Professional Documents
Culture Documents
Simulation of An Integrated Planning of Power and Gas Distribution Grids Considering Power-To-gas and Gas-To-power Units
Simulation of An Integrated Planning of Power and Gas Distribution Grids Considering Power-To-gas and Gas-To-power Units
Abstract: This study presents the simulation of a concept for the integrated planning of power and gas distribution grids.
For this purpose, the influence of grid coupling units, as power-to-gas and gas-to-power units, is examined. Afterwards,
the developed concept is applied to exemplary power and gas distribution grids and the results are compared with
conventional power grid expansion.
1 Introduction carry out these three steps of planning in a joint manner for power
and gas grids is shown in Fig. 1 and explained in detail afterwards.
The energy system is undergoing an unprecedented transformation The concept aims to obtain a cost-optimal solution for a possible
because of the required defossilisation of the energy mix. The future energy system. In addition, it attempts to describe a possible
integration of renewable energy sources has a particular impact on interaction between grid operators and operators of CU (unit
the power grid infrastructures designed to transport energy from operators). To this end, in the first step, data with a significant
central, conventional power plants to end customers. Furthermore, influence on the integrated planning process are identified. To
the integration of synthetic gaseous fuels into the gas grid leads to determine the schedules of the CU, time series for energy prices,
a need for adaptation of the gas infrastructure, e.g. to enable a temperature and gas pipeline flows are used. These time series are
higher hydrogen tolerance. The joint planning of the power and deployed as input factors for the solution of a mixed-integer linear
gas grid – in combination with coupling units (CUs) like problem (MILP), in which the revenue from the operation of the
power-to-gas (PtG) and gas-to-power (GtP) – expands the solution CU (influenced by the energy prices) is maximised. The objective
space, whereby an overall more cost-efficient solution can be function of the optimisation problem is shown in the following
found to overcome these challenges. This is gaining additional equation:
relevance nowadays due to the long investment cycle of many
components of the energy system (e.g. about 40 years for power
lines). The first concepts for integrated planning of power and gas min : ci(s,e) (t ) · wi(s,e) (t ) ·t (1)
distribution grids are described in recent publications [1–3]. As the t[T (s,e)[E i[I
main contribution of these publications, the integrated planning
pursues the goal of a more holistic view of the future energy The function consists of the energy flow wi(s, e) of the CU with the
system in which a far larger number of actors must interact with respective costs ci(s, e) resulting from the energy price times series
each other to come as close as possible to the overall systemic for power and gas. These, in turn, are multiplied with the
optimum. Thus, based on the assumption that the energy system time-increment of the simulation (t=15 min). The equation is
has to be considered as a whole, new methods of integrated energy summed over the time horizon T, the number E of CU and the
system planning are needed. This paper presents the simulation of cost time-series I. The compliance with the constraints of the
a concept for integrated power and gas distribution grid planning, hydrogen feed-in limit and the volatile heat demand is ensured by
with the added value of identifying the most economic systemic the use of gas pipe flow and temperature time series. For the
result, as shown in Section 4.4. hydrogen feed-in, simulations were performed for different limits
(10, 20, 30 and 100 vol.%). Since current developments indicate
that a higher feed-in limit (current regulation: if no critical
2 Integrated planning concept consumers are connected to the grid, up to 10 vol.% can be fed in
[5]) can be assumed for a future scenario, in the following only
Grid expansion planning is based on the synthesis, analysis and the results for 30 vol.% will be presented. Further, it is assumed
optimisation of development strategies or expansion variants [4]. that above a limit temperature of 16°C the heat demand can be
To carry out these processes, grid models are required, on the covered by more cost-efficient units or processes, and therefore no
basis of which new development scenarios can be defined more heat can be supplied by combined heat and power (CHP)
(synthesis). In the following analysis, possible solutions for units. The MILP and the associated energy system are modelled
guaranteeing the supply task under the developed conditions and solved with the open energy modelling framework (OEMOF).
