Professional Documents
Culture Documents
Rotary Screw
Gas Compressor
Operation and
Maintenance
Handbook
2
Introduction
Thank you for choosing our Cummins powered LeROI rotary
screw compressor system for your production needs. We
specialize in well head gas compression with packages ranging
from 15 to 500 horsepower. As an ASME code welding shop, we
have the capability and flexibility to fabricate a custom package to
suite all of your well head and booster production needs. We have
engineered our units to have optimum production, maximum run
times (including cold weather environments), and years of great
performance when properly maintained.
3
Table of Contents
Warnings………………………………………..…………………………5
Pre-start Checklist……………………………………………….……..…7
Starting Procedure…………………………………………..…………….8
Commissioning…………………………………………………………..12
Maintenance………………………………………………….……….….14
• PM Schedule……...………………………..…….…………..14
4
CAUTION!
Read before proceeding!
WARNING: If the information in these instructions is not followed exactly, a
fire or explosion may result, causing property damage, personal injury, or loss
of life.
Never alter the manufactured system in any way. Any changes will void the warranty and
product liability if not authorized in writing by Fluid Compressor Partners.
5
Installing the Unit
1. Set the unit on a flat, level, and packed surface. The suction inlet and discharge
outlet are oriented on opposite ends of the skid and sight preparation should be
handled with this in mind. Fluid Compressor’s equipment is built for rugged
reliability. However, care should be taken when moving the unit to prevent
damage.
2. When planning the installation, consider the cooling air flow. This machine’s
heat exchanger uses an induced draft cooling air flow (air flows through the cooler
towards the engine). Do not set unit where the prevailing winds will be opposite
of cooling air flow.
3. Install a by-pass in the flow line and full port valves at the suction and discharge
to isolate the compressor. Therefore, if the compressor has to be maintained your
gas flow will not be shut off. It is also recommended to install a check valve in
the by-pass that will allow gas to flow past the machine during a plunger cycle or
downtime.
4. Depending on the site conditions, a suction pressure controller may be required.
Be sure it is of sufficient design to positively hold against the highest possible
well-head build up pressures and that it is adequately sized for the expected flow
rates.
5. Depending on the site conditions and machine configuration, a discharge back-
pressure regulator may be required. Be sure it is of sufficient pressure rating to
handle the highest possible discharge pressures and is adequately sized for the
expected flow rates.
6. Open sight glass valves on the engine coolant surge tank and open the compressor
lube oil block valve at the discharge separator oil outlet. Open all ball valves on
engine oil supply system, except for the drain hose valve. Ensure all engine jacket
water valves are open, including the vessel heat trace lines and the coolant filter
block valves that are located on the engine.
** Unit shipped with valves closed.
6
Pre-start Checklist
1. Before starting, read and adhere to the warnings on page 5.
2. Check engine oil level on the dipstick on the right side of the engine. Oil can be
added through the filler next to the dipstick. Do not run the engine if the oil
level is too high or too low.
3. Check compressor lube oil level. Oil should be visible in the discharge vessel
sight glass above the minimum level line.
4. Ensure all valves in the engine and compressor oiling systems are fully open.
5. Ensure engine coolant is visible in sight glass on surge tank and is at least at half
level.
6. Check suction scrubber sight glass and drain if fluids are present. Ensure there
is no pressure or vacuum on the system before opening drain valve!
7. Drain fuel gas bottle daily. If fluids are continually present, slightly open the
needle valve that will allow the liquid to drain into the suction scrubber’s
blowcase.
8. Ensure all drain valves are fully closed. Drain valves are included on the suction
scrubber, discharge, filtration, engine oil, cooler, and fuel vessels.
9. Check V-belts for proper tension, alignment, and for cracks or wear.
10. If equipped with TTD annunciator panel, set shutdown pins in panel box. The
sizing and conditions determine the settings for suction and discharge pressure
shutdowns. If there is no oil pump, the low discharge shutdown must be set at
60 psig higher than the actual suction pressure. Never operate outside of design
conditions unless sizing calculations have been made by Fluid Compressor
Partners. Engine oil pressure gauge should be set at 20 psig. Use a hex head
wrench to adjust. Engine temperature gauge should be set at 245 º F.
11. If well pressure exceeds design suction pressure due to head pressure build up, a
pressure regulating device must be installed on the inlet side of the compressor.
12. Ensure Versatrol control valves are in the open position.
13. If equipped with a mechanical governor, turn the throttle cable clockwise until it
stops to be in the idle position.
14. Visually inspect and listen for leaks. Correct any problems before starting.
15. Ensure all guards are in place, secure, and undamaged before starting.
7
Starting Procedure
1. Before starting, read and adhere to the warnings on page 5.
2. Open discharge valve to sales line.
3. Open suction valve. Refer to previous page if high well pressures exist.
4. Set system power to on.
5. If equipped with an electronic governor, set switch to idle and turn
potentiometer knob fully counterclockwise.
6. Press reset on the Murphy TTD annunciator.
7. Push and hold start button, engine should start quickly. Release start button
when engine is running.
8. If engine does not start quickly, do not hold start button for more than 10
seconds.
9. Let engine idle until oil pressure is above 20 psig and all operating conditions
are checked. Ensure pressure gauges are functioning.
10. Ensure all four Versatrol valve position indicators are extended (unloaded). If
not, change position of the control valves under the panel.
11. Ensure engine manifold vacuum is 3” hg vacuum or deeper vacuum. If it is at
less vacuum than 3” hg, reduce suction pressure.
12. Allow engine to reach 125 deg F before increasing speed.
13. For electronic governors, switch from idle to rated. Engine will ramp up to
potentiometer set point. Increase speed slowly, while watching gauges, by
turning the potentiometer clockwise. Operate Engine between 1500 rpm and
1800 rpm.
