July 2018
Prepared by the Viet Nam Expressway Corporation for the Asian Development Bank.
NOTE
This social monitoring report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any designation of
or reference to a particular territory or geographic area in this document, the Asian Development
Bank does not intend to make any judgments as to the legal or other status of any territory or area.
SOCIALIST REPUBLIC OF VIETNAM
MINISTRY OF TRANSPORT
Vietnam Expressway Corporation (VEC)
Final
July 2018
--------------------------------------------------------------------------------------------------------------------------------------
---
I. INTRODUCTION ......................................................................................................... 1
II. PROJECT DESCRIPTION WITH CONSTRUCTION PACKAGES .......................................... 1
III. QUARTER REPORT OF MONITORING ON RP IMPLEMENTATION .................................. 3
IV. OBJECTIVES OF INTERNAL MONITORING REPORT (IMR) ............................................. 4
V. LAND ACQUISITION AND RESETTLEMENT IMPACTS .................................................... 5
5.1. NUMBER OF HOUSEHOLD AFFECTED BY LAND ACQUISITION ........................................................................... 5
5.2. AREA OF IMPACTED LAND AS PER UPDATED DECISION ................................................................................. 7
5.3. BUDGETED AMOUNT FOR RP IMPLEMENTATION ........................................................................................ 8
VII. GENERAL PROGRESS ON GROUND CLEARANCE AND HANDING OVER LAND .............. 13
7.1. STATUS FOR LAND CLEARANCE AND HANDING OVER OF ACQUIRED LAND........................................................ 13
7.2. STATUS ON GROUND CLEARANCE AND HANDING OVER OF LAND BY AFFECTED HOUSEHOLDS ............................ 14
LIST OF TABLES
Table 1. Construction Packages detail and Length and Location of the BLLT Expressway project .... 2
Table 2. The project profile and contractors and time of construction ............................................. 2
Table 3. Updated number of Affected Households in comparison to RP .......................................... 6
Table 4. Updated Area of Affected Land ............................................................................................ 7
Table 5. Resettlement Budget as per URP and Updated Decision ..................................................... 8
Table 6. Number of Fully Paid Affected Households (HHs) ................................................................ 9
Table 7. Total Land area paid........................................................................................................... 10
Table 8. Disbursement of Compensation to Affected Households ................................................... 11
Table 9. General Progress in Land Clearance and Handing over of Land ........................................ 13
Table 10. General Progress in Land Clearance and Handing over Land........................................... 14
Table 11. Main Issues on delay of Handing over of land up till 18 January 2018 ............................ 16
Table 12. No. of Grievances Received and Resolved ........................................................................ 23
Table 13. Resettlement Preferences of Fully Affected Households. ................................................. 25
Table 14. Status of Resettlement Site Development up till June 2017 ............................................. 26
Table 15. Obstruction in Relocation ................................................................................................. 28
Table 16. Final Households list to Participate in IRP (Tranche-1+2 and JICA section II)................... 37
Table 17. Vulnerable Group Participation in IRP .............................................................................. 38
Table 18. Vulnerable Group Participation in IRP with their selected income activity ...................... 39
Table 19. Status on IRP implementation .......................................................................................... 41
Table 20. Provision of Training to IRP Participating Households ..................................................... 45
LIST OF FIGURES
--------------------------------------------------------------------------------------------------------------------------------------
---
Figure 3. General Location of Project in transport system of Ho Chi Minh City and Surrounding .......... 28
Figure 4. Package A1: Status of Project Location updated to February, 2018 on Aerial Photograph ..... 29
Figure 6. Package A2-2: Status of Project Location updated to January 23, 2018 on Aerial Photograph 30
Figure 7. Package A3: Status of Project Location updated to February, 2018 on Aerial Photograph ..... 31
Figure 8. Package A4: Status of Project Location updated to January 23, 2018 on Aerial Photograph .. 32
Figure 9. Package J1, J2, J3: Status on Location updated January 23, 2018 on Aerial Photograph ......... 34
Figure 10. Package A5, A6, A7-ADB Section III- Status of Project Location ............................................. 34
LIST OF ANNEXURES
Annex 1: Status on Handing over of land and Ground Clearance (ADB Section) updated December 2017 ............. 52
Annex 2: Critical Locations need urgent Ground Clearance and Handing Over, December 2017............................. 55
Annex 7. Decision of re-establishment of management committee to carry out IRP Can Giuoc District ................. 72
--------------------------------------------------------------------------------------------------------------------------------------
---
2. The Ben Luc - Long Thanh Expressway Project has an overall length of 57.7km. It
traverses through 16 Communes in 7 Districts of 3 Provinces. This expressway starts from My
Yen Commune and part of an access-road in Tan Buu Commune in Ben Luc District, Phuoc Ly
commune and Long Thuong commune in Can Giuoc District of Long An Province; and traverses
through Binh Chanh Commune, Tan Quy Tay Commune, Hung Long Commune, Da Phuoc
Commune in Binh Chanh District; Nhon Duc Commune, Long Thoi Commune in Nha Be District,
and Binh Khanh Commune in Can Gio District of Ho Chi Minh City; then goes through Phuoc
Khanh commune, Vinh Thanh Commune, Phuoc An Commune in Nhon Trach District, Long
Phuoc Commune, and ends at Phuoc Thai Commune in Long Thanh District of Dong Nai
Province. The right of way (PROW) and land acquisition area along the route varies from 56m -
73m wide.
Length
District
Sl. No. Pkg. No. From Km to Km Province Commune Remark
(in Km.) Covered
My Yen/
Ben Luc
Long An Tan Buu
1 Package A-1 Km0+600 Km7+900 7.300 Km Can Giuoc Phuoc Ly
Binh Chanh
Ho Chi Minh City Binh Chanh
Tan Quy Tay
ADB section I
Ho Chi Minh City Binh Chanh Tan Quy Tay
2 Package A 2-1 Km7+900 Km11+200 3.300 Km Long An Can Giuoc Long Thuong
Ho Chi Minh city Binh Chanh Hung Long
Hung Long
3 Package A 2-2 Km11+200 Km16+600 5.400 Km Ho Chi Minh city Binh Chanh
Da Phuoc
Binh Chanh Da Phuoc
4 Package A-3 Km16+600 Km20+169 2.114 Km Ho Chi Minh city
Nha Be Nhon Duc
Nhon Duc/
5 Package A- 4 Km20+169 Km21+744 3.026 km Ho Chi Minh city Nha Be
Long Thoi
Nha Be Long Thoi
JICA section II
6 Package J- 1 Km21+744 Km23+769.0 2.025 km Ho Chi Minh city
Can Gio Binh Khanh
7 Package J -2 Km23+769.0 Km29+531.5 5.762 km Ho Chi Minh city Can Gio Binh Khanh
Ho Chi Minh city Can Gio Binh Khanh
8 Km29+531.5 Km32+450 2.92 km
Package J- 3 Dong Nai Nhon Trach Phuoc Khanh
Phuoc Khanh
9 Km32+450 Km35+900 3.45 km Dong Nai Nhon Trach
Package A -5 Vinh Thanh
Source of Fund ADB Loan ADB Loan No.: ADB Loan No.: ADB Loan No.: ADB Loan No
No.2730-VIE 2730-VIE 2730-VIE 2730-VIE 2730-VIE
Contractor JV Halla Corp– JV Kukdong Joint Venture JV Halla Corp– JV of Kukdong
Vinaconex Eng.Consut. of Samwhan Vinaconex Eng. &
Eng.Cons. & Co.-Trung Corporation - Eng.Cons& Construction Co.,
Invest.JSC. Chinh T.C. Vạn Cuong Invest.JSC. Ltd., Dong Me
Kong
Description ADB section I ( Tranche 1)- Packages*
Project Name Package A1 Package A2.1 PackageA2.2 PackageA3 PackageA4
Construction and
Trading Service
Co. Ltd.
