Project : STANFORD SUITES 3 Ref#C0082017

Location : SOUTH FORBES, BRGY. INCHICAN, SILANG, CAVITE


Owner : CATHAY LAND, INC.
Subject : SUMMARY BILL OF QUANTITIES
Date : July 04, 2018

SUMMARY BILL OF QUANTITIES

ITEM DESCRIPTION AMOUNT


A GENERAL REQUIREMENTS 6,832,517.89
B EARTHWORKS 6,108,007.53
C REBAR WORKS 7,194,793.54
Rebar Guaranteed Quantities = (kgs) 528,818.19
D CONCRETING WORKS 28,462,596.89
E FORMWORKS 19,802,434.83
F MASONRY WORKS 20,389,183.40
Cement Guaranteed Quantities = (bags) 29,000.00
Eurotles 102 = (pails) 2,000.00
G METAL WORKS 3,694,397.76
H THERMAL AND MOISTURE PROTECTION 9,527,574.41
I FLOOR AND WALL FINISHES 2,754,899.77
J OPENINGS 8,418,604.18
K CARPENTRY WORKS 9,023,258.36
L ELECTRICAL & AUXILIARY WORKS 30,511,994.96
M PLUMBING & SANITARY WORKS 31,962,628.40
N FIRE PROTECTION 11,026,179.61
O MECHANICAL WORKS 13,941,964.87
P GAS LINE N/A
Q PAINTING WORKS 16,618,473.80

Material Cost 140,484,277.08


Labor Cost 78,952,715.21
TOTAL DIRECT COST 219,436,992.28
General Requirements 6,832,517.89
Contingency 2,628,929.01
Vat 18,101,560.81
TOTAL INDIRECT COST 27,563,007.71

TOTAL PROJECT COST PHP 247,000,000.00

CONTRACTOR : EC Construction Technologies & Realty Inc.

SUBMITTED BY : EDUARD C. CHONG


DESIGNATION : GENERAL MANAGER
Excluded Items
1. Supply of the following: Cements, Rebars, Floor & Wall Finishes, Steel Doors & Windows, Plumbing Fixtures, Grease Trap,
T&B Accessories, Tel.System, CCTV System, ATS, MTS, Wiring Devices, Electrical Fixtures, Panel Boards & ECB, Meter
Centers & Gutters, Pumps & Accessories, PRV-SAV at Cistern & Firewater Tanks (not in plan), Water Filter, Fire Alarm System,
Smoke Detectors, ACU, Fans & Blowers, Door hardwares

2. Supply and Installations of the following: Vinyl Planks, Gensets, Elevators, STP, Swimming Pool, Aluminum Doors &
Windows, Signage's, Reception Table, FIRE EXTINGUISHER 50LBS, WIFI System, CPS Constant Pressure System