Professional Documents
Culture Documents
SEMESTER II 2020/2021
GROUP K8
SUPERVISORS:
GROUP MEMBERS:
DECLARATION
We hereby declare that the work in this thesis is our own except for quotations and
summaries which have been duly acknowledged.
kash
20 MAY 2022 KASHVINWARMA A/L BASKARAN
A169128
zaf
NUR ZAFIRAH ALIAH BINTI
BAHARUDDIN
A169320
ana
HUSNA BINTI AHMAD RADZUAN
A167664
mira
NOR EZZATI AMIRA BINTI
MUSTAPA PADZIR
A169229
naim
MUHAMMAD NA'IM NAJMI BIN
MOHAMAD SALJI
A168963
iii
ACKNOWLEDGEMENT
Praise to Allah, the most gracious the most merciful. Thank you for giving us strength
and spirit to us to complete this project. We will never complete this challenging Final
Year Design Project if we did not receive some help from these people.
First and foremost, we would like to express our highest appreciation to our
beloved supervisor, Assoc. Prof Dr Masli Irwan Rosli, Dr. Ebrahim Mahmoudi and our
industrial mentor, Mr. Yeow Eu Lun for their concern and guidance in this project.
Special thanks to our lecturers, Prof Dr Ir Siti Kartom Kamarudin, Dr Ir Syuhaida
Harun, Dr Rosiah Rohani, Prof Ir Dr Abdul Wahab, Dr Darman Nordin, Prof Ir Dr Sobri
Tarrif, Dr Teow Yeit Haan, Dr Ir Nor Yuliana Yuhana and Assoc Prof Dr Ir Dr Hassimi
Abu Hassan for guiding and giving us knowledge complete this project. Without the
encouragement and patience, we believe that we would hardly finish our tasks before
the due date. Also, we would like to express our highest gratitude to our parents for
giving us all the moral support when we really need one. Thank you very much and
may god bless your help,
Lastly, we would like to thank all our course mates, seniors, and those who are
involved in helping our in this project directly and indirectly. Without all of the help it
is impossible for us to complete this project. Your kindness and cooperation is highly
appreciated. Just words alone cannot illustrate how much we thank you all.
iv
EXECUTIVE SUMMARY
discounted cash flow rate of return, DCFRR with the 25 years of design life. The NPV
value is positive, RM 75.47 million value with 31% DCFRR, the project can be
considered as profitable and favorable.
For plant safety, all the potential hazards of all chemicals involving in the
production are identified by referring to the material safety data sheet (MSDS). All the
chemical hazards, toxic and flammable materials in this production are identified.
Hazard identification, risk assessment and risk control (HIRARC) study is conducted
throughout the plant to evaluate all possible hazards and their related risks. As such, the
plant has undergone Hazard and Operability Study (HAZOP) to identify the possible
hazards and the actions taken at main units of operation The legal requirement followed
according to Environmental Quality Act 1974, Occupational Safety and Health Act
1994 and Factory and Machinery 1967.
A plant location is often a result of compromise among conflicting social,
economic, and geographical conditions. A proper decision has been made wisely for
future planning because it will have a long-term positive or negative effect on the
production process. Based on our research there are several proposals proposed for our
site location, which are Tanjung Langsat Industrial Complex, 81700 Pasir Gudang,
Johor, Pengerang Industrial Park (PIP), 81600, Pengerang, Johor, and Bukit Rambai
Industrial Park, 75250 Melaka. This site was the shortlist of our proposed site and
Tanjung Langsat Industrial Complex got the highest marks with value 253. This is
because all the factories we are looking for are suitable for our plant production.
Detailed designs for each unit operations are done, and design specifications are
obtained. This design step is important in determining the size of the equipment which
ultimately decides the location and arrangement of unit operations in plant layout. There
are total of 2 reactors, 6 separation units such as distillation column, gas absorption, stripper
and filter and utilities such as cooler, heat exchanger, condenser and reboiler being
designed.
Mechanical designs for pressure vessels are also done. The vessel's wall thickness
is estimated and ensured to be safe by comparing the maximum permissible working
pressure (MAWP) with the operating pressure, as well as performing a combined loading
analysis and an elastic stability test. Vessel supports and flanged couplings are also
constructed with this in mind. AutoCAD is also used to create mechanical drawings for the
planned pressure vessels. As a design foundation, several rules and standards, such as those
of the American Society of Mechanical Engineering (ASME) and the Tubular Exchanger
Manufacturers Association (TEMA), are employed. To ensure safe operations and a safe
working environment, mechanical design is critical in determining the maximum allowable
stress for each unit operation or pressure vessel.
vi
TABLE OF CONTENTS
Page
DECLARATION ii
ACKNOWLEDGEMENT iii
EXECUTIVE SUMMARY iv
TABLE OF CONTENTS vi
CHAPTER I INTRODUCTION 1
1.1 Introduction 1
1.2 Source of Raw Material 1
1.3 Product Usage 2
1.4 Raw Material, Product and By Product 2
1.4.1 Raw Material 2
1.4.2 By Product 4
REFERENCE 305
Appendix E Piping And Intrumentation Diagram Before And After Hazop 333
LIST OF TABLES
Table 5.15 The sizing for the piping system of liquid flow 86
Table 5.16 The sizing for the piping system of vapor flow 88
Table 6.10 The summary of design dimension for all wastewater treatment
units 105
Table 7.7 Operator per shift for each equipment type 114
xvii
Table 9.1 Water bill for industrial and commercial in Johor 177
Table 9.2 Water bill for industrial and commercial in Melaka 181
Table 9.3 Electric tariff for the industrial and commercial 182
Table 10.3 Result for design of packed bed reactor (R-101) 191
Table 10.4 Result for design of packed bed reactor (R-102) 192
Table 10.8 Temperature and pressure of inlet and outlet streams 198
Table 10.9 Molar flowrate and composition at Distillation Column D-101 198
Table 10.10 Data for heat capacity in J/kmol K of paraffin and triglycerides 199
Table 10.12 Heat vaporization for IPA, DIPE and water 200
Table 10.25 Internal Pressure and MAWPvessel for Each Part 222
Table 10.28 Size of flanges used for fitting on each pipe on D-104 230
Table 11.3 Internal pressure and MAWPvessel for each part of the reactor R-
101 263
Table 11.5 Size of flanges used for fitting on each pipe on R-101 267
Table 11.34 Standard Dimensions for Saddle Supports with Vessel Diameter
0.3m 301
Table 11.35 Size of flanges used for fitting on each pipe on C-101 302
LIST OF FIGURES
Figure 2.1 Global Demand and Supply of Aviation Fuel from 2019-
2030 11
Figure 11.2 Closure of the type (b-1) for jacket vessel 264
CHAPTER I
INTRODUCTION
1.1 INTRODUCTION
C10H22 is the chemical formula for decane, an alkane hydrocarbon. Although decane
has 75 structural isomers, it is most associated with the normal-decane ("n-decane"),
which has the formula CH3(CH2)8CH3. All isomers, on the other hand, have similar
qualities, and the composition isn't given much thought. These liquid isomers are
combustible. Decane is a component of kerosene and gasoline (petrol). It is a nonpolar
solvent that does not dissolve in water and is easily flammable, just like other alkanes.
Despite being a component of fuels, unlike a few other alkanes, it has minimal use as a
chemical feedstock (Gao & Demain 2001).
The main raw material used in our production plant is triglycerides that contain in waste
cooking oil (WCO). WCO is one of waste oil that have been used mostly is palm
cooking oil. Since Malaysia known as second largest producer of palm oil in world, thus
mostly cooking oil used made up from palm oil. Malaysia has contributed share of
global production in 1999 at 51% however it decreased to 38% in 2011 (MPOB 2017).
We decided to build our plant location at Pasir Gudang, Johor and the area is an
industrial area. Thus, the companies can supply for our raw material is Pacific Edible
Oil Industries Sdn Bhd and SE Resources Sdn Bhd. As stated before palm oil has often
been used in cooking thus we also can collect the used cooking oil at household,
restaurant and industrial palm oil waste nearby our production process.
2
In our production process, the main raw material is Waste Cooking Oil (WCO). This
raw material contains accumulated free fatty acid (FFAs) that can be used to produce
biofuel and biodiesel (De Feo et al. 2020). There are five FFAs composition which is
myristic acid, palmitic acid, steric acid, oleic acid and linoleic acid. The main FFA
chosen in this project is palmitic acid and we used triglycerides as our raw material.
Supplier for this raw material easilyget from household or supplier Pacific Edible Oil
Industries Sdn Bhd The table below describethe properties of WCO. Table 1.1 shows
the properties of waste cooking oil.
b. Hydrogen
Hydrogen is a colorless, odorless, melting, and boiling point below 0°C and (SDS,
2019). The hydrogen will use two different process which is hydrotreating,
hydrocracking and deoxygenation process. This gas required will pump into two
different reactors (R-101 & R-102) to break the bond between molecule in triglycerides.
Figure and Table shows the molecule and properties of hydrogen gas.
1.4.2 Product
a. Decane
The main product in this process is synthesis decane. The decane will generated in the
second reactor (R-102) and separated with other component is at distillation column (D-
103). Decane a flammable hydrocarbon that is colorless and petroleum distillates.
Decane is one of material applications in jet engine fuel, fire entertainment, and
chemical industry. The Figure and Table 1.3 shows the molecular structure and
properties of decane.
4
1.4.2 By product
From our production process produce decane as main product, there are several by
product from the production such as organic waste, waste gas, wastewater, synthetic
propane, synthetic petrol, and paraffin. This section will describe all the properties our
by product.
a. Waste gas
This waste gas consists unreacted syngas which is carbon monoxide (CO) and
hydrogen. This waste gas will be removed from the top of the reactor (R-102)
i. Carbon monoxide
Carbon monoxide is a highly poisonous gas that is colorless, odorless and tasteless. It
is highly flammable and easily mixed with air that resulting explosive if mixture. The
Figure and Table 1.4 below shows the structure and properties of carbon monoxide.
5
ii. Hydrogen
The molecular formula of hydrogen gas is H2. Hydrogen gas is a colorless, odorless,
melting, and boilingpoint is below 0°C and (SDS, 2019). The hydrogen required in all
process in two different reactors (R-101 & R-102) to break the bond between molecule
in triglycerides. Figure and Table 1.5 shows the molecules and properties of hydrogen
gas.
Hydrogen also is our plant's raw material, but it becomes waste because it is unreacted gas.
This gas is a colorless, odorless, melting, and boiling point below 0°C and (SDS, 2019).
The hydrogen will be removed at different unit processes which are gas absorption (G-
101) and reactor (R-102). Gas hydrogen separated from gas absorption is pure gas
which will be sold since this gas is valuable and expensive. Meanwhile hydrogen
consists of waste gas will undergo further treatment before release to the environment.
Figure and Table 1.5 shows the molecules and properties of hydrogen gas.
6
b. Wastewater
Molecular formula of water is H2O. Water is a clear, colorless, odorless, and tasteless
liquid that freezes to ice below 0°C and boils above 100°C (National Center for
Biotechnology Information, 2021) . The water produced in this production is in liquid
form. This wastewater produces from synthesis in reactor (R-102) and separated at
distillation column (D-103). The Figure and Table 1.6 shows the structure and
properties of water.
c. Propane
Propane is an odorless and colorless liquid gas. It known as liquefied petroleum gas
(LPG) or propane auto gas. In production, this propane is product from hydroprocessing
in reactor (R-101) and will removed at stripper (G-102) and benzene as solvent to
produce pure propane. The Figure and Table 1.7 shows the structure and properties of
propane.
d. Petrol
Petrol in this production also known as hexane because of the molecular formula is
C6H14. Physical state in normal condition is clear, colorless liquid and mild
hydrocarbon. This liquid is flammable bur very useful material especially for movement
8
e. Paraffin
CHAPTER II
MARKET ANALYSIS
Aviation fuel is a petroleum- or kerosene-based fuel that is used to power airplane. The
quality of aviation gasoline is superior to that of other modes of transport. Kerosene,
kerosene-gasoline, kerosene-biofuel, and other blends are used to make them. The use
of additives such as corrosion inhibitors and other additives in aviation fuels reduces
the risk of icing or explosion owing to high temperatures. To improve fuel efficiency
and decrease operational costs, most military and commercial aircraft use aviation fuel.
North America was the largest shareholder in terms of revenue in 2018, owing
to presence of key players in the developing countries and rise in number of air travelers.
However, Asia-Pacific is expected to grow at a higher CAGR, owing to increase in
investment by the government, introduction of new flight routes, increased fleet sizes,
and high demand for fuel from emerging economies in the region.(Parihar & Prasad
2020)
11
The global aviation fuel market was worth $179.2 billion in 2018 and is expected to be
worth $238.5 billion by 2026. From 2019 to 2026, the market is expected to increase at
a CAGR of 3.5 percent. Major factors contributing to market expansion are projected
to include an increase in demand from the military sector and an increase in air
transportation. New flight routes and airports also increase demand for fuel, propelling
the aviation fuel market forward. However, because of the high amount of carbon
emissions, strict laws regarding the use of fuel types and additives, as well as volatility
in crude oil prices, the aviation fuel market is hampered. Meanwhile, biofuels, which
can greatly cut carbon emissions, and new sustainable aviation fuel (SAF), which is
now being researched and developed, provide attractive potential for the aviation fuel
business to flourish. Alternative environmentally friendly sources for aviation fuel
production will have a significant future impact on the aviation fuel sector.
(AlliedMarketResearch, 2020)
Figure 2.1 Global Demand and Supply of Aviation Fuel from 2019-2030
below shows the global supply and demand of aviation fuel between year 2018 until
forecast period, 2019-2030. This year also witness some loss in the aviation fuel
production as a result of the pandemic, Covid-19.
Figure 2.1 Global Demand and Supply of Aviation Fuel from 2019-2030
12
One of the major factors driving the growth of aviation fuel is due to the
worldwide vaccination program that grant the opportunity for the industry to get back
on track. Travelling and transportation were slowly operating which contribute to the
increment.
In the forecast period, the jet fuel market is predicted to grow at a CAGR of more than
1%, reaching a market value of USD 120 billion (RM 502.62 million) in 2026, up from
USD 114 billion (RM 477.49) in 2019 (Mordor 2021). The COVID-19 pandemic, which
resulted in global lockdowns and drastically curtailed domestic & global travel,
impacted negatively on the aviation sector. In contrast to 2019, passenger traffic fell by
94% from February to April 2020. The COVID-19 pandemic, which forced
international commercial flights to be cancelled save for cargo, had a significant
influence on aviation fuel use. Commercial airlines have roughly 960 new aircraft slated
for delivery by 2020 (Mordor 2021). After the pandemic's recovery, the recent of
decreasing cost of ticket lead to the increasing the number of air passengers. This
situation can strengthen economic conditions and expanding disposable income which
are the major factors for the market (Mordor 2021).
13
Globally, the number of renewable diesel plants is increasing, but only two facilities
generated aviation fuel in 2019 which are Neste, Rotterdam and World Energy,
California (Anon 2021). The Neste Singapore factory is undertaking infrastructural
upgrades to begin producing aviation on a regular basis by 2022. It's worth noting that
only around 15% of the overall capacity of these refineries can be differentiated for
aviation production. Although this proportion may be raised to a maximum of 50%, it
comes at a significant cost and yield loss (Renewable Energy Agency 2021). It is not
economically viable for enterprises to create a higher aviation proportion currently
(UOP, 2020).
The plant is decided to start operating in 2025, since our plant will take four years to
build. The plant's capacity has been calculated based on a global market shortfall in
2025. Aviation fuel demand is predicted to be 1485 kilo tonnes per year, while supply
is expected to be 1072.5 kilo tonnes per year. In 2025, a global deficit of 412.5 kilo
tonnes per year is projected. To meet the global market's shortfall with Compound
Annual Growth Rate (CAGR) 3.5%, we decided to create aviation fuel at a rate of 91.25
kilo tonnes per year. Our factory is up and running for 330 days, with 30 days set aside
for maintenance. The total number of working hours in a year is 7920.
Thus, in year of 2025, the production rate of aviation fuel from waste cooking oil plant
is estimated as below:
=10416.67 kg/hr
15
By 2050, this was expected to have more than doubled in the current state. The use of
sustainable aviation fuels will be critical to achieving early emissions reductions in the
2020s and 2030s, as well as profound reductions by 2050 (IRENA 2021). This is
because of the fuels produce lower emissions than conventional jet fuel. Bio-jet fuels
are the most widely accepted sort of sustainable aviation fuel currently available, with
a variety of other options being considered. Synthetic jet fuel produced by the
conventional pathway may only fit inside existing authorized paths in select situations,
and present production is extremely limited due to its high cost. Thus, in the future
decade, bio-jet fuels show the most potential for cost-effective scale-up and application.
The maximum percentage of bio-jet fraction which can be used might be increased from
15% to around 50%, however this would result in increased production costs based on
increased processing and hydrogen consumption, as well as a 10% loss in liquid product
yield (Pearlson, 2011).
16
CHAPTER III
CONCEPTUAL DESIGN
After considering the economic aspect of the production, a production plant is designed
to produce aviation fuel from waste cooking oil. The production plant is designed level
by level, where in each level, a future potential economic analysis will be conducted to
ensure the production plant is profitable.
Process design level 1 requires determining the process and operating conditions in the
selected product's production. The required information in this process design involves
raw material, chemical reaction, operation conditions, physical and chemical properties
of the materials involved and design constraints.
In our production, the raw material required are triglycerides that can be found in waste
cooking oil and hydrogen gas. The product formed is decane with purity 98% as main
product, propane and petrol as by-product.
17
There are many potential pathways for the production of aviation fuel from biomass
such as hydro-processing of esters and fatty acids (HEFA), gasification-to-Fischer-
Tropsch process, Alcohol-to-jet process (ATJ) and direct sugars to Hydrocarbons
(DSHC). Table 3.1 below shows the comparison of each process
18
Among all the pathways, we choose hydro-processed of esters and fatty acids
(HEFA) process in our production because HEFA process has been considered the only
process commercially available that converts triglycerides into renewable jet fuel (Chen
& Wang 2019). There are three generations of types of raw materials for the production
of biojet fuels in general. The first generation raw materials consist of edible vegetable
oils, the second generation raw materials include inedible oil crops and lignocellulose
biomass, while the third generation raw materials are based on microalgae biomass
(Goh et al. 2020a). Today most first generation biojet fuels are commercially available
but the main disadvantage of first-generation biofuels is based on the food-versus-fuel
debate, which according to which the rise in food prices is due to an increase in energy
crops versus food crops. This issue caused scientists to shift their interest to second and
third generation biofuels that are based solely on waste biomass. Nevertheless, the
production of second and third generation biofuels is still non-commercial, although
pilot and demonstration facilities are being developed (Bezergianni et al. 2010).
Pollution problems are due to the high volume of WCO in which it is generated,
and there is usually an inappropriate disposal of such waste (Moreno‐Gómez et al.
2020). Therefore, WCO can substitute the edible of vegetable as the feedstock of biojet
fuels. Futhermore, the main advantage of hydroprocessing is that it requires widely
available infrastructure.
In order to produce the jet fuel, we used a process named hydro-processed renewable
jet (HRJ) which converts oils and fat into renewable jet fuel. HRJ includes the hydro-
treating of glyceride-based oils into straight-chain alkanes which will occur in reactor
R-101 and hydrocracking of the produced long-chain alkanes into jet fuel which will
occur in reactor R-102. Both of this reaction used catalyst. The chemical reaction is
shown as below:
Reaction 1:
Reaction 2:
Overall equation:
Both reactions took place at high temperature and pressure which is 375°C and 40 bar
with the need of catalyst NiMo/Al2O3.
Design constraints are restrictions on the design's needs to function at the expected
parameters to assure the plant's safety, economic aspect, and optimal production of the
desired output. There are two type of design which are design constrain external and
design constraint internal External constraints are those that are established on a
business. The limitation is beyond the company's (or little) control. The company's
product and systems must be developed around those constraints. The design constraint
external show in the Table 3.2
21
Design internal constraint can be defined the internal constraint is different and
there are two types which are good and bad. Internal constraints are constraints that a
company place on themselves. They are artificial. Good internal constraints are those
that are put in place to keep a company focused.
Selected catalyst with poor performance that can The conjugation of a base and acid catalyst for a
lead to the undesirable cracking. better performance coke formation reducing.
Non-uniform morphology of support catalyst can By using continuous reactor with a fixed catalyst.
lead to a rapid deactivation of catalyst, poor
catalyst activity and bio-jet fuel conversion
Short alkanes that will form deposit in the jet Use zeolite to control the size of alkane formed
engine and may cover the catalyst which will
reduce its lifespan and effectiveness.
According to the hierarchy of Douglas 1988, level 2 in the design of process includes
process input-output structure and recycles structure. It can also be called as synthesis
of chemical transformation process since it involves the transformation of chemical
substances from reactants to products.
22
The inputs for our designed plant are waste cooking oil, hydrogen gas, benzene
and water. WCO feedstock and hydrogen gas will react at a high temperature and
pressure to forms free fatty acids or paraffin. Propane gas will be produced, and it will
then be purified in the gas absorption and stripper. Benzene will act as solvent in the
gas absorption and water will acts as vaporizing agent in order to separate propane from
impurities. The paraffin is then converted into jet fuel through hydro-cracking and are
accompanied with the deoxygenation process which is also called decarbonylation with
the formation of carbon monoxide and water, which produce the main product decane
and by-product petrol. Carbon monoxide, paraffin, wastewater will exist as waste.
Figure below shows the input and output structure for our production.
Design capacity of our plant is set according to supply and demand of aviation fuel
globally. It is decided to produce 91.25 kilo tonnes of decane per year, which accounts
for 2% of the shortage in global market in the future. The plant will operate for 330 days
per annum with 30 days shut down period.
23
The plant capacity used in the production of decane is 10416.67 kg/hr. From the overall
reaction, the mass balance of the production can be obtained. The overall mass balance
of this production is shown in Table 3.4 below.
Economy potential level 2 (FPE2) for the process is calculated in order to determine the
gross profit obtained from the production. Equation below is the general equation used
to determine economy potential level 2 with respect to product prices and prices of raw
material.
fPE2 = Cost for Main Product + Cost for byproduct − Cost for Raw material
Results for calculation of economic potential level 2 versus conversion of process are
tabulated in Table 3.6 and Figure .
Level 3 of process design is synthesis of recycle system. Reactor and recycling systems
are considered in more detail at this stage, so that the distribution of the product can be
calculated with greater precision. The number, type and design of the reactor, excess
reactant, compressor requirement and its design, reactor heat management and
equilibrium reaction effect are design variables to be determined (Wan Ramli 2002).
There is two reactions occur during synthesis of aviation fuel which are hydrocracking
and hydrotreating. Therefore, there are two packed bed reactors used in our plant.
The reactor that has been chosen for the hydrotreating is packed bed reactor.
Hydrotreating processes aim at the removal of impurities such as sulfur and nitrogen
from distillate fuels naphtha, kerosene, and diesel by treating the feed with hydrogen at
elevated temperature and pressure in the presence of a catalyst. (Parkash 2003)
For the second process which is hydrocracking, the reactor chosen is fixed bed reactor
that is packed with solid catalyst particles which is Ni-Mo/y-alumina. This is because
the reaction occurs heterogeneous reaction and can have high conversion per unit mass
of catalyst. Hydrocracking is a process by which the hydrocarbon molecules of
petroleum are broken into simpler molecules, as of gasoline or kerosene, by the addition
of hydrogen under high pressure and in the presence of a catalyst.
The adiabatic temperature of the reaction needs to be calculated so that the condition
whereby the reactor operates adiabatically or thermally can be determined. According
to the Figure as the conversion increases, the adiabatic temperature rises, indicating
that the process is exothermic. Estimation of Heat effects on both reactors can refer to
the Table 3.7.
26
The height, diameter and volume for packed bed reactor is calculated using the equation
of PFR with catalyst since there are catalyst used in the reactor.
𝑋𝐴
𝑉 𝑑𝑋𝐴
=∫
𝐹𝐴𝑜 0 𝜌𝑐 (1 − 𝜀)(−𝑟𝑎 )
Where,
𝑉 = Volume of reactor
FAo = Flowrate inlet
27
X = Conversion
ρc = Density of catalyst
ε = Bed voidage
By using the ratio of H/D = 3, then H = 3D. The summary of both reactor height,
volume and dimensions are shown in the table below.
Where,
Design material factor, Fm and pressure factor, Fp is shown inTable 3.10 . Table
3.11 and Table 3.12shows the annual cost of reactor as a function of conversion.
where,
Hence, the economic potential can be evaluated from the data obtained from the
economic potential level 2. Table 3.13 and Figure showed the economic potential of
level 3.
At this level, separation processes are discussed. Separation process is important to the
overall process. It separates two or more mixtures to obtain the desired end products.
The separation units involved are gas absorption, stripper and distillation column.
Distillation column is used to separate mixture of solvent into two pure components.
This unit process usually used in plant production. Table 3.14 Sizing and cost of
distillation column (D-101) shows the sizing and cost of distillation column.
Benzene and propane being separated from the feed in a steam. Stripping columns are
absorbed by the water vapor, effectively isolating them from the desired product.
Scrubbing is another name for steam stripping, which refers to how the constituent
molecules are "scrubbed" out of the feed. Steam stripping is often known as steam
distillation, although distillation is a separate chemical process.
In our process, this distillation column (D-102) was used to separate four different
components which is wastewater and petrol will pump into distillate stream. Meanwhile
mixture of decane and paraffin out from bottom of distillation column. Table 3.17 shows
the sizing and cost of distillation column.
For third distillation column for our process is to separate mixture of petrol and
wastewater. This process, petrol will go to distillate which is top stream and wastewater
will pump into bottom stream. The Table 3.18 shows the sizing and cost of distillation
column.
For the last distillation column, it used to separate mixture of decane and paraffin. These
two components in liquid phase with different boiling point. Because decane has lower
boiling point than paraffin thus decane will goes out at top stream of distillation and
paraffin at bottom stream. The Table 3.19 shows the sizing and cost of distillation
column.
Where,
Hence, the economic potential for level 4 is shown in Table 3.20 and Figure .
Our plant will produce decane from waste cooking oil using the hydroprocess which
this reaction needs a large amount of hydrogen gas. Petrol and propane will be produced
as by-product.
This hydro processing unit can be used for both hydrotreating and hydrocracking
reactions at high pressures and temperatures. It mainly consists of a liquid feed system,
hydrogen feed system, a packed-bed reactor system and a product separation system
(Bezergianni et al. 2010). In our process, we use waste cooking oil (WCO) with
molecular formula C54H102O6 as our feedstock. The WCO feedstock first undergoes
filtration to remove any food sediments from the mixture before entering the reactor
(Goh et al. 2020a). In the first reactor (R-101), WCO will undergoes hydro-treating
process where WCO will react with hydrogen gas in a high temperature and pressure
condition, where the glyceride-based oils will be converted into free fatty acids (FFAs)
or paraffin (Chen & Wang 2019). This catalytic reaction occurs in a packed bed reactor
at 40 bar and 375°C over NiMo/γ-Al2O3 catalyst. Propane gas will be produced, and it
will then be purified in the gas absorption and stripper. Benzene will act as solvent in
the gas absorption and water will acts as vaporizing agent in the stripper in order to
separate propane from impurities.
The liquid effluent produced from the first reactor will enter distillation column (D-101)
to make sure that the paraffin is purified before entering the second reactor. In this
distillation column, we want to separate paraffin from unreacted WCO. The paraffin
will exit as a top product at temperature 180°C and it will be condensed into liquid form
before entering the second reactor.
In the second reactor (R-102), again the hydrogen gas will be supplied to react with
paraffin also in a high temperature and pressure condition which is 40 bar and 375°C.
This reaction is called hydro-cracking where the produced paraffin is then converted
into jet fuel through the deoxygenation process which is also called as decarbonylation
(DCO), also using NiMo/γ-Al2O3 catalyst (Chen & Wang 2019). The jet fuel that will
be produced is decane, C10H22, with formation of water and carbon monoxide. Aside
from that, petrol with molecular formula C6H14 will also be produced as by-product.
The liquid product will enter distillation column to separate the jet fuel and petrol. The
distillation column (D-102) will operate at 100°C and petrol will exit as top product
37
while decane will exit as bottom product. Both products will enter distillation column
again to further be purified so that the product will be produced in a high purity. In the
third distillation column (D-103), the petrol with 95% purity will exit as top product at
70°C and it will be condensed at room temperature. Same goes to decane, it will also
exit as top product with 98% purity at 175°C and the temperature will be decreased so
that it can be kept in room temperature.
Based on the principle of conservation of mass, the mass of the products will always be
equal to the mass of the reactants (Boundless 2015). If the total mass flowrate of the
inlet is almost equal to the total mass flowrate of the outlet, the mass balance of the
production is balance. Below shows the basic assumption used in our production.
Assumption:
The overall mass balance is calculated using formula manually for each major
equipment. Figure shows reactor (R-101) where waste cooking oil and hydrogen are
fed into as raw material to produce paraffin and propane. Table 3.21 shows the mass
balance at reactor (R-101).
38
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
The paraffin produced from reactor (R-101) will then enter reactor (R-102) and
reacts with hydrogen gas to produce our main product which is decane. Figure shows
reactor (R-102) and mass balance at reactor (R-102) is shown in Table 3.22.
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
Overall mass balance is shown below with Table 3.23 shows the input streams flowrate
and
41
Table 3.24 shows the output stream flowrate. The mass balance for other unit is shown
in Appendix A.
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
25.05 + 6479.07 + 15.32 + 1395.07 + 989.18 + 2168.88 + 6507.42 + 1540.23 + 10416.67 + 4547.9
This section will discuss the comparison between the mass balance manual calculation
and simulation by SuperPro calculation. This comparison to check the final mass of
products that are obtained from manual calculation. Based on the result obtained in
SuperPro is different value get from manual calculation. These differences occur because
SuperPro® uses more accurate method to solve the equation during the simulation at each
of the streams. The table below shows the comparison between calculation of manual and
simulation for each unit process.
