Packer Systems
Single String Retrievable Hydraulic/
Hydrostatic Set Rev. A
SU 10375
Effective Date: 6 Oct 2014
Table of Contents
1 Introduction ...................................................................................................................................... 4
2 Description ....................................................................................................................................... 4
3 Application ........................................................................................................................................ 4
4 Features and Benefits ...................................................................................................................... 5
5 Engineering Tables and Information .............................................................................................. 6
Specification Guide ............................................................................................................................ 6
Setting Sequence Shear Values ........................................................................................................ 7
POWER Tool ..................................................................................................................................... 7
DB™ Underreamer ............................................................................................................................ 7
Ordering Guide .................................................................................................................................. 7
Accessory Equipment ........................................................................................................................ 7
Product Selection Chart ..................................................................................................................... 7
6 HSE&S ............................................................................................................................................... 7
Revision History
Rev. DCR Amendment Detail Reviewer Approver Effective Date
New — Updates throughout document R. Ramirez D. Ruddock 24 Sept 2013
A Replaced 659 Packer Test Envelope R. Ramirez D. Ruddock 6 Oct 2014
1 Introduction
The Premier® removable production packer with Strik-
er® is a new class of removable packers for wells that
demand the sealing performance of a permanent pack-
er and the flexible workover options of a traditional re-
trievable packer. The tool is a hybrid hydrostatic and
hydraulic packer with the features and advantages of
both designs.
2 Description
The Premier removable production packer with Striker
has a primary setting mechanism actuated by absolute
well pressure, so it may be set without running a plug or
packer setting tool.
The secondary setting mechanism is the standard hy-
draulic method of running a plug in the packer tail pipe
and pressurizing the tubing.
The packer comes in two basic configurations:
1) Premium thread, box × pin, or 2) Left hand (LH)
square thread with sealbore × premium pin. The first
configuration allows threading the packer directly to the
tubing, while the second configuration provides work-
over flexibility so the tubing can be disconnected via an
anchor type seal assembly from the upper sealbore of
the packer. With the appropriate completion design, ei-
ther configuration can be retrieved on the production
tubing using a specialized Baker Hughes chemical cut-
ter. Alternatively, the second configuration can be re-
trieved on the work string using a Premier Work string
Retrieving Tool (POWER™) (Product Family H78464).
3 Application
The Premier packer with Striker has been developed
for markets where remote actuation of the production
packer within a completion brings added benefit and
cost savings to the customer. Savings can be achieved
by reducing rig and packer setting time and minimizing
the risk associated with standard well intervention set-
ting methods. It also reduces the need for additional
well services.
In addition to the cost savings, the Premier packer with
Striker and its tail pipe assembly are removed from the
well on the production tubing by mechanically or chem-
ically cutting the packer mandrel.
Drawing 385-178-00
4-1/2 in. 4-1/2 in. 4-1/2 in. 5-1/2 in. 4-1/2 in.
Tubing
15.1 lb/ft 12.75 lb/ft 17 lb/ft 23 lb/ft 12.6 lb/ft
175,000 lb
(10,000 psi)/ 230,000 lb (6,963 psi)/
System tensile rating* 300,000
220,000 lb 165,000 lb (10,000 psi)
(10,000 psi)
**Rupture disk supplied is as specified by customer and can range from 7,000–12,500 psi. Refer to Premier packer with Striker
specification sheet for minimum parameters required to select, design, and quote this tool.
†Outside diameter.
‡Inside diameter.
659-356
H784646500
645-356
831-463 H784648304
831-387 H784648303
659-356
H150973623
645-356
831-463 H150973629
831-387 H150973623
Ordering Guide
Not applicable
Accessory Equipment
Not applicable
Product Selection Chart
Not applicable
6 HSE&S
7 Preservation of Product
Storage Recommendations
Packers should be stored in a clean, dry area, preferably with climate control. Packers stored in a hor-
izontal position should be rotated 90° at least once every two weeks. A packer should be supported
by either the packer body or external metal components near the ends of the tool that have smooth,
flat surfaces. Supports must avoid contact with slips, cones, packing element systems, thread profiles
and any components that have direct contact with o-rings and other seals such as pistons and hous-
ings/covers.