14. For mechanical governors, turn throttle cable slowly counter-clockwise while
watching gauges to increase speed. Operate Engine between 1500 rpm and 1800
rpm.
15. Once at full speed, allow compressor to warm up until discharge temperature is
at least 125 deg F.
16. Load Versatrol ports one at a time while watching gauges, particularly manifold
vacuum and discharge pressure. Do not over-load the machine. Often times, the
well must be pulled down before there is enough power to fully load the
compressor.
17. The loading order for the Versatrol valves is 4,3,2,1, and the unloading order is
opposite. (See the LeROI compressor section of this document for more detail
on Versatrol valves).
18. The indicator on each Versatrol valve will be fully retracted when loaded.
19. Ensure all conditions stabilize and are within operating specs and design
capabilities of the machine.
8
PLC Panel Starting Procedure
1. Before starting, read and adhere to the warnings on page 5.
9
PLC Panel Starting Procedure Continued
1. Before starting, read and adhere to the warnings on page 5.
During normal operation, when left untouched, the screen will go into a screen
saver mode that scrolls through screens displaying various gauge functions in a very
large easy to read format.
Touching the screen at any point will return you to the Main screen.
10
Shutdown Procedure
Before shutting down machine, read and adhere to the warnings on page 5.
Check all gauges for normal function and operating conditions and listen for
unusual sounds or signs of problems or maintenance requirements. Look for leaks.
Ensure that performance is as expected. If all checks out OK, proceed with shut-
down:
1. Unload compressor (ignore if Versatrol indicators are extended (unloaded)).
• With manual Versatrol control, unload valves in the order 1,2,3,4 slowly
while watching gauges between each step.
• With PLC automation, select MANUAL operating mode from the
touchscreen, then touch the UNLOAD cells. All valves can be
commanded to unload and the computer will ensure they unload in the
proper order.
2. Slow the engine down to idle speed (900 rpm to 1400 rpm is acceptable).
• For mechanical governors, turn the throttle cable clock-wise slowly
while watching gauges.
• For electronic governors and TTD panels, turn the potentiometer
counter-clockwise slowly while watching gauges.
• For PLC automated panels, select IDLE from the Main page on the
touchscreen.
3. Allow the system to cool down for 2 minutes idling in an unloaded state.
4. Stop the engine.
• For TTD panels, press stop on the annunciator.
• For PLC panels, turn the switch to the off position.
• Do not use the ESD button to stop the engine unless it is an emergency.
11
Commissioning
Always follow previously outlined start-up and shutdown procedures, including
safety precautions outlined on page 5, but when a machine is started for the first time
on a location or when operating conditions change considerably, some very specific
settings and adjustments must be made.
*First, start compressor and fully load in accordance to previously outlined steps.
Ignition Timing
1. Per the Cummins manual, check timing and adjust if necessary.
• The factory setpoint is 26 deg BTDC. This is ideal for most applications
running on natural gas.
• High elevations or unusual fuel or temperature conditions may require
timing changes.
• If timing is to be adjusted, follow procedures outline in the Cummins
manual.
• Beware that this is a 24VDC system and will ruin a 12 volt timing light.
Fuel Pressure
Adjust the fuel pressure as follows:
• Ensure engine is at full speed and load.
• First cut regulator should be set to allow 25 psi on the fuel gas scrubber.
• Second cut regulator should be set to allow 14” water column pressure.
This is to be checked at the 1/8” valve on the upstream side of the final
cut regulator (on the bottom of the regulator).
• Final cut regulator is to be set to allow 5” water column pressure to the
carburetor. This pressure is to be checked at the downstream 1/8” ball
valve on the bottom of this regulator.
Fuel Mixture
1. Ensure engine is at full speed and load.
2. If equipped with an air/fuel ratio controller, manually set the controller to the
off position.
• Scroll down on the controller to the password section and enter the
password.
• The password is the serial number of the controller, plus 10 (ex: s/n of
1234 would have a password of 1244).
• Scroll to the operating mode and set it to OFF.
• The enclosed manual gives full detail on the operation of the controller.
• If the area requires the use of the AFRC, it must be turned on again after
carburetor adjustments are made.
3. With properly calibrated test equipment, analyze the exhaust gas content.
12
4. If equipped with a catalytic converter, the exhaust gas must be sampled from
upstream of the element. There is a 3/8” stainless steel line connected to the
upstream sampling port of the housing running down the face of the cooler.
5. The specified excess O2 content is 0.54%.
6. Less O2 indicates a rich condition which will cause severe engine damage.
7. More O2 indicates a lean condition which limits the engine’s power and can
cause damage if extremely lean.
8. Adjust the power valve on the carburetor until the mixture reads the specified
O2.
9. The adjustment is made by inserting a 1/8” Allen wrench into the hole directly
opposite of the fuel inlet.
10. To richen the mixture, turn the screw counter-clockwise.
11. To lean out the mixture, turn the screw clockwise.
12. Make small changes and allow the analyzer time to stabilize before changing
again. ¼ turn increments would be a good starting point with smaller changes
when you are getting close to the specified setpoint.
13. Check exhaust gas temperatures after all adjustments are made and ensure they
are within operating limits.
• Note that the rated 100% load is not acceptable for continuous operation.
Never allow the engine to run with less than 3” hg vacuum on the intake
manifold.
Compressor Set-Up
1. Ensure bearing lube oil pressure is at least 60 psig above suction pressure. It is
recommended to keep 75 psig or more on it.
• If the pressure is too low, consult the attached LeROI operation manual
for instruction on changing orifice size.
• When changing the orifice, always follow the shutdown and re-start
procedures and be sure the unit is isolated and all pressure is relieved.
2. Adjust vi ratio for optimum performance per the LeROI manual.
13
Maintenance
This compression package will offer years of trouble free service if properly operated
and maintained.