NTP May 26th, 2015 May 19th, 2015 Aug. 15th May 19th, 2015 February 17th,
2015 2016
Contract Period 1080 days 1,076 days 1050 days 1,095 days 900 days
*
Description JICA section I - Packages
Project Name Package J1 Package J2 Package J3
Project Location Km. 21+744 – 23+769 Km.: 23+769 – 29+531.5 Km29+531.5- 32+450
Contract Number
Executing Agency Vietnam Expressway Corp. Vietnam Expressway Corp. Vietnam Expressway Corp.
Contract Period 47 months ( 1410 days) 32 months ( 960 days) 42 months ( 1260 days)
Description ADB section III ( Tranche 2) - Packages*
Project Name Package A 5. Package A6 Package A7
Project Location Km. 32 +450– 35+900 Km.: 35+900 – 52+400 Km52+400.0-57+700.0
Contract Number
Executing Agency Vietnam Expressway Corp. Vietnam Expressway Corp. Vietnam Expressway Corp.
Source of Fund ADB Loan No.3391-VIE ADB Loan No.3391-VIE ADB Loan No. 3391-VIE
8. South Expressway Project Management Unit (SEPMU) of Ben Luc - Long Thanh (BLLT)
Expressway Project is the representative of the executing agency for VEC and is responsible for
internal monitoring.
9. As per agreed updated RPs, the SEPMU has to submit quarterly monitoring report to
ADB and VEC. This quarterly monitoring report No.4 (QRNo-4) of 2017 presents the status of
land acquisition and handing over of land for the project & income restoration program (IRP)
implementation up from October of 2017 to December 2017.
11. The range of activities and issues that need to be recorded and verified, include:
15. Besides, Resettlement Plan (RP) addendum for electricity Pole removal and T14 internal
road will also be prepared for Ben Luc and Can Giuoc districts respectively.
16. However, up till December 2017 only Resettlement Plan (RP) addendum for electricity
Pole removal of Ben Luc district has been prepared and submitted to EPMU for its final
submission to ADB as Ben Luc District is the only district that has approved plan of
compensation and completed land acquisition. Remaining RP addendums of other districts are
pending due to lack of approval of compensation plan and incomplete land acquisition
process.
17. The area of recovered land, reflected in the DMS (Detailed Measurement Survey) at
design stage was a generic assessment; however, actual recovered land area at the time of
implementation is different due to construction demand or any other reasons. Therefore, in
this report the assessment on status of land acquisition for each construction package is
updated at micro level of each household. These information and data is verified and supplied
by cadres of EPMU, Contractors and Local Authority of each District and Commune from the
actual recovered land area, which is specifically summarized in end of the month and every
quarter in a year at each construction site in the commune and at every construction packages
5.1. Number of Household affected by land acquisition
18. There is no change in the final list of affected households from March 2017 up till
December 2017, the reporting period. This list is updated and verified every quarter by Center
of Land Fund Department (CoLFD) of the Project districts on the basis of decisions of land
acquisition and compensation plan, and finally approved by Chairman, Peoples Committee of
the Province and District. Given that there is a change in the number of AHs relative to the
uRPs, RP addendum will be prepared for each district with an accounting of the additional AHs
including mitigation measures corresponding to the impacts. The details are presented in
Table-3 below:
-----------------------------------------------------------------------------------------------------------------------------------------
Affecte
Sl. District / up till Sep 2017 Up till December 2017 %
Package d HH
No. Commune Govt. Private Total Govt. Private Total Change
number
Land Land Land Land Land Land
1 Ben Luc A1 319 5.04 34.7 39.7 5.04 34.7 39.7 0.0
A1, A2-1,
2 Binh Chanh A2-2 and 1161 12.5 105.3 117.77 12.5 105.3 117.77 0.0
A3
3 Can Giuoc A1, A2-1 240 0 19.0 19.0 0 19.0 19.0 0.0
4 Nha Be A3, A4, J1 417 2.72 43.5 46.2 2.72 43.5 46.2 0.0
5 Can Gio J1+J2 +J3 204 12.57 18.1 30.7 12.57 18.1 30.7 0.0
Nhon J3,A 5, A
6 942 10.26 137.5 147.8 10.26 137.5 147.8 0.0
Trach 6, A-7
Long
7 A7 275 16 11.8 27.8 16 11.8 27.8 0.0
Thanh
Total 3558 59.09 369.9 429.0 59.09 369.9 429.0 0.0
-----------------------------------------------------------------------------------------------------------------------------------------
20. The above table shows that there is not a change in recovered land area from previous
reporting period.
21. To date, the process for land acquisition for Tranche 1 is nearly completed, while in
JICA section it is already completed. On the other hand, the process of land acquisition in
Tranche 2 is under progress.
5.3. Budgeted amount for RP implementation
22. The table below shows the resettlement budget as per updated decision up till 18
February 2018 and its comparison with the URP and the previous quarter (please see remarks
column in the table):
Table 5. Resettlement Budget as per URP and Updated Decision
Unit: (VND billion)
LAR Budget Requirement (in Billion VND)
Sl.
District Remarks
No. Updated as Up till
As per
on June Sep-17 December
URP
2017 2017
1 Ben Luc 247 255.043 255.043 255.043 The updated information on
final resettlement budget in
2 Can Giuoc 188.51 255.668 255.668 255.686 this report is based on
3 Binh Chanh 1,873.37 1,658.37 1,658.37 1658.37 Master list and various
4 Nha- Be 631.17 680.092 680.092 680.092 updated Decision of each
District compensation
5 Can Gio 139 124.781 124.781 124.781 Committee of land
6 Nhon Trach 377.058 399.376 399.376 399.376 acquisition area and
7 Long Thanh 157.497 179.429 179.429 179.429 payment of compensation,
support and resettlement to
Total 3,613.61 3552.76 3552.78 3552.78 each affected household
updated to December 2017.