8 Inspection
Step Action
1. Check that the body lock ring is visible through the sight hole in the body lock ring housing.
2. Check that the brass shear screws are backed off 1/4 turn.
3. Check that the ODs of the packing elements and the threaded backup rings are lower than the
upper cone and lower cone.
4. Check that the wickers on the upper slips and lower slips are sharp and not damaged.
5. Ensure all screws are installed and below flush OD.
6. Drift ID of packer with drift bar called out in the assembly and test fixture tools list.
7. Check the maximum OD of the packer against tabulated values.
8. Install thread protectors to premium connections.
9 Test Procedures
Testing and Removal
Step Action
1. Make up the Test Plugs (T004) to the packer and Striker and Pressure Test (T005).
2. Remove the Test Plugs, Clamshell Housings, Clamshell Quarters Spacers and Pressure Testing
Housing.
Pressure Testing
Each Premier packer and Striker has its own test fixtures. Both test fixture assemblies must be in-
stalled for proper pressure testing.
10 Operation
Size
The Premier packers with Striker are sized with two 3-digit numbers. The first number denotes the OD
of the tool, and the second one denotes the minimum ID. For example: A 645-356 is a 6.450-in. OD
packer with a minimum ID of 3.565 inches.
InQuest TUBEMOVE/Performance Envelope Instructions
To use the performance envelope, the differential pressure and tubing forces at the packer must be
calculated using the InQuest TUBEMOVE™ program. To run the InQuest TUBEMOVE program for
this packer, input the seal diameter as given in the specification guide as the seal diameter and input
the tubing as being anchored into the packer. With the pressure and force at the packer calculated by
InQuest TUBEMOVE, consult the attached performance rating envelope to ensure that the plotted co-
ordinate (pressure, force) is inside the envelope.
Prejob Preparations
Not applicable
Running Procedures
It is suggested that pup joints be made up above and below the packer for handling purposes. Run
the appropriate tubing tail pipe and make up the Premier packer to the top of the string. The tail pipe
assembly must contain a means to plug the tubing for the secondary actuation method. This may be
a Baker Hughes seating nipple or a shear-out plug. Run the packer into the well, slowly installing tub-
ing.
Primary Actuation (Hydrostatic)
The rupture disk of the Striker module is installed into the annulus side of the packer. To set the pack-
er, the absolute pressure of the well at the packer is increased to the specified value of the installed
disk and held for 15 minutes.
A minimum setting pressure of 7,000 psi is required to set the packer using the primary setting method,
Therefore, the minimum disk that can be installed has a 7,000-psi value. The maximum value of the
disk that can be installed has a value of 12,500 psi, due to the packer being rated to 13,500 psi. These
values take into account the tolerances of rupture disk burst pressures.
While pressuring the entire well to set the packer, an indication of packer setting can be achieved by
monitoring tubing and annulus pressure individually. On rupture of disk and packer setting while pres-
suring the well, tubing pressure will continue to rise while pressure in the annulus above the element
will remain constant giving an indication of packer setting.
Note: This option is only available if the well has not been perforated or pres-
sure can be applied against a barrier in the liner.
Step Action
1. The rupture disk of the Striker module will burst once its rating has been exceeded, allowing the
applied pressure to flood the lower atmospheric chamber.
2. The pressure will act across the lock dog retaining piston and push it upwards. The shear screws,
which hold the dog retainer in place, will shear due to this action.
Step Action
3. The lock dogs will then be able to unseat from their seating groove in the packer body, enabling
the setting piston to move upwards.
4. Continued application of the pressure will drive the setting piston up against the packoff parts of
the packer.
a button type slip, which anchors the tool during the cutting operation. Once the cutting operation is
completed the slips retract and the tool is free to be pulled from the well.