14
MAINTENANCE/REPAIR PARTS LIST
Part Number Brand/Vendor Description
HDAX LA
Chevron/Texaco Engine oil
15W-40
15
DAILY: ROUTINE INSPECTION
Operating conditions
Check all gauges and record the following. Ensure the conditions are within
design parameters.
• Suction Pressure
• Discharge Pressure
• Discharge Temperature
• Engine Manifold Vacuum
• Engine Oil Pressure
• Engine Jacket Water Temperature
• Gas Production Volume (if available to read)
Fluid Levels
Visually inspect the following fluid levels and replenish if necessary. (Where
applicable, ensure sight glass valves are opened).
• Engine Oil Level (when running, check sight glass on level maintainer,
with engine down, check at dip stick)
• Engine Oil Day Tank Level
• Engine Jacket Water Level
• Compressor Lube Oil Level
• Suction Scrubber (dump if liquids are present)
• Fuel Gas Scrubber (auto drain valve may be cracked open if fluids exist)
• Governor Sump Oil Level (check only with engine down. Uses same oil
as engine. Only applies to mechanical governors)
Machine Status
Check the following items to ensure they are within allowable parameters.
Take appropriate action as needed.
• Compressor Lube Oil Filter Differential Indicator
• Compressor Lube Oil Injection Pressure (must be 60 psig or more above
suction pressure unless oil pump is present)
• Inlet Filter Differential Pressure (install test gauge in ports before and
after filter)
• Discharge Coalescent Filter Differential Pressure (install test gauge in
ports before and after filter)
• Engine Air Filter Restriction Indicator
• Test Spark Plug Firing Voltage (all firing within 25% of each other and
all firing with no more than 25 KV)
• Check Ignition Timing (26 degrees BTDC unless conditions require
otherwise)
• Check for leaks and unusual noises or vibrations
16
750 HOURS: MAINTENANCE ONE (M1)
Routine Inspection
Before performing M1, the daily routine inspection procedure (previous page)
must be performed.
After the inspection is completed, unload and shutdown the compressor in
accordance with the shutdown procedure on page 11.
17
General PM Inspection and Maintenance
• Remove and inspect air filter, replace if necessary
• Grease cooling fan bearings per the label on the cooler shroud
• Remove mesh pad from crankcase vent and thoroughly clean
• Inspect engine accessory belt and cooling system belts
• Inspect unit for leaks, loose fittings and bolts, cracked welds, etc
• Inspect cooling system for cracked hoses
• Inspect throttle linkages for damage or wear
• Inspect exhaust system for cracks, leaks, loose catalyst door latches, etc
• Wash unit as needed. A clean unit is safer, easier to maintain, and acts
as an example of our company’s commitment to the environment
18
1500 HOURS: MAINTENANCE TWO (M2)
Routine Inspection
Before performing M1, the daily routine inspection procedure (page 14) must
be performed.
After the inspection is completed, unload and shutdown the compressor in
accordance with the shutdown procedure on page 11.
750 Hour M1
Before performing M2, M1 (previous pages) must be performed.
Spark Plugs
If spark voltage was near or exceeding 25 KV during routine inspection,
replace spark plugs. If voltage was normal and had less than 25% variance between
cylinders, remove and inspect spark plugs. Use a clean, magnetic spark plug socket.
Replace with new spark plugs if:
• Electrode appears worn or is fouled with deposits
• Electrode insulator has cracks
• Porcelain has cracks, corona marks, or flashover (dark markings that
will not wipe clean)
If sparks plugs appear good upon inspection, re-install them:
• Check gap. Set at 0.020”. Do not pry between electrode and ground;
this will damage the precious metal electrode. Only bend ground
• Clean porcelain with rubbing alcohol and do not touch it
• Replace spark plug gasket (PN 3075639)
• Install with clean magnetic spark plug socket (rubber inserts will
contaminate the spark plug that you just cleaned)
• Hand tighten all spark plugs gently, then torque each to 28 ft-lbs
* New spark plugs must also have the gap set, be kept clean, and be properly
torqued. They will come with new gaskets.
* Always use dielectric grease on wires. Clean wires and apply dielectric
grease at coil connection and spark plug connection.
* Never use any type of power or air tool on spark plugs. The harsh vibrations
will crack the ceramic.
*NOTE: If inductive voltage measuring tool is not available, replace spark plugs at
each M2 interval
19
• Rotate engine by turning the nut on the accessory drive (in front of the
magneto) with a 1 5/16” end wrench. It can be accessed from the
bottom without removing the guard. Turn it until the timing indicator
lines up with the 1-6 VS mark.
• If at the #1 TDC compression stroke, both rocker arms on cylinder one
can be moved side to side. If not, turn the engine one full revolution and
stop again at the 1-6 VS mark
• Adjust the cross heads to zero lash per the manual. This can be done by
feel by loosing the jam nut, holding the cross head down, and adjusting
the screw until it just touches, then turn it about 1/24th of a turn, which is
the distance of ¼ of a wrench flat on the jam nut. Re-set jam nut while
holding screw in place with large screwdriver
• Loosen jam nuts on valves and adjust with a screwdriver until a feeler
gauge between the valve stem and rocker arm can be moved between
them with drag. Set the jam nut while holding the screw in place
• The clearance for the intake valves is 0.014”. The intake valves are the
inner two on each rocker box.
• The clearance for the exhaust valves is 0.038”. The exhaust valves are
the outer two on each rocker box
• Do the above steps for valves:
o Cyl 1 intake and exhaust
o Cyl 2 intake
o Cyl 3 exhaust
o Cyl 4 intake
o Cyl 5 exhaust
• Rotate engine 360 degrees by turning the nut on the accessory until the
timing indicator lines up with the 1-6 VS mark again. You should be
able to move the rockers side to side for both valves on cylinder 6
• Make the same adjustments as above, but for valves:
o Cyl 2 exhaust
o Cyl 3 intake
o Cyl 4 exhaust
o Cyl 5 intake
o Cyl 6 intake and exhaust
• Re-install valve covers with new gaskets. The torque spec for the valve
cover bolts is 59 ft-lbs
Re-start compressor per the start-up procedure outlined on pages 8-10.
