilities for RM
Budgeting – establishing a budget for RM activities to be included in the cost
baseline
Timing – how often RM will be done in the project lifecycle
Risk Reporting Categories (RBS) and Reporting formats/ Definitions of risk
Probability and Impact
Revised Stakeholders’
Tolerances

“The cost of performing Risk Management must be balanced against


the expected benefits and the cost of solving the problem”

5
Sample Risk Breakdown Structure

Project

Project
Technical External
Management

Project
Performance Dependencies Resources
Technology

Regulatory Customer
Complexity and
Interfaces

6
Identify Risks

This process focuses on identification of specific risks


concerning the project

Risk Management Plan, Scope Baselines,


Activity Cost Estimates, Activity Duration
Estimates, Stakeholder Register and multiple
Management Plans/Baselines

Data Gathering (Brainstorming


Sessions, Checklists, Interviewing),
Data Analysis (SWOT Analysis, Root
Cause Analysis and Assumption and
Constraint Analysis, Document
Analysis), Prompt Lists

Risk Register, Risk reports

Project Management Institute, A Guide to the Project Management


7 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Risk Event / Impact matrix

Contingency
Management
Reserve
‘kept’ Reserve

Planning
N.A.
Known

Known Unknown
Event

8
Risk Register Contents

Includes:

List of Identified risks, their descriptions, WBS and other project elements
impacted
Potential Risk owners

Potential Risk Responses

Risk Report presents summary information on project risks


Sources of overall project risks, key drivers to overall project risk exposure
Number of threats and opportunities
Distribution of risks

9
Perform Qualitative Risk Analysis

Qualitatively identifying the impact of identified


risks on the project

Risk Management Plan, Risk Register

Expert Judgment, Interviews, PI Assessments, PI Matrix,


Risk Categorization, Meetings

Updates to Risk Register and Risk Report

This process can lead to Perform Quantitative Risk Analysis or directly into
Plan Risk Responses

Project Management Institute, A Guide to the Project Management


10 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Probability – Impact Matrix

Severe III II I
Likely Impact

IV
III II
Medium

Low V IV III

Low Medium High

Likely Probability of occurrence

11
Definition of Impact Scale

Impact Type Low Medium High

Budget <10% cost increase 10-20% cost >20% cost increase


increase
Schedule <5% time increase 5-20% time increase >20% time increase

Scope Minor areas of scope Major areas of scope Scope affected


affected affected renders end
deliverable
unacceptable

Quality Quality degradation barely Quality reduction Deliverable is


noticeable requires sponsors effectively useless
approval

12
Perform Quantitative Risk Analysis

Quantitative Risk Analysis enables the PM to


prioritize the risks in an objective manner

Risk Register, Risk Management Plan ,


Schedule/Cost Management Plans, PM Plan

EMV, Decision Tree Analysis,


Simulation

Project Documents updates

Project Management Institute, A Guide to the Project Management


13 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Perform Quantitative Risk Analysis

Quantification helps the Project Manager to :


Assess/ Quantify the risk exposure for the project
to determine Cost and Schedule Contingency Reserves
Prioritize and assign a numerical rating to risks
Assess the probability of achieving specific project objectives
Probability Distributions , Modelling , Simulations and Sensitivity Analysis are
used during Quantitative Risk Analysis

14
Decision Tree - application

A Fixed Price Contract worth $150,000 has a clause of $1000 penalty per day of
schedule delay. The following estimates for Cost and Schedule are provided:

Self-execute
Cost can vary : with a likelihood 80% 120,000 vs. with a likelihood
of 20% 140,000
Schedule: can vary : 95% on time, 5% possibility of 2 days delay

Subcontract
Cost can vary : with a likelihood of 60% 110,000 vs. with a likelihood
of 40% 120,000
Schedule can vary:: 80% on time, 20% possibility of 20 days delay