Once activated, the chemical cutter will cut cleanly through the packer mandrel allowing the packer
and tail pipe to be retrieved. In stacked packer applications, all the packers can be retrieved on the
production tubing simply by cutting all the packer mandrels.
Through-Tubing, Mechanical Cut
In restricted ID-type completions, coiled-tubing-conveyed mechanical cutting allows retrieval of the
Premier packer on the completion string. This cutting method must be predesigned into the original
completion as it requires the use of a through-tubing cutting extension (TCE). The TCE, placed above
the Premier packer, allows the cutting bottomhole assembly to locate and position itself across the cut-
ting zone of the packer.
A Baker Hughes DB underreamer should be run on an appropriately designed coiled tubing tool string
consisting of connector, dual flapper backpressure valve, hydraulic disconnect, dual actuated circula-
tion sub, adjustable no-go locating sub, mud motor, and DB underreamer. The adjustable no-go locat-
ing sub will be spaced out with the DB underreamer to place the cut in the required location. Care
should be given when running the bottomhole assembly to take accurate length, ID, and OD measure-
ments of the packer, pipe, and crossover connections. Enough space should be allowed above the
desired cutting area for the adjustable no-go locating sub to locate and still provide sufficient distance
for the mud motor and the DB underreamer.
The adjustable no-go locating sub is the only mechanism required to provide for set down weight of
the coiled tubing and accurate location of the DB underreamer and the subsequent cut of the packer
mandrel.
Once the cutting operation is completed, the cutting knives retract into the DB underreamer and the
entire bottomhole assembly is removed from the well.
In stacked packer applications, additional cuts will be required to sever all the packer mandrels before
the packers can be retrieved.
Milling Procedure
In the event the packer cannot be retrieved using standard retrieving procedures, the packer can be
milled over and retrieved.
A Type MJ™ Packer Retriever Tool (Product Family H14133) can be used in conjunction with a wash-
over assembly to burn over and retrieve the Premier packer in one trip. Run in the hole with the wash-
over assembly and appropriately sized METAL MUNCHER® milling shoe. Mill down to the slips or until
the packer moves downhole. Pull out of the hole with the washover assembly and recovered packer.
Software Procedure
Not applicable
11 Associated Units
• Premier Cut Release Removable Production Packer and Through-Tubing Removing Tool,
Size 7 in. × 3-1/2 in. (Product Family H78464), Unit 10026 under Packer Systems.
• Premier Cut Release Removable Production Packer, Sizes 7-5/8 × 4-1/2 and 3-1/2 and 7-5/8
Premier Workstring Retrieving (POWER) Tool (Product Family H78464), Unit 10026-2 under
Packer Systems.
• Premier Cut Release Removable Production Packer (Product Family H78464), Unit 10425 under
Packer Systems.
• Type MJ Packer Retriever Tool (Product Family H14133), Unit 4936 under Conventional Fishing.
12 Disassembly Instructions
This product should not be disassembled or redressed in the field. Contact AEG for further information.
13 Assembly Instructions
Test Fixture Assembly
Refer to Drawings 385-178-00P03 and 385-215-00P03.
Note: Before installing test fixtures, be sure all parts are cleaned and free of
debris and rust to allow for good contact between parts and to prevent
presetting the tool.
Step Action
1. Install the Male Clamshell Housing (T002) with the step closest to the slips. Slide the clamshell
past the groove in the Lower Slip Ring.
2. Install two Clamshell Quarters (T001) in the groove of the Lower Slip Ring (22) with the step
closest to the slips.
Step Action
3. Slide the Male Clamshell Housing (T002) down until the Clamshell Quarters (T001) are covered.
4. Install two Clamshell Quarters (T001) in the groove in the Body Lock Ring Housing (26) with the
step farthest away from slips and other Clamshell Quarters.
5. Slide the Male Clamshell Housing (T002) down until it shoulders on the Clamshell Quarters
(T001).
