You are on page 1of 1

Proyek : Additional Concrete Pedestrian CJS R.

0
Lokasi : Deltamas

No Items Unit Quantity Unit Rate Total

I PRELIMINARIES
1 Transportation (Staff), Mess, Small Tools ls 1,00 277.778 277.778

II MAIN WORKS
1 Add Concrete Pedestrian (0,9 m x 2 m)
Include :
- Basecourse 100 mm Thick (minimum order 1 m3) m3 0,24 1.800.000 432.000
- Concrete 120 mm Thick (Instant Concrete) m3 0,20 5.640.000 1.128.000
- Wiremesh M6 1 layer m2 2,00 450.000 900.000
- Multipleks 10 mm ls 1,00 200.000 200.000
- Dowel Bar ls 1,00 150.000 150.000

- 2 Worker + 1 Foreman + Transportation ls 1,00 3.200.000 3.200.000


- Remove Waste Material, Tool) ls 1,00 500.000 500.000

Profit + Overhead 543.022


Total (Exclude Ppn 10%) 7.330.800
Rounded 7.300.000