Carefully watch all gauges until machine is at full speed, temperature, and
operating conditions.
Listen for unusual sounds and carefully inspect for leaks.
Check flow meter to ensure performance is as expected for the local
conditions.
Check O2 level in exhaust and adjust per procedure on pages 12-13.
20
21000 HRS: MAINTENANCE THREE (M3)
Routine Inspection
Before performing M3, the daily routine inspection procedure (page 14) must
be performed.
After the inspection is completed, unload and shutdown the compressor in
accordance with the shutdown procedure on page 11.
Replenish Fluids
• Re-fill cooling system with new coolant and DCA4 additive. The
mixture is 1.2 units of DCA4 per gallon, which in this system equates to
approximately 7.5 quarts of additive and 60 US gallons of 50/50
antifreeze and water mixture
• Change engine oil and filter, water filter, and top off day tank
• Change governor oil (Woodward PSG hydraulic governor only)
21
39000 HRS: MAINTENANCE FOUR (M4)
Routine Inspection
Before performing M4, the daily routine inspection procedure (page 14) must
be performed.
After the inspection is completed, unload and shutdown the compressor in
accordance with the shutdown procedure on page 11.
Engine Over-Haul
• Drain engine jacket water, including heat trace system
• Drain engine oil
• Over-haul engine per the master over-haul manual
• Set valve clearances per the procedure outlined in the previous pages
• Install new spark plugs per the procedure outlined in the previous pages
Engine Replacement
An alternative to an in-frame overhaul would be to replace the engine with a
new or remanufactured engine
• Properly support the front of the screw compressor or remove the
compressor
• Remove cooling fan belts and guard
• Remove fuel plumbing, oil plumbing, etc
• Replace engine
• Re-install compressor, guards, plumbing, etc
• Set valve clearances per the procedure outlined in the previous pages
• Install new spark plugs per the procedure outlined in the previous pages
Replenish Fluids
• Re-fill cooling system with new coolant and DCA4 additive. The
mixture is 1.2 units of DCA4 per gallon, which in this system equates to
approximately 7.5 quarts of additive and 60 US gallons of 50/50
antifreeze and water mixture
• Change engine oil and filter, water filter, and top off day tank
• Change governor oil (Woodward PSG hydraulic governor only)
22
General PM Inspection and Maintenance
• Remove and inspect air filter, replace if necessary
• Grease cooling fan bearings per the label on the cooler shroud
• Inspect engine accessory belt and cooling system belts
• Inspect unit for leaks, loose fittings and bolts, cracked welds, etc
• Inspect cooling system for cracked hoses
• Inspect throttle linkages for damage or wear
• Inspect exhaust system for cracks, leaks, loose catalyst door latches, etc
• Wash unit as needed. A clean unit is safer, easier to maintain, and acts
as an example of our commitment to the environment
23
THE FOLLOWING SECTION OUTLINES THE
MAINTENANCE AND OPERATING REQUIREMENTS OF
THE LEROI ROTARY SCREW COMPRESSOR
24
Identifying Your Compressor
LeROI gas compressors have a nameplate that provides valuable information
compressor.
25
Oil Flow and Orifice Sizing
As mentioned previously in this manual, rotary screw compressors require oil lubrication of
the bearings, cylinder and rotors. Bearing lubrication is necessary for long life. Cylinder and
2. Provides a seal between the cylinder and rotors to reduce gas slippage.
In certain applications the pressure differential (discharge-suction) is such that an oil pump is not required.
However, if the application has a lower pressure differential than an oil pump will be required. It is
important for the application to be reviewed especially if the the unit will be moved from one site to
LeROI gas compressors have an oil injection manifold that distributes oil supplied by the pump or pressure
differential. The orifice creates a restriction. A smaller orifice results in a greater restriction, which forces
more oil to the bearing and less oil to the rotors. The goal is to create a proper balance in the compressor
26
Oil Flow and Orifice Sizing
Pumps are installed at the factory based on packager instructions or specified operating
operation. After testing, the standard orifce or an orifice specified by the customer is
There are several size options for each compressor. In the event that an orifice is needed and one is not
readily available one can easily be created. Simply drilling a hole in a solid plug will provide the orifice. It is
also important to note that you may need to create an orifice in the event your desired size is in between
Temperature/Viscosity/Pressure
Refer to Figure 7 for temperature and pressure methods and locations.
(Switch must be located between compressor discharge flange and separator tank inlet.)
27
Temperature/Viscosity/Pressure (Continued)
For heavy gas streams, a 30-40 °F temperature difference may not be possible
Oil pressure difference – gas inlet versus oil injection: 60-100 psi
(When gas discharge pressures are 50 psig or less, it may not be possible
to achieve 60 psig oil pressure. That is acceptable if all other specifications are met.)
28
Field Evaluation of Pump & Oil
Injection Orifice Size
Temperature measurements at points A, B, and C should
Equipment & Measurement Location be made on sections of pipe or tube (not fittings) as
close to the compressor as possible.
Although other permanent instrumentation is
necessary for monitoring overall package Pressures at points D and E should be as close to the
performance, the following are specifically for the compressor as possible. There is typically an unused
purpose of evaluating the pump and orifice size. port on the oil injection manifold for E. Point D is
Table 2 Instruments & Measurement Locations located in the package inlet piping. If pressures are not
Instrument Data Location
taken at these specific locations, they should at least be
Infrared (IR) a. oil injection (A) pipe located on the compressor side of any major restrictions
temperature
gun
temperature
b. gas discharge (B) pipe
such as a filter.
temperature
c. discharge bearing
oil drain temperature
(C) tube (goes
down on some
WHEN TO CHANGE A PUMP OR ORIFICE
models) Yes
Pressure gage or d. gas inlet pressure (D) inlet pipe Is difference between gas Larger pump or orifice is
transducer 1 disch & oil injection temp required. Use
o
Pressure gage or e. oil injection (E) injection more than 40 F? performance program to
transducer 2 pressure manifold resize
No
C
B Smaller pump or orifice is
required. Use performance
program to resize
Although probes inserted directly in the gas or oil Is diff between bearing
oil drain & oil injection Install smaller injection
stream will give more accurate results, an infrared temp more than 20 F?
o
orifice.