(scenarios) are investigated. Finally, optimisation is conducted, The energy system consists of CU interconnecting both energy
whereby the obtained solution is further improved. The method to grids. For the scheduling of these units, in the first step, the power
CIRED, Open Access Proc. J., 2020, Vol. 2020, Iss. 1, pp. 70–73
70 This is an open access article published by the IET under the Creative Commons
Attribution License (http://creativecommons.org/licenses/by/3.0/)
objective function (1), a model was then created in which the unit
operator tries to maximise his profit. This means, for example, that
the operator of a PtG unit always operates his unit when the price
for gas is greater than or equal to the price for power multiplied
by the efficiency of the unit. The operator of a CHP unit, on the
other hand, operates his unit whenever the revenues from the
outputs power and heat multiplied by the respective efficiencies
exceed the costs for the gas input.
CIRED, Open Access Proc. J., 2020, Vol. 2020, Iss. 1, pp. 70–73
This is an open access article published by the IET under the Creative Commons 71
Attribution License (http://creativecommons.org/licenses/by/3.0/)
Fig. 5 Power line loading over 1 year
steps over the year. It was found that the problems occur locally
Fig. 4 SimBench power grid model (only a few lines are affected). These are lines, which are located
in strands 1 and 2. In strand 1, limit value violations occur
grid can be divided into strands with an open ring topology. For the frequently, whereas, in strand 2, these occur only occasionally
purpose of visibility, the strands are numbered in the order shown in over the year.
Fig. 4. Due to the open ring topology, and considering the N − 1
criterion, a maximum load of 60% of the maximum thermal 4.2 Technical results – conventional grid expansion
current is assumed for the power lines [8]. In addition, 105.5% of
the nominal voltage is assumed as the upper voltage limit and To prevent limit value violations in the power grid, the power lines in
96.5% as the lower voltage limit. the affected grid sections can be conventionally reinforced. For this
purpose, a standard 240 mm2 line (NA2XS2Y 1 × 240) replaces the
3.4 Synthesis: SimBench power grid scenario 2034 overloaded lines. Fig. 6 shows the results for the line loading in
percent after the grid reinforcement. It can be seen that no more
A first preliminary power grid analysis showed that problems as limit violations occur for the described scenario. The grid
thermal power line overloads or voltage limit occur in particular at expansion activities in strands 1 and 2 and the assumed costs are
strand 1 and strand 2. At strand 1 these problems are caused by an summarised in Table 1.
increased feed-in of wind energy. On strand 2, on the other hand,
the voltage dip (node with minimum voltage in the grid) is found
at node 96, in 72% of all simulated time steps over the year. In the 4.3 Technical results – integrated planning
following, the scenario developed within the project SimBench [7]
If instead of grid expansion the presented concept is applied to the
for the year 2034 is applied to both strands. The scenario for
energy grids with the respective scenario, all limit violations can
generation capacity (2034) is applied to strand 1 and the load
also be successfully eliminated by the use of the CU. For this
scenario to strand 5. The scenario is applied to these two strands,
purpose, a 1 MW electrical power PtG unit was placed on strand 1
each equipped with one CU (PtG respectively CHP), to enable the
(node 14) and a 2.1 MW electrical power CHP unit (with an
demonstration of the advantages of the proposed method in a lucid
additional 2.4 MW heat output) on strand 2 (node 96). The results
manner.
for the power line loading are shown in Fig. 7.
4 Simulation results
The results of the simulation entail the power grid state for the Fig. 6 Power line loading after grid expansion
scenario and the technical and financial results of the conventional
grid expansion as well as of the case with grid serving operation
of the CU.
Table 1 Power line reinforcement at strands 1 and 2
4.1 Analysis of the power grid Line Strand Line length, km CAPEX, €/km OPEX
CIRED, Open Access Proc. J., 2020, Vol. 2020, Iss. 1, pp. 70–73
72 This is an open access article published by the IET under the Creative Commons
Attribution License (http://creativecommons.org/licenses/by/3.0/)
can be found. However, this requires close cooperation between
the two parties responsible for infrastructure planning in the two
sectors and the operators of CU. The multi-use employment of CU
increases the economic viability. In general, from the point of
view of the grid operator, grid expansion is in the simulated case
and under the considered assumptions the most favourable option.
However, CUs are important and necessary actors, not only to
maintain the stability of the power grid, but also, for example, for
the defossilisation of other demand sectors. The regulatory
framework must be designed in a way that allows investments in
and the operation of CU with the desired effect.
