BID DOCUMENT
FOR
Tender ID 2021_GAIL_99063
VOLUME – I OF IV
1 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
CONTENT
‐ 2 ‐
2 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
SECTION-I
‐ 3 ‐
3 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
SECTION-I
"INVITATION FOR BID (IFB)”
Dear Sir/Madam,
1.0 GAIL (India) Limited [having registered office at 16, Bhikaji Cama Place, New
Delhi 110066 CIN No. L40200DL1984GOI018976], the largest state-owned
natural gas processing and distribution company and the Maharatna, has engaged
MECON limited as Project Management Consultant, for ANGUL-SRIKAKULAM
PIPELINE PROJECT ( PART-B)
MECON Ltd. on behalf of GAIL (India) Ltd. invites bids from bidders for the
subject job/works, in complete accordance with the following details and enclosed
Tender Documents. Bids submitted online on e-tendering CPP portal of Government
(https://etenders.gov.in/eprocure/app) shall only be considered for processing.
SINGLE BID
SYSTEM 𝐗
E-TENDER
√
‐ 4 ‐
4 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Tender ID : 2021_GAIL_99063
COMPLETION/CONTRACT PERIOD :
For any Section, more than one Section, or for all the Sections
(E)
Completion schedule shall be 9 (Nine) months from the date of Go –ahead/ Fax of
Acceptance (FOA) for Mechanical Completion including mobilization period of 1 (one)
month and thereafter 1 (One) month for drying, commissioning and Gas-in.
Date : 06.01.2022
Time : 1500 Hrs (IST)
Shall be conducted through Video
DATE, TIME & VENUE OF PRE-BID
(H) Conferencing
MEETING
Details of VC via Google Meet -
Video call link:
https://meet.google.com/rsw-kqqa-euz
DUE DATE & TIME OF BID- Date : 24.01.2022
(I)
SUBMISSION (ON OR BEFORE) Time : Upto 1400 Hrs (IST)
Date : 25.01.2022
DATE AND TIME OF UN-PRICED BID Time : At 1500 Hrs (IST)
(J)
OPENING Shall be conducted through Video
Conferencing
‐ 5 ‐
5 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Details of VC via Google Meet -
Video call link:
https://meet.google.com/bpd-jwfe-owj
Mr. Rakesh Sharma
Sr. GM (Contracts)
MECON Limited 15th Floor,
CONTACT DETAILS OF TENDER SCOPE Minar, North Tower
(K)
DEALING OFFICER Laxmi Nagar, District Center, Delhi – 110 092
Telephone: +91-11-22401103/22401143
Fax: +91-11-22041214/22421310
E-mail: cont-delhi@mecon.co.in
M/s GAIL (India) Limited
(L) DEALING GAIL’S OFFICE ADDRESS 17th Floor, Jubilee Tower, B-35/36, Sector-1,
Noida, U.P., India
In case of the days specified above happens to be a holiday in GAIL, the next working day
shall be implied.
3.0 Bids must be submitted strictly in accordance with Clause No. 11 of ITB (Section-III)
depending upon Type of Tender [refer Clause no. 2.0 (D) above]. The IFB is an integral
and inseparable part of the bidding document.
4.0 In case of E-Tender, bid must be submitted only on https://etender.gov.in/eprocure/app
Further, the following documents in addition to uploading the bid on Govt. CPP Portal
shall also be submitted in Original (in physical form) within 7 (seven) days from the bid
due date provided the scanned copies of the same have been uploaded in e-portal by the
bidder along with e-bid within the due date and time to the address mentioned in Bidding
Data Sheet(BDS)[Annexure-IV to Section-III]:-
i) Declaration for Bid Security
ii) Power of Attorney
iii) Integrity Pact (if applicable)
5.0 In case of Manual Tenders, bids complete in all respect should reach at the address
specified in Bid Data Sheet on or before the due date & time. Bids received after the due
date and time is liable to be rejected.
6.0 Bidder(s) are advised to quote strictly as per terms and conditions of the tender documents
and not to stipulate any deviations/exceptions.
7.0 Any bidder, who meets the Bid Evaluation Criteria (BEC) and wishes to quote against
this Tender Document, may download the complete Tender Document alongwith its
amendment(s) if any from websites as mentioned at 2.0 (G) of IFB and submit their Bid
complete in all respect as per terms & conditions of Tender Document on or before the
Due Date & Time of Bid Submission.
8.0 Bid(s) received from bidders to whom tender/information regarding this Tender
Document has been issued as well as offers received from the bidder(s) by downloading
Tender Document from above mentioned website(s) shall be taken into consideration for
evaluation & award provided that the Bidder is found responsive subject to provisions
contained in Clause No. 2 of ITB (Section-III).
‐ 6 ‐
6 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
The Tender Document calls for offers on single point “Sole Bidder” responsibility basis
(except where JV/Consortium bid is allowed pursuant to clause no. 3.0 of ITB) and in
total compliance of Scope of Works as specified in Tender Document.
9.0 Any revision, clarification, corrigendum, time extension, etc. to this Tender Document
will be hosted on the above mentioned website(s) only. Bidders are requested to visit the
website regularly to keep themselves updated. In case of manual tendering,
Clarification(s)/Corrigendum(s), if any, shall be sent to the prospective bidder(s) by
email/post.
10.0 All bidders including those who are not willing to submit their bid are required to submit
F-6 (Acknowledgement cum Consent letter) duly filled within 7 days from date of
receipt of tender information.
11.0 SAP generated Request for Quotation (RFQ), if any shall also form an integral part of the
Tender Document.
(Rakesh Sharma)
Sr.GM (Contracts)
MECON Limited 15th Floor, SCOPE Minar, North Tower
Laxmi Nagar, District Center, Delhi – 110 092
Telephone: +91-11-22401103 / 22401143
Fax: +91-11-22041214 / 22421310
E-mail: cont-delhi@mecon.co.in
‐ 7 ‐
7 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
DO NOT OPEN - THIS IS A QUOTATION
From: To:
MECON LIMITED
DELHI – 110092
Ph No.: 91-11-22401144/22401103
Email : cont-delhi@mecon.co.in
‐ 8 ‐
8 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
SECTION-II
BID EVALUATION
CRITERIA &
EVALUATION
METHODOLOGY
‐ 9 ‐
9 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
BID EVALUATION CRITERIA & EVALUATION METHODOLOGY
A. Technical Criteria
A.1 The bidder should have successfully executed (*)/ completed in last 7 (Seven) years to be
reckoned from the bid due date, at least one single contract (**) involving laying /
installation, Hydro-testing and ‘EGP or Drying or Nitrogen purging or Commissioning’
of buried cross country hydrocarbon steel Pipeline of diameter and length as given below
for qualifying for the section(s):
Note:
i) (*) As defined in ‘Documents required for qualification’ at clause no. F [A.1 (b)].
ii) (**) In case more than one contract are emanating against one tender, these
contracts are to be considered as single contract for evaluation of credentials of a
bidder for meeting their experience criteria (Applicable for all sections).
iii) If a bidder quote for one section, the bidder must meet the qualification
requirement of respective section in a single contract, as mentioned in above
table.
iv) If a bidder quote for more than one section and meet respective qualification
requirement through separate contract(s) the bid shall be considered qualified for
all such quoted sections on individual basis. In such case, award shall be done for
any one section only out of such quoted section(s), on least cost basis.
v) If a bidder to qualify for two quoted sections, the bidder shall have to meet the
qualification criteria for combined quoted sections under single contract for single
diameter execution, as under:
(a) Bidder who quotes for any two sections, must meet the BEC (Technical)
requirements on cumulative length basis and with higher diameter for two
quoted sections, in a single contract.
‐ 10 ‐
10 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
(b) If a bidder quotes for more than two sections, then bidder must meet the
qualifying BEC (Technical) requirement of length on cumulative basis
applicable for any two quoted sections having highest length
requirement(s), in a single contract. However, if quoted section(s) include
Section–I, the required cumulative length as defined above, shall be for
minimum diameter of 12”.
A.2 In case the bidder has an experience as a consortium member and such a member has
executed earlier a job within its scope as a member of the consortium, which is required
as experience as per the qualification criteria in clause no. A.1, will be considered.
Appropriate documentary evidence to establish this is to be submitted towards such
experience.
Bidder shall meet the minimum construction equipment requirement as specified in the
bidding document (Annexure-II to Section-II).
Bidder who quotes for any two sections shall meet the qualifying Equipment
Deployment Criteria of BEC (Technical) requirement on cumulative basis.
Further, if a bidder quotes for more than two sections to get qualified for all such quoted
sections, then bidder must meet the qualifying minimum Equipment Deployment Criteria
of BEC (Technical) requirement on cumulative basis of any two quoted sections having
maximum number of equipment requirement.
(i) A Job executed by a Bidder for its own plant/ project cannot be considered as
experience for the purpose of meeting BEC of this Tender Document. However, jobs
executed for Subsidiary/Fellow subsidiary / Holding company will be considered as
experience for the purpose of meeting BEC subject to submission of tax paid invoice (s)
duly certified by Statutory Auditor of the Bidder towards payments of statutory tax in
support of the job executed for Subsidiary/Fellow subsidiary/ Holding company. Such
Bidders to submit these documents in addition to the documents specified to meet BEC.
(iii) Eligibility criteria in case bid is submitted on the basis of technical experience of
FOREIGN BASED ANOTHER COMPANY(SUPPORTING COMPANY) which holds
more than fifty percent of the paid up share capital of the bidder company or vice versa:
Offers of those bidders (not under consortium arrangement) who themselves do not meet
the technical experience criteria as stipulated in the BEC and are quoting based on the
experience of Foreign based another company (Supporting Company) can also be
considered. In such case the supporting company should hold more than fifty percent of
the paid up share capital of the bidding company or vice versa.
‐ 11 ‐
11 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Credential of Supporting company from a country which shares a land border with India
will only be considered if they are registered with the Competent Authority as on bid due
date, specified in Annexure I of Order (Public Procurement No. 1) dated 23.07.2020 of
Department of Expenditure.
However, the supporting company should on its own meet the technical experience as
stipulated in the BEC and should not rely on any other company or through any other
arrangement like Technical collaboration agreement.
In that case as the bidding company is dependent upon the technical experience of
another company with a view to ensure commitment and involvement of the companies
involved for successful execution of the contract, the participating bidder should enclose
the following Agreements/ Guarantees/ Undertakings along with the techno-commercial
bid:
(ii) Guarantee (as per format enclosed at Appendix-A2 & A2A to Section-II) by the
supporting company to GAIL for fulfilling the obligation under the Agreement.
(iii) Registration of Supporting company with the Competent Authority as on bid due
date, specified in Annexure I of Order (Public Procurement No. 1) dated
23.07.2020 of Department of Expenditure.
In cases where foreign based supporting company does not have Permanent
Establishment in India as per Indian Income Tax Act, the bidding company can
furnish Performance Bank Guarantee for an amount which is sum of PBG amount
to be submitted by the bidder and additional PBG amount required to be
submitted by the supporting company subject to the condition that supporting
company have 100% paid up equity share capital of the bidder either directly or
through intermediate subsidiaries or vice versa.
In such case bidding company shall furnish an undertaking that their foreign
based supporting company is not having any Permanent Establishment in India in
terms of Income Tax Act of India.
(v) Undertaking from the supporting company to the effect that in addition to
invoking the PBG submitted by the bidding company, the PBG provided by
supporting company shall be invoked by GAIL due to non-performance of the
bidding company.
Note:
‐ 12 ‐
12 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
In case supporting company fails to submit Bank Guarantee as per (iv) above, SD
submitted by the bidder shall be forfeited and action shall be taken against the bidder as
per declaration for bid security
B FINANCIAL CRITERIA
The minimum annual turnover (i.e. Revenue from Operations) of the bidder as per their
audited financial statement in any one of the three immediate preceding financial years
shall be as under:
Net worth of the bidder should be positive as per the last audited financial year. For the
purpose of net worth for this tender, the same shall be as defined in Format F-10.
The minimum working capital of the bidder as per the last audited financial year shall be
as under: -
Note to B:
‐ 13 ‐
13 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
(i) If the bidder’s working capital is negative or inadequate, the bidder shall submit a
letter from their bank having net worth not less than Rs.100 crores (or equivalent
USD), confirming the availability of line of credit for the amount mentioned herein
above. The line of credit letter from bank to be submitted strictly as per format at F-
9.
The Declaration Letter/Certificate for line of credit due to short fall of working
capital shall be from single bank only. Letters from multiple banks shall not be
applicable. However, banking syndicate will also be acceptable wherein a group of
banks can jointly provide line of credit to the bidder.
(ii) Bidder who quotes for any two sections to get qualified for both quoted sections
shall have to meet the qualifying annual turnover & working capital requirement on
cumulative basis for the quoted section(s). Further, bidder who quotes for more than
two sections to get qualified for all such quoted sections, shall have to meet the
qualifying, annual turnover & working capital requirement on cumulative basis, of
any two quoted section(s) having highest value requirement, shall be considered
qualified for any two combination of quoted sections.
(iii) Annual Turnover: Preceding 3 financial years mentioned in aforesaid BEC refer to
immediate 3 preceding financial years wherever the closing date of the bid is after
30th November (or as amended by Government time to time) of the relevant
financial year. In case the tenders having the due date for submission of bid up to
30th November (or as amended by Government time to time) of the relevant
financial year, and audited financial results of the immediate 3 preceding financial
years are not available, the audited financial results of the 3 years immediately prior
to that will be considered. Further, in case bidder is meeting the Annual Turnover
criteria of BEC based on Audited Financial Statement of any one of the preceding 3
financial years (as mentioned above), the same shall suffice and bidder may submit
format F-10 accordingly.
C. VOID
D. Only documents (Work Order, Completion certificate, Execution Certificate etc.) which
have been referred/ specified in the bid shall be considered in reply to queries during
evaluation of Bids.
‐ 14 ‐
14 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Further, any shortfall information / documents on the Audited Annual Report / Financial
Statement of the Bidder and/or line of credit for working capital issued on or before the
final bid due date can only be considered as submitted in bid/subsequent response against
GAIL/PMC’s query, if any. Any information/ documents issued post final bid due date
shall not be considered for evaluation.
Not Applicable
BEC
Clause Description Documents required for qualification
no.
A Documents Required-Technical Criteria
A.1 Experience as a single (a) Detailed work order along with Schedule of
bidder Rates.
(b) Completion certificate issued by end user /
Owner (or their consultant who has been
duly authorized by owner to issue such
certificate).
Note to Jobs executed for Tax paid invoice(s) duly certified by statutory
A (i) Subsidiary / Fellow auditor of the bidder towards payments of
subsidiary/ Holding statutory tax in support of the job executed for
company Subsidiary / Fellow subsidiary /Holding
company.
B Documents Required-Financial Criteria
B.1 Annual Turn-over Bidder(s) shall submit copy of Audited Annual
Financial Statement [Balance Sheet and Profit &
Loss Account Statement] alongwith Audit
Report of three (3) preceding Financial Year(s)
along with un-price bid.
B.2 Net Worth Bidder(s) shall submit copy of Audited Annual
Financial Statement [Balance Sheet and Profit &
Loss Account Statement] alongwith Audit
Report of last Financial Year along with un-
‐ 16 ‐
16 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
BEC
Clause Description Documents required for qualification
no.
price bid.
B.3 Working Capital Bidder(s) shall submit copy of Audited Annual
Financial Statement [Balance Sheet and Profit &
Loss Account Statement] alongwith Audit
Report for the last audited Financial Year along
with un-price bid.
H. VOID
I. Apart from above, Bidder must submit all other relevant documents/ information as
specified in the Scope of Work/SCC for Technical Evaluation of bid or specified
elsewhere in the Tender Document, towards proof of its responsiveness.
2. Any bidder from a country which shares a land border with India will be eligible
to bid in this tender only if the bidder is registered with the Competent Authority.
For details of competent authority refer to Annexure I of Order (Public
Procurement No. 1) dated 23.07.2020.
Further the above will not apply to bidders from those countries (even if sharing a
land border with India) to which the Government of India has extended lines of
credit or in which the Government of India is engaged in development projects.
Updated lists of countries to which lines of credit have been extended or in which
development projects are undertaken are given in the website of the Ministry of
External Affairs, Govt. of India
‐ 17 ‐
17 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
3. "Bidder" (including the term 'tenderer', 'consultant' 'vendor' or 'service provider'
in certain contexts) for purpose of this provision means any person or firm or
company, including any member of a consortium or joint venture (that is an
association of several persons, or firms or companies), every artificial juridical
person not falling in any of the descriptions of bidders stated hereinbefore,
including any agency, branch or office controlled by such person, participating in
a procurement process.
4. "Bidder from a country which shares a land border with India" for the
purpose of this:
Explanation—
ii) In case of a partnership firm, the beneficial owner is the natural person(s)
who, whether acting alone or together, or through one or more juridical
person, has ownership of entitlement to more than fifteen percent of
capital or profits of the partnership;
‐ 18 ‐
18 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
iv) Where no natural person is identified under (i) or (ii) or (iii) above, the
beneficial owner is the relevant natural person who holds the position of
senior managing official;
6. "Agent" for the purpose of this Order is a person employed to do any act for
another, or to represent another in dealings with third persons
The successful bidder shall not be allowed to sub-contract works to any contractor
from a country which shares a land border with India unless such contractor is
registered with the Competent Authority. The definition of "contractor from a
country which shares a land border with India" shall be as in Para 4 herein above.
A Certificate to this regard is to be submitted by bidder is placed at Form-I to
Section-II.
K.1 The “Schedule of Rates/BOQ” quoted for Section I, II, III & IV including GST shall be
taken up for evaluation on section wise basis. The entire work shall be finalized on least
cost basis to owner, if a bidder happens to be lowest in more than one Section and has
qualified only for one or more than one of the sections and not all quoted sections, as the
case may be. Once such Section(s) is considered for award to such L-1 bidder, the bidder
ceases to be lowest bidder for the remaining Section(s) which are not considered for
award and inter-se ranking for all remaining bidders shall be re-worked.
Maximum Two sections shall be awarded to single bidder based on its meeting the
eligibility criteria on least cost basis as per methodology mentioned herein above.
‐ 19 ‐
19 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
K.2 To arrive at the evaluated price, loading on total quoted price shall be done taking into
account Extended stay compensation for 1/5th of the time schedule or 1 (One) Month,
whichever is less. In case schedule for extended stay is not enclosed or the prices are left
blank, it will be considered that prices towards extended stay if any, are included in
quoted price as NIL.
K.3 Preferences: Purchase Preference for PP-LC shall be applicable as per Government
Guideline in vogue.
ii. It will be responsibility of the bidder to inform MECON / GAIL within 15 (Fifteen) days
from the date of order of insolvency resolution process or liquidation or bankruptcy
proceeding passed by the Adjudicating Authority namely National Company Law
Tribunal (NCLT) or Debt Recovery Tribunal (DRT) under the Code.
iii. If bidder refuses or fails to share the information regarding their status of insolvency
resolution process or liquidation or bankruptcy proceeding in their bid or at any latter
stage, their offer is liable to be rejected by MECON/ GAIL.
iv. MECON / GAIL reserve the right to cancel / terminate the contract without any liability
on the part of MECON/ GAIL immediately on the commencement of insolvency
resolution process or liquidation or bankruptcy proceeding of any party under the
contract.
v. MECON / GAIL reserve the right to evaluate and finalise the bid without considering the
bid of any party undergoing insolvency resolution process or liquidation or bankruptcy
proceeding under the code regardless of the stage of tendering.
A declaration in this regard shall be furnished by the bidder as per format which shall be made as
Annexure-III to Section-II.
‐ 20 ‐
20 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ANNEXURE –I TO SECTION-II
Authentication of documents to be submitted in support of BEC
All charges of the Third party for verification and certification shall be borne by
the Bidder.
In absence of requisite documents, GAIL / MECON reserve the right to reject the bid without
making any reference to the bidder.
‐ 21 ‐
21 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ANNEXURE-I to ANNEXURE-I to SECTION-II
Format for Undertaking from TPIA
(on TPIA letter head duly stamped & signed)
Ref.:
Date:
To,
M/s GAIL (India) Limited
17th Floor, Jubilee Tower, B-35/36, Sector-1, Noida, U.P., India
Dear Sir,
The tender conditions stipulates that the BIDDER shall submit Documents pertaining to
Technical Bid Evaluation Criteria (BEC) duly verified and certified by designated
independent Third Party Inspection Agency.
In this regard, this is to certify that copies of documents pertaining to Technical Bid
Evaluation Criteria (BEC) submitted to us by the bidder have been verified and certified by
us with the originals and found to be genuine. We have signed and stamped on the copies
of all the verified and certified documents.
‐ 22 ‐
22 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ANNEXURE –II TO SECTION-II
Notes:
1. Bidder who quotes for any two sections shall meet the qualifying minimum Equipment
Owning Criteria of BEC (Technical) requirement on cumulative basis.
Further, if a bidder quotes for more than 2 sections, then bidder must meet the qualifying
Equipment Owning Criteria of BEC (Technical) requirement on cumulative basis of any
two quoted sections having maximum number of equipment requirement.
i. The bidder shall submit the certificate from chartered accountant (for ownership /
possession of equipments / vehicles) as per format F-19 enclosed in the Bid
Document.
ii. The submission of Format F-19 is mandatory.
iii. “For equipment to be purchased" - Purchase order duly accepted by equipment
supplier and with equipment delivery to project site, meeting the equipment
deployment schedule. However, contractor to own minimum 50% of the equipment
against each type of equipment; balance 50% may be covered under to be purchased
"Category". If 50% is a fraction, the same needs to be rounded off to next higher
number for the minimum owned category. The purchase order shall be duly signed &
stamped by Chartered Accountant / statutory auditor. Date of purchase order shall be
before bid due date.
iv. The bidder shall submit Certificate from Chartered Engineer certifying that the
bidder own equipments are under good health and working condition as per Format
F-20 enclosed in the Bid Document.
‐ 23 ‐
23 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ANNEXURE –III TO SECTION-II
OR
(a) ____________________________________________________________
(b) ____________________________________________________________
(c) ____________________________________________________________
It is understood that if this declaration is found to be false, GAIL (India) Limited shall have
the right to reject my/our bid, and forfeit the EMD. If the bid has resulted in a contract, the
contract will be liable for termination without prejudice to any other right or remedy
(including black listing or holiday listing) available to GAIL (India) Limited.
‐ 24 ‐
24 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Form-I to Section II
UNDERTAKING ON LETTERHEAD
To,
M/s GAIL (India) Limited
17th Floor, Jubilee Tower, B-35/36, Sector-1, Noida, U.P., India
Dear Sir
We have read the clause regarding Provisions for Procurement from a Bidder of a country which
shares a land border with India and on sub-contracting to contractors from such countries; we
certify that, bidder M/s____________ (Name of Bidder) is:
We further certify that bidder M/s____________ (Name of Bidder) will not sub-contract any work
to a contractor from such countries unless such contractor is registered with the Competent
Authority.
We hereby certify that bidder M/s____________ (Name of Bidder) fulfills all requirements in this
regard and is eligible to be considered.
‐ 25 ‐
25 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Appendix-A1 to Section II
This agreement made this ___ day of ____ month ____ year by and between M/s.
____________________ (Fill in Bidder’s full name, constitution and registered office address)
___________ hereinafter referred to as bidder on the first part and M/s. ___________ (Fill in
full name, constitution and registered office address company which hold more than fifty
percent of the paid up share capital of the bidding company or vice versa) hereinafter referred to
as “Supporting Company” of the second part.
Whereas
M/s. GAIL (India) Limited (hereinafter referred to as GAIL) has invited offers vide their tender
No. _____________ for _______________and M/s. __________________ (Bidder) intends to
bid against the said tender and desires to have technical support of M/s. ________________
[Supporting Company]
And whereas Supporting Company represents that they have gone through and understood the
requirements of the subject tender and are capable and committed to provide the services as
required by the bidder for successful execution of the contract, if awarded to the bidder.
a) M/s.____________ (Bidder) will submit an offer to GAIL for the full scope of
work as envisaged in the tender document as a main bidder and liaise GAIL directly for
any clarifications etc. in this context.
c) The Bidder/ Supporting Company holds more than 50% paid up equity capital of
the Supporting Company/ Bidder.
d) This agreement will remain valid till validity of bidder's offer to GAIL including
extension if any and till satisfactory performance of the contract, the same is awarded by
GAIL to the bidder.
f) The bidder shall have the overall responsibility of satisfactory execution of the
contract awarded by GAIL, however without prejudice to any rights that GAIL might
have against the Supporting Company
‐ 26 ‐
26 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
g) It is further agreed that, if contract pursuant to Supporting Company shall be
jointly and severely responsible to GAIL for the performance of works during contract
period and for the satisfactory execution of the contract, and for all the consequences for
non-performance thereof.
In witness whereof the parties hereto have executed this agreement on the date mentioned above.
Witness: Witness:
1) 1)
2) 2)
‐ 27 ‐
27 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Appendix-A2 to Section II
THIS DEED OF GUARANTEE executed at ……….. this …….. day of ……… by M/s
………………………… (mention complete name) a company duly established and existing
under the laws of …………………. (insert country), having its Registered Office at
……………………………………… hereinafter called “the Guarantor and/ or the Supporting
Company” which expression shall, unless excluded by or repugnant to the subject or context
thereof, be deemed to include its successors and permitted assignees.
FOR
M/s ………………………… (bidder) a company duly established and existing under the laws of
…………………. (insert country), having its Registered Office at
……………………………………… hereinafter called the “Bidder” which expression shall,
unless excluded by or repugnant to the subject or context thereof, be deemed to include its
successors and permitted assignees.
TOWARDS
M/s GAIL(India) Limited, a company duly registered under the law of India having its
Registered Office at 16, Bhikaiji Cama Place, R. K. Puram, New Delhi-110066, India, and
having Purchase center at …………… hereinafter called “GAIL” which expression shall unless
excluded by or repugnant to the context thereof, be deemed to include its successor and
assignees
WHEREAS GAIL has invited tender number ………………… for …….. on ………….., and
the bidder has submitted it bid number…………… in response to the above mentioned tender
invited by GAIL.
AND WHEREAS the bidder/ Guarantor Company holds more than 50% paid up equity capital
of the Supporting Company/ Bidder .