(IR) temperature gun is recommended for this OR Is oil injection
pressure less than 60 PSI
procedure. Since a probe cannot be readily used on above gas inlet? (see Note: When gas disch
pressure is below 60 PSI it
the discharge bearing drain, the IR gun will allow a Note)
may not be possible to
better comparison. No
achieve 60 PSI oil pressure,
even with the smallest orifice.
This is acceptable if the
For best results when using an IR gun, slowly bearing oil drain temp is
moving the IR gun over the item to obtain the Is diff between bearing
no oil within spec.
drain & oil injection temp
highest temperature. Be careful not to pick up less than 3°F? OR is oil Yes
Install larger injection
temperatures from background objects. injection pressure more
orifice.
than 100 PSI above inlet
pressure?
29
Variable VI Adjustment
Variable Vi is used to minimize the power required by the compressor. It does not change flow
directly, but can allow an increase in flow through more efficient use of power. Vi is the volume
compression ratio of a compressor: V1 / V2. The internal Vi of the compressor is determined by the size
of the discharge port. A small port causes gas to be released later in the compression cycle resulting in a
higher internal Vi, while a larger port allows the gas to be released earlier in the cycle resulting in a lower
internal Vi. The ideal Vi for an application can be calculated if the inlet and discharge pressures and k
(Cp/Cv) of the gas are known.
The compressor makes the most efficient use of power when the internal Vi equals the ideal Vi. For
example, if the internal Vi is high but the ideal Vi is low, the gas is compressed to a pressure greater than
the external pressure prior to being released. On the other hand, if the internal Vi is low but the ideal Vi
is high, gas momentarily flows backward into the compressor and is re-compressed. Both of these
scenarios result in wasted energy.
The standard discharge housings of the HG17, HG24, LG30, and LGL30 compressors have a 4.4 Vi
port, but are fitted with four valves that can be opened to increase the total size of the discharge port, so
that the following internal Vi’s can be achieved.
Instructions
THE COMPRESSOR CAN BE VERY HOT!
PROTECT YOUR SKIN WHEN ADJUSTING A RUNNING OR HOT
COMPRESSOR.
30
P1 and P2 must be in PSIA, and be at the compressor inlet and discharge flanges. Be sure to
account for package pressure drops, which decrease the inlet pressure and increase the
discharge pressure at the compressor flanges. As a quick reference, for a typical natural gas
with k = 1.26, the pressure ratios that correspond to available internal Vi’s are:
Vi P2 / P1
4.4 6.5
3.0 4.0
1.9 2.2
Since there are three available internal Vi settings, each must cover a range of ideal application
Vi’s:
After Determining the appropriate Vi ratio perform the following steps to adjust the internal
Vi ratio:
Figure 8:
Compressor discharge end showing four
closed Vi valves fitted with special locknut-
thread protectors.
Figure 9:
Remove locknuts with wrench before
making adjustments.
31
Figure 10: For MEDIUM Vi, turn the inner
valves counterclockwise until they are fully
out.
32
Versatrol Capacity Control
Versatrol capacity control is used to regulate compressor flow and reduce power requirements.
Versatrol consists of a set of pressure actuated valve assemblies mounted on the side of the compressor.
When opened, these valves allow gas to leave the compression cycle and return to the compressor inlet
prior to compression and delivery, thus reducing flow and horsepower. A valve is closed by applying
actuating pressure and opened by releasing actuating pressure. This can be used to ramp up the
compressor during start up. Start the compressor with all the ports open then close them.
Versatrol is available on the HG12 and larger models. Due to the small cylinder size, the HG12 has two
valves and an external by-pass (Figure 14). All larger models have four valves with an internal by-pass
(Figures 15 and 16).
33
Versatrol Capacity Control Continued
Actuation:
The Versatrol valves can be operated with pressurized air, gas or lubricating fluid depending on
whether it is step or stepless control. The actuation pressure should be the same or nearly the same
as the compressor discharge pressure. The valves should be opened in the 1-2-3-4 sequence and
closed in the 4-3-2-1 sequence, except the HG12. The HG12 can be opened or closed in any
sequence.
Oil may be used for either step or stepless control. Oil taken from the gas/ oil separator or after the
oil pump should have adequate pressure to allow Versatrol actuation. Oil should always be filtered
prior to entering the control system.
Air or gas can be used for step control systems only. Air and gas are compressible and will not allow
accurate or quick control responses. Air can be used for stepless control systems without a problem.
As mentioned previously, the valve is unloaded or opened by reducing the control pressure. When
the control pressure is reduced the higher pressure inside of the compressor opens the valve.
Therefore, it is important for the actuation pressure during the unloading stage to be lower than the
cylinder pressure. To ensure this occurs, the Versatrol valve assembly should be vented to the
cylinder inlet if actuated by gas or oil. If the air is used in the control system then it will have to be
vented to the atmosphere.
Plumbing:
Steel or stainless steel tubing and fittings should be used. Copper tubing is not recommended.
Copper and gas can react and reduce the reliability of your system.
Tubing runs should not be any longer than necessary in order to avoid reduced response times
between controls and the Versatrol valves. Tubing should be 3/8”. Tubing size increases in
importance in cold environments or when tubing runs exceed 4 feet.