Source: VEC’s documents and DCCs of each project District
23. The above table elaborates that there is no change in the total budget for land
acquisition in comparison to previous reporting period. This Land acquisition cost has been
updated at micro level at the time of actual payment of compensation and support to each
household (updated to December 2017)
26. 100% compensation has been made to JICA section, while it is 97.81 % in Section-1
(Western section- A1, A2-1, A2-2, A3 & A4), almost 1.31 % more from last reporting period.
27. A significant improvement has been witnessed in compensation payment for section-III
(Eastern Section- A5, A6 & A7), where an average to 72.33% HHs have been paid up till this
reporting period, a significant rise of 3.78 % from last reporting period.
28. 95.24% Households and 88.62 % Households have been paid in package A5 and A6
separately; a huge advancement from previous reporting period, while in last reporting period
the payment was only 91.43 % and 86.11 % in reporting in September of 2017 of A5 and A6
separately.
29. Remaining HHs, who are unpaid, are being paid as per priority, or put in District
treasury with other reasons.
Table 6. Number of Fully Paid Affected Households (HHs)
-----------------------------------------------------------------------------------------------------------------------------------------
7.1. Status for land clearance and handing over of Acquired land
40. To up 18 January 2018. Land Acquisition and Ground Clearance are nearly on
completion in all districts of the project, in Long An province and Ho Chi Minh City (Tranche 1
reached up 98 % for all construction packages). Handing over of land area to Project in
Packages A1, A2-1 are being reached near to 99%, Separately, A3 & A4 have completed 100
%, howevr, in package A2-2, Land Acquisition and Ground Clearance has reached 95 %.
41. The disbursement in two Districts; Nhon Trach and Long Thanh are being carried out as
per priority, linked to construction activity. However, during this reporting period, there was a
good progress in compensation payment as well as handing over of land, where averages 83 %
of the affected Households have handed over the land ( A5 is 98%; A6 is 83% and A7 is 75%)
42. The details of progress in land clearance and status of handing over of land to Civil
works up to December 2017 has been weighed up in Table No 9: (See more detail in Annex 1)
Table 9. General Progress in Land Clearance and Handing over of Land
Recover up to December
Up till June 2017 Up to 14 Sep 2017
ed land 2017
Remaining
area
Package Land land land up till Dec,
(ha) / % Handed % hand % hand
Handed handed handed 2017 (%)
AHHs over (ha)
Over
over ( ha)
over
over ( ha)
over
No.
Package A1 89.83 87.63 98% 87.65 98% 89.00 99% 0.9%
Package A2-1 22.34 22.15 99% 22.15 99% 22.15 99% 0.9%
Package A2-2 61.53 57.79 94% 57.88 94% 58.70 95% 4.6%
Package A3 9.68 9.68 100% 9.68 100% 9.68 100% 0.0%
Package A4 31.24 31.21 100% 31.21 100% 31.21 100% 0.1%
Total (A) 214.62 208.46 97% 208.57 97% 210.74 98% 1.8%
Package J1 11.46 11.46 100% 11.46 100% 11.46 100% 0.0%
Package J2 22.12 22.12 100% 22.12 100% 22.12 100% 0.0%
Package J3 13.24 13.24 100% 13.24 100% 13.24 100% 0.0%
Total (B) 46.82 46.82 100% 46.82 100% 46.82 100% 0.0%
Package A5 21.1 19.23 91% 19.23 91% 20.60 98% 2.4%
-----------------------------------------------------------------------------------------------------------------------------------------
7.2. Status on Ground Clearance and Handing over of land by Affected Households
43. The assessment of handing over land by affected households (AHHs) has also been
done. The finding reveals 89.8 % HHs have handed over the land for construction up till 18
January 2018, which is about 1.6 % more than last reporting period. Paying attention, in March
2017 was only 64.96 % of the AHHs. The percentage of affected households, who handed over
land in Binh Chanh District, is now 96.2% (Previous reporting period of 93.63%), while
remaining districts in western section have achieved the target of either 100.% or over 99.69 %
(Ben Luc District is 99.7 %; Can Giuoc is 100 %, Nha Be is 100 % and Can Gio is 100 %
respectively).
44. Up to December 2017. In Binh Chanh District, remaining 44 households are still
pending handing over land and ground clearance to project;
45. In 2 Districts of eastern section; Nhon Trach and Long Thanh Districts have also
achieved good progress of 90.2 % & 17.9 % respectively in handing over land. Entire average
for Dong Nai Province has reached 74.0% AHHs, who already handed over land to Project. See
Table 10
Table 10. General Progress in Land Clearance and Handing over Land
up to September 2017 up to Decmber 2017
% rate
of
not Already handed over not yet hand over
Total Already % rate hand
District yet
HHs handed of hand over
hand
over over
over
Male Female Total Male Female Total
-----------------------------------------------------------------------------------------------------------------------------------------
48. The information on critical locations and other details of obstruction, which need
urgent action on Ground Clearance in Binh Chanh District, is highlighted in Annex. -2.
8.2. Initiative to resolve the Issues, affecting Timely Land Handover:
49. As described in the last reporting period that People’s committee (PC), Ben Luc District
and Binh Chanh District and CoLFD and Committee of Compensation of District have organized
more discussion to directly talk with HH to resolve the pending issues of handing over land for
the Project. The Positive outcome of this discussion is visible on ground, when the HHs has
started handing over the land for civil construction.
50. About 9 HHs in Binh Chanh District, who are not handing over the land due to
complaining low of compensation rate.the authority, may issue an enforcement decision. . It is
pertinent to mention here that In Binh Chanh District, the compensation plan is based on the
compensation policy of HCMC province. The compensation plan is based on replacement cost and is
well explained in the compensation policy, i.e., Document No 7250/UBND-ĐT, dated 23 November
2017 of Ho Chi Minh City PC. This replacement cost is especially designed for BLLT project in
compliance with safeguards policy of ADB
51. However, current, local authority levels still try to mobilize and lobby to these HHs to
hand over land to project. In Parallel this activity, the local authority also prepares steps to
enforce handing over land according to regulations of land law, policy of the local authority is
minimized or avoid land acquisition by coercion
52. It is pertinent to mention here that Article 39 of Law of Land on ‘Land recovery for
use for objectives of national defense and security, national interest or public interest’ says
that ‘after a decision on land recovery and a plan for compensation, site clearance and
resettlement have been approved by the competent State body, publicly announced and
become effective, the person, having land to be recovered, must comply with the decision on
land recovery. Where a person, having land to be recovered, fails to comply with the decision
on land recovery, the people's committee at district level, which is authorized to make the
decision on land recovery, shall have the right to issue an enforcement decision.’
