You are on page 1of 1

FORM ESTIMASI Model Hoist 3S(H)-ST R0

ESTIMASI FORM No. 22E066 KH-HO OHC SG W / BEAM


Estimasi Date 22 Juni 2022 Customer Capacity / Load 3 Ton
SALES Khairul PT. Tigaraksa Span 10 Meter
ERF No. Project Long Travel 18 Meter
EFR Date. 22 Juni 2022 Kalimantan Timur Lifting 6 Meter

TRAVERSING / CROSS TRAVEL


1 Unit Standard Box Single With Beam
Material Specification
1 x 6 Meter Girder : WF 400 Rp 23.000.000
1 Base Plate : Plate 14 mm
Finishing : Painting + Wire Brush
1 x 10 Meter Cross Travel Supply : Festoon System + Flat Cable
3 Unit C-Track : KY-BC3040
5 Unit Track Support Bracket : KY-BC3100
1 Unit Track Coupler : KY-BC3300
8 Unit Cable Trolley : KY-BC3525 Rp 4.700.000
1 Unit End Cable Clip : KY-BC3200
2 Unit End Cap : KY-BC3201
1 Unit Towing Trolley : KY-BC3625
1 x 15,00 Meter Flat Cable : 4 x 4 mm
1 x 10 Meter Mobile Control : Festoon System + Flat Cable
3 Unit C-Track : KY-BC3040
5 Unit Track Support Bracket : KY-BC3100
1 Unit Track Coupler : KY-BC3300
8 Unit Cable Trolley : KY-BC3525 Rp 6.000.000
1 Unit End Cable Clip : KY-BC3200
2 Unit End Cap : KY-BC3201
1 Unit Connect Box : KY-BC3412A
1 x 15,00 Meter Flat Cable : 12 X 1,5 mm
1 Unit Crane Panel Cross : Without Inverter Rp 2.500.000
1 Unit Push Button : PB6SS Rp 3.100.000
1 Set Limit Switch Rp 1.000.000
1 Set Lamp + Sirine Rp 1.200.000

Sub Total - A Rp 41.500.000

TRAVELING / LONG TRAVEL


2 x 18 Meter Gantry Legs
Runway Rail With Sq. Bar Size : 38 X 38 38 mm Rp 9.763.200
Plat Runway Rail : 200 X 18.000 X 2 Plat 6 mm Rp 10.500.000
Long Travel Power Conductor Type: 3P75 Troreel System Rp 9.360.000

Sub Total - B Rp 29.623.200

GANTRY LEGS
4 x 6 Meter Gantry Legs
Material Specification
Main Legs : WF 200
Rp 26.500.000
Second Legs : Double UNP 150
Support Legs & Base Plate : Plate 14 mm
Finishing : Painting + Wire Brush

Sub Total - C Rp 26.500.000

ERECTION & DELIVERY


1 Lot Biaya Erection Rp 5.100.000
1 Lot Sewa Forklip Rp 3.500.000
1 Lot Sewa Scaffolding Rp 1.600.000
1 Lot Biaya Pengiriman Rp 3.500.000
Sub Total - D Rp 13.700.000

NOTE : Total A+B+C + D Rp 111.323.200


Harga belum termasuk Wheel & Motor Unit untuk End Safety Factor 15% Rp 16.698.480
Carriage Sub Total 1 Rp 128.021.680

END CARRIAGE FOR LONG TRAVEL


1 Set Frame For End Carriage type : E2-3000 Rp 5.600.000
4 Pcs Wheel Diameter : 150 mm
2 Unit Motor Wheel : 0,75 kw Rp 31.830.000
Output Speed : 21 m/min
1 Unit Crane Panel Long : Without Inverter Rp 2.500.000
Sub Total 2 Rp 39.930.000

LOAD TEST & CERTIFICATION


0 Lot Test Beban & Sertifikat Depnaker (Exclude Load For Testing)
Sub Total 3 Rp 8.000.000
Rp 8.000.000

Grand Total ( 1 + 2 + 3 ) Rp 175.951.680


Load Test dan sertifikat di sarakan dari user
Total Rp 176.000.000

NOTE : Inverter Hoist : 2,2 Kw Rp 11.725.000


NOTE : Inverter Trolley : 0,75 Kw Rp 6.820.000
NOTE : Inverter Saddle : 1,5 Kw Rp 7.270.000
NOTE : Estimasi untuk Biaya Erection berlaku pada hari biasa (harga tiket normal) tidak berlaku pada hari besar (harga tiket naik)