(1) A manufacturer produced two products, klunk and klick, klunk has a contribution of N3

per unit and klicks N4 per unit. The manufacturer wishes to establish the weekly
production plan which maximizes contribution.
Production data are as follows:

Per unit
Machining (Hour) Labour (Hour) Material (kg)
Klunk 4 4 1
Klick 2 6 1
Total available per 100 180 40
week

Because of the trade agreement sale of klunk are limited to a weekly maximum of 30 units
and to honour an agreement with an old establishment customer at least 10 units of klick
must be sold per week.
Solve the above using graphical method in linear programming and determine the feasible
region.
(2) Write short notes on the following:
(i) Work measurement
(ii) Time study
(iii) Resource allocation
(iv) Work study
(3) Write short notes on the following terms.
(i) Standard time
(ii) Productivity
(iii) Method study
(iv) Work flow
(4) Explain the following terms.
(i) Quantity control technique
(ii) Timing and rating
(iii) Motivation
(iv) Financial
(v) Non – financial

(5). Explain the following factors that influence productivity of construction workers.

(i) Product Factor

(ii) Plant and equipment


(iii) Technology

(v) Material and Energy

(vi) Human factors