Figure shows the plantwide simulation of the production plant. The details data will be
shown in Appendix C.
44
The relationship between energy in and out is referred to as energy balance. This
relationship, which is determined by thermodynamic rules, determines whether mass is
lost, gained, or remains constant. Energy, according to these rules, is never truly
generated and never truly destroyed. Energy is instead exchanged between entities. The
system's energy balance is used to determine the energy that must be fed into the system
as well as the energy that is released during the process. Engineers apply energy balance
calculations to determine the heat change of the unit process under consideration. The
assumption for energy balance calculation that we consider is as below:
2. There are no potential energy, kinetic energy and work done by the system because
the unit processing used is close system.
According to the assumption, enthalpy change in each component for inlet and
outlet stream needed to determine by formula below:
𝑇2
∆𝐻 = ∫ 𝐶𝑝 𝑑𝑡
𝑇𝑟𝑒𝑓
𝑄 = 𝑚𝐶𝑃 ∆𝑇
46
The data for heat capacity of each component are shown in table Table 3.27
a. Reactor (R-101)
Based on table A.8, standard heat of reaction was calculated by formula below:
47
̂ 𝑟 = ∑ 𝐻°
∆𝐻° ̂𝑓 (𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑠) − ∑ 𝐻°
̂𝑓 (𝑟𝑒𝑎𝑐𝑡𝑎𝑛𝑡)
̂𝑖/𝑗 = ∫𝑇2 𝐶𝑝 𝑑𝑡
∆𝐻 𝑇1
𝑇2
=∫𝑇1 (𝑎 + 𝑏𝑇 + 𝑐𝑇 2 + 𝑑𝑇 3 𝑑𝑡
𝑏𝑇 2 𝑐𝑇 3 𝑐𝑇 4
=[𝑎𝑇 + + + ]
2 3 4
Where Cp is the molar heat capacity of the component as stated on table C.2
while 𝑇1 is a reference temperature and 𝑇2 is an inlet or outlet temperature.The molar
heat capacity of component in the reactor (R-101) were calculated and simplify as table
below:
b. Reactor (R-102)
Based on table Table 3.26 standard heat of reaction was calculated by formula
below:
̂ 𝑟 = ∑ 𝐻°
∆𝐻° ̂𝑓 (𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑠) − ∑ 𝐻°
̂𝑓 (𝑟𝑒𝑎𝑐𝑡𝑎𝑛𝑡)
∆𝐻𝑟𝑥𝑛 = ∆𝐻𝑓 𝐷𝑒𝑐𝑎𝑛𝑒 + ∆𝐻𝑓 𝑃𝑒𝑡𝑟𝑜𝑙 + ∆𝐻𝑓 𝐶𝑎𝑟𝑏𝑜𝑛 𝑚𝑜𝑛𝑜𝑥𝑖𝑑𝑒 + ∆𝐻𝑓 𝑊𝑎𝑡𝑒𝑟
− ∆𝐻𝑓 𝑝𝑎𝑟𝑟𝑎𝑓𝑖𝑛 − 3∆𝐻𝑓 ℎ𝑦𝑑𝑟𝑜𝑔𝑒𝑛
= (−46200) + (−44000) + (−110525) +
(−285830) — (−46200) − (−120000)
= -860555 kJ/mol
The molar heat capacity of component in the reactor (R-102) were calculated
and simplify as table below:
CHAPTER IV
HEAT INTEGRATION
4.1 INTRODUCTION
Energy conservation has always been important in process design. Heat integration or
pinch analysis is a simple method for systematically analyzing chemical processes and
the surrounding utilities with the aid of first and second laws of thermodynamics. The
heating and cooling cost of a chemical processes plant contributes to the total production
cost significantly. A stream that needs to be heated is called a cold stream while a stream
that needs to be cooled is called a hot stream. In a process, a hot stream can be used to
heat a cool stream so that the utility costs can be reduced.
Pinch analysis is the most generally used technique developed to design a process in
such a way that optimum usage of available energy within the process itself is
achieved. It is a systematic method to analyze potential for heat integration in a
process. The actual temperature Tact is converted into interval temperature Tint using
equations below in the problem table method.
1
Hot Stream: 𝑇𝑖𝑛𝑡 = 𝑇𝑎𝑐𝑡 − (2)∆𝑇𝑚𝑖𝑛
1
Cold Stream: 𝑇𝑖𝑛𝑡 = 𝑇𝑎𝑐𝑡 + (2)∆𝑇𝑚𝑖𝑛
𝑇𝑚𝑖𝑛 = 20°C
51
a. Data extraction
b. Pinch Point
In order to get pinch point, there are two methods which are temperature enthalpy
diagram and problem-table method. In our calculation, we selected the problem-table
method. The following heat capacity for each stream placed at the very right position in
the is calculated from respective heat capacity of intermediate temperature. Table 4.1
shows the data for each utility.
Stream Type Heat 𝑻𝒊𝒏 (°𝐂) 𝑻𝒐𝒖𝒕 (°𝐂) Heat 𝑻𝒊𝒏,𝒊𝒏𝒕 𝑻𝒐𝒖𝒕,𝒊𝒏𝒕
No Capacity, load, (°𝐂) (°𝐂)
CP
Q
(kW)
c. Heat cascade
Heat cascade is worked out to find the pinch point which is the pinch temperature to get
the above and below pinch for the addition of heater and cooler. The pinch point is
35°C. Heat cannot be transferred across the pinch. Hot utilities should be below the
pinch and cold utilities should be above the pinch. Figure shows the relationship
between inlet cold and hot temperatures. Table 4.2 also shows the heat cascade
iterations.
52
A grid can represent a heat exchanger network where the process streams are
drawn as horizontal lines, with the stream number shown in square boxes. Hot streams
are drawn at the top of the grid and flow from left to right. The streams are drawn at the
53
bottom and flow from right to left for the cold streams. Figure shows a heat exchanger
network in grid form for this process.
For heat exchanger design above the pinch, the condition that must be fulfilled is
CpH<CpC. Only hot utilities are allowed for this design. The heat transfer design for
the above pinch is shown in Figure .
54
For heat exchanger design below the pinch, the condition that must be fulfilled is
Total heat recovery indicates that energy saved after heat integration by using pinch
analysis. It can be calculated using formula. Heat transfer design for the above pinch as
in Figure .
The total energy recovery is the energy saved after heat exchanger network is performed
using pinch analysis.
CHAPTER V
5.1 INTRODUCTION
Piping and instrumentation diagram (P&ID) refer to the diagram detail about the
specific process within plant. This specific process which shows comprises of piping,
vessels, control valves and equipment in system. In the process industry widely used
this drawing to represent their plant and a standard set of symbols was used to prepare
the drawing. This chapter will explain about P&ID and analysis based on process
control on our production process
Process control is referring to methods that are used to control process variables when
manufacturing a product. It is the most important part in production plant because it
allows complex plant operations to be carried out automatically. Automatic control of
process offers many advantages such as increasing efficiency of product, energy usage
and enhanced process safety. The table below shows the type of configuration and
objectives of each control.
Pressure control Pressure transmitter (PT) Detect the changes in pressure and send signal
to controller
Pressure controller (PC) Control the pressure of vessel pipeline after
receiving signal from transmitter to achieve
within set point
Flow control Flow transmitter (FT) Detect the changes of flow in pipeline and send
signal to flow controller.
Flow controller (FC) Control the flow rate of pipeline to prevent
flooding of vessel.
Level control Level transmitter (LT) Detect the changes of level and send signal to
level controller.
Level controller (LC) Controlling the level of vessel is within set
point
Composition Composition analyser (AT) Detect the changes of component composition
control in the process and send signal to controller
Composition controller (AC) Control the composition in the process to
obtain required purity
Filter (F-101) is used to separate out all the undesired substances in the waste cooking
oil before entering the reactor. This is to ensure that the reaction can occur smoothly.
Information below shows the mathematical model for filter (F-101).
a. Mathematical Model
i. Filter Equation:
𝑑𝜌
𝑉[ ] = 𝜌3 𝐹3 − 𝜌6 𝐹6 − 𝜌9 𝐹9 (1)
𝑑𝑡
𝑑𝑇
𝑉𝜌𝐶𝑣 [ ] = ∑ 𝜌3 𝐹3 𝐶𝑝 𝑇3 + ∑ 𝜌6 𝐹6 𝐶𝑝 𝑇6 + ∑ 𝜌9 𝐹9 𝐶𝑝 𝑇9 (2)
𝑑𝑡
58
b. Degree of freedom
Disturbances = 2 (Tref, P)
Number of equations = 2
Hydro-treating process will occur in the first reactor (R-101) is where the triglycerides
from the WCO and hydrogen will react to produce paraffin and propane gas. This
reaction will occur in a high pressure and temperature. Information below shows the
mathematical model packed bed reactors (R-101).
i. Reactor Equation:
𝜕𝑉
𝜌( ) = 𝜌8 𝐹8 − 𝜌14 𝐹14 − 𝜌11 𝐹11 − 𝜌15 𝐹15 (1)
𝜕𝑡
𝜕𝑉
𝜌𝐶𝑝 𝑉 ( ) = 𝜌𝐶𝑝 𝐹𝑖 (𝑇𝑖 − 𝑇𝑜 ) − ∆𝐻 + 𝑄 (2)
𝜕𝑡
b. Degree of freedom
Number of equations = 2
The gas effluent from reactor (R-101) will enter gas absorption (G-101) to separate
propane gas from other impurities. Benzene will enter as solvent to absorb propane.
Information below shows the mathematical model for Gas Absorption (G-101).
61
a. Mathematical Model
𝜕𝑉
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 = 𝜌𝐹1 − ( 𝜌𝐹2 + 𝜌𝐹3 ) (1)
𝜕𝑡
𝜕𝑉
𝜌𝐶𝑝 𝑉 ( ) = 𝐶𝑝 𝐹1 𝑇1 − 𝐶𝑝 𝐹1 𝑇1 − 𝐶𝑝 𝐹1 𝑇1 − 𝑈𝐴(𝑇 − 𝑇𝑐 ) + 𝑄 (2)
𝜕𝑡
b. Degree of freedom
Disturbances = 2 (Tref, P)
Number of equations = 4
After the propane has been separated from other impurities, the propane then needs to
be separated from the solvent which is benzene. In order to do that, the propane-benzene
mixture will enter stripper (G-102) to produce propane with 97% purity. Information
below shows the mathematical model for Stripper (G-102)
a. Mathematical Model
i. Stripper Equation:
𝜕𝑉
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 = 𝜌𝐹1 − ( 𝜌𝐹2 + 𝜌𝐹3 ) (1)
𝜕𝑡
𝜕𝑉
𝜌𝐶𝑝 𝑉 ( ) = 𝐶𝑝 𝐹1 𝑇1 − 𝐶𝑝 𝐹1 𝑇1 − 𝐶𝑝 𝐹1 𝑇1 − 𝑈𝐴(𝑇 − 𝑇𝑐 ) + 𝑄 (2)
𝜕𝑡
𝑃𝑉 = 𝑛𝑅𝑇 (3)
63
4. Design of volume
4
𝑉 = 𝜋𝑟 2 ℎ1 + 𝜋𝑟 3 (4)
3
b. Degree of freedom
Disturbances = 2 (Tref, P)
Number of equations = 4
Level To control the Level of fluid Flowrate LT will detect the Globe
controller level of fluid inside stripper bottom of level changes and valve used
and avoid at set point product at send signal to LC to handle
spillage of 75% stream 39 which will adjust liquid
containment the valve level in
accordingly pipeline.
Distillation column is used to separate heavy and light components inside the feed flow.
Distillation column (D-101) is used to separate paraffin from the unreacted WCO that
will entering the reactor for the second rection. Information below shows the
mathematical model for Distillation Column (D-101).
a. Mathematical Model
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 = 𝜌𝐹1 − ( 𝜌𝐹2 + 𝜌𝐹3 ) (1)
𝜕𝑡
2. Total energy balance
𝑑𝑇 𝑑ℎ 𝑄
𝐴 (ℎ + 𝑇 ) = 𝜌𝐹1 − 𝜌𝐹2 − 𝜌𝐹3 − (2)
𝑑𝑡 𝑑𝑡 𝜌𝐶𝑝
3. Ideal gas law,
𝑃𝑉 = 𝑛𝑅𝑇 (3)
4. Equilibrium vapor composition each stage,
𝛼𝑥𝑖
𝑦𝑖 = (4)
1 + (∝ −1)𝑥𝑖
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 (1)
𝜕𝑡
2. Reflux ratio
𝐹𝑖
𝑅= (2)
𝐹𝑜
b. Degree of freedom
i. Distillation Column
Disturbances = 2 (Tref, R)
Number of equations = 4
Disturbances = 1 (F22)
Number of equations = 2
In the second reactor (R-102) hydro-treating process will occur is where the purified
paraffin will be converted into fuel jet. This reaction will occur in a high pressure and
temperature. Information below shows the mathematical model packed bed reactors (R-
102).
i. Reactor Equation:
𝜕𝑉
𝜌( ) = 𝜌24 𝐹24 − 𝜌27 𝐹27 − 𝜌32 𝐹32 − 𝜌33 𝐹33 (1)
𝜕𝑡
𝜕𝑉
𝜌𝐶𝑝 𝑉 ( ) = 𝜌𝐶𝑝 𝐹𝑖 (𝑇𝑖 − 𝑇𝑜 ) − ∆𝐻 + 𝑄 (2)
𝜕𝑡
b. Degree of freedom
Number of equations = 2
68
The effluent from Reactor (R-102) will enter Distillation column (D-102) to separate
the products which is petrol and decane based on their boiling point. Information below
shows the mathematical model for Distillation Column (D-102).
69
a. Mathematical Model
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 = 𝜌𝐹1 − ( 𝜌𝐹2 + 𝜌𝐹3 ) (1)
𝜕𝑡
𝑑𝑇 𝑑ℎ 𝑄
𝐴 (ℎ + 𝑇 ) = 𝜌𝐹1 − 𝜌𝐹2 − 𝜌𝐹3 − (2)
𝑑𝑡 𝑑𝑡 𝜌𝐶𝑝
𝑃𝑉 = 𝑛𝑅𝑇 (3)
𝛼𝑥𝑖
𝑦𝑖 = (4)
1 + (∝ −1)𝑥𝑖
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 (1)
𝜕𝑡
2. Reflux ratio
𝐹𝑖
𝑅= (2)
𝐹𝑜
b. Degree of freedom
i. Distillation Column
Disturbances = 2 (Tref, R)
Number of equations = 4
Disturbances = 1 (F42)
Number of equations = 2
The gas effluent from Distillation column (D-102) will first condensed until its liquid
form before entering Distillation column (D-103). In Distillation Column (D-103), the
petrol will be purified so that it can be sold in a high purity. Information below shows
the mathematical model for Distillation Column (D-103).
72
a. Mathematical Model
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 = 𝜌𝐹1 − ( 𝜌𝐹2 + 𝜌𝐹3 ) (1)
𝜕𝑡
𝑑𝑇 𝑑ℎ 𝑄
𝐴 (ℎ + 𝑇 ) = 𝜌𝐹1 − 𝜌𝐹2 − 𝜌𝐹3 − (2)
𝑑𝑡 𝑑𝑡 𝜌𝐶𝑝
𝑃𝑉 = 𝑛𝑅𝑇 (3)
𝛼𝑥𝑖
𝑦𝑖 = (4)
1 + (∝ −1)𝑥𝑖
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 (1)
𝜕𝑡
2. Reflux ratio
𝐹𝑖
𝑅= (2)
𝐹𝑜
73
b. Degree of freedom
i. Distillation Column
Disturbances = 2 (Tref, R)
Number of equations = 4
Disturbances = 1 (F2)
Number of equations = 2
Level To avoid Level of fluid Flow rate of LT will detect the Globe
controller of spillage of in distillation bottom level changes and valve used
distillation containment column product at send signal to LC to handle
column stream 55 which will adjust liquid level
the valve in pipeline.
accordingly.
Finally, to produce decane with 98% purity, the effluent from Distillation Column (D-
102) will enter Distillation Column (D-104). In this distillation column, the product will
be purified and exit as top product. Information below shows the mathematical model
for Distillation Column (D-104).
75
a. Mathematical Model
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 = 𝜌𝐹1 − ( 𝜌𝐹2 + 𝜌𝐹3 ) (1)
𝜕𝑡
𝑑𝑇 𝑑ℎ 𝑄
𝐴 (ℎ + 𝑇 ) = 𝜌𝐹1 − 𝜌𝐹2 − 𝜌𝐹3 − (2)
𝑑𝑡 𝑑𝑡 𝜌𝐶𝑝
𝑃𝑉 = 𝑛𝑅𝑇 (3)
𝛼𝑥𝑖
𝑦𝑖 = (4)
1 + (∝ −1)𝑥𝑖
𝜕𝐴ℎ
𝜌( ) = ∑ 𝜌𝐹𝑖 − ∑ 𝜌𝐹𝑜 (1)
𝜕𝑡
2. Reflux ratio
𝐹𝑖
𝑅= (2)
𝐹𝑜
b. Degree of freedom
i. Distillation Column
Disturbances = 2 (Tref, R)
Number of equations = 4
Disturbances = 1 (F2)
Number of equations = 2
The function of heater is to increase the temperature of stream to certain desired value.
There are 3 heaters sin the process which is H-101, H-102, and Information below
shows the mathematical model for Heater (H-101).
a. Mathematical Model
𝜕𝑉
𝜌 = 𝜌𝑖𝑛 𝐹𝑖𝑛 − 𝜌𝑜𝑢𝑡 𝐹𝑜𝑢𝑡 (1)
𝑑𝑡
2. Energy balance
𝜕𝑉
𝜌𝐶𝑝 𝑉 = 𝐶𝑃 𝜌𝐹𝑖𝑛 𝑇𝑖𝑛 − 𝐶𝑃 𝜌𝐹𝑜𝑢𝑡 𝑇𝑜𝑢𝑡 + 𝑄 (2)
𝑑𝑡
78
𝑑𝑇ℎ
𝜌ℎ 𝐶𝑝ℎ 𝑉ℎ = 𝐶𝑃ℎ 𝜌ℎ 𝐹ℎ𝑖 𝑇ℎ𝑖 − 𝐶𝑃ℎ 𝜌ℎ 𝐹ℎ𝑜 𝑇ℎ𝑜 + 𝑈𝐴(𝑇ℎ − 𝑇) (3)
𝑑𝑡
4. Assumption:
Disturbances = 2 (F, T)
Number of equations = 3
Temperature To heat up the Temperature Inlet flowrate TT will detect the Globe
controller temperature of of the stream of the stream temperature valve used
flowrate changes and send suitable to
stream to the signal to TC regulate
desired point which will adjust the liquid
the valve
accordingly
a. Mathematical Model
𝜕𝑉
𝜌 = 𝜌𝑖𝑛 𝐹𝑖𝑛 − 𝜌𝑜𝑢𝑡 𝐹𝑜𝑢𝑡 (1)
𝑑𝑡
Energy balance
𝜕𝑉
𝜌𝐶𝑝 𝑉 = 𝐶𝑃 𝜌𝐹𝑖𝑛 𝑇𝑖𝑛 − 𝐶𝑃 𝜌𝐹𝑜𝑢𝑡 𝑇𝑜𝑢𝑡 + 𝑄 (2)
𝑑𝑡
𝑑𝑇𝑐
𝜌𝑐 𝐶𝑝𝑐 𝑉𝑐 = 𝐶𝑃𝑐 𝜌𝑐 𝐹𝑐𝑖 𝑇𝑐𝑖 − 𝐶𝑃𝑐 𝜌ℎ 𝐹𝑐𝑜 𝑇𝑐𝑜 + 𝑈𝐴(𝑇𝑐 − 𝑇) (3)
𝑑𝑡
Assumption:
Disturbances = 2 (F, T)
80
Number of equations = 3
The function of cooler is to decrease the temperature of a stream to desired value. There
are 8 coolers in the process which is C-101, C-102, C-103, C-104, 1-105, C-106, C-107
and C-108. Information below shows the mathematical model for Cooler (C-104).
The main purpose of heat exchanger is to provide a place for the process fluid to
exchange heat with other fluid. So, the main objective is to increase or decrease the
temperature of process fluid to desired temperature. Information below shows the
mathematical model for Heat Exchanger (J-101).
81
a. Mathematical Model
𝜕𝑉
𝜌 = 𝜌𝑖𝑛 𝐹𝑖𝑛 − 𝜌𝑜𝑢𝑡 𝐹𝑜𝑢𝑡 (1)
𝑑𝑡
2. Energy balance
𝜕𝑉
𝜌𝐶𝑝 𝑉 = 𝐶𝑃 𝜌𝐹𝑖𝑛 𝑇𝑖𝑛 − 𝐶𝑃 𝜌𝐹𝑜𝑢𝑡 𝑇𝑜𝑢𝑡 + 𝑄 (2)
𝑑𝑡
𝑑𝑇𝑐
𝜌𝑐 𝐶𝑝𝑐 𝑉𝑐 = 𝐶𝑃𝑐 𝜌𝑐 𝐹𝑐𝑖 𝑇𝑐𝑖 − 𝐶𝑃𝑐 𝜌ℎ 𝐹𝑐𝑜 𝑇𝑐𝑜 + 𝑈𝐴(𝑇𝑐 − 𝑇) (3)
𝑑𝑡
4. Assumption:
Disturbances = 2 (F, T)
Number of equations = 3
Pressure relief devices are an essential requirement for the safe use of pressure
vessels. Pressure relief devices provide a mechanical means of ensuring that the
pressure inside a vessel cannot rise to an unsafe level. All pressure vessels within the
scope of Section VIII of the ASME Boiler and Pressure Vessel Code must be fitted with
a pressure relief device. The purpose of the pressure relief device is to prevent
catastrophic failure of the vessel by providing a safe means of relieving over-pressure
if the pressure inside the vessel exceeds the maximum allowable working pressure.
Three different types of relief devices are commonly used:
83
Bursting discs: thin discs of material that are designed and manufactured to fail
at a predetermined pressure.
One of the most fundamental aspects of developing a chemical industry facility is the
pipe system. Pipes are used to transport solid, liquid, and gaseous material from one
unit activity to another. Fiberglass, steel, aluminum, and other materials are utilized to
create plumbing systems. Pipes, plates, gaskets, fittings, valves, bolts, and pipe support
are all part of the piping system. The pipe diameter is the most important factor to
consider when building a pipe system. The pipe's ideal diameter had to be estimated to
reduce the piping system's cost and get the pipe's optimum size. The ideal diameter for
a pipe system varies depending on the condition of the material. With optimal diameter
calculations, its nominal size specifies the diameter of pipes. Because of its capacity to
endure pressure and temperature for our chemical plant process, we chose stainless steel
as the piping system material for our plant. Schedule 10 stainless steel piping was
84
utilized throughout. The pipe's size is established using ASME/ANSI B36.19 Stainless
Steel Pipe as a guide.
The diameter for stainless steel pipe can be determined by the equation below.
For a long pipe, the gas velocity can approach the sonic velocity. The vapor velocity
is determined using the thermodynamic relationship.
𝑅𝑇
𝑈=√
𝑀
Where
The vapour velocity value, U then will be used in the equation below,
𝑄𝑚 = 𝜌𝑈𝐴
85
Where 𝑄𝑚 is the gas flow rate (kg/s), 𝜌 is the density of the fluid (kg/𝑚3 ), U is the sonic
velocity (m/s) and A is the cross sectional area of pipe (𝑚2 ),
Thus, the diameter of the pipe can be determined by the equation below,
4𝐴
Dv=√ 𝜋
The diameter determined from the equation above will be compared with the standard
ANSI/ASME B36.10/19 Stainless Steel Pipe to determine nominal pipe dimension. The
estimation diameter of vapor piping show as the Table 5.16.
86
Table 5.15 The sizing for the piping system of liquid flow
Stream G(kg/h) G(kg/s) Density Doptimum Doptimum Schedule Dnominal Dout (in) t(in) Din(in)
(kg/m3) (m) (in) No (in)
1 943.52 0.26 997.00 0.02 0.88 10s 1.00 1.32 0.11 1.10
2 92.83 0.03 876.00 0.01 0.28 10s 3.00 3.50 0.12 3.26
3 32395.36 9.00 923.20 0.14 5.52 10s 6.00 6.63 0.13 6.36
6 32395.36 9.00 923.20 0.14 5.52 10s 6.00 6.63 0.13 6.36
9 32395.36 9.00 923.20 0.14 5.52 10s 6.00 6.63 0.13 6.36
13 32395.36 9.00 923.20 0.14 5.52 10s 6.00 6.63 0.13 6.36
14 32395.36 9.00 923.20 0.14 5.52 10s 6.00 6.63 0.13 6.36
15 31108.73 8.64 900.00 0.14 5.46 10s 6.00 6.63 0.13 6.36
16 92.83 0.03 876.00 0.01 0.28 10s 3.00 3.50 0.12 3.26
18 31108.73 8.64 900.00 0.14 5.46 10s 6.00 6.63 0.13 6.36
19 31108.73 8.64 900.00 0.14 5.46 10s 6.00 6.63 0.13 6.36
20 31108.73 8.64 900.00 0.14 5.46 10s 6.00 6.63 0.13 6.36
21 24629.66 6.84 900.00 0.12 4.84 10s 5.00 5.56 0.13 5.30
22 24629.66 6.84 900.00 0.12 4.84 10s 5.00 5.56 0.13 5.30
23 24629.66 6.84 900.00 0.12 4.84 10s 5.00 5.56 0.13 5.30
24 24629.66 6.84 900.00 0.12 4.84 10s 5.00 5.56 0.13 5.30
25 6479.07 1.80 923.20 0.06 2.43 10s 2.50 2.88 0.12 2.64
26 6479.07 1.80 923.20 0.06 2.43 10s 2.50 2.88 0.12 2.64
30 92.83 0.03 876.00 0.01 0.28 10s 3.00 3.50 0.12 3.26
31 92.83 0.03 876.00 0.01 0.28 10s 3.00 3.50 0.12 3.26
33 23012.19 6.39 3427.00 0.07 2.89 10s 3.00 3.50 0.12 3.26
34 23012.19 6.39 3427.00 0.07 2.89 10s 3.00 3.50 0.12 3.26
35 23012.19 6.39 3427.00 0.07 2.89 10s 3.00 3.50 0.12 3.26
36 6479.07 1.80 923.20 0.06 2.43 10s 2.50 2.88 0.12 2.64
87
37 6479.07 1.80 923.20 0.06 2.43 10s 2.50 2.88 0.12 2.64
38 1395.07 0.39 1490.00 0.02 0.93 10s 1.00 1.32 0.11 1.10
39 989.18 0.27 1873.00 0.02 0.72 10s 0.75 1.05 0.08 0.88
41 8047.65 2.24 3427.00 0.04 1.69 10s 2.00 2.38 0.11 2.16
42 8047.65 2.24 3427.00 0.04 1.69 10s 2.00 2.38 0.11 2.16
43 8047.65 2.24 3427.00 0.04 1.69 10s 2.00 2.38 0.11 2.16
44 8047.65 2.24 3427.00 0.04 1.69 10s 2.00 2.38 0.11 2.16
45 14964.54 4.16 3427.00 0.06 2.32 10s 2.50 2.88 0.12 2.64
46 14964.54 4.16 3427.00 0.06 2.32 10s 2.50 2.88 0.12 2.64
47 14964.54 4.16 3427.00 0.06 2.32 10s 2.50 2.88 0.12 2.64
48 14964.54 4.16 3427.00 0.06 2.32 10s 2.50 2.88 0.12 2.64
49 6507.42 1.81 3427.00 0.04 1.52 10s 2.00 2.38 0.11 2.16
88
Table 5.16 The sizing for the piping system of vapor flow
Stream TºC T(K) M G Velocity Density A Doptimum Dopt Dnominal Dout T Din
(g/mol) (kg/s) (kg/m3) (m2) (m) (inch) (inch) (inch) (inch)
4 25 300 2 1.28 10.19 83.77 0.16 0.22 8.75 10.00 10.75 0.13 10.48
5 25 300 2 1.28 10.19 83.77 0.16 0.22 8.75 10.00 10.75 0.13 10.48
7 90 365 2 1.28 19.34 83.77 0.29 0.31 12.06 12.00 12.75 0.16 12.44
8 110 385 2 9.19 21.38 83.77 2.35 0.86 34.02 36.00 36.00 0.31 35.38
11 375 650 35 22.72 9.44 122.80 1.75 0.75 29.35 30.00 30.00 0.25 29.50
12 100 375 35 22.72 4.87 122.80 0.90 0.54 21.09 22.00 22.00 0.19 21.62
17 25 300 35 22.72 2.44 122.80 0.45 0.38 14.91 16.00 16.00 0.17 15.67
27 110 385 2 9.19 21.38 83.77 2.35 0.86 34.02 36.00 36.00 0.31 35.38
28 110 385 18 15.73 7.13 997.00 0.11 0.19 7.45 8.00 8.00 0.11 8.41
29 25 300 2 0.26 10.19 83.77 0.03 0.10 3.92 4.00 4.00 0.08 4.33
32 375 650 16.86 36.15 13.60 1040.00 0.47 0.39 15.27 16.00 16.00 0.17 15.67
40 25 300 16.86 36.15 3.51 1040.00 0.12 0.20 7.76 8.00 8.63 0.11 8.41
57 220 495 233.29 173.61 2.80 900.00 0.54 0.41 16.32 18.00 18.00 0.17 17.67
58 150 425 233.29 173.61 2.31 900.00 0.45 0.38 14.83 14.00 14.00 0.16 13.69
89
CHAPTER VI
WASTE MANAGEMENT
6.1 INTRODUCTION
In this production plant to produce aviation fuel from waste cooking oil (WCO), there
are a few types of wastes generated which are solid, liquid and gaseous waste. These
wastes can only be discharged after treatment to reduce the pollution towards
environment and public health. The waste generated from the plant is summarized in
the table below.
