Design for JTA Anchor Channel


Project: Pos. No.:
Oberoi City Center Fronte Face

Print date:

11-May-11

Input

geometry and design loads (factored)

Vertical load FV,d [kN]:

Wind load: suction FH,d [kN]:

Dead load excentricity u [mm]:

Edge distance c1 [mm]:

6,75

13,50

140
Wind load excentricity z [mm]:

100
Center to edge of the attached part e [mm]:

No. of bolts:

-55

85

Design loads acting on anchor channel


D [kN]: N [kN]: V [kN]: 2,80 16,30 6,75
Proof of concrete compression stress required!

Tension load Shear load

Design loads per bolt


NEd [kN]: VEd [kN]: 8,15 3,38

Version: JTA-CEN-0.1.10

Construction project: Oberoi Mumbai Construction member: Front face_200 mm Project number: Date: 13.05.2011

1. Input information: Anchor channel: Bolt: Anchorage depth: Stand-off installation Concrete:

JTA W 40/22-hdg-0300-2A CE, l = 300 mm, 2 Anchor JC M10 x 40, hdg 4.6, On stock hef = 79 mm Distances = 0 mm (No spacing), Attaching part thickness = 10 mm Cube 40 MPa, Cracked concrete, fck,cube = 40 N/mm, d = 500 mm, c = 25 mm, cs = 25 mm, c1,1 = 100 mm, c1,2 = 100 mm, c2,1-x Not available, c2,2-x Not available x = channel overhang = 25 mm Concrete with normal reinforcement Not available Not available

Reinformcement: Tension reinforcement: Shear reinforcement:

Overall result: OK (Maximum utilisation 96 %)

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 1 of 5

Construction project: Oberoi Mumbai Construction member: Front face_200 mm Project number: Date: 13.05.2011

Loads Load point 1 2 25,00 175,00 8,15 8,15 3,38 3,38 (*)

Note: The specified load positions correspond to the critical load positions (-50 mm) within the displacement range x = 50 mm. Pair- and continuous loads will be shifted on the channel with constant load spacings. (*) load point 1 is relevant concerning the calculation.

2. anchor positions and resulting anchor loads (CEN/TS 1992-4, chapter 5) Anchor 1 2 25,00 275,00 10,07 6,23 4,18 2,58 (*)

(*) anchor 1 is relevant concerning the calculation.

3. Tension (CEN/TS 1992-4, chapter 6.2) 3.1 Steel failure Proof steel failure anchor (Anchor 1)

Proof connection between anchor and channel (Anchor 1)

OK

Proof local flexure (Load 1)

OK

Proof steel failure bolt (Load 1)

OK

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 2 of 5

Construction project: Oberoi Mumbai Construction member: Front face_200 mm Project number: Date: 13.05.2011

Proof flexure of channel (Load 1)

3.2 Concrete failure Proof pull-out (Anchor 1) OK

Proof concrete cone (Anchor 1)

OK

4. Shear (CEN/TS 1992-4, chapter 6.3) 4.1 Steel failure Proof steel failure anchor (Anchor 1)

Proof connection between anchor and channel (Anchor 1)

OK

Proof flexure of channel lip (Load 1)

OK

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 3 of 5

Construction project: Oberoi Mumbai Construction member: Front face_200 mm Project number: Date: 13.05.2011

Proof steel failure bolt (Load 1)

OK

4.2 Concrete failure Proof pry-out (Anchor 1) OK

Proof concrete edge c11 (Anchor 1)

OK

Proof concrete edge c12 (Anchor 1)

Proof concrete edge c21 (Anchor 1)

Proof concrete edge c22 (Anchor 1)

5. Interaction (CENT/TS 1992-4, chapter 6.4) Concrete (Anchor 1)

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 4 of 5

Construction project: Oberoi Mumbai Construction member: Front face_200 mm Project number: Date: 13.05.2011

Steel (Anchor 1)

Anchor channel (Load 1)

Bolt (Load 1)

6. Summary of the calculations All proofs are okay


The acting loads can be passed into the concrete member, the transfer of the loads has to be verified separately This calculation bases on product specific properties. Changes, even to similar products are only possible with new calculations.
All data have to be checked with the given edge boundaries and the feasibility. DKG assumes no ability for the input data of the user

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 5 of 5

C40

JTA W 40/22-hdg-0300-2A CE 2 x JC M10

40

200

Design for JTA Anchor Channel


Project: Pos. No.: Oberoi wind suction geometry and design loads (factored) Print date: 05-May-11

Input

Vertical load FV,d [kN]:

Wind load: suction FH,d [kN]:

Protrusion u [mm]:

Edge distance c1 [mm]:

6,75

13,50

50
Wind load excentricity z [mm]:

150
Distance of pressure center v [mm]:

No. of bolts:

40

25

Design loads acting on anchor channel


H=0D=FVd+Z
Z=[Fv,d*(u+v)+FH,d*z]/(c1-v) V=0Q=FHd+Z

D [kN]: N [kN]: V [kN]:

15,12 8,37 13,50

Proof of concrete compression stress required!

