Professional Documents
Culture Documents
Signature : Date :
Site :
Section 2 - Detail of the Excavation (Attach As-Built Drawing showing limits of the excavation work to this Certificate)
Section 3 - Detail of the Existing Underground Services near the Excavation Work (Attach As-Built Drawing showing limits of the
excavation work to this Certificate)
Section 4 - Departmental Approval (Responsible Supervisor to nominate Departments that require to be consulted. Nominated
departments complete required information below)
Department / Division
Nominated Remarks / Conditions / Observations Name / Signature Ref ID Position Date
Telecom/IT
Electrical
Instruments
Pipelines
Survey
O Banksman/Rigger/Watchman to be provided
I authorise the excavation work specified above to be carried out, subject to the above precautions being enforced and maintained, during the
validity period of the covering Permit to Work/No Permit Certificate for the work specified in Section 1 of this form.
Name : Ref ID :
Signature : Date :
Expiry date :
NOTE : This certificate is valid for the scope defined in Section 02 (including the supporting drawings). The certificate may be used to support sub sequent permits
etc, provided the scope or any associated risks do not change.
I understand the cotent of this certificate and shall ensure that all work is undertaken in accordance with the instruction stated and in accordance
with any other mandatory governing procedure(s) that are/is in affect.