For improved productivity and a cleaner environment, the waste generated must be
monitored. The waste must be examined to guarantee that the final effluent of
wastewater released into the environment complies with government environmental
laws.
The waste is categorized into three different categories which are gaseous waste, liquid
waste and solid waste.
90
a. Gaseous Waste
The characteristics of gaseous waste generated are shown in the Table 6.2.
b. Liquid Waste
The liquid waste produced are shown in the Table 6.3 these wastes are also known as
wastewater.
c. Solid Waste
In solid waste, only impurities are present. Impurities stated here is from waste cooking
oil. The composition of the impurities is shown in the Table 6.4
The parameters that are taken into consideration are Chemical Oxygen Demand (COD),
Biochemical Oxygen Demand (BOD) and the temperature. Below shows the
wastewater composition and the summary of COD and BOD calculation in the Table
6.5 and Table 6.6.
The amount of oxygen required for the oxidation of all organic compounds in water is
known as Chemical Oxygen Demand (COD). If the COD value is high, it means the
sample contains a lot of oxidizable organic material, which reduces the soluble oxygen.
The COD value can be computed using the component concentrations in the
wastewater. The equation below is used to calculate the COD in wastewater.
Oxidation reaction of Decane: 2𝐶10 𝐻22 (𝑙) + 31𝑂2 (𝑔) → 20𝐶𝑂2 (𝑔) + 22𝐻2 𝑂(𝑔)
𝑛𝑂2 × 𝑀𝑂2
𝐶𝑂𝐷 = × 𝐶𝑜𝑛𝑐𝑒𝑛𝑡𝑟𝑎𝑡𝑖𝑜𝑛 𝑜𝑓 𝑐𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡
𝑛𝑐 × 𝑀𝑊 𝑐𝑜𝑚𝑝𝑜𝑛𝑒𝑛𝑡
Where,
52.20×1000×10000
𝐷𝑒𝑐𝑎𝑛𝑒: = 3389.10 𝑚𝑔/𝐿
1540.23×1000
93
31 × 32 × 3389.10
𝐶ℎ𝑒𝑚𝑖𝑐𝑎𝑙 𝑂𝑥𝑦𝑔𝑒𝑛 𝐷𝑒𝑚𝑎𝑛𝑑, 𝐶𝑂𝐷 = = 11814.69 𝑚𝑔/𝐿
2 × 142.28
The amount of carbon monoxide released from our waste gas streams is as follows: The
concentration of carbon monoxide releases from waste gas streams from our process as
below:
Concentration of CO emitted,
22.4 25 + 273.15 1
𝐶𝑐𝑜 = ( ) ( ) (5) = 3.12 𝑝𝑝𝑚
28.01 273.15 1.4
In Malaysia, the air pollution index is used to assess the potential for harm to
people and the environment if gas emissions exceed safety standards. The averaging
time in Table 6.8 of the Recommended Malaysian Air Quality Guidelines (Ambient
Standards, T=25oC and P=91.13kPa) represents the amount of time during which
96
measurements are monitored and reported for the assessment of human health impacts
of various air contaminants.
Table 6.8 Recommended Malaysian Air Quality Guidelines (Ambient Standards, T=250°C and
P=91.13kPa)
Pollutant Averaging Time Malaysia Guidelines
(ppm) (µg/m3)
Carbon Monoxide 1 hour 30 35000
8 hour 9 9000
Carbon Dioxide 8 hour 5000 90
Source: Department of Environment (1996)
Waste reduction is a waste management strategy that focuses on lowering the amount
of hazardous waste produced while also lowering its toxicity. Waste minimization is
also vital for environmental protection. By-products and surplus reactants that do not
fully react in reactions are considered waste. One of the reasons that prevents the
specification of the product required and is considered waste is the operational state.
Handling or regulating trash is riskier than minimizing or reducing waste. Waste
disposal is frequently costly; hence waste minimization should be considered in a
production operation to reduce costs. Waste minimization reduces the negative
consequences on the environment and human health. Some modifications should be
done in order to reduce waste.
In the production of aviation fuel from waste cooking oil plant, the waste emitted
by the process is the unreacted liquid waste that are cannot be reuse as a raw material.
Other than that, benzene and paraffin also exist as a liquid waste from the absorption
column and distillation column. In order to reduce waste emission, the unreacted
benzene can be recycling as a raw material needed in the process. The paraffin produced
can be further purified to be sell for other companies. In stream 37 produced waste that
contain triglycerides can be recycled to minimize waste discharge and reduce cost.
The other way to minimize the waste by increasing the retention time in order
to have higher conversion of product and reduce the unreacted component produced.
97
Moreover, the gas waste can be purged since the emission value meet the condition of
Malaysian Air Quality Guidelines, which is below 30 ppm.
Wastewater treatment plant to release the water used in the process of manufacturing
aviation fuel to the environment safely, consists of several processes. The wastewater
is treated by using primary and secondary treatment methods. The wastewater produce
needs to be treated until it fulfilled the discharge limit for BOD, COD. The unit includes
the equalization tank, skim tank, aeration tank, clarifier, sludge tank, and filter press in
the wastewater treatment plant. The wastewater treatment plant block diagram is shown
in Figure below.
Equalization tank is the first step for wastewater treatment in our plant. It is to minimize
and eliminate organic shock load besides stabilizing pH. Equalization tank minimizes
chemical treatment and flow surge to chemical treatment. Other than that, it is to reduce
number of toxic materials entering biological treatment system.
98
i. Design
Nearest volume 40 m3
Height = 2 m
Length= 2 m
Width= 10 m
iii. Efficiency
An efficiency of 55% removal for COD and 70% for BOD are taking for equalization.
b. Skim tank
The Skim tank act as an organic fuel-water separator as the mixture coming from the
equalization tank is a mixture with two layers. Thus, the separation will be using
physical separation, which is separation based on gravity difference. The organic
substance will rise at the top sludge will be settled at the bottom of the tank, and
99
wastewater leaving in the tank's middle layer. The reduction at this stage is 99% of
removal oil, 45% COD and 40% BOD and gives the outlet discharge shown. The
calculation for the designed skim tank is shown below.
i. Design
Where,
ρw = 1000kg/m3 at 30°C
ρo = 361.1 kg/m3 at 30 C
ii. Dimensions
Choose depth, d = 2 m
Width, w = 10 m
A= d x w = 20 m2
Horizontal velocity, U
iii. Efficiency
An efficiency of 55% removal of COD and BOD are taken to the skim process
Aeration tank function to reduce chemical oxygen demand (COD) and biochemical
oxygen demand (BOD) in a waste management system aeration tank function. Aeration
tanks use bacteria to oxidize organic substances in wastewater, which will reduce the
COD and BOD. It promotes the growth of bacteria by the quantity of food and oxygen
supplied in the wastewater. In the aviation fuel, production plant wastewater, the most
contributed COD and BOD are Decane, Petrol and Paraffin. The design calculation is
shown below:
i. Design
𝑘𝑔
1186.362
ℎ𝑟
Q= 𝑘𝑔
1000 3
𝑚
Q = 1.187608 m^3/hr
V = 72 h x 1.187 m3/hr
ii. Dimension
iii. Efficiency
Clarifier used to remove heavier sludge solids by settling and being separated from the
liquid. The settled solids or sludge are directed towards the center by using a collection
scrapper. The treated effluent will at the top be separated from sludge produce. The
design of the clarifier depends on the surface of the tank and the time of water retained
in the systems.
i. Design
Q = 1.1865.46 m3
Volume = 6h x 1.186 m3
= 7.116 m3
𝑉
Height of tank, H = 𝜋𝑟 2
= 7.116 / 3.142 x r2
= 0.92
ii. Dimensions
Height,h = 1 m
Radius,r =2.45 m
103
iii. Efficiency
The most common unit that is used for thickening the sludge is by using gravity sludge.
All the sludge forms will be collected in a tank to let it settle and compact at the bottom
by gravity, and then the sludge will be discharge from the bottom of the tank to the filter
press. The sludge is collected once a day.
i. Design
ST = 4 m3/h
𝑉 = 𝜏𝑥𝑄
= 4(6)
= 24 m3;
HRT, t = 6h
ii. Dimensions
Length, L = 2 m
Width, W = 2 m
104
Height, H = 6 m
Efficiency
b. Filter
Filter press is operating 22 hours a day and Q = 40 m3/hr. The amount of sludge
collected room the wastewater treatment is assuming as 2.0% from suspended solid,
0.2% from flocculation tank and 0.2% from aeration tank. From Table 57 below, 40 cm
width of belt is used for filter press capacity (International Dehydration Equipment Co.
Ltd. 2012).
i. Design
=0.96 m3/hr
= 21 m3
The summary of design dimension for all wastewater treatment units is shown in Table
58 below.
Table 6.10 The summary of design dimension for all wastewater treatment units
Treatment Unit Dimension Value
Equalization tank Width 10 m
Height 2m
Length 2m
Skim tank Height 2m
Length 2m
Width 10 m
Aeration Tank Height 5.5 m
Length 3m
Width 5.2 m
Clarifying Tank Radius 2.45 m
Height 0.92 m
Sludge Tank Width 2m
Length 2m
Height 6m
The wastewater treatment plant after production of decane will bw shown in Appendix
F.
106
CHAPTER VII
ECONOMIC ANALYSIS
7.1 INTRODUCTION
In chemical plant, was built to gain a profit and an estimate of the investment required
is needed before gain a profit. Economic analysis is one of important factor in designing
a plant which helps to determine the feasible the plant that will be in commercial level.
It also can calculate and shows how many years is needed to get the profit. In order to
fulfill the criteria, economy analysis have to be calculated. This section will discuss
about the profitability analysis by calculate the payback period, return on investment,
net present value (NPV), internal rate of return and discounted cash flowrate rate of
return (DCFRR).
The start-up of industrial plant needed a large amount of money to be prepare. The usage
of money for purchase and installed needed equipment, building and other facilities.
The large amount of money will be used to several factor like purchase and install
equipment, utility services, construction building and more the amount of investment
can be estimated through the calculation of the total capital investment. The factor
include in calculation of capital investment is fixed capital investment, working capital
and capital purchased land. Capital investment calculation can be simplify based on the
formula below.
Amount of money that need to be invested for starting plant is fixed investment capital.
This investment divided into two component which is manufacturing fixed capital
investment and non-manufacturing investment. Manufacturing fixed investment is
known as direct cost that necessary for installed process equipment and all component
needed in process operation. Meanwhile, non-manufacturing fixed capital investment
as indirect cost that refers to component that not directly related to manufacturing and
construction overheads. To calculated cost fixed investment can be calculated through
the summation of direct cost estimation and indirect estimations. The table below shows
component in section of manufacturing and non-manufacturing for process operation.
The calculation and description for direct and indirect cost is below section.
Direct cost and indirect cost calculation can be done based on purchased equipment
cost. The estimated purchased equipment cost is related to the following formula which
is.
𝐶𝑒 = 𝑎 + 𝑏𝑆 𝑛
S = Size parameter
The constant value of a b and n is referred to the Towler & Sinnott (2013) .
Other than that, the value used as installation factor also stated in the same book
Meanwhile the size parameter based on sizing each equipment used in our production
plant and there are range each equipment sizing. From the calculation result cost of the
past time and the cost at the present time can be determined by multiplying the original
cost by the ration of the present index value to the index value applicable. The equation
of equipment cost as time function is shown below and the value of index was estimated
from the (Marshall Swift Valuation Services 2018). Since the purchased equipment cost
is 2010, thus the index value is 1695.1 and at present time is 2021 which is 2217.3.
Table 7.2 shows a summary of purchased equipment and installation cost for all plant
equipment in our production.
b. Direct cost
The cost value from purchased cost will be used to calculate direct cost. The direct cost
comprises calculation of all components that are needed for complete process operation
such as instrumentation and controls, piping, electrical system, building, yard
improvements and service facilities. The percentage uses for purchased equipment has
stated in Plant Design and Economics for Chemical Engineers (1920). The table below
shows summarized the cost value for direct costs estimation.
c. Indirect costs
Same as direct cost, this cost is estimated based on purchased equipment cost by
multiply with percentage of equipment cost. Each indirect cost has different percentage,
110
and this percentage is mostly affected by the size of the plant and other. The Table 7.4
shows summarized calculation cost for indirect cost.
From the calculation have been calculated therefore, the fixed capital investment
for our plant is RM 91.092 M. Calculation of fixed capital investment shows as below
= RM 60.87 M + RM 22.224 M
= RM 83.094 M
Land capital is the most important cost involved in building a plant. The selected plant
location at Pasir Gudang, Johor with the price Rm 50 per square feet and we decided to
get size of the plant is 435600 square feet. The below calculation is the land capital cost.
= RM 21,780,000
= RM 22 million
111
Working capital is the additional investment that needed for start the plant up. This
additional amount of money has to be invested in for the raw material and supplies to
be kept as stock, accounts receivable, finished product in stock and semi-finished
materials in the process of being manufactured, cash kept on hand for monthly payment
of operating expenses, and also tax payable. Set point for the working capital is 20% of
total fixed capital investment for our plant design (Towler & Sinnott 2013). However,
in the calculation there are some unknown that call as total capital investment. It can
calculate based on the derivation of formula below
𝐶𝑊𝐶 = 0.2𝐶𝐹𝐶
(𝐶𝐹𝐶 + 𝐶𝐿 )
𝐶𝑇𝐶 =
0.8
= 20% X RM 83.094 M
= RM 16.6188 M
= RM 17 M
The total product cost is related to the cost of operation of the plant, selling product, price
of raw material and other. This estimation cost is divided into two categories which is
manufacturing cost and general expenses. Basically, total product cost is the sum of two
component which comprises the general expenses in the plant and the manufacturing cost.
CTPC = COM + GE
Where,
GE = General expenses
Manufacturing cost is required in production and processing the main product of the
palnt which is decane. Manufacturing cost can be classified into three categories which
is direct manufacturing costs or variable production costs, fixed charges or fixed
manufacturing costs, and plant overhead costs. Below equation is the calculation that will
be used to find cost of manufacturing.
Where,
Direct manufacturing cost are the expenses that directly involved in the production of
products. DMC value also is depending on the rate of production. There are some cost need
to consider when calculating the direct manufacturing cost. The section below was the cost
need to consider in direct manufacturing cost.
i. Raw material
The cost of raw material is calculated based on our production rate which is 10232.28
kg/hr for decane. The Table 7.6 shows the feed flowrate and calculation annual cost
each raw material in our plant.
ii. Utilities
Based on Towler & Sinnott, (2013) utilities cost usually covered about 10% to 20% of
the total product cost. Steam, compressed air, electricity and cooling water is each
component for cost utilities. Thus, we decided to assumed our plant utilities cost to be 10%
and the formula as below.
This section was divided into two categories which are skilled labor and unskilled labor.
To determine the operating labor cost, Ulrich method has been chosen. Meanwhile hourly
wage rate for operating labor is obtained from the Labor Department of the Ministry of
Human Resources. The Table 7.7 shows operating per shift based on equipment type in
our plant.
The basic average salary in Malaysia was range RM 1500 to RM 2000 per month
(tarrence tan 2021). The Table 7.8 shows the labor cost estimation per year.
In manufacturing operation, there are certain amount of direct direct supervisory and
clerical assistance is required. This amount cost for supervisory and clerical assistance is
related to the complexity of the operation and product quality standards.This type of cost
estimated covered about 15% of the total cost for operating labor. Calculation for this
type is shows as below:
= RM 135,000.00
Range of the total cost maintenance and repairs for chemical plant is about 2% to 10%
from the fixed capital investment (CFC). We decided to estimate our total cost
maintenance and repairs is cover about 6%. Below is calculation for our cost
maintenance and repairs.
Operating supplies are the consumable items such as charts, lubricants, test chemicals,
custodial supplies and similar supplies which cannot be considered as raw materials or
maintenance and repairs. The annual cost for type of supplies is 15% of the cost
maintenance and repairs. Calculation shows as below:
116
= RM 819, 825.00
Laboratory expenses involves the test for control of operations, product quality control
and improvement of the current product. The cost may be taken as 10% to 20% of
operating labour. For laboratory expenses in our plant is about 10% and calculation
show as:
= RM 90,000.00
In our production plant, catalyst is required in the reactor for our chemical reaction. Cost
for catalyst and solvents are important and should be estimated based on catalyst
requirement and price for the process. The cost for this type is about 6% of the total cost
for raw material.
Patents covers many products and manufacturing processes. Patents are the payment
due to usage of process that is developed by other company or person. It necessary to pay
for the patent rights or royal. A rough approximation of this cost is 0 to 6% of the CTPC
and for our production plant is 2%.
x. Summary
Fixed charge which is also known as fixed costs are the costs that change in little or not at
all with the amount of production in the plant. Financing cost is the interest payable for the
capital obtained by borrowing from financial institutions. Meanwhile local taxes are the
magnitude of local property taxes depends on the locality of the plant and regional laws.
For insurances rates it depends on the type of process being carried out in the manufacturing
operation The table below shows the estimation of FMC of our production plant.
118
Plant overheads costs are expenditures required for routine general plant service whereby
non-manufacturing machinery, equipment and buildings are required to provide such
services. The range for this PO is about 50% to 70% of the total expenses for operating
labor, supervision, and maintenance.
General expenses are the cost that is related to the management and administrative level
which is not directly involved to the manufacturing process. It may be classified into
three categories which is administrative expenses, distribution and marketing expenses,
and research and development expenses. Table 7.11 shows the summary of GE for our
production.
7.4 DEPRECIATION, AD
Depreciation is a measure of the decrease in the value of an asset over time. There are
several methods for depreciation, and we decided to used method straight-line to determine
our depreciation value. In this calculation the value of scrap value is 0% after 25 years. This
scrap value has been stated in Chemical Process (2012) since for chemical plant does not
sell the unit process in production plant. The annual depreciation charge is given:
𝐶𝐹𝐶 − 𝑆
𝐴𝐷 =
𝑛
Where,
Thus, from calculation the depreciation cost for the plant is RM 3.324 Million
120
There are two types of profitability analysis for a development project which are
the techniques that do not consider the time value of money and methods that do
consider the time value of money. The project's success is totally dependent on sales,
taxes, depreciation, and operational expenses.
7.5.1 The method that does not consider the time value of money.
Net profit for our project is typically not consistent from 1st year to 25th year, and total
investment fluctuates if further investments are made throughout project operation.
121
Thus, the ROI for a project is calculated as an average across the project's life cycle,
and the equation to be employed is:
1
(𝑛) ∑𝑛𝑗=1(𝑁𝑃𝐽 )
𝑅𝑂𝐼 =
∑𝑛𝑗−𝑏 𝐶𝑗
Where,
ROI = Annual return on investment
𝑁𝑃𝐽 = Net profit for the year j
𝐶𝑗 = Amount of investment made for the year j
n = Design life of the project
Following that, the calculated ROI, 0.21 is compared to a rate of return value
known as the Minimum Acceptable Rate of Return (MARR), which is denoted by the
sign mar. According to Table 7.13, the project's minimum acceptable rate of return,
mar, is set at 10% because the range of new capacity plant with established corporate
market position is between 8% - 16%.
Payback Period (PBP) or pay out period is a profitability ratio that measures the time it
takes for the total return to exceed the initial invested. The strategy is predicated on the
idea that the sooner fixed capital is returned, the better the enterprise. The following
equation is used to calculate the initial fixed capital investment and the annual cash
flow:
𝑉 + 𝐴𝑥
𝑃𝐵𝑃 =
𝐴𝑗
Where
The PBP reference might well be calculated using the equation below, which
can then be used as a parameter to compare the PBP calculated above. If the project's
PBP will be less than PBPref, the project is considered as acceptable.
123
0.85
𝑃𝐵𝑃𝑟𝑒𝑓 =
0.85
𝑀𝐴𝑅𝑅 + 𝑛
Where
n = Number of years
The PBPref is calculated and get a value of 6.34. By comparing the calculated
PBP and 𝑃𝐵𝑃𝑟𝑒𝑓 , the value of PBP calculated is less than PBPref. Then, the plant is
acceptable.
c. Net Return, Rn
The amount of cash flow required to obtain the minimal acceptable return rate and
return the total capital investment is more than the amount of cash flow required to
achieve the net return. The formula for calculating the net return is as follows:
𝑛 𝑛
𝑅𝑛 = ∑ 𝑁𝑝, 𝑗 − 𝑚𝑎𝑟𝑟 (𝑛 ∑ 𝐶𝑗
𝑗=1 𝑗=−𝑏
Where
The calculated value of net return in this plant is RM 629.08 million. The
positive net return value means that the cash flow to the project currently higher than
the amount required to repay the investment and earn a return that satisfies the minimum
reasonable rate. The project profits at a rate higher than the margin
125
21 1.00 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 598.339
22 1.00 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 632.7215
23 1.00 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 667.104
24 1.00 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 701.4865
25 1.00 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 735.869
TOTAL 735.869 8027.44
AVERAGE 54.48 594.28
ROI 0.21
PBP 2.9
Rn
629.08
127
The time value of capital, Net Present Value (NPV) and Discounted Cash Flow Rate of
Return are considered by two techniques (DCFRR). The discount factor for both
methods should be determined by using the equation below:
1 1
𝑓𝑑𝑖,𝑛 = =
𝑓𝑖,𝑛 (1 + 𝑖)𝑛
The current total value of a cash flow time series is defined as the Net Present
Value (NPV). If Mar is positive for a project's NPV value at the lowest acceptable rate
of return, the project is considered to have a higher return than Mar and is desirable.
The NPV value of the project is calculated using the calculation below.
NPV =∑𝑁 𝑁
𝑗=1 𝑓𝑑𝑖,𝑗 [𝐴𝑗 + 𝑟𝑒𝑐𝑗 + 𝑑𝑗 ] − ∑𝑗=1 𝑓𝑑𝑖,𝑗 𝐶𝑗
Where
𝑓𝑑𝑖,𝑗 = Selected present worth factor for the cash flows with interest rate I in year j
Table 7.15 show the estimation of the NPV value of this project. The NPV value for
this project at a minimum acceptable rate of return, MARR = 0.1 is RM 75.47 million
which is positive. Then this project is to earn a return greater than MARR and
acceptable.
The return gained from an investment in which all investments and cash flows are
discounted is known as the discounted cash flow rate of return, or DCFRR. The value
of the interest rate, I such that NPV = 0 is obtained using this procedure. The discounted
cash flow rate of return, or DCFRR, is calculated in
129
21 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.14 4.65 179.88
22 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.12 4.22 184.10
23 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.11 3.84 187.94
24 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.10 3.49 191.43
25 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.09 3.17 194.60
NPV 75.47
14 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.26 9.05 135.80
15 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.24 8.23 144.03
16 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.22 7.48 151.51
17 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.20 6.80 158.31
18 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.18 6.18 164.50
19 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.16 5.62 170.12
20 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.15 5.11 175.23
21 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.14 4.65 179.88
22 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.12 4.22 184.10
23 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.11 3.84 187.94
24 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.10 3.49 191.43
25 1 83.09 131.73 48.64 3.64 45.00 11.25 30.74 34.38 0.09 3.17 194.60
DCFRR 31%
132
The breakeven point, which is 0.9 years, is calculated using the total income and
total expenditure in the design plant at full capacity, as illustrated in the diagram
below. Based on figure 7.1, the profit start to increase after 1 year because the
production start to produce at a full capacity. To conclude, a production does not
make a profit or a loss at the breakeven point. As a result, the break-even point is
sometimes known as the "no-profit" or "no-loss" position.
The plant capacity of the main product, Decane is 100585.97 tonnes/year. Based
on the specific breakeven analysis in Figure 7.2 Specific Breakeven analysis, the
133
Sensitivity analysis is a financial model that analyzes how changes in other factors,
known as input variables, influence target variables. By employing the Microsoft Excel
function "Data Table," this model is also known as a what-if. It is a method of predicting
the result of a choice based on a set of factors. An analysis can identify how changes in
one variable impact the outcome by generating a collection of variables.
Based on our analysis, a suitable selling price for Decane can be calculated as RM 6.60
per kg, considering the capacity of Decane, which is 1232035 kg/year. The sensitivity
analysis for Decane is shown in Table 7.17
Based on our analysis, a suitable selling price for Petrol can be calculated as RM 5 per
kg, considering the capacity of Petrol, which is 621007 kg/year. The sensitivity analysis
for Petrol is shown in Table 7.18.Table 7.19 Summary of sensitivity analysis Petrol
Based on our analysis, a suitable selling price for Propane can be calculated as RM 3.25
per kg, considering the capacity of Propane, which is 10675288 kg/year. The sensitivity
analysis for Propane is shown in Table 7.19
Based on our analysis, a suitable selling price for Paraffin can be calculated as RM 4.5
per kg, considering the capacity of Paraffin, which is 34760959 kg/year. The sensitivity
analysis for Paraffin is shown in Table 7.20
Direct
Total
Depreciation Working Capital Land Capital Manufacturing
Production Cost
Cost
25% increment 4.55 27.50 108.89 164.66 22.50
25% decrement -2.73 -16.5 -65.3325 -98.7975 -13.5
25% increment 25% decrement
CHAPTER VIII
8.1 INTRODUCTION
Safety is one of the crucial aspects that must be consider in any industrial facilities. This
is because the consequences of hazards and incidents affect more than people and
property on the factory floor. Fires at work, missed days due to injuries or chemical
hazards can affect your production output, which can delay delivery schedules,
fulfillment, vendor relationships and customer satisfaction. Practicing good industrial
safety is the best way to ensure smooth operations that have the best interests of
employees, vendors and customers at heart. Industrial safety plays a major role to
prevent workplace hazards, including chemical exposure, poor ergonomics and physical
hazards so that business can continue as normal without disruption to production. In
this chapter, we will identify the possible hazard and also will further discuss the
legislative requirement regarding our plant. In addition, we will also elaborate on the
preventive steps or measures to reduce or eliminate the hazards.
To ensure the safety of the public, property and the environment, the government has
enacted regulations and act for every industrial category in Malaysia. Department of
Environment (DOE) and the Department of Occupational Safety and Health (DOSH) is
the body that responsible for measuring and ensuring compliance with the act and
environmental quality standards. In order to operate any plant, we must first comply
and obtain permission from them.
137
OSHA 1994 defines the general duties of employers, employees, the self-
employed, designers, manufacturers, importers and suppliers of plant or substances. The
Act provides a comprehensive and integrated system of law to deal with the safety and
health of virtually all people at work and the protection of the public where they may
be affected by the activities of people at work. In part IV of OSHA 1994, it stated the
general duties of employers and self-employed persons. “It shall be the duty of every
employer and every self-employed person to ensure, so far as is practicable, the safety,
health and welfare at work of all his employees” and “It shall be the duty of every
employer and every self-employed person to conduct his undertaking in such a manner
as to ensure, so far as is practicable, that he and other persons, not being his employees,
who may be affected thereby are not thereby exposed to risks to their safety or health.”
This emphasize that as an employer, we not only have to ensure the safety of our
workers but also other people that maybe exposed to the risk. In order to ensure the
employees safety, we can provide information, instructions, training and supervision to
138
ensure safety and health such as handling reactor that operates in a high pressure and
temperature while to persons other than their employees, we have to conduct our
activities, so far as is practicable, that others are not exposed to risks of their safety and
health.
FMA 1967 is an Act to provide for the control of factories with respect to matters
relating to the safety, health and welfare or persons therein, the registration and
inspection of machinery and for matter connected therewith. As stated in part II, safety,
health and welfare, section 18, machinery for hire or sale must comply with regulations.
“No person shall sell or let on hire any machinery other than transmission machinery
which does not comply with any regulations made under this Act applicable to the
machinery.” It is important to make sure to ensure that all the machinery that we will
used in our plant such as reactor, distillation column, gas absorption comply with any
regulations made under this Act applicable to all machinery.
caps, foot-wear and protective ointment or lotion. This is as protection to a person while
handling a risky situation.
Considering that we will produce jet fuel, so there is also waste that contain oil.
We can’t discharge our waste into any river, lake or ocean. In section 27, there is
prohibition of discharge of oil into Malaysian water where, “No person shall, unless
licensed, discharge or spill any oil or mixture containing oil into Malaysian water in
contravention of the acceptable conditions. We must take a good care while treating our
waste containing oil because it will cause a severe pollution to the environment and also
will cause fires and explosions that will result in death of many lives.
In our production, there are some chemicals that identified as hazardous material such
as flammable, irritation, toxicity, corrosive, explosive or hazard to environment. The
identified of hazard will analyze which material is hazard and need to take more caution
when handle. Table 8.1 below shows the chemical hazard identification.
141
Paraffin -Flammable -Highly flammable liquid and vapor -Keep away from heat/sparks/open flames/hot surfaces.
-Wear protective gloves/protective clothing/eye protection/face
protection
Carbon -Flammable -Extremely flammable gas. -Close valve after each use and when empty.
Monoxide -Health hazard -Contains gas under pressure; may explode if heated. -Use equipment rated for cylinder pressure.
-Toxic -Toxic if inhaled. -Do not open valve until connected to equipment prepared for use.
-Skin irritation -May damage fertility or the unborn child. -Use a back flow preventative device in the piping.
-Compressed gas -Causes damage to organs through prolonged or -Use only equipment of compatible materials of construction.
repeated exposure -Approach suspected leak area with caution.
-Asphyxiating even with adequate oxygen.
-May form explosive mixtures with air.
Waste cooking Not classified as a - -
oil hazardous chemical.
Water Not classified as a - -
hazardous chemical.
143
From the hazard identification, most of our chemicals are hazardous materials
in this plant. Therefore, a lot of precautions need to follow to make sure any accident
can be prevented.
Occurrence of the unwanted event is due to the realization of a hazard system. A hazard
system mainly consists of 4 elements which is hazard source, receptors, transmission
paths and barrier. A source has the capacity to be realized at many different levels of
severity. The effect from realization of a hazard system may be chronic or acute.
