Project : SHRI RAM JANMBHOOMI TEERATH KSHETRA TRUST

Major observations Date: 18.06.2022


SI.No Element Description Remarks
General
1 Measurement taken as per drawing :,

-
3 All quantities increased by 5% of the measured quantity except numbers.

Excavation
1 The building was filling only, and the site grading area consider maximum size of
building plus each sided 600mm additional consider.
2 Earthwork calculated based as below mentioned stage.
Stage - 1; Filling up to bottom of footing/ foundation and compacting accordance
specification.
Stage - 2; excavation footing/ foundation area 1000mm GSB and PCC qto and fill
compact required materials.
Stage - 3; Construction of footing/ foundation, wall, beam, trench etc.
Stage - 4; backfill up to bottom of rubble soling of slab, beam, trench.
Stage - 5; construction of balance work accordance with specification.

Concrete
1 DG Pad dimension and depth follow as per RFI-001.
2 Drawing no TCE.12182B-CV-3000-RC-30205 (Civil), TCE.12182B-AC-1005-AC-10637
(Arch); as per architectural drawing at roof level cantilever slab available, based on
RFI-001 125mm Thk consider.
3 RCC Ramp thickness considered as 150mm based on RFI-001 Response.
4 Below plinth beam production section not available, hence not consider.
5 Lintel beam size consider 300 mm deep
Structural Steel
1 Angle of size 50X50X5 considered at the corner edge of the trench as per RFI-001
Response.

Reinforcement Reinforcement according to the design ratio (Waiting for input)