34
Oil and Related Items
The lubrication system is vital for reliable operation of LeROI gas compressors. Following these guidelines
about oil and related items will ensure years of reliable service.
Oil Filter: Check after first 100 hours. Change once a month if continuously operated or every 1000
hours otherwise. Filter must be changed with every oil change.
At the minimum a differential pressure is recommended for the oil filter. A differential gauge
with an alarm is advised.
Viscosity: The packager/user is responsible for selecting oil that is compatible with the gas, and can
maintain minimum viscosity at the operating conditions. The recommended viscosity is 15
centistokes regardless of the operating conditions. The minimum viscosity is 13 centistokes
regardless of the operating conditions.
Oil viscosity greater than 15 centistokes can affect performance, especially horsepower.
Analysis: Oil should be analyzed on a regular basis. Oil should be checked once a week for the first
month, with at least two of those samples being analyzed. If the first month of samples is
okay then the analysis can be reduced to once a month. Increases in water content and metals
should be watched closely. All reputable oil suppliers and manufacturers will analyze oil
samples at no charge.
Recirculation: It is important that the oil recirculates at least two times per minute, especially with heavier
hydrocarbon and water saturated gases. This keeps the oil temperature higher, thereby
reducing the possibility of hydrocarbons condensing and affecting the viscosity of the oil, or
having water condense and cause lubrication problems.
Strainer: When there is an oil pump, it is recommended that a Y-strainer be installed between the
separator and the suction to the pump
It is recommended that a Y-strainer be installed downstream of where the oil leaves the
discharge bearing retainer, and where it is injected in the casing. This will reduce the
possibility of a catastrophic failure if a bearing fails on the discharge end.
Coalescing: The coalescing element in the gas oil separator should be monitored with a differential
pressure gauge. This element should be changed as required. It should be checked at least
once a year. It is important that the filter element have enough surface area to remove oil
from the gas stream.
Gas Filtration: Gas filtration is recommended. Particulate in the gas stream can contaminate the oil and
cause premature failure.
Temperature: Oil temperature in and out of the rear-bearing retainer should be checked regularly. If
differential is greater than 30°F, there may not be sufficient lubrication for that are. This
could also be an indication of worn bearings.
35
Service Procedures - Components
BEFORE REMOVING ANY COMPONENTS SHUT THE UNIT DOWN,
CLOSE ALL INLET AND DISCHARGE SHUTOFF VALVES, RELIEVE ALL
PRESSURE BY “PUMPING OUT”. MAKE CERTAIN THE PRESSURE
SYSTEM REMAINS VENTED TO ATMOSPHERE. DISABLE, LOCKOUT
AND TAG THE PRIME MOVER.
Compressor Service:
The compressor for these units is serviced only as a complete assembly using a new or factory rebuilt
compressor. Parts available for field service include the input shaft rotary oil seal and the seal retainer
gasket or o-ring seal.
The compressor input shaft rotary seal may be replaced as follows, Refer to Figure 21:
1. Make certain the unit cannot be started and system has all pressure removed.
2. Remove any coupling guards and/ or shields.
3. Clean the front of the compressor thoroughly to prevent dirt from entering the
compressor.
4. Disconnect the drive coupling.
12. Carefully reinstall the seal retainer, retainer capscrews and tighten all capscrews
securely.
13. Reinstall the compressor input shaft drive hub. Reconnect the drive coupling and
align, if necessary, following the coupling manufacturer’s instructions
14. Reinstall all coupling guards and/ or shields.
36
Service Procedure Components
Figure 21-Compressor Input Shaft Seal Figure 22- Minimum Pressure Check Valve (Small)
The minimum pressure valve may be purchased as an assembly if required. Service parts are available,
however, to repair/overhaul this valve. This valve may be serviced as follows:
1. Make certain the unit cannot be started and that all the pressure has been removed from the
system.
2. Remove the service piping from the minimum pressure valve.
3. Remove the valve from the receiver-oil reservoir cap.
4. Securely clamp the valve in a vertical position (cap end up) in a suitable fixture (bench vise).
5. With a suitable wrench remove the valve cap from the valve body.
37
Service Diagnosis
Low Inlet Pressure 1. Improperly set inlet valve or other 1. Set or adjust control correctly.
control.
2. Restricted inlet (dirty or clogged filters, 2. Service inlet filters or screens.
screens, etc).
3. Damaged or faulty inlet pressure 3. Service inlet pressure regulator.
regulator.
High Inlet Pressure 1. Improperly set inlet valve or other 1. Set or adjust control correctly.
control.
High Discharge Pressure 1. Operating at higher than rated 1. Adjust to operate at rated pressure.
pressure. 2. Service discharge check valve.
2. Damaged or worn discharge check
valve. 3. Install correct minimum pressure valve.
3. Incorrect minimum pressure valve 4. Service minimum pressure valve.
installed.
4. Damaged or worn minimum pressure 5. Correct cause of excessive restriction.
valve.
5. Excessive restriction in separator or
outlet piping.
Excessive Oil Consumption 1. Incorrect oil installed in reservoir. 1. Drain unit and install correct oil.
2. Reservoir over-filled.
3. External oil leaks. 2. Drain to correct level.
4. Operating with discharge pressure too 3. Check for and correct all leaks.
low. 4. Operate at rated pressure.
5. Drain tube missing, broken or not
touching bottom of separator element. 5. Replace drain tube with correct length tube.
6. Worn, damaged, or restricted
separator element. 6. Service separator element.
7. Clogged or restricted separator drain
line drain tube or filter. 7. a. Service drain line filter.
b. Check condition and installation of drain
line check valve. Clean or install correctly.
Replace if worn. Service drain line as
required.