Receptors is the suffer harm due realization of hazard. There are two types of receptors
which are voluntary receptor and involuntary receptor. A receptor may be a receptor for
more than one source. Transmission path is a medium via which the consequence of a
hazard is “transfer” from the source to the receptor while barrier is a physical and non-
physical means planned to prevent, control, mitigate undesired event or accident.
In our production, we use waste cooking oil as the raw material and our process will
operates at high temperature and pressure. The product which is the jet fuel, petrol and
propane gas will be stored in the warehouse. There are other industries, residential area,
school and other facilities are located nearby our plant location which is at Tanjung
Langsat Industrial Complex. Since all the raw material, the process, and the product in
our plant has the potential to cause harm, thus it is essential to identify the hazards and
reduce the risk well in advance of an accident. Table 8.2 below shows the hazard system
for our plant.
144
Packed bed reactor, Personnel Nearby residents, residential Explosion due Bund wall surrounding Schedule maintenance/inspection, safety
R-101 and R-102 workers community, neighboring to a storage tank and training, hazard signage, insurance to
operating at pressure companies, commercial and overpressure explosion proof protect workers and property
40 bar government workers, and control room
environment
Gas absorption, G- Personnel Nearby residents, residential Dispersion of Fire extinguisher, Schedule maintenance/inspection, safety
101 that containing workers community, neighboring propane gas in emergency & training, hazard signage, insurance to
propane companies, commercial and the air shutdown facility protect workers and property
government workers, and
environment
Distillation column, Personnel Nearby residents, residential Dispersion of Fire extinguisher, Schedule maintenance/inspection, safety
D-101, D-102, D- workers community, neighboring methanol gas emergency & training, hazard signage, insurance to
103 and D-104 companies, commercial and in the air, shutdown facility protect workers and property
containing mixture of government workers, and thermal
oil environment radiation
145
The priorities of HIRARC implementation are to identify all of the factors that
may cause harm to employees and others (the hazards), to consider what the chances
are of that harm actually falling on anyone in the circumstances of a specific case and
the potential severity that could result from it (the risks), and to enable employers to
plan, implement, and monitor preventive measures to ensure that risks are adequately
controlled at all times (Ahmad et al 2016).
According to the Table 8.3, Table 8.4, Table 8.5 and Table 8.6 the hazard is
directly related to the risk. Risk is a scale used to analyse and assess hazards. The
measurement is made by determining how serious the hazard is and when it is likely to
occur. In other words, risk assessment is a thorough examination of circumstances,
processes, and other potentially hazardous actions or hazards in the workplace (Ahmad
et al 2016). Risk is communicated in several methods to express the distribution of risk
throughout a plant and workplace environment (Ahmad et al 2016). The findings of risk
assessment, as provided in a risk matrix, are critical for making risk control decisions.
According to the table below, risk may be assessed using the following formula:
146
The risk (R) is equal to the likelihood (L) multiplied by the severity (S)
In our project, we use packed bed reactor that function can be used in chemical process. These tubular reactors are packed with solid catalyst
particles and are often used to stimulate gas processes/ The chemical reaction occur on reactor, R-101 are triglyceride react with the hydrogen
gas producing propane gas and paraffins. According to the MSDS, the product from the reactor, R-101 not too hazardous.
Fail to pump Possible to occur 3 May cause spillage 2 6 Perform schedule inspection Install leakage sensor
triglyceride to the and not permanent Medium and maintenance on efficiency system.
reactor injury occur. pump.
Fail to pump in Possible to occur 3 May cause gas 2 6 Perform schedule inspection Install gas leakage
hydrogen gas to leaking but not Medium and maintenance on efficiency detector system.
the reactor. permanent injury pump.
occurs.
Gas absorption was used to separate propane gas from waste gas by using benzene as solvent. Propane gas not a toxic gas but it is an asphyxiating
gas.
Overtemperature Might be occur 3 Propane gas is not a 5 15 -Perform schedule -Installation of the
inside gas in the future. toxic gas but inhaled a High inspection and maintenance temperature alarm.
absorption may significant amount of (Corrective, preventive, -Monitor the
cause overheating propane or high risk-based and condition – temperature alarm
and explosion. concentration can led to based maintenance) on frequently.
the difficult/impossible temperature controller.
breath. -Perform a safety training
for workers to overcome the
hazard.
In the reactor (R-102), paraffin will react to the hydrogen gas and produce, decane, petrol, water, and carbon monoxide.
Pipeline leakage (Gas Has a good chance 5 -May cause toxic 4 20 Schedule inspection -Installation of gas
Outlet) of occurring and is gas leaking. High and maintenance on leakage detection
not unusual. -Pollution inhalation the pipe frequently. system.
-Choose suitable -Follow
material for pipeline emergency plan.
to avoid leakage.
Pipeline leakage Has a good chance 5 -Flammable 4 20 Schedule inspection -Installation of gas
(Liquid Outlet) of occurring and is product. High and maintenance on leakage detection
not unusual. -Chemical spillage. the pipe frequently. system.
-Choose suitable -Follow
material for pipeline emergency plan
to avoid leakage.
valve monitoring
app as an example
Siemens.
High temperature inside Might be occur in 3 Numerous fatalities, 5 15 -Perform schedule -Installation of the
distillation may cause the future. irrecoverable High inspection and temperature alarm.
overheating and property damage maintenance -Monitor the
explosion of the D-103. and productivity (Corrective, temperature alarm
preventive, risk-based frequently.
and condition – based
maintenance) on
temperature
controller.
-Perform a safety
training for workers
to overcome the
hazard.
Internal corrosive of Has not been 2 -May cause leaking 5 10 -Choose suitable Ensure no ignition
distillation column wall known to occur and flammable Medium material to overcome source nearby.
led to the rupture. after many years chemical. or decrease corrosive Follow SOP and
-Air pollution effect. Emergency plan.
-Regular maintenance
Valve malfunction Might be occur in 3 -Overflow mixture. 4 12 Implement scheduled -Install low/high
the future. -No or fewer flow Medium inspection and level alarm.
mixture maintenance. - Monitor the
valve by using
valve monitoring
app as an example
Siemens.
Internal corrosive of Has not been 2 -May cause leaking 5 10 -Choose suitable Ensure no
distillation column wall known to occur and flammable Medium material to ignition source
led to the rupture. after many years chemical. overcome or nearby.
-Air pollution decrease corrosive Follow SOP and
effect. Emergency plan.
-Regular
maintenance
Valve malfunction Might be occur in 3 -Overflow mixture. 4 12 Implement -Install low/high
the future. -No or fewer flow Medium scheduled level alarm.
mixture inspection and -Monitor the
maintenance. valve by using
valve monitoring
app as an
example Siemens.
157
Based on the HIRARC result, there are two major risk that can considered as high risk
at mostly unit operation which are overpressure and overheating that should be assess.
With a risk rating 15, it can cause irrecoverable property damage and numerous
fatalities for the hydrocracking and hydrotreating process especially at reactor. The risk
can be controlled by installing the high alarm for pressure and temperature to increase
the safety and alert among workers. Next, pipeline leakage can also cause highest risk
with rating of 20 because the chemical spillage can endanger the environment with the
pollution and the random and contamination mixed chemical spillage can cause the
explosion. To overcome this hazard, suitable material to avoid leakage and perform
schedule inspection and maintenance about corrective, preventive, risk- based and
condition. Every worker also needs to undergo a safety training to overcome the hazard.
The parameters of an operational reactor and other unit must be managed to obtain a
decent result as well as avoid having undesired products that might pose a problem.
Even if it is a less essential procedure, safety measurement should be evaluated from all
angles since it might function as one of the receptors for an injury incidence. The
HIRARC studies for minor unit operations such as filter (F-101), Stripper (G-102), heat
exchanger (J-101) are shown in Appendix G.
Low Low flow of raw Valve partially closed Low production None Schedule inspection and
material into reactor Pipe partially blocked rate maintenance
Longer time to fill Install flow controller
the reactor to
desired volume.
High High product flow into Valve failed opened Pipeline rupture or None Schedule inspection and
reactor cause leakage maintenance
Install high level alarm
No No product flow to Valve failed closed Process cannot be None Scheduled inspection and
next process Pipe blocked proceed maintenance
Total ruptured of the Reactor become
pipeline overpressure
Pumps fail to operate
HAZARD AND OPERABILITY STUDY REPORT
Low Low level inside Pipe partial clogged & Overheating in None Schedule inspection and
reactor leakage reactor maintenance
High High level inside Output pipe blockage Overflow inside None ▪ Schedule inspection
reactor reactor and maintenance
▪ Install level
controller
Less Less pressure in Blower before enter -Low Pressure Schedule inspection and
output liquid production rate controller maintenance
stream reactor failed to operate
-Incomplete
Pressure control valve reaction
failure
High High pressure in Pressure control valve -Vessel or -Pressure relief -Schedule inspection and
output liquid failure. pipeline valve maintenance
stream rupture
-Pressure -Install high pressure
-Explosion controller alarm
High High temperature ▪ Cooling water tank ▪ Explosion of ▪ Temperature ▪ Schedule inspection
of cooling water temperature detector reactor occur • controller and maintenance
broken Pipeline
around the ▪ Install high
reactor rupture temperature alarm
▪ Emergency shutdown
system
164
Low Low temperature in Valve cooled water failed Low ▪ Temperature ▪ Schedule inspection and
inlet stream opened controller maintenance
production
rate
Incomplete
165
reaction
High High temperature Valve cooled water failed Vessel or ▪ Temperature ▪ Schedule inspection and
in inlet stream closed pipeline controller maintenance
rupture
▪ Install high temperature
alarm
166
inside reactor
High High pressure Outlet flow is too • Lead to vessel • Pressure • Schedule
inside reactor low or pipeline relief inspection and
rupture. valve maintenance
• The desired
product Pressure Install high pressure
unachievable. controller alarm
Release of flammable
biogas cloud
Less Low temperature of Heat inside reactor is not The pipeline become Temperature Schedule inspection and
flowrate from the working cold and danger to controller maintenance
reactor touch by hands Install low temperature
alarm
High High temperature of Cooling water at reactor not Overheat or damage to Temperature Schedule inspection and
flowrate from the working well the pipeline controller maintenance
reactor Install high temperature
alarm
171
No No product flow to the next • Pipe blocked • Process cannot be proceed • Temperature • Scheduled inspection
process • Pipeline is • Reaction cannot occur inside controller and maintenance
ruptured reactor • Install flow indicator
• Temperature inside reactor
increase
Low Low flow of raw material • Valve • Low production rate • Temperature • Schedule inspection and
inside reactor partially • Temperature inside reactor controller maintenance
closed increase • Install flow controller
• Pipe partially
blocked
172
High High product flow inside • Valve failed • Pipeline rupture or cause • Temperature • Schedule inspection and
reactor opened leakage controller maintenance
• Temperature inside reactor • Install flow meter
become low
173
Low Low level inside reactor • Pipe partial • Overheating in reactor None • Schedule inspection and
clogged and maintenance
leakage
High High level inside reactor • Output pipe • Overflow inside reactor None • Schedule inspection and
blockage maintenance
• Install level controller
174
CHAPTER IX
PLANT LOCATION
9.1 INTRODUCTION
A plant should be located at a place where inhabitants are interested in its success,
the product can be sold profitably and production cost is minimum. A plant location
is often result of compromise among conflicting social, economic and geographical
conditions. A proper decision must be made wisely for future planning because it will
have a long-term positive or negative effect on the production process. There are many
factors that need to be evaluated when selecting a suitable location. There are three
main locations that have been shortlisted to be conceived as the most strategic site
location in Malaysia. All proposal site was been obtained in Federation of Malaysian
Manufacturing (Manufacturers 2018)The proposed location is:
The geographical location of the final plant can have a strong influence on the
success of an industrial venture. Great care must be taken in choosing a plant site, and
many varied factors must be considered. Especially the plant must be located where
minimum production and distribution costs can be obtained but other factors such as
space for expansion and safe living conditions for plant operations as well as the
surrounding community as well important. The location of the plant can also have a
significant impact on the profitability of a project. The selection of the final site should
176
4. Transport facilities.
5. Availability of labors.
9. Climate.
Tanjung Langsat Industrial Complex is one of few industrial park that located in
southern Malaysia. This location site specifically designated for heavy industries and
there also already several heavy industries built at this site. For our production that
involves with palm oil thus, it very suitable with target market this site which wanted
palm oil and chemical industries. The industrial area can be accessed by two roads
177
linking which is Highway Senai – Desaru about 4 km from the site and Jalan Persiaran
Tanjung Langsat with road code E17. For transportation, there are several which is it
near to Senai International Airport within 59km, and since this site located near to the
port thus the distance between Tanjung Langsat Port is on 0.5 km. Besides, it near to
Johor Port within 16 km which will easy facilitate the delivery production to the
international level. Furthermore, this Johor port one of the largest port in Malaysia to
import local product to international. In terms of utility, this industrial area was
supported by the power supplied from Tenaga Nasional Berhad Johor (TNB) and there
are small power supplies at this area that known as PMU TLIE under Perindustrian
Tanjung Langsat (2.5 km away from site). For availability of water supplied by Syarikat
Air Johor, Pasir Gudang 9 km away from the site and well internet accessibility. The
below Table 9.1shows the water tariff for this industrial site.
Labor availability has high population where there are many household
settlements nearby. For example, Taman Kota Masai (5km), Kampung Tanjung Langsat
(3km) and Taman Tanjung Puteri (8km). In this area location also provided centralized
worker’s hostel easier for workers who live far away. The climate at this location is fine
even though it is near the port. However there some incident happened near TLIC area
which was an explosion of gasoline in 2006. This blast occurs at 6.30 p.m. after work
in TLIC area and away from residential areas. Unfortunately, this incident occurs in
2208 with the same source which is explosion of gasoline. To upgrade the level of
security in this area, we intend to improve the safety plant with design emergency plan
for workers and firefighters if this incident happens again. Figure 8.1 shows the proposal
land for our plant location.
Tanjung Langsat Industrial Complex is one of few industrial park that located in
southern Malaysia. This location site specifically designated for heavy industries and
there also already several heavy industries built at this site. For our production that
involves with palm oil thus, it very suitable with target market this site which wanted
palm oil and chemical industries. The industrial area can be accessed by two roads
linking which is Highway Senai – Desaru about 4 km from the site and Jalan Persiaran
179
Tanjung Langsat with road code E17. For transportation, there are several which is it
near to Senai International Airport within 59km, and since this site located near to the
port thus the distance between Tanjung Langsat Port is ony 0.5 km. Besides, it near to
Johor Port within 16 km which will easy facilitate the delivery production to the
international level. Furthermore, this Johor port one of the largest ports in Malaysia to
import local product to international. In terms of utility, this industrial area was
supported by the power supplied from Tenaga Nasional Berhad Johor (TNB) and there
are small power supplies at this area that known as PMU TLIE under Perindustrian
Tanjung Langsat (2.5 km away from site). For availability of water supplied by Syarikat
Air Johor, Pasir Gudang 9 km away from the site and well internet accessibilty. The
below table shows the electric tariff and water tariff for this industrial site.
Pengerang Industrial Park was under TPM Technopark Sdn Bhd specifically developed
for Oil & Gas supporting industries. This area was designated to welcome Heavy and
medium industries. Furthermore, this specializes area is one of the development areas
for industry area Pengerang. This location can be access only through one way which
is Pengerang Highway (Jalan Raya Pengerang) that runs from Kota Tinggi to Sungai
Rengit. This highway known as federal route 92 which is 6km away from our plant
location.In terms of transportation, this site were near with Johor Port which is 79km,
Tanjung Langsat Port (75 km) and Senai International Airport that 107 km. However,
transportation for taxi and bas stop still available in that area since this park was
industrial site. For electric and water supported can be obtained from Pengerang Power
Sdn Bhd (1.5 km) and Pengerang Deepwater (4.2 km). At our plant, we can easily obtain
electric power since there are substation electric about 1.2 km away. For water tariff is
same value as table 8.1 because this site location is under Johor Government.
Malaysian Palm Products and Pacific Edible Oil. This company was away from plant
area which is their need to through Lebuhraya Senai Desaru and with tolls before
arriving to our site location that is 90 km away. In case for waste management, it could
be sent to Pengerang Integrated Complex Management that its specialty is waste for oil
refinery that located 8.5 km away. The Figure below shows proposal our site location
and power supply.
Currently, Bukit Rambai Industrial Park has been built up to phase 4. Our site location
in phase 4 which is suitable for mixed industry and suitable for our production involves
with chemical. It also located at area industrial area which suitable to build factory for
our plant. In this case, our site location can be access through one way which is federal
route 19 and 5 that known as Lebuhraya AMJ. There are also several highways nearby
which is Highway Shah Alam Expressway (6.5 km from site) and Sungai Besi-Ulu
Klang Expressway (6.8 km). Batu Berendam Airport and Melaka International Jetty one
of transportation nearby site which is 127 km and 162 km. This transportation the
important transport in Melaka to import product to outside Melaka. It also available
transporation for taxi and bas stop in that area since this park was industrial site and
easy to access for worker. Supplier for electricity and water is available where TNB
181
Bukit Rambai (3km) and Syarikat Air Melaka Berhad (SAMB) located 6km away. The
Table 9.2 shows the water tariff for this industrial site.
For the land price is between RM 35 to RM 40 per square feet. The total size
industrial land available for this site maxima is 8.93 acres which is total price is RM 14
million. For land taxes the price RM 42 per 100 m3. Rather than that, the infrastructure
available is electricity, water, gas and internet accessibility also in better condition. Due
to labor available is high rate since this site nearby neighborhood such as Kg Bukit
Salleh (6.4km), Taman Bukit Rambai (3.5 km), Taman Rambai Utama (2.5 km) and Kg
Ayer Salak (3 km). In term raw material supplier there are several companies nearby
this site which is Evergreen Oil and Rintiz, Rezky (M) Sdn Bhd. The distance between
supplier companies with this site location is below 20 km and going through via Jalan
Tanjung Minyak without any tolls. However, there are several incidents happen within
radius of site location such as incident burning coal warehouse and water consumption
saving. This burning coal happen unidentifiable cause and 20% of industrial area
affected. For saving water due to air pollution at the high index at year 2005. The figure
8.3 shows proposal site at Bukit Rambai Industrial Park.
182
The tariff used in Malaysia is Tenaga Nasional Berhad (TNB) and this regulation was
applied to all around commercial and industrial sites. This tariff important to calculated
cost electricity used in industries. Table 9.3 below shows electric tariff for the
commercial and industrial.
Before considering choosing our site plant location there are several factors need to
look. The various key factors that must be considered when selecting a suitable plant
site based on raw material, infrastructure, cost of land, labor availability and climate,
environment, and geographical factors. There are three places needed to choose and the
mark analysis for each factor is show in table below. This mark analysis shows the how
important the factor for our site location.
To choose site location within three place an evaluation of the location was made as
shown in table below. The highest score indicates the location meet most of the
requirements and covered the important factors discussed above.
Labor 6 9 54 7 42 7 42
availability
Climate, 3 7 21 9 27 6 21
environmentand
geographical
There are two entrances located at the front of our plant where it will be for the
general use. One is the main entrance, and one is for back up so that jam and accident
185
can be avoided during busy hour. This entrance can be used by all staffs, contractors
and visitors. There is also another entrance located near the storage house will be mainly
used for loading and unloading of storage and products. This is to ease the movement
of huge truck that will be used for transportation of goods to the plant. All the entrances
will be strictly guarded by the security team.
The entrances will be strictly guarded to stop anyone who simply enters the
premises. Non-employees of our production plant will have to register themselves
before entering the plant. There will be also an emergency response team where their
job is to ensure the safety of all personnel. It is located near the main process plant as it
is a high-risk area. Anyone who are in the premises are required to always wear their
personal protective equipment (PPE). Vehicles will have to parked at the designated
parking area to avoid any incidents. The assembly area is located at the center of plant
to facilitate the movement of people in any emergency cases.
Administrative building is located right after the entrance so that visitors and
staffs can easily reach the office. Other convenient facilities like cafeteria are also
located near this building. Visitors or contractors who are going to work in the plant for
a short period of time are required to do a working permit and an employee will assist
them throughout their work. All the main process which are the pretreatment plant and
main production plant are located near each other so that the materials can be transferred
easily and can also reduce the cost of piping. The control room positioned in a safe
distance from the processing units so that the operator can still control the plant in case
there are any incident happen at the process plant.
The wastewater treatment plant (WWTP) is located near at the lowest point of
the site to collect all effluent streams. This area is restricted because it may be hazardous
due to the waste released. The waste discharged will be checked every day by the lab
assistants to ensure the parameters are within range. There will have a future expansion
area provided so that the plant will expand if there are any possibilities of doing so in
the future. Plant layout is shown in Appendix I
186
CHAPTER X
This type of unit process usually used by chemical industrial for chemical reaction.
Packed bed reactor is filled with solid catalyst particles that most often used to catalyst
gas reactions. Before this reaction the waste cooking oil has been filtered to separated
unwanted material and get the cooking oil. Conversion for this process is 80% with
catalyst used is NiMo/Al2O3.
The mechanical design of Packed Bed Reactor R-101 is subjected to ASME internal
pressure procedure. This is because the absolute pressure of the vessel is higher than
the atmospheric pressure, which is higher than 15 psi. Figure below shows the shape of
the vessel and its dimension. Cylindrical body is chosen because this is the common
shape of reactor shell. And ellipsoidal heads are chosen for both bottom and top. This
is because it is more economical, and suitable for high pressure and domed to reduce
mechanical stresses.
The table below shows the operating conditions of reactor, R-101 and design
specification of the reactor.
Reaction 1:
𝑑𝑋
𝐹𝑎𝑜 = −𝑟𝑎 ′
𝑑𝑊
The rate law for the reaction is a first order reactor, therefore,
−𝑟𝑎′ = 𝑘𝑃𝑎
= 𝑘𝑅𝑇𝐶𝑎
Stoichiometry,
𝑃𝑜
𝑣 = 𝑣𝑒 (1 + 𝜀𝑋) ( )
𝑃
𝐹𝑎
𝐶𝑎 =
𝑣
𝐶𝑎𝑜 (1 − 𝑋) 𝑃𝑜 𝐶𝑎𝑜 (1 − 𝑋)
= ( )= 𝑦
1 + 𝜀𝑋 𝑃 1 + 𝜀𝑋
𝑃𝑜
𝑤ℎ𝑒𝑟𝑒 𝑦 = ( )
𝑃
𝑑𝑦 𝛼
= (1 + 𝜀𝑋)
𝑑𝑊 2𝑦
𝐶𝑎𝑜 (1 − 𝑋) 𝑃𝑜
−𝑟𝑎′ = 𝑘𝑅𝑇𝑂 ( )
1 + 𝜀𝑋 𝑃
r1 = 30.6328,
(24629.66)(0.8)
𝑉=
1024(1 − 0.4)(30.6328)
= 0.4425 m3
By taking ratio height shell to diameter 1:4 where Hvessel = 4D while taking ratio 1:2 for
diameter to height head for both bottom and top, D = 2Hhead. Hence the height for packed
bed reactor is 1.478 m with 0.2952m head for both bottom and top
Pressure drop for this packed bed reactor can be calculated by using Ergun equation
shows as below;
191
∆𝑃 𝑉(1 − 𝜀)2 𝜌𝑓 𝑉 2 (1 − 𝜀)
= 150 2 2 + 1.75
𝐿 ∅𝑆 𝐷𝑃 𝜀 3 ∅𝑆 𝐷𝑝 𝜀 3
Where,
Thus the pressure drop of the packed bed reactor, R-101 ∆P = 0.0941bar
The table below shows the summary of the calculation of packed bed reactor R-101.
In reactor R-102, paraffin will reacts with hydrogen to produce our main product which
is decane and by-product, petrol. The operating condition are same as reactor R-101.
The table below shows the summary of the calculation of packed bed reactor R-102.
The absorber is designed with a vertical layout with 2:1 ellipsoidal head at the top and
bottom. The column is designed under internal pressure with random packing column.
The construction material is carbon steel with corrosion allowance (CA) of 4 mm is
chosen as the strean contain high consentration of propane gas. The operating condition
and the shape of each part of the gas absorption had shown in table below.
Hydrogen
gas
Benzene (Stream 29)
(Stream 16)
Gas in
Propane gas
(Stream 17)
+ Benzene
(Stream 30)
Metal, carbon steel (76 mm size) was chosen as the packing for the adsorption
column, with void fraction of 50% (Towler & Sinnot 2013), packing factor, 𝐹𝑝 is
105𝑚−1.
𝐿𝑤 𝜌𝑣
𝐹𝑙𝑣 = √ = 1.44
𝑉𝑤 𝜌𝐿
From Figure 5.2 in Towler and Sinnot (2013), 𝐾4 = 0.8 and flooding = 1.8
1
2
𝑘4 𝜌𝑣(𝜌𝑙−𝜌𝑣)
Gas mass flowrate per unit column cross-sectional area, 𝑉𝑤 = [ 𝜇𝐿 0.1
]
13.1𝐹𝑝 ( )
𝜇𝑉
=200.73 kg/𝑚2 . 𝑠
4
Column diameter = √𝜋 × 6.79
𝜋
Column area after rounding of the diameter = 4 × 32 = 7.069 𝑚2
= 64%
𝑦1 1
= = 50
𝑦2 1 − 𝑝𝑒𝑟𝑐𝑒𝑛𝑡𝑎𝑔𝑒 𝑟𝑒𝑚𝑜𝑣𝑎𝑙
Cornell’s method is used to estimate the height of an overall gas – phase transfer units
𝐻𝑂𝐺 .
𝜇𝑣
Gas Schmidt number, (𝑆𝑐)𝑣 = 𝜌 = 1.08
𝑣 𝐷𝑣
𝜇1
Liquid Schmidt number, (𝑆𝑐)𝑙 = =9.18
𝑝 𝑙 𝐷𝑙
Cornell’s equations:
𝐷𝑐 1.11 𝑍 0.33
0.011𝜓ℎ(𝑆𝑐)𝑣 0.5 ( ) ( )
0.305 3.05
𝐻𝐺 = = 5.07 m
𝐿𝑤 ∗𝑓1 𝑓2 𝑓3 0.5
0.5 𝑍
𝐻𝐿 = 0.605𝜙ℎ (𝑆𝑐)𝐿 𝐾3 (3.05)0.15 = 0.17 m
𝐷𝑖 2.94
ℎ𝑒 = = = 0.735𝑚
4 4
The goal of distillation is to achieve a distillate rich in the light key and a bottom rich
in the heavy key. The feed of distillation column consists of three components which
are triglycerides, paraffin and water This separation process is to achieve paraffin in a
higher purity before entering the second reactor. The feed contains a more volatile
component which is light key (LK) and a less volatile component which is the heavy
key (HK). In this separation process at distillation column D-101, our LK is paraffin,
and our HK is triglycerides.
198
The operating temperature of the process is 98°C at 2 bar. Table 10.8 below shows the
temperature and pressure of inlet and outlet streams.
The compositions and flowrates of each of the components in feed, distillate and bottom
part is shown in the Table 10.9 below.
The material selected for the construction of column is Stainless Steel type 304. The
maximum allowable stress of this type of material is 21030 psi. Ellipsoidal head with
ratio of 2:1 is chosen as it is suitable for high pressure and able to reduce mechanical
stresses (Towler & Sinnot 2013). Ellipsoidal heads are generally considered as weldable
steel, as well as easily manufactured and more economical. Cylindrical body is chosen
because this is the common shape of distillation column body.
𝑇2
Qsensible = n∫𝑇𝑟 𝐶𝑝 𝑑𝑇
Qc = Qsensible +Qlatent
The data for heat capacity of water, triglycerides and paraffin are shown in the tables
below.
Table 10.10 Data for heat capacity in J/kmol K of paraffin and triglycerides
Component a b c d
Paraffin 44.0
Triglycerides 32.7
Water 40.8
The inlet temperature for inlet stream 20 is 459.15 K. For temperature of outlet stream
21 and 25 are 326.05 K and 459.85 K respectively.
= 15,827.415 kJ/h
In this separation process, we use tray distillation column. There are three important
variables in designing the tray type distillation column, which are the number of trays,
feed stage and reflux ratio. Capital cost of a column is related to the number of trays,
and operating cost depends on the feed stage and reflux ratio (Chua et al. 2017).
Short-Cut Method
Underwood method, number of equilibrium stages for a reflux ratio greater than
minimum by the Gilliland correlation and feed stage.
In determining the number of stages within the column, Fenske and Underwood
equations can be applied. To solve it, the K-value of each components are computed by
using Antoine equation which is to obtain the saturated pressure first for each of the
components.
By assuming the liquid and vapor phases are in ideal state, the K-value can be
calculated by using Raoult’s Law equation which is Ki = Pisat /P. Its volatility, 𝛼 can be
calculated by using 𝛼i,j = Ki / KHK.