6. Make up the Female Clamshell Housing (T003) to the Male Clamshell Housing (T002) hand tight
until it shoulders on the Clamshell Quarters (T001).
7. Make sure the Male (T001) and Female Clamshell (T002) Housings are tightened so that the
clamshells are not loose. Try to slide the assembled fixture back and forth on the packer. If it
moves then the housings need to be tightened.
Step Action
1. Install the long Clamshell Housing [T012 (T018 for size 659)] on the striker with the small ID
closest to the packer. Slide the Clamshell Housing past the groove on the setting piston.
2. Place the Pressure Testing Housing (T001) to cover split between the bottom guide and lock dog
piston cover.
3. Install two Clamshell Quarters (T010) into the groove on the setting piston with the step closest
to the packer.
4. Start threading the long Clamshell Housing [T012 (T018 for size 659)] to the Pressure Testing
Housing (T001) without tightening completely.
5. Install two Clamshell Quarters (T010) in the groove of the bottom guide.
6. For 645 and 831 sizes only: Lay two Spacer Sleeves (T011) next to the step of the two
Clamshell Quarters (T010) against the bottom guide.
7. For 645 and 831 sizes only: Slide the short Clamshell Housing (T013) over the Spacer Sleeves
(T011) and the Clamshell Quarters (T010).
For 659 size only: Slide the short Clamshell Housing (T020) over the Clamshell Quarters.
8. Make up the short Clamshell Housing to the Pressure Testing Housing (T001). Make sure the
short Clamshell Housing is tight before tightening the long Clamshell Housing (T012).
9. Tighten the long Clamshell Housing (T012) to the Pressure Testing Housing (T001).
10. Check that the fixtures are tight so that the packer will not preset or damage the striker by trying
to slide the test fixture along the striker.
11. If loose, tighten both Clamshell Housings.
7 Key 2 H035459200
Premier Packer
Assembly and Test Fixture Parts List, Sizes 645-356 and 659-356
Refer to Drawing 364-028-00P01.
Material
Item Description Qty. Req’d
645-356 659-356
HPRESSTEST08 HPRESSTEST10
T005 Tubing Pressure Test 1 (8,000 psi tubing (10,000 psi tubing
pressure test) pressure test)
*May be ordered together as a unit (Material H036472500).
A 10.38 7.78
B 8.30 8.31
D 46.81
E 127.5 128.1
F 15.75
G 10.38
HWWG51D0W0
3 Set Screw 2 HWWG51D0W0
(3/8–16×7/8)
6 Key 2 H035731600
9 C-ring 1 H035732000
24 Housing 1 H035740100
HWWGE1D0SB
37 Brass Shear Screw 2 HWWGE1D0SB
(3/8–16×3/4)
HWWGE1D0DB
38 Brass Shear Screw 22 HWWGE1D0DB
(3/8–16×3/8)
HPRESSTEST08 HPRESSTEST075
T005 Tubing Pressure Test 1 (8,000 psi tubing (7,500 psi tubing
pressure test) pressure test)
Hydrostatic Set
Premier Removable Production Packer With Striker
Uncontrolled when printed - confirm the correct revision is used
SU 10375,
T010 Clamshell Quarters 2 H036369200
Rev. A
*These test fixtures are not required for the final test of the tubing.
Premier Striker Test Fixture
Hydrostatic Set
Premier Removable Production Packer With Striker
Uncontrolled when printed - confirm the correct revision is used
SU 10375,
T010 Clamshell Quarters 2 H036393100
Rev. A
*These test fixtures are not required for the tubing test.
16 Redress Kit
Hydrostatic Set
Premier Removable Production Packer With Striker
Uncontrolled when printed - confirm the correct revision is used
This product should not be disassembled or redressed in the field. Contact AEG for further information.