53. Land recovery, compensation and ground clearance procedures were first touched
upon in Decree No. 197 and then detailed in Decree No. 84 with 12 steps. However, some of
these procedures proved impractical and their implementation time limits were not clearly set,
causing rampant project construction delay and affecting investor interests. In face of such
situation, Decree No. 69 was issued, re-arranging the land recovery, compensation and ground
clearance procedures defined in Decree No. 84 in only four steps, which is well illustrated in
the following Table:
Land recovery, compensation and ground clearance procedures
54. The decision on Coercive land recovery by local authority can be imposed in following
cases:
- If, the land recovery has been strictly carried out according to the above-mentioned
three steps; or,
- Past 30 days after the deadline for land handover, the land users concerned fail to hand
over to-be-recovered land; or,
- The land users decline to hand over to-be-recovered land though they have been
persuaded by local administrations and compensation bodies; or,
- A coercion decision has been issued according to law by a competent state body; or,
- The coercion decision has been received by the land users concerned or publicly
displayed at the office of the commune- level People’s Committee of the place with the
land to be recovered.
55. Coercion decisions will be enforced by coercion forces under the direction of district-
level People’s Committees 15 days after the decisions are received by the land users
concerned or publicly displayed at the offices of the commune-level People’s Committees and
the land areas are not handed over. Any person, subject to a land recovery enforcement
decision, must comply with it, however; he has the right to make a complaint.
56. The District People's Committee has directed the Compensation Clearance Board of
Binh Chanh District to speed up the completion of the legal documents so that the site
clearance can be completed.
57. The obstruction caused by TL Shoe Company, a major obstruction for A2-1 package in
Tan Buu Commune, has been resolved by the Can Giuoc District and construction work is going
on this location, See status of construction on above said land in Fig.-1 below:
58. Can Gio District have completed handing over of land to Project of 100%
59. The resolved cases of handing over and present obstruction, updated up till December,
2017, is shown in the figures below (Fig.-1)
Figure 1. Pictures of status of Handing over land to Project updated as on December, 2017
Fig.-1: A pilot study of road at Km 7+00 of package Fig.-2: HH: [This information has been removed as it falls
A1- Tan Quy Tay commune- Binh Chanh District, Ho within exceptions to disclosure specified in paragraph 97,
Chi Minh city- in December 2017 (exception (x) Information that, if disclosed, would or
would be likely to endanger the life, health, safety, or
security of any individual, or safety or security of ADB
assets, or to prejudice the defense or national security of a
member) of ADB’s Public Communications Policy (2011).]
have temporary agreed for drilling foundation of EP 2 and
EP 3 but not yet hand over land in August-September 2017
Fig.-3: 1 HH ( name: [This information has been Fig.-4: Confirmation page of Service Organization is
removed as it falls within exceptions to disclosure carrying out procedure to have Permit of new house
specified in paragraph 97, (exception (x) Information construction for family – May, 2017 of HH: [This
that, if disclosed, would or would be likely to information has been removed as it falls within exceptions
endanger the life, health, safety, or security of any to disclosure specified in paragraph 97, (exception (x)
individual, or safety or security of ADB assets, or to Information that, if disclosed, would or would be likely to
prejudice the defense or national security of a endanger the life, health, safety, or security of any
member) of ADB’s Public Communications Policy individual, or safety or security of ADB assets, or to
(2011).]) is obstructing handover land by waiting for prejudice the defense or national security of a member) of
Permit of house construction- A1 – Binh Chanh ADB’s Public Communications Policy (2011).]
Commune- Nov.2017
-----------------------------------------------------------------------------------------------------------------------------------------
Fig.-7: Location of 1 Household is obstructing in right Fig.-8: Resettlement Specialist and related parts were
side of HW 1A in Package A1 ( complaint of low working with Contractor of A2-2 of cases of obstructions
compensation price- HH already relocated but not for handing over land to project and discuss how to resolve
yet hand over land. December 2017 obstructions at Contractor’s office. October 2017
Fig.-9: an section is handed over land and Fig.-10: actual at construction site to discuss on every case
constructing in Da Phuoc Commune A2-2 in October is obstructing with contractor of A2-2 in October 2017
2017
Fig.-11: One house in A2-2 is obstructing construction Fig.-12: 1 HH in Branch A-A4- June 2017 already handed
in Da Phuoc Commune, October 2017 ( HH; Doan Thi over land to project (October 2017).
Ut in Da phuoc Commune)
-----------------------------------------------------------------------------------------------------------------------------------------
• One HH in Nha Be District: HH: Doan Xanh, opted relocation into Resettlement site,
already received land plot in Resettlement site from 2015.
• Another 1 household of Vulnerable group in Can Giuoc District has petitioned to be
received a plot in Hai Son resettlement site , to replace self-relocation before and
subsequently, she already received plot in Hai Son SR from May of 2016
• In other two districts of Tranche-2; i.e., Nhan Trach District and Long Thanh District (in
ADB section III), 273 HHs have opted relocation into resettlement sites, and however,
relocation of these households have not been initiated up till date. Nhon Trach have
arranged 2 Resettlement Sites ( Long Tho Resettlement Site and HUB Resettlement
Site) for the AHHs, These 2 RSs have completed construction, the Long Thanh District,
Tan Hiep Commune Resettlement Site is being constructed and plan will be completed
and handed over plot in March – July 2018. See detail Table 14)
X. GRIEVANCES AND REDRESSAL
67. The nature of grievances and its redressed requirement are diverse, which need
corrective action at different levels and by different institutions. Most of the grievances,
specified below, are concerned with the claimed inadequacy of compensation and rate and
disputes among HHs. The nature of the grievances received and redressed up till December
2017 are summarized in the table-12.
68. In Tranche 1: Comparison with previous report, this QR No4 of 2017 reduced 30 cases,
only remaining is 45 HHs: (1 household: [This information has been removed as it falls within
exceptions to disclosure specified in paragraph 97, (exception (x) Information that, if disclosed,
would or would be likely to endanger the life, health, safety, or security of any individual, or
safety or security of ADB assets, or to prejudice the defense or national security of a member)
of ADB’s Public Communications Policy (2011).] of Ben Luc District and 44 households in Binh
Chanh district).
69. In Tranche 2: The 39 HHs in Nhon Trach district are complained compensation for
location of recovered land and is being resolved by local government.
70. Compensation of the 16 HHs/ 44 HHs in Binh Chanh District have temporary put in
district treasury to wait decision of resolving or completed legal documents to pay
compensation. See table 12
Table 12. No. of Grievances Received and Resolved
-----------------------------------------------------------------------------------------------------------------------------------------
Pending Court
Waiting for court
cases on 4 4
decision
compensation
the
Other reasons
compensation
46 16 (inheritance, Co
put in treasury
LUR...)…
of District
Total 68 38
Local authority is
Nhon complaint of
1 39 39 adjusting to
Trach land location
compensate addition
Total 39 39
Grand Total 107 77
*Resource: Report of CoLFD and DCC in each District to December, 2017
In this table is not included 7 HHs, who have committed handing over land after received plot in resettlement sites
73. On the other hand, in two districts; i.e., Nhan Trach and Long Thanh (mostly ADB
section III), 273 HHs have opted relocation into resettlement sites.