𝑑𝑖 𝑏𝑗
ln [( )( )]
Nmin = 𝑑𝑗 𝑏𝑖
𝑙𝑛𝛼𝑚
Relative volatility:
𝐾𝑃,𝐷 1.3416
𝛼𝑖,𝑗(𝐷) = = = 2.2739
𝐾𝑇,𝐷 0.5900
202
𝐾𝑃,𝐵 1.2880
𝛼𝑖,𝑗(𝐵) = = = 2.2184
𝐾𝑇,𝐵 0.5806
0.3077 0.9841
ln [(0.6923)(0.0030)]
Nmin = = 6.16
ln (2.2460)
𝛼𝑖 𝑍𝐹,𝑖
Σ( )=1−𝑞
𝛼𝑖 − 𝜃
𝛼𝑖 𝑥𝐷,𝑖
𝑅𝑚𝑖𝑛 + 1 = Σ( )
𝛼𝑖 − 𝜃
203
𝛼𝑖 𝑥𝐷,𝑖
𝑅𝑚𝑖𝑛 = Σ ( )−1
𝛼𝑖 − 1.9784
= 0.5837
Assume R= 2Rmin
𝑁 − 𝑁𝑚𝑖𝑛
= 0.4041
𝑁+1
𝑁 = 11.02
𝑁𝑚𝑖𝑛 6.16
Tray efficiency = × 100% = 11.02 × 100% = 55.9%
𝑁
With the number of theoretical stages and the tray efficiency, the actual number of
stages can be calculated. Actual number
Parameter known:
= 73.05 kg/kmol
= 59.68 kg/kmol
PMv (180)(73.05)
𝜌V = = (8.314)(371.65) = 4.2555 kg/m3
RT
The value of Cf depends on tray spacing and abscissa ratio, FLV. From Separation
Process Principle (Seader, JD et.al. 2011), we get Cf = 0.03 ft/s when FLV = 2.56. The
value of C can be calculated from the equation below:
𝐶 = 𝐹𝑆𝑇 𝐹𝐹 𝐹𝐻𝐴 𝐶𝐹
Where,
Hence,
𝐶 = (0.9564)(1.0)(1.0)(0.03) = 0.0287
1 1
ρ𝐿 −ρ𝑣 2 787.4935−4.2555 2
Uf = C(
ρ𝑣
)= (0.0287)(
4.2555
) = 0.3893 ft/s = 0.1187 m/s
4𝑉𝑀𝑣 4(3.25/3600)(73.05)
DT = √ 𝐴 = √(0.8)(0.1187)𝜋(1−0.2)(4.2555) = 0.51 m
𝑓𝑈𝑓 𝜋(1− 𝑑 )ρ𝑣
A
= (24)(11)
= 264 inches
= 6.71 m
206
The approximation of the optimal feed-stage location can be made with the Kirkbride
empirical equation:
2 0.206 0.206
𝑁𝑅 𝑧𝐻𝐾,𝐹 𝑥𝐿𝐾,𝐵 𝐵 0.9775 0.003 2 138.75
= [( )( ) ( )] = [( )( ) ( )] = 0.592
𝑁𝑆 𝑧𝐿𝐾,𝐹 𝑥𝐻𝐾,𝐷 𝐷 0.01 0.6923 3.25
Therefore,
0.592
𝑁𝑅 = ( ) (11.02) = 4.1
1.592
Rounding the estimated stage requirements leads to 7 stages below the feed, and 4 stages
above the feed.
The data obtained from the distillation column D-101 design is shown in Table 10.16
below.
Parameter Value
Number of stages 11
207
The function of this distillation column is to separate the mixture stream containing
decane, petrol, paraffin and water due to their boiling point and volatility which suits
the criteria. In this distillation unit, the product, decane will be separated from the by-
product, petrol. Final product petrol would be light key component (LK) while decane
as the heavy key (HK) component since petrol has lower boiling point compared to
decane, so petrol will be vaporized as top product and leaves distillation system as
distillate. Water is categorized in non-heavy key component because it does not directly
contribute to the separation.
The data obtained from the distillation column D-102 design is shown in
Table 10.17 below.
Parameter Value
Number of stages 13
One of usually separater unit process used is distillation column with functional
deperate component with different volatility using boiling point as references. In the
inlet stream there contain paraffin, decane, petrol and water. In this unit process to
separate petrol from water to get the purity petrol at the end. Since petrol has the lower
boiling point it identify as light key component (LK) meanwhile water is the heavy key
(HK).
209
For the type of tray used in this unit separation is sieve tray column. This type of tray
gives the high efficiency to separate the component and this due to its minimum back
mixing. Furthermore, this type also easy to find in market and can get at the lower price.
The pressure vessel design codes and standards lists of acceptable material in
accordance with the appreciate material standard. Stainless steel SA-304 has been
chosen since it provides good corrosion resistance and good weldability. It also provides
a good to resist intergranular corrosion. (International Stainless Steel Forum 2012).
210
By using Antoine equation, we can have calculated K-value for each component. K
value is obtained by using Raout’s law that assume the solution at ideal gas. (Christie
John Geankoplis, 2003)
𝐵
𝑙𝑜𝑔10 𝑃𝑠𝑎𝑡 = 𝐴 −
𝐶+𝑇
𝑃𝑠𝑎𝑡
𝐾=
𝑃
Table 2.3 shows the constant each component for Antoine equation. By using
formula obtained using Raout’s law can calculated the value of K-values. The Table 2.4
shows summary of K values and relative volatility of distillate and bottom.
Using the specified flow of light key (LK) and heavy key (HK) component, the
minimum number of stages of column is calculated by using the following formula,
211
𝑋 𝑋
log [(𝑋𝑑 ) (𝑋𝐵 )]
𝐵 𝐷
𝑁𝑚𝑖𝑛 =
log 𝛼𝑚
1/2
𝛼𝑚 = [(𝛼𝐿𝐾,𝐻𝐾 )𝑁 (𝛼𝐻𝐾,𝐿𝐾 )1]
Reflux ratio of the distillation column can be calculated by using Underwood equation.
Minimum reflux ratio, Rmin that consist of first and second Underwood equation. First
Underwood equation is used to determine the theta value and using it to solve in second
Underwood equation in order to obtain Rmin.
(𝛼𝑖,𝑟 )∞ 𝑧𝑖,𝑓
1−𝑞 = ∑
(𝛼𝑖,𝑟 )∞ − 𝜃
𝜃 = 0.146
212
(𝛼𝑖,𝑟 )∞ 𝑋𝑖,𝐷
1 − (𝑅∞ )𝑚𝑖𝑛 = ∑
(𝛼𝑖,𝑟 )∞ − 𝜃
𝑅𝑚𝑖𝑛 = 0.0891
The actual reflux ratio and the number of theoretical stages must be greater than
minimum values. The actual reflux ratio considered in this design is 1.2 of the minimum
reflux ratio. Hence, the actual reflux ratio,
𝑅 = 1.2𝑅𝑚𝑖𝑛
𝑅 = 0.1069
𝑅 − 𝑅𝑚𝑖𝑛
𝑋=
𝑅+1
𝑌 + 𝑁𝑚𝑖𝑛
𝑁=
1−𝑌
While the equation for tray efficiency is using the O’Connell correlation,
𝜇 = Average viscosity
From the definition of fractional overall stage efficiency, actual number of stages can be
determined.
𝑁𝑡ℎ𝑒𝑟𝑜𝑡𝑖𝑐𝑎𝑙
𝑁𝑎𝑐𝑡𝑢𝑎𝑙 =
𝐸𝑜
Table 2.5 below shows the summary of number of stages after calculation.
Kirkbride empirical equation is used to estimate the optimal feed stage location at
distillation column. The equation is as shown below
2 0.206
𝑁𝑅 𝑧𝐻𝐾,𝐹 𝑥𝐿𝐾,𝐵 𝐵
= [( )( ) ( )]
𝑁𝑆 𝑧𝐿𝐾,𝐹 𝑧𝐻𝐾,𝐷 𝐷
𝑁𝑅 + 𝑁𝑆 = 𝑁𝑎
where 𝑁R = number of stages above the feed, including any partial condenser
By solving the two equations above, the optimal feed stage location is at stage 9 from
top of the distillation column which NR = 15.67 and NS = 9.46.
214
v. Column diameter
The column diameter is determined such that vapor velocity in the column is less than
flooding velocity. Assumption
𝑃𝐿 − 𝑃𝑉 0.5
𝑈𝐹 = 𝐶 ( )
𝑃𝑉
𝜌𝐿 = Liquid density
Vp = Vapour density
C = FSTFFFHACF
FF = Foaming factor
FHA = 1.0 for Ah/Aa ≥ 0.1 and 5 (Ah/Aa) + 0.5 for 0.06 ≤ Ah/Aa ≤ 0.1
CF = Flooding capacity
215
FHA for this distillation column is 1.0. CF is determined by calculating the value of FLV
and obtaining the value from by Seader (2011) shown below.
𝐿𝑀𝐿 𝜌𝑣 0.5
𝐹𝐿𝑉 = ( )( )
𝑉𝑀𝑉 𝜌𝐿
0.5
4𝑉𝑀𝑣 − 𝜌𝑣
𝐷𝑇 = ( )
𝐴𝑑
𝑓𝑈𝜌𝜋 (1 − 𝐴 ) 𝜌𝑣
UF = Flooding velocity
𝜌𝑉 = Density of vapour
f = fraction of flooding
0.1
𝐴𝑑 𝐹𝐿𝑉 − 0.1
= {0.1 + , 0.1 ≤ 1.0
𝐴 9
0.2
The table shows the summary of column diameter after the calculation
Parameter Values
Capacity parameter of Sounders and Brown, C 0.31 m/hr
Flooding velocity, UF 2.519 m/hr
216
=0.6×19
=11.4 𝑚
𝐻𝑆 =𝐻𝑂 ×1.1
=11.4 𝑚×1.1
=12.54 𝑚
The ratio between height and diameter is needed to be calculated in order to compare
with the industry distillation column. In industrial practice, the ratio is always between
2 to 3. Thus, the ratio between height and diameter of this distillation column is 2.96
which is acceptable.
The below shows the summary of specifications for distillation column, D-103.
Distillation column (D-104) in the production of aviation fuel from waste cooking oil
is used to separate mainly Decane and Paraffin. There are also other components in
small quantity such as water and petrol.
The total feed flowrate of distillation column D-104 is 14964 kg/h, which is the capacity
of D-104. The top product flowrate is 10416.67 kg/h while bottom product flowrate is
4547.88 kg/h.
The height to diameter ratio of cylindrical shell is about. This is within the typical
dimension ratio for distillation column.
𝐷𝑖
ℎ𝑜 = = 0.448𝑚
4
𝐻𝑠 = 𝐻 − ℎ𝑜 = 5.586 𝑚
219
𝐷𝑖
ℎ𝑜 = = 0.448𝑚
4
𝐻𝑠 = 𝐻 − ℎ𝑜 = 5.586 𝑚
Design pressure for each part of the vessel is calculated by using equation:
𝑃𝐷 = 𝑃𝑜 + 0.433ℎ
𝑃𝑜 = 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒
Hence,
𝑃𝐷 = 21.756 + 0.433(1.470)
220
𝑃𝐷 = 21.756 + 0.433(1.470)
𝑃𝐷 = 21.756 + 0.433(11.470)
𝑃𝐷 = 21.756 + 0.433(11.470)
𝑃𝐷 = 21.756 + 0.433(20.545)
𝑃𝐷 = 21.756 + 0.433(20.545)
The wall thickness formulas for each part of the column are from ASME Code UG-32
(d) and UG-27 (c). It is assumed as thin wall where t/D < 1:10. Assume welding joint
efficiency is 85% and the stress design from ASME code is 21030 psi. $mm corrosion
allowance is included for non-corossive stream as suggested by Source
𝑃𝑅 (24.772 ×57.087)
Thickness, t = 𝑆𝐸−0.6𝑃 = 2(21030)(0.85)−(0.2)(24.772) = 0.056 𝑖𝑛𝑐ℎ
i. Circumferential stress
𝑷𝑹 (𝟐𝟒.𝟕𝟕𝟐 ×𝟓𝟕.𝟎𝟖𝟕)
ii. Thickness, t = = 𝟐(𝟐𝟏𝟎𝟑𝟎)(𝟎.𝟖𝟓)−(𝟎.𝟐)(𝟐𝟒.𝟕𝟕𝟐) = 𝟎. 𝟎𝟕𝟔 𝒊𝒏𝒄𝒉
𝑺𝑬−𝟎.𝟔𝑷
𝑃𝑅 (24.772 ×57.087)
Thickness, t = 𝑆𝐸−0.6𝑃 = 2(21030)(0.85)−(0.2)(24.772) = 0.053 𝑖𝑛𝑐ℎ
𝑃𝑅 (24.772 ×57.087)
Thickness, t = 𝑆𝐸−0.6𝑃 = 2(21030)(0.85)−(0.2)(24.772) = 0.076 𝑖𝑛𝑐ℎ
𝑇𝑚𝑖𝑛 = 𝑡𝑛𝑜𝑚𝑖𝑛𝑎𝑙 − 𝐶𝐴
=10 𝑚𝑚 − 4 𝑚𝑚
=6 𝑚𝑚 (0.2362 𝑖𝑛𝑐ℎ𝑒𝑠)
The maximum allowable working pressure for any type of pressure vessel, MAWP is
determined by calculating all MAWP for every part under internal pressure. The
formula of internal design pressure for each part of the column can be found in
ASMECode UG-32(d) and UG-27(c). By using tmin, the MAWPpart is calculated.
2𝑆𝐸𝑡
MAW𝑃𝑝𝑎𝑟𝑡 = 𝐷+0.2𝑡
222
i. Circumferential MAWP_part
2𝑆𝐸𝑡
=
𝐷+0.6𝑡
2𝑆𝐸𝑡
𝐷 + 0.4𝑡
To calculate the value of static head and MAW𝑃𝑝𝑎𝑟𝑡 , 𝑡ℎ𝑒 𝑒𝑞𝑢𝑎𝑡𝑖𝑜𝑛 𝑢𝑠𝑒𝑑 𝑖𝑠 𝑎𝑠 𝑓𝑜𝑙𝑙𝑜𝑤𝑠:
The value of internal pressure and MAW𝑃𝑣𝑒𝑠𝑠𝑒𝑙 is obtained and shown in table
10.25.
Since MAW𝑃𝑣𝑒𝑠𝑠𝑒𝑙 < 𝑃𝑑𝑒𝑠𝑖𝑔𝑛 where 32.725 psi > 25.656 psi so it is valid.
223
Pressure vessels are always exposed to other loads in addition to pressure and it must
be designed to withstand the maximum combination of loading without experiencing
failure.
1
𝜎1 = [𝜎ℎ + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
1
𝜎2 = [𝜎 + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
𝜎1 = 𝜎ℎ ; 𝜎2 = 𝜎𝑧
(∆𝜎)𝑚𝑎𝑥 < 𝑆
Therefore, the vessel wall thickness is sufficient to ensure the maximum stress intensity
does not exceed the design stress (nominal design strength) for the material of
construction at any point.
1
𝜎1 = [𝜎ℎ + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
1
𝜎2 = [𝜎ℎ + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
𝜎1 = 𝜎ℎ ; 𝜎2 = 𝜎𝑧
(∆𝜎)𝑚𝑎𝑥 < 𝑆
Therefore, the vessel wall thickness is sufficient to ensure the maximum stress
intensity does not exceed the design stress (nominal design strength) for the material
of construction at any point.
𝐸 𝑡
Critical buckling stress, 𝜎𝑐 = (𝑅 )
√3(1−𝑉 2 ) 𝑝
Since the value of (∆𝜎)𝑚𝑎𝑥 < 𝜎𝑐 , therefore, the design is safe to use
The method used to support vessel will depend on the size, shape and wight of vessel,
the design temperature and pressure, the vessel location and arrangement and internal
fittings and attachments. Skirt support is used as they are particularly suitable for tall
column subject to wind loading.
a. Skirt thickness
The minimum height of the skirt is normally set by the process based on the NPSH
requirements of the pumps or the reboiler hydraulic requirements, Tus, skirt support
height for reactor, hsk = 1 m.
Ds=Di = 11352.53 mm
W = 1733.84 N/m
𝑊𝑥 2
Bending moment at the base of skirt Ms = = 66568.048Nm
2
4𝑀𝑠
𝜎𝑏𝑠 =
Π(𝐷𝑠 + 𝑡𝑠𝑘 )𝑡𝑠𝑘 𝐷𝑠
𝑁
= 2861766.307 𝑚𝑚2
227
𝑊𝑠
𝜎𝑤𝑠 =
Π(𝐷𝑠 + 𝑡𝑠𝑘 )𝑡𝑠𝑘
= 0.025 𝑁/𝑚𝑚2
Assumptions:
Base angle, 𝜃𝑠 = 90
𝑡𝑠𝑘 16
0.125𝐸 ( ) 𝑠𝑖𝑛𝜃𝑠 = 0.125 × 200000 × ( ) sin 90 = 264.386 𝑁/𝑚𝑚2
𝐷𝑠 1352.56
𝑡
𝜎𝑆 (𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒) < 0.125𝐸 ( 𝐷𝑠𝑘 ) 𝑠𝑖𝑛𝜃𝑠 → 2.837𝑁/𝑚𝑚2 < 264.386 𝑁/𝑚𝑚2
𝑠
Since both criteria are satisfied, the assumed value of skirt thickness 𝑡𝑠 = 0.010 m is
acceptable. With corrosion allowance of 2mm, the design skirt thickness, 𝑡𝑠 =0.012 m
=18 m. Table 10.27 shows the summary of skirt design.
228
Skirt thickness mm 12
The loads carried by the skirt will be transmitted to the foundation slab by the skirt base
ring. The moment produced by wind other lateral loads will tend to overturn the pressure
vessel. This will be opposed by the couple set up by the weight of vessel and tensile
load of anchor bolts, For our column, single plate with gusset as the base ring design of
the skirt support is used. The anchor bolts assumed to share the overturning load
equally, and the bolt area required is given by:
1 4𝑀𝑏
𝐴𝑏 = [ − 𝑊]
𝐴𝑏 𝐴𝑏 𝐷𝑏
Assumption:
1 66568.048
𝐴𝑏 = [4 × − 1733.840]
8 × 125 1.4
= 188.461 mm
The base ring must be sufficiently wide to distribute the load to the foundation. The
total compressive load on the base ring is determined.
4𝑀 𝑊
𝐹𝑏 = [𝜋𝐷2𝑠 − 𝜋𝐷 ]= 46.73 kN/m
𝑠 𝑠
𝐹𝑏 1
The minimum width of the base ring, 𝐿𝑏 = × 103
𝑓𝑐
𝐹𝑏 1
𝐿𝑏 = × 103 = 13.35 mm
𝑓𝑐
This is the minimum width required, actual width depends on the chair design.
As the bolt diameter calculated is 45.80 mm. Nominal bolt size M48 (BS 4190 1967) is
used.
𝐹 46.731
= 𝑎𝑐𝑡𝑢𝑎𝑙 𝑤𝑖𝑑𝑡ℎ𝑏 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = = 0.320 𝑁/𝑚𝑚2
146
√3(𝑓𝑐′ ) √3(0.568)
𝐿𝑟 = 𝐿𝑟 = 6.294mm (round off to 10 mm)
𝐹𝑟 140
230
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required. Welding neck
flange can reduce high-stress concentration at the base of the flange by transferring
stress to the adjoining pipe. It has high strength and high resistance to dishing,
manufacturing with a long-tapered hub. The welding next flange diagram and
dimensions is shown in Table 10.28.
Table 10.28 Size of flanges used for fitting on each pipe on D-104
Connectio D1(mm D2(mm D3(mm D4(mm H1(mm H2(mm T(mm
n ) ) ) ) ) ) )
10.8.1 Introduction
From the top of distillation column 24629.66 kg/h of paraffin, in aqueous vapour is
being discharged and sent to a condenser to be recovered into liquid. The condenser
used is shell and tube type of heat exchanger. Shell and tube design is being chosen due
toits several advantages than over bear the others.Shell and tube condenser also known
as surface condenser make up for the majority of installed base for industrial
applications. It is more compact in size and come in a wider variety of physical
configurations. The most important is that it suited for large pressure drop and yet is
less expensive as compared to plate type condenser. Due to its design, this type of
condenser offers a large heat transfer area and provides a high heat transfer efficiency
in comparison with others. So it can be employed for our process as it requires large
232
The floating head of this condenser is split ring floating head. The floating head cover
is secured against the floating tube sheet by bolting it to an ingenious split backing ring.
This floating head closure is located beyond the end of the shell and counted by a shell
cover of a larger diameter. While the tube layout pattern used in square pitch pattern.
This condenser is used to condense the outlet stream of distillation column ( N-101)
from 185 °C to 125 °C. Due to higher viscosity and flowrate concerns of process fluid,
condensation happens at horizontal shell side with vertical tube suide filled with cooling
water as coolant. It is designed as counter current flow pattern. Cooling water is
introduced at 30 °C and rise to 40 °C. Tubes of 38.1 mm outside diameter, 16.8mm
inside diameter, 5 m long, of carbon steel are adopted. The vapor is to be totally
condensed and no subcooling is required. The general schematic diagram of condenser
can be seen from figure below.
The table 10.3 below shows the summary of the calculation of condenser, N-101.
233
8047.65 kg/h mixture of paraffin, petrol, decane and water from the top of distillation
column in aqueous vapour is being discharged and sent to condenser N-102 to be
recovered into liquid. The table below shows the summary of the calculation of
condenser N-102.
6507.42 kg/h mixture of paraffin, petrol, decane and water from the top of distillation
column in aqueous vapour is being discharged and sent to condenser N-103 to be
recovered into liquid. The table below shows the summary of the calculation of
condenser N-103.
10416.67 kg/h mixture of paraffin, petrol, decane and water from the top of distillation
column in aqueous vapour is being discharged and sent to condenser N-104 to be
recovered into liquid. The table below shows the summary of the calculation of
condenser N-104.
Cooler C-101 is used to cool down stream 12 which contains propane and hydrogen gas
from 100°C to 25°C in stream 17. The type of heat exchanger used is shell and tube
heat exchanger and Kern’s method is applied. This form of heat exchanger has a wide
surface area for its size. It can be made of a variety of materials to withstand corrosion
and other issues. Furthermore, since shell and tube heat exchangers can be dismantled,
cleaning and repair are relatively simple.
236
We are using split-ring floating head. Here the floating head bonnet is bolted to a split
backing ring instead of the tube sheet. This eliminates bolt circle diameter and allows a
full complement of tubes to fill the shell. Carbon steel SA516 (grade 70) is used as the
material of construction. Carbon steel is most commonly used engineering material as
it is cheap, available in a wide range of standard forms and sizes, has good tensile
strength and ductility. Cooling water is used as the cooling agent and is assigned to the
tube side because it is more corrosive than the process fluid to lower the cost of an
expensive alloy or clay part. The process fluid, on the other hand, is assigned to the
shell-side. It is designed as counter-current pattern.
T1=100°C
t2=25° C
T2=25° C
t1=15° C
The type of flow for the temperature profile is counter current flow, as shown
inFigure 10.12 Figure 10.12. Due to its increased effectiveness in establishing a more
consistent temperature difference between the fluids over the whole length of the fluid
route, counter current flow is more efficient than co-current flow.
To design the cooler C-101 in the process, few assumptions needs to be made:
5. The cooler used for this process is shell and tubes heat exchanger.
237
6. This cooler use one shell pass and one tube passes
8. Choose tube size do=19.05 mm, di=16.942 mm, L=3.66m (with 0.05 tube-
sheet thickness), carbon steel.
1ℎ
= (1363.21) (3600𝑠) (1611.8)(100 − 25)
= 45776.6𝑘𝑊
45776.6
𝑚𝑐𝑜𝑜𝑙𝑖𝑛𝑔 𝑤𝑎𝑡𝑒𝑟 = = 1.094𝑘𝑔/𝑠
(4186)(25 − 15)
Temperature ratio, R
𝑇1 − 𝑇2 100 − 25
𝑅= = = 7.5°𝐶
𝑡2 − 𝑡1 25 − 15
Temperature efficiency, S
𝑡2 − 𝑡1 25 − 15
𝑆= = = 0.118°𝐶
𝑇1 − 𝑡1 100 − 15
Ft = 0.82
Assume value of heat transfer coefficient, Uo from Figure 12.1 Chemical engineering
design (use high pressure gas and cooling water), U=300 W/m2°C
𝑄 45776.6
𝐴 = 𝑈∆𝑇𝑚 = (300)(12.7) = 11.9 𝑚2
As the shell side is relatively clean, use 1.25 triangular pitch. From Table 12.4 Chemical
engineering design,
Bundle diameter, Db
1 1
𝑁𝑡 𝑛1 56 2.142
𝐷𝑏 = 𝑑𝑜 (𝑘1) = (19.05) (0.319) = 212.67 𝑚𝑚
From Figure 12.10 chemical engineering design, bundle diameter clearance, C = 52mm.
Shell diameter, Ds
Ds = Db + C = 212.67 + 52 = 264.7 mm
𝑡1 + 𝑡2 15 + 25
Mean steam temperature = = = 20°C
2 2
𝜋 𝜋
Tube cross sectional area, 𝐴𝑡 = (𝑑𝑖 )2 = (16.942)2
4 4
= 225.4 𝑚𝑚
1.094
Fluid mass velocity, G = = 86.62 𝑘𝑔/𝑚2 𝑠
0.012
240
86.62
Linear velocity, 𝑈𝑡 = = 0.087 𝑚/𝑠
997
𝑈𝑡 0.8
ℎ𝑖 = (4200)(1.35 + 0.02𝑡) ( 0.2 )
𝑑𝑖
0.0870.8
= 4200((1.35 + 0.02(20)) ( 0.2
) = 591.08 W/m2 °C
16.942
(𝑝𝑡 − 𝑑𝑜 )𝐷𝑠𝑙𝑏
𝐴𝑠 =
𝑝𝑡
(23.8 − 19.05)(264.7)(52.9)
𝐴𝑠 =
23.8
= 2801.9 𝑚𝑚
Mass velocity, Gs
Equivalent diameter, de
1.10 2
𝑑𝑒 = (𝑝𝑡 − 0.917𝑑𝑜2 )
𝑑𝑜
1.10
= (23.8 mm − 0.917(19.052 )) = 780.38 𝑚𝑚
19.05
Reynold number, Re
241
𝐺𝑠 𝑑𝑒 (1229.09)(780.38)
𝑅𝑒 = = = 28177.74
𝜇 0.011
𝐶𝑝μ (1611.8)(0.011)
𝑃𝑟 = = = 1009.7
𝐾𝑓 0.018
Choose 25% baffle cut because the baffle cut 20% to 25% provide good heat transfer
with reasonable pressure drop. From Figure 12.29 shell side heat transfer coefficient,
segmental baffle;
jh= 0.03
Nu = jhRePr1/3 = (0.03)(28177.74)(1009.7)1/3
= 90268982.2
𝑁𝑢 90268982.2
ℎ𝑠 = = = 2178.33 𝑊/𝑚2 °𝐶
𝑑𝑒 780.38
Take;
19.05
(19.05 × 10−3 ) ln (
1
=
1
+
1
+ 16.94) + (19.05) ( 1 + 1
)
𝑈𝑜 2178.33 10000 2(16.3) 16.94 5000 591.08
𝑈𝑜 = 391.35 W/m2°C
242
The different between overall coefficient and initial assumed value is 23.34% which is
in between 0 to 30%, thus all parameters acceptable.
𝜌𝑈𝑡 𝑑𝑖 (997)(0.277)(16.942)
𝑅𝑒 = = = 16594.56
𝜇 0.282
𝐶𝑝 𝜇 (4186)(0.282)
𝑃𝑟 = = = 1975.4
𝐾𝑓 0.598
jh = 0.07
The data obtained from the cooler C-101 design shows in Table 10.35 below
Tube Side
Number of tube 56
Shell Side
Pitch Triangle
Baffle cut 25 %
Total flowrate that enter cooler, C-106 is 1540.23 kg/h which are decane, petrol, water
and paraffin.
𝑇1 = 90°C
𝑇2 = 25°C
𝑡2 = 70°C
𝑡1 = 15°C
1540.23
=( ) × 6.859 × (90 − 25) = 190.75 𝑘𝑤
3600
𝑄
Mass flowrate, 𝑚̇ = 𝐶
𝑝 ∆𝑇
190.75 𝑘𝑔
= = 0.428
6.859 × (90 − 25) 𝑠
245
𝑡2 − 𝑡1 70 − 15
𝑆= = = 0.733
𝑇1 − 𝑡1 90 − 15
𝐹𝑡 = 0.96
𝑄 190.75
Provisional area, A = 𝑈𝑇 = = 2.75
𝑚 5000(13.85)
70+15
Mean temperature = = 42.5 °C
2
26
Tube per pass = = 12
2
Total flow area, A = Number of tube per pass × tube cross sectional area
= (29)(201.06×10−6 ) = 0.00248 𝑚2
𝑚 0.428
Tube velocity, 𝑈𝑡 = = (20.09×0.00248) = 8.601 𝑚/𝑠
𝜌𝐴
𝜌𝑢𝑑𝑒 𝐶𝑝 𝜇
Re = = 2764.78 , Pr = =7.103, L/di =122.25
𝜇 𝑘𝑓
With 𝑘1 =0.249, 𝑛1 = 2.207 from table 12.4 of Towler & Sinnot 2013
1 1
𝑁 𝑛 25 2.207
Bundle diameter,𝐷𝑏 =𝑑𝑜 (𝐾𝑡 ) 1 =20 (0.249) = 160.3𝑚𝑚
1
Use a pull-through floated head type, so accordingto the figure 12.10 of Towler &
Sinnot 2013, bundle diametrical clearance = 88mm
1.1
Equivalent diameter, 𝑑𝑒 = (𝑝𝑡 2 − 0.917𝑑0 2 ) = 14.201𝑚𝑚
𝑑𝑜
247
(𝑝𝑡−𝑑𝑜 )𝐷𝑠 𝑙𝑏
Area of cross flow, 𝐴𝑠 = ( ) = 3.08𝑚
𝑝𝑡
𝑀 0.209𝑘𝑔
Shell velocity, 𝑢𝑠 = 𝐴 =
𝑠 𝑠𝑚2
𝜌𝑢𝑑𝑒 𝐶𝑝 𝜇
Re = = 2084.25, Pr = =18.63
𝜇 𝑘𝑓
Choose 25% baffle cut from figure 12.29 of towler & Sinnot 2013, 𝑗𝑛 = 0.14
𝑊
Heat transfer coefficient, ℎ𝑠 = 286.17 𝑚2 .°𝐶
5000𝑊 5000𝑊
Taking fouling coefficient from table 12,2 where ℎ𝑜𝑑 = . °𝐶 and ℎ𝑖𝑑 = . °𝐶
𝑚2 𝑚2
𝑑
1 1 1 𝑑𝑜 𝐼𝑛 ( 𝑜 ) 𝑑 1 𝑑 1
𝑑𝑖 𝑜 𝑜
= + + + +
𝑈𝑜 ℎ𝑜 ℎ𝑜𝑑 2𝑘𝑤 𝑑𝑖 ℎ𝑖 𝑑𝑖 ℎ𝑖𝑑
𝑊
𝑈𝑜 = 100.415 . °𝐶
𝑚2
𝐿 𝜌𝑢𝑡 2
Pressure drop, ∆𝑃 = [8𝑗𝑓 (𝑑 ) + 2.5] = 1862.49 N/𝑚2 / 0.0056 𝑝𝑠𝑖
𝑖 2
𝐷 𝐿 𝜌𝑢2
Pressure drop, ∆𝑃 = 8𝑗𝑓 (𝑑 𝑠 )(𝑙 ) =7.861× 103 N/𝑚2
𝑒 𝐵 2
The summarize detail design of other coolers and heat exchangers are shown in tables
below.
