The Gulu Logistics hub is designed as a dry port with both rail and truck terminals. Construction commenced in May 2020. The final award of this PPP arranged constructions works has been announced by Uganda Railways Corporation
The Gulu Logistics hub is designed as a dry port with both rail and truck terminals. Construction commenced in May 2020. The final award of this PPP arranged constructions works has been announced by Uganda Railways Corporation
The Gulu Logistics hub is designed as a dry port with both rail and truck terminals. Construction commenced in May 2020. The final award of this PPP arranged constructions works has been announced by Uganda Railways Corporation
NOTIFICATION FOLLOWING THE EVALUATION OF THE REQUEST FOR
QUALIFICATION (RFQ) REF NO.URC/PPP/2021-22/00001 FOR THE PROCUREMENT OF A PRIVATE PARTY FOR THE GULU LOGISTICS HUB PROJECT UNDER A PUBLIC PRIVATE PARTNERSHIP (PPP) ARRANGEMENT
Procurement Ref. No.: URC/PPP/2021-22/00001
Date: 16th June, 2022
Address: Plot 57, Nasser Rd, Kampala, Uganda
The Government of Uganda (GoU) through Uganda Railways Corporation (URC)
is developing the Gulu Logistics Hub (GLH) project in conjunction with TradeMark East Africa (TMEA), Foreign, Commonwealth and Development Office, U.K. (FCDO) and the European Union (EU).
Following the completion of the evaluation process, one Respondent, Unifreight
Mitchell Cotts Consortium was pre-qualified for the next stage of the Procurement process.
Accordingly, Unifreight Mitchell Cotts Consortium will, at an appropriate time be
invited to submit a proposal for consideration by Uganda Railways Corporation
Further details can be viewed / downloaded from the URC portal at www.urc.go.ug