AND WHEREAS one of the condition for acceptance of Bidder’s bid against said tender is that
in case the bidder is seeking to qualify upon the technical credentials of its Guarantor Company,
then the bidder shall arrange a guarantee from its Guarantor Company guaranteeing due and
satisfactory performance of the work covered under the said tender including any change
therein as may be deemed appropriate by the GAIL at any stage.
The Guarantor represents that they have gone through and understood the requirement of the
above said tender and are capable of and committed to provide technical and such other supports
as may be required by the Bidder for successful execution of the same.
The Bidder and the Guarantor have entered into an agreement dated ……… as per which the
Guarantor shall be providing technical, financial and such other supports as may be necessary
for performance of the work under the tender, if the contract is awarded to the Bidder.
Accordingly, at the request of the Bidder and in consideration of and as a requirement for the
GAIL to enter into agreement(s) with the Bidder, the Guarantor hereby guarantees and
undertakes that upon award of Contract to Bidder against bid number ……………, made by the
Bidder under tender number………………:
‐ 28 ‐
28 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
2.Signature________________
Full Name _________________
Address___________________
1. The official(s) executing the guarantee should affix full signature(s) on each page.
2. Resolution passed by Board of Directors of the guarantor company authorizing the
signatory(ies) to execute the guarantee, duly certified by Company Secretary should be
furnished along with Guarantee.
‐ 30 ‐
30 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Appendix-A2A to Section II
“Obligations contained in deed of guarantee No. ______ furnished against tender No.
______ are enforceable against the Guarantor Company and the same do not, in any way,
contravene any law of the country of which the Guarantor Company is the subject.”
‐ 31 ‐
31 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Appendix-A3 to Section II
Further, M/s _____________ (Name of the Supporting company) having its registered/head office
at ______________________ based on whose experience/technical strength, the SUPPLIER has
qualified for award of contract (hereinafter referred to as the 'SUPPORTING COMPANY') which
expression shall, unless repugnant to the context or meaning thereof include all its successors,
administrators, executors and assignees) has agreed to provide complete technical and other support
to the SUPPLIER for successful completion of the contract as mentioned above, entered between
GAIL and the SUPPLIER and GAIL having agreed that the 'SUPPORTING COMPANY' shall
furnish to GAIL a
performance guarantee for Indian Rupees/US$ .............. towards providing complete
financial and other support to the SUPPLIER for successful completion of the contract as
mentioned above,
11. 12.
Notwithstanding anything contained herein:
a) The Bank’s liability under this Guarantee shall not exceed (currency in figures) . . . . . . .
. . . . . . . . . (currency in words only ) . . . . .
b) This Guarantee shall remain in force upto ___________ (this date should be expiry date
13.
of defect liability period of the Contract) and any extension(s) thereof; and
c) The Bank shall be released and discharged from all liability under this Guarantee unless
‐ 33 ‐
33 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
a written claim or demand is issued to the Bank on or before the midnight of
………………….(indicate date of expiry of claim period which includes minimum three
months from the expiry of this Bank Guarantee) and if extended, the date of expiry of the
last extension of this Guarantee. If a claim has been received by us within the said date, all
the rights of GAIL under this Guarantee shall be valid and shall not cease until we have
satisfied that claim.
Yours faithfully,
_______________
Bank by its Constituted Attorney
‐ 34 ‐
34 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
SECTION-III
INSTRUCTION TO
BIDDERS
(TO BE READ IN CONJUNCTION WITH
BIDDING DATA SHEET (BDS)
‐ 35 ‐
35 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
SECTION-III
INSTRUCTION TO BIDDERS
INDEX
[A] GENERAL:
1. SCOPE OF BID
2. ELIGIBLE BIDDERS
3. BIDS FROM CONSORTIUM
4. ONE BID PER BIDDER
5. COST OF BIDDING
6. SITE-VISIT
‐ 36 ‐
36 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
[G] ANNEXURES:
1. ANNEXURE-I: PROCEDURE FOR ACTION IN CASE
CORRUPT/FRAUDULENT/COLLUSIVE/COERCIVE PRACTICES
2. ANNEXURE-II: VENDOR PERFORMANCE EVALUATION
PROCEDURE
3. ANNEXURE-III : ADDENDUM TO INSTRUCTIONS TO BIDDERS
(INSTRUCTION FOR PARTICIPATION IN E-TENDER)
4. ANNEXURE-IV: BIDDING DATA SHEET (BDS)
5. ANNEXURE-V: POLICY FOR PURCHASE PREFERENCE LINKED
WITH LOCAL CONTENT (PP-LC)
‐ 37 ‐
37 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
INSTRUCTIONS TO BIDDERS [ITB]
(TO BE READ IN CONJUNCTION WITH BIDDING DATA SHEET (BDS)
[A] – GENERAL
1 SCOPE OF BID
1.1 The Employer as defined in the "General Conditions of Contract [GCC]", wishes to
receive Bids as described in the Invitation For Bid(the “Tender Document /Bid
Document”)issued by Employer. Employer/Owner/GAIL occurring herein under shall
be considered synonymous.
1.2 SCOPE OF BID: The scope of work/ Services shall be as defined in the Tender
documents.
1.3 The successful bidder will be expected to complete the scope of Bid within the period
stated in Special Conditions of Contract.
1.4 Throughout the Tender Documents, the terms 'Bid', 'Tender'& ‘Offer’ and their
derivatives [Bidder/Tenderer, Bid/Tender/Offer etc.] are synonymous. Further, 'Day'
means 'Calendar Day' and 'Singular' also means 'Plural'.
2 ELIGIBLE BIDDERS
2.1 The Bidder shall not be under a declaration of ineligibility by Employer for Corrupt/
Fraudulent/ Collusive/ Coercive practices, as defined in "Instructions to Bidders [ITB],
Clause No. 39” (Action in case Corrupt/ Fraudulent/ Collusive/ Coercive Practices).
2.2 The Bidder is not put on ‘Holiday’ by GAIL or Public Sector Project Management
Consultant (like EIL, Mecon only due to “poor performance” or “corrupt and fraudulent
practices”) or banned/blacklisted by Government department/ Public Sector on due date
of submission of bid. Further, neither bidder nor their allied agency/(ies) (as defined in
the Procedure for Action in case of Corrupt/ Fraudulent/ Collusive/ Coercive Practices)
are on banning list of GAIL or the Ministry of Petroleum and Natural Gas.
If the bidding documents were issued inadvertently/ downloaded from website, offers
submitted by such bidders shall not be considered for opening/ evaluation/Award and
will be returned immediately to such bidders.
In case there is any change in status of the declaration prior to award of contract, the
same has to be promptly informed to GAIL by the bidder.
It shall be the sole responsibility of the bidder to inform about their status regarding para
1 of clause 2.2 herein above on due date of submission of bid and during the course of
finalization of the tender. Concealment of the facts shall tantamount to misrepresentation
of facts and shall lead to action against such Bidders as per clause 39 of ITB.
2.3 The Bidder should not be under any liquidation court receivership or similar proceedings
on due date of submission of bid. In case there is any change in status of the declaration
prior to award of contract, the same has to be promptly informed to GAIL by the bidder.
It shall be the sole responsibility of the bidder to inform GAIL there status on above on
due date of submission of bid and during the course of finalization of the tender.
Concealment of the facts shall tantamount to misrepresentation of facts and shall lead to
action against such Bidders as per clause no.39 of ITB.
2.4 Bidder shall not be affiliated with a firm or entity:
(i) that has provided consulting services related to the work to the Employer during
the preparatory stages of the work or of the project of which the works/services
forms a part of or
‐ 38 ‐
38 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
(ii) that has been hired (proposed to be hired) by the Employer as an Engineer/
Consultant for the contract.
2.5 Neither the firm/entity appointed as the Project Management Consultant (PMC) for a
contract nor its affiliates/ JV’S/ Subsidiaries shall be allowed to participate in the
tendering process unless it is the sole Licensor/Licensor nominated agent/ vendor.
2.6 Pursuant to qualification criteria set forth in the bidding document, the Bidder shall
furnish all necessary supporting documentary evidence to establish Bidder’s claim of
meeting qualification criteria.
2.7 Power of Attorney:
Power of Attorney (POA) to be issued by the bidder in favour of the authorised
employee(s), in respect of the particular tender, for purpose of signing the documents
including bid, all subsequent communications, agreements, documents etc. pertaining to
the tender and act and take any and all decision on behalf of the bidder (including
Consortium). Any consequence resulting due to such signing shall be binding on the
Bidder (including Consortium).
(I) In case of a Single Bidder, the Power of Attorney shall be issued as per the
constitution of the bidder as below:
a) In case of Proprietorship: by Proprietor
b) In case of Partnership: by all Partners or Managing Partner
c) In case of Limited Liability Partnership: by any bidder’s employee
authorized in terms of Deed of LLP
d) In case of Public / Limited Company: PoA in favour of authorized
employee(s) by Board of Directors through Board Resolution or by the
designated officer authorized by Board to do so. Such Board Resolution
should be duly countersigned by Company Secretary / MD / CMD / CEO.
(II) In case of a Consortium, Power of Attorney shall be issued both by Leader as
well as Consortium Member(s) of the Consortium as per procedure defined herein
above in favour of employee of Leader of Consortium.
The Power of Attorney should be valid till award of contract / order to successful bidder.
2.8 In case of change of constitution of bidder after submission of bid, the same shall be
informed by the bidder to GAIL promptly. Failure to same shall be considered as
misrepresentation by the bidder.
Not Applicable
4 ONE BID PER BIDDER
4.1 A Bidder shall submit only 'one [01] Bid' in the same Bidding Process either as single
entity or as a member of any consortium (wherever consortium bid is allowed). A Bidder
who submits or participates in more than 'one [01] Bid' will cause all the proposals in
which the Bidder has participated to be disqualified.
4.2 More than one bid means bid(s) by bidder(s) having same Proprietor / Partners / Limited
Liability Partner in any other Bidder (s). Further, more than one bids shall also include
two or more bidders having common power of attorney holder.
Failure to comply this clause during tendering process will disqualify all such bidders
from process of evaluation of bids.
4.3 Alternative Bids shall not be considered.
4.4 The provisions mentioned at sl. no. 4.1 and 4.2 shall not be applicable wherein bidders
are quoting for different Items / Sections / Parts / Groups/ SOR/BOQ items of the same
‐ 39 ‐
39 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
tender which specifies evaluation on Items / Sections / Parts / Groups/ SOR/BOQ items
basis.
5 COST OF BIDDING
The Bidder shall bear all costs associated with the preparation and submission of the Bid
including but not limited to Documentation Charges, Bank charges, all courier charges,
translation charges, authentication charges and any associated charges including taxes &
duties thereon. Further, GAIL will in no case, be responsible or liable for these costs,
regardless of the outcome of the bidding process.
6 SITE VISIT
6.1 The Bidder is advised to visit and examine the site of works and its surroundings and
obtain for itself on its own responsibility all information that may be necessary for
preparing the Bid and entering into a Contract for the required job. The costs of visiting
the site shall be borne by the Bidder.
6.2 The Bidder or any of its personnel or agents shall be granted permission by the Employer
to enter upon its premises and land for the purpose of such visits, but only upon the
express conditions that the Bidder, its personnel and agents will release and indemnify
the Employer and its personnel, agents from and against all liabilities in respect thereof,
and will be responsible for death or injury, loss or damage to property, and any other
loss, damage, costs, and expenses incurred as a result of inspection.
6.3 The Bidder shall not be entitled to hold any claim against GAIL for non-compliance due
to lack of any kind of pre-requisite information as it is the sole responsibility of the
Bidder to obtain all the necessary information with regard to site, surrounding, working
conditions, weather etc. on its own before submission of the bid.
*Request for Quotation’, wherever applicable, shall also form part of the Bidding
Document.
**The subject tender is based on standard formats and applicability of some specific clauses
may be seen in Annexure-IV to Section-III i.e. BDS (Bidding Data Sheet).
‐ 40 ‐
40 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
For participation in e-tender, instructions are mentioned at Annexure-III to Section-III.
7.2 The Bidder is expected to examine all instructions, forms, terms & conditions in the
Bidding Documents. The "Request for Quotation [RFQ] &Invitation for Bid (IFB)"
together with all its attachments thereto, shall be considered to be read, understood and
accepted by the Bidders. Failure to furnish all information required by the Bidding
Documents or submission of a Bid not substantially responsive to the Bidding
Documents in every respect will be at Bidder's risk and may result in the rejection of his
Bid.
8 CLARIFICATION OF TENDERDOCUMENTS
8.1 A prospective Bidder requiring any clarification(s) of the Bidding Documents may notify
GAIL in writing by email at GAIL's mailing address indicated in the BDS no later than
02 (two) days prior to pre-bid meeting (in cases where pre-bid meeting is scheduled) or
05 (five) days prior to the due date of submission of bid in cases where pre-bid meeting
is not scheduled. GAIL reserves the right to ignore the bidders request for clarification if
received after the aforesaid period. GAIL may respond in writing to the request for
clarification. GAIL's response including an explanation of the query, but without
identifying the source of the query will be uploaded on GAIL’s tendering web site /
communicated to prospective bidders by e-mail.
8.2 Any clarification or information required by the Bidder but same not received by the
Employer at clause 8.1 (refer BDS for address) above is liable to be considered as "no
clarification / information required".
9.1 At any time prior to the 'Bid Due Date', Employer may, for any reason, whether at its
own initiative or in response to a clarification requested by a prospective Bidder, modify
the Bidding Documents by addenda/ corrigendum.
9.2 Any corrigendum thus issued shall be integral part of the Tender Document and shall be
hosted on the websites as provided at clause no. 2.0 (G) of IFB /communicated to
prospective bidders by e-mail. Bidders have to take into account all such corrigendum
before submitting their Bid.
9.3 The Employer, if consider necessary, may extend the Bid Due Date in order to allow the
Bidders a reasonable time to furnish their most competitive bid taking into account the
addenda/corrigendum issued thereof.
[C] – PREPARATION OF BIDS
10 LANGUAGE OF BID:
The bid prepared by the Bidder and all correspondence, drawing(s), document(s),
certificate(s) etc. relating to the Bid exchanged by Bidder and GAIL shall be written in
English language only. In case a document, certificate, printed literature etc. furnished by
the Bidder in a language other than English, the same should be accompanied by an
English translation duly authenticated by the Indian Chamber of Commerce, in which
case, for the purpose of interpretation of the Bid, the English translation shall govern.
In case the Bids are invited under the Manual two Bid system. The Bid prepared by the
Bidder shall comprise the following components sealed in 2 different envelopes:
‐ 42 ‐
42 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
under the “Schedule of Rates (SOR)/ BOQ” and indicate the discounted unit
rate(s) only.
iii) If any unconditional rebate has been offered in the quoted rate the same shall be
considered in arriving at evaluated price. However no cognizance shall be taken
for any conditional discount for the purpose of evaluation of the bids.
iv) In case, it is observed that any of the bidder(s) has/have offered suo-moto
Discount/Rebate after opening of unpriced bid but before opening of price bids
such discount /rebate(s) shall not be considered for evaluation. However, in the
event of the bidder emerging as the lowest evaluated bidder without considering
the discount/rebate(s), then such discount/rebate(s) offered by the bidder shall be
considered for Award of Work and the same will be conclusive and binding on
the bidder.
v) In the event as a result of techno-commercial discussions or pursuant to seeking
clarifications / confirmations from bidders, while evaluating the un-priced part of
the bid, any of the bidders submits a sealed envelope stating that it contains
revised prices; such bidder(s) will be requested to withdraw the revised prices
failing which the bid will not be considered for further evaluation.
11.1.3 In case of bids invited under Single Bid System (clause no. 2.0(C) of IFB refers), all the
documents as specified at Clause 11.1.1 & 11.1.2 of ITB can be submitted in single
envelope /folder, as per instructions of Tender Document.
11.3 In case of bids invited under single bid system, a single envelope containing all
documents specified at Clause 11.1.1 & 11.1.2 of ITB above form the BID. All
corresponding conditions specified at Clause 11.1.1 & 11.1.2 of ITB shall become
applicable in such a case.
12 BID PRICES
12.1 Unless stated otherwise in the Bidding Documents, the Contract shall be for the whole
works as described in Bidding Documents, based on the rates and prices submitted by
the Bidder and accepted by the Employer. The prices quoted by the Bidders will be
inclusive of all taxes except GST (CGST & SGST/UTGST or IGST).
‐ 43 ‐
43 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
12.2 Prices must be filled in format for "Schedule of Rates [SOR]/ BOQ" enclosed as part of
Tender document. If quoted in separate typed sheets and any variation in item
description, unit or quantity is noticed; the Bid is liable to be rejected.
12.3 Bidder shall quote for all the items of "SOR/ BOQ" after careful analysis of cost
involved for the performance of the completed item considering all parts of the Bidding
Document. In case any activity though specifically not covered in description of item
under "SOR/ BOQ" but is required to complete the works as per Specifications, Scope of
Work / Service, Standards, General Conditions of Contract (“GCC"), Special Conditions
of Contract ("SCC") or any other part of Bidding Document, the prices quoted shall
deemed to be inclusive of cost incurred for such activity.
12.4 All duties, taxes and other levies [if any] payable by the Contractor under the Contract,
or for any other cause except final GST (CGST & SGST/ UTGST or IGST) shall be
included in the rates / prices and the total bid-price submitted by the Bidder.
Bidder shall indicate applicable rate of GST (CGST & SGST/ UTGST or IGST) in
SOR/BOQ.
12.5 Prices quoted by the Bidder, shall remain firm and fixed and valid till completion of the
Contract and will not be subject to variation on any account unless any price
escalation/variation is allowed elsewhere in the Tender Document.
12.6 The Bidder shall quote the prices in 'figures' & words. There should not be any
discrepancy between the prices indicated in figures and the price indicated in words. In
case of any discrepancy, the same shall be dealt as per clause no. 30 of ITB.
12.7 Bidder shall also mention the Service Accounting Codes (SAC) / Harmonized System
of Nomenclature (HSN)at the designated place in SOR/BOQ.
13 GST (CGST & SGST/ UTGST or IGST)
13.1 Bidders are required to submit copy of the GST Registration Certificate while submitting
the bids wherever GST (CGST & SGST/UTGST or IGST) is applicable.
13.2 Quoted prices should be inclusive of all taxes and duties, except GST (CGST & SGST
or IGST or UTGST).Please note that the responsibility of payment of GST (CGST &
SGST or IGST or UTGST) lies with the Contractor only. Contractor providing taxable
service shall issue an e-Invoice/Invoice/Bill, as the case may be as per rules/ regulation
of GST. Further, returns and details required to be filled under GST laws & rules should
be timely filed by Contractor with requisite details.
Payments to Contractor for claiming GST (CGST & SGST/UTGST or IGST) amount
will be made provided the above formalities are fulfilled. Further, GAIL may seek copies
of challan and certificate from Chartered Accountant for deposit of GST (CGST &
SGST/UTGST or IGST) collected from Owner.
13.3 In case CBIC (Central Board of Indirect Taxes and Customs)/ any tax authority / any
equivalent government agency brings to the notice of GAIL that the Contractor has not
remitted the amount towards GST (CGST & SGST/UTGST or IGST) collected from
GAIL to the government exchequer, then, that Contactor shall be put under Holiday list
of GAIL for period of six months after following the due procedure. This action will be
in addition to the right of recovery of financial implication arising on GAIL.
13.4 In case of statutory variation in GST (CGST & SGST/UTGST or IGST), other than
due to change in turnover, payable on the contract value during contract period, the
Contractor shall submit a copy of the 'Government Notification' to evidence the rate as
applicable on the Bid due date and on the date of revision.
Beyond the contract period, in case GAIL is not entitled for input tax credit of GST
(CGST & SGST/UTGST or IGST), then any increase in the rate of GST (CGST &
SGST/UTGST or IGST) beyond the contractual delivery period shall be to
‐ 44 ‐
44 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Contractor’s account whereas any decrease in the rate GST (CGST & SGST/UTGST
or IGST) shall be passed on to the Owner.
Beyond the contract period, in case GAIL is entitled for input tax credit of GST (CGST
& SGST/UTGST or IGST), then statutory variation in quotedGST (CGST &
SGST/UTGST or IGST) on supply and on incidental services, shall be to GAIL’s
account.
Claim for payment of GST (CGST & SGST/UTGST or IGST)/ Statutory variation,
should be raised within two [02] months from the date of issue of 'Government
Notification' for payment of differential (in %) GST (CGST & SGST/UTGST or
IGST), otherwise claim in respect of above shall not be entertained for payment of
arrears.
The base date for the purpose of applying statutory variation shall be the Bid Due Date.
13.5 Where GAIL is entitled to avail the input tax credit of GST (CGST & SGST/UTGST
or IGST):-
13.5.1 Owner/GAIL will reimburse the GST (CGST & SGST/UTGST or IGST) to the
Contractor at actuals against submission of E-Invoices/Invoices as per format specified
in rules/ regulation of GST to enable Owner/GAIL to claim input tax credit of GST
(CGST & SGST/UTGST or IGST) paid. In case of any variation in the executed
quantities, the amount on which the GST (CGST & SGST/UTGST or IGST) is
applicable shall be modified in same proportion. Returns and details required to be filled
under GST laws & rules should be timely filed by supplier with requisite details.
13.5.2 The input tax credit of quoted GST (CGST & SGST/UTGST or IGST) shall be
considered for evaluation of bids, as per evaluation criteria of tender document.
13.6 Where GAIL is not entitled to avail/take the full input tax credit of GST (CGST &
SGST/UTGST or IGST):-
13.6.1 Owner/GAIL will reimburse GST (CGST & SGST/UTGST or IGST) to the Contractor
at actuals against submission of E-Invoices/Invoices as per format specified in rules/
regulation of GST subject to the ceiling amount of GST (CGST & SGST/UTGST or
IGST) as quoted by the bidder, subject to any statutory variations, except variations
arising due to change in turnover. In case of any variation in the executed quantities (If
directed and/or certified by the Engineer-In-Charge) the ceiling amount on which GST
(CGST & SGST/UTGST or IGST) is applicable will be modified on pro-rata basis.
13.6.2 The bids will be evaluated based on total price including quotedGST (CGST &
SGST/UTGST or IGST).
13.7 GAIL will prefer to deal with registered supplier of goods/ services under GST.
Therefore, bidders are requested to get themselves registered under GST, it not registered
yet.
However, in case any unregistered bidder is submitting their bid, their prices will be
loaded with applicable GST (CGST & SGST/UTGST or IGST) while evaluation of
bid (if applicable as per Govt. Act/ Law in vogue). Where GAIL is entitled for input
credit of GST (CGST & SGST/UTGST or IGST), the same will be considered for
evaluation of bid as per evaluation methodology of tender document.Further, an
unregistered bidder is required to mention its Income Tax PAN in bid document.
13.8 In case GAIL is required to pay entire/certain portion of applicableGST (CGST &
SGST/UTGST or IGST) and remaining portion, if any, is to be deposited by Bidder
directly as per GST (CGST & SGST/UTGST or IGST) laws, entire applicable
rate/amount of GST (CGST & SGST/UTGST or IGST) to be indicated by bidder in
the SOR/BOQ.
Where GAIL has the obligation to discharge GST (CGST & SGST/UTGST or IGST)
liability under reverse charge mechanism and GAIL has paid or is /liable to pay GST
(CGST & SGST/UTGST or IGST) to the Government on which interest or penalties
‐ 45 ‐
45 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
becomes payable as per GST laws for any reason which is not attributable to GAIL or
ITC with respect to such payments is not available to GAIL for any reason which is not
attributable to GAIL, then GAIL shall be entitled to deduct/ setoff / recover such
amounts against any amounts paid or payable by GAIL to Contractor / Supplier.
13.9 Contractor shall ensure timely submission of correct invoice(s)/e-invoice(s), as per GST
rules/ regulation, with all required supporting document(s) within a period specified in
Contract to enable GAIL to avail input credit of GST (CGST & SGST/UTGST or IGST).
Further, returns and details required to be filled under GST laws & rules should be timely
filed by Contractor with requisite details.
If input tax credit is not available to GAIL for any reason not attributable to GAIL, then
GAIL shall not be obligated or liable to pay or reimburse GST (CGST & SGST/UTGST
or IGST) claimed in the invoice(s) and shall be entitled to deduct / setoff / recover such
GST amount (CGST & SGST/UTGST or IGST) or Input Tax Credit amount together
with penalties and interest, if any, against any amounts paid or becomes payable by
GAIL in future to the Contractor under this contract or under any other contract.
13.10 Anti-profiteering clause
As per Clause 171 of GST Act it is mandatory to pass on the benefit due to reduction in
rate of tax or from input tax credit to the consumer by way of commensurate reduction in
prices. The Contractor may note the above and quote their prices accordingly.
13.11 In case the GST rating of contractor on the GST portal / Govt. official website is negative
/ black listed, then the bids may be rejected by GAIL. Further, in case rating of bidder is
negative / black listed after award of work, then GAIL shall not be obligated or liable to
pay or reimburse GST to such vendor and shall also be entitled to deduct / recover such
GST along with all penalties / interest, if any, incurred by GAIL.
13.12 GST (CGST & SGST/UTGST or IGST) is implemented w.e.f. 01.07.2017 which
subsumed various indirect taxes and duties applicable before 01.07.2017. Accordingly,
the provisions of General Condition of Contract relating to taxes and duties which are
subsumed in GST are modified to aforesaid provisions mentioned in clause no. 12 and 13
of ITB.
13.13 GST, as quoted by the bidder in Schedule of Rates/BOQ, shall be deemed as final and
binding for the purpose of bid evaluation (applicable for tenders where bidder quotes the
GST rates). In case a bidder enters “zero/blank” GST or an erroneous GST, the bid
evaluation for finalizing the L1 bidder will be done considering the “Zero” or quoted
GST rate, as the case may be. No request for change in GST will be entertained after
submission of bids.
In cases where the successful bidder quotes a wrong GST rate, for releasing the order, the
following methodology will be followed:
In case the actual GST rate applicable is lower than the quoted GST rate, the
actual GST rate will be added to the quoted basic prices. The final cash outflow
will be based on actual GST rate.
In case the actual GST rate applicable is more than the quoted GST rate, the basic
prices quoted will be reduced proportionately, keeping the final cash outflow the
same as the overall quoted amount.