Tube Side
Material Cupro-nickel
Outer diameter, Do 19 mm
Number of tube 92
Shell Side
Pitch Triangle
Baffle cut 25 %
Parameter Values
Tube side
Outer diameter,do (mm) 20.00
Inner diameter, di (mm) 16.00
length of tube, L (m) 1.78
Area of one tube, A (m2) 0.11
Number of tubes 13.6
250
Reboiler (B-101) are used with distillation column (D-101) to vapourise a fraction of
the bottom product. In the reboiler, liquid flows from the column into the shell where
there is a tube bundle. Boiling taking place from the outside the tube bundle and the
vapour passes back to the column (Hewitt 1983). There is a retaining wall or overflow
weir separating the tube bundle from the reboiler section, where residual reboiled liquid
(bottom product) is withdrawn, so that the tube bundle is kept covered with liquid.
Kettle reboilers are the easiest and reliable type of reboiler to design. It can handle high
vapourization of up to 80% and are easy to maintain.
6479.07
Total heat load = (142.38 + 133.08) × ( ) = 495.76 𝑘𝑊
3600
From Figure 12.1 (Coulson & Richardson 2005), assume value U=300 W/m2 oC
Mean temperature difference; both sides isothermal, steam saturation temperature at 1.4
bar = 126.3 oC
𝐴 = 27.43 𝑚2
Select 16 mm inner diameter, i.d and 20 mm outer diameter, o.d for plain tubes.
27.43
Number of tubes = = 60 𝑡𝑢𝑏𝑒𝑠
0.02×𝜋×3.66
By using the Monstinski’s equation, the heat flux based on estimated area can be
calculated:
Heat flux, q:
𝑄𝑚𝑎𝑥
𝑞=
𝐴𝑟𝑒𝑎 (𝑜𝑢𝑡𝑠𝑖𝑑𝑒)
= 18.97 𝑘𝑊/𝑚2
𝑃 0.17 𝑃 𝑃
ℎ𝑛𝑏 = 0.104𝑃𝑐 0.69 𝑞 0.7 [1.8( ) + 4( )1.2 + 10( )10 ]
𝑃𝑐 𝑃𝑐 𝑃𝑐
Overall coefficient, Uo
0.02
1 1 1 0.02 ln (0.016) 20 1 1
= + + + ( + )
𝑈𝑜 947.9 5000 2 × 16 16 5000 8000
𝑈𝑜 = 555.35 𝑊 ⁄𝑚2 °𝐶
Check the maximum allowable heat flux by using the modified Zuber equation.
258
𝑃𝑡 𝜆
𝑍𝑢𝑏𝑒𝑟 ′ 𝑠 𝑒𝑞𝑢𝑎𝑡𝑖𝑜𝑛: 𝑞𝑐 = 𝐾𝑏 ( ) ( ) [𝜎𝑔(𝜌𝐿 − 𝜌𝑣 )𝜌𝑣 2 ]0.25
𝑑𝑜 √𝑁
𝑞𝑐 = 214.7 𝑊 ⁄𝑚2
Assume liquid level 51% = 261 mm from base, freeboard = 512-261 = 251mm > 250
mm.
6479.07 1 1
Vapour velocity at surface = × 1.33 × 10.6 = 0.13 𝑚⁄𝑠
3600
𝜌𝐿 −𝜌𝑣 1⁄2
Maximum allowable velocity: 𝑢̂𝑣 < 0.2[ ]
𝜌𝑣
CHAPTER XI
MECHANICAL DESIGN
The operating temperature and pressure are 375ºC and 40 bar respectively. In this
reactor consists of triglycerides, hydrogen gas, propane and paraffin. This chemical
needs special construction material to construct the pressure vessel. Stainless steel SA-240
grade 304 is selected as the construction material since its excellent resistance to corrosion
and is available in a wide range of standard forms and sizes. This grade is an austenitic
chromium alloy which contains 18% chromium and 8% nickel has high the tensile strength
and high yield strength.
The mechanical design of Packed Bed Reactor R-101 is subjected to ASME internal
pressure procedure. This is because the absolute pressure of the vessel is higher than
the atmospheric pressure, which is higher than 15 psi. Figure below shows the shape of
the vessel and its dimension. Cylindrical body is chosen because this is the common
shape of reactor shell. And ellipsoidal heads are chosen for both bottom and top. This
is because it is more economical, and suitable for high pressure and domed to reduce
mechanical stresses.
261
The table below shows the operating conditions of reactor, R-101 and design
specification of the reactor.
𝐷𝑖
ℎ𝑒 =
4
0.591
=
4
= 0.1478 𝑚
ℎ𝐶 = 𝐻 − 2ℎ𝑒
= 1.773 − 2(0.1478)
= 1.478 𝑚
The wall thickness formulas for each part of the column are from ASME Code UG-
32(d) and UG-27 (c). The maximum allowable stress value, S is from ASME Code
givenin Subpart 1 of Section II, Part D.
𝑃𝐷 (638.40)(23.271)
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠, 𝑡 = =
2𝑆𝐸 − 0.2𝑃 2(17694.6)(0.8) − 0.2(638.40)
= 0.5271 in
Cylinder shell,
𝑃𝑅 (640.71)(23.271/2)
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠, 𝑡 = =
𝑆𝐸 − 0.6𝑃 (17694.6)(0.8) − 0.6(640.71)
= 0.5413 in
𝑃𝐷 (640.94)(23.271)
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠, 𝑡 = =
2𝑆𝐸 − 0.2𝑃 2(17694.6)(0.8) − 0.2(638.40)
= 0.5292 in
Thus, the overall thickness, toverall is determined, which is the highest value of minimum
thickness calculated for each part
t= 13.5 + 2 = 15.5mm
tmin = tnominal – CA
= 16.0 mm – 2 mm
= 14 mm (0.551 in)
The table below shows summary calculation of internal and MAWP of reactor and
primary stress. All calculation stated at Appendix J.1.
Table 11.3 Internal pressure and MAWPvessel for each part of the reactor R-101
Part of the column MAWPpart (psi) Static head, PH(psi) MAWPvessel
(psi)
Top ellipsoidal head 571.91 0.21 571.70
A cooling jacket is designed into R-101 for cooling purposes which are to prevent any
heat loss and also maintaining the temperature of the system. The Type 1 jacket, which
confined entirely to the cylindrical shell is chosen as listed in ASME code. The closure
of the jacket chosen to be typed (b-1) as shown in FIG 9-5, ASME code, Section VIII-
Division I. Type of jacket used for this reactor is dimple jacket since it can withstand
high temperature and high pressure. For the material construction for the jacket packed
bed reactor which is stainless steel grade 340. Figure 1.3 and 1.4 show Type 1 jacketed
vessels and type (b-1) closure for a jacket, respectively.
To find the minimum thickness of closure member, trc. It should be at least equal
or not less than minimum thickness of jacket, trj nominal thickness of outer jacket wall,
tj can be calculated based on the formula below.
265
𝑡𝑟𝑐 = 0.707𝑗√𝑃/𝑆
𝑡𝑗 = 2𝑡𝑟𝑐
𝑡𝑟𝑐 = 0.707𝑗√𝑃/𝑆
= 0.707(1)√(15)/(7901.08)
= 1.7146 𝑖𝑛
= 43.55 𝑚𝑚
𝑡𝑐 = 43.55 𝑚𝑚 + 2 𝑚𝑚 (𝐶𝐴)
𝑡𝑟𝑐 = 45.55 𝑚𝑚
266
The vessels support must be designed to withstand the weight of the vessel including
weight of material are packed inside and contents and any superimposed loads such as
wind loads. Support will impose localized loads on the vessel wall, and the design must
be checked to ensure resulting stress concentrations are below the maximum allowable
design stress. It is also important to allow the ease of access to the vessel and the fittings
for inspection and maintenance (Sinnott 2005).
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required for maintenance
or inspection. It also used on the vessel body when it is required to divide the vessel
into sections for transport and maintenance. It reduce high-stress concentration at the
base of the flange by transferring stress to the adjoining pipe. Welding-neck flangeis
the best-designed butt weld available because of its inherent structural value and easeof
assembly. Welding-neck flange have high strength and high resistance to dishing, itis
manufactured with a long-tapered hub. The tapered hub is created by the gradual
increase in metal thickness from the weld join to the flange facing. The welding-neck
flange diagram is shown in Figure 11.3 below.
267
Table 11.5 Size of flanges used for fitting on each pipe on R-101
Stream NPS D(mm) B(mm) H(mm) OD(mm) f (mm) L(mm) K(mm) N(mm)
8 14 77 12 26 36 4 11 52 28
11 14 92 16 26 36 2 14 62 29.6
14 14 77 12 26 36 4 11 52 28
15 14 92 16 26 36 2 14 62 29.6
By considering the internal pressure of the vessel, reactor R-101, the conditions that are
needed for the design have been calculated through series of formula stated. The
conditions for the design have been summarized as followed in Table 11.6. All the
calculation stated at Appendix J.1
268
11.2.1 Introduction
Distillation column (D-104) in the production of aviation fuel from waste cooking oil
is used to separate mainly decane and paraffin. There are also other components in small
quantity such as water and petrol. Table 12.1 and table 12.2 shows the components and
operating conditions respectively.
Sieve plate tray column is chosen in our production plant as it is cheaper in terms of
cost. This type of regeneration column can handle with wide variation of flow rates and
easy installation since it has a lighter wight. Vapor comes out from the holes to give a
270
multi orifice effect. The vapor velocity keeps the liquid from flowing down through the
holes.
Firstly, the volatility and boiling point of each key components were identified.
Components with high volatility and low boiling point make up light key components
while components with low volatility and high boiling point make up the heavy key
components. Light key components will be top products and heavy key components
will be bottom products. In this distillation column Decane petrol and water are top
products while paraffin is a bottom product.
𝐵
Log10 𝑃 = 𝐴 −
𝐶+𝑇
𝑃 𝑠𝑎𝑡
𝐾=
𝑃
Relative volatility of top product and bottom products are both calculated by using the
following equation. Table 12.3 shows the relative volatilities of end products.
𝐾𝑗.𝑚
𝑎𝑖,𝑗 =
𝐾𝑗,𝑝
(1 × 689.58)0.5
= 26.25
Thus, the minimum number of stages is determined using Mc Cabe Thiele Method.
Table 12.4 shows the plotting point for equilibrium curve
𝑎1,2 𝑥1
𝑦1 =
1 + 𝑥1 (𝑎1,2−1 )
The wquilibrium curve 45 degree line and composition of feed, top product and bottom
product (𝑥𝑓 = 0.69, 𝑥𝑑 = 0.98, 𝑥𝑏 = 0.02) are plotted on graph. Based on the curve and
composition plotted in figur 11.5, the minimum number of stages are stages.
272
To determine the minimum reflux ratio, q-line has been drawn from 𝑥𝑓 and 𝑥𝑑 using
equation to find q.
𝐿𝑓
𝑞=
𝐹
= 0.9
𝑞 𝑥𝑓
𝑞=( )𝑥 +( ) = −9𝑥 + 0.58
𝑞−1 𝑞−1
Rmin is determined from the intersection of rectifying section operating line and the
equilibrium curve. This happens at a slope of 0.91
Rmin = 10.1
The theoretical number of stages can be estimated by drawing rectifying and stripping
operating line and actual number of stages is determined. Figure 11.6 shows the plot of
actual number of stages.
N= 10 stages
Pressure vessel is made of cylindrical shell. The ends are closed by ellipsoidal heads.
Thuis is chosen based on operating pressure less than 10 bar where it is cheaper and
easier to fabricate compared to ellipsoidal (source). Ellipsoidal head parameter is taken
from nominal head available in market by referring inside diameter calculated.
𝐿 √𝑝𝑣
𝐹=
𝑉 𝑝𝑙
p = Liquid density
0.3171 0.485
𝐹𝐿𝑉 = √ = 0.00124
5.081 1223.9
By assuming tray spacing is 18 inch, along with the calculated flv. Cf value is
determined at 0.25 from source. The flooding velocity Uf is calculated by using
equation
𝑝𝐿 − 𝑝𝑉
𝑈𝑓 = 𝐹𝑆𝑇 𝐹𝐹 𝐹𝐻𝐴 𝐶𝑓 √
𝑝𝑉
FHA= 1.0 for Ab/Aa > 0.1 and 5 (Ab/Aa) + 0.5 for 0.06 < Ab/Aa <0.1
1223.91 − 0.485
𝑈𝑓 = (0.05)(0.6)(1)(0.25)√
0.485
√(4𝑣𝑀𝑉 )
Dimeter of column, 𝐷𝑇 = 𝐴 = 1.45 m
𝑓𝑈𝑓 (𝑎− 𝑑 )𝑝𝑣
𝐴
275
The column height for a distillation column is determined using the equation tray
spacing times with number of stage. Table 12.5 shows the number of stages and tray
spacing.
= 0.4572 × 12
= 5.5864 𝑚
Height of ellipsoidal head is determined by using following equation. Table 12.6 shows
the height of ellipsoidal head for top and bottom part
Since the operating pressure of the reactor 3 atm is greater than atmospheric pressure (
Pa> Patm) the reactor is designed under internal pressure. Firstly, the design opressure
for each part of f the vveesel is calculated by using equation:
𝑃𝐷 = 𝑃𝑜 + 0.433ℎ
𝑃𝑜 = 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑝𝑟𝑒𝑠𝑠𝑢𝑟𝑒
10% is added to design pressure as safety factor. Table 12.7 shows the design opressure
for each part of regeneration column.
Part h (ft) 𝑷𝑫 𝑷𝑫
Top head 1.109 22.520 24.772
Shell 19.109 30.314 33.345
Bottom head 20.218 30.794 33.873
The maximum operating temperature of regeneration column is 155C. Thus, the design
temperature have to be 205c after adding 50C for safety purposes
From ASME code VIII, the maximum allowable stress for carbon steel is 13758 psi
is when circumferential welded joint involving main shell, nozzles, transisiton diameter
and flanges are interecting with longitudinal welded joints.
The fluid inside the column is moderately corrosive so 4mm is chose as the minimum
corrosion allowance
The vessel diameter is 88888 so the minimum thickness is 6mm including 2 mm for
corrosion allowance. However, since the paraffin is partially corrosive the corrosion
allowance is
The method used to support vessel will depend on the size, shape and wight of vessel,
the design temperature and pressure, the vessel location and arrangement and internal
278
fittings and attachments. Skirt support is used as they are particularly suitable for tall
column subject to wind loading.
a. Skirt thickness
The minimum heioght of the skirt is normally set by the process based on the NPSH
requirements of the pumps or the reboiler hydraulixc requirements, Tus, skirt support
height for reactor, hsk = 1 m.
Ds=Di = 1.45m
W = 1733.84 N
𝑊𝑥 2
Bending moment at the base of skirt Ms = = 66568.048Nm
2
4𝑀𝑠
𝜎𝑏𝑠 =
Π(𝐷𝑠 + 𝑡𝑠𝑘 )𝑡𝑠𝑘 𝐷𝑠
𝑁
= 2861766.307 𝑚𝑚2
𝑊𝑠
𝜎𝑤𝑠 =
Π(𝐷𝑠 + 𝑡𝑠𝑘 )𝑡𝑠𝑘
279
= 0.025 𝑁/𝑚𝑚2
Assumptions:
Base angle, 𝜃𝑠 = 90
𝑡 16
0.125𝐸 ( 𝐷𝑠𝑘 ) 𝑠𝑖𝑛𝜃𝑠 = 0.125 × 200000 × (1352.56) sin 90 = 264.386 𝑁/𝑚𝑚2
𝑠
𝑡
𝜎𝑆 (𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒) < 0.125𝐸 ( 𝐷𝑠𝑘 ) 𝑠𝑖𝑛𝜃𝑠 → 2.837𝑁/𝑚𝑚2 < 264.386 𝑁/𝑚𝑚2
𝑠
Since both criteria are satisfied, the assumed value of skirt thickness 𝑡𝑠 = 0.010 m is
acceptable. With corrosion allowance of 2mm, the design skirt thickness, 𝑡𝑠 =0.012 m
=18 m. Table 12.8 shows the summary of skirt design.
Skirt thickness mm 12
The loads carried by the skirt will be transmitted to the foundation slab by the skirt base
ring. The moment produced by wind other lateral loads will tend to overturn the pressure
vessel. This will be opposed by the couple set up by the weight of vessel and tensile
load of anchor bolts, For our column, single plate with gusset as the base ring design of
the skirt support is used. The anchor bolts assumed to share the overturning load
equally, and the bolt area required is given by:
1 4𝑀𝑏
𝐴𝑏 = [ − 𝑊]
𝐴𝑏 𝐴𝑏 𝐷𝑏
Assumption:
1 66568.048
𝐴𝑏 = [4 × − 1733.840]
8 × 125 1.4
= 188.461 mm
281
The bese ring must be sufficiently wide to distribute the load to the foundation. The
total compressive load on the base ring is determined.
4𝑀 𝑊
𝐹𝑏 = [𝜋𝐷2𝑠 − 𝜋𝐷 ]= 46.73 kN/m
𝑠 𝑠
𝐹𝑏 1
The minimum width of the base ring, 𝐿𝑏 = × 103
𝑓𝑐
𝐹𝑏 1
𝐿𝑏 = × 103 = 13.35 mm
𝑓𝑐
This is the minimum widthrequired, actual width depends on the chair design.
As the bolt diameter calculated is 45.80 mm. Norminal bolt size M48 (BS 4190 1967)
is used.
𝐹 46.731
= 𝑎𝑐𝑡𝑢𝑎𝑙 𝑤𝑖𝑑𝑡ℎ𝑏 𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 = = 0.320 𝑁/𝑚𝑚2
146
√3(𝑓𝑐′ ) √3(0.568)
𝐿𝑟 = 𝐿𝑟 =6.294mm (round off to 10 mm)
𝐹𝑟 140
Flanged joints are used for connecting pipes and instruments to vessels, for manhole
cover, and for removable vessel heads when ease of access is required. Welding neck
flange can reduce high-stress concentration at the base of the flange by transferring
282
stress to the adjoining pipe. It has high strength and high resistance to dishing,
manufacturing with a long-tapered hub.
The summary nof mechanical design of Distillation Column D-104 is shown in table
12.10
Condition Values
Operating Pressure, 𝑷𝟎 (bar) 1.6
Temperature (°C) 25
Type of material Carbon Steel
Corrosion allowance, CA (mm) 4
Joint efficiency, E 0.85
H/D 4
Assumption Type
Top head Ellipsoidal 2:1
Shell Cylindrical
Bottom head Ellipsoidal 2:1
284
𝐷𝑖 2.94
ℎ𝑒 = = = 0.735𝑚
4 4
The skirt support had been chosen as the support for gas absorption. Since the height of
gas absorption is 11.76 m with the internal diameter, 𝐷𝑖 is 2.94 m, the skirt support is
suitable for the use of tall columns which subject to wind loading. One of the most
important factor is they do not imposed concentrated load on the vessel shell.
Welded – neck flange is chosen in this design because it is suitable for extreme
conditions where the flange is likely to be subjected to temperature, shear and vibration
loads for the absorption column, G-101. The welded connection will not interfere with
the flow of the fluid.
285
The skirt thickness must be sufficient to withstand the dead-weight loads and bending
moments imposed on it by the vessel and it will not be under the vessel pressure.
The skirt base ring transmits the loads carried by the skirt to the foundation slab. Wind
and other lateral loads will tend to overturn the vessel, but this will be countered by the
couple formed by the vessel's weight and the tensile load. For G-101, random packing
design as the base ring design of the skirt support is used to make the vessel more stable
and stronger.
Table 11.22 shows the base ring and anchor bolt specification for DC-101.
Flanged joints are utilized to connect pipes and instruments to vessels, as well as
manhole covers and removable vessel heads. When it is required to divide the vessel
into sections for maintenance or transport, flanges might be utilized on the vessel body.
Pipes are also joined together with flanged joints. Flanged joints are also used to connect
pipes to other. Different types of flanges are used for various purposes.
In the G-101, welding-neck flanges are used. It has a long-tapered hub between
the flange ring and the welded joint. This gradual transition of the section reduces the
discontinuity stresses between the flange and branch and increase the strength of the
flange assembly. Welding-neck flanges are suitable for extreme service conditions,
where the flange is likely to be subjected to temperature, shear and vibration loads.
Welding-neck flanges were found to be the best option for this design. Details of the
flanges design are summarized in
By considering the internal pressure of the vessel, absorption column G-101, the
conditions that are needed for the design have been calculated through series of formula
stated. The design of gas absorption is summarized and tabulated as followed in table
below. The detailed calculation for the mechanical design in Appendix J.3.
Reboiler (B-101) is used to vapourize mixture and return the vapour back to the
distillation column (D-101). Boiling takes place from outside the tube bundle and at
maximum temperature of 180℃ at 1.3 bar. Steam is used as the service fluid of the
kettle reboiler at 1.8 bar at tube side. The specification of the vessel is shown in Table
11.24.
steel), S
Corrosion allowance, CA 2 mm
Safety factor 10%
Joint efficiency, E 0.85
The thickness of the vessel's wall is determined by the amount of pressure it can handle,
and as the pressure rises, so does the thickness. According to ASME code UG-32(d)
and UG-27, the minimum wall thickness, tmin, is computed (c). The nominal thickness,
tnominal, that is accessible on the market will be compared to the highest value of tmin.
Before that, the original thickness, tcal will be calculated to know the required thickness
for each part as shown in
Highest value of tcal will be taken as uniformity and only longitudinal joints will
be considered as circumferential joint results low thickness value. Table 4 shows the
tmin calculations by considering corrosion allowance and nominal thickness.
289
The MAWP part is the maximum pressure each part can withstand. The calculation is
shown in Table 11.28
There are a few types of weight that need to take into account when calculating
the total weight of the vessel. The combined loading and weight analysis are shown in
Table 11.29 below.
The saddle support is the most frequent type of support for shell and tube heat
exchangers. The total relative stress on the saddle is computed to ensure that it does not
exceed the saddle's maximum capacity.
A flange is a piece of equipment that connects pipes, valves, and other pieces of
equipment to construct a plumbing system. Flanges can also be utilised to join vessel
components, allowing for easy cleaning, inspection, and modification. Flanged joints
are produced by bolting two flanges together and sealing them with a gasket. Welding
neck flanges were chosen because they are suited for rigorous service situations in
which the flange would be exposed to temperature, shear, and vibration loads.
For the cooler design, carbon steel SA516 (grade 70) is used as the material of
construction. Carbon steel is most commonly used engineering material as it is cheap,
available in a wide range of standard forms and sizes, has good tensile strength and
292
ductility. The calculations of design of the cooler are to ensure the equipment is safe to
be used. The data for mechanical design of the heat exchanger is shown in Error!
Reference source not found..
Parameter Value
Joint efficiency, E 1
Since Po>Patm, the design will follow the internal pressure procedure. As the heat
exchanger will be fitted horizontally, the cylinder height equal to the shell diameter,
where h=Ds. The wall thickness, t for each part of the pressure vessel has to be known
in order to get the minimum wall thickness, tmin which is needed in maximum allowable
working pressure (MAWP) part calculation.
Circumferential stress:
293
𝑃𝑅
𝑡1 =
𝑆𝐸 − 0.6𝑃
(159.96)(5.21)
=
(20000)(1) − 0.6(159.96)
= 0.0419 𝑖𝑛
Longitudinal stress:
𝑃𝑅
𝑡2 =
𝑆𝐸 + 0.4𝑃
(159.96)(5.21)
=
(20000)(1) − 0.4(159.96)
= 0.0209 𝑖𝑛
𝑃𝐿
𝑡3 =
2𝑆𝐸 − 0.2𝑃
(159.96)(1.63)
=
2(20000)(1) − 0.2(159.96)
= 0.0065 𝑖𝑛
To account for corrosion that might happen in the vessel, corrosion allowance is added
for every thickness obtained. Since the process fluid is corrosive, we choose the
minimum value for corrosion allowance, CA = 4 mm (0.157 in) as safety precaution to
allow material loss due to hydrogen embrittlement and erosion.
𝑆𝐸𝑡
𝑃=
𝑅 + 0.6𝑡
2𝑆𝐸𝑡
𝑃=
𝑅 − 0.4𝑡
𝑆𝐸𝑡
𝑃=
𝐿 + 0.2𝑡
Hence, subtract the hydrostatic pressure for each part to obtain MAWPvessel.
The result of MAWPpart and MAWPvessel are tabulated in Table 11.33 below.
Cylindrical Shell
We take the smallest value from cylindrical shell circumferential stress to be the
MAWPvessel which is 941 psi.
Pressure vessels are subjected to other loads in addition to pressure and must be
designed to withstand the worst combination of loading without failure.
a. Primary Stresses
For a cylindrical vessel, primary stresses (required to achieve static equilibrium) are due
to following sources:
c) Bending stresses due to wind loads, seismic loads and external loads.
b. Direct stress
Shell Weight, Ws
Cv = 1.08
Ws = 240CvDmHv +0.8Dmt
= 240(1.08)(0.266)(2.784) + 0.8(0.22)(2)
296
= 414.29 N
Tube Weight, Wt
Number of tubes, Nt = 56
= 128.06 𝑁
Internal fitting, Wf
Number of baffles = 26
Area, As = 0.0028 m2
= 8.415 𝑁
Number of tubes, Nt = 56
′
𝜋𝜌𝑡 𝑑𝑖2 𝑁𝑡 𝑔
𝐹𝑙𝑜𝑤 𝑠 𝑤𝑒𝑖𝑔ℎ𝑡 =
4
= 3509.5 𝑁
𝐹𝑙𝑜𝑤 ′ 𝑠 𝑤𝑒𝑖𝑔ℎ𝑡 = 𝜌𝑠 𝐴𝑠 𝐻𝑠 𝑔
= 600.6 𝑁
= 4660.9 N =4.66 kN
𝑊𝑡
𝐷𝑖𝑟𝑒𝑐𝑡 𝑠𝑡𝑟𝑒𝑠𝑠, 𝜎𝑤 =
𝜋(𝐷𝑖 + 𝑡)𝑡
= 2.782 𝑁/𝑚𝑚2
The direct stress, σw will be tensile (positive) for points below the plane of the vessel
supports and compressive (negative) for points above the supports.
298
Circumferential stress
𝑃𝐷𝑖 (159.95)(0.265)
𝜎ℎ = = = 10.58 𝑁/𝑚𝑚2
4𝑡 4(2)
Longitudinal stress
𝑃𝐷𝑖 (159.95)(0.265)
𝜎ℎ = = = 5.29 𝑁/𝑚𝑚2
4𝑡 4(2)
d. Principal Stresses
1
𝜎1 = [𝜎 + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
1
𝜎1 = [𝜎 + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
𝜎1 = 0.5𝑃
Where,
σw = should be counted as positive if tension and negative if compressive (in our case
is negative due to compressive stress)
Therefore,
σz = 8.073
σ1 =10.58
299
σ2 = 8.073
The maximum shear-stress theory is normally used for pressure vessel design. The
maximum stress intensity, (∆σ)max at any point is taken for design purposes as the
greatest value of the formula below.
σ1 – σ2 = 2.51 N/mm2
σ1 – σ2 = 10.58 N/mm2
σ1 – σ2 = 8.073 N/mm2
The design is safe because the (∆σ)max does not exceed the design stress, S for the
material of construction at any point for the vessel wall thickness. Thus, the analysis of
stress obeyed the condition.
e. Bending stress
Since the heat exchanger is in horizontal position and not considered tall, there is
assumed to be no wind loads and hence the bending stress, σb = 0.
f. Elastic stability
When a material structure is not elastically stable, the buckling failure will occur and
results in a sudden change in shape of the structure. This could happen when the material
lacks sufficient stiffness or rigidity to withstand the load.
For a curve plate subjected to an axial compressive load, the critical buckling stress,
300
𝐸 𝑡
𝜎𝑐 =
3(1 − 𝑣 2 ) 𝑅𝑝
For carbon steel at ambient T, E = 200000 N/mm2 and with a safety factor of 12 and
Poisson’s ratio, v = 0.3 gives
𝑡 2
𝜎𝑐 = (2 × 104 ) = (2 × 104 ) = 1511.33 𝑁/𝑚𝑚2
𝐷𝑖 264.6
The vessels support must be designed to withstand the weight of the vessel and contents
and any superimposed loads such as wind loads. Horizontal vessels are installed on two
saddle supports as shown in figure 1.1. A vessel supported on two saddles can be known
as simple beam. The location in which the limit at the supports and at the mid is equal
in magnitude would be at an equally uniform charge and the distribution of the
longitudinal axial bending moment.
The total weight loads that have to be withstand by the saddle support is 4660.9
N with a vessel diameter of 0.265 m. From Chemical Engineering Design Sinnot (2009),
the dimension of the standard saddle support should be designed according to the
following conditions in table 1.4 where figure 1.2 illustrates the dimensions of the
conditions.