74. According to Report of CoLFD of Nhon Trach District in November of 2017:
Preparation for resettlement site have been selected for resettlement as after:
• Long Tho Resettlement Site and HUB resettlement site, Construction for these 2 RSs
completed;
• Currently. Local Authority have allocated plots in the 2 RSs to each households:
- Phuoc Khanh Commune have completed handing over plot in RS to 21 HHs/21 HHs,
resulted to November 2017
- Vinh Thanh commune have completed review on status of 20 AHHs of relocation.
According to Plan: the 20 HHs to be handed over plot in RS in next time ( January- July
2018)
- Phuoc An Commune has completed review on status of 70 AHHs/70HHs to be handed
over plot in Resettlement Site in next time. It is planned to handover plot to 65 HHs in
March – July, 2018
75. Long Thanh District, 162 AHHs will be resettled into Tan Hiep Resettlement site, this
Resettlement site is being constructed with total plots of 167 Plots ( the 162 AHHs arranged to
relocate the HHs into this RS, Local authority will organize lottery of plot to each HH and
afterward will hand over plot to each HH according to plan in February – July 2018,
76. 2 Households ([This information has been removed as it falls within exceptions to
disclosure specified in paragraph 97, (exception (x) Information that, if disclosed, would or
would be likely to endanger the life, health, safety, or security of any individual, or safety or
security of ADB assets, or to prejudice the defense or national security of a member) of ADB’s
Public Communications Policy (2011).] ), who have opted for Resettlement sites have already
received land plot in Resettlement site. Another 1 household, namely: [This information has
been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety,
or security of any individual, or safety or security of ADB assets, or to prejudice the defense or
national security of a member) of ADB’s Public Communications Policy (2011).] of Vulnerable
group (disabled), in Can Giuoc District have petitioned to be received a plot in Hai Son
resettlement site, which was latter approved by Can Giuoc District people’s committee and
CoLFD and he has already received the plot in Hai Son Resettlement site in December 2016.
The details are given in Table- 13.
Table 13. Resettlement Preferences of Fully Affected Households.
Opting to
Fully Required to Opting for Self
Sl. Resettlement Sites
Location Affected Relocate Relocation
No (RSs)
(HHs)
(HHs) (HHs) (HHs)
1 Ben Luc 35 35 0 35
2 Can Giuoc 131 131 1 130
3 Binh Chanh 265 265 45 220
4 Nha Be 56 56 1 55
5 Can Gio 15 15 0 15
6 Nhon Trach 21+20+70 111 111 0
7 Long Thanh 162 162 162 0
775 774 320 455
*Resource: Report of CoLFD and DCC in each District to December, 2017
-----------------------------------------------------------------------------------------------------------------------------------------
78. Ho Chi Minh City and Dong Nai Province are developing more new urban areas and
industrial zones and which may need more resettlement sites. To meet the challenges and
demand, the authority is setting up new resettlement sites for local people, workers and to
reduce the population density from its central area into suburban. In 2 suburb districts, Binh
Chanh and Nhà Be in Ho Chi Minh City and 2 Districts: Nhon Trach and Long Thanh of Dong Nai
province; more resettlement sites and new residential apartments are being developed to
meet the resettlement demands. The same resettlement sites will be available for the affected
persons of Ben Luc- Long Thanh expressway project.
79. The status of development of Resettlement Sites and relocation status of affected
households are described in the Table -14:
83. In Dong Nai Province. Total of 273 HHs of two Districts: Nhon Trach and Long Thanh of
Dong Nai Province will be relocated after land acquisition. The all 273 HHs have opted for
relocation on Resettlement sites, set up in the district
84. During monitoring of obstruction in relocation at construction sites by social Team at
the end of November 2017; it was witnessed that in package A1, 3 households, namely: [This
information has been removed as it falls within exceptions to disclosure specified in paragraph
97, (exception (x) Information that, if disclosed, would or would be likely to endanger the life,
health, safety, or security of any individual, or safety or security of ADB assets, or to prejudice
the defense or national security of a member) of ADB’s Public Communications Policy (2011).]
are creating hindrance in construction of main road as said in previous report ( QR No 3 of
2017), 2 HHs [This information has been removed as it falls within exceptions to disclosure
specified in paragraph 97, (exception (x) Information that, if disclosed, would or would be
likely to endanger the life, health, safety, or security of any individual, or safety or security of
ADB assets, or to prejudice the defense or national security of a member) of ADB’s Public
Communications Policy (2011).] agreed relocation and already handed over land to Project,
Separately HH: [This information has been removed as it falls within exceptions to disclosure
specified in paragraph 97, (exception (x) Information that, if disclosed, would or would be
likely to endanger the life, health, safety, or security of any individual, or safety or security of
ADB assets, or to prejudice the defense or national security of a member) of ADB’s Public
Communications Policy (2011).] is completing procedure to change remaining land from
agricultural land to residential land to relocation, plan will complete in February 2018
85. One HH in A2-2 in Da Phuoc Commune: namely: [This information has been removed as
it falls within exceptions to disclosure specified in paragraph 97, (exception (x) Information
that, if disclosed, would or would be likely to endanger the life, health, safety, or security of
any individual, or safety or security of ADB assets, or to prejudice the defense or national
security of a member) of ADB’s Public Communications Policy (2011).] approved that HH will
be resettled on remaining land part, but currently, this land part is not accessed into, Local
authority is proposing to EPMU to support access road with width of road is 2 m. This request
is being reviewed
-----------------------------------------------------------------------------------------------------------------------------------------
Figure 5. Package A2-1: Status of Project Location updated to February 2018 on Aerial Photograph
Figure 6. Package A2-2: Status of Project Location updated to January 23, 2018 on Aerial Photograph
Figure 7. Package A3: Status of Project Location updated to February, 2018 on Aerial Photograph
-----------------------------------------------------------------------------------------------------------------------------------------
Figure 10. Package A5, A6, A7-ADB Section III- Status of Project Location
(Being implemented Land Acquisition and Ground Clearance, updated February, 2018)
-----------------------------------------------------------------------------------------------------------------------------------------
1The number of vulnerable HHs is already included in the list, except for Nhan Trach District, as data on this is not yet
available
-----------------------------------------------------------------------------------------------------------------------------------------
95. During working with ADB mission last time (20-23 November 2017). Co LFD of Binh
Chanh District have supplied to SEPMU and ADB mission, consultant: an official eligible
households list in the District will be participated IRP and including Households are vulnerable
group in this District of 410 HHs
96. All of the 46 vulnerable households in IRP list will be invited to participate in IRP and
who selected income restoration activity for them. Small Business is main opted income
restoration activity for the vulnerable group (27 HHs); next income activity of livestock raising
and farming (12 HHs), Vocation training (4 HHs); cultivation (3 HHs).
