MONITORING PENGIRIMAN GRANULAR BACKFILL BOX TRAFFIC/CULVERT
RUAS PEKANBARU-PADANG, SEKSI BANGKINANG-PANGKALAN
Box Culvert (Bc) 45 + 400 2x2 m3 430.20 645.30 92.66 Baby Roller 7 29-Oct 4-Nov
Box Culvert (Bc) 49 + 645 2x2 m3 1,000.00 1,500.00 92.66 Baby Roller 17 22-Oct 7-Nov
Box Culvert (Bc) 50 + 275 2x2 m3 630.06 945.09 92.66 Baby Roller 11 22-Oct 1-Nov
Box Culvert (Bc) 50 + 633 4x4 m3 1,001.94 1,502.91 130.45 Vibro Roller 12 29-Oct 9-Nov
Box Culvert (Bc) 50 + 852 2x2 m3 444.87 667.30 92.66 Baby Roller 8 3-Nov 10-Nov
Box Culvert (Bc) 51 + 334 3x3 m3 834.50 1,251.75 130.45 Vibro Roller 10 29-Oct 7-Nov
Box Culvert (Bc) 51 + 496 2x2 m3 470.49 705.74 92.66 Baby Roller 8 12-Nov 19-Nov
Box Culvert (Bc) 53 + 019 2x2 m3 586.07 879.10 92.66 Baby Roller 10 8-Nov 17-Nov
Box Culvert (Bc) 53 + 337 4x3 m3 2,261.66 3,392.49 130.45 Vibro Roller 27 11-Nov 7-Dec
Box Culvert (Bc) 54 + 229 6x3 m3 1,024.24 1,536.37 130.45 Vibro Roller 12 30-Nov 11-Dec
Box Culvert (Bc) 55 + 219 2x2 m3 341.26 511.89 92.66 Baby Roller 6 21-Nov 26-Nov
Box Culvert (Bc) 55 + 463 6x4 m3 1,567.95 2,351.92 130.45 Vibro Roller 19 9-Dec 27-Dec
Box Culvert (Bc) 56 + 063 6x3 m3 1,339.55 2,009.33 130.45 Vibro Roller 16 13-Dec 28-Dec