301
Table 11.34 Standard Dimensions for Saddle Supports with Vessel Diameter
0.3m
Flanged joints are used for connecting pipes and instruments to vessels, for
manhole cover, and for removable vessel heads when ease of access is required. It also
used on the vessel body when it is required to divide the vessel into sections for transport
and maintenance. It can reduce high-stress concentration at the base of the flange by
transferring stress to the adjoining pipe. Welding-neck flange is the best-designed butt
weld available because of its inherent structural value and ease of assembly. Welding-
neck flange has high strength and high resistance to dishing, it is manufactured with a
long-tapered hub. The tapered hub is created by the gradual increase in metal thickness
from the weld join to the flange facing. The welding-neck flange diagram is shown in
Figure 11.12.
302
Table 11.35 Size of flanges used for fitting on each pipe on C-101
Tube inlet 0.75 99 20.8 15.7 4 12.7 52.3 38.1 26.7 42.9 0.73
Tube outlet 0.75 99 20.8 15.7 4 12.7 52.3 38.1 26.7 42.9 0.73
Stream 12 25.4 108 26.7 15.7 4 14.2 55.6 49.3 33.5 50.8 1.05
Stream 17 25.4 108 26.7 15.7 4 14.2 55.6 49.3 33.5 50.8 1.05
By considering the internal pressure of the vessel, Cooler C-101, the conditions
that are needed for the design have been calculated through series of formulae stated.
The conditions for the design our cooler have been summarized and tabulated as
followed in Table 6.8.
Corrosion allowance, CA 4 mm
Number of bolts 4
CONCLUSION
For the conclusion, our plant production is focus on production of decane as sustainable
aviation fuel. Decane is a component of kerosene and gasoline (petrol) which is a non-
polar solvent. The process involved in our production is process hydrocracking and
hydrotreating process. Our raw material is triglycerides and hydrogen gas to produce
decane. This source can be obtained from waste cooking oil especially palm cooking
oil. Since malaysia known as second largest producer of palm oil in world thus source
of our production is easier to obtained. Our main product is decane and for by product
is as paraffin, propane, petrol, carbon monoxide and water. The conversion of decane
by process hydrocracking and hydrotreating process from waste cooking oil is 80% and
the plant capacity for our production is 10416.67 kg/hr which is continuous process.
Furthermore, the total heat energy recovery from heat integration is 50.86 % obtained
by using the pinch analysis steps. For piping and instrumentation diagram (p&id) the
type of configuration used are temperature control, pressure control, flow control, level
control and composition control. It can be done by finding mathematical model for each
of the unit processes and from the degree of freedom configuration type can be predict.
Meanwhile relief system used in our plant is spring loaded valve that can be found at
reactor and distillation column. For every waste produced during the process, it must
undergo treatment process before it can discharge through the drainage. The value of
cod and bod of inlet stream wastewater containing is 11814.69 and 3544.41 mg/l
respectively. After the treatment process, the value of cod and bod is reduced to 100
and 30 mg/l respectively which below standard b discharge limit. Other that for
economic analysis our plant npv value is positive, rm 629.15 million value with 31%
DCFRR, considered as profitable and favorable. Also, our production is is expected to
have a profit after three years which is the estimated payback period is 3.2 years. All
the chemical hazards, toxic and flammable materials in this production are identified
where most of our materials is flammable. Lastly for our site location is Tanjung
Langsat Industrial Compkex, 81700 Pasir Gudang, Johor with the highest marks
compared from other site location.
305
REFERENCE
Bezergianni, S., Dimitriadis, A., Kalogianni, A. & Pilavachi, P.A. 2010. Hydrotreating
of waste cooking oil for biodiesel production. Part I: Effect of temperature on
product yields and heteroatom removal. Bioresource Technology 101(17):
6651–6656.
Díaz-Pérez, M. A., & Serrano-Ruiz, J. C. (2020). Catalytic production of jet fuels from
biomass. In Molecules (Vol. 25, Issue 4). MDPI AG.
https://doi.org/10.3390/molecules25040802
Chen, R.X. & Wang, W.C. 2019. The production of renewable aviation fuel from waste
cooking oil. Part I: Bio-alkane conversion through hydro-processing of oil.
Renewable Energy 135: 819–835.
Goh, B.H.H., Chong, C.T., Ge, Y., Ong, H.C., Ng, J.H., Tian, B., Ashokkumar, V., Lim,
S., Seljak, T. & Józsa, V. 2020a. Progress in utilisation of waste cooking oil for
sustainable biodiesel and biojet fuel production. Energy Conversion and
Management 223(August).
Goh, B.H.H., Chong, C.T., Ge, Y., Ong, H.C., Ng, J.H., Tian, B., Ashokkumar, V., Lim,
S., Seljak, T. & Józsa, V. 2020b, November 1. Progress in utilisation of waste
cooking oil for sustainable biodiesel and biojet fuel production. Energy
Conversion and Management. Elsevier Ltd.
Goh, B. H. H., Chong, C. T., Ge, Y., Ong, H. C., Ng, J. H., Tian, B., Ashokkumar, V.,
Lim, S., Seljak, T., & Józsa, V. (2020). Progress in utilisation of waste cooking
oil for sustainable biodiesel and biojet fuel production. In Energy Conversion
and Management (Vol. 223). Elsevier Ltd.
https://doi.org/10.1016/j.enconman.2020.113296
Huq, N. A., Hafenstine, G. R., Huo, X., Nguyen, H., Tifft, S. M., Conklin, D. R., Stück,
D., Stunkel, J., Yang, Z., Heyne, J. S., Wiatrowski, M. R., Zhang, Y., Tao, L.,
Zhu, J., Mcenally C , C. S., Christensen, E. D., Hays, C., van Allsburg, K. M.,
Unocic, K. A., … Vardon, D. R. (n.d.). Toward net-zero sustainable aviation
fuel with wet waste-derived volatile fatty acids.
https://doi.org/10.1073/pnas.2023008118/-/DCSupplemental
Kallio, P., Pásztor, A., Akhtar, M. K., & Jones, P. R. (2014). Renewable jet fuel. In
Current Opinion in Biotechnology (Vol. 26, pp. 50–55).
https://doi.org/10.1016/j.copbio.2013.09.006
Lin, C. H., Chen, Y. K., & Wang, W. C. (2020). The production of bio-jet fuel from
palm oil derived alkanes. Fuel, 260. https://doi.org/10.1016/j.fuel.2019.116345
306
Marshall Swift Valuation Services. 2018. Report - Inventory Index Factors 1–9.
Morgan, T.J., Youkhana, A., Turn, S.Q., Ogoshi, R. & Garcia-Pérez, M. 2019. Review
of Biomass Resources and Conversion Technologies for Alternative Jet Fuel
Production in Hawai’i and Tropical Regions. Energy and Fuels 33(4): 2699–
2762.
MPOB. 2017. Welcome to the Malaysian Palm Oil Board // Malaysian Palm Oil
Industry // Washington, DC // 1-202-572-9768. Official Palm Oil Information
Source.
Muanruksa, P., Winterburn, J., & Kaewkannetra, P. (2021). Biojet fuel production from
waste of palm oil mill effluent through enzymatic hydrolysis and
decarboxylation. Catalysts, 11(1), 1–10. https://doi.org/10.3390/catal11010078
Murphy, H. T., O’Connell, D. A., Raison, R. J., Warden, A. C., Booth, T. H., Herr, A.,
Braid, A. L., Crawford, D. F., Hayward, J. A., Jovanovic, T., McIvor, J. G.,
O’Connor, M. H., Poole, M. L., Prestwidge, D., Raisbeck-Brown, N., & Rye, L.
(2015). Biomass production for sustainable aviation fuels: A regional case study
in Queensland. In Renewable and Sustainable Energy Reviews (Vol. 44, pp.
738–750). Elsevier Ltd. https://doi.org/10.1016/j.rser.2015.01.012
Ng, K. S., Farooq, D., & Yang, A. (2021). Global biorenewable development strategies
for sustainable aviation fuel production. In Renewable and Sustainable Energy
Reviews (Vol. 150). Elsevier Ltd. https://doi.org/10.1016/j.rser.2021.111502
Parihar, Y. & Prasad, E. 2020. Aviation Fuel Market Size, Share Statistics | Forecast -
2026.
Renewable Energy Agency, I. (2021). Reaching zero with renewables: Biojet fuels.
www.irena.org
TARRENCE TAN, R.R. and M.C. 2021. Raise min wage for blue-collar workers to
RM1,500, white-collar to RM2,500, Muar MP proposes | The Star.
TNB. 2020. Pricing & Tariffs - Tenaga Nasional Berhad. Tenaga Nasional.
Towler, G. & Sinnott, R. 2013. Principle, Practice and Economics of Plant and Process
Design. Journal of Chemical Information and Modeling. Vol. 53.
308
APPENDIX A
i. MASS BALANCE
a. Filter (F-101)
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
𝐹4 += 𝐹8 + 𝐹9
309
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
c. Stripper (G-102)
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
∑ 𝐹𝑖𝑛 = ∑ 𝐹𝑜𝑢𝑡
i. ENERGY BALANCE
a. Reactor (R-101)
Based on table C.1, standard heat of reaction was calculated by formula below:
̂ 𝑟 = ∑ 𝐻°
∆𝐻° ̂𝑓 (𝑝𝑟𝑜𝑑𝑢𝑐𝑡𝑠) − ∑ 𝐻°
̂𝑓 (𝑟𝑒𝑎𝑐𝑡𝑎𝑛𝑡)
∆𝐻𝑟𝑥𝑛 = 3∆𝐻𝑓 𝑝𝑎𝑟𝑎𝑓𝑓𝑖𝑛 + ∆𝐻𝑓 𝑝𝑟𝑜𝑝𝑎𝑛𝑒 − ∆𝐻𝑓 ℎ𝑦𝑑𝑟𝑜𝑔𝑒𝑛 𝑔𝑎𝑠 − ∆𝐻𝑓 𝑇𝑟𝑖𝑔𝑙𝑦𝑐𝑒𝑟𝑖𝑑𝑒𝑠
= -268633.8 kJ/mol
̂𝑖/𝑗 = ∫𝑇2 𝐶𝑝 𝑑𝑡
∆𝐻 𝑇1
𝑇2
=∫𝑇1 (𝑎 + 𝑏𝑇 + 𝑐𝑇 2 + 𝑑𝑇 3 𝑑𝑡
𝑏𝑇 2 𝑐𝑇 3 𝑐𝑇 4
=[𝑎𝑇 + + + ]
2 3 4
̂7
𝐻 = ∑ 𝑛7 ∆𝐻7
= (38.29 × 2516.42)
̂11
𝐻 = ∑ 𝑛11 ∆𝐻11
= (38.29 × 195.5)
= 6333291.98 kJ/h
̂12
𝐻 = ∑ 𝑛12 ∆𝐻12
= 23577063.93 kJ/h
̂16
𝐻 = ∑ 𝑛16 ∆𝐻16
317
= 50722260.78 kJ/h
h. Reactor (R-102)
The molar heat capacity of component in the reactor (R-102) were calculated and
simplify as table below:
2
Table A.9 Heat capacity of R-102
Components Molecular ∆𝐻22 ∆𝐻18 ∆𝐻33 ∆𝐻35
formular (kJ/kmol.K) (kJ/kmol.K) (kJ/kmol.K) (kJ/kmol.K)
Triglycerides C54H102O6 0 0 0 0
Hydrogen gas H2 0 1387577.60 0 1163446.741
Decane C10H22 0 0 7344564.688 0
Petrol C6H14 0 0 4713675.844 0
Propane C3H8 0 0 0 0
Paraffin C17H32O2 4459199.99 0 3672282.344 0
Carbon CO 0 0 0 21573754.18
monoxide
Water H2O 0 0 4289618.533 0
̂𝑥 = ∑ 𝑛𝑥 ∆𝐻𝑥
Total enthalpy, 𝐻
̂22
𝐻 = ∑ 𝑛22 ∆𝐻22
= (91.90 × 181.05)
= 4459199.99 kJ/h
̂18
𝐻 = ∑ 𝑛18 ∆𝐻18
= (275.71 × 2516.41)
= 1387577.60 kJ/h
̂35
𝐻 = ∑ 𝑛35 ∆𝐻35
= 22737200.92 kJ/h
̂33
𝐻 = ∑ 𝑛33 ∆𝐻33
= 20020141.41 kJ/h
i. Stripper (G-102)
The molar heat capacity of component in the distillation column (G-102) were
calculated and simplify as table below:
The molar heat capacity of component in the distillation column (D-101) were
calculated and simplify as table below:
The molar heat capacity of component in the distillation column (D-102) were
calculated and simplify as table below:
= (4051052.03+26261.91+1841387.29+236838.43) - (1573835.29 +
1010073.40 + 786917.65 + 904304.83 + 9443.01 + 599983.60 + 47215.06 +
487417.49)
321
The molar heat capacity of component in the distillation column (D-103) were
calculated and simplify as table below:
The molar heat capacity of component in the distillation column (D-104) were
calculated and simplify as table below:
APPENDIX B
1 Steam 27
out
WATER
Steam
15 in H-103 28 FAKULTI KEJURUTERAAN
2
HYDROGEN DAN ALAM BINA
BENZENE 16 17 GAS
CW in
P-101 31
JABATAN KEJURUTERAAN
CW
4 out C-102 PROPANE KIMIA DAN PROSES
3 G-101 29 30 32
CW in
WCO BENZENE
CW GROUP KK8
P-102 out C-104
G-102
PRODUCTION OF DECANE
F-101 33 CW 34 FROM WASTE COOKING OIL
in
9
WASTE GAS
CW
10
CW in
out C-105 46 47
Steam SUPERVISORS:
P-103 out
N-103
8
Steam H-102
in
CW out 1. ASSOC. PROF. DR MASLI
R-102 48 49 IRWAN BIN ROSLI
11
E-103
PETROL 2. DR. EBRAHIM MAHMOUDI
41 3. YEOW EU LUN (FAETH ASIA
CW in 39
PACIFIC)
N-102 51
22
38
CW out
in 18
K-101 37 CW
35 CW 36 Hot C-107 1. KASHVINWARMA A/L
water B-103 out
in
out
BASKARAN (A169128)
2. MUHAMMAD NA’IM NAJMI
CW
C-103 43
out P-105 BIN MOHAMAD SALJI (A168963)
54 CW in 55
3.NOR EZZATI AMIRA BINTI
CW in
CW 20 Steam MUSTAPA PADZIR (A169229)
in 44
D-102 in N-104 4. NUR ZAFIRAH ALIAH BINTI
42 CW out
N-101 BAHARUDDIN (A169320)
19
CW
C-101 CW out 56 E-104 57
out B-102 5. HUSNA BINTI AHMAD
E-101 Steam
21 out
DECANE
RADZUAN (A167664)
13
45
14
59
P-106 SUBMISSION DATE:
24 Steam
P-104 D-104 60 61
in CW in
17TH MAY 2022
58
PARAFFIN
Hot oil
D-101 in
25 26 Steam
CW C-108
CW in B-104 out
23 out
UNREACTED
CW out OIL SYMBOLS:
B-101 C-106
Hot oil
out
ORGANIC
WASTE Reactant
Product
Stream 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Temperature (°C) 25 25 25 25 25 25 110 25 25 25 110 375 140 140 25 375 25 110 180 125 110 110 190 200 200 25 110 25 30 25
Pressure (atm) 1 1 1 1.5 1 1.5 1.5 1.3 1.3 2 2 40 1.3 1.5 1.5 40 1.3 1.5 1.1 1.3 1.3 1.3 1.3 1.5 1.5 1 1.2 1 1.6 1.2
Phase L L S&L S&L G G G S L L L L L L L G L G G V L L L V L L V G V V
Mass flowrate of component (kg/h)
Triglycerides 0 0 32395.36 32395.36 0 0 0 0 32395.36 32395.36 32395.36 6479.07 6479.07 6479.07 0 0 0 0 0 0 0 0 6479.07 6479.07 6479.07 6479.07 0 0 0 0
Hydrogen gas 0 0 0 0 628 628 76.58 0 0 0 0 0 0 0 0 15.32 15.32 551.41 0 0 0 0 0 0 0 0 0 15.32 0 0
Decane 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Petrol 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Propane 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1347.89 1347.89 0 0 0 0 0 0 0 0 0 0 0 1347.89 1347.89
Paraffin 0 0 0 0 0 0 0 0 0 0 0 24629.66 24629.66 24629.66 0 0 0 0 24629.66 24629.66 24629.66 24629.66 0 0 0 0 0 0 0 0
Carbon monoxide 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Water 943.52 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 943.52 0 0 0
Benzene 0 92.83 0 0 0 0 0 0 0 0 0 0 0 0 92.83 0 0 0 0 0 0 0 0 0 0 0 0 0 92.83 92.83
Organic waste 0 0 0 0 0 0 0 25.05 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTAL 943.52 92.83 32395.36 32395.36 628.00 628.00 76.58 25.05 32395.36 32395.36 32395.36 31108.73 31108.73 31108.73 92.83 1363.21 1363.21 551.41 24629.66 24629.66 24629.66 24629.66 6479.07 6479.07 6479.07 6479.07 943.52 15.32 1440.72 1440.72
Stream 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61
Temperature (°C) 25 25 375 25 375 85 85 100 80 55 55 130 155 155 155 70 45 25 25 80 90 90 25 175 100 25 25 185 190 190 25
Pressure (atm) 1 1 40 1.8 40 1.3 1.5 1.4 1.5 1.5 1.5 1.4 1.6 1.6 1.7 1.2 1.4 1.4 1 1.3 1.6 1.6 1 1.2 1.4 1.4 1 1.3 1.6 1.6 1
Phase G L G G L L L G V L L L V L L G V L L L V L L G V L L L V L L
Mass flowrate of component (kg/h)
Triglycerides 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hydrogen gas 0 0 110 110 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Decane 0 0 0 0 10440.04 10440.04 10440.04 104.40 104.40 104.40 104.40 10335.63 10335.63 10335.63 10335.63 52.20 52.20 52.20 52.20 52.20 52.20 52.20 52.20 10232.28 10232.28 10232.28 10232.28 103.36 103.36 103.36 103.36
Petrol 0 0 0 0 6322.84 6322.84 6322.84 6259.61 6259.61 6259.61 6259.61 63.23 63.23 63.23 63.23 6197.01 6197.01 6197.01 6197.01 62.60 62.60 62.60 62.60 47.42 47.42 47.42 47.42 15.81 15.81 15.81 15.81
Propane 1347.89 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Paraffin 0 0 0.00 0.00 4925.93 4925.93 4925.93 492.59 492.59 492.59 492.59 4433.34 4433.34 4433.34 4433.34 246.30 246.30 246.30 246.30 246.30 246.30 246.30 246.30 44.33 44.33 44.33 44.33 4389.01 4389.01 4389.01 4389.01
Carbon monoxide 0 0 2058.60 2058.60 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Water 47.18 896.35 0 0 1323.38 1323.38 1323.38 1191.05 1191.05 1191.05 1191.05 132.34 132.34 132.34 132.34 11.91 11.91 11.91 11.91 1179.14 1179.14 1179.14 1179.14 92.64 92.64 92.64 92.64 39.70 39.70 39.70 39.70
Benzene 0 896.35 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Organic waste 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTAL 1395.07 1792.70 2168.88 2168.88 23012.19 23012.19 23012.19 8047.65 8047.65 8047.65 8047.65 14964.54 14964.54 14964.54 14964.54 6507.42 6507.42 6507.42 6507.42 1540.23 1540.23 1540.23 1540.23 10416.67 10416.67 10416.67 10416.67 4547.87 4547.87 4547.87 4547.87
326
APPENDIX C
SIMULATION
Reactor (R-101)
Stripper
Reactor (R-102)
APPENDIX D
WATER
16 29 FAKULTI KEJURUTERAAN
2 HYDROGEN DAN ALAM BINA
BENZENE GAS
12 CW 17
P-101 in JABATAN KEJURUTERAAN
38
CW
6 out C-101 PROPANE KIMIA DAN PROSES
3 G-101 30 CW 31 39
in
WCO BENZENE
CW
P-102 out C-103
GROUP KK8
G-102
F-101 13
9
40 PRODUCTION OF DECANE
CW in
FROM WASTE COOKING OIL
10
WASTE GAS
CW
P-103 out C-104 49 CW in 50
14 18 28
11 N-103
CW out SUPERVISORS:
J-102 J-103 51 52
32 E-103
J-101 PETROL 1. ASSOC. PROF. DR MASLI
44 IRWAN BIN ROSLI
CW in 42
2. DR. EBRAHIM MAHMOUDI
15 3. YEOW EU LUN (FAETH ASIA
N-102 54
41
5
CW out
E-103 PACIFIC)
R-102 43 Hot
7
R-101 water
D-103 in 55 CW 56
19 53 in
4 WASTEWATER
35 CW
8
GROUP MEMBERS:
HYDROGEN Steam
33 CW in
34 Hot B-103
out
C-106
out water
K-101 out 1. KASHVINWARMA A/L
27 CW out C-102 46 BASKARAN (A16)
Steam H-101 P-105
in 57 CW in 58 2. MUHAMMAD NA’IM NAJMI
CW in
22 Steam BIN MOHAMAD SALJI (A16)
47
D-102 45 in N-104 3.NOR EZZATI AMIRA BINTI
CW out MUSTAPA PADZIR (A16)
N-101 60
21
59 E-104
24
61
Hot oil
36 37 CW
D-101 in P-133 Steam C-107
25 CW in
out B-104 out
UNREACTED
B-101
CW
OIL SYMBOLS:
Hot oil out C-105
out
ORGANIC
WASTE Reactant
Product
Stream 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
Temperature (°C) 25 25 25 25 25 25 90 110 25 25 375 100 25 110 375 25 25 150 140 140 180 125 110 110 190 200 110 110 25 30 25 375
Pressure (bar) 1 1 1 1 1.5 1.5 1.5 1.5 1.3 1.3 40 40 2 2 40 1.5 1.3 1.3 1.3 1.5 1.1 1.3 1.3 1.3 1.3 1.5 1.5 1.2 1 1.6 1.2 40
Phase L L S&L G G S&L 1.5 G L S 40 G L L L L L L L L G V L L L V G V G V V G
Mass flowrate of component (kg/h)
Triglycerides 0 0 32395.36 0 0 32395.36 0 0 32395.36 0 0 0 32395.36 32395.36 6479.07 0 0 6479.07 6479.07 6479.07 0 0 0 0 6479.07 6479.07 0 0 0 0 0 0
Hydrogen gas 0 0 0 628.00 628.00 0 76.58 76.58 0 0 15.32 15.32 0 0 0 0 15.32 0 0 0 0 0 0 0 0 0 551.41 0 0 0 0 110.28
Decane 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Petrol 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Propane 0 0 0 0 0 0 0 0 0 0 1347.89 1347.89 0 0 0 0 1347.89 0 0 0 0 0 0 0 0 0 0 0 0 1348 1348 0
Paraffin 0 0 0 0 0 0 0 0 0 0 0 0 0 0 24629.66 0 0 24629.66 24629.66 24629.66 24629.66 24629.66 24629.66 24629.66 0 0 0 0 0 0 0 0
Carbon monoxide 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2058.60
Water 943.52 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 943.52 943.52 0 0 0
Benzene 0 92.83 0 0 0 0 0 0 0 0 0 0 0 0 0 93 0 0 0 0 0 0 0 0 0 0 0 0 0 92.83 92.83 0
Impurities 0 0 0 0 0 0 0 0 0 25.05 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTAL 943.52 92.83 32395.36 628.00 628.00 32395.36 76.58 76.58 32395.36 25.05 1363.21 1363.21 32395.36 32395.36 31108.73 92.83 1363.21 31108.73 31108.73 31108.73 24629.66 24629.66 24629.66 24629.66 6479.07 6479.07 551.41 943.52 943.52 1440.72 1440.72 2168.88
Stream 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64
Temperature (°C) 375 85 85 200 25 25 25 25 100 80 55 55 130 155 155 155 70 45 185 25 80 90 90 25 175 100 25 25 185 190 190 25
Pressure (bar) 40 1.3 1.5 1.5 1 1 1 1.8 1.4 1.5 1.5 1.5 1.4 1.6 1.6 1.7 1.2 1.4 1.3 1 1.3 1.6 1.6 1 1.2 1.4 1.4 1 1.3 1.6 1.6 1
Phase L L L L L G L G G V L L L V L L G V L L L V L L G V L L L V L L
Mass flowrate of component (kg/h)
Triglycerides 0 0 0 6479.07 6479.07 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hydrogen gas 0 0 0 0 0 0 0 110.28 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Decane 10440.04 10440.04 10440.04 0 0 0 0 0 104.40 104.40 104.40 104.40 10335.63 10335.63 10335.63 10335.63 52.20 52.20 52.20 52.20 52.20 52.20 52.20 52.20 10232.28 10232.28 10232.28 10232.28 103.36 103.36 103.36 103.36
Petrol 6322.84 6322.84 6322.84 0 0 0 0 0 6259.61 6259.61 6259.61 6259.61 63.23 63.23 63.23 63.23 6197.01 6197.01 6197.01 6197.01 62.60 62.60 62.60 62.60 47.42 47.42 47.42 47.42 15.81 15.81 15.81 15.81
Propane 0 0 0 0 0 1347.89 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Paraffin 4925.93 4925.93 4925.93 0 0 0 0 0 492.59 492.59 492.59 492.59 4433.34 4433.34 4433.34 4433.34 246.30 246.30 246.30 246.30 246.30 246.30 246.30 246.30 44.33 44.33 44.33 44.33 4389.01 4389.01 4389.01 4389.01
Carbon monoxide 0 0 0 0 0 0 0 2058.60 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Water 1323.38 1323.38 1323.38 0 0 47.18 896.35 0 1191.05 1191.05 1191.05 1191.05 132.34 132.34 132.34 132.34 11.91 11.91 11.91 11.91 1179.14 1179.14 1179.14 1179.14 92.64 92.64 92.64 92.64 39.70 39.70 39.70 39.70
Benzene 0 0 0 0 0 0 896.35 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Impurities 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
TOTAL 23012.19 23012.19 23012.19 6479.07 6479.07 1395.07 1792.70 2168.88 8047.65 8047.65 8047.65 8047.65 14964.54 14964.54 14964.54 14964.54 6507.42 6507.42 6507.42 6507.42 1540.23 1540.23 1540.23 1540.23 10416.67 10416.67 10416.67 10416.67 4547.87 4547.87 4547.87 4547.87
333
APPENDIX E
1
WATER FT FC PT PC
2 2 3 3
16 29 FAKULTI KEJURUTERAAN
2 HYDROGEN DAN ALAM BINA
TC TT
BENZENE 4 4 CW 30
Hot water GAS
12 in
17 in TC
14
P-101 38 JABATAN KEJURUTERAAN
TT
CW 14
6 FC FT C-101 out CW TC TT LT LC
PROPANE KIMIA DAN PROSES
3 1 1 G-101 in 10 10 31 9 9 39
WCO BENZENE
LT
P-102 1 C-103 CW
Hot water G-102
GROUP KK8
out
out
F-101 LC
13 TC TT PRODUCTION OF DECANE
1 CW 11 11
40
9
in
FROM WASTE COOKING OIL
10
PT PC
WASTE GAS
CW in
6 6
P-103 TC TC C-104 CW 49 50
5 7 out
14 TT 18 TT 28
TT 5 7 SUPERVISORS:
TC
11 N-103
1 1 V-105
CW out LT
PT PC 6 52
J-102 J-103 4 4 E-103 1. ASSOC. PROF. DR MASLI
V-101 V-102 32
J-101 PETROL IRWAN BIN ROSLI
CW in LC
41 42 51 6 2. DR. EBRAHIM MAHMOUDI
15
TT
TC TT PT
3
PC
3
8 LT 3. YEOW EU LUN (FAETH ASIA
44
3 3 7
TC N-102
PC
8 CW out 54
5 CW out PACIFIC)
5
CW in CW out TT
15 TC TT
PT LC 17 17
R-102 43 E-102
7
5 V-104 Hot 7
R-101 water
D-103 out
55 CW 56
CW in 53 in
19 33
LC LT TC
4
8
12 45 CW out LT
8
24
N-101
E-101
PT
E-104 60 4. NUR ZAFIRAH ALIAH BINTI
PC CW out
7 V-106 59
2
V-103 B-102 BAHARUDDIN (A169320)
PT
WASTEWATER 5. HUSNA BINTI AHMAD
LT
2 23 2
Steam
LC
in
48 9
RADZUAN (A167664)
LT
LC 8
2
20 62
TC
P-106 LC 17
TT 8 SUBMISSION DATE:
16
26 LT TT
P-104 3 Steam 63 CW 17
TT
TC D-104 61 out in 64 17TH MAY 2022
16
6 TT
D-101 Hot oil LC CW TC PARAFFIN
3 36 in
13 13
37 Steam
CW
TC 25 out
B-104 C-107 out
6
in UNREACTED SYMBOLS:
CW
OIL
B-101 C-105 out
Hot oil
in ORGANIC Reactant
WASTE
Product
K-101 Blower P-103 Pump E-101 Reflux Drum
C-102 Cooler G-102 Stripper P-106 Pump D-104 Distillation Column
P-101 Pump R-101 Jacketed Reactor N-101 Condenser
C-103 Cooler E-102 Reflux Drum D-103 Distillation Column C-106 Cooler
P-102 Pump C-101 Cooler B-101 Reboiler
C-104 Cooler N-102 Condenser E-103 Reflux Drum E-104 Reflux drum
H-101 Heater P-104 Pump G-101 Gas Absorption
P-105 Pump B-102 Boiler N-103 Condenser N-104 Condenser
F-101 Filter D-101 Distillation Column R-102 Jacketed Reactor
D-102 Distillation Column C-105 Cooler B-103 Boiler B-104 Reboiler
V-101 Relief Valve V-102 Relief Valve V-103 Relief Valve
V-104 Relief Valve V-105 Relief Valve V-106 Relief valve C-107 Cooler
J-101 Heat Exchanger J-102 Heat Exchanger J-103 Heat Exchanger
To FAL/
FAH
1 To PAL/
PAH
WATER FT FC PT PC
2 2 3 3
16 29 FAKULTI KEJURUTERAAN
2 HYDROGEN DAN ALAM BINA
TC TT
BENZENE 4 4 CW 30
Hot water GAS
12 in
17 in TC
14
P-101 38 JABATAN KEJURUTERAAN
TT
CW 14
6 FC FT To FAL/ C-101 out CW TC TT LT LC
PROPANE KIMIA DAN PROSES
3 1 1 FAH G-101 in 10 10 31 9 9 39
WCO BENZENE
LT To LAL/
P-102 1 LAH C-103 CW
Hot water G-102
GROUP KK8
out
out
F-101 LC
13 TC TT PRODUCTION OF DECANE
1 CW 11 11
40
9
in
FROM WASTE COOKING OIL
10
PT PC
WASTE GAS
To PAL/ CW in
PAH 6 6
P-103 TC TC C-104 CW 49 50 To LAL/
5 7 out
To FAL/ LAH
FC
FAH 14 TT 18 TT 28 To PAL/
TT 5 7 SUPERVISORS:
TC
11 PAH N-103
1 1 V-105
CW out LT
FT PT PC 6 52
J-102 J-103 4 4 E-103 1. ASSOC. PROF. DR MASLI
To TAL/
V-101 V-102 32
J-101 TAH To PAL/ PETROL IRWAN BIN ROSLI
PAH CW in LC
41 42 51 6 2. DR. EBRAHIM MAHMOUDI
15
To TAL/ TT
TC TT PT
3
PC
3
TAH 8
To TAL/
LT To LAL/ 3. YEOW EU LUN (FAETH ASIA
44
3 3 To LAL/ 7 LAH
TC N-102 TAH
LT LC LAH PC
8 CW out 54
5 CW out PACIFIC)
5
CW in CW out TT
15 TC TT
To PAL/ PT LC 17 17
R-102 43 E-102
7
12 45 CW out LT
8
24
N-101
E-101
To PAL/ PT
E-104 60 4. NUR ZAFIRAH ALIAH BINTI
PC CW out PAH 7 V-106 59
2
V-103 B-102 BAHARUDDIN (A169320)
To PAL/ PT To LAL/
WASTEWATER 5. HUSNA BINTI AHMAD
LT
PAH 2 23 2 LAH
Steam
LC
in
48 9
RADZUAN (A167664)
LT To LAL/
LC 8 LAH
2
20 62
TC
P-106 LC 17
To TAL/ TT 8 SUBMISSION DATE:
TAH 16
26 LT To LAL/ TT
P-104 3 LAH Steam 63 CW 17
To TAL/ TT
TC D-104 61 out in 64 17TH MAY 2022
16
TAH 6 TT
D-101 Hot oil LC CW TC PARAFFIN
3 36 in
13 13
37 Steam
CW
TC 25 out
B-104 C-107 out
6
in UNREACTED SYMBOLS:
CW
OIL
B-101 C-105 out
Hot oil
in ORGANIC Reactant
WASTE
Product
336
APPENDIX F
WASTEWATER
FAKULTI KEJURUTERAAN DAN
ALAM BINA
JABATAN KEJURUTERAAN
E-101 KIMIA DAN PROSES
5
2
3 4
OIL
GROUP KK8
WASTEWATER TREATMENT
P-104
S-101 PLANT AFTER PRODUCTION OF
P-101
DECANE
6
KKKR 4774
COURSE LECTURERS:
P-102 7
8
1. PROF. IR. DR. SITI KARTOM
BINTI KAMARUDIN
2. Assoc. PROF. IR. DR.
AIR
SHUHAIDA HARUN
12
A-101
10 11 TREATED SUPERVISORS:
9
WATER 1. Assoc. PROF. DR MASLI IRWAN
BIN ROSLI
P-105 2. DR. EBRAHIM MAHMOUDI
15
13
14
GROUP MEMBERS:
16
Filter 4. NUR ZAFIRAH ALIAH BINTI
18
BAHARUDDIN
17
5. HUSNA BINTI AHMAD RADZUAN
19
SYMBOLS:
Reactant
APPENDIX G
HIRARC
Filter (F-101) was used to filter the triglyceride from impurities as a pre- treatment before the main process started in the reactor. Triglyceride
in the room temperature and not hazardous according to the MSDS.