97. Additionally, in two Districts; Long Thanh and Nhon Trach of Dong Nai Province, list of
vulnerable group only identified in Long Thanh District with 2 HHs ( [This information has
been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety,
or security of any individual, or safety or security of ADB assets, or to prejudice the defense or
national security of a member) of ADB’s Public Communications Policy (2011).] ) ; Nhon Trach
district are not completed vulnerable group at this time
98. The number of vulnerable households, with name and address in each district,
summarized in Table-17 and Table 18 and annexed as Annex.- 5 of this quarter No 4 report of
2017
Vulnerable Group
No Location Total
WHF Landless Poor Elderly Disable Policy
A Long An Province 15 6 5 1 0 1 2
1 Ben Luc District 6 5 1
My Yen commune 6 5 1
Tan Buu commune 0 No vulnerable Household
2 Can Giuoc district 9 6 1 2
Phuoc Ly Commune 7 6 1
Long Thuong
2 2
commune
B Ho Chi Minh City 29 8 13 6 0 1 1
1 Binh Chanh 10 4 1 5
Binh Chanh
2 1 1
commune
Tan Quy Tay
commune
Hung Long
commune
Da Phuoc commune 8 3 1 4
2 Nha Be District 15 1 12 1 0 0 1
Nhon Duc 13 1 12
Vulnerable Group
No Location Total
WHF Landless Poor Elderly Disable Policy
Commune
Long Thoi
2 1 1
commune
3 Can Gio District 4 3 1
BInh Khanh
4 3 1
Commune
C Dong Nai Province
1 Nhon Trach District NA NA NA NA NA NA NA
Phuoc Khanh
NA NA NA NA NA NA NA
commune
Vinh Thanh
NA NA NA NA NA NA NA
Commune
Phươc An commune NA NA NA NA NA NA NA
2 Long Thanh District 2 1 1
Phuoc Thai
2 1 1
Commune
Total 46 14 18 8 0 3 3
*Resource: Districts committee of IRP implementation –updated to December 2017
Table 18. Vulnerable Group Participation in IRP with their selected income activity
Income activity
Cultivatio Vocation Trade and
No Location Total Livestock Handicraf
n training and service
& farming t and Policy
Compone introduction promotion
component other
nt of job component
A Long An Province 15 1 7 0 0 7 0
1 Ben Luc District 6 0 2 4
My Yen commune 6 2 4
Tan Buu commune 0
2 Can Giuoc district 9 1 5 3
Phuoc Ly Commune 7 1 4 2
Long Thuong
2 1 1
commune
B Ho Chi Minh City 30 2 4 0 4 20
1 Binh Chanh 11 2 3 4 2
Binh Chanh
2 1 1
commune
Tan Quy Tay
commune
Hung Long
commune
Da Phuoc commune 8 2 3 3 1
2 Nha Be District 15 15
Nhon Duc
13 13
Commune
-----------------------------------------------------------------------------------------------------------------------------------------
101. Long An Province issued approval letter No: 4236/UBND – KT dated 20 September 2017
of additional approval of 43 households list to participate IRP at Can Giuoc District (Period
No2)
102. Separately. Can Giuoc District of Long An province. Some members of management
committee of IRP Implementation at the District, who have retired or removed to other unit,
this reason need re-organize according to request from EPMU and Consultant. Can Giuoc
District PC have issued Decision No 35/QĐ- UBND dated 8 February 2018 of: Re-establishment
of management committee of income restoration program (IRP) committee for Ben Luc- Long
Thanh Express way Project, section passes Can Giuoc District? See Annex -7
103. IRP implementation is being carried out in each district of Dong Nai Province, set up of
organization to implement IRP completed in each districts (Long Thanh District and Nhon Trach
District).
104. Implementation of IRP in Long Thanh district: eligible 128 HHs in Phuoc Thai
Commune of Long Thanh District is identified participating IRP, Long Phuoc Commune is only 2
AHHs, they are not eligible HHs to be participated IRP. In the 128 AHHs list of IRP in Long
Thanh District, who selected income restoration activity as after: (i) 26 HHs of vocation
training; (ii) 45 HHs in service and trade; (iii) 53 HHs in livestock and farming; (iv) 4 HHs of
cultivation.
105. The summary of status on handing over of IRP input is briefed here in Table 19:
-----------------------------------------------------------------------------------------------------------------------------------------
Ho Chi
B 425 214 639 55 37 370 187 12.83
Minh city
• Completion of official final
Binh household list, who will
2.1 Chanh 270 140 410 0 0 270 140 0 participate in IRP and Binh
district Chanh District people’s
committee approved
Status on IRP Implementation up to December, 2017
No Commune Received
Eligible HHs Not Received Progres
Input of IRP Remarks
s%
M F Total M F M F
• Will carry out process of
Binh chanh
2.1.1 67 33 100 0 0 67 33 0 disbursement for IRP
commune implementation
• According to plan, after quart
No 1 of 2018, IRP
implementation at Binh
Tan Quy Chanh District will begin after
2.1.2 Tan 36 8 44 0 0 36 4 0 obstruction of handing over
commune land to Project completed,
plan will be started
September 2018
• Currently, Binh Chanh do not
2.1.3 Hung Long 81 52 133 0 0 81 52 0 start IRP implementation
because they are
concentrating and acquisition
2.1.4 Da Phuoc 86 47 133 0 0 86 47 0 in the District
• A completion report of
2.3 Can Gio 55 37 92 55 37 0 0 100.00
implementation of the IRP in
-----------------------------------------------------------------------------------------------------------------------------------------
108. The working groups, involved in IRP Implementation activities, prepared a detailed plan
to organize training courses/ workshop for eligible HHs under IRP. They prepared a proper
plan, equipped with relevant materials and tools, for imparting the training to the participant
HHs including technical requirements, human resources and operating costs for each income
activity
109. The proposed IRP workshops or training program was organized at commune level and
was meant to help and advice to each participant to make their choices of income activity
based on their education and skills and how to carry out the specified income activity and
contact the relevant persons or institutions, in case they require any advice and technical
inputs to run their business. The training program were organized as per following program
(see table 20):
110. Separately in 2 Districts of Can Giuoc and Ben Luc in Long An Province. Organization to
train for income restoration activities component as agriculture, cultivation, small business…
are not trained separately. It is only general organized and quickly trained in each workshop of
IRP, Currently. The management committee of IRP implementation in each Districts and
DOLISA of Long An province are being requested to re-open of training courses separately to
households as regulation, a concreted plan of training courses will be prepared by the DOLISA
and management committee of IRP implementation in the 2 Districts of Long An Province and
will be sent to EMPU and Consultant in May 2018 for monitoring on implementation
111. In Long An province. Currently, Two Districts: Can Giuoc and Ben Luc are summarizing
result of evaluating and monitoring IRP implementation in all HHs, who received input of IRP in
2016-2017.
112. In Ho Chi Minh city: Binh Chanh District do not carry out IRP at this time; Nha Be
District is carrying out training as above written; Can Gio District completed IRP
implementation in 2017 and completion report of IRP implementation submitted.
