Windows Time and Hourly Demand Concrete

Volume Windows Time


WBS Duration
(m3) 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 24:00 01:00 02:00 03:00 04:00 05:00 06:00
Menggunakan Cycle Time 24 Jam
Borepile 256.00 6 42.67 42.67 42.67 42.67 42.67 42.67
Box Culvert Elevated 2 55.70 2 27.85 27.85
PCI Girder 3 mould Yogya-Bawen 150.35 9 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71
PCI Girder 2 mould Solo-Yogya 66.82 4 16.71 16.71 16.71 16.71
CSSP 30 mould Semarang-Demak 71.10 2 35.55 35.55
Grand Total Per Hour 599.97 - 42.67 42.67 42.67 42.67 42.67 42.67 27.85 27.85 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 16.71 35.55 35.55