Valve Has a good chance 4 -No or fewer triglyceride 2 8 Perform schedule Installation of the level
malfunction (Fail of occurring and is flow to the filter. inspection and alarm
to open/close) not unusual Low maintenance
-Overflow the
triglyceride flow to the
filter.
-Perform a safety
training for workers to
overcome the hazard.
-Perform a
safety training
for workers to
overcome the
hazard.
At Distillation Column (D-101), Paraffin was separated from unreacted triglyceride at 180°𝐶
-Perform a safety
training for
workers to
342
overcome the
hazard.
-Perform a safety
training for
workers to
overcome the
hazard.
valve
monitoring app
as an example
Siemens.
According to the process flow diagram (PFD) after heat exchanger, we use 3 heat exchangers to transfer heat from one medium to another.
-Perform a safety
training for
workers to
overcome the
hazard.
APPENDIX H
HAZOP
i. Node 1 of G-101
No No flow rate Inlet pipe ruptured or -Separation does None Schedule inspection and
distillate blocked not occur. maintenance
347
Low Less flow rate Partially blockage of -Efficiency of Flow controller Schedule inspection
distillate pipeline separation
decreases and maintenance
Leakage of pipe
-Distillation
column may run
dry
-Release
hazardous
chemical into
working
environment
High Intense flow rate Large flow from previous -Overflow and Flow Schedule inspection and
distillate unit operation spillage of
containment controller maintenance
-Overpressure
and causing
rupture of the
column
348
Low Low pressure Low flowrate of reactant -Low Pressure Scheduled inspection
inside the column controller
into the column production rate and maintenance
-Energy wastage
349
High High pressure Outlet flow too low Vessel or Pressure Scheduled inspection
inside the column
pipeline rupture controller and maintenance
350
b. Stripper, G-102
351
i. Node 1 of G-102
High High temperature Valve failed to closed -Ineffective Temperature Schedule inspection and
in the column separation
process controller maintenance
-The desired
separation
cannot be
achieved
High High level inside the High flowrate into Overflow inside Level Scheduled inspection
column column vessel controller and maintenance
354
i. Node 1 of D-101
Low Low pressure in the -Not enough vapor builds up -Product may not Pressure -Schedule inspection and
column in column meet requirement controller maintenance
High High pressure in the Outlet flow rate is too low Cause distillation Pressure Schedule inspection and
column column fracture maintenance
as pressure rises controller
up Installation of high
pressure alarm
Workers exposed
to hazardous
chemicals
Less Low level of liquid -Outlet bottom pipe leakage -Distillation Level controller -Schedule inspection and
in distillation maintenance at the inlet
column -Leakage of column column may pipe
separation
process
decreased
High High level liquid of -Outlet bottom pipe -Overflow -Schedule inspection
liquid in the blockage
357
distillation column -Outlet flow rate too low of column Level controller and maintenance
column
Low Low temperature in the Break down of reboiler Efficiency of Temperature -Schedule inspection and
column controller maintenance frequency
separation -Installation of low
decreased
High High temperature in the Temperature controller fail -Can lead to Temperature -Schedule inspection and
distillation column overheated and controller maintenance
damaged of the -Installation of high
column
-Product may temperature alarm
not meet
specification
359
Low Low level of liquid -Outlet bottom pipe leakage -Distillation Level controller -Schedule inspection and
in distillation column may run maintenance at the inlet
column -Leakage of column dry pipe
-Outlet flow rate is too -Efficiency -Installation of low level
360
process
decreased
High High level liquid of -Outlet bottom pipe -Overflow of Level -Schedule inspection and
liquid in the blockage column maintenance at the outlet
distillation column controller pipe
-Outlet flow rate too low -Overpressure
-Installion of high level
inside the
alarm
column
361
APPENDIX I
PLANT LAYOUT
362
APPENDIX J
MECHANICAL DESIGN
Inlet 11
Outlet 16
14 FACULTY OF ENGINEERING AND BUILT
ENVIRONMENT
DEPARTMENT OF CHEMICAL ENGINEERING
AND PROCESS
724
789
GROUP
K8
GROUP MEMBERS
KASHVINWARMA A/L BASKARAN A169128
2759
TOP AND SIDE OF TOP AND SIDE VIEW OF HUSNA BINTI AHMAD RADZUAN A167664
WELDING NECK FLANGE SKIRT SUPPORT NUR ZAFIRAH ALIAH BINTI BAHARUDDIN A169320
NOR EZZATI AMIRA BINTI MUSTAPA PADZIR A169229
MUHAMMAD NA'IM NAJMI BIN MOHAMAD SALJI A168963
591
DRAWN BY
NUR ZAFIRAH ALIAH BINTI BAHARUDDIN
87
DATE
Outlet 12
16
Inlet 7 DESIGN SPECIFICATIONS
690
16
D2 Design Temperature : 375°C
690
Operating Pressure : 4000 kPa
H Design Pressure : 4419 kPa
Design Thickness : 14 mm
b
Corrosion Allowance : 2 mm
f
113
D4 Inside Diameter : 591.1 mm
648 K Vessel Height : 2069 mm
113
D
648 Height of cylindrical shell : 1478 mm
Height of ellipsoidal head : 295.6 mm
ANCHOR BOLT DESIGN WELDING NECK FLANGED
Material Used : Stainless Steel (SA240) Grade 304
STREAM 29
2940.5
735.4
TOP VIEW OF VESSELS
TOP VIEW OF FLANGE TOP VIEW OF MAN HOLE PRODUCTION OF AVIATION FUEL FROM
COOKING OIL
SUPERVISORS
PROF. MADYA DR. MASLI IRWAN ROSLI
DR EBRAHIM MAHMOUDI
INDUSTRIAL MENTOR
SIDE VIEW OF SKIRT
11750.3
GROUP K8:
DRAWN BY:
Ø16.4 NOR EZZATI AMIRA BINTI MUSTAPA PADZIR
2000
A169229
SUBMISSION DATE:
17 MEI 2022
STREAM 30
SI UNIT : MILIMETER
76.2
305
DESIGN SPECIFICATIONS
E
DESIGN TEMPERATURE: 25 °C
G
H
D
C
B
A CORROSION ALLOWANCE, CA: 4 MM
GROUP MEMBERS
B1
C 1. KASHVINWARMA A/L BASKARAN
2. MUHAMMAD NA’IM NAJMI BIN
MOHAMAD SALJI
5586 3.NOR EZZATI AMIRA BINTI
Top and Side view of 1500 MUSTAPA PADZIR
welding neck flange 4. NUR ZAFIRAH ALIAH BINTI
10 BAHARUDDIN
d1 5. HUSNA BINTI AHMAD RADZUAN
d4
B2
1500
E t1 MAWP VESSEL: 2.21 bar
265
FACULTY OF ENGINEERING AND
BUILT ENVIRONMENT
DEPARTMENT OF CHEMICAL
ENGINEERING AND PROCESS
TOP VIEW OF HEAT EXCHANGER PRODUCTION OF AVIATION FUEL
132.5
STREAM 17 FROM WASTE COOKING OIL
TUBE SIDE INLET 25% baffle cut 52.9
MECHANICAL DESIGN OF
COOLER (C-101)
GROUP
KK 8
19.05
SUPERVISORS
265 D DRAWN BY
D C HUSNA BINTI AHMAD RADZUAN
DATE
G 20th MAY 2022
C
G J
t2 DRAWING NOT TO SCALE
J A UNIT DIMENSION IN MILLIMETER
G A (mm)
CROSS SECTIONAL VIEW OF Y TUBE SIDE FLANGE
TUBE BUNDLE SHELL SIDE FLANGE
SADDLE DESIGN SPECIFICATIONS
MECHANICAL DESIGN:
KETTLE REBOILER
256
V
DRAWING NOT TO SCALE
t1 UNIT DIMENSION IN MILIMETER (MM)
J J
E E
16
C DESIGN SPECIFICATION
20
CORROSION ALLOWANCE : 2 MM
APPENDIX J.1
Since the operating pressure of the reactor (40 bar) is greater than atmospheric pressure
(Pa > Patm), the reactor is designed under internal pressure. Firstly, the design pressure
for each part of the vessel is calculated by using equation:
𝑃𝐷 = 𝑃𝑂 + 0.433ℎ
Cylinder shell, PD
= 580.151 + 0.433 (0.485+ 4.848) = 582.460 psi
A safety factor about 10% is added to design pressure for safety purpose. The new
design pressure is Pj = 1.10PD and the data is tabulated in the Table 1,4 below
The wall thickness formulas for each part of the column are from ASME Code UG-
32(d) and UG-27 (c). The maximum allowable stress value, S is from ASME Code
givenin Subpart 1 of Section II, Part D.
𝑃𝐷 (638.40)(23.271)
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠, 𝑡 = =
2𝑆𝐸 − 0.2𝑃 2(17694.6)(0.8) − 0.2(638.40)
= 0.5271 in
Cylinder shell,
𝑃𝑅 (640.71)(23.271/2)
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠, 𝑡 = =
𝑆𝐸 − 0.6𝑃 (17694.6)(0.8) − 0.6(640.71)
= 0.5413 in
𝑃𝐷 (640.94)(23.271)
𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠, 𝑡 = =
2𝑆𝐸 − 0.2𝑃 2(17694.6)(0.8) − 0.2(638.40)
= 0.5292 in
Thus, the overall thickness, toverall is determined, which is the highest value of minimum
thickness calculated for each part
t= 13.5 + 2 = 15.5mm
The maximum allowable working pressure for any type pressure vessel, MAWP is
determined by calculating every part under internal pressure. The formula of internal
design pressure for each part of the reactor can be found in ASME Code UG-32 part (D)
and UG-27 part (c). By using tmin from the calculation above, the MAWPvessel is
calculated.
2𝑆𝐸𝑡 2(17694.6)(0.8)(0.551)
Internal pressure = = (23.271)+0.2 (0.551)
= 571.91 𝑝𝑠𝑖
𝐷+0.2𝑡
𝑆𝐸𝑡 (17694.6)(0.8)(0.551)
Internal pressure = = (23.271/2)+0.6 (0.551)
= 560.59 𝑝𝑠𝑖
𝑅+0.6𝑡
2𝑆𝐸𝑡 2(17694.6)(0.8)(0.551)
Internal pressure = = (23.271)+0.2 (0.551)
= 571.91 𝑝𝑠𝑖
𝐷+0.2𝑡
The value of internal pressure and MAWPvessel is obtained and the result is shown.
Table J.2 Internal pressure and MAWPvessel for each part of the reactor R-101
Part of the column MAWPpart (psi) Static head, PH(psi) MAWPvessel (psi)
Top ellipsoidal head 571.91 0.21 571.70
Cylindrical Shell 560.59 2.31 558.28
Bottom ellipsoidal head 571.91 2.52 569.39
By choosing the smallest value, the MAWPvessel is 558.28 psi (38.49 bar)
Pressure vessel subjected to other loads (major and subsidiary load) in addition to
pressure. Hence, it must be designed to withstand the worst combination of loading
without failure. There are the sources of combined loading which are internal and
external pressure, weight loads, wind loads, earthquake (seismic load), and eccentric
loads (Sinnott 2005). All of these are related to primary stresses and summarized into
principal stresses in the end of calculation.
a. Primary stresses
PD = (1.10) (580.15)
𝑃𝐷𝑖
𝜎𝐿 =
4𝑡
4.4 (591.1)
= = 54.184 N/mm2
4 (14)
𝑃𝐷𝑖
𝜎𝐶 =
2𝑡
4.4 (591.1)
= = 108.37 N/mm2
2(14)
Direct stress, W
𝑊
𝜎𝑤 = 𝜋(𝐷 +𝜏)𝑡 where, W= WV+WI
𝑖
Thus,
𝑊
𝜎𝑤 =
𝜋(𝐷𝑖 + 𝜏)𝑡
(3.755)
𝜎𝑤 = = 0.0001652𝑁/𝑚𝑚2
𝜋(591.1 + 12)(14)
Bending stress, b
𝑀 𝐷𝐼
𝜎𝑏 = ± ( + 𝑡)
𝐼𝑉 2
𝑀 = 𝑇𝑜𝑡𝑎𝑙 𝑏𝑒𝑛𝑑𝑖𝑛𝑔 𝑚𝑜𝑚𝑒𝑛𝑡
Iv = Second moment of area the vessel about plane of bending
𝑊𝑥 2
𝑀=
2
x = 𝐻𝑣 = 1.5765 m
𝐷𝑒𝑓𝑓(including insulation) = 𝐷𝑜 = 𝐷𝑖 + 2t = 0.6151 m
Pw = 1280 N/m2
W = 𝑃𝑤𝐷𝑒𝑓𝑓 = (1280)(0.6151) = 787.33 N/m
787.33(1.57652 )
M= = 978.39 Nm = 9.784 x 105 Nmm
2
𝜋 𝜋
Iv = 64 (𝐷𝑂 4 − 𝐷𝑖 4 ) = (0.61514 − 0.59114 ) = 0.00103m
64
b. Principal Stresses,
1
𝜎1 = [𝜎 + 𝜎𝑧 √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
1
𝜎2 = [𝜎ℎ + 𝜎𝑧 √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
σz(upwind) = σL + σW + σb
= 54.476 N/mm2
σz(downwind) = σL + σW − σb
= 53.892 N/mm2
1
𝜎1 = [𝜎 + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
1
= [(108.368) + (54.476) + √(108.368 − 54.476)2 + 4(0)2 ]
2
370
𝑁
= 108.368 𝑚𝑚2 = 𝜎ℎ
1
𝜎2 = [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
1
= [(108.368) + (54.476) − √(108.368 − 54.476)2 + 4(0)2 ]
2
𝑁
= 54.476 𝑚𝑚2 = 𝜎𝑧 (upwind)
1
𝜎1 = [𝜎 + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
1
= [(108.368) + (54.476) + √(108.368 − 54.476)2 + 4(0)2 ]
2
𝑁
= 108.368 𝑚𝑚2 = 𝜎ℎ
1
𝜎2 = [𝜎ℎ + 𝜎𝑧 − √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
1
= [(108.368) + (54.476) − √(108.368 − 54.476)2 + 4(0)2 ]
2
𝑁
= 54.476 𝑚𝑚2 = 𝜎𝑧 (upwind)
σ1 – σ3 = 108.36-2.757
= 105.603 N/mm2
σ1 – σ3 = 54.476-2.757
= 51.719 N/mm2
Hence, the maximum allowable stress intensity, (∆σmax) = 105.603 N/mm2 According
to ASME Code, maximum allowable stress at temperature 375 oC,S = 122 N/mm2
Since, (∆σmax) = 105.603 N/mm2 ˂ S = 122 N/mm2, therefore, the design is safe to use.
d. Elastic Stability
𝐸 𝑡
Critical buckling stress, 𝜎𝑐 = ( )
√3(1−𝑉 2 ) 𝑅𝑝
0.472
= (2 × 104 )( )
615.1
= 15.347 𝑁/𝑚𝑚2
Compressive stress,
𝜎𝑐𝑜𝑚 = 𝜎𝑏 + 𝜎𝑤
= 0.29+ 0.0001652
=0.2902 𝑁/𝑚𝑚2
Since the value of (∑ 𝜎)𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ˂ σc, therefore, the design is safe to use.
From the analysis of combined loading, the material we chose has fulfilled
bothrequirements of maximum stress intensity and elastic stability:
(Δσ)max < S and (∑ 𝜎𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑠𝑖𝑣𝑒 ) < 𝜎𝑐. Therefore, the design is safe.
The vessels support must be designed to withstand the weight of the vessel including
weight of material are packed inside and contents and any superimposed loads such as
372
wind loads. Support will impose localized loads on the vessel wall, and the design must
be checked to ensure resulting stress concentrations are below the maximum allowable
design stress. It is also important to allow the ease of access to the vessel and the fittings
for inspection and maintenance (Sinnott 2005).
a. Thickness of support
The skirt support had been chosen as the support for distillation column. Since the
height of distillation column, H = 1.7734 m with the internal diameter, Di = 0.591 m, the
skirt support is suitable for the use of tall vessel which subject to wind loading.
4(7051.59 × 1000)
= = 2.099𝑁/𝑚𝑚2
𝜋(591.1 + 12)(12)(591.1)
(3.775)
= = 2.8 × 10−7 𝑁/𝑚𝑚2
𝜋(591.1 + 12)(12)
𝑊
Dead weight stress in skirt (operating),ws = 𝜋(𝐷 +𝑡
𝑠 𝑠 )𝑡𝑠
(5674.52)
= = 4.22 × 10−4 𝑁/𝑚𝑚2
𝜋(591.1 + 12)(12)
The loads carried by the skirt will be transmitted to the foundation slab by the skirt base
ring. This will be opposed by the couple set up by the weight of the vessel and the tensile
load of the anchor bolts (Sinnott 2005). The anchor bolts are assumed to share the
overturning load equally and the bolt arearequired:
1 4𝑀𝑠
𝐴𝑏 = [ − 𝑊]
𝑁𝑏 𝑓𝑏 𝐷𝑏
Nb = number of bolts
W = weight of the
vessel, N
Db = bolt circle
diameter, m
Assumptions:
• number of bolts as 8
𝜋×1.750×1000
Bolt spacing = 8
374
= 687.22mm >
600mm
1 4(7051.59)
𝐴𝑏 = [ − 3.755]
(8 × 100) 1.75
= 20.14 𝑚𝑚2
4𝑀𝑠 𝑊
𝐹𝑏 = [ 2 + ]
𝜋 × 𝐷𝑆 𝜋𝐷𝑆
4(7051.59) 3.755
𝐹𝑏 = [ 2
+ ]
𝜋 × (0.5911) 𝜋(0.5911)
𝐹𝑏 = 5698.60 𝑁𝑚−1
By taking the bearing pressure as 3.5 N/mm2, the minimum width of the base ring, Lb
𝐹𝑏 1
𝐿𝑏 = [ + 3 ]
𝑓𝑐 10
5698.60
𝐿𝑏 = [ ]
3.5 × 103
𝐿𝑏 = 1.628𝑚𝑚
376
APPENDIX J.2
To determine the wall thickness, calculation of design pressure needed to calculate and
determine by considering 10% for safety purpose and following the calculation of
cirsumferential stress and longitudinal stress to determine minimum wall thickness.
i. Design pressure
The operating pressure of the absorber (1.6 bar), therefore the absorption column is
designed under internal pressure. Firstly, the design for each part of the vessel is
calculated by using equation.
𝑃𝐷 = 𝑃𝑜 + 0.433ℎ
Hence,
As safety factor about 10% is added to design pressure for safety purpose. So, the
innovative design pressure is 𝑃𝐽 = 1.10𝑃𝐷 .
Hence,
The table show the parameter needed to determine first before calculation of minimum
wall thickness.
From ASME Code UG-32 part (D), for top ellipsoidal head:
𝑃𝐷
Thickness, 𝑡 = 2𝑆𝐸−0,2𝑃
26.67×115.17
=2(16700×0.85)−0.2(26.67) = 0.109 𝑖𝑛
Circumferential stress:
𝑃𝑅
Thickness, 𝑡 = 𝑆𝐸−0.6𝑃
115.17
45.06×( )
2
= (16700×0.85)−(0.6×45.06) = 0.184 𝑖𝑛
Longitudinal stress:
𝑃𝑅
Thickness, 𝑡 = 2𝑆𝐸−0.4𝑃
115.17
45.06×
2
=2(16700×0.85)−(0.4×45.06) = 0.181 𝑖𝑛
378
From ASME Code UG-32 part (D), for top ellipsoidal head:
𝑃𝐷
Thickness, 𝑡 = 2𝑆𝐸−0,2𝑃
46.2×115.17
=2(16700×0.85)−0.2(46.2) = 0.188 𝑖𝑛
Thus, the overall thickness, 𝑡𝑜𝑣𝑒𝑟𝑎𝑙𝑙 is determined which is the highest value of
minimum thickness calculated. After considering the corrosion allowance of 4 mm.
t = 4.78mm + 4 mm
= 8.78 mm / 0.266 in
Based on standard thickness in the market, the closes to the thickness calculated
is 0.315 in
2𝑆𝐸𝑡
𝑃=
𝐿 + 0.2𝑡
2(16700×0.85×0.236)
= (10.29+0.2(0.236)
= 648.14 psi
Circumferential stress:
𝑆𝐸𝑡
𝑃=
𝑅 + 0.6𝑡
(16700×0.85×0.236)
= 115.17
( )+0.6(0.236)
2
= 58.03 psi
Longitudinal stress:
2𝑆𝐸𝑡
𝑃=
𝑅 − 0.4𝑡
2(16700×0.85×0.236)
= 115.17
( )−0.4(0.236)
2
= 116.54 psi
Circumferential stress, 58.03 psi < longitudinal stress, 116.54 psi which means
the circumferential stress has a weaker link and suitable condition for shell.
𝑆𝐸𝑡
𝑃=
𝑅 + 0.6𝑡
(16700×0.85×0.236)
= (2.4+0.6(0.236)
= 115.35 psi
c. Combined loading
i. Primary stresses
For a cylindrical vessel, primary stresses which are required to achieve static
equilibrium are due to the folowing sources:
Direct stress.
Bending stress.
Some assumptions are made for calculation of primary stress, the assumptions stated as
below:
3
Liquid level = 4 × 10.29 = 7.72 𝑚
𝑃 × 𝐷𝑖 1294.51 × 2940.57 𝑁 2
𝜎𝐿 = = = 8871.30
4𝑡 4 × 8.002 𝑚𝑚
381
𝑃 × 𝐷𝑖 1294.51 × 2940.57 𝑁 2
𝜎ℎ = = = 17742.61
4𝑡 2 × 8.002 𝑚𝑚
𝑤
𝜎𝑤 =
𝜋 × 𝐷𝑖 + 𝑡
With 𝐶𝑣 = 1.5,
𝑊𝑣 = 111605.32
𝑊𝑣
Direct stress, 𝜎𝑤 = = 1505.84 𝑁/𝑚𝑚2
𝜋(𝐷𝑖 +𝑡)𝑡
Distance, x = 𝐻𝑣
= 1.167−6 𝑁/𝑚𝑚2
The torsional shear stress can be neglected in preliminary vessel design because these
loads will normaly be small. 𝜏 = 0.
382
Principal Stresses:
As there is no torsional shear stress, the principal stresses will be 𝜎𝑧 and 𝜎ℎ . The
radial stress is negligible.
1
𝜎1 = [𝜎 + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2 ℎ
𝜎1 = 𝜎ℎ
1
𝜎2 = [𝜎ℎ + 𝜎𝑧 + √(𝜎ℎ − 𝜎𝑧 )2 + 4𝜏 2 ]
2
𝜎2 = 𝜎𝑧
𝑁
𝜎1 = 177.42
𝑚𝑚2
𝑁
𝜎2 = 73.65
𝑚𝑚2
= 177.42 – 73.65
=103.77 𝑁/𝑚𝑚2
383
𝑁
Since 𝜎𝑚𝑎𝑥 , 103.77 𝑚𝑚2 < 𝑡𝑒𝑛𝑠𝑖𝑙𝑒, 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ, 𝑆𝑑𝑒𝑠𝑖𝑔𝑛 , 206.84 𝑁/𝑚𝑚2 , then
∑ 𝜎𝑐𝑜𝑚𝑝𝑟𝑒𝑠𝑖𝑣𝑒 = 𝜎𝑏 + 𝜎𝑤
=1505.84 N/𝑚𝑚2
𝑡
Critical buckling stress, 𝜎𝐶 = 2× 104 (𝐷 ) = 40284.03 N/𝑚𝑚2
𝑜
The skirt support had been chosen as the support for gas absorption. Since the height of
gas absorption is 11.76 m with the internal diameter, 𝐷𝑖 is 2.94 m, the skirt support is
suitable for the use of tall columns which subject to wind loading. One of the most
important factor is they do not imposed concentrated load on the vessel shell.
Welded – neck flange is chosen in this design because it is suitable for extreme
conditions where the flange is likely to be subjected to temperature, shear and vibration
loads for the absorption column, G-101. The welded connection will not interfere with
the flow of the fluid.
i. Skirt thickness
The skirt thickness must be sufficient to withstand the dead-weight loads and bending
moments imposed on it by the vessel and it will not be under the vessel pressure.
384
Elements Specification
Type of support Straight cylindrical skirt with base angel, 𝜃𝑠 = 90°
Material of construction Carbon steel
Type of weld Welded flush with the shell
Weld joint factor, J 1.0
Young’s Modulus 200,000
Design stress, S (N/mm2) 135
Bending stress, 𝜎bs (N/mm2) 14.44
Dead weight stress, 𝜎ws (Test)(N/mm2) 0.056
Dead weight stress, 𝜎ws (Operating)(N/mm2) 0.112
𝜎s (Compressive)(N/mm2) 14.5
𝜎s (Tensile)(N/mm2) 19
Skirt diameter, Ds (m) 3
Height of the support, hs (m) 2
Skirt thickness, ts (m) 0.2
The skirt base ring transmits the loads carried by the skirt to the foundation slab. Wind
and other lateral loads will tend to overturn the vessel, but this will be countered by the
couple formed by the vessel's weight and the tensile load. For G-101, random packing
design as the base ring design of the skirt support is used to make the vessel more stable
and stronger.
Table 11.22 shows the base ring and anchor bolt specification for DC-101.
e. Summary of design
By considering the internal pressure of the vessel, absorption column G-101, the
conditions that are needed for the design have been calculated through series of formula
stated. The design of gas absorption is summarized and tabulated as followed in table
below. The detailed calculation for the mechanical design in appendix A.
APPENDIX J.3
= 15111.25 × 1.12
= 16924.60 𝑘𝑔/ℎ𝑟
5
= × 16924.60
60
= 1410.38 𝑚3
= 2820.77 𝑚3
3 4𝑉
Diameter of drum = √3 𝜋
3 4 2820.77
=√
3 𝜋
= 10.33 𝑚
= 10.33 × 3
= 30.98 𝑚
388