Based on the Total Cash Outflow calculated as above, GAIL shall place orders.
13.14 Wherever TDS under GST Laws has been deducted from the invoices raised / payments
made to the Contractors, as per the provisions of the GST law / Rules, Contractors should
accept the corresponding GST-TDS amount populated in the relevant screen on GST
common portal (www.gst.gov.in). Further, Vendors should also download the GST TDS
certificate from GST common portal (reference path: Services > User Services >
View/Download Certificates option).
‐ 46 ‐
46 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
13.15 Provision w.r.t. E- Invoicing requirement as per GST laws:
Supplier who is required to comply with the requirements of E-invoice for B2B
transactions as per the requirement of GST Law will ensure the compliance of
requirement of E Invoicing under GST law. If the invoice issued without following this
process, such invoice can-not be processed for payment by GAIL as no ITC is allowed
on such invoices.
Therefore, all the payments to such supplier who is liable to comply with e-invoice as per
GST Laws shall be made against the proper e-invoice(s) only. Further, returns and details
required to be filled under GST laws & rules against such e-invoices should be timely
filed by Supplier of Goods with requisite details.
If input tax credit is not available to GAIL for any reason attributable to supplier (both
for E-invoicing cases and non-E-invoicing cases), then GAIL shall not be obligated or
liable to pay or reimburse GST (CGST & SGST/UTGST or IGST) claimed in the
invoice(s) and shall be entitled to deduct / setoff / recover such GST amount (CGST &
SGST/UTGST or IGST) or Input Tax Credit amount together with penalties and interest,
if any, by adjusting against any amounts paid or becomes payable in future to the
supplier under this contract or under any other contract.
13.16 New Taxes & duties: Any new taxes & duties, if imposed by the State/ Central Govt. of
India after the due date of bid submission but before the Contractual Completion Date,
shall be reimbursed to the Service Provider on submission of copy of notification(s)
issued from State/ Central Govt. Authorities along with documentary evidence for proof
of payment of such taxes & duties, but only after ascertaining it’s applicability with
respect to the Contract.
13.17 Full payment including GST will be released at the time of processing of invoice for
payment, where the GST amount reflects in Form GSTR-2A of GAIL. However, in
case where the GST amount doesn’t reflect in Form GSTR-2A of GAIL, the amount of
GST will be released after reflection of GST amount of corresponding invoice in Form
GSTR-2A of GAIL.
14 BID CURRENCIES:
15 BID VALIDITY
15.1 Bids shall be kept valid for period specified in BDS from the final Due date of
submission of bid'. A Bid valid for a shorter period may be rejected by GAIL as 'non-
responsive'.
15.2 In exceptional circumstances, prior to expiry of the original 'Bid Validity Period', the
Employer may request the Bidders to extend the 'Period of Bid Validity' for a specified
additional period. The request and the responses thereto shall be made in writing or by
email. A Bidder may refuse the request without forfeiture of his EMD / Bid Security.
A Bidder agreeing to the request will not be required or permitted to modify his Bid, but
will be required to extend the validity of its EMD for the period of the extension and in
accordance with "ITB: Clause-16" in all respects.
‐ 47 ‐
47 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
16 EARNEST MONEY DEPOSIT
DELETED
17.1 The Bidder(s) or his designated representative are invited to attend a "Pre-Bid Meeting"
which will be held at address specified in IFB. It is expected that a bidder shall not
depute more than 02 representatives for the meeting.
17.2 Purpose of the meeting will be to clarify issues and to answer questions on any matter
that may be raised at that stage and give hands-on e-tendering.
17.3 Text of the questions raised and the responses given, together with any responses
prepared after the meeting, will be uploaded on Govt. CPP Portal against the Tender as
specified in "ITB: Clause-8. Any modification of the Contents of Bidding Documents
listed in "ITB: Clause-7.1", that may become necessary as a result of the Pre-Bid
Meeting shall be made by the Employer exclusively through the issue of an Corrigendum
pursuant to "ITB: Clause-9", and not through the minutes of the Pre-Bid Meeting.
17.4 Non-attendance of the Pre-Bid Meeting will not be a cause for disqualification of Bidder.
18.1 The original and all copies of the Bid shall be typed or written in indelible ink [in the
case of copies, photocopies are also acceptable] and shall be signed by a person or
persons duly authorized to sign on behalf of the Bidder (as per POA). The name and
position held by each person signing, must be typed or printed below the signature. All
pages of the Bid except for unamendable printed literature where entry(s) or
amendment(s) have been made shall be initialed by the person or persons signing the
Bid.
18.2 The Bid shall contain no alterations, omissions, or additions, unless such corrections are
initialed by the person or persons signing the Bid.
18.3 In case of e-tendering, digitally signed documents to be uploaded as detailed in
addendum to ITB (Annexure-III to Section III).
19.1 ZERO DEVIATION: Deviation to terms and conditions of "Bidding Documents" may
lead to rejection of bid. GAIL will accept bids based on terms & conditions of "Bidding
Documents" only. Bidder may note GAIL will determine the substantial responsiveness
of each bid to the Bidding Documents pursuant to provision contained in clause 29 of
ITB. For purpose of this, a substantially responsive bid is one which conforms to all
terms and conditions of the Bidding Documents without deviations or reservations.
GAIL's determination of a bid's responsiveness is based on the content of the bid itself
without recourse to extrinsic evidence. GAIL reserves the right to raise technical and/or
commercial query(s), if required, may be raised on the bidder(s). The response(s) to the
same shall be in writing, and no change in the price(s) or substance of the bids shall be
‐ 48 ‐
48 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
sought, offered or permitted. The substance of the bid includes but not limited to prices,
completion, scope, technical specifications, etc. Bidders are requested to not to take any
deviation/exception to the terms and conditions laid down in this "Tender Documents",
and submit all requisite documents as mentioned in this "Tender Documents", failing
which their offer will be liable for rejection. If a bidder does not reply to the queries in
the permitted time frame then its bid shall be evaluated based on the documents
available in the bid.
20 E-PAYMENT
21.1 In case of e-tendering, bids shall be submitted through e-tender mode in the manner
specified elsewhere in tender document. No Manual/ Hard Copy (Original) offer shall
be acceptable. Physical documents shall be addressed to the owner at address specified
in IFB.
21.2 In case of manual tendering bid must be submitted in sealed envelope. If the envelope is
not sealed & marked as per Clause No. 11 of ITB, the employer will assume no
responsibility for misplacement or pre-mature opening of the bid.
21.3 All the bids shall be addressed to the owner at address specified in IFB.
21.4 Bids submitted under the name of AGENT/REPRESENTATIVE/
RETAINER/ASSOCIATE etc. on behalf of a bidder/affiliate shall not be accepted.
22.1 In case of e-bidding, the bids must be submitted through e-tender mode not later than the
date and time specified in the tender documents/BDS.
‐ 49 ‐
49 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
22.2 In case of manual tendering EMD along with bid must be submitted within the due date
& time, as specified in Clause no. 2.0 (I) of IFB and place mentioned in BDS.
22.3 GAIL may, in exceptional circumstances and at its discretion, extend the deadline for
submission of Bids (8.0 and/or 9 of ITB refers). In which case all rights and obligations
of GAIL and the Bidders, previously subject to the original deadline will thereafter be
subject to the deadline as extended. Notice for extension of due date of submission of bid
will be uploaded on Govt. CPP Portal, GAIL’s website/ communicated to the bidders.
23 LATE BIDS
23.1 Any bids received after the notified date and time of closing of tenders will be treated as
late bids.
23.2 In case of e-tendering, e-tendering system of GAIL shall close immediately after the due
date for submission of bid and no bids can be submitted thereafter.
In case of manual tendering, bids received by GAIL after the due date for submission of
bids shall not be considered. Such late bids shall be returned to the bidder within “10
days” in ‘unopened conditions’.
23.3 Physical documents received to address other than one specifically stipulated in the
Tender Document will not be considered for evaluation/opening/award if not received to
the specified destination within stipulated date & time.
2.3.4 Unsolicited Bids or Bids received to address other than one specifically stipulated in the
tender document will not be considered for evaluation/opening/award if not received to
the specified destination within stipulated date & time.
The bidder may withdraw or modify its bid after bid submission but before the due date
and time for submission as per tender document.
The bidder may withdraw or modify its bid after bid submission but before the due date
for submission as per tender document provided that the written notice of the
modification/ substitution/ withdrawal in received by GAIL prior to the deadline for
submission of bid.
24.2 The modification shall also be prepared, sealed, marked and dispatched in accordance
with the provisions of the clause 11, 21 & 22 of ITB with relevant ‘Cut-Out Slip’ duly
pasted and mentioning on top of the envelope as “MODIFICATION”. In case of
withdrawal of bid, the Envelope containing withdrawal letter duly superscribing the
envelope as “WITHDRAWAL” and “Tender Document number :….”/ communication
regarding withdrawal of bid with “Tender Document number :….”/ must reach
concerned dealing official of GAIL within Due date & Time of submission of Bid. No
bid shall be modified/ withdrawn after the Due Date & Time for Bid submission.
24.3 Any withdrawal/ modification/substitution of Bid in the interval between the Due Date
& Time for Bid submission and the expiration of the period of bid validity specified by
the Bidder in their Bid shall result in the Bidder’s invocation of action as per Bid
Security declaration and rejection of Bid.
‐ 50 ‐
50 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
24.4 The latest Bid submitted by the Bidder before Bid Due Date & Time shall be considered
for evaluation and all other Bid(s) shall be considered to be unconditionally withdrawn.
GAIL reserves the right to accept or reject any Bid, and to annul the Bidding process and
reject all Bids, at any time prior to award of Contract, without thereby incurring any
liability to the affected Bidder or Bidders or any obligations to inform the affected
Bidder or Bidders of the ground for GAIL's action. However, Bidder if so desire may
seek the reason (in writing) for rejection of their Bid to which GAIL shall respond
quickly.
26 BID OPENING
27 CONFIDENTIALITY
28.1 From the time of Bid opening to the time of award of Contract, if any Bidder wishes to
contact the Employer on any matter related to the Bid, it should do so in writing.
28.2 Any effort by the Bidder to influence the Employer in the Employer's 'Bid Evaluation',
'Bid Comparison', or 'Contract Award' decisions may result in the rejection of the
Bidder's Bid and action shall be initiated as per procedure for action in case Corrupt /
Fraudulent / Collusive / Coercive practices in this regard, apart from forfeiture of EMD/
Bid Security, if any.
‐ 51 ‐
51 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
29 EXAMINATION OF BIDS AND DETERMINATION OF RESPONSIVENESS
29.1 The employer’s’s determination of a bid’s responsiveness is based on the content of the
bid only. Prior to the detailed evaluation of Bids, the Employer will determine whether
each Bid:-
(a) Meets the "Bid Evaluation Criteria" of the Bidding Documents;
(b) Has been properly signed;
(c) Is accompanied by the required ‘Bid Security Declaration';
(d) Is substantially responsive to the requirements of the Bidding Documents; and
(e) Provides any clarification and/or substantiation that the Employer may require to
determine responsiveness pursuant to "ITB: Clause-29.2"
29.2 A substantially responsive Bid is one which conforms to all the terms, conditions and
specifications of the Bidding Documents without material deviations or reservations or
omissions for this purpose employer defines the foregoing terms below:-
a) “Deviation” is departure from the requirement specified in the tender documents.
b) “Reservation” is the setting of limiting conditions or withholding from complete
acceptance of the requirement in the tender documents.
c) “Omission” is the failure to submit part or all of the information or
documentation required in the tender document for evaluation of bid.
29.3 A material deviation, reservation or omission is one that,
a) If accepted would,
i) Affect in any substantial way the scope, quality, or performance of the job
as specified in tender documents.
ii) Limit, in any substantial way, inconsistent with the Tender Document, the
Employer’s rights or the tenderer’s obligations under the proposed
Contract.
b) If rectified, would unfairly affect the competitive position of other bidders
presenting substantially responsive bids.
29.4 The employer shall examine all aspects of the bid to confirm that all requirements have
been met without any material deviation, reservation or omission.
29.5 If a Bid is not substantially responsive, it may be rejected by the Employer and may not
subsequently be made responsive by correction or withdrawal of the of material
deviation, reservation or omission.
30 CORRECTION OF ERRORS
30.1 Bids determined to be substantially responsive will be checked by the Employer for any
arithmetic errors. Errors in Price Schedule/Schedule of Rates (SOR)/BOQ will be
corrected by the Employer as follows:
(i) Deleted
(ii) Deleted
(iii) Deleted.
(iv) In case any bidder does not quote for any item(s) of “Schedule of Rates/ BOQ”
and the estimated price impact is more than 10% of the quoted price, then the bid
will be rejected. If such price impact of unquoted items is 10% or less of his
quoted price, then the unquoted item(s) shall be loaded highest of the price
quoted by the other bidders . If such bidder happens to be lowest evaluated
bidder, price of unquoted items shall be considered as included in the quoted bid
price.
‐ 52 ‐
52 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
30.2 The amount stated in the bid will be adjusted by the Employer in accordance with the
above procedure for the correction of errors. If the bidder does not accept the corrected
amount of bid, its bid will be rejected, and the actions shall be invoked as per
Declaration for Bid Security.
Not Applicable. All bids submitted must be in the currency specified at clause 14 of ITB.
33.1 In the event of the time of completions of work getting delayed beyond the time schedule
indicated in the bidding document plus a grace period equivalent to 1/5th of the time
schedule or 2 months whichever is more, due to reasons solely attributable to Employer,
the Contractor shall be paid compensation for extended stay (ESC) to maintain necessary
organizational set up and construction tools, tackles, equipment etc. at site of work
maximum period 01(one) month.
33.2 The bidder is required to specify the rate for ESC on per month basis in the “PRICE
PART” of his bid, which shall be considered for loading on total quoted price during
price bid evaluation. The loading shall be done of a period of 1/5th of the time schedule
or 1 month whichever is less. In case bidder does not indicate the rate for ESC in price
part of his bid, it will be presumed that no ESC is required by the bidder and evaluation
shall be carried out accordingly.
34 PURCHASE PREFERENCE
35 AWARD
‐ 53 ‐
53 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Subject to "ITB: Clause-29", GAIL will award the Contract to the successful Bidder
whose Bid has been determined to be substantially responsive and has been determined
as the lowest provided that bidder, is determined to be qualified to satisfactorily perform
the Contract.
“GAIL intent to place the contract directly on the address from where Goods are
produced/dispatched or Services are rendered. In case, bidder wants contract at some
other address or supply of Goods/ Services from multiple locations, bidder is required
to provide in their bid address on which order is to be placed”.
GAIL will place the Contract directly on the successful bidder from whom the bid has
been received & evaluated and will not place order on other entities such as subsidiary,
business associate or partner, dealer/distributor etc. of the Bidder.
36.1 Prior to the expiry of ‘Period of Bid Validity’, Notification of Award for acceptance of
the Bid will be intimated to the successful Bidder by GAIL either byE - mail /Letter or
like means defined as the “Fax of Acceptance (FOA)”. The Contract shall enter into
force on the date of FOA and the same shall be binding on GAIL and successful Bidder
(i.e. Contractor). The Notification of Award/FOA will constitute the formation of a
Contract. The detailed Letter of Acceptance shall be issued thereafter incorporating
terms & conditions of Tender Document, Corrigendum, Clarification(s), Bid and agreed
variation(s)/acceptable deviation(s), if any. GAIL may choose to issue Notification of
Award in form of detailed Letter of Acceptance without issuing FOA and in such case
the Contract shall enter into force on the date of detailed Letter of Acceptance only.
36.2 Contract period shall commence from the date of "Notification of Award" or as
mentioned in the Notification of Award. The "Notification of Award" will constitute the
formation of a Contract, until the Contract has been effected pursuant to signing of
Contract Agreement as per "ITB: Clause-37".
36.3 Upon the successful Bidder's / Contractor's furnishing of 'Contract Performance Security
/ Security Deposit', pursuant to "ITB: Clause-38", GAIL will promptly discharge his
'Earnest Money Deposit / Bid Security', pursuant to "ITB: Clause-16"
36.4 The Order/ contract value mentioned above is subject to Price Reduction Schedule
clause.
36.5 GAIL will award the Contract to the successful Bidder, who, within 'fifteen [15] days' of
receipt of the same, shall sign and return the acknowledged copy to GAIL.
37 SIGNING OF AGREEMENT
‐ 54 ‐
54 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
38.1 Within 30 days of the receipt of the notification of award/ Fax of Acceptance from
GAIL, the successful bidder shall furnish the Contract Performance Security (CPS) in
accordance with of General Conditions of the Contract. The CPS shall be in the form of
either Banker’s Cheque or Demand Draft or Bank Guarantee or Letter of Credit and shall
be in the currency of the Contract. However, CPS shall not be applicable in cases
wherein the individual contract value as specified in Notification of Award is less than
INR 5 Lakh (exclusive of GST).
38.2 The contract performance security shall be for an amount equal to specified in Bidding
Data Sheet (BDS)towards faithful performance of the contractual obligations and
performance of equipment. For the purpose of CPS, Contract/order value shall be
exclusive of GST (CGST & SGST/UTGST or IGST).
Bank Guarantee towards CPS shall be from any Indian scheduled bank or a branch of an
International bank situated in India and registered with Reserve bank of India as
scheduled foreign bank. However, in case of bank guarantees from banks other than the
Nationalized Indian banks, the bank must be a commercial bank having net worth in
excess of Rs 100 crores and a declaration to this effect should be made by such
commercial bank either in the Bank Guarantee itself or separately on its letterhead.
38.3 Failure of the successful bidder to comply with the requirements of this article shall
constitute sufficient grounds for consideration of the annulment of the award and action
as per declaration for Bid Security.
38.4 The CPS has to cover the entire contract value including extra works/services also. As
long as the CPS submitted at the time of award take cares the extra works/ services
executed and total executed value are within the awarded contract price, there is no need
for additional CPS. As soon as the total executed value is likely to burst the ceiling of
awarded contract price, the contractor should furnish additional CPS.
38.5 Further, Ministry of Finance (MOF) Department of financial service has issued direction
for submission of Bank Guarantee through online vide letter ref number
F.No.7/112/2011-BOA dated 17th July 2012. The successful bidder can submit CPS
online through issuing bank to GAIL directly as per the above direction including its
revisions, if any. In such cases confirmation will not be sought from issuing banker by
GAIL.
38.6 In addition to existing specified form (i.e. Demand Draft (DD)/ Banker’s Cheque/ Bank
Guarantee/Letter of Credit) mentioned in tender documents for submission of Security
Deposit/ Contract Performance Security, the successful bidder can also submit the
Security Deposit/ Contract Performance Securitythrough online banking transaction i.e.
IMPS/NEFT/RTGS/SWIFT etc.For this purpose, the details of GAIL’s Bank Account is
mentioned in BDS. Further, in case a successful Bidder is willing to furnish CPS through
SWIFT, the details may be obtained from Purchase Officer immediately after receipt of
FOA.
While remitting such online transaction, the bidder must indicate “Security Deposit/
Contract Performance Security against FOA/DLOA no. _______(contractor to
specify the FOA/DLOA No.)” under remarks column of such transaction of respective
bank portal. The contractor/vendor shall be required to submit the successful transaction
details to the dealing officer immediately through email/letter and necessarily within 30
days from the date of Fax of Acceptance.
38.7 In case of forfeiture of Contract Performance Security/ Security Deposit in terms of
GCC, the forfeited amount will be considered inclusive of tax and tax invoice will be
issued by GAIL. The forfeiture amount will be subject to final decision of GAIL based
on other terms and conditions of order/ contract.
‐ 55 ‐
55 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
38.8 The Contractor will also submit covering letter along with CPS as per format at F-4.
38.9 CPBG/Security Deposit will not be accepted in case the same has reference of
‘remitter’/’financer’ other than bidder on the aforementioned financial instrument of
CPBG/ Security Deposit submitted by the Contractor.
The Contractor/ Bidder understands and agrees that in such cases where Contractor/
Bidder has been banned (in terms of aforesaid procedure) from the date of issuance of
such order by GAIL (India) Limited, such decision of GAIL (India) Limited shall be
final and binding on such Contractor/ Bidder and the ‘Arbitration clause’ in the GCC and
other "CONTRACT DOCUMENTS" shall not be applicable for any consequential issue
/dispute arising in the matter.
40.1 Government of India, vide Gazette of India No. 503 dated 26.03.2012 proclaimed the
Public Procurement Policy for Micro and Small Enterprises (MSEs). The following
benefit is available in case of work contract also:
i) Issue of tender document to MSEs free of cost.
ii) Exemption to MSEs from payment of EMD/Bid Security.
40.2 In case bidder is a Micro or Small Enterprise, the bidder shall submit the following :
(i) Ministry of MSME vide Gazette notification no. CG-DL-E-26062020-220191
dated 26.06.2020 had notified certain criteria for classifying the enterprises as
Micro, Small and Medium Enterprises and specified form and procedure for filing
the memorandum (Udyam Registration) w.e.f. 01.07.2020 (for complete details
of policy refer website of Ministry of MSME i.e. https://msme.gov.in/).
Accordingly, Micro and Small Enterprises (MSEs) shall be required to submit
Udyam Registration Certificate for availing benefit under Public Procurement
Policy for MSEs-2012
(ii) An enterprise registered prior to 30.06.2020 and who is not re-registered
with Udyam Registration, shall continue to be valid for a period upto 31.12.2021.
‐ 56 ‐
56 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Such enterprise shall submit EM Part-II or Udyog Aadhaar Memorandum (UAM)
for availing benefits of PPP-2012.
The above documents submitted by the bidder shall be duly certified by the Chartered
Accountant (not being an employee or a Director or not having any interest in the
bidder’s company/firm) and notary public with legible stamp.
If the bidder does not provide the above confirmation or appropriate document or any
evidence, then it will be presumed that they do not qualify for any preference admissible
in the Public Procurement Policy (PPP) 2012.
Further, MSEs who are availing the benfits of the Public Procurement Policy (PPP) 2012
get themselves registered with MSME Data Bank being operated by NSIC, under SME
Division, M/o MSME, in order to create proper data base of MSEs which are making
supplies to CPSUs.
40.3 If against an order placed by GAIL, successful bidder(s) (other than Micro/Small
Enterprise) is procuring material/services from their sub-vendor who is a Micro or Small
Enterprise as per provision mentioned at clause no.40.2 with prior consent in writing of
the purchasing authority/Engineer-in-charge, the details like Name, Registration No.,
Address, Contact No. details of material & value of procurement made, etc. of such
Enterprises shall be furnished by the successful bidder at the time of submission of
invoice/Bill.
40.4 The benefit of policy are not extended to the traders/dealers/
Distributors/Stockiest/Wholesalers.
40.5 NSIC has initiated a scheme of “Consortia and Tender Marketing Scheme” under which
they are assisting the Micro & Small enterprises to market their products and services
through tender participation on behalf of the individual unit or through consortia.
Accordingly, if the MSEs or the consortia, on whose behalf the bid is submitted by
NSIC, is meeting the BEC and other terms and conditions of tender their bid will be
considered for further evaluation.
Further, in such cases a declaration is to be submitted by MSE/ consortia on their letter
head (s) that all the terms and conditions of tender document shall be acceptable to them.
40.6 It may be noted that Government of India has implemented Trade Receivable
Discounting System (TReDS) to address challenges faced by MSMEs in delayed
payments (after receipt/acceptance of Material/Services) from Government buyers
leading to shortfall of Working Capital. TReDS is an online electronic institutional
mechanism for facilitating the financing of trade receivables of MSMEs through multiple
financiers. GAIL is already registered on the following TReDS platform:
M/s Receivable Exchange of India (RXIL), Mumbai
M/s Mynd Solutions Private Limited (Mynd), New Delhi
M/s A. TREDS (Invoicemart), Mumbai
MSME Bidders are required to register on the TReDS platform. The MSME vendors can
avail the TReDS facility, if they want to.
40.7 Interest payment on delayed payments to MSME is payable in line with Micro, Small
and Medium Enterprises Development Act, 2006
41 AHR ITEMS
In item rate contract where the quoted rates for the items exceed 50% of the estimate
rates, such items will be considered as Abnormally High Rates (AHR) items and
‐ 57 ‐
57 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
payment of AHR items beyond the SOR/BOQ stipulated quantities shall be made at the
lowest amongst the following rates:
I) Rates as per SOR/BOQ, quoted by the Contractor.
II) Rate of the item, which shall be derived as follows:
a. Based on rates of Machine and labour as available from the contract
(which includes contractor’s supervision, profit, overheads and other
expenses).
b. In case rates are not available in the contract, rates will be calculated
based on prevailing market rates of machine, material and labour plus
15% to cover contractor’s supervision profit, overhead & other expenses.
43.1 Income tax deduction shall be made from all payments made to the contractor as per the
rules and regulations in force and in accordance with the Income Tax Act prevailing from
time to time.
43.2 Corporate Tax liability, if any, shall be to the contractor’s account.
43.3 TDS
As per Section 206AB of Income Tax Act, 1961, in case of any vendor/customer
who does not filed their Income Tax Return for both of the two previous years
preceding to current year and aggregate amount of TDS is more than or equal to
50,000/- in each of those previous two years (or limit defined by Govt. from time
to time), then TDS will be deducted at the higher of following rates:
(I) Twice the rate mentioned in relevant TDS section.
(II) Twice the rate or rates in force
(III) 5%
‐ 58 ‐
58 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
During execution of orders, various issues may arise. In order to timely detect and to
address the contractual issue(s) during the execution of contracts, GAIL has introduced a
mechanism of Quarterly Closure of the contract, under which all the related issues
/disputes will be monitored and addressed on quarterly basis for resolution. Vendor
(hereinafter referred ‘Vendor’)should first refer any issues/disputes to Engineer-in-
Charge(EIC) for LOA/contracts/ Dealing C&P Executive for Purchase Orders and co-
operate them for smooth execution of the contract and to timely address the issues, if
any.For applicability of ‘Quarterly Closure’, please refer BDS.
In case issue is not resolved by above, Supplier may submit their issue(s) to Vendor
Grievance Portal “Samadhan”, which will be addressed by GAIL within 15 days. The
Samadhan Portal is available at https://gailebank.gail.co.in/grievance/welcome.aspx .