15
Decision Tree - Solution

Cost Schedule Probability Profit Potential


.76 150,000-120,000 = 30,000 22,800
Self -execute

.95

.04 150,000-(120,000+2000) = 28,000 1,120


.05
.8
.95 .19 150,000-140,000 = 10,000 1,900
.2
.05 .01 150,000-(140,000+2000) = 8,000 80
25,900
.8 .48 150,000-110,000 = 40,000 19,200
.6

.2 .12 150,000-(110,000+20,000) = 20,000 2,400


.4
.8
.32 150,000-120,000 = 30,000 9,600

.2 150,000-(120,000+20,000) = 10,000 800


.08
32,000

16
Probability of achieving cost objectives

1.00

.75
.68
Probability

.50

.25

20 40 50 55 60 80
50

Cost (‘000 $)
For a particular cost-value in x- axis, the corresponding y-axis value
indicates the probability of completing the Project within that cost-value

17
Plan Risk Responses

Planning Risk responses facilitates development


of Risk response stances for the identified and
prioritized risks in the Risk Register

Risk Management Plan, Risk Register

Strategies for Threats, Strategies for


Opportunities, Contingent Response
Strategy, Data Analysis (Alternative
Analysis, Cost-Benefit Analysis),
Multicriteria decision analysis
Change Requests, Updates to PM Plan
and Project Documents

Project Management Institute, A Guide to the Project Management


18 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Plan Risk Responses

Strategies to deal with Negative risks


Escalate – The threat happens to be outside the scope of the project or the
proposed response in beyond the Project Managers authority
These are taken care of at the Program/Portfolio level
Avoid - Eliminate the threat by eliminating the cause
Changing the Project Management Plan or alternatives to eliminate the risk
or condition.

Transfer - Make another party responsible for the risk


Transfer the Risk to a third Party

Mitigate - Reduce the probability or the impact of a threat, thereby making it a


smaller risk
Reduce the probability and/or consequences of an adverse risk event to an
acceptable threshold.

19
Plan Risk Responses

Strategies to deal with Positive risks


Escalate – The threat happens to be outside the scope of the project or the
proposed response in beyond the Project Managers authority
These are taken care of at the Program/Portfolio level
Exploit – Ensuring the opportunity occurs
Exploiting the Opportunity for best response forward

Share - Allocate ownership of the opportunity to a third party


Enhance - Maximising the ‘size’ of the opportunity
Increase the likelihood and/or Impact of the risk event
Acceptance – Do nothing about the risk (applicable for both Threats and
Opportunities)
Active acceptance would mean no response plan but keeping some buffer in
terms of time or money whereas Passive acceptance is deciding to deal with it
when it occurs (do nothing)

20
Plan Risk Response outputs

Updates to Risk Register and Risk Report


Identified risks, WBS elements impacted, risk owners and their
responsibilities
Risk Symptoms and Agreed upon Risk Response Strategies
Contingency Reserves of time and cost
Primary and Fallback plans
Description of Secondary and Residual Risks

Updates to PM Plan
The Schedule and Cost Baselines and Management Plans may get
impacted because of identified Risk responses

The Assumptions Log can get updated because of the Risk Management
Process

21
Implement Risk Responses

The process of implementing agreed upon risk


response plans

Risk Management Plan, Risk Register

Expert Judgment, Interpersonal Skills


(Influencing)

Change Requests, Updates to Risk


Register

Project Management Institute, A Guide to the Project Management


22 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Monitor Risks

Monitor risks relates to monitoring the implementation of risk


response plans, tracking identified risks, identifying and analyzing
new risks, and evaluating risk process effectiveness throughout the
project
Risk Register, Risk Report, Work Performance
Reports

Risk Audits, Reserve Analysis,

Change Requests, Updates to Risk


Register and PM Plan

Project Management Institute, A Guide to the Project Management


23 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 396
Monitor Risks – key Points

Involves:
Tracking identified risks/ Identifying new risks
Monitoring residual risks and trigger conditions
Validating project assumptions and ensuring
compliance to Risk Management processes
Assessing Whether the Reserves are adequate for future expected Risks
Ensuring the execution of appropriate risk response plans
Is an ongoing process during the life of the project

