13.5.2.3 ENGINE SPEED ADJUSTMENT


• Prior to the adjustment, sufficiently warm up the
machine.
1. Set the engine key to the "ON" position (the engine
is not started).
2. Set the engine key to the "ON" position (the engine
is not started).

3. Press the "CHECK" switch of the cluster gauge.


(The screen can be changed whenever this switch
is pressed.)
Then, the message "STEP3" is displayed on the
display screen of the cluster.

4. Start the engine, and press the "ZERO" switch of the


cluster gauge. Then, the engine speed is acceler-
MEMORY
ated gradually.

5. When the engine speed reaches the high idling, it is


decreased gradually.

6. When the engine speed reaches the low idling, the


message "G-5" is displayed on the display screen
of the cluster.

7. Return the "ADJUSTMENT" switch to the "RUN" po-


sition.

Adjustment of engine speed


A. Adjustment switch: "TEST" position
"STEP 3" ENG.
B. Inching switch:
START
C. "Zero" switch: Press
D. Engine automatic adjustment
E. Adjustment switch: "RUN" position