Accordingly, the methodology for resolution of issue(s)/ grievance (s) of
Vendor/Supplier shall be as under:
(i) Any issue should be first referred to EIC for LOA/contracts/ Dealing C&P
Executive for Purchase Orders.
(ii) In case issue is not resolved, Vendor may submit their issue/ grievance through
online Vendor Grievance Portal-“Samadhan”.
(iii) In case, Vendor is not satisfied, there is a provision of escalation of issue to higher
authority in GAIL. This option is available two times to vendor.
(iv) Further, issue(s) can only be submitted upto 1 month after closure of respective
Contract.
(v) Vendor should refer their issue/ grievance through above mode only. Issue/
grievance received through any other mode shall not be entertained.
1.0 CONCILIATION
GAIL (India) Limited has framed the Conciliation Rules 2010 in conformity with Part –
III of the Arbitration and Conciliation Act 1996 as amended from time to time for
speedier, cost effective and amicable settlement of disputes through conciliation. All
issue(s)/dispute(s) arising under the Contract, which cannot be mutually resolved within
a reasonable time, may be referred for conciliation in accordance with GAIL
Conciliation Rules 2010 as amended from time to time A copy of the said rules have
been made available on GAIL’s web site i.e www.gailonline.com.
Where invitation for Conciliation has been accepted by the other party, the Parties shall
attempt to settle such dispute(s) amicably under Part-III of the Arbitration and
Conciliation Act, 1996 and GAIL (India) Limited Conciliation Rules, 2010. It would be
only after exhausting the option of Conciliation as an Alternate Dispute Resolution
Mechanism that the Parties hereto shall invoke Arbitration Clause. For the purpose of
this clause, the option of ‘Conciliation’ shall be deemed to have been exhausted, even in
case of rejection of ‘Conciliation’ by any of the Parties.
2.0 ARBITRATION
All issue(s)/dispute(s) excluding the matters that have been specified as excepted
matters and listed at clause no. 2.6 and which cannot be resolved through Conciliation,
such issue(s)/dispute(s) shall be referred to arbitration for adjudication by Sole
Arbitrator.
‐ 59 ‐
59 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
The party invoking the Arbitration shall have the option to either opt for Ad-hoc
Arbitration as provided at Clause 2.1 below or Institutionalized Arbitration as provided
at Clause 2.2 below, the remaining clauses from 2.3 to 2.7 shall apply to both Ad-hoc
and Institutional Arbitration:-
2.1 On invocation of the Arbitration clause by either party, GAIL shall suggest a
panel of three independent and distinguished persons (Retd Supreme Court &
High Court Judges only) to the other party from the Panel of Arbitrators
maintained by ‘Delhi International Arbitration Centre (DIAC) to select any one
among them to act as the Sole Arbitrator. In the event of failure of the other party
to select the Sole Arbitrator within 30 days from the receipt of the communication
from GAIL suggesting the panel of arbitrators, the right of selection of the sole
arbitrator by the other party shall stand forfeited and GAIL shall appoint the Sole
Arbitrator from the suggested panel of three Arbitrators for adjudication of
dispute(s). The decision of GAIL on the appointment of the sole arbitrator shall
be final and binding on the other party. The fees payable to Sole Arbitrator shall
be governed by the fee Schedule of ‘‘Delhi International Arbitration Centre’.
OR
2.2 If a dispute arises out of or in connection with this contract, the party invoking the
Arbitration shall submit that dispute to any one of the Arbitral Institutions i.e
ICADR/ICA/DIAC/SFCA and that dispute shall be adjudicated in accordance
with their respective Arbitration Rules. The matter shall be adjudicated by a Sole
Arbitrator who shall necessarily be a Retd Supreme Court/High Court Judge to be
appointed/nominated by the respective institution. The cost/expenses pertaining
to the said Arbitration shall also be governed in accordance with the Rules of the
respective Arbitral Institution. The decision of the party invoking the Arbitration
for reference of dispute to a specific Arbitral institution for adjudication of that
dispute shall be final and binding on both the parties and shall not be subject to
any change thereafter. The institution once selected at the time of invocation of
dispute shall remain unchanged.
2.3 The cost of arbitration proceedings shall be shared equally by the parties.
2.4 The Arbitration proceedings shall be in English language and the seat, venue and
place of Arbitration shall be New Delhi, India only.
2.5 Subject to the above, the provisions of Arbitration & Conciliation Act 1996 and
any amendment thereof shall be applicable. All matter relating to this Contract
and arising out of invocation of Arbitration clause are subject to the exclusive
jurisdiction of the Court(s) situated at New Delhi.
2.6 List of Excepted matters:
a) Dispute(s)/issue(s) involving claims below Rs 25 lakhs and above Rs 25
crores.
b) Dispute(s)/issue(s) relating to indulgence of Contractor/Vendor/Bidder in
corrupt/fraudulent/collusive/coercive practices and/or the same is under
investigation by CBI or Vigilance or any other investigating agency or
Government.
c) Dispute(s)/issue(s) wherein the decision of Engineer-In-
Charge/owner/GAIL has been made final and binding in terms of the
Contract.
2.7. Disputes involving claims below Rs 25 Lakhs and above Rs. 25 crores:- Parties
mutually agree that dispute(s)/issue(s) involving claims below Rs 25 Lakhs and
‐ 60 ‐
60 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
above Rs 25 crores shall not be subject matter of Arbitration and are subject to
the exclusive jurisdiction of the Court(s) situated at New Delhi.
3. GOVERNING LAW AND JURISDICTION:
The Contract shall be governed by and construed in accordance with the laws in
force in India. The Parties hereby submit to the exclusive jurisdiction of the
Courts situated at New Delhi for adjudication of disputes, injunctive reliefs,
actions and proceedings, if any, arising out of this Contract.
INAM-Pro (Platform for infrastructure and materials providers) is a web based platform
for infrastructure provides and materials suppliers and was developed by Ministry of
Road Transport and Highways (MoRT&H) with a view to reduce project execution
delays on account of supply shortages and inspire greater confidence in contractors to
procure cement to start with directly from the manufacturers. Presently, numerous
cement companies are registered in the portal and offering cement for sale on the portal
with a commitment period of 3 years. These companies have bound themselves by
ceiling rates for the entire commitment period, wherein they are allowed to reduce or
increase their cement rates any number of times within the ceiling rate, but are not
permitted to exceed the said ceiling rate.
MoRT&H is expanding the reach of this web-portal by increasing both the product width
as well as the product depth. They are working on incorporating 60 plus product
categories. The product range will span from large machineries like Earth Movers and
Concrete Mixers, to even the smallest items like road studs. MoRT&H intend to turn it
into a portal which services every infrastructure development related need of a modern
contractor.
GAIL’s contractors may use this innovative platform, wherever applicable. The usage of
web – Portal is a completely voluntary exercise. The platform, however, can serve as a
benchmark for comparison of offered prices and products.
‐ 61 ‐
61 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
47 PROMOTION OF PAYMENT THROUGH CARDS AND DIGITAL MEANS
While engaging the contractual manpower, Contractors are required to make efforts to
provide opportunity of employment to the people belonging to Scheduled Castes and
weaker sections of the society also in order to have a fair representation of these
sections.
Not Applicable
PRS is the reduction in the consideration / contract value for the services covered under
this contract. In case of delay in execution of contract, service provider should raise
invoice for reduced value as per Price Reduction Schedule Clause (PRS clause). If
service provider has raised the invoice for full value, then service provider should issue
Credit Note towards the applicable PRS amount with applicable taxes.
In such cases if service provider fails to submit the invoice with reduced value or does
not issue credit note as mentioned above, GAIL will release the payment to service
provider after giving effect of the PRS clause with corresponding reduction of taxes
charged on service provider’s invoice, to avoid delay in payment.
In case any financial implication arises on GAIL due to issuance of invoice without
reduction in price or non-issuance of Credit Note, the same shall be to the account of
service provider. GAIL shall be entitled to deduct / setoff / recover such GST amount
(CGST & SGST/UTGST or IGST) together with penalties and interest, if any, against
any amounts paid or becomes payable by GAIL in future to the service provider under
this contract or under any other contract.
GAIL has implemented “Anjani" e-Measurement Book & e-Billing Portal for ease in
‐ 62 ‐
62 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
submission of measurement book/bill and reduction in paper transaction.
Accordingly, GAIL will process the Bill with Measurement Book through "Anjani" e-
Measurement Book & e-Billing Portal (link:
https://gailebank.gail.co.in/MBAutomation/frmlogin.aspx). Accordingly, Contractor/
Service Provider/ Consultant is requested to forward the RA Bill on "Anjani" e-
Measurement Book & e-Billing Portal through concerned EIC/CIC/SIC, whichever is
applicable.
Further, User Manual is also available on aforesaid portal.
Annexure-I to Section-III
A Definitions:
‐ 63 ‐
63 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
A.1 “Corrupt Practice” means the offering, giving, receiving or soliciting, directly or indirectly, anything of
value to improperly influence the actions in selection process or in contract execution.
“Corrupt Practice” also includes any omission for misrepresentation that may mislead or attempt to mislead
so that financial or other benefit may be obtained or an obligation avoided.
A2 “Fraudulent Practice” means and include any act or omission committed by a agency or with his
connivance or by his agent by misrepresenting/ submitting false documents and/ or false information or
concealment of facts or to deceive in order to influence a selection process or during execution of contract/
order.
A3 “Collusive Practice amongst bidders (prior to or after bid submission)” means a scheme or arrangement
designed to establish bid prices at artificial non-competitive levels and to deprive the Employer of the
benefits of free and open competition.
A.4 “Coercive practice” means impairing or harming or threatening to impair or harm directly or indirectly, any
agency or its property to influence the improperly actions of an agency, obstruction of any investigation or
auditing of a procurement process.
A.5 “Vendor/Supplier/Contractor/Consultant/Bidder” is herein after referred as “Agency”
A.6 ”Appellate Authority” shall mean Committee of Directors consisting of Director (Finance) and Director
(BD) for works centers under Director (Projects). For all other cases committee of Directors shall consist of
Director (Finance) & Director (Projects).
A.7 “Competent Authority” shall mean the authority, who is competent to take final decision for Suspension of
business dealing with an Agency/ (ies) and Banning of business dealings with Agency/ (ies) and shall be
the “Director” concerned.
A.8 “Allied Agency” shall mean all the concerns within the sphere of effective influence of banned/ suspended
agencies. In determining this, the following factors may be taken into consideration:
(a) Whether the management is common;
(b) Majority interest in the management is held by the partners or directors of banned/ suspended
firm.
(c ) substantial or majority shares are owned by banned/ suspended agency and by virtue of this it has
a controlling voice.
A.9 “Investigating Agency” shall mean any department or unit of GAIL investigating into the conduct of
Agency/ party and shall include the Vigilance Department of the GAIL, Central Bureau of Investigation,
State Police or any other agency set up by the Central or state government having power to investigate.
If it is observed during bidding process/ bids evaluation stage that a bidder has indulged in
corrupt/fraudulent /collusive/coercive practice, the bid of such Bidder (s) shall be rejected and its Earnest
Money Deposit (EMD) shall be forfeited.
Further, such agency shall be banned for future business with GAIL for a period specified in para B 2.2
below from the date of issue of banning order.
After conclusion of process and issuance of Speaking order for putting party on banning list, the
order (s)/ contract (s) where it is concluded that such irregularities have been committed shall be
terminated and Contract cum Performance Bank Guarantee (CPBG) submitted by agency against
such order (s)/ contract (s) shall also be forfeited. Further such order/ contract will be closed
following the due procedure in this regard.
The amount that may have become due to the contractor on account of work already executed by
him shall be payable to the contractor and this amount shall be subject to adjustment against any
amounts due from the contractor under the terms of the contract. No risk and cost provision will be
enforced in such cases.
‐ 64 ‐
64 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Further, only in the following situations, the concerned order (s)/ contract(s) (where
Corrupt/Fraudulent/ Collusive/ Coercive Practices are observed) and payment shall be suspended
after issuance of Suspension cum Show Cause Notice:
Suspension cum Show Cause Notice being issued in above cases after approval of the competent
authority (as per provisions mentioned under Clause no. D) shall also include the provision for
suspension of Order (s)/ Contract (s) and payment. Accordingly, after issuance of Suspension cum
Show Cause Notice, the formal communication for suspension of Order (s)/ Contract (s) and
payment with immediate effect will be issued by the concerned person of GAIL.
During suspension, Contractor/ Service Providers will be allowed to visit the plant/ site for upkeep
of their items/ equipment, GAIL’s issued materials (in case custody of same is not taken over),
demobilizing the site on confirmation of EIC, etc.
(ii) After execution of contract and during Defect liability period (DLP)/ Warranty/Guarantee
Period:
‐ 65 ‐
65 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
mentioned sl. no. 1 above) /Collusive/ Coercive Practices in
subsequent cases after their banning, such situation of repeated
offense to be dealt with more severity and following shall be the
period of banning:
2.1
C.1 If an agency is put on Banning, such agency should not be considered in ongoing tenders/future tenders.
C.2 However, if such an agency is already executing other order (s)/ contract (s) where no corrupt/fraudulent/
collusive/coercive practice is found, the agency should be allowed to continue till its completion without
any further increase in scope except those incidental to original scope mentioned in the contract.
C.3 If an agency is put on the Banning List during tendering and no irregularity is found in the case under
process:
C.3.1 after issue of the enquiry /bid/tender but before opening of Technical bid, the bid submitted by the agency
shall be ignored.
C.3.2 after opening Technical bid but before opening the Price bid, the Price bid of the agency shall not be opened
and BG/EMD submitted by the agency shall be returned to the agency.
C.3.3 after opening of price, BG/EMD made by the agency shall be returned; the offer of the agency shall be
ignored & will not be further evaluated. If the agency is put on banning list for fraud/ mis-appropriation of
facts committed in the sametender/other tender where errant agency emerges as the lowest (L1), then such
tender shall also be cancelled and re-invited.
Action for suspension business dealing with any agency/(ies) shall be initiated by Corporate C&P
Department when
(i) Corporate Vigilance Department based on the fact of the case gathered during investigation by
them recommend for specific immediate action against the agency.
(ii) Corporate Vigilance Department based on the input from Investigating agency, forward for
specific immediate action against the agency.
(iii) Non performance of Vendor/Supplier/Contractor/Consultant leading to termination of Contract/
Order.
D.2.1 The order of suspension would operate initially for a period not more than six months and is to be
communicated to the agency and also to Corporate Vigilance Department. Period of suspension can be
‐ 66 ‐
66 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
extended with the approval of the Competent Authority by one month at a time with a ceiling of six
months pending a conclusive decision to put the agency on banning list.
D.2.2 During the period of suspension, no new business dealing may be held with the agency.
D.2.3 Period of suspension shall be accounted for in the final order passed for banning of business with the
agency.
D.2.4 The decision regarding suspension of business dealings should also be communicated to the agency.
D.2.5 If a prima-facie, case is made out that the agency is guilty on the grounds which can result in banning
of business dealings, proposal for issuance of suspension order and show cause notice shall be put up
to the Competent Authority. The suspension order and show cause notice must include that (i) the
agency is put on suspension list and (ii) why action should not be taken for banning the agency for
future business from GAIL.
The competent authority to approve the suspension will be same as that for according approval for
banning.
D.3.1 No enquiry/bid/tender shall be entertained from an agency as long as the name of agency appears in
the Suspension List.
D.3.2 If an agency is put on the Suspension List during tendering:
D.3.2.1 after issue of the enquiry /bid/tender but before opening of Technical bid, the bid submitted by the
agency shall be ignored.
D.3.2.2 after opening Technical bid but before opening the Price bid, the Price bid of the agency shall not be
opened and BG/EMD submitted by the agency shall be returned to the agency.
D.3.2.3 after opening of price, BG/EMD made by the agency shall be returned; the offer of the agency shall be
ignored & will not be further evaluated. If the agency is put on Suspension list for fraud/ mis-
appropriation of facts conducted in the sametender/other tender where errant agency emerges as the
lowest (L1), then such tender shall also be cancelled and re-invited.
D.3.3 The existing contract (s)/ order (s) under execution shall continue.
D.3.4 Tenders invited for procurement of goods, works and services shall have provision that the bidder
shall submit a undertaking to the effect that (i) neither the bidder themselves nor their allied
agency/(ies) are on banning list of GAIL or the Ministry of Petroleum and Natural Gas and (ii)
bidder is not banned by any Government department/ Public Sector.
F.1 The agency may file an appeal against the order of the Competent Authority for putting the agency on
banning list. The appeal shall be filed to Appellate Authority. Such an appeal shall be preferred within one
month from the of receipt of banning order.
F.2 Appellate Authority would consider the appeal and pass appropriate order which shall be communicated to
the party as well as the Competent Authority.
F.3 Appeal process may be completed within 45 days of filing of appeal with the Appellate Authority.
G. Wherever there is contradiction with respect to terms of ‘Integrity pact’ , GCC and ‘Procedure for action in
case of Corrupt/Fraudulent/ Collusive/Coercive Practice’, the provisions of ‘Procedure for action in case of
Corrupt/Fraudulent/ Collusive/Coercive Practice’ shall prevail.
1.0 GENERAL
‐ 67 ‐
67 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
A system for evaluation of Vendors/ Suppliers/Contractors/ Consultants and their performance is a key
process and important to support an effective purchasing & contracting function of an organization.
Performance of all participating Vendors/ Suppliers/Contractors/ Consultants need to be closely monitored
to ensure timely receipt of supplies from a Vendor, completion of an assignment by a Consultant or
complete execution of order by a contractor within scheduled completion period. For timely execution of
projects and meeting the operation & maintenance requirement of operating plants, it is necessary to
monitor the execution of order or contracts right from the award stage to completion stage and take
corrective measures in time.
2.0 OBJECTIVE
The objective of Evaluation of Performance aims to recognize, and develop reliable Vendors/
Suppliers/Contractors/ Consultants so that they consistently meet or exceed expectations and requirements.
The purpose of this procedure is to put in place a system to monitor performance of Vendors/
Suppliers/Contractors/ Consultants associated with GAIL so as to ensure timely completion of various
projects, timely receipt of supplies including completion of works & services for operation and
maintenance of operating plants and quality standards in all respects.
3.0 METHODOLOGY
4.0 EXCLUSIONS:
The following would be excluded from the scope of evaluation of performance of Vendors/
Suppliers/Contractors/ Consultants :
However, concerned Engineer-in-Charge /OICs will continue to monitor such cases so as to minimize the
impact on Projects/O&M plants due to non performance of Vendors/ Suppliers/Contractors/ Consultants in
all such cases.
iv) Reply from concerned Vendor/ Supplier/Contractor/ Consultant shall be examined. In case of
satisfactory reply, Performance Rating data Sheet to be closed with a letter to the concerned for
improving performance in future.
v) When no reply is received or reasons indicated are unsatisfactory, the following actions need to be
taken:
A) Where performance rating is “POOR” (as per Performance Rating carried out after
execution of Order/ Contract and where no reply/ unsatisfactory reply is received from
party against the letter seeking the explanation from Vendor/Supplier/Contractor/
Consultant along with sharing the performance rating)
2. Poor Performance on account of other than Quality (if marks obtained against
Quality parameter is more than 20):
(a) First such instance:Advisory notice(Yellow Card) shall be issued
and Vendor/Supplier/Contractor/ Consultantshall be put on watch list
for a period of Three (3) Years.
(b) Second such instance in other ongoing order (s)/ contract (s) or
new order (s) /contact (s) on such Vendor/ Supplier/ Contractor/
Consultant: Putting on Holiday (Red Card) for a period of One
Year
(c) Subsequent instances (more than two) in other ongoing order (s)/
contract (s) or new order (s) /contact (s) on such Vendor/ Supplier/
Contractor/ Consultant: Putting on Holiday (Red Card) for a
period of Three Years.
(a) First instance: Advisory notice (Yellow Card) shall be issued and
Vendor/Supplier/Contractor /Consultantshall be put on watch list for a period of
Three (3) Years.
Further such vendor will not be allowed to participate in the re-tender of the
same supply/work/services of that location which has terminated / offloaded.
‐ 69 ‐
69 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Moreover, it will be ensured that all other action as per provision of contract
including forfeiture of Contract Performance Security (CPS) etc. are
undertaken.
However, such vendor will be allowed to participate in all other tenders and to
execute other ongoing order/ contract (s) or new contract/ order (s).
The Yellow card will be automatically revoked after a period of three years
unless the same is converted into Red Card due to subsequence instances of
poor/ non-performance in other ongoing order (s)/ contract (s) or new order (s)
/contact (s) on such Vendor/ Supplier/ Contractor/ Consultant.
(b) Second instances in other ongoing order (s)/ contract (s) or new order (s)
/contact (s) on such Vendor/ Supplier/ Contractor/ Consultant: Holiday (Red
Card) for period of One Year and they shall also to be considered for
Suspension.
(c) Subsequent instances (more than two) in other ongoing order (s)/ contract (s)
or new order (s) /contact (s) on such Vendor/ Supplier/ Contractor/ Consultant:
Holiday (Red Card) for period of Three Years and they shall also to be
considered for Suspension.
Monitoring and Evaluation of consultancy jobs will be carried out in the same way as described in para 5.1
for Projects.
iv) Reply from concerned Vendor/ Supplier/Contractor/ Consultant shall be examined. In case of
satisfactory reply, Performance Rating data Sheet to be closed with a letter to the concerned for
improving performance in future.
v) When no reply is received or reasons indicated are unsatisfactory, the following actions need to be
taken:
A) Where performance rating is “POOR” (as per Performance Rating carried out after
execution of Order/ Contract and where no reply/ unsatisfactory reply is received from
party against the letter seeking the explanation from Vendor/Supplier/Contractor/
Consultant along with sharing the performance rating)
‐ 70 ‐
70 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
(b) Subsequent instance (s) in other ongoing order (s)/ contract (s) or
new order (s) /contact (s) on such Vendor/ Supplier/ Contractor/
Consultant: Holiday (Red Card) for Three Years
2. Poor Performance on account of other than Quality (if marks obtained against
Quality parameter is more than 20):
(a) First such instance:Advisory notice(Yellow Card) shall be issued and
Vendor/Supplier/Contractor/ Consultantshall be put on watch list for a
period of Three (3) Years.
(b) Second such instance in other ongoing order (s)/ contract (s) or
new order (s) /contact (s) on such Vendor/ Supplier/ Contractor/
Consultant: Putting on Holiday (Red Card) for a period of One
Year
(c) Subsequent instances (more than two) in other ongoing order (s)/
contract (s) or new order (s) /contact (s) on such Vendor/ Supplier/
Contractor/ Consultant: Putting on Holiday (Red Card) for a
period of Three Years.
(b) Second instances in other ongoing order (s)/ contract (s) or new order (s)
/contact (s) on such Vendor/ Supplier/ Contractor/ Consultant: Holiday (Red
Card) for period of One Year and they shall also to be considered for
Suspension.
(c) Subsequent instances (more than two) in other ongoing order (s)/ contract (s)
or new order (s) /contact (s) on such Vendor/ Supplier/ Contractor/ Consultant:
Holiday (Red Card) for period of Three Years and they shall also to be
considered for Suspension.
6.1 An order for Holiday passed for a certain specified period shall deemed to have been automatically
revoked on the expiry of that specified period and it will not be necessary to issue a specific formal order
of revocation.
Further, in case Vendor/ Supplier/Contractor/ Consultant is put on holiday due to quality, and new order is
placed on bidder after restoration of Vendor/ Supplier/Contractor/ Consultant, such order will be properly
monitored during execution stage by the concerned site.
‐ 71 ‐
71 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
(a) The party may file an appeal against the order of the Competent Authority for putting the party on
Holiday list. The appeal shall be filed to Appellate Authority. Such an appeal shall be preferred
within one month from the of receipt of Holiday order.
(b) Appellate Authority would consider the appeal and pass appropriate order which shall be
communicated to the party as well as the Competent Authority.
(c) Appeal process may be completed within 45 days of filing of appeal with the Appellate Authority.
(d) “Appellate Authority” shall mean Committee of Directors consisting of Director (Finance) and
Director (BD) for works centers under Director (Projects). For all other cases committee of
Directors shall consist of Director (Finance) & Director (Projects).
In case after price bid opening the lowest evaluated bidder (L1) is not awarded the job for any mistake
committed by him in bidding or withdrawal of bid or modification of bid or varying any term in regard
thereof leading to re-tendering, GAIL shall forfeit EMD if paid by the bidder and such bidders shall be
debarred from participation in retendering of the same job(s)/item(s).
Further, such bidder will be put on Watch List (Yellow Card) for a period of three years after following the
due procedure. However, during the period in watch list such vendor will be allowed to participate in all
other tenders and to execute other ongoing order/ contract (s) or new contract/ order (s).
In case of subsequent instances of default in other tender(s) during aforesaid watch list period, the action
shall be initiated as per provision of sl. no. 2 of para A of Clause no. 5.1 (v) and 5.3 (v).
The Yellow card will be automatically revoked after specified period unless the same is converted into Red
Card
12. In case CBIC (Central Board of Indirect Taxes and Customs)/ any tax authority / any equivalent
government agency brings to the notice of GAIL that the Supplier has not remitted the amount towards
GST (CGST & SGST/UTGST or IGST) collected from GAIL to the government exchequer, then, that
Supplier shall be put under Holiday list of GAIL for period of six months after following the due
procedure. This action will be in addition to the right of recovery of financial implication arising on GAIL.
‐ 72 ‐
72 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Annexure-1
GAIL (India) Limited
PERFORMANCE RATING DATA SHEET
(FOR PROJECTS/ CONSULTANCY JOBS)
i) Project/Work Centre :
ii) Order/ Contract No. & date :
iii) Brief description of Items :
Works/Assignment
‐ 73 ‐
73 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
iv) Order/Contract value (Rs.) :
v) Name of Vendor/Supplier/ :
Contractor/ Consultant
vi) Contracted delivery/ :
Completion Schedule
vii) Actual delivery/ :
Completion date
Note:
Remarks (if any)
PERFORMANCE RATING (**)
Note :
(#) Vendor/Supplier/Contractor/Consultant who seek repeated financial assistance or deviation beyond
contract payment term or seeking direct payment to the sub-vendor/sub-contractor due to financial
constraints, then ‘0’ marks should be allotted against Reliability Performance.
(*) Allocation of marks should be as per enclosed instructions
(**) Performance rating shall be classified as under :
‐ 74 ‐
74 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
A. FOR WORKS/CONTRACTS
or
B. FOR SUPPLIES
ii) Attending complaints and requests for after sales service/ 5 marks
warranty repairs and/ or query/ advice (upto the evaluation
period).
‐ 75 ‐
75 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Annexure-2
GAIL (India) Limited
PERFORMANCE RATING DATA SHEET
(FOR O&M)
i) Location :
ii) Order/ Contract No. & date :
iii) Brief description of Items :
Works/Assignment
iv) Order/Contract value (Rs.) :
v) Name of Vendor/Supplier/ :
Contractor/ Consultant
vi) Contracted delivery/ :
Completion Schedule
vii) Actual delivery/ :
Completion date
‐ 76 ‐
76 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
” 16 weeks 20
” 20 weeks 15
” 24 weeks 10
More than 24 weeks 0
A. FOR WORKS/CONTRACTS
or
B. FOR SUPPLIES
‐ 77 ‐
77 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Annexure-III to Section-III
1. General
This section contains detailed instructions regarding bid submission procedure under e-
tendering system (e-tender portal). Bidders are required to read the following instructions
in addition to various instructions mentioned elsewhere in this document for e-tendering,
Bidders manual kit and FAQs etc. The instructions mentioned herein related to bid
submission procedure shall supersede and shall prevail over the conditions enumerated
elsewhere in the bid/tender document.
GAIL (India) Ltd. has associated with Govt. e-Procurement System of National
Informatics Center (NIC) for processing e-tenders. CPP is a secured and user friendly e-
tender system enabling bidders to Search, View, Download tender document(s) directly
from the portal https://etenders.gov.in/eprocure/app(referred hereunder as “E-Tender
Portal”) and also enables the bidders to participate and uploading of SOR/BOQ/Price
Schedule (Price Bid)and technical bids in the portal in secured and transparent manner
maintaining absolute confidentiality and security throughout the tender evaluation
process and award.
More information useful for submitting online bids on the CPP Portal may be obtained
at: https://etenders.gov.in/eprocure/app
The Bidder must have a high speed internet connectivity with at least 2Mbpsspeed (512
kbps Speed)(preferably Broadband) to access e-Tender Portal for downloading the
Tender document and uploading/submitting the Bids.
Bidder must possess an e-mail Id, preferably of the Organisation (in case of a
company)/Individual (in case of proprietorship concern)/Partner having Power of
Attorney (in case of a partnership firm) to create login Id. The e-mail Id should not be
changed frequently. All communication related to e-tendering including system
generated mails shall be sent on this e-mail Id only. The communication to bidder is fully
automated through the system and hence email-id of bidder is very important for online
communication with bidder during various stages of tendering process and should be
preferably common e-mail Id of the Organisation.
To participate in the bidding process, it is mandatory on the part of bidder(s) to have user
Id and password. Without user Id (Login Id), bidders cannot participate in E-tender.
There will be single login Id for a bidder.
ii) Fill the Online Enrollment of Corporate/Bidder form and submit. Ensure that the
e-mail address and mobile number given in the form is valid and active.These would
be used for any communication from the E-tender Portal.
iii) Ensure that all the mandatory fields (identified with a * mark) are filled in the
Online Enrollment of Corporate/Bidder for User Id creation.
iv) Upon enrolment, the bidders will be required to register their valid Digital Signature
Certificate (Class III Certificates with signing key usage) issued by any Certifying
Authority recognized by CCA India (e.g. Sify / nCode / eMudhra etc.), with their
profile.
v) Only one valid DSC should be registered by a bidder. Please note that the bidders
are responsible to ensure that they do not lend their DSC’s to others which may lead
to misuse.
‐ 79 ‐
79 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
vii) Bidder then logs in to the site through the secured log-in by entering their USER
ID / password and the password of the DSC / e-Token.
User Id and password is unique for each vendor and the vendor can use the same to
view/download/participate in all e-tenders of GAIL.
In their own interest, Bidder(s) are advised to apply for User Id immediately on
publishing of tender or well in advance of the bid due date. User Id shall normally be
issued immediatelyafter complete information has been furnished by the vendor in
“Online Enrollment of Corporate/Bidder”and on successful submission of the same.
GAIL/CPP shall not be responsible for any delays in allocation of User Id/password and
in registering Digital Signature Certificateand the ensuing consequences including but
not limited to timely submission of bids.
The e-mail-id of the bidder/Vendor Code is captured and registered in CPP Portal when a
bidder submits his request for user-id / password.
In case bidder desires for change in the registered e-mail id in CPP Portal, the same has
to be updated in CPP portal only.
One Digital Certificate is valid for a specified period and can be used for digitally
signing any number of documents.
‐ 80 ‐
80 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Bidder can submit only digitally signed documents/bids/offersin
https://etenders.gov.in/eprocure/app
In order to bid for GAIL e-tenders bidders are required to obtain a legally valid
Digital Certificate as per Indian IT Act 2000 from the licensed Certifying
Authorities (CA) operating under the Root Certifying Authority of India (RCAI),
Controller of Certifying Authorities (CCA) of India.
Note: The Digital signatures should be obtained directly from certifying authority
(CA). Digital signature taken from Sub CA will not be acceptable in the e-
tendering system.
‐ 81 ‐
81 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
6. How to search, view and download e-tender?
There are various search options built in E-tender Portal, to facilitate bidders to search
active tenders by several parameters. These parameters could include Tender ID,
Organization Name, Location, Date, Value, etc. There is also an option of advanced
search for tenders, wherein the bidders may combine a number of search parameters such
as Organization Name, Form of Contract, Location, Date, Other keywords etc. to search
for a tender published on the CPP Portal.
Once the bidders have selected the tenders they are interested in, they may download the
required documents / tender schedules.To download the tender Click on the Latest Active
Tenders, and search the tender in e-tender website
(https://etenders.gov.in/eprocure/app) (e-tender portal) that you are interested in using
certain search criteria documents. However, it is advised to login to the system and set
the tender as favorite so that these tenders can be moved to the respective ‘My
Tenders’folder. This would enable the E-tender Portal to intimate the bidders through
SMS / e-mail in case there is any corrigendum/addendum issued to the tender document.
The bidder should make a note of the unique Tender ID assigned to each tender, in case
they want to obtain any clarification / help from the Helpdesk.
7. PREPARATION OF BIDS
1) Bidder should take into account any corrigendum published on the tender
document before submitting their bids.
4) To avoid the time and effort required in uploading the same set of standard
documents which are required to be submitted as a part of every bid, a provision
of uploading such standard documents (e.g. PAN card copy, annual reports,
auditor certificates etc.) has been provided to the bidders. Bidders can use “My
Space” or ‘’Other Important Documents’’ area available to them to upload such
documents. These documents may be directly submitted from the “My Space”
area while submitting a bid, and need not be uploaded again and again. This will
lead to a reduction in the time required for bid submission process.
Note: My Documents space is only a repository given to the Bidders to ease the
uploading process. If Bidder has uploaded his Documents in My Documents
space, this does not automatically ensure these Documents being part of
Technical Bid.
‐ 82 ‐
82 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
8. Directions for submitting online offers, electronically, against e-procurement
tenders directly through internet
ii) Bidder should log into the site well in advance for bid submission so that they can
upload the bid in time i.e. on or before the bid submission time. Bidder will be
responsible for any delay due to other issues
iii) Vendors are advised in their own interest to ensure that their bids are submitted in
e-Procurement system well before the closing date and time of bid. If the vendor
intends to change/revise the bid already submitted, they shall have to change /
revise the bid and submit once again. Bid once withdrawn cannot be resubmitted.
iv) The server time (IST) (which is displayed on the bidders’ dash board) shall be
considered as the standard time for referencing the deadlines for submission of
the document by the bidders and determining the expiry of due date and time of
the tender and no other time shall be taken into cognizance.
v) Bidder has to select the payment option as “offline” to pay the tender fee / EMD
as applicable and enter details of the instrument.
vi) The BOQ template must not be modified/replaced by the bidder and the same
should be uploaded after filling the relevant columns, else the bidder is liable to
be rejected for that tender. Bidders are allowed to enter the Bidder Name and
Values only.
vii) Bidders are requested to note that they should necessarily submit their financial
bids in the format provided and no other format is acceptable. If the price bid has
been given as a standard BoQ format with the tender document, then the same is
to be downloaded and to be filled by all the bidders. Bidders are required to
download the BoQ file, open it and complete the white coloured (unprotected)
cells with their respective financial quotes and other details (such as name of the
bidder). No other cells should be changed. Once the details have been completed,
the bidder should save it and submit it online, without changing the filename. If
the BoQ file is found to be modified by the bidder, the bid is liable for rejection.
The BOQ template must not be modified/replaced by the bidder and the same
should be uploaded after filling the relevant columns, else the bidder is liable to
be rejected for that tender. Bidders are allowed to enter the Bidder Name and
Values only.
viii) In case vendor is not able to complete the submission of the changed/revised bid
within due date & time, the system would consider it as no bid has been received
from the vendor against the tender and consequently the vendor will be out of
contention. The process of change / revise may do so any number of times till the
due date and time of submission deadline. However, no bid can be modified after
the deadline for submission of bids.
‐ 83 ‐
83 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ix) Bids / Offers shall not be permitted in e-procurement system after the due date /
time of tender. Hence, no bid can be submitted after the due date and time of
submission has elapsed.
x) All the documents being submitted by the bidders would be encrypted using PKI
encryption techniques to ensure the secrecy of the data. The data entered cannot
be viewed by unauthorized persons until the time of bid opening. The
confidentiality of the bids is maintained using the secured Socket Layer 128 bit
encryption technology. Data storage encryption of sensitive fields is done. Any
bid document that is uploaded to the server is subjected to symmetric encryption
using a system generated symmetric key. Further this key is subjected to
asymmetric encryption using buyers/bid opener’s public keys. Overall, the
uploaded tender documents become readable only after the tender opening by the
authorized bid openers.
xi) The uploaded tender documents become readable only after the tender opening by
the authorized bid openers.
xii) Upon the successful and timely submission of bids (i.e. after Clicking “Freeze
Bid Submission” in the portal), the portal will give a successful bid submission
message & a bid summary will be displayed with the bid no. and the date & time
of submission of the bid with all other relevant details.
xiii) Once the entire process of submission of online bid is complete, they will get an
auto mail/SMS from the system stating you have successfully submitted your bid
in the following tender with tender details.
xv) It is important to note that, the bidder has to Click on the Freeze Bid Button, to
ensure that he/she completes the Bid Submission Process. Bids Which are not
Frozen are considered as Incomplete/Invalid bids and are not considered for
evaluation purposes.
xvi) The bid summary has to be printed and kept as an acknowledgement of the
submission of the bid. This acknowledgement may be used as an entry pass for
any bid opening meetings.
Note:
i) Bidder may save/store the bid documents in the PC/Laptop before submitting the
bid into in e-tender portal.
ii) Bidder is required to fill up the price(s)/rate(s) strictly in the Schedule of Rate
(SOR)/Price Schedule/BOQ attached with the tender.
Bidders are required to submit the Earnest Money Deposit (EMD)/Bid Bond in original
in the prescribed formats and in the manner prescribed in the tender at the time of bid
submission in sealed envelope.
‐ 84 ‐
84 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
However, if the bidder is unable to submit EMD/Bid Bond in original on the due date,
he may upload scanned copy of the EMD/Bid Bond while submitting the bid
electronically, provided the original EMD/Bid Bond, copy of which has been uploaded,
is received within 7 (seven) days from the date of un-priced bid opening, failing which
the bid will be rejected irrespective of their status / ranking in tender and
notwithstanding the fact that a copy of the Earnest Money Deposit/Bid Bond was earlier
uploaded by the bidder.
During the pre-bid conference, GAIL shall also arrange demonstration for submission of
bids in e-tender portal for interested bidders.
System does not allow for submission or modification of bids beyond the deadline for bid
submission. However, if the bidder for some reason intends to change the bid already
entered, he may change/revise the same on or before the last date and time of submission.
The system time displayed on e-tender webpage shall be final and binding on the bidders
for all purposes pertaining to various events of the subject tender and no other time shall
be taken into cognizance.
Bidders are advised in their own interest to ensure that bids are uploaded in e-tender
system well before the closing date and time of bid.
13. In case of any clarification pertaining to e-procurement process, the vendor may
contact the concerned dealing officer/purchasing officer mentioned in tender
document along with marking copy to etender@gail.co.in.
.................................................................................................................................
Disclaimer:
a) No responsibility will be taken by GAIL or the e-procurement service provider for any
delay due to connectivity and availability of website. They shall not have any liability to
vendors for any interruption or delay in access to the site irrespective of the cause. It is
advisable that vendors who are not well conversant with e-tendering procedures, start
filling up the tenders much before the due date /time so that there is sufficient time
available with him/her to acquaint with all the steps and seek help if they so require.
Even for those who are conversant with this type of e-tendering, it is suggested to
complete all the activities ahead of time. It should be noted that the individual bid
becomes viewable only after the opening of the bid on/after the due date and time. Please
be reassured that your bid will be viewable only to you and nobody else till the due date/
time of the tender opening. The non availability of viewing before due date and time is
true for e-tendering service provider as well as GAIL officials.
‐ 85 ‐
85 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
b) GAIL or the e-procurement service provider shall not be responsible for any direct or
indirect loss or damages and or consequential damages, arising out of the bidding process
including but not limited to systems problems, inability to use the system, loss of
electronic information etc.,
FAQ:
https://etenders.gov.in/eprocure/app?page=FAQFrontEnd&service=page
Feedback:
https://etenders.gov.in/eprocure/app?page=FrontFeedback&service=page
‐ 86 ‐
86 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ANNEXURE-IV to Section-III
2.1 The name of the Works/Services to be performed is: LAYING & CONSTRUCTION
OF STEEL GAS PIPELINE AND TERMINALS ALONG WITH
ASSOCIATED FACILITIES FOR ANGUL-SRIKAKULAM PIPELINE
PROJECT ( PART-B)
APPLICABLE
X
NOT APPLICABLE
√
B. BIDDING DOCUMENT
ITB clause Description
8.1 For clarification purposes only, the communication address is:
Attention: Rakesh Sharma, Sr. GM (Contracts)
Street Address: MECON LIMITED
Floor/Room number: 15th Floor, Scope Minor, District Centre , Laxmi Nagar
City: Delhi
ZIP Code: 110092
Country: India
Tel no.: 011-22401112/ 22401143
Email : cont-delhi@mecon.co.in
C. PREPARATION OF BIDS
YES
𝑋
NO
√
‐ 87 ‐
87 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
14 The currency of the Bid shall be INR
15 The bid validity period shall be 03 (Three) months from final ‘Bid Due Date’.
38.6 In case “Contract Performance Security” is in the form of 'Demand Draft' or
'Banker's Cheque', the same should be favor of GAIL (India) Limited, payable
at Noida.
In case of submission through online banking transaction i.e. IMPS / NEFT / RTGS
/ SWIFT, etc, the details of GAIL’s Bank account are as under:
Account Holder’s Name: GAIL (India) Limited
Details of GAIL’s Bank account:
Correspondence STATE BANK OF INDIA
address Coprate Accounts Group II. 4th & 5th Floor, Red Fort
Capital, Parsvnath Towers, Bhai Veer Singh Marg,
Near Gole Market, New Delhi 110 001.
Account no. 000000032849362991
Branch Code 17313
‐ 88 ‐
88 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
33 Compensation for Extended Stay:
APPLICABLE
√
NOT APPLICABLE
𝑋
F. AWARD OF CONTRACT
ITB clause Description
37 State of which stamp paper is required for Contract Agreement: Uttar Pradesh
38 Contract Performance Security/ Security Deposit
APPLICABLE
√
NOT APPLICABLE
X
NOT APPLICABLE
√
APPLICABLE
√
NOT APPLICABLE
X
‐ 89 ‐
89 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
44.1 Quarterly Closure of Contract
APPLICABLE
√
NOT APPLICABLE
X
NOT APPLICABLE
√
APPLICABLE
x
NOT APPLICABLE
√
‐ 90 ‐
90 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
ANNEXURE-V TO SECTION-III
1.0 Ministry of Petroleum & Natural Gas (MoPNG) vide communication no. FP-
2013/2/2017-FP-PNG dated 17.11.2020 has forwarded Policy to provide Purchase
Preference (linked with Local Content) in all the Public Sector Undertakings under the
Ministry of Petroleum and Natural Gas. A copy of the policy is available on website of
MoP&NG (i.e. http://petroleum.nic.in/).
2.0 DEFINITIONS
2.1 Oil and Gas Business Activity shall comprise of Upstream, Midstream and Downstream
business activities.
2.2 Domestic products shall be goods and/or service (including design and engineering)
produced by companies, investing and producing in India.
2.3 Local Content hereinafter abbreviated to LC means the amount of value added in India
which shall, unless otherwise prescribed by the Nodal Ministry, be the total value of the
item procured (excluding net domestic indirect taxes) minus the value of imported
content in the item (including all customs duties) as a proportion of the total value, in
percent.
2.5 Supplier of goods and/or provider of service shall be a business entity having
capability of providing goods and/or service in accordance with the business line and
qualification thereof and classified as under:
'Class-I local supplier' means a supplier or service provider, whose goods, services or
works offered for procurement, has local content equal to or more than 50%, as defined
under this Policy.
`Class-II local supplier' means a supplier or service provider, whose goods, services or
works offered for procurement, has local content more than 20% but less than 50%, as
defined under this Policy.
2.9 Local Content (LC) in Goods shall be the use of raw materials, design and engineering
towards manufacturing, fabrication and finishing of work carried out within the country.
2.10 Local Content (LC) in Services shall be the use of services up to the final delivery by
utilizing manpower (including specialist), working appliance (including software)
and supporting facilities carried out within in the country.
2.11 Local Content (LC) in EPC contracts shall be the use of materials, design and
engineering comprising of manufacturing, fabrication, assembly and finishing as
well as the use of services by utilizing manpower (including specialist), working
appliance (including software) and supporting facility up to the final delivery, carried out
within the country.
2.14 Indian Company means a company formed and registered under the Companies
Act, 2013.
2.15 Foreign company means any company or body corporate incorporated outside India
which— (a) has a place of business in India whether by itself or through an agent.
physically or through electronic mode: and (b) conducts any business activity in India
in any other manner.
3.0 SCOPE
3.1 This PP-LC policy is not applicable for goods/ services falling under the list of items
reserved for exclusive purchase from Micro and Small Enterprises (MSEs) or
Domestically manufactured Electronic Products (DMEP) or Domestically Manufactured
Products, Services or works Relating to Telecom under the respective policies.
3.2 VOID
3.3 Further, this policy is not applicable for HP-HT operations for time being. The Charter
Hiring of Offshore vessels shall continue to be governed by DG, Shipping Guidelines.
Indian Flag Vessels shall be considered as having 100% LC.
3.4 The prescribed local content in the Policy shall be applicable on the date of Notice
Inviting Tender/ Issuance of tender.
‐ 92 ‐
92 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
5.0 ELIGIBILITY OF ‘CLASS-I LOCAL SUPPLIER’/ ‘CLASS-II LOCAL
SUPPLIER’/ ‘NON-LOCAL SUPPLIERS’ FOR DIFFERENT TYPES OF
PROCUREMENT
5.1 In respect of all goods, services or works in respect of which the Nodal Ministry/
Department under DPIIT's Public Procurement (Preference to Make in India) Order,
2017 has communicated that there is sufficient local capacity and local competition, only
‘Class-I local supplier’ shall be eligible to bid. Details of such notified goods, services or
works is available on https://dipp.gov.in/public-procurements
5.2 For all other Domestic Competitive tenders, ‘Class-I local supplier’ and ‘Class-II local
supplier’ shall be eligible to bid irrespective of purchase value, but preference to be given
as per PP-LC to the ‘Class-I local supplier’.
5.3 Only ‘Class-I local supplier’ and ‘Class-II local supplier’ shall be eligible to bid, except
when Global tender enquiry/International Competitive Bidding has been issued. In
Global tender enquiry/International Competitive Bidding, ‘Non-local suppliers’ shall also
be eligible to bid along with ‘Class-I local suppliers’ and ‘Class-II local suppliers’.
5.4 ‘Class-II local supplier’ and ‘Non-local supplier’ will not get purchase preference in any
tender.
5.5 The producers of goods and/or providers of services shall be obliged to fulfil the
requirements of quality and delivery time in accordance with the provisions of the
respective contracts of goods and services.
5.6 If the Ministry is satisfied that Indian suppliers of an item are not allowed to participate
and/or compete in procurement by any foreign government, it may, if it deems
appropriate, restrict or exclude bidders from that country from eligibility for procurement
of that item and/or other items relating to the Ministry.
5.7 For the purpose of para 5.6 above, a supplier or bidder shall be considered to be from a
country if (i) the entity is incorporated in that country, or (ii) a majority of its
shareholding or effective control of the entity is exercised from that country, or (iii) more
that 50% of the value of the item being supplied has been added in that country. Indian
suppliers shall mean those entities which meets any of these tests with respect to India.
6.1.1 The manufacturers/ service providers having the capability of meeting/ exceeding
the local content targets shall be eligible for purchase preference under the policy, i.e. LC
manufacturers/ LC service providers respectively as described below.
6.1.2 Wherever the goods/ services are procured under this policy, eligible (techno-
commercially qualified) ‘Class I Local supplier’ shall be granted a purchase
preference where the quoted price is within the margin of purchase preference of the
lowest price, other things being equal, purchase preference shall be be granted to the
eligible (techno-commercially qualified) Class I Local supplier concerned, at the lowest
valid price bid.
‐ 93 ‐
93 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
6.1.3 Goods:
(a) If the tenders can be split (as specified in BDS) then the order for 50% ** of the
procured quantity would be awarded to the lowest techno-commercially qualified
‘Class I Local supplier’, subject to matching with L1, if such bidders are
available. The remaining will be awarded to L1.
** If the tendered quantity cannot be divided exactly 50:50, the eligible Class I
Local supplier will have right for quantity not less than 50% of tendered
quantity.
(b) If the tender cannot be split (as specified in BDS)then the order shall be
awarded to the eligible ‘Class I Local supplier’ for the entire quantity.
(a) In case tender for services/ EPC cannot be split (as specified in BDS), The
entire contract would be awarded to the lowest techno-commercially qualified
‘Class I Local supplier’, subject to matching with L1, if such bidders are
available.
(b) In case tender for services/EPC can be split (as specified in BDS), then
splitting shall be allowed and specified in tender documents. Such services shall
follow the procedure outlined for goods as described in goods above at para at
6.1.3 (a).
6.1.5 For para 6.1.3 and 6.1.4 above, only those ‘Class I Local supplier’ whose bids are within
the margin of purchase preference would be allowed an opportunity to match L1 bid.
6.1.6 The procedure for award of contract/ order under the policy is at Enclosure-I.
7.0 Determination of LC: The following process shall be adopted by the bidder to
determine the content of LC:
6.1 LC of Goods
7.1.1 LC of goods shall be computed on the basis of the cost of domestic components
in goods, compared to the whole cost of product.
7.1.2 The criteria for determination of the local content cost in the goods shall be as follows:
7.1.3 The calculation of LC of the combination of several kinds of goods shall be based on the
ratio of the sum of the multiplication of LC of each of the goods with the acquisition
price of each goods to the acquisition price of the combination of goods.
‐ 94 ‐
94 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
7.2 LC of service
7.2.1 LC of Service shall be calculated on the basis of the ratio of service cost of domestic
component in service to the total cost of service.
7.2.2 The total cost of service shall be constituted of the cost spent for rendering of service,
covering:
7.2.3 The criteria for determination of cost of local content in the service shall be as follows
a) in the case of material being used to help the provision of service, based on
country of origin;
b) in the case of manpower and consultant based on INR component of the services
contract;
c) in the case of working equipment/facility, based on country of origin: and
d) in the case of general service cost, based on the criteria as mentioned in clauses a,
b, and c above.
e) Indian flag vessels in operation as on date.
7.3.1 LC of EPC contracts shall be the ratio of the whole cost of domestic components
in the combination of goods and services to the whole combined cost of goods and
services.
7.3.2 The whole combined cost of goods and services shall be the cost spent to produce the
combination of goods and services, which is incurred on work site. LC of the
combination of goods and services shall be counted in every activity of the combination
work of goods and services.
7.3.3 The spent cost as mentioned in paragraph 7.3.2 shall include production cost in the
calculation of LC of goods as mentioned in clause 7.1.1 and service cost in the
calculation of LC of services as mentioned in clause 7.2.2.
LC shall be calculated on the basis of verifiable data. In the case of data used in the
calculation of LC being not verifiable, the value of LC of the said component shall be
treated as nil.
‐ 95 ‐
95 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
8.1.1 At bidding stage:
a) Price Break-up:
• The bidder shall provide the percentage of local content in the bid.
b) The bidder shall submit an undertaking [Form -2] from the authorised signatory
of bidder having the Power of Attorney alongwith the bid stating the bidder meets
the mandatory minimum LC requirement and such undertaking shall become a
part of the contract.
(c) In cases of procurement for a value in excess of Rs. 10 crores, the Undertaking
[Form-3] submitted by the bidder shall be supported by a certificate from the
statutory auditor or cost auditor of the company (in the case of companies) or
from a practicing cost accountant or practicing chartered accountant (in respect of
other than companies) giving the percentage of local content.
However, in case of foreign bidder, certificate from the statutory auditor or cost
auditor of their own office or subsidiary in India giving the percentage of local
content is also acceptable. In case office or subsidiary in India does not exists or
Indian office/ subsidiary is not required to appoint statutory Auditors or cost
auditor, certificate from practising cost accountant or practicing chartered
accountant giving the percentage of local content is also acceptable.
(d) VOID
• The bidder shall submit an undertaking from the authorised signatory of bidder
having the power of Attorney alongwith the bid stating the bidder
meets the mandatory minimum LC requirement and such undertaking shall
become a part of the contract.
• However, in case of foreign bidder. certificate from the statutory auditor or cost
auditor of their own office or subsidiary in India giving the percentage of local
content is also acceptable. In case office or subsidiary in India does not exist or
Indian office/ subsidiary is not required to appoint statutory auditor or cost
auditor, certificate from practising cost accountant or practising chartered
accountant giving the percentage of local content is also acceptable.
8.2 Each supplier shall provide the necessary local-content documentation to the statutory
auditor or cost auditor of the company (in case of companies) or from a practicing cost
accountant or practising chartered accountant (in respect of other than companies), which
shall review and determine that local content requirements have been met, and issue
a local content certificate to that effect on behalf of procuring company, stating the
‐ 96 ‐
96 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
percentage of local content in the good or service measured. The statutory auditor or cost
auditor of the company (in case of companies) or from a practicing cost accountant or
practising chartered accountant (in respect of other than companies) shall keep all
necessary information obtained from suppliers for measurement of Local Content
confidential.
8.3 The Local Content certificate shall be submitted along with each invoice raised.
However, the % of local content may vary with each invoice while maintaining the
overall % of local content for the total work/purchase of the pro-rata local content
requirement. In case, it is not satisfied cumulatively in the invoices raised up to that
stage, the supplier shall indicate how the local content requirement would be met in
the subsequent stages.
8.4 As regards cases where currency quoted by the bidder is other than Indian Rupee,
exchange rate prevailing on the date of Notice Inviting Tender (NIT)/ Issuance of Tender
shall be considered for the calculation of Local Content.
8.5 GAIL shall also have the authority to audit as well as witness production processes to
certify the achievement of the requisite local content.
9.0 Sanctions
9.2 In the event that a manufacturer or supplier of goods and/or provider of services does not
fulfill his obligation after the expiration of the period specified in such warning, the
GAIL shall initiate action for banning such manufacturer/supplier/service provider as per
as per GAIL’s extant “Procedure for action in case
Corrupt/Fraudulent/Collusive/Coercive Practices”
9.3 A manufacturer and/or supplier of goods and/or provider of services who has been
awarded the contract after availing Purchase Preference is found to have violated the LC
provisions, in the execution of the procurement contract of goods and/or services shall be
subject to financial penalty an amount equal to 10% of the Contract Price. This financial
penalty shall be over and above the CPBG value prescribed in the contract.
9.4 In case a manufacturer and/or supplier of goods and/or provider of services desires
to change the origin of sourcing of material/services, the same may be allowed with the
understanding that in case this results in non compliance to minimum local content, the
penal action as above shall be applicable.
‐ 97 ‐
97 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
PROCEDURE FOR AWARD OF CONTRACTS/ ORDERs
1.1. In procurement of all items which are divisible in nature, the 'Class I local
supplier' shall get purchase preference over 'Class II local supplier' as well as
'Non Local Supplier' as per following procedure:
i. Among all qualified bids, the lowest bid will be termed as L1. If L1 is
'Class I local supplier', the contract for full quantity will be awarded to L1.
ii. If L1 bid is not a 'Class I local supplier', 50% of the order quantity shall
be awarded to L1. Thereafter, lowest bidder among the 'Class I Local
supplier' will be invited to match the L1 price for the remaining 50%
quantity subject to the Class I local supplier's quoted price falling within
the margin of purchase preference. and contract for that quantity shall be
awarded to such 'Class I local supplier' subject to matching the L1 price.
In case such lowest eligible 'Class I local supplier' fails to match the L1
price or accepts less than the offered quantity, the next higher 'Class I local
supplier' within the margin of purchase preference shall be invited to
match the L1 price for remaining quantity and so on, and contract shall be
awarded accordingly. In case some quantity is still left uncovered on Class
I local suppliers, then such balance quantity may also be ordered on the L1
bidder.
1.2. In the procurement of all items which are not divisible in nature and in
procurement of services where the bid is evaluated on price alone, the 'Class-I
local supplier' shall get purchase preference over 'Class-II local supplier' as
well as 'Non-local supplier', as per following procedure:
i. Among all qualified bids, the lowest bid will be termed as L1. If L1 is
'Class-I local supplier', the contract will be awarded to L1.
ii. If L1 is not 'Class-I local supplier', the lowest bidder among the 'Class-I
local supplier', will be invited to match the L1 price subject to Class-I
local supplier's quoted price falling within the margin of purchase
preference, and the contract shall be awarded to such 'Class-I local
supplier' subject to matching the L1 price.
iii. In case such lowest eligible 'Class-I local supplier' fails to match the L1
price, the 'Class-I local supplier' with the next higher bid within the
margin of purchase preference shall be invited to match the L1 price and
so on and contract shall be awarded accordingly. In case none of the
'Class-I local supplier' within the margin of purchase preference matches
the L1 price, the contract may be awarded to the L1 bidder.
B. VOID
‐ 98 ‐
98 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
FORM-1 TO ANNEXURE-V TO SECTION-III
NOT APPLICABLE
‐ 99 ‐
99 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
FORM-2 TO ANNEXURE-V TO SECTION-III
To,
Dear Sir
We, M/s____________ (Name of Bidder) confirm that as per the definition of mentioned in PP-
LC Policy we are:
It is further confirm that M/s ____________ (Name of Bidder)/ )/ M/s …………….meet the
mandatory minimum Local content requirement of ………………………% specified for Class-I
Local supplier/ Class-II Local supplier (strikethrough which is not applicable) under Policy to
Provide Purchase Preference (linked with local content).
We further confirm that in case we fail to meet the minimum local content, the same shall be
treated false information and GAIL will take action as per provision of tender document.
‐ 100 ‐
100 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
FORM-3 TO ANNEXURE-V TO SECTION-III
To,
Dear Sir
‐ 101 ‐
101 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
FORMS & FORMAT
LIST OF FORMS & FORMAT
‐ 103 ‐
103 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-1
BIDDER'S GENERAL INFORMATION
To,
M/s GAIL (INDIA) LIMITED
17th Floor, Jubilee Tower, B-35/36, Sector-1, Noida, U.P., India
‐ 104 ‐
104 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
9 E-mail address
10 Website
11 Mobile Number:
FORMAT F-2
VOID
‐ 106 ‐
106 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
FORMAT F-2A
To,
After examining / reviewing provisions of above referred tender documents (including all
corrigendum/ Addenda), we M/s____________ (Name of Bidder) have submitted our offer/ bid
no. ………………….
We, M/s____________ (Name of Bidder) hereby understand that, according to your conditions,
we are submitting this Declaration for Bid Security.
We understand that we will be put on watch list/holiday/ banning list (as per polices of GAIL in
this regard), if we are in breach of our obligation(s) as per following:
(a) have withdrawn/modified/amended, impairs or derogates from the tender, my/our Bid
during the period of bid validity specified in the form of Bid; or
(b) having been notified of the acceptance of our Bid by the GAIL during the period of bid
validity:
(i) fail or refuse to execute the Contract, if required, or
(ii) fail or refuse to furnish the Contract Performance Security, in accordance
provisions of tender document.
(iii) fail or refuse to accept ‘arithmetical corrections’ as per provision of tender
document.
‐ 107 ‐
107 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-3
LETTER OF AUTHORITY
[Pro forma for Letter of Authority for Attending 'Pre-Bid Meetings' /'Un-priced Bid Opening' /
'Price Bid Opening']
Ref: Date:
To,
M/s GAIL (INDIA) LIMITED
17th Floor, Jubilee Tower, B-35/36, Sector-1, Noida, U.P., India
Dear Sir,
I/We, _____________________________________ hereby authorize the following
representative(s) for attending any 'Meetings [Pre-Bid Meeting]', 'Un-priced Bid Opening', and
'Price Bid Opening' against the above Tender Documents:
Note:
(i) This "Letter of Authority" should be on the "letterhead" of the Bidder and should be
signed by a person competent and having the 'Power of Attorney' to bind the Bidder.
Not more than 'two [02] persons per Bidder' are permitted to attend 'Pre-Bid
Meetings' /'Un-priced Bid Opening' / 'Price Bid Opening'.
(ii) Bidder’s authorized representative is required to carry a copy of this authority letter
while attending the 'Pre-Bid Meetings' /'Un-priced Bid Opening.
‐ 108 ‐
108 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-4
___________________ BG Valid up to
Dear Sir(s),
M/s. __________________________________________________________________ having
registered office at _______________________ (herein after called the “contractor” which
expression shall wherever the context so require include its successors and assignees) have been
placed/ awarded the job/work of _______________________________________________ vide
LOA /FOA No. _______________________________dated______ for GAIL (India) Limited
having registered office at 16, Bhikaiji Cama Place, R.K. Puram, New Delhi (herein after called the
“GAIL” which expression shall wherever the context so require include its successors and
assignees).
The Contract conditions provide that the CONTRACTOR shall pay a sum of Rs.
____________________ (Rupees _________________________________________) as full
Contract Performance Guarantee in the form therein mentioned. The form of payment of Contract
Performance Guarantee includes guarantee executed by Nationalized Bank/Scheduled Commercial
Bank, undertaking full responsibility to indemnify GAIL (INDIA) LIMITED, in case of default.
‐ 109 ‐
109 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
M/s.__________________________ and such postponement forbearance would not have
the effect of releasing the bank from its obligation under this debt.
1. The Bank Guarantee by successful Bidder(s) will be given on non-judicial stamp paper
as per 'stamp duty' applicable. The non-judicial stamp paper should be in name of the
issuing bank.
2. The Bank Guarantee by Bidders will be given from bank as specified in cl.no. 38.3 of
ITB [Section-III] of Tender Document.
3. A letter from the issuing bank of the requisite Bank Guarantee confirming that said Bank
Guarantee and all future communication relating to the Bank Guarantee shall be
forwarded to Employer.
4. If a Bank Guarantee is issued by a commercial bank, then a letter to Employer and copy
to Consultant (if applicable) confirming its net worth is more than Rs. 100,00,00,000.00
[Rupees One Hundred Crores] or its equivalent in foreign currency alongwith
documentary evidenceOR in the Bank Guarantee itself.
5. Contractor shall submit attached cover letter (Annexure) while submitting Contract
Performance Security
‐ 111 ‐
111 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
‐ 112 ‐
112 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-5
This Questionnaire duly filled in, signed & stamped must form part of Bidder’s Bid and should
be returned along with Un-priced Bid. Clauses confirmed hereunder need not be repeated in the
Bid.
‐ 115 ‐
115 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Sl. DESCRIPTION BIDDER'S
CONFIRMATION
22. Bidder hereby confirms that they are not on ‘Holiday’ by
GAIL or Public Sector Project Management Consultant (like
EIL, Mecon only due to “poor performance” or “corrupt and
fraudulent practices”) or banned by Government
department/ Public Sector on due date of submission of bid.
Bidder also confirms that they are not under any liquidation,
court receivership or similar proceedings or 'bankruptcy'.
‐ 116 ‐
116 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Sl. DESCRIPTION BIDDER'S
CONFIRMATION
25. Bidder confirms that (i) any variation in GST at the time of
supplies for any reasons, other than statutory, including
variations due to turnover, shall be borne by them and (ii)
any error of interpretation of applicability of rate of GST
(CGST & SGST/ UTGST or IGST) on components of an
item and/or various items of tender by them shall be dealt as
per clause no. 13.13 of Section-III.
26. Bidders confirm to submit signed copy of Integrity Pact
(wherever included in tender).
‐ 117 ‐
117 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-6
ACKNOWLEDGEMENT CUM CONSENT LETTER
To,
Dear Sir,
We hereby acknowledge receipt of a complete set of bidding document along with enclosures for
subject item/job and/or the information regarding the subject tender.
We intend to bid as requested for the subject item/job and furnish following details with
respect to our quoting office:
‐ 118 ‐
118 of 896
F-7
BIDDER’S EXPERIENCE
To,
Sl. Descript LOA Full Postal Value Date of Scheduled Date of Reasons
No ion of /WO Address & of Commenc Completio Actual for delay
the No. phone nos. of Contrac ement of n Time Comple in
Services and Client. Name, t/Order Services (Months) tion executio
date designation (Specify n, if any
and address of Currenc
Engineer/ y
Officer-in- Amount)
Charge (for
cases other
than
purchase)
(1) (2) (3) (5) (6) (7) (8) (9) (10)
119 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-8 (A)
CHECK LIST
Bidders are requested to duly fill in the checklist. This checklist gives only certain important
items to facilitate the bidder to make sure that the necessary data/information as called for in the
bid document has been submitted by them along with their offer. This, however, does not relieve
the bidder of his responsibilities to make sure that his offer is otherwise complete in all respects.
Please ensure compliance and tick (√) against following points:
S. No. DESCRIPTION CHECK REFERENCE
BOX PAGE NO. OF THE
BID SUBMITTED
1.0 Digitally Signing (in case of e-bidding)/ Signing and Stamping
(in case of manual bidding) on each sheet of offer, original
bidding document including SCC, ITB, GCC ,SOR/BOQ
drawings, corrigendum (if any)
2.0 Confirm that the following details have been submitted in the
Un-priced part of the bid
i Covering Letter, Letter of Submission
5.0 VOID
120
120 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
121
121 of 896
F-8(B)
CHECKLIST FOR BID EVALUATION CRITERIA (BEC) QUALIFYING DOCUMENTS
(refer Section II of Tender document)
BEC Description Documents required for qualification Documents Submitted Documents Reference
Clause by Bidder attested as per Page No. of the
No. Section-II of Bid submitted
Tender
Technical BEC
A.1 Experience as a (a) Detailed work order along with Schedule of Rates.
single bidder (b) Completion certificate issued by end user / Owner Yes/No
(or their consultant who has been duly authorized by
owner to issue such certificate).
122 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
123
123 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Note Job executed for Tax paid invoice(s) duly certified by statutory auditor Yes/No
to A (i) Subsidiary / of the bidder towards payment of statutory tax in
Fellow subsidiary/ support of the job executed for Subsidiary / Fellow
Holding company. subsidiary/ Holding company.
Financial BEC
1. Annual Turn Over Audited Financial Statements [including Auditor’s Submitted Yes/No
Report, Balance sheet, Profit & Loss Accounts
statements, Notes & schedules etc.] for last Audited
Financial Year. [In case the Annual Turnover criteria is (Mention specific
not met in last Audited Financial Year, then the Audited year…………… )
Financial Statements for previous two years of last
Audited Financial Year is to be submitted]
2. Net Worth Audited Financial Statements [including Auditor’s Submitted Yes/No
Report, Balance sheet, Profit & Loss Accounts
statements, Notes & schedules etc.] for last Audited
Financial Year. (Mention specific year
……………)
3. Working Capital Audited Financial Statements [including Auditor’s Submitted Yes/No
Report, Balance sheet, Profit & Loss Accounts
statements, Notes & schedules etc.] for last Audited
Financial Year. (Mention specific
year…………… )
If the bidder’s working capital is negative or inadequate,
the bidder shall submit a letter (in prescribed format)
from their bank having net worth not less than Rs.100
Crores, confirming the availability of line of credit for at Submitted/ Not
least working capital requirement as stated above. Applicable
(Bidder to tick
appropriate option)
124
124 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
4. Format for Details Bidder shall submit “Details of financial capability of Submitted
of financial Bidder” in prescribed format duly signed and stamped
capability of by a chartered accountant / Certified Public Accountant
Bidder (CPA).
125
125 of 896
F-9
FORMAT FOR CERTIFICATE FROM BANK
IF BIDDER’S WORKING CAPITAL IS INADEQUATE/NEGATIVE
(To be provided on Bank’s letter head)
Date:
To,
M/s. GAIL (India) Limited
17th Floor, Jubilee Tower, B-35/36, Sector-1, Noida, U.P., India
Dear Sir,
This is to certify that M/s ………………………………….. (name of the Bidder with address)
(hereinafter referred to as Customer) is an existing Customer of our Bank.
The Customer has informed that they wish to bid for GAIL’s Tender No.
.................................................. dated …………… for
……………………………………..(Name of the supply/work/services/consultancy) and as per
the terms of the said Tender Document they have to furnish a certificate from their Bank
confirming the availability of line of credit.
It is also confirmed that the net worth of the Bank is more than Rs. 100 Crores (or Equivalent
USD) and the undersigned is authorized to issue this certificate.
Yours truly
(Authorized signatory)
Name of the signatory :
Designation :
Email Id :
Contact No. :
Stamp
Note:
This Declaration Letter for line of credit shall be from single bank only. Letters from multiple
banks shall not be applicable. However, banking syndicate will be acceptable wherein a group of
banks can jointly provide line of credit to the bidder.
The bank shall be required to issue the letter for declaration/ certificate of line of credit on their
letter head along with the contact details of the issuing authority like email id, contact number
etc.
126 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-10
FORMAT FOR CHARTERED ACCOUNTANT CERTIFICATE/ CERTIFIED PUBLIC
ACCOUNTANT (CPA) FOR FINANCIAL CAPABILITY OF THE BIDDER
We have verified the Audited Financial Statements and other relevant records of
M/s……………………………… (Name of the bidder) and certify the following:
*Refer Instructions
Note: It is further certified that the above mentioned applicable figures are matching with
the returns filed with Registrar of Companies (ROC) [Applicable only in case of Indian
Companies]
127
127 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Instructions:
1. The Separate Pro-forma shall be used for each member in case of JV/ Consortium.
2. The financial year would be the same as one normally followed by the bidder for its
Annual Report.
3. The bidder shall provide the audited annual financial statements as required for this
Tender document. Failure to do so would result in the Proposal being considered as non-
responsive.
(i) Annual Turnover shall be “Revenue from Operations” as per Profit & Loss
account of audited annual financial statements
(ii) Working Capital shall be “Current Assets less Current liabilities” and
(iii) Net Worth shall be Paid up share capital plus Free Reserves & Surplus less
accumulated losses, deferred expenditure and miscellaneous expenditure not
written off, if any.
5. Above figures shall be calculated after considering the qualification, if any, made by
the statutory auditor on the audited financial statements of the bidder including
quantified financial implication.
(Page 2 of 2)
128
128 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-11
FORMAT FOR CONSORTIUM AGREEMENT
(ON NON- JUDICIAL STAMP PAPER OF APPROPRIATE VALUE)
CONSORTIUM/JV AGREEMENT
DELETED
129
129 of 896
F-12
BIDDER'S QUERIES FOR PRE BID MEETING
To,
SUB: LAYING & CONSTRUCTION OF STEEL GAS PIPELINE AND TERMINALS ALONG WITH ASSOCIATED
FACILITIES FOR ANGUL-SRIKAKULAM PIPELINE PROJECT ( PART-B)
TENDER NO: 05/51/23VA/GAIL/001(i)-3 (Tender ID : 2021_GAIL_99063)
SL.
NO. REFERENCE OF BIDDING DOCUMENT BIDDER'S QUERY GAIL'S REPLY
Subject
NOTE: The Pre-Bid Queries may be sent by e-mail before due date for receipt of Bidder's queries.
130 of 896
F-13
E-Banking Mandate Form
(To be issued on vendors letter head)
1. Vendor/customer Name :
2. Vendor/customer Code:
I/We hereby authorize GAIL(India) Limited to release any amount due to me/us in the bank account as
mentioned above. I/We hereby declare that the particulars given above are correct and complete. If the
transaction is delayed or lost because of incomplete or incorrect information, we would not hold the
GAIL (India) Limited responsible.
(Signature of vendor/customer)
BANK CERTIFICATE
131 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-14
INTEGRITY PACT
132
132 of 896
133 of 896
134 of 896
135 of 896
136 of 896
137 of 896
138 of 896
139 of 896
140 of 896
141 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-15
INDEMNITY BOND
WHEREAS GAIL (India) Ltd. (hereinafter referred to as “GAIL”) which expression shall, unless
repugnant to the context include itssuccessors and assigns, having its registered office at 16, Bhikaiji,
Cama Place, R.K. Puram, New Delhi 110066 has entered into a contract with
M/s*…………………………. (hereinafter referred to as the “Contractor”) which expression shall
unless repugnant to the context include its representatives, successors and assigns, having its registered
office at *………………….. and on the terms and conditions as set out, inter-alia in the [ mention the
work order/LOA/Tender No.]and various documents forming part thereof, hereinafter collectively
referred to as the ‘CONTRACT’ which expression shall include all amendments, modifications and / or
variations thereto.
GAIL has also advised the Contractor to execute an Indemnity Bond in general in favour of GAIL
indemnifying GAIL and its employees and Directors including Independent Directors from all
consequences which may arise out of any prospective litigation or proceedings filed or may be initiated
by any third party, including any Banker / financial institution / worker(s) /vendor(s)/ subcontractor(s)
etc. who may have been associated or engaged by the Contractor directly or indirectly with or without
consent of GAIL for above works.
NOW, THEREFORE, in consideration of the promises aforesaid, the Contractor hereby irrevocably and
unconditionally undertakes to indemnify and keep indemnified GAIL and all its employees, Directors,
including Independent Directors, from and against all/any claim(s), damages, loss, which may arise out
of any litigations/ liabilities that may be raised by the Contractor or any third party against GAIL under
or in relation to this contract. The Contractor undertakes to compensate and pay to GAIL and/or any of
its employees, Directors including Independent Directors, forth with on demand without any protest the
amount claimed by GAIL for itself and for and on behalf of its employees, Directors including
Independent Directors together with direct/indirect expenses including all legal expenses incurred by
them or any of them on account of such litigation or proceedings.
(i) This Indemnity shall remain valid and irrevocable for all claims of GAIL and/or any of its
employees and Directors including Independent Directors arising out of said contract with
respect to any such litigation / court case for which GAIL and/or its employees and Directors
including Independent Directors has been made party until now or here-in-after.
The undersigned has full power to execute this Indemnity Bond for and on behalf of the
133
142 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
SIGNED BY :
For [ Contractor]
Authorised Representative
Place:
Dated:
Witnesses:
1.
2
134
143 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-16
2.0 Should the Bid Evaluation Criteria Yes. Please refer Section II of Tender
documents be attested? document
3.0 Is attending Pre Bid
Meeting No. Refer Clause No. 17 of Instruction to
mandatory. Bidders of Tender Document. However
attending Pre Bid Meeting is recommended
to sort out any issue before submission of bid
by a Bidder.
4.0 Can a vendor submit more than 1 offer? No. Please refer Clause No. 4 of Instruction
to Bidders of Tender Document.
5.0 Is there any Help document available Refer FAQs as available on GAIL E-Tender
for e-Tender. portal.
6.0 Are there are any MSE (Micro & Small Yes. Refer Clause No. 40 of Instructions to
Enterprises) benefits available? Bidders of Tender Document.
7.0 Are there are any benefits available to Refer Clause No. 49 of Instructions to
Startups? Bidders of Tender Document.
135
144 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-17
To,
M/s GAIL (INDIA) LIMITED
………………………
SUB: ……………………………………
PO NO: ………………………………….
Dear Sir,
We _______________________ (Name of the Supplier) hereby confirm that E-Invoice provision as per
the GST Law is
(i) Applicable to us [ ]
In case, same is applicable to us, we confirm that we will submit E-Invoice after complying with all the
requirements of GST Laws. If the invoice issued without following this process, such invoice can-not be
processed for payment by GAIL as no ITC is allowed on such invoices. We also confirm that If input tax
credit is not available to GAIL for any reason attributable to Supplier (both for E-invoicing cases and
non-E-invoicing cases), then GAIL shall not be obligated or liable to pay or reimburse GST (CGST &
SGST/UTGST or IGST) claimed in the invoice(s) and shall be entitled to deduct / setoff / recover such
GST amount (CGST & SGST/UTGST or IGST) or Input Tax Credit amount together with penalties and
interest, if any, by adjusting against any amounts paid or becomes payable in future to the Supplier
under this contract or under any other contract.
136
145 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Format F-18
POWER OF ATTORNEY
SUB: LAYING & CONSTRUCTION OF STEEL GAS PIPELINE AND TERMINALS ALONG
WITH ASSOCIATED FACILITIES FOR ANGUL-SRIKAKULAM PIPELINE
PROJECT ( PART-B)
TENDER NO: 05/51/23VA/GAIL/001(i)-3 (Tender ID : 2021_GAIL_99063)
Name of Bidder:____________________
The signature of the authorized person/(s) herein constitutes unconditional obligations of M/s
_______________________ (Name of bidder).
This Power of Attorney shall remain valid and in full force and effect before we withdrawal it in
writing (by fax, or mail or post). All the documents signed (within the period of validity of the
Power of Attorney) by the authorized person/(s) herein shall not be invalid because of such
withdrawal.
_____________________________
137
146 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
_____________________________
(Name of person)
E-mail id: …………………………
Digital token no. used for uploading the bid: …………………..
(*)In case of a Single Bidder, Power of Attorney issued by the Board of Directors/ CEO / MD /
Company Secretary of the Bidder/ all partners in case of Partnership firm/Proprietor (for
Proprietorship firm) in favour of the authorized employee(s) of the Bidder, in respect of the
particular tender for signing the Bid and all subsequent communications, agreements, documents
etc. pertaining to the tender and to act and take any and all decision on behalf of the Bidder, is to
be submitted.
138
147 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-19
This is to certify that M/s. (Bidder’s Name), having their registered office at (Bidder’s Address), is the
owner of the equipment mentioned below (or in the attachment) as per our inspection of records / books
of accounts / documents of M/s. (Bidder’s Name) on (Date).
Further, these equipment will be deployed for (Project Name) in case M/s. (Bidder’s Name) is
awarded with the job.
Place: ---------
Date: DD.MM.YYYY
Note: The above certificate shall be issued in the letter head of Chartered Accountant / Statutory
Auditor.
139
148 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-20
During our visit to various storage yards and project sites of M/s. (Bidder’s Name), from (Date) to
(Date), we have inspected the condition of equipment mentioned below (or in attachment).
We certify that the below mentioned equipment are in good health and working condition presently.
Further, these equipment are fit be deployed in Project Name.
Place: --------- \
Date: DD.MM.YYYY
Note: The above certificate shall be issued in the letter head of Chartered Engineer.
140
149 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-21
COMPLETION CERTIFCATE
ON LETTER HEAD
COMPLETION CERTIFICATE
Name of Work :
Name of Contractor :
Contractual Value :
141
150 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Certified that all the works under the subject Contract have been completed as per contractual
terms & conditions, specifications, drawings and approved deviations etc. to the satisfaction of
Engineer-In-Charge.
(xxxxxxxxxxxx)
Engineer – In – Charge
142
151 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Format F-22
NO CLAIM CERTIFICATE
We, _________________, a company incorporated under the laws of India/ a Consortium between *___
and *____ (name of Consortium partners to be inserted)/ a Partnership Firm consisting of *___ and
*___ (name of Partners to be inserted)/ a Sole Proprietorship (as the case may be), having its registered
office at __________________ and carrying on business under the name and style M/s.
_______________________ were awarded the contract by GAIL (India) Ltd. in reference to Tender No.
______________ dated _______ (“Contract”).
After completion of the above-said Work under the contract, we have scrutinized all our claims,
contentions, disputes, issues and we hereby confirm that after adjusting all payments received by us
against our R.A. Bills, our balance entitlement under the Contract is to a sum of Rs. __________
(Rupees _________ only) as per our Final Bill dated ________ towards full and final settlement of all
our claims, dues, issues and contentions from GAIL (India) Ltd.
We confirm and declare that with the receipt of aforesaid monies, all our claims, dues, disputes,
differences between M/s. ___________ and GAIL (India) Ltd. under and with reference to said Contract
stands fully and finally settled.
We further absolve GAIL (India) Ltd. from all liabilities present or future arising directly or indirectly
out of the Contract.
We further confirm that the present settlement has been arrived at after mutual negotiations and is freely
and fairly entered into between the parties. There is no economic duress or any other compulsion on us
in entering into this settlement.
Dated :
143
152 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-23
PROFORMA OF BANK GUARANTEE FOR MOBILISATION ADVANCE
Ref................
Date...............
In consideration of the GAIL (India) Limited, hereinafter called the "Owner" which expression shall
unless repugnant to the context or meaning thereof include its successors, executors, administrators and
assignees, having awarded to M/s............................. having its registered office at ...............................
hereinafter referred as the 'CONTRACTOR', which expression shall unless repugnant to the context or
meaning thereof, include its successors, administrators, executors and assignees, a contract hereinafter
referred to as the 'Contract' for related works................ referred to as the 'WORK' on terms and
conditions set out, inter-alia in the Owner's Contract No.............dated............ valued
at........................................ (in words & figures) and as the Owner having agreed to make an advance
payment (herein referred as Mobilization advance) for the performance of the above contract to the
CONTRACTOR amounting to.............................(in words & figures) as an advance against Bank
Guarantee to be furnished by the CONTRACTOR.
The OWNER shall have the fullest liberty without affecting in any way the liability of the BANK under
this guarantee, from time to time to vary the advance or to extend the time for performance of the works
by the CONTRACTOR. The BANK shall not be released from its liability under these presents by any
exercise of the Owner of the liberty with reference to the matter aforesaid.
144
153 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
The Owner shall have the fullest liberty, without reference to CONTRACTOR and without affecting this
guarantee to postpone for any time or from time to time the exercise of any powers vested in them or of
any right which they might have against the CONTRACTOR, and to exercise the same at any time in
any manner, and either to enforce or to forebear to enforce any power, covenants contained or implied in
the Contract between the OWNER and the CONTRACTOR or any other course or remedy or security
available to the OWNER and the BANK shall not be released of its obligations under these presents by
any exercise by the OWNER of its liberty with reference to matters aforesaid or other acts of omission
or commission on the part of the OWNER or any other law would, but for this provision, have the effect
of releasing the BANK.
The right of the OWNER to recover the outstanding sum of advance upto Rs.................. from the BANK
in the manner aforesaid is absolute and unequivocal and will not be affected or suspended by reason of
the fact that any dispute or disputes has or have been raised by the CONTRACTOR and/or that any
dispute or disputes is or are pending before any officer, tribunal or court or arbitrator or any other
authority / forum and any demand made by OWNER on the BANK shall be conclusive and binding.
The BANK further undertakes not to revoke this guarantee during its currency without previous consent
of the OWNER and further agrees that the guarantee contained shall continue to be enforceable until it is
discharged by GAIL in writing.
The BANK also agrees that the OWNER shall at its option be entitled to enforce this guarantee against
the BANK as a principal debtor, in the first instance, notwithstanding any other security or guarantee
that OWNER may have in relation to the CONTRACTOR's liabilities towards the said advance.
The amount under the Bank Guarantee is payable forthwith without any delay by Bank upon the written
demand raised by GAIL. Any dispute arising out of or in relation to the said Bank Guarantee shall be
subject to the exclusive jurisdiction of courts at New Delhi.
Therefore, we hereby affirm that we are guarantors and responsible to you on behalf of the Contractor
up to a total amount of (amount of guarantees in words and figures) and we undertake to pay you, upon
your first written demand declaring the Contractor to be in default under the contract and without caveat
or argument, any sum or sums within the limits of (amount of guarantee) as aforesaid, without your
needing to prove or show grounds or reasons for your demand or the sum specified therein.
Notwithstanding anything contained hereinabove, our liability under this guarantee is restricted to
_________ and it will remain in force upto and including _____________ and shall be extended from
time to time for such periods as may be advised by M/s on whose behalf this guarantee has been given.
We have power to issue this guarantee in your favour under Memorandum and Articles of Association
and the undersigned has full power to do so under the Power of Attorney/ resolution of the Board of
Directors dated............... accorded to him by the BANK.
145
154 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
Dated.................this.............day of...............20...............
Signed by
Place:
WITNESS :
1...................................... (Signature)
2...................................... (Designation)
......................................
(Common Seal)
146
155 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
1. The Bank Guarantee by successful bidder(s) will be given on non-judicial stamp paper as
per stamp duty applicable. The non-judicial stamp paper should be in name of the issuing
bank. In case of foreign bank, the said bank guarantee to be issued by its correspondent
bank in India on requisite non-judicial stamp paper and place of bid to be considered as
Noida.
2. The bank guarantee by bidders will be given from bank as specified in ITB.
3. A letter from the issuing bank of the requisite Bank Guarantee confirming that said bank
guarantee and all future communication relating to the Bank Guarantee shall be
forwarded to Employer
4. If a bank guarantee is issued by a commercial bank, then a letter to Owner confirming its
net worth is more than Rs. 1,000,000,000/- (Rupees one hundred Crores). or its
equivalent in foreign currency along with a documentary evidence.
147
156 of 896
‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐‐
F-24
UNDERTAKING REGARDING SUBMISSION CONTRACT PERFORMANCE SECURITY/ SD
WITHIN STIPULATED TIME LINE
(to be submitted on letter head of bidder)
To,
SUB: LAYING & CONSTRUCTION OF STEEL GAS PIPELINE AND TERMINALS ALONG
WITH ASSOCIATED FACILITIES FOR ANGUL-SRIKAKULAM PIPELINE
PROJECT ( PART-B)
TENDER NO: 05/51/23VA/GAIL/001(i)-3 (Tender ID : 2021_GAIL_99063)
Dear Sir,
We hereby confirm that we have clearly understood the requirement of Contract Performance Security/
SD specified in the tender document.
We also hereby confirm that in case of award of contract / order, we will submit Contract Performance
Security/ SD within 30 days from the date of Fax of Acceptance.
148
157 of 896
FORMAT F-25
CHECKLIST FOR RUNNING BILLS
Signature Of
SL.No Document Description Annexure
Contractor PMC GAIL
(A) Bill Specific point
14
Whether bill has sent through BWS or not(attach BWS receipt)
Signature Of
SL.No Document Description Annexure
Contractor PMC GAIL
(B) General Points
(a) Copy of contractor all risk policy
1
(b) Validity of above exist or not
(a) Free issue material (FIM) insurance copy
2
(b)Validity of above exists or not
(a) Copy of indemnity bond for FIM
3
(b) Validity of above exist or not
(a) Employee Insurance Policy
4
(b) Validity of above exist or not
(a) Workman Compensation insurance policy
5
(b) Validity of above exist or not
(a) Copy of contrac PBG separetly for INR & forign currency
8 price
(b) Validity of above exist or not
9 Contract agreement copy
Power of attorny in the name of signatory of the bill /indemnity
10
bond
11 Copy of PAN umber of contractor
Copy of Contract registration certificate with RBI in case of
12
forign contractor
Copy of registration certificate of TIN/Tan of concerened state
13 in which WOT is deducted & deposited
NOTE :-
1 There will be signature of concerned contractor, PMC & GAIL representative in place
2 Cenvatalbe invoice, Memorundum of payment to be signed by GAIL Section In-charge & GAIL Construction Incharge
3 Abstract of Payment, measurement sheets are to be signed by GAIL Section Incharge/ his repersentative
4 GAIL spread in-charge / construction in-charge may also require to sign any other relevent documents as applicable from
case to case.
5 NOC from sub-contractor, if any (deployed after getting approval from GAIL / PMC) regarding receipt of payment
from contractor upto previous month.
6 In case of final bill contractor shall be required to submit NOC & Indeminity Bond and also NOC from sub-contractor about receipt of full payment from the contractor.
7 Copy of Hindrance register for the specified period (RA Bill period) dully signed by contractor /PMC/GAIL/ to be submitted alongwith RA Bill.
160 of 896
SECTION – V
SPECIAL CONDITION OF CONTRACTS
(SCC)
&
ANNEXURES to SCC
161 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 1 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
SPECIAL CONDITIONS
OF
CONTRACT
162 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 2 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
INDEX
1.0 GENERAL
2.0 SCOPE OF WORK & SCOPE OF SUPPLY
3.0 SUPPLY OF WATER, POWER & OTHER UTILITIES
4.0 COMPLETION SCHEDULE/ COMPLETION PERIOD
5.0 DRAWINGS AND DOCUMENTS
6.0 COMPLIANCE WITH LAWS
7.0 GOVERNMENT OF INDIA NOT LIABLE
8.0 REGISTRATION OF THE CONTRACT WITH STATUTORY
AUTHORITIES (FOR FOREIGN BIDDER)
9.0 LIMITATION OF LIABILITY
10.0 WORKS TO BE CARRIED OUT BY CONSORTIUM LEADER AND
MEMBER - DELETED
11.0 CONTRACT PERFORMANCE SECURITY/ SECURITY DEPOSIT
12.0 TAXES, DUTIES AND LEVIES IN INDIA
13.0 TAXES, DUTIES AND LEVIES IN FOREIGN COUNTRIES
14.0 SUBSEQUENT LEGISLATION
15.0 DELETED
16.0 INCOME TAX & CORPORATE TAX
17.0 CUSTOM DUTY
18.0 CUSTOM DUTY ON CONSTRUCTION EQUIPMENTS
19.0 ISSUE OF ESSENTIALITY CERTIFICATE
20.0 IMPORT LICENCE
21.0 WITHHOLDING, ACCOUNTING AND TAX REQUIREMENTS
22.0 INTELLECTUAL PROPERTY
23.0 FIRM PRICE
24.0 WORKS CONTRACT
25.0 PROVIDENT FUND ACT
26.0 MOBILIZATION ADVANCE
27.0 CHANGE ORDERS/ EXTRA WORKS/ DEVIATIONS
28.0 CONSTRUCTION RIGHT -OF-USE AND PERMITS
29.0 CONSTRUCTION EQUIPMENT AND ORGANIZATION
30.0 MECHANISED CONSTRUCTION
31.0 GENERAL GUIDELINES DURING AND BEFORE ERECTION
32.0 PRICE ADJUSTMENT DUE TO DELAYED MOBILISATION OR
SHORTFALL IN DEPLOYMENT OF EQUIPMENT AND KEY
PERSONNEL
33.0 MEASUREMENT OF WORKS
163 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 3 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
164 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 4 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
165 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 5 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
1.0 GENERAL
1.1 Special Conditions of Contract shall be read in Conjunction with the General
conditions of Contract, specification of work, Drawings and any other
documents forming part of this Contract wherever the context so requires.
1.2 Notwithstanding the sub-division of the documents into these separate sections
and volumes, every part of each shall be deemed to be supplementary to and
complementary of every other part and shall be read with and into the Contract
so far as it may be practicable to do so.
1.4 Wherever it is mentioned in the specifications that the Contractor shall perform
certain work or provide certain facilities, it is understood that the Contractor
shall do so at his own cost and the value of contract shall be deemed to have
included cost of such performance and provisions, so mentioned.
1.5 The materials, design, and workmanship shall satisfy the relevant Indian
Standards, the Job Specifications contained herein and Codes referred to.
Where the job specification stipulate requirements in addition to those
contained in the standard codes and specifications, these additional
requirements shall also be satisfied.
i) Contract Agreement
ii) Detailed Letter of Acceptance along with Statement of Agreed
Variations.
iii) Fax / Letter of Intent / Fax of Acceptance.
iv) Schedule of Rates as enclosures to Letter of Acceptance.
v) Job / Particular Specifications.
166 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 6 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
vi) Drawings
vii) Technical / Material Specifications.
viii) Special Conditions of Contract.
ix) Instruction to Bidders
x) General Conditions of Contract.
xi) Indian Standards
xii) Other applicable Standards
1.8 In the absence of any Specifications covering any material, design of work (s)
the same shall be performed / supplies / executed in accordance with Standard
Engineering Practice as per the instructions / directions of the Engineer-in-
Charge, which will be binding on the Contractor.
1.9 In case of any conflict in technical requirements among PJS, TS, SCC, SOR
etc. of tender document and international / national codes / standards, more
stringent requirement shall govern or as per the decision of EIC.
167 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 7 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
3.3 Contractor shall, if required by him, for the entire duration of the execution of
the work make available near the site, land for construction of Contractor’s
office, Warehouse, Workshops and for any purpose in connection with
providing infrastructure required for the execution of the Contract. The
Contractor shall at his own cost construct all temporary buildings and provide
suitable water supply and sanitary arrangement as required. On completion of
the work undertaken by the Contractor, he shall remove all temporary works
erected by him and have the site cleared as directed by Engineer-in-Charge. If
the Contractor shall fail to comply with these requirements, the Engineer-in-
Charge may at the expense of the Contractor remove such surplus and rubbish
materials and dispose off the same as he deems fit and get the site cleared as
aforesaid, and the Contractor shall forthwith pay the amount of all expenses so
incurred and shall have no claims in respect of any such surplus material
disposed of as aforesaid.
3.4 Cutting of trees shall not be permitted except in the case that tree is falling on
the line of ROU/ROW. In such circumstances, details of such tree being cut
shall be prepared and forest/ municipal authorities be informed and necessary
approval be obtained by contractor.
4.1 The work shall be executed strictly as per completion schedule / completion
period given in Annexure-3 to SCC in the bidding document. The period of
completion given includes the time required for mobilization as well as testing,
rectifications, if any, retesting and completion in all respects to the entire
satisfaction of the Engineer-in-Charge.
4.2 A joint programme of execution of work will be prepared by the Engineer-in-
Charge and Contractor. This programme will take into account the time of
completion mentioned above.
4.3 Monthly/ weekly construction programme will be drawn up by Engineer-in-
Charge jointly with the contractor based on availability of work fronts and the
joint construction programmes as above clause. The Contractor shall
scrupulously adhere to these Targets/ Programme by deploying adequate
personnel, construction tools & tackles and shall also supply all materials of his
scope of supply in good time to achieve the targets set out in the weekly and
168 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 8 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
monthly programme. In all matters concerning the extent of targets set out in
the weekly and achievements, the decision of the Engineer-in-Charge shall be
final and binding on the contractor.
4.4 If the Contractor fails to achieve the targeted progress schedule of each month
as mentioned in the bidding document, the Employer/Consultant at its option,
may terminate the contract as contractor’s default and get the work completed
from other sources at contractor’s risk & cost.
4.5 Contractor shall give every day report on category wise labour and equipment
deployed along with the progress of work done on previous day in the
proforma prescribed by the Engineer-in-Charge.
4.6 The contractor shall submit fortnightly report covering all major activities
indicating schedule / actual progress, slippages & its reasons and catch up plan.
4.7 The Bidder shall also consider local labour / Trade unionism in the state while
quoting. No waiver shall be attributable to the stoppage due to union activities
& due to the influence of trade unionism and adverse weather conditions.
5.1 The drawings accompanying the bid document (if any) are of indicative nature
and issued for bidding purpose only. Purpose of these drawing is to enable the
bidder to make an offer in line with the requirements of the Employer /
Consultant. However no extra claim whatsoever, shall be entertained for
variation in the "Approved for Construction" and "Bid document drawings"
regarding any changes/units. Construction shall be as per drawings /
specifications issued/approved by the Engineer-in-Charge during the course of
execution of work. Detailed construction drawings (wherever required) on the
basis of which actual execution of work is to proceed will be prepared by the
contractor.
169 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 9 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
drawings. MECON shall review the drawings/ documents within two weeks
from the date of submission provided the same are accompanied by relevant
calculations, data as required and essential for review.
5.5 Copies of all detailed working drawing relating to the works shall be kept at the
contractors’ office at the site and shall be made available to the Engineer-in-
charge/ Employer/Consultant at any time during execution of the contract.
However no extra claim what so ever shall be entertained for any variation in
the “approved/issued for construction drawings” and “tender drawings”
regarding any changes/units unless otherwise agreed.
5.6 The Contractor shall rectify any inaccuracies, errors and non-compliance to
contractual requirements. Any delay occurring on this shall not construe a
reason for delay/ extension.
6.1 The Contractor shall abide by all applicable rules, regulations, statutes, laws
governing the performance of works in India, including but not limited to the
following:
i) Contract Labour (Regulation & Abolition) Act 1970 & the centre rules,
1971 framed there under.
ii) Payment of Wages Act.
170 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 10 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
7.1 It is expressly understood and agreed by and between the Contractor and the
Employer/Consultant that the Employer/Consultant is entering into this
agreement solely on its own behalf and not on behalf of any other person or
entity. In particular, it is expressly understood and agreed that the Government
of India is not a party to this agreement and has no liabilities, obligations or
rights there under. It is expressly understood and agreed that the
Employer/Consultant is an independent legal entity with power and authority to
enter into contract, solely in its own behalf under the applicable laws of India
and general principal of Contract Law. The Contractor expressly agrees,
acknowledges and understands that the Employer/Consultant is not an agent,
representative or delegate of Govt. of India. It is further understood and agreed
that the Govt. of India is not and shall not be liable for any acts, omissions,
commissions, breaches or other wrongs arising out of the contract.
Accordingly, contractor hereby expressly waives, releases and foregoes any
and all actions or claims, including cross claims, impleader claims or counter
claims against the Govt. of India arising out of this contract and covenants not
to sue to Govt. of India as to any manner, claim, cause of action or thing
whatsoever arising of or under this agreement.
8.1 DELETED
171 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 11 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
11.1 Please refer clause no. 38 of ITB (Vol I) and clause no. 24.0 of GCC (General
Condition of Contract).
11.2 In addition to clause no.38 of ITB and 24 of GCC following will also apply:-
172 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 12 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
Contractor’s warranty/guarantee for the work done by him or for the Works
supplied and performance as per the specifications and any other conditions
against this Contract. The warranty/guarantee shall remain in force for 12
months from the date of issuance of certificate of Completion and Acceptance
against this Contract as per GCC. Contractor shall also arrange for the
Performance Guarantee to remain valid until expiration of the guarantee period
for entire works covered under the contract.
12.1 The Contractor agrees to and does hereby accept full and exclusive liability for
the payment of any and all taxes, duties, including GST etc. now in force and
hereafter increased, imposed or modified from time to time in respect of works
and materials and all contributions and taxes for unemployment compensation,
insurance and old age pensions or annuities now or hereafter imposed by any
Central or State Government authorities which are imposed with respect to or
covered by the wages, salaries, or other compensations paid to the persons
employed by the Contractor and the Contractor shall be responsible for the
compliance with all obligations and restrictions imposed by the Labour Law or
any other law affecting employer-employee relationship and the Contractor
further agrees to comply, and to secure the compliance of all subcontractors
with all applicable Central, State, Municipal and local law and regulation, and
requirement of any central, State or Local Government agency or authority.
Contractor further agrees to defend, indemnify and hold Employer/Consultant
harmless from any liability or penalty which may be imposed by the Central,
State or Local authorities by reason of any violation by Contractor or
Subcontractor of such laws, regulations or requirements and also from all
claims, suits or proceedings that may be brought against the Employer /
Consultant arising under, growing out of, or by reason of the work provided for
by this Contract, by third parties, or by Central or State Government authority
or any administrative sub-division thereof. The prices shall also be inclusive of
173 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 13 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
GST as applicable.
12.2 Employer/Consultant shall make from Contractors’ bills such tax deductions as
are required as per rules and regulations in force from time to time.
12.3 If GST is applicable during site fabrication, the same must be assessed and
deemed to be included by the bidder in the quoted prices. The bidder in this
regard shall arrange all required formalities.
12.4 Bidder shall take care of all applicable taxes & duties while submitting their
prices.
13.1 The Contractor agrees to and does hereby accept full and exclusive liability at
is own cost for the payment of any and all taxes, duties and levies etc as are
payable to any government, local or statutory authority in any country other
than India, as in force on bid due date or as hereafter imposed, increased or
modified, and as are payable by Contractor, his agents, sub-contractor and their
employees etc. for performance of work under this contract. The Contractor
shall be deemed to have been fully informed with respect to all such liabilities
and considered the same in his bid, and the contract shall not be varied in any
way on this account.
14.1 All duties, taxes, fees, charges, expenses, etc. (except where otherwise
expressly provided in the Contract) as may be levied/ imposed in consequence
of execution of the works or in relation thereto or in connection therewith as
per the Acts, Laws, Rules, Regulations in force shall be to Contractor's account.
However, any new taxes /duties imposed after the date of submission of last
price bid & up to Contractual Completion date shall be to the GAIL’s account
but such Taxes /duties imposed beyond Contractual Completion date shall be to
the Contractor’s account. However if such new taxes etc. are in substitute of
existing taxes, it will be considered on merit of each case.
174 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 14 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
DELETED
DELETED
DELETED
20.1 Contractor shall arrange import of all materials required for permanent
incorporation in the works as well as construction equipment as per the
guidelines laid down by the Government of India. Employer/Consultant shall
not provide import licence.
21.1 Contractor agrees for withholding from wages and salaries of its agents,
servants or employees all sums, required to be withheld by the laws of the
Republic of India or any other agency having jurisdiction over the area where
Contractor is conducting operations, and to pay the same promptly and directly
when due to the proper authority. Contractor further agrees to comply with all
accounting and reporting requirements of any Nation having jurisdiction over
the subject matter hereof and to conform to such laws and regulations and to
pay the cost of such compliance. If requested, Contractor will furnish the
evidence of payment of applicable taxes, in the country(ies) of the Contractor's
and his sub-contractor(s) and expatriate employees.
175 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 15 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
22.1 Neither Employer/Consultant nor Contractor nor their personnel, agents nor
any sub-contractor shall divulge to any one (other than persons designated by
the party disclosing the information) any information designated in writing as
confidential and obtained from the disclosing party during the course of
execution of the works so long as and to the extent that the information has not
become part of the public domain. This obligation does not apply to
information furnished or made known to the recipient of the information
without restriction as to its use by third parties or which was in recipient's
possession at the time of disclosure by the disclosing party. Upon completion
of the works or in the event of termination pursuant to the provisions of the
contract, Contractor shall immediately return to Employer/Consultant all
drawings, plans, specifications and other documents supplied to the Contractor
by or on behalf of Employer/Consultant or prepared by the Contractor solely
for the purpose of the performance of the works, including all copies made
thereof by the Contractor.
23.1 The quoted prices shall be firm and shall not subjected to price escalation till
the work is completed in all respects.
24.1 The work covered under this contract shall be treated as "Works Contract".
25.1 The Contractor shall strictly comply with the provisions of Employees
Provident Fund Act and register themselves with RPFC before commencing
work. The Contractor shall deposit Employees and Employers contributions to
the RPFC every month. The Contractor shall furnish along with each running
bill, the challan/ receipt for the payment made to the RPFC for the preceding
months.
176 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 16 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
177 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 17 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
26.2.1 Recoveries will be effected from each Running Account Bill at the rate
of 10% of the gross bill value, till the entire Mobilization Advance
(together with interest accrued thereon) is fully recovered. In any case,
mobilization advance shall be fully recovered before release of payment
due towards Mechanical completion / pre final bill.
ii) Contractor requests to delete any part of the work which will not
adversely affect the operational capabilities of the project and if agreed
by the Employer/Consultant and for which cost and time benefits shall
be passed on to the Employer/Consultant.
178 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 18 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
27.2 Any changes required by the Employer/Consultant before giving their approval
to detailed procedure or any other document relating to material procurement,
layout plans etc for complying with the requirements of bidding document shall
not be construed to be a change in the scope of work under the contract.
27.3 Any change order as above comprising an alteration which involves a change
in the cost of the works (which sort of alteration is hereinafter called a
“Variation") shall have impact on the contract value that shall be dealt towards
end of contract. All change orders shall be approved by the EIC.
27.4 If the contract provides applicable rates for the valuation of the variation in
question the contract price shall be increased or decreased in accordance with
those rates. If the parties agree that the contract does not contain applicable
rates then the parties shall negotiate a revision of the contract price which shall
represent the change in cost of the works caused by the variations. Any change
order must be duly approved by the Employer/Consultant in writing.
27.6 Within 10 (Ten) working days of receiving the comments from the Employer /
Consultant on the documents submitted by the Contractor for approval, the
Contractor's response in writing stating which item(s) is/are potential change
(s), if applicable, will be submitted to the Employer/Consultant.
27.7 Procedure
27.7.1 During execution of work if the Contractor observes that any new
requirements which is not specific or intended in the bidding document has
been indicated by Employer/Consultant, they shall discuss the matter with
Employer/Consultant's representatives.
27.7.2 In case such requirement arises from the side of the Contractor they would
also discuss the matter with Employer/Consultant's Representative.
27.7.3 In either of the two cases above, the representatives of both the parties shall
179 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 19 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
discuss the project requirement and mutually decide whether the project
requirement constitutes a change order.
27.7.4 If it is mutually agreed that the project requirement/Inquiry constitutes a
"Change Order" then a joint memorandum will be prepared to confirm a
"Change Order" and basic ideas of necessary agreed modifications.
27.7.5 Contractor will study the work required in accordance with the Joint
memorandum and assess subsequent schedule and cost effect if any.
27.7.6 The results of this study would be discussed mutually to enable Employer /
Consultant to give a final decision whether Contractor should proceed with the
Change Order or not, in the best interest of the Project.
27.7.9 The time and cost effect in such a case shall be mutually verified for the
purpose of record. Should it be established that the said work is constituting a
Change Order, the same shall be compensated taking into account the records
180 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 20 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
27.7.10 Should the amount of Extra Work/ Change Order, if any, which the
Contractor may be required to perform by the Employer/Consultant, fairly
entitles the Contractor to extensions of time beyond the scheduled completion
date for completion of either the whole of the works or for such Extra Work
only, the Employer/Consultant and the Contractor shall mutually discuss and
decide the extension of time, if any to be granted to the Contractor.
28.1
A. Company will acquire the ROU free of any encroachments/
temporary/permanent structures under P&MP act in general. Acquiring of ROU
means publishing of 3(1) and 6(1) Gazette notification/publication under P&MP
act 1962.Therfore, handing over of 6(1) gazette shall mean handing over of
ROU to the Contractor for opening of RoU. Contractor shall open the ROU with
revenue team of competent authority appointed by GAIL and start the
construction activities.
C. All the awards declared by the Competent Authority will be binding to the Land
owners except when such dispute(s) is/are
2. If any dispute upheld by the District court and stay order is passed, then the
181 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 21 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
period or time lapse between the dispute raised till the stay order is
dismissed shall not be accountable to the Contractor and then this portion of
the ROU shall not be considered acquired ROU and will be deducted from
the ROU handed over to Contractor.
D. If any intervention from State Administration in any section of the ROU where
work had to be stopped due to intervention from State Administration shall not
be accountable to the Contractor and then this portion of the ROU shall not be
considered acquired ROU and will be deducted from the ROU handed over to
Contractor.
E. Removal of all the hindrances in the ROU shall be sole responsibility of the
contractor except due to reasons as in A to D as above, not accountable to
Contractor.
28.2 For pipeline construction purposes, ROU of varying width shall be made
available depending upon site condition. In cross country areas the ROU of 20
m width shall normally be made available to Contractor to the extent feasible.
Pipeline shall be laid on one side of boundary of ROU as advised by Engineer-
in-Charge. In Forest areas, hilly terrain and congested areas such as built-up
areas etc., ROU of 10 m or less shall be available. The pipeline shall be laid at
2 m from the ROU edge in reserve forest areas. All these eventualities shall be
taken into account. It shall be Contractor’s responsibility to make arrangement
for any additional land required for fabrication, construction, storage and all
other work areas.
28.3 Contractor shall carry out construction work within the width as made available
to him. Where the pipeline route passes through forest/plantation areas
contractor shall clear only the minimum width required for laying the pipeline
182 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 22 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
28.4 The Contractor must ensure that during laying of the pipeline minimum
damage occurs to the land. The land has to be restored to original condition. All
construction activities shall be in accordance with the local Government
regulations and shall be performed by the competent and qualified persons for
providing adequate protection to the general public, livestock, wild life, forest,
power lines, buildings etc. in the vicinity of the pipeline.
28.6 In case of any detour from the acquired ROU due to constructability problems
or otherwise, contractor may be permitted to do so after approval from CA /
Company. All statutory payments shall be paid/ reimbursed by Company.
However, such activity shall not affect the construction schedule and overall
completion period.
28.7 Clean-up and restoration of ROU and other conveniences like road, rail, canals,
cultivable land, water facilities, irrigation facilities, boundary wall/fence etc. to
original condition as per specification and drawings to the entire satisfaction of
Company and/or Landowner/Cultivator/ Authorities having jurisdiction over
the same, including disposal of surplus excavated soil and other construction
materials to a location identified by Contractor approved by local authority
without causing any disturbance to environment and to the entire satisfaction of
Company.
183 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 23 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
28.9 Local state Government may impose Taxes/ Duties/ royalty etc towards the
excavation and filling of earth for the pipe line and terminals works. It is the
responsibility of contractor to make such payments without any cost
implications to GAIL.
28.11 ROU shall be opened in stretches and may not be continuous. In such an event
contractor shall skip the section and jump over to next stretch where ROU is
available, without any cost & time implication to the Company.
29.1.3 DELETED
184 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 24 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
29.2.1 The complete list of minimum skilled manpower to be deployed are mentioned
in Annexure 10 to SCC. Bidder shall submit their compliance for
deployment of manpower along with the bid.
Qualification and Experience of key construction personnel shall be as per
Annexure-10A to SCC.
30.1 Contractor shall without prejudice to his overall responsibility to execute and
complete the work as per specifications and time schedule adopt as far as
practicable, mechanized construction techniques for major site activities.
Contractor agrees that he will deploy the required numbers and types of the
plant & machinery applicable for different activities in consultation with the
Engineer-in-charge during execution of works.
30.2 Contractor further agrees that Contract price is inclusive of all the associated
costs, which he may incur for actual mobilization, required in respect of use of
mechanised construction techniques and that the Employer / Consultant /
Consultant in this regard shall entertain no claim whatsoever.
185 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 25 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
31.1 Contractor shall be responsible for organising the lifting of the equipment in
the proper sequence, that orderly progress of the work is ensured and access
routes for erecting the other equipments are kept open.
31.3 During the performance of the work the Contractor at his own cost, shall keep
structures, materials and equipment adequately braced by guys, struts or
otherwise approved means which shall be supplied and installed by the
Contractor as required till the installation work is satisfactorily completed.
Such guys, shoring, bracing, strutting, planking supports etc. shall not interfere
with the work of other agencies and shall not damage or cause distortion to
other works executed by him or other agencies.
186 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 26 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
31.6.1 All the erection shall be carried out by Cranes of suitable capacity. Erection by
derrick shall not be permissible. The contractor shall arrange the crane of
suitable capacity required for erection and include cost for same in respective
items without any liability on the part of Employer/Consultant.
31.6.2 Bidder shall submit the indicative erection scheme for compressor/equipment
and shall undertake the erection only after obtaining approval of erection
scheme by Engineer-in-charge.
31.6.3 Grouting of equipments, anchor bolts, pockets and under base plates shall be
carried out as per technical specifications.
Section I II III IV
Asking Rate
7 21 10 9
(Km/Month)
187 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 27 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
RETENTION OF AMOUNT
MONTHLY CONSTRUCTION
FROM CONTRACTOR’S RA
PROGRESS
BILLS
< 35% of asking rate @ 0.15% of total contract value
> 35% and < 80% of asking rate @ 0.1% of total contract value
> 80% of asking rate No retention
32.3 For the purpose of calculation of retention amount, date of FOA/ Go ahead
shall be considered as the base date and duration of month shall be considered
as 30 days (avg.).
32.4 Asking rate shall not be applicable during mobilization period and hence, there
shall be no retention on account of asking rate for first month from date of
FOA/Go Ahead.
32.5 The asking rate retentions shall be applicable only during contractual
completion period.
32.6 For the purpose of calculation of retention, ROU released up to 1 month prior
shall be taken into consideration.
32.7 These retentions shall be calculated every month, however retentions shall be
done in RA bills based upon quarterly reconciled calculations jointly signed by
CONTRACTOR, MECON and GAIL.
32.8 In case monthly progress is more than 35% of asking rate, then no retention
shall be done for first 2 months of each quarter. However if at the end of
each quarter the progress is less than 80% of the cumulative progress
required for the quarter, then retentions at the rate as defined in clause no.
32.2 above shall be retained for each month of the quarter from the RA bill
of the CONTRACTOR.
32.9 In case the ROU released 1 month prior is less than the cumulative progress
required from the CONTRACTOR, then the target progress shall be calculated
on pro-rata basis and accordingly retentions will be calculated.
32.10 In case the CONTRACTOR achieves the contractual completion period for
mechanical completion of the pipeline, the already deducted amount against
deductions on account of failure to meet the asking rate shall be refunded in the
188 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 28 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
final bill. However, in case the CONTRACTOR fails to achieve the contractual
completion period for mechanical completion of the pipeline, the already
deducted amount shall not be refunded.
32.11 Deduction under this clause shall be in addition to PRS applicable pursuant to
GCC clause 27.0 and SCC Clause. The provision of GCC clause no. 27.0 shall
have no bearing on this clause. The CONTRACTOR’s maximum liability
towards retention/ deduction for non-achievement of construction asking rate
shall be limited to 2.5% of the final contract price.
32.12 In case CONTRACTOR achieves more than the asking rate in each month, then
the CONTRACTOR shall not be entitled to any bonus/ extra claim.
32.13 In case work front is not made available during the month, a joint record
between GAIL/ MECON & CONTRACTOR shall be prepared.
32.14 Quarterly closure report clearly mentioning the ROU handed over, progress
achieved, constraints, extra items/ claims etc. shall be prepared and jointly
signed by CONTRACTOR, MECON and GAIL, failing which the RA bills of
the CONTRACTOR shall not be processed.
Deleted
189 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 29 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
34.1 Basis and terms of payment for making “On Account Payment” shall be as set
out in Annexure-5 to SCC.
35.1 Immediately prior to aligning pipe for welding, the bevelled ends of each joint
of pipe and the area immediately adjacent thereto (at least 25mm from the edge
on the inside and outside of the pipe) shall be thoroughly cleaned of paint, rust,
mill scale, dirty or other foreign matter by use of power drive wire buffing
wheels, disc sanders, or by other methods approved by Employer/Consultant.
This shall be done at no extra cost to Employer/Consultant.
35.2 All damaged ends of pipe that are bent, cut or otherwise mutilated to such an
extent that in the opinion of the Employer/Consultant, faulty alignment or
unacceptable welding would result, shall be repaired or cut-off and rebevelled
to the correct angle with a bevelling machine of a type approved by
Employer/Consultant. No compensation shall be allowed by reason of such
recutting or bevelling, except when required because of the original bevel being
damaged before the pipe is "taken over" by Contractor.
35.3 Dents in bevels with a depth of less than 1 mm shall be removed by Contractor
during cleaning and grinding, ahead of the welding in the field. Contractor shall
rebevel dented bevel ends with a depth between 1 and 3 mm. Dents over 3mm
depth shall be repaired by cutting and rebevelling.
36.1 The conditions for issue of material and reconciliation refer enclosed
Annexure-8 to SCC.
36.2 The reconciliation of material shall be applicable only for the material issued
by Employer/Consultant as free issue to the contractor.
190 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 30 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
37.2 The Contractor shall collect the line pipes from the above dump yard(s) and
arrange handling of pipes including crane etc. for unloading, transportation of
pipes to required location or pipeline ROU shall be the responsibility of
contractor.
37.3 Similarly other items issued as Free Issue Material (FIM) shall be collected by
the Contractor from Employer/Consultant’s designated storage yard(s) as
directed by Engineer-in-Charge. Contractor shall arrange for handling of FIM
including crane etc for loading/unloading, transportation of FIM to required
site location free of cost.
37.4 Contractor shall lift the entire quantity envisaged for the part (inclusive of 3%
extra pipe quantity) to cater to the wastage, re-routing etc., encountered during
the construction; store it properly in the pipe yard maintained by the contractor.
38.1 Employer shall obtain general in-principle permissions from most of the
authorities having jurisdiction over the area as necessary for construction of the
pipeline. However, specific site related work / coordination with concerned
authority required for executing the job will have to be done by the Contractor.
Contractor may have to follow up/expedite with the concerned authorities to
execute the job in time. All the statutory payment required for such purpose
shall be reimbursed by Employer at actuals on production of documentary
evidence.
38.2 The Contractor shall arrange the inspection of the works by the authorities and
necessary co-ordination and liaison work in this respect shall be the
responsibility of the contractor. However statutory fees paid, if any, for all
inspections and approvals by such authorities shall be reimbursed at actual by
the Employer/Consultant to the contractor on production of documentary
evidence.
38.3 Any change/ addition required to be made to meet the requirements of the
statutory authorities shall be carried out by the contractor free of charge. The
inspection and acceptance of the work by statutory authorities shall however,
not absolve the contractor from any of his responsibilities under this contract.
38.4 Statutory approvals of all type of permanent buildings are to be in the scope of
191 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 31 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
39.1 The Contractor shall carry out the various tests as enumerated in the technical
specifications of this bid document and the technical documents that will be
furnished to him during the performance of the work.
39.2 All the tests either on the field or at outside laboratories concerning the
execution of the work and supply of materials by the Contractor shall be
carried out by Contractor at his own cost.
39.3 The work is subject to inspection at all times by the Engineer-in-Charge. The
contractor shall carry out all instructions given during inspection and shall
ensure that the work is being carried out according to the technical
specifications of this bid document, the technical documents and the relevant
codes of practice will be furnished to him during the performance of the work.
39.4 The Contractor shall provide for purposes of inspection access ladders, lighting
and necessary instruments at his own cost.
39.5 Any work not conforming to execution drawings, specifications or codes and
approved methodology / scheme shall be rejected forthwith and the Contractor
shall carryout the rectifications at his own cost.
39.6 All results of inspection and tests will be recorded in the inspection reports,
proforma of which will be approved by the Engineer-in-Charge. These reports
shall form part of the completion documents.
39.8 Statutory fees paid to IBR authorities and for repeat tests and inspection due to
failures, repairs etc. such reasons attributable to the Contractor shall be borne
by the Contractor.
192 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 32 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
39.9 Inspection and acceptance of work shall not relieve the Contractor from any of
his responsibilities under this Contract.
40.1 All inspection and tests on bought out items shall be made as per the
specifications forming part of this contract. The Contractor shall submit a
Categorisation Plan of all the supply items indicating the type of inspection
required for review by PMC. Various stages of inspection and testing shall be
identified after receipt of Quality Assurance Programme from the Contractor/
Manufacturer. All supplies are subject to pre-dispatch inspection from any of
the TPI agencies (Refer Appendix-VI to PJS) and shall be arranged by the
Contractor at his own cost.
40.3 The contractor shall ensure full and free access to the inspection Engineer of
Employer/Consultant at the Contractor’s or their sub-contractor’s premises at
any time during contract period to facilitate him to carry out inspection and
testing assignments.
40.4 The contractor/ sub-contractor shall provide all instruments, tools, necessary
testing and other inspection facilities to inspection engineer of
Employer/Consultant free of cost for carrying out inspection.
40.5 Where facilities for testing do not exist in the Contractor’s/ sub-contractor’s
laboratories, samples and test pieces shall be drawn by the Contractor/ Sub-
Contractor in presence of Inspection Engineer of a Employer/Consultant and
duly sealed by the later and sent for testing in Government approved Test
House or any other testing laboratories approved by the Inspection Engineer at
the Contractor’s cost.
193 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 33 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
41.1 After completion of all tests as per specification the whole work will be subject
to a final inspection to ensure that job has been completed as per requirement.
If any defects noticed in the work attributable to Contractor, the Contractor at
his own cost shall attend these, as and when the Employer/Consultant brings
them to his notice. The Employer/Consultant shall have the right to have these
defects rectified at the risk and cost of the contractor if he fails to attend to
these defects immediately
43.2 The bills will be prepared by the contractors on their own PCs as per the
standard formats and codification scheme proposed by GAIL/MECON. The
contractors will be provided with data entry software to capture the relevant
billing data for subsequent processing. Contractors will submit these data to
GAIL/MECON in an electronic media along with the hard copy of the bill,
necessary enclosures and documents. The contractor will also ensure the
correctness and consistency of data so entered with the hard copy of the bill
submitted for payment.
43.3 Employer/Consultant will utilize these data for processing and verification of
the Contractor's bill and payment."
44.1 All Temporary and ancillary works including enabling works connected with
the work shall be responsibility of the Contractor and the price quoted by them
shall be deemed to have included the cost of such works which shall be
removed by the contractor at his cost, immediately after completion of his
work.
194 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 34 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
45.1.1 For all Equipment pedestals, pipe racks, other foundation and R.C.C.
Structures, work done upto 300 mm level above finished grade level will be
taken as work in foundations and work above this level will be treated as work
in superstructures and payments would be made accordingly.
45.1.2 For Buildings only, all works upto level corresponding to finished floor level
shall be treated as `Work in foundation' and all works above the finished floor
level shall be treated as "Work in superstructure".
45.1.3 Irrespective of what has been stated above, all pavements, R.C.C. Retaining
wall, all pipe sleepers and any similar item would be taken as work done in
foundations irrespective of locations, nomenclature and levels given anywhere.
45.1.4 Where not specifically pointed out all works in Cellars/ sumps, Tank Pads,
Cable trenches, or such similar item would be taken as work in foundation.
46.1 Bidder shall include in his offer the Quality Assurance Programme containing
the overall quality management and procedures, which is required to be
adhered to during the execution of contract. After the award of the contract
detailed quality assurance programme shall be prepared by the contractor for
the execution of contract for various works, which will be mutually discussed
and agreed to.
46.2 The Contractor shall establish document and maintain an effective quality
assurance system outlined in recognized codes.
46.3 Quality Assurance System plans/procedures of the Contractor shall be
furnished in the form of a QA manual. This document should cover details of
the personnel responsible for the Quality Assurance, plans or procedures to be
followed for quality control in respect of Engineering, Procurement, Supply,
Installation, Testing and Commissioning.
195 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 35 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
46.5 The contractor has to ensure the deployment of Quality Assurance and Quality
Control Engineer(s) depending upon the quantum of work. This QA/QC group
shall be fully responsible to carryout the work as per standards and all code
requirements. In case Engineer-in-Charge feels that Contractor's QA/QC
Engineer(s) are incompetent or insufficient, contractor has to deploy other
experienced Engineer(s) as per site requirement and to the full satisfaction of
Engineer-In-Charge.
46.7 The Contractor shall adhere to the quality assurance system as per MECON
Specification enclosed in the Bidding Document as Annexure-6.
47.1 The Contractor, during entire duration of the Contract, shall adhere to HSE
requirement as per spec. enclosed in the bidding document as Annexure-7.
48.1 The Contractor shall clean and keep clean the work site from time to time to
the satisfaction of the Engineer-in-Charge for easy access to work site and to
ensure safe passage, movement and working.
48.2 If the work involves dismantling of any existing structure in whole or part, care
shall be taken to limit the dismantling up to the exact point and/or lines as
directed by the Engineer-in-Charge and any damage caused to the existing
structure beyond the said line or point shall be repaired and restored to the
196 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 36 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
original condition at the Contractor's cost and risks to the satisfaction of the
Engineer-in-Charge, whose decision shall be final and binding upon the
Contractor.
48.3 The Contractor shall be the custodian of the dismantled materials till the
Engineer-in-Charge takes charge thereof.
48.4 The Contractor shall dispose off the unserviceable materials, debris etc. to any
area as decided by the Engineer-in-Charge.
48.5 The Contractor shall sort out, clear and stack the serviceable materials obtained
from the dismantling/renewal at places as directed by the Engineer-in-Charge.
(i) One complete bound set of all original documents as mentioned but not
limited to documents listed elsewhere in the bid document.
(ii) Three complete bound sets of documents as mentioned at (i) above,
in original size and in 3 (three) CD-ROM/DVD.
(iii) Three complete bound sets of Contractor's specification including design
calculations.
(iv) Three copies of Daily Progress Reports
(v) Three sets of all raw data collected / generated for and during execution
of the entire job as specified in documents requirement.
(vi) Three sets of Closure report.
B) Completion Documents
197 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 37 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
Note: The Contractor shall be eligible to apply for issue of completion certificate
after submission of completion documents as mentioned above.
50.1 Work shall be carried out in such a manner that the work of other agencies
operating at the site is not hampered due to any action of the Contractor. Proper
coordination with other agencies will be Contractor's responsibility. In case of
any dispute, the decision of Engineer-in-Charge shall be final and binding on
the Contractor.
DELETED
198 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 38 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
construction activities and take necessary steps to ensure safety and protection
to men, materials and utility provided. The Contractor shall execute the work in
such a manner that the said structures, utilities, pipelines etc. are not disturbed
or damaged, and shall indemnify and keep indemnified the
Employer/Consultant from and against any destruction thereof or damages
thereto.
53.1 Bidder shall be required to submit recent test certificates for the material being
used in works from the recognized laboratories. These certificates should
indicate all properties of the materials as required in relevant IS Standards or
International Standards.
53.2 Contractor shall also submit the test certificate with every batch of material
supplied which will be approved by Engineer-in-Charge. No secured advance
will be given for the materials not having test certificate. In case any test is to
be carried out, the same shall be got done in the approved laboratory at the cost
of contractor.
54.0 ROYALTY
54.1 Contractor's quoted rate should include the royalty on different applicable items
as per the prevailing Government rates. In case, Employer/Consultant is able
to obtain the exemption of Royalty from the State Government, the contractor
shall pass on the same to Employer/Consultant for all the items involving
Royalty.
55.1 The Contractor shall obtain licence from the District authorities for undertaking
blasting work as well as for obtaining and storing the explosive as per
Explosive Rules 1940, corrected up to date. He shall purchase the Explosives,
fuses, detonators etc. only from a licensed dealer. He shall be responsible for
the safe custody and proper accounting of the explosive materials. The
Engineer-in-Charge and his authorised representative shall have the access to
check the contractor's store of explosives and his accounts. In case where the
explosive are required to be transported and stored at site, relevant clauses of
the Explosive rules 1940 as amended subsequently shall apply. The Contractor
199 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 39 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
56.1 Following facilities are to be ensured at all work places where workmen are
deployed/engaged by Contractor.
58.1 The bidder as per the Technical specification along with their offer taking into
account the completion schedule shall furnish the detailed procedure proposed
for the hydrostatic testing of pipeline. The necessary piping, pumps etc. shall
be provided by the contractor. The final disposal of water after testing shall be
contractor's responsibility and should be in such a way that neither the traffic
movement even pedestrians nor the standing crop in nearby fields gets affected.
Suitable drains shall be provided for this purpose as directed by the Engineer-
in-Charge within the contracted prices.
58.2 The Contractor shall propose and obtain approval of Engineer-in-Charge for
exact number of test sections, based on drawings, availability of water for
hydro testing and keeping in view other exigencies, if any before starting hydro
testing work. The Contractor will carryout the hydrostatic test for approved
200 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 40 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
number of test section including preparation for test and tie-ins, without any
time and cost implication on this account to Employer/Consultant. Any
increase or decrease in number of test sections will not have any cost
implication to Owner / Consultant / Contractor.
59.0 ARBITRATION
DELETED
60.1 The materials required to be supplied by the contractor under this contract shall
be procured only from Employer/Consultant approved vendors. Where the
makes of materials are not indicated in the Bidding document contractor shall
furnish the details of makes and shall obtain prior approval of Engineer-in-
Charge of vendors/sub-vendors before placing order.
61.1 Employer/Consultant reserves their right to execute any additional works/ extra
works, during the execution of work, either by themselves or by appointing any
other agency, even though such works are incidental to and necessary for the
completion of works awarded to the Contractor. In the event of such decisions
taken by Employer/Consultant Contractor is required to extend necessary
cooperation, and act as per the instructions of Engineer-in-Charge.
62A.1 Clause no. 27.0 of GCC, pertaining to Compensation for Delay (Price
Reduction Schedule) stands modified to the following extent:
62A.1.1 The contractual completion period is as given in the Invitation for Bids
and sub-divided into two parts:
201 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 41 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
62A.1.2 The Price Reduction Schedule (PRS) under 62A.1.1 above shall be
applied as under:
ii) “In case of delay in works related to clause 62A.1.1 b): at the rate of ½ % of
20% of the total contract value per week of delay or part thereof subject to
maximum of 5% of 20% of the total contract value.
The total liability of the Contractor to Employer/ Consultant under sub clause
no. 62A.1.1 on Compensation for Delay/Price Reduction Schedule shall not
exceed 5% (Five Percent) of contract value. The compensation on account of
any liability (ies) other than above shall be as per provisions of Bidding
Documents.
The value referred in PRS clause is excluding taxes and duties reimbursable by
GAIL.
202 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 42 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
a) Time Schedule
203 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 43 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
e) Functional Schedules
The Contractor shall present the programme and status at various review
meetings as required.
204 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 44 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
B) Weekly Reports
The report will be prepared and submitted by the Contractor on weekly
basis and will cover following items:
a) Activities programmed and completed during the week.
b) Resource deployed men and machines.
c) Quantities achieved against target in construction
205 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 45 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
C) Daily Repots
a) Activity programme for the day
b) Progress of the previous day and commutative progress.
c) Manpower & machinery deployed.
63.4.1 CONTRACTOR shall make every effort to keep the OWNER adequately
informed as to the progress of the WORK throughout the CONTRACT period.
63.4.2 By the 10th (tenth) of each month, CONTRACTOR shall furnish the OWNER a
detailed report covering the progress as of the last day of the previous month.
These reports will indicate actual and scheduled percentage of completion of
construction as well as general comments of interest or the progress of various
phases of the WORK. The frequency of progress reporting by the
CONTRACTOR shall be weekly.
206 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 46 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
63.4.5 Contractor shall prepare daily progress report (DPR) in the desired format and
submit it to Engineer-in-charge alongwith schedule of next day to Engineer-in-
charge.
Project Progress shall be reviewed by the PRT Team of GAIL on regular basis.
Contractor shall be liable to submit compliance report(s) within 15 days of PRT
review meeting(s).
Contractor is also required to submit quarterly closure report within 15 days (of
completion of each quarter).
64.1 It shall be the responsibility of the Contractor to obtain the approval for any
revision and/or modifications decided by the Contractor from the
Employer/Consultant/ Engineer-in-charge before implementation. Also such
revisions and/or modifications if accepted/ approved by the
Employer/Consultant/Engineer-in-charge shall be carried out at no extra cost to
the Employer/Consultant. Any changes required during and/or after approval
for detailed construction drawings due to functional requirements or for
efficient running of system keeping the basic parameters unchanged and which
has not been indicated by the Contractor in the data/drawings furnished along
with the offer will be carried out by the Contractor at no extra cost to the
Employer/Consultant.
207 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 47 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
64.4 Preparing approaches and working areas for the movement and operation of the
cranes, levelling the areas for assembly and erection shall also be the
responsibility of the Contractor. The Contractor shall acquaint himself with
access availability, facilities such as railway siding, local labour etc. to provide
suitable allowances in his quotation. The Contractor may have to build
temporary access roads to aid his own work, which shall also be taken care
while quoting for the work.
64.5 The procurement and supply in sequence and at the appropriate time of all
materials and consumables shall be entirely the Contractor's responsibility and
his rates for execution of work will be inclusive of supply of all these items.
65.1 The Contractor shall be responsible for checking levels, orientation plan of all
foundations, foundation bolts, etc., well in advