Enter the plant and material master and select views
In MRP 2 Select the BLACKFLUSH as 1 and save Here we need to understand which is header material and components. For header mater there is no goods issue only for the components We need to issue. PROCESS FOR GOODS RECEIPT
Open master recipe and enter the material and plant
Here we need to select the CONTROL KEY PIO1
Here we need to select the phases according to us
Here we can see the control values for the particular phases. Then save. Once the data is saved convert planned order into the Process order and save
After entering the required quantity check and material availability
and save. Once the process order is number is generated open COR6N Open COR6N to confirm the process order