38
Fluid Compressor Partners, Limited
General Terms of Sale and Warranty Information
1. GENERAL This order together with any additional writings signed by Seller shall represent the final, complete and
exclusive statement of the Agreement between the parties and may not be modified, supplemented, explained or
waived by parol evidence, Buyer's purchase order, a course of dealing, Seller's performance of delivery, or in any
other way except in writing signed by an authorized employee of the Seller. These terms are intended to cover all
activity of Seller and Buyer hereunder, including sales and use of products, parts and work and all related matters
(references to products include parts and references to work include construction, installation, and start-up). Any
reference by Seller to Buyer's specification and similar requirements are only to describe the products and work
covered hereby, and no warranties or other terms therein shall have any force or effect. Catalogs, circulars and
similar pamphlets of the Seller are issued for general information purposes only and shall not be deemed to modify
the provisions hereof.
B. All claims whatsoever by Buyer, excepting only those provided for under the WARRANTY statement and
PATENTS Clause hereof, must be asserted in writing by Buyer within ten (10) days period or they are waived. If this
contract involves partial performance, all such claims must be asserted within said ten (10) day period for each partial
performance. There shall be no revocation of acceptance. Rejection may be only for defects substantially impairing
the value of products or work and Buyer's remedy for lesser defects shall be those provided for under the
WARRANTY statement.
C. Seller shall not be responsible for nonperformance or delays in performance occasioned by any causes beyond
Seller's reasonable control, including, but not limited to labor difficulties, delays of vendors or carriers, fires,
governmental actions and material shortages. Any so occasioned shall effect a corresponding extension of Seller's
performance dates, which are in any event, understood to be approximate. In no event shall Buyer be entitled to
incidental or consequential damages for late performance or failure to perform.
3. TITLE AND RISK OF LOSS Full risk of loss (including transportation delays and losses) shall pass to the Buyer
upon delivery of products to the Ex-works point or if Seller consents to a delay in shipment beyond the contract date
at the request of the Buyer upon notification by the Seller that the products are manufactured.
4. PATENTS Seller agrees to assume the defense of any suit for infringement of any United States patents brought
against Buyer to the extent such suit charged infringement of an apparatus or product claim by Seller's product in and
of itself, provided (i) said products is built entirely to Seller's design, (ii) Buyer notifies Seller in writing of the filing of
such suit within ten (10) working days after the service of the process thereof, and (iii) Seller's given complete control
to the defense of such suit, including the right to defend, settle and make changes in the product for the purpose of
avoiding infringement. Seller assumes no responsibility for charges of its infringement of any process or method
claims, unless infringement of such claims is the result of following specific instructions furnished by Seller.
5. TERMS OF PAYMENT
A. Unless other terms are specified, all payment shall be in US dollars and shall become due in 30 days after
shipment. All shipments, unless otherwise specified, shall be Ex-works manufacturer's plant. If delivery is delayed by
purchaser, date of readiness for delivery shall be billed separately for payment purposes. If manufacture is delayed
by purchaser, a payment shall be due based on purchase price and percentage of completion. Balance payable in
accordance with terms stated herein.
B. If Seller has not received full payment within thirty (30) days after such payment is due then Buyer's outstanding
balance will be subject to an interest charge equal to two (2) percentage points above prime rate.
6. TAXES Any sales, use or other similar type taxes imposed on this sale or on this transaction are not included in the
price. Such taxes shall be billed separately to the Buyer. Seller will accept a valid exemption certificate from the Buyer
42
is applicable, however, if an exemption certificate previously accepted is not recognized by the governmental taxing
authority involved and the Seller is required to pay the tax covered by such exemption certificate. Buyer agrees to
promptly reimburse Seller for taxes paid.
7. CANCELLATION Following approval by Seller, Buyer may not cancel except upon payment of fifty percent (50%)
to one hundred percent (100%) of the total price of the product and work depending on the status of completion, plus
Seller's non-recoverable costs (including incidental and consequential damages) attributed to this order.
8. SECURITY INTEREST Buyer represents that the product is to be used for business, and shall remain personality.
Buyer grants Seller a security interest in the product to secure the payment of the purchase price. Buyer will not
lease, transfer or encumber the product and will keep it free from any and all liens and security interest. Upon default,
Seller shall have all the remedies available to it under the Uniform Commercial Code and other applicable laws of the
state in which the product is located and shall be entitled to all legal costs, reasonable attorney's fees, and all other
reasonable expenses and costs permitted by law which are incurred by Seller in enforcing its remedies. The security
interest herein granted shall be in Buyer's interest in the product and shall be fully discharged upon receipt by Seller
of the unpaid balance of the purchase price. Buyer agrees (a) to sign all financing statements and other instruments
or documents that Seller may reasonably believe are necessary to protect this security interest (b) i movement of the
product to another location is allowed under any other documents relating to this proposal to give Seller at least thirty
(30) days advance written notice of any such change in location, (c) to inform Seller of any change in the law of
jurisdiction in which the product is located whether such change is statutory or otherwise, which change could affect
the continued status of the product as personality and (d) to procure and maintain insurance on the product for its full
purchase price, the policy to name the Seller as loss payee.
9. CONFIDENTIALITY Technical data and layouts supplied by Seller in connection herewith are confidential pending
Buyer's acceptance of this proposal.
10. OSHA LAWS Seller has taken the Occupational Safety and Health Act of 1970 (OSHA) and like state and local
laws into account in the design of its products with the objectives that when such equipment is placed in appropriate
environment it will enable the operator or user to comply with the applicable OSHA and similar requirements,
however, because compliance is significantly affected by many factors over which Seller has little control (such as
installation, plant layout, building acoustics, materials processed, processing procedures and supervision and training
of employees), Seller does not represent or warrant that equipment sold by it complies with OSHA or any like state or
local law or regulation and the cost for modifications and responsibility for compliance are the Buyer's responsibility.
PRODUCT WARRANTY
43
Subject to the terms and conditions hereinafter set forth and set forth in General Terms of Sale, FCP (the seller)
warrants products and parts of its manufacture, when shipped, and its work (including start-up) when performed, will
be of good quality and will be free from defects in material and workmanship. This warranty applies only to Seller's
equipment, under use and service in accordance with seller's written instructions, recommendations and ratings for
installation, operating, maintenance and service of products, for a period as stated in the table below.
Equipment in question must be returned to FCP, via prepaid freight, at which time either FCP or original equipment
manufacturer will determine reason for failure due to abuse, neglect or workmanship. No warranty assessment will
be made without the product being examined at an FCP facility or at original manufacturer’s facility, either of which
must be authorized by FCP.
All replacement products not purchased from FCP will void warranty and the performance, maintainability or longevity
of the system will not be guaranteed.
THIS WARRANTY EXTENDS ONLY TO BUYER AND/OR ORIGINAL END USER, AND IN NO EVENT SHALL THE
SELLER BE LIABLE FOR PROPERTY DAMAGE SUSTAINED BY A PERSON DESIGNATED BY THE LAW OF
ANY JURISDICTION AS A THIRD PARTY BENEFICIARY OF THIS WARRANTY OR ANY OTHER WARRANTY
HELD TO SURVIVE SELLER'S DISCLAIMER.
All accessories furnished by Seller but manufactured by others bear only a 90 day, or 2500 hour, warranty.
All claims for defective products, parts, or work under this warranty must be made in writing immediately upon
discovery and, in any event within 5 days from date of shipment of the applicable item and all claims for defective
work must be made in writing immediately upon discovery and in any event within 10 days from date of delivery
thereof by Seller. Unless done with prior written consent of Seller, any repairs, alterations or disassembly of Seller's
equipment shall void warranty. Installation and transportation costs are not included and defective items must be held
for Seller's inspection and returned to Seller upon request.
THERE ARE NO WARRANTIES, EXPRESSED, IMPLIED OR STATUTORY WHICH EXTEND BEYOND THE
DESCRIPTION ON THE FACE HEREOF, INCLUDING WITHOUT LIMITATION, THE IMPLIED WARRANTIES OF
MERCHANTABILITY AND FITNESS OF PURPOSE.
After Buyer's submission of a claim as provided above and its approval, Seller shall at its option either repair or
replace its product, part, or work at the original point of shipment, or refund an equitable portion of the purchase price.
The products and parts sold hereunder are warranted only for specific conditions in which the compression system
was quoted, excluding quality of natural gas. The system is not intended for operation with erosive or corrosive
material or those which may lead to build up of material within the product supplied, nor those which are incompatible
with the materials of construction. The Buyer shall have no claim whatsoever and no product or part shall be deemed
to be defective by reason of failure to resist erosive or corrosive action nor for problems resulting from build-up of
material within the unit nor for problems due to incompatibility with the materials of construction.
Any improper use, operation beyond capacity, substitution of parts not approved by Seller, or any alteration or repair
by others in such manner as in Seller's judgment affects the product materially and adversely shall void this warranty.
No employee or representative of Seller other than a Partner of the Company is authorized to change this warranty in
any way or grant any other warranty. Any such change by an Officer of the Company must be in writing.
44
The foregoing is Seller's only obligation and Buyer's only remedy for breach of warranty, and except for gross
negligence, willful misconduct and remedies permitted under the General Terms of Sale in the sections on
CONTRACT PERFORMANCE, INSPECTION AND ACCEPTANCE and the PATENTS Clause hereof, the foregoing
is BUYER'S ONLY REMEDY HEREUNDER BY WAY OF BREACH OF CONTRACT, TORT OR OTHERWISE,
WITHOUT REGARD TO WHETHER ANY DEFECT WAS DISCOVERED OR LATENT AT THE TIME OF DELIVERY
OF THE PRODUCT OR WORK. In no event shall Buyer be entitled to incidental or consequential damages. Any
action for breach of this agreement must commence within one 90 days after the cause of action has occurred.
45
PROOF OF WORKABILITY SHEET
(START-UP AND COMMISIONING RECORD REQUIRED FOR WARRANTY)
START
SKID NUMBER: MODEL:
DATE:
ADDRESS: STATE:
CITY: COUNTY:
STATE: ZIP CODE: NOTES:
OPERATING CONDITIONS: MACHINE SPECIFICS:
ELEVATION: ENGINE MODEL:
AMBIENT TEMP: ENGINE SERIAL NUMBER:
FUEL GAS TYPE: COMPRESSOR MODEL:
SUCTION PRESSURE: COMPRESSOR GEAR RATIO:
DISCHARGE PRESSURE: COMPRESSOR SERIAL NO:
SALES VOLUME: CONTROL PANEL MODEL:
ENGINE SPEED: CONTROL PANEL SERIAL NO:
ENGINE MANIFOLD VACUUM: COOLING PACKAGE MODEL:
ENGINE OIL PRESSURE: COOLING PACKAGE SERIAL NO:
COMPRESSOR OIL INJECTION PRESS: HOUR METER AT START-UP:
DISCHARGE TEMPERATURE: SAFETY SHUT-DOWN SETPOINTS:
ENGINE TEMPERATURE: HI DISCHARGE PRESS:
EXHAUST
TEMPERATURE: LO DISCHARGE PRESS:
IGNITION TIMING: HI SUCTION PRESS:
EXHAUST GAS OXYGEN CONTENT: LO SUCTION PRESS:
FUEL GAS SCRUBBER PRESSURE: LO ENGINE OIL PRESS:
FIRST CUT FUEL PRESSURE: ENGINE OVERSPEED:
FUEL PRESSURE AT CARBURETOR: ENGINE UNDERSPEED:
START-UP AND INSPECTION BY: HI DISCHARGE TEMP:
NAME: LO DISCHARGE TEMP:
TITLE: HI ENGINE TEMP:
COMPANY: HI EXHAUST GAS TEMP:
SIGNATURE: HI ENGINE MANIFOLD PRESS: