Pekerjaan Engineering Service – Kajian Teknis Perubahan

Metode Crossing Fasilitas Milik ENI Muara Bakau Proyek Senipah


Balikpapan

Rev. Reason For


No Document Number Discipline Document Title
Code Issue
OPEN CUT
1 Soil Investigation ( 2 sample )
2 Alignment Sheet
3 Detail Drawing for Pipe Rack Crossing
4 Detail Drawing for Road Crossing
5 Detail Pipe Support Foundation & Layout
6 Shoring Protection System
7 Slope Stability Report
8 Construction Method
HDD
1 Soil Investigation ( 3 sample )
2 Alignment Sheet
3 Construction Method
4 Detail Drawing HDD Crossing Section
5 Bentonite Composition
6 Frack Out Analysis & Mitigation
GENERAL
1 Procons HDD vs Open Cut
2 Quantitative Risk Assesment
3 Layout Plan
4 Survey Topography