113. In Dong Nai province (of tranche 2) in 2 Districts ; Long Thanh and Nhon Trach in Dong
Nai Province, they do not training at this time due to carrying out first step of IRP of
organization. Please as in the figures below (Fig.11).
Figure.11. Iimplementing IRP in Districts
Fig-1: Discussing with staffs of DoLISA of Long Anh Fig-2: Delegation go to Surveying and Interviewing
Province and Can Giuoc district and My yen Commune Household, the HH is raising cow ( 16 August 2017)
before conducting monitoring and evaluating IRP at the
commune- 16 August- Sep 2017
Fig-3: Local staff is interviewing household of proccesing Fig-4: Raising CUT Bird in an HH in Tan Buu
IRP implementation ( 16 August 2017) commune, Can Giuoc District, Long An province of
IRP
Fig-5: Local staff is interviewing a households of IRP after Fig-6: Duck is be raising by HH in IRP at My Yen
received cow at Tan Bưu commune, Can giuoc District, commune, Ben Luc District, Long An province- Sep
-----------------------------------------------------------------------------------------------------------------------------------------
Fig-7: Meeting to deploy IRP implementation at Long Fig-8: other Meeting to carry out IRP at Long Thanh
Thanh District, Dong nai Province dated 1 Sep 2017 District, Dong nai Province dated 1 Sep 2017 ( for
workshop at Phuoc Thai Commune
Fig 9: Workshop organized meeting hall of Phuoc Thai Fig 10: Minutes of confirmation: participation of IRP
Commune of IRP and consultant of proposed income and Income activity is opted by household,
activities to participant and participant opts income participant of IRP in Phuoc Thanh Commune, Long
activity for household in 9 November 2017 Thanh District- Nov 2017
115. The implementation plan for the income restoration program activities are generally
designed in 2 years (24 months); from date of commencement of the implementation of the
project. Keeping in mind, the implementation plan schedule of IRP was made and updated from
time to time to match the project progress in each commune.
116. There are delays in implementation schedule of original plan of each project district for
IRP , attributed to various reasons:
(i) first, IRP is carried out at local and
(ii) Local authority conducts IRP, they met new strange problem on procedures of
organization, and mechanism to carry out ;
(iii) the limit capacity and experience of local authority and working group as well
as assigned staffs to carry out IRP, most of these assigned staffs in first time for
IRP implementation are limit
(iv) delay and difficulty in procedures and issued decision and mobilizing local staffs
to set up management committee of IRP implementation and working groups
to assist implementation of IRP;
(v) delay in availability of budget to carry out IRP implementation;
(vi) time of IRP implementation of 24 months, therefore difficulty in mobilizing
local staffs to participate IRP with reason is stagger their job and position after
IRP completed,
(vii) level to support to each HH is small ( 9 M đ) in comparison with total of income
restoration activity investment ;
(viii) some households considers income activity of IRP as sub -income activity is not
main income activity therefore they do not spending more time in
implementing;
(ix) some Households persists to be received cash of support level ;
(x) changes market and climate are reason to affect IRP implementation and result
of IRP
118. The handing over of input in Ben Luc and Can Giuoc District in Long An province has
been done in 2016-2017. Monitoring and evaluating and monitoring conducted in 2017 and is
summarizing result of this survey
120. In Can Giuoc District, according to IRP implementation committee in Can Giouc district
has communicated that 76 HHs, who have received the IRP input before in 2016- 2017, the
evaluation and monitoring of those HHs will be conducted in the month of August 2017 and will
completely summarize in February – March 2018 and additional Information that, 43 HHs are
additional approved in household list of IRP of Can Giouc District by Long An Province PC as
according to Letter No 4236/UBND- KT dated 20 September 2017 to carry out future, Currently.
Management committee of IRP of Can Giuoc District is waiting Budget to conduct for these 43
HHs
-----------------------------------------------------------------------------------------------------------------------------------------
• Binh Chanh District: additional Compensation plan for land acquisition to relocate
electricity poles in The District was prepared and submitted to Department of finance
of Ho Chi Minh City for reviewing and approval before Binh Chanh district PC approval
on the additional compensation plan for land acquisition to removing electricity poles
in District but pending at this time, with reason: MOT’s approval on assessment of
compensation price is not clear. Currently this submission is pending at Department of
Finance of Ho Chi Minh City and EPMU is working and explaining with them on this
issue.
• Nha Be District: CoLFD of The District is awaiting approval for cadastral map of
recovered land area part for each pole from DoNRE of Ho Chi Minh City to have basis
issue of decisions for land acquisition and preparation of compensation plan. This
cadastral map is being pended at DoRNE. Therefore, Compensation plan is not yet
prepared up till now. EPMU and local authority are resolving
• Nhon Trach District: CoLFD is carrying out land acquisition for project and not yet
started process for preparing compensation Plan for relocating Power poles.
• Consultant and EPMU are following up compensation committee of districts to speed
up completion of compensation plan addendum as request
APPENDIX
Annex 1: Status on Handing over of land and Ground Clearance (ADB Section) updated December 2017
-----------------------------------------------------------------------------------------------------------------------------------------
Recovered
Plot Schedule
No Full name area Km… existing content status of land acquisition propose to carry out
number to carry out
( m2)
I. Package A1: 01 HH
[This
information has
been removed
as it falls within
exceptions to
disclosure
specified in
paragraph 97,
(exception (x)
Information
that, if
disclosed, would
or would be
handed over 7260m2 plan will be
likely to
/9140 m2, propose to be resolved quarter 4
1 endanger the 68 Km 3+680
1,880.0 constructed on remaining of 2017 or 1 of
life, health,
land part 2018
safety, or
security of any
individual, or
safety or
security of ADB
assets, or to
prejudice the
defense or
national security
of a member) of
ADB’s Public
Communications
Policy (2011).]
II. Package A2-1: 01 HH
[This
information has
been removed
as it falls within
exceptions to
disclosure
specified in
paragraph 97,
(exception (x)
Information
that, if
disclosed, would
or would be
likely to
waiting decision from
1 endanger the 341.2 81 (1p) Km10+190 Disputing
Court
life, health,
safety, or
security of any
individual, or
safety or
security of ADB
assets, or to
prejudice the
defense or
national security
of a member) of
ADB’s Public
Communications District Court is
Policy (2011).] resolving
III. Package A2-2: 10 HHs
[This request additional
information has compensation for land, Binh Chanh district Court is
42, HH is complaining at court
been removed cost for infrastructure issued the decision, HH
1 road Km11+760 and Co LFD is waiting
as it falls within 1,117.60 investment, bonus, disagree and submitted
(38) Court's decision
exceptions to complaining land area, high court level
disclosure land type
specified in currently. HH District compensation
adjustment of
paragraph 97, 82 (1p) disagree committee has submitted 2
2 Km11+900 compensation, HH do not
(exception (x) 1,203.60 (37) residential land plans of residential land.
receive compensation
Information rate, Inspector is Plan is on next time, District
that, if surveying. PC will issue new rate
disclosed, would according to HH's
or would be requirement.