17 Rating Envelopes
Premier With Striker, Size 659-356
Figure 10: Unplugged Performance Envelope, (Material H784650048), Qualified per ISO 14310:V0
300000
0
Tension
200000
-10000
Page 29 of 33
200000 10000
200000
175000
100000
Force (lbs)
-100000
Set Down
Baker Hughes - Company Confidential
-220000 -220000
SU 10375,
-300000
-15000 -10000 -5000 0 5000 10000 15000
Above Pressure (psi) Below
Rev. A
Premier Packer with Striker, Size 645-356
Hydrostatic Set
Premier Removable Production Packer With Striker
Uncontrolled when printed - confirm the correct revision is used
200000 88964
10,000 psi
165,000 lbs
Tension
Tension
150000 66723
100000 44482
Seal Diameter = 4.750 in.
Casing ID Range: 6.625-6.750 in.
Page 30 of 33
Force (DaN)
Force (lbs)
50000 22241
10,000 psi
0 lbs
0 0
10,000 psi
0 lbs
-50000 -22241
Set-Down
Set-Down
-100000 -44482
Baker Hughes - Company Confidential
SU 10375,
141,000 lbs
-200000 -88964
-12000 -10000 -8000 -6000 -4000 -2000 0 2000 4000 6000 8000 10000 12000
Rev. A
Above Pressure (psi) Below
Figure 12: Premier Packer with Striker, Sizes 831-463/387
Hydrostatic Set
Premier Removable Production Packer With Striker
Uncontrolled when printed - confirm the correct revision is used
350,000 155,687
300,000 133,446
Point 2 Point 1
Tension
Tension
300,000 lbs 300,000 lbs
200,000 88,964
150,000 66,723
100,000 44,482
50,000 22,241
Page 31 of 33
Force (lbs)
Force (DaN)
0 0
(50,000) (22,241)
Seal Diameter: 6.135 in.
(100,000) Casing ID Range: 8.405-8.822 (44,482)
i
(150,000) (66,723)
Set-Down
Set-Down
(200,000) (88,964)
Point 3 Point 4
-10,000 psi 10,000 psi
Baker Hughes - Company Confidential
(250,000) (111,205)
-300,000lbs -300,000 lbs
SU 10375,
(350,000) (155,687)
(400,000) (177,928)
(12,000) (10,000) (8,000) (6,000) (4,000) (2,000) 0 2,000 4,000 6,000 8,000 10,000 12,000
Rev. A
Above Pressure (psi) Below
Premier Removable Production Packer With Striker SU 10375, Rev. A
Hydrostatic Set Effective Date: 6 Oct 2014
18 Forms
Premier Packer With Striker
Specification Sheet
This specification sheet is intended to be used as a guide to establish ratings and parameters required to select or
design a Premier packer with Striker for a customer’s specific application.
General
Size
Maximum OD inches
Minimum ID inches
End connection up
Material
Flow wetted components: Components that can come in direct contact with the dynamic movement of well fluids
in the flow stream. (typically body and guide).
Internally wetted components: Flow wetted components plus components out of the flow stream, but they are
contacted by well fluids through a port or other passage to the flow wetted area (typically body, guide, upper setting
piston and secondary piston).
Exposed components: Flow wetted components plus internally wetted components plus components contacted
by well fluids below the packing element (typically all parts, please specify if this includes pack-off parts i.e., slips,
rings, cones).
Elastomers
Packing element
Note: Double O-rings are used on all atmospheric chambers. Nitrile is used as
the initial seal for low temperature sealing (i.e., while running downhole,
with the secondary seal being chosen to be compatible with the well en-
vironment.)
Performance ratings
Note: Rupture disk setting is what would actually be installed with regard to
burst value (psi) on the packer. Rupture disk range minimum-maximum
is based on the maximum value that can be installed due to the packers
chamber rating and the minimum value is based on the minimum load
to set the packing element.
Note: Secondary setting pressure is as a rule, kept to around the same pres-
sure as standard Premier packer hydraulic tubing set pressures for that
specific size.
Miscellaneous