Table 2 Economic results (NPV for the year 2020) The authors gratefully acknowledge funding by the German Federal
Ministry of Education and Research (BMBF) within the Kopernikus
Strand Grid expansion, € Grid serving CU, € Multi-use CU, € project ENSURE ‘New ENergy grid StructURes for the German
Energiewende’.
1 −251,473.03 −436.817,92 −393.080,40
2 −27,122.21 −426.165,85 191.492,10
7 References
(integrated planning case). The values correspond to the NPV for the 1 Yang, F., Yuan, X., Bai, H., et al.: ‘Collaborative planning of integrated natural gas
year 2020. Overall, it can be noticed that for both strand 1 (PtG) and and power supply system considering P2G technique’, 2018
strand 2 (CHP) the exclusive grid serving usage of the CU is not 2 Sun, K., Yin, W., Li, C.: ‘Optimal planning model for integrated district energy
systems considering electricity and gas distribution networks’, IEEE PES Innov.
profitable compared to grid expansion. This result is coherent with Smart Grid Technol. Asia, Chengdu, China, May 2019, pp. 1733–1738
other available literature (e.g. [9]). For the multi-use case, the 3 Ghasemi, H., Aghaei, J., Gharehpetian, G.B., et al.: ‘Effect of smart multiple hub
utilisation of the CU is profitable for strand 2 (CHP) due to the planning on distribution networks integrated expansion’, 2019 International
high revenues of the UO and relatively low negative revenues of Conference on Smart Energy Systems and Technologies (SEST), Porto,
Portugal, September 2019, pp. 1–6
the GO. However, strand 1 (PtG) is not profitable and, compared 4 Sillaber, A.: ‘Leitfaden zur verteilnetzplanung und systemgestaltung’, 2016,
to grid expansion, more expensive. This is due to the high pp. 133–142
CAPEX and the low revenues of the PtG unit. For the economic 5 DVGW Deutscher Verein des Gas- und Wasserfaches e.V.: ‘Arbeitsblatt DVGW
analysis of the PtG unit, a CAPEX of 842.80 €/kW [10] has been G262 (A)’, 2011
6 Ruf, J., Zimmerlin, M., Sauter, P.S., et al.: ‘Simulation framework for multi-carrier
used. For the used set of assumptions, CAPEX would need to energy systems with power-to-gas and combined heat and power’, 2018
drop below 440 €/kW to make a business case. However, the 7 Spalthoff, C., Sarajlic, D., Kittl, C., et al.: ‘Simbench: open source time series of
literature clearly indicates that the impact on the PtG potential of power load, storage and generation for the simulation of electrical distribution
system drivers (ambitious GHG reduction targets, high PV and grids’. Int. ETG-Congress, Esslingen, Germany, 2019, pp. 1–6
8 Gwisdorf, B., Stepanescu, S., Rehtanz, C.: ‘Effects of demand side management on
wind capacities, high CO2 prices, regulatory framework, the planning and operation of distribution grids’, 2010
unavailability of CCS and biomass potential) is significantly 9 Robinius, M., Raje, T., Nykamp, S., et al.: ‘Power-to-gas: electrolyzers as an
higher than the influence of technology drivers (efficiency, alternative to network expansion – an example from a distribution system
CAPEX, subsidies) [11, 12]. operator’, Appl. Energy, 2018, 210, pp. 182–197
10 Gorre, J., Ortloff, F., van Leeuwen, C.: ‘Production costs for synthetic methane in
2030 and 2050 of an optimized power-to-gas plant with intermediate hydrogen
storage’, Appl. Energy, 2019, 253, article 113594
5 Conclusions 11 Blanco, H., Nijs, W., Ruf, J., et al.: ‘Potential for hydrogen and power-to-liquid in a
low-carbon EU energy system using cost optimization’, Appl. Energy, 2018, 232,
pp. 617–639
The simulation of a concept for an integrated power and gas grid 12 Liu, W., Wen, F., Xue, Y.: ‘Power-to-gas technology in energy systems: current
planning is presented in this paper. The application of the concept status and prospects of potential operation strategies’, J. Mod. Power Syst. Clean
to exemplary data shows that a better overall systemic optimum Energy, 2017, 5, (3), pp. 439–450
CIRED, Open Access Proc. J., 2020, Vol. 2020, Iss. 1, pp. 70–73
This is an open access article published by the IET under the Creative Commons 73
Attribution License (http://creativecommons.org/licenses/by/3.0/)