likely to
endanger the Complaining to District PC,
life, health, House is constructed on
safety, or agricultural land due to plan will be
Co LFD is reviewing at time
security of any 1p 803, already received not sufficient to be resolved quarter 4
3 45.70 Km13+120 of constructed house to
individual, or 112 compensation compensated. Application of 2017 or 1 of
compensate
safety or to be constructed new 2018
security of ADB house on remaining land
assets, or to part
prejudice the complaining
defense or compensation rate,
national security submitting additional
of a member) of compensation for
ADB’s Public agricultural land in
plan will be
Communications DCC is preparing to residential land, waiting plan will pay additional
111 resolved quarter 4
4 Policy (2011).] Km13+220 compensate agricultural DPC for approving, the HH compensation in end of
1,193.40 (1p) of 2017 or 1 of
land in residential land agrees compensation and 2017
2018
handing over land,
Decision of additional
compensation is waiting
District Chairman 's
signature
-----------------------------------------------------------------------------------------------------------------------------------------
(HH: Nguyen Viet Cuong- My Yen Commune – Ben Luc District, Long An Province on 28 March 2017- A 1)
SOCIALIST REPUBLIC OF VIET NAME
Independent – freedom – happiness
------------------000--------------
MINUTES OF WORKING
OF HANDIND OVER GROUND TO CONSTRUCT BEN LUC- LONG THANH EXPRESSWAY PROJECT AT LAND PLOT NO
1435 MAP NO 5 OF HOUSEHOLD: NGUYEN VIET CUONG AT TAN BUU COMMUNE, BEN LUC DISTRICT, LONG AN
PROVINCE
B- Detail Contents
Handing over ground to construct The Ben Luc-Long Thanh Expressway at land plot No 1435 of map No 5 of
HH: Nguyen Viet Cuong at Tan Buu Commune, Ben Luc District
Base on Document No 4420/UBND-NN dated 22 December, 2011 of Long An Province PC of unification on
land acquisition spheres for The Ben Luc-Long Thanh Expressway, Section passes Long An Province
Ben Luc District Co LFD has organized handing over ground to construct the Ben Luc-Long Thanh
Expressway project as after:
- Mr. Nguyen Viet Cuong agreed and handed over ground to construct the project to Co LFD of Ben Luc
District according to border of land acquisition measured by Centre of natural technique and Environment
to identify actually for border of land acquisition in Land plot No 1435 of map No 5 having concreted stake
on actually. Mr. Nguyen Viet Cuong also agreed to Construction contractor to construct P2 Bridge Piles of
the Ben Luc- Long Thanh Expressway in land plot No 1435 of Map No 5 belong Tan Buu Commune
The Minutes ended at 15 PM 30 someday, repeating to sides to head and same agreement and signature
-----------------------------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------------------------
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
- Total of affected household list to submit for second additional approval: 43 HHs (Phước Lý: 14 HHs,
Long Thương 29 HHs). Second of additional IRP list
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
-----------------------------------------------------------------------------------------------------------------------------------------
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
Annex 6. List of HHs already received input in IRP
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
C.
[This information has been removed as it falls within exceptions to disclosure specified in paragraph 97, (exception
(x) Information that, if disclosed, would or would be likely to endanger the life, health, safety, or security of any
individual, or safety or security of ADB assets, or to prejudice the defense or national security of a member) of
ADB’s Public Communications Policy (2011).]
Annex 7. Decision of re-establishment of management committee to carry out IRP Can
Giuoc District
CAN GIUOC DISTRICT SOCIALIST – REPUBLIC OF VIET NAME
PEOPLE’S COMMITTEE Independent- freedom- happiness
----------------------------------------------------------------------------------------------------------------------------------
-------
DECISION
Of: Establishment of Income Restoration Program Management – Ben Luc Long Thanh Expressway
Project, section passes Can Giuoc District
DECISION
Article 1: Re-establishment of income restoration program ( IRP) committee for Ben Luc- Long Thanh
Express way Project, section passes Can Giuoc District, including Mr., MS with name as after:
1. Mr. Nguyen Anh Duc ; Vice Chairman of District People Committee – Chief of the Committee
2. Mr. Ho Van Son; head of DoLISA of Can Giuoc District; Vice Chief of the committee
3. Ms. Dong Quang Don; Head of Do ARD of Can Giuoc District; Vice Chief of the Committee
4. Ms. Nguyen Thi Phuong Loan, Vice Head of Department of Finance of Can Giuoc District- Member
5. Mr. Tran Van Ngoc Sinh ; Director of Co LFD of Can Giuoc District; Member
6. Mr. Pham Tan Loi, Head of department of economic and infrastructure of Can Giuoc District]
7. Mr. Bach Ngoc Bay, Vice chairman of Farmer Association of The District; Member
8. Ms. Huynh thi Tuyet Hong, Chairwoman of woman Union of The District
9. Ms. Tran Thi Thanh Phuong, Vice manager of PC office and People’s Council office; member
Working Groups to assist for the management committee of IRP, including name as after:
1. Mr. Vo Dinh Xuong, Vice head of DoLISA of The District- Leader of the Group
2. Mr. Nguyen Thanh Tu; Vice Director of Co LFD of The District- Vice leader of the group
3. Mr. Nguyen Minh Khoa, Staff of PC office and People’s Council of the District-member
4. Mr. Nguyen Van Kiet, staff of DOLISA of the District- member
5. Ms. Thi Lan Dai, Staff of DOLISA of the District- member
6. Mr. Tran Tuan Thanh, Chairman of Phuoc Ly Commune PC- member
7. Ms. Tran Thi My Dung, Vice Chairwoman of Long Thuong Commune PC- member
8. Mr. Dang Tran Quoc Thai; Staff of Team of Labor and invalids, social affairs of the Phuoc ly
commune- member
9. Mr. Nguyen Phan Quang Thien, Staff of Team of Labor and invalids, social affairs of the
Long Thuong commune- member
Article 2. The management committees have responsibility of organization to carry out IRP for the Ben Luc-
Long Thanh Expressway Project; section passes Can Giuoc District according to approved contents of the
IRP, prepared by KEI-NE Consultant and under guiding by guiding committee of the Province
The working groups will assist in implementing IRP according to assign the IRP implementation Management
committee of the Ben Luc- Long Thanh Expressway Project, section passes Can Giuoc District
The IRP implementation Management Committee will use stamp and account of DoLISA of The Can Giuoc
District to liquidate budget as regulation
Article 3. Office manager of District People’s committee and People’s council, Head of DoLISA, Leaders of
related agencies, MS, Mr. having name as in article 1 and PC chairman of Phuoc Ly Commune and Long
Thuong Commune responsible in implementation of this decision
This decision effects since signed and replace decision No 10/QD9-UBND dated 06/January/2016 of Can
Giuoc PC. /.
----------------------------------------------------------------------------------------------------------------------------------
-------