24
Emerging Trends

Some emerging trends in project communications include:


Non-event risks - There is an increasing recognition that non-event risks need to be
identified and managed. There are two types of non-event based risks:
o Variability Risk: Uncertainty exists about some key characteristics of a planned
event or activity (like rate of interest may increase or decrease)
o Ambiguity Risk: Uncertainty exists about what might happen in the future (like
regulatory changes)
Project Resilience – There is increased awareness regarding emergent risks
(unknown unknowns). Emergent risks can be tackled through developing project
resilience by
o Provisioning for adequate schedule and cost contingencies for emergent risks
o Flexible project processes that can cope with emergent risk
o Empowered project team with agreed upon limits
o Frequent review of early warning indicators

25
Emerging Trends

Integrated risk management – Projects form part of programs/portfolios. Project


risks identified at the program level may be assigned to the Project Manager to
manage at the project level. Likewise risks outside the scope of project identified by
the Project Manager may be escalated to the program to manage. This can avoid
duplication of efforts at various levels/multiple projects.

In high variability environment (Agile) there tends to be more uncertainty. Certain


practices adopted in Agile methodologies to deal with uncertainty include:
o Frequent reviews of incremental work to accelerate knowledge sharing
o Risk is considered while selecting the scope of each iteration and managed during
the iteration
o Reprioritization of backlog is performed based on better understanding of risk
exposure

26
What we learnt here?

Risk Management Process

Risk register and its updation

Various Risk Response strategies

27
12. Procurement
Management

www.qaiglobal.com

1
Procurement Management

Includes the processes to purchase or acquire products and services from


outside the project

This can also arise in the context of administering any Contracts issued by an
outside Organisation , in the context of project performance by the Seller

2
What goes Where?

Plan Procurement Management: Finalizing product Purchase decisions, specifying


the approach and identifying potential Sellers

Conduct Procurements : Obtaining Seller responses, selecting a Seller and entering


into a Contract

Control Procurements : Monitoring Contract performance, performing changes as


needed and closing out contracts

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 459
Plan Procurement Management

What to procure? When? And How to procure?

Project Charter, Business Documents,


Requirement Documentation, Risk Register,
Resource Requirements, Project Schedule, PM
Plan

Make or Buy Analysis, Market


Research, Meetings, Source selection
Analysis

Procurement Management Plan,


Procurement Strategy, Bid Documents,
Procurement SOW , Make or Buy
Decisions, Source Selection Criteria,
Independent Cost Estimates
Project Management Institute, A Guide to the Project Management
4 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 460
Types of Contract

Firm Fixed Price or Lump sum


Fixed Price Incentive Fee
Buyer’s Risk
Fixed Price with Economic Price Adjustment
FFP
Cost-Plus Fixed Fee
Cost-Plus Incentive Fee
FPEPA
Cost Plus Award Fee

Time & Material FPIF

CPIF

CPFF

Seller’s Risk

5
Type of Contract

Contract Type Pros Cons

FFP Total likely cost known at the Scope needs to be defined unambiguously –
outset else the buyer may not receive the right
Transfers maximum risk to the product
Seller Seller can try to make profit on
‘non-Tender’ items
Seller’s motivation generally low for good
quality work

CPFF/ Easier Scope mgt Total price unknown at the outset


CPIF Seller gets an incentive for Need to audit seller’s invoices
meeting the project objectives
(in CPIF)

T&M Easy to administer Seller has no incentive to control project


Can ‘mix-match’ resources costs
Total cost is unknown if the scope is not
well-defined
Requirements of record keeping/ monitoring
of seller activities

6
Procurement Management Plan

How procurement will be coordinated with other project aspects


Timetable for Procurement activities
Procurement Metrics to manage contracts
Roles and responsibilities
Constraints and assumptions
Legal jurisdiction and currency for payments
States if Independent Estimates will be used during Proposal Evaluation
Pre-qualified sellers

7
Procurement Strategy

Could include:
Delivery Methods - Like sub-contracting allowed/not allowed, Turnkey, design build
(DB), design build operate (DBO), build own operate transfer (BOOT) etc
Contract Payment Terms - Need to be aligned with organization’s internal financial
systems. Like lump sum, cost plus, T&M etc
Procurement Phases - Defining phases and guidelines on how to move to the next
phase, objective of each phase etc.

8
Bid Documents

Bid Documents seek Proposals from prospective Sellers

The format of the document may also be linked with the Buyer’s Organization's
policies and should be flexible enough to accommodate any Sellers’ suggestions for a
better discharge of the Procurement

Are known by different names like IFB, RFI, EOI,RFP, RFQ, Tender Notice etc. in
different Organizations/contexts

9
Typical Source selection criteria

Source selection analysis is performed to prioritize competing demands to decide upon


the source selection criteria. The selection method may include:
Least Cost - Appropriate for procurements of a standard products/services where
well-established practices and standards exist
Qualifications only – Where the value of procurement is less, contract is awarded
basis quality, credibility, expertise, reference etc.
Quality based – Technical evaluation based, one scoring highest is invited first to
negotiate and agree cost
Quality and cost based – Both quality and cost are given weightage
Sole Source – Buyer is not in a negotiating position
Fixed cost – The budget is fixed and often specified in RFP. The buyer selects the
highest ranking technical proposal within the specified budget

10
Statement Of Work

A statement of work (SOW) is a formal document that captures and defines the work
activities, deliverables, and timeline a vendor will execute against in performance of
specified work for a client.
Detailed requirements and pricing may also be included in the Statement Of Work,
along with standard regulatory and governance terms and conditions
A well written SOW shall
Specify requirements clearly to permit the seller to estimate the probable
cost
Allows seller to determine the levels of expertise, manpower, and other
resources needed to accomplish the work
States specific duties of the seller in such a way that the seller knows what is
required and completes all tasks to the satisfaction of the contract
Sites applicable specifications and standards

11
Statement Of Work

Areas typically addressed by a SOW are


Purpose – Why are we doing the project?
Scope of Work – Roughly describes the work to be done in detail
Where the work will be performed
Period of performance – specifies the allowable time
Deliverables Schedule – specifies when specific deliverables are due
Applicable Standards – Any industry specific standard that needs to be
adhered to
Acceptance criteria – How the buyer would determine whether the
product/service is acceptable
Special requirements – any specialized workforce requirement such as
certified professionals, travel requirements etc.

SOWs are carried forward and may be further negotiated with the seller into the final
contract

12
Comparison of Procurement Documentation

13
Conduct Procurements

This Process focuses on evaluating Proposals Buyer


and selecting a Seller
Bid Documents

Procurement Documentation, Procurement


Management Plan, Seller Proposals (during
iteration of the Process) Seller
Proposals

Bidder Conferences, Proposal


Evaluation, Independent Estimates, Mutual
Advertising, Negotiation
Contract

Selected Sellers, Agreements, Resource


Calendars

Project Management Institute, A Guide to the Project Management


14 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 460
Proposals

Proposals are Seller-prepared documents:


Portray the Seller’s ability to deliver the requested Services
It is a formal and legal offer in response to the Buyer’s request
Can be supplemented by additional material or oral presentations

15
Typical Source Selection Process

Screening off of ‘ unqualified’ Vendors


Consideration of Technical / Commercial Proposals of screened Vendors
Explicit consideration of any risks associated
Application of Weighted Ranking Systems to shortlist and prioritize Vendors
Comparison with ‘Independent Estimates’
Conduct Negotiations and Final Source Selection
Negotiations can cover multiple aspects and are subject to elaborate processes
Sellers can be ‘Multiple’ in some cases – or a ‘Sole Seller’ may exist in the market

16
Contracts

The Award Cycle results in a signed Agreement


Legal Requirements :
An offer
Acceptance
Consideration
Legal capacity
Legal purpose

17
Typical Contract contents

SOW
Schedule/ period of performance
Roles and responsibilities
Pricing and Payment criteria
Acceptance criteria
Warranty and product support clauses
Limitation of liability
Fees, retainage, penalty, incentive related clauses
Change request handling procedures
Payment procedures
Termination and dispute handling mechanism

18
Control Procurements

This process focuses on managing Procurement relationships, monitoring


Contract Performance and making changes as needed and closing cotracts

Project Management Plan, Agreements,


Procurement Documentation, Approved
Change Requests

Claims Administration , Performance


Reviews, Earned Value Analysis,
Inspection and Audits

Closed Procurements, Procurement


Documentation updates, Change
Requests, Updates to PM Plan, Project
Documents and Organizational Process
Asset

Project Management Institute, A Guide to the Project Management


19 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 460
Control Procurements

Matching of Seller’s Performance with Contractual obligations-


considering the Performance Reports from Vendors
Management of multiple Vendors and Communications updation with Key
Stakeholders
Making of necessary payments and maintaining necessary documentation
against invoices
Management of Change Requests through Contract Change Control Systems
and conducting Procurement Performance Reviews
Claims Administration and updation of Organizational Process Assets
Control Procurement can be treated as a separate administrative function
separate from project organization for large scale projects

Managing the relationship between the Buyer and Seller

20
Contract Closure

Involves notification that all the work and deliverables were acceptable
Includes updating of records to reflect final results and archiving results for
future use
How effective the procurement procedures were?’
Can be useful information for the current or succeeding projects
In some cases, the early termination of the Contract is invoked, which can
call for Negotiated Settlements
Organizational Process Assets are updated – including updates to
Procurement File, Deliverables Acceptance and Lessons Learned Seller
Performance Reports etc.

21
Emerging Trends

Some emerging trends in project communications include:


Advance Tools – Use of Online tools provide buyer/seller a single point for all
information, submission of bids etc.
Changing contracting processes – In mega projects in the past several years the
use of internationally recognized standard contract forms is increasing in order to
reduce problems and claims during execution
Logistics and supply chain management – Especially in large engineering projects
items with long lead times (1-2 years) need to be procured in advance even before
detailed design has happened.
Trial engagements - Some projects will engage several candidate sellers for initial
deliverables and work products before making the full commitment to a larger portion
of the project scope

22
Agile Considerations

Larger projects may use an adaptive approach for some deliverables and a more
stable approach for other parts. In such cases a MSA may be used for the overall
engagement , with Adaptive work placed as an appendix
In agile environments, specific sellers may be used to extend the team.

23
What we learnt here?

Overview of Procurement Process


Multiple types of Contracts
Vendor selection process
Contract administration
Role of Procurement audits

24
13. Stakeholder
Management

www.qaiglobal.com

1
What goes where?

Identify Stakeholder: The process of identifying stakeholders and analysing such


information as their interest, influence and need in the project

Plan Stakeholder Engagement: Developing appropriate management strategies to


effectively engage stakeholders throughout the project

Manage Stakeholder Engagement: Proactively communicating with stakeholders to


meet their needs and foster appropriate stakeholder engagement

Monitor Stakeholder Engagement: The process of monitoring stakeholder


engagement and adjusting strategies to increase effectiveness of Stakeholder
Engagement

Project Management Institute, A Guide to the Project Management


2 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 503
Plan Stakeholder Engagement

Developing approaches to effectively engage stakeholders


throughout the project.

PM Plan, Stakeholder Register,


Agreements

Prioritization/Ranking, Data Representation (Mind Mapping,


Stakeholder Engagement Assessment Matrix), Meetings

Stakeholder Engagement Plan

Project Management Institute, A Guide to the Project Management


3 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 504
Defining Stakeholder Engagement

Current engagement levels of stakeholders are compared to the Desired engagement


levels. This can be represented in a ‘Stakeholder Engagement Assessment Matrix’
Any gaps between the current and desired engagement levels are identified and
required actions/communications to close these gaps are defined.

Develop strategies to for gaining support or reducing obstacles

4
Stakeholder Engagement Plan

The Stakeholder Engagement Plan may include the following:

o Existing and desired levels of engagement in the project


o Scope and impact of change to stakeholders
o Details of how stakeholders are to be involved in the project
o What key messages to be passed on to the stakeholders
o Who from within the project would interface with the stakeholder
o What information to be distributed to stakeholders and why

5
Sample Stakeholder Register

Standardization of specification for Telecom Tower Roll out


Assessment of
Stakeholder Name Major Need Strategy
Influence

Share:
Top end specification
1. Reliability analysis report
Customer required High
2. Cost-benefit analysis (marginal analysis)
Cost is secondary
Involve in decision making

Low CAPEX and OPEX Clearly communicate Cost-benefit analysis


Top Management Very High
but still meeting SLAs and reliability analysis

Top end specs to


Plan User trials
O &M reduce down time. Medium
Involve in decision making
Cost secondary

Low - have less say


Circle Project Team Ease of rollout Convince by using Prototype deployment
in decision making

Off the shelf availability Low - company Float questionnaires on specs availability
Equipment vendors No need for being the biggest Involve in field trials
customization vendor Plan Lead times in procurement

6
Manage Stakeholder Engagement

Stakeholder Engagement Plan, Communication


Management Plan ,Stakeholder Register,
Change Log, Issue Log

Communication skills, Interpersonal and


Team Skills (Conflict Management,
Cultural Awareness, Negotiation,
Observation/Conversation, Ground
Rules
Issue Log, Change Requests, updates to
PM Plan

Project Management Institute, A Guide to the Project Management


7 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 504
Manage Stakeholder Engagement

This process focuses on the process of communicating with the Stakeholders


and addressing issues as they occur

Addressing concerns which have not become issues- so that early resolution
is achieved

It is imperative that all the Stakeholders understand the Risks and Benefits of
projects for their effective involvement

8
Monitor Stakeholder Engagement

Monitoring overall project stakeholder engagement and adjusting


strategies and plans as appropriate

Stakeholder Engagement Plan,


Stakeholder Register, Issue Log

Data Analysis (Alternative Analysis, Root Cause Analysis),


Stakeholder Engagement Assessment Matrix, Communication skills,
Interpersonal skills, Expert Judgment, Meetings

Change Requests, Updates to PM Plan, Project Documents

Project Management Institute, A Guide to the Project Management


9 Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project
Management Institute Inc., 2017, Page 504
Monitor Stakeholder Engagement

Monitor Stakeholder engagement involves:

o Checking stakeholder engagement was done in accordance with the Stakeholder


Engagement plan
o Measure the effectiveness of Stakeholder Engagement in overall
o Reassess the stakeholder register for any new stakeholders, new needs from the
identified stakeholders

Based on above analysis, this process may lead to

o Updating the stakeholder register with better strategies to address stakeholder


needs
o Revising the Stakeholder Engagement plan with more effective ways to engage
with the stakeholders

10
Emerging Trends

Trends and emerging practices in Stakeholder engagement include:


Identifying all stakeholders, not just project team and customer
Participation of project team in stakeholder engagement activities
Reviewing stakeholder community regularly
Involving most affected stakeholders of the project through the concept of co-creation

Agile considerations…

Adaptive teams engage with stakeholders directly rather than going through layers of
management
Agile methods promote aggressive transparency. Inviting any stakeholders to project
meetings and reviews and posting project artifacts in public spaces is to surface as
quickly as possible any misalignment

11
What we learnt here?

Stakeholder Identification Process

Defining Stakeholder Engagement Strategy

Preparing Stakeholder Engagement Assessment Matrix

Manage and monitor stakeholder engagement

12
14. Professional
Responsibility

www.qaiglobal.com

1
PMI ® code of Ethics and Professional Conduct

Collective Conduct of Individual Practitioners adhering to this code is


expected to foster credibility and reputation of the PM Profession

A Project Manager has professional responsibilities towards the

Profession

Project

Stakeholders

And Society at large

2 PMI is a registered mark of the Project Management Institute, Inc.


Code of Ethics and Professional Conduct

A new ‘Code of Ethics and Professional Conduct’ has been brought out by the PMI® –
as applicable to:
All PMI® Members
Non- PMI® Members – but hold a PMI® Certification/ commencing to apply
for a PMI® Certification/ Serving PMI® in a volunteer capacity

Values that support this code include: Responsibility, Respect, Fairness and Honesty-
as foundation.

Under each of the values – Aspirational and Mandatory standards have been
prescribed.

3 PMI is a registered mark of the Project Management Institute, Inc.


Theme – Responsibility- Aspirational Standards

Responsibility consisting in owning the decisions taken ( or failed to be taken)


The Aspirational standards include:
PM takes responsibilities for the actions of the team
The PM undertakes to complete the commitments undertaken to
completion
Protecting Confidential information entrusted
A mutual upholding of the code is implied

4
Theme – Responsibility- Mandatory Standards

Inform ourselves and uphold the Code

The PM undertakes to bring to the notice of any violations in discharge of PM


responsibilities

Any violations are substantiated by facts and brought to the notice of the appropriate
authorities

Not to abuse the rights of others – including the IP rights

5 PMI is a registered mark of the Project Management Institute, Inc.


Theme – Respect

Respect includes the regard for self, public and the resources entrusted to us

It also includes respecting the cultural diversity – facilitating trust, cooperation and
Performance excellence

Aspirational Standards in this theme include:

Seeking to understand the viewpoints of others


Conducting self in a professional manner

Mandatory Standards include:


Carrying out Negotiations in good faith
during Procurement
Respecting the property rights of others

6
Theme – Fairness

Fairness relates to the duty to make decisions impartially and


objectively
Aspirational Standards in this theme include:

The PM must exercise fairness in dealing with Team


Members
and Stakeholders- as appropriate
Provision of equal access to information to all qualified
Stakeholders is implied

Mandatory Standards include:


Conflict of Interest: All conflict of interest situations are
disclosed to appropriate authorities
In case of real or potential conflict of interest, The PM
notifies the appropriate authorities and proceed as per
best judgment

7 PMI is a registered mark of the Project Management Institute, Inc.


Theme – Honesty

Honesty – refers to understanding of the truth and act in a truthful manner in


communications and conduct

It relates to the duties of the PM in correct understanding of the factual situations and
taking decisions thereof

Mandatory Standards include:


Develop credibility by not making misleading or false statements
Not engaging in a dishonest behaviour with an intention of personal gain or at the
expense of another

8
Other Themes in Professional Responsibilities

Ensure individual integrity

Contribute to the PM knowledge base

Enhance individual competence

Balance stakeholders’ interests

Interact with the team and stakeholders in a professional and cooperative manner

9
Ensure Individual Integrity….

Ensure Legal Compliance with all business matters related to the geography of the
project

Protect:
Company data and processes
Classified information

Refrain from offering and accepting bribes or inappropriate gifts / payments for
personal gains

10
Knowledge Management

Keep abreast of best practices and disseminate them

Seek new information that would enhance your Organization’s business practices and
professional efficiencies

Contribute back to the PM knowledge base

11
Balance Project and Stakeholders Interests

Provide truthful information on scope, costs, status and expected results of the
project

Resolve Conflicts within the project in favour of the Customer - if there is a choice

Ensure personal rapport with the stakeholders does not bias professional judgments

Escalate project problems to higher levels when necessary in a timely and effective
manner

12
Professional Responsibilities towards the Team

Keep the Team Members informed of the project progress and future course of
actions

Provide training where necessary

Give Team Members honest, timely and transparent feedbacks and be interested in
their welfare

Manage Conflicts with fairness

No bias on the basis of Nationality, Gender, Religion

13
What we learnt here?

Key themes of PMI® Code of Ethics and Professional Conduct

Description of Four fundamental values supporting the Code of Ethics and Professional
Standards

Aspirational and Mandatory Standards governing these values

14 PMI is a registered mark of the Project Management Institute, Inc.

You might also like