Tension Shear direction: to the edge

Design loads per bolt


NEd [kN]: VEd [kN]: 4,19 6,75

Version: JTA-CEN-0.1.10

Design for JTA Anchor Channel


Project: Pos. No.: Oberoi wind pressure geometry and design loads (factored) Print date: 05-May-11

Input

Vertical load FV,d [kN]:

Wind load: pressure FH,d [kN]:

Protrusion u [mm]:

Edge distance c1 [mm]:

6,75

-13,50

50
Wind load excentricity z [mm]:

150
Distance of pressure center v [mm]:

No. of bolts:

40

25

Design loads acting on anchor channel


H=0D=FVd+Z
Z=[Fv,d*(u+v)+FH,d*z]/(c1-v) V=0Q=FHd+Z

D [kN]: N [kN]: V [kN]:

6,48 -0,27 13,50

Proof of concrete compression stress required!

Pressure Shear direction: away from the edge

Design loads per bolt


NEd [kN]: VEd [kN]: -0,14 6,75

Version: JTA-CEN-0.1.10

Construction project: Oberoi Mumbai Construction member: Top slab_200 mm Project number: Date: 13.05.2011

1. Input information: Anchor channel: Bolt: Anchorage depth: Stand-off installation Concrete:

JTA W 40/22-hdg-0300-2A CE, l = 300 mm, 2 Anchor JC M10 x 40, hdg 4.6, On stock hef = 79 mm Distances = 0 mm (No spacing), Attaching part thickness = 10 mm Cube 40 MPa, Cracked concrete, fck,cube = 40 N/mm, d = 200 mm, c = 25 mm, cs = 25 mm, c1,1 = 150 mm, c1,2 Not available, c2,1-x Not available, c2,2-x Not available x = channel overhang = 25 mm Concrete with normal reinforcement Not available Not available

Reinformcement: Tension reinforcement: Shear reinforcement:

Overall result: OK (Maximum utilisation 94 %)

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 1 of 5

Construction project: Oberoi Mumbai Construction member: Top slab_200 mm Project number: Date: 13.05.2011

Loads Load point 1 2 25,00 125,00 4,19 4,19 6,75 6,75 (*)

Note: The specified load positions correspond to the critical load positions (-75 mm) within the displacement range x = 75 mm. Pair- and continuous loads will be shifted on the channel with constant load spacings. (*) load point 1 is relevant concerning the calculation.

2. anchor positions and resulting anchor loads (CEN/TS 1992-4, chapter 5) Anchor 1 2 25,00 275,00 5,67 2,71 9,14 4,36 (*)

(*) anchor 1 is relevant concerning the calculation.

3. Tension (CEN/TS 1992-4, chapter 6.2) 3.1 Steel failure Proof steel failure anchor (Anchor 1)

Proof connection between anchor and channel (Anchor 1)

OK

Proof local flexure (Load 1)

OK

Proof steel failure bolt (Load 1)

OK

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 2 of 5

Construction project: Oberoi Mumbai Construction member: Top slab_200 mm Project number: Date: 13.05.2011

Proof flexure of channel (Load 1)

3.2 Concrete failure Proof pull-out (Anchor 1) OK

Proof concrete cone (Anchor 1)

OK

4. Shear (CEN/TS 1992-4, chapter 6.3) 4.1 Steel failure Proof steel failure anchor (Anchor 1)

Proof connection between anchor and channel (Anchor 1)

OK

Proof flexure of channel lip (Load 1)

OK

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 3 of 5

Construction project: Oberoi Mumbai Construction member: Top slab_200 mm Project number: Date: 13.05.2011

Proof steel failure bolt (Load 1)

OK

4.2 Concrete failure Proof pry-out (Anchor 1) OK

Proof concrete edge c11 (Anchor 1)

OK

Proof concrete edge c12 (Anchor 1)

Proof concrete edge c21 (Anchor 1)

Proof concrete edge c22 (Anchor 1)

5. Interaction (CENT/TS 1992-4, chapter 6.4) Concrete (Anchor 1)

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 4 of 5

Construction project: Oberoi Mumbai Construction member: Top slab_200 mm Project number: Date: 13.05.2011

Steel (Anchor 1)

Anchor channel (Load 1)

Bolt (Load 1)

6. Summary of the calculations All proofs are okay


The acting loads can be passed into the concrete member, the transfer of the loads has to be verified separately This calculation bases on product specific properties. Changes, even to similar products are only possible with new calculations.
All data have to be checked with the given edge boundaries and the feasibility. DKG assumes no ability for the input data of the user

Deutsche Kahneisen Gesellschaft mbH

Nobelstrae 51, D-12057 Berlin www.jordahl.de/home

JordahlExpert Version 1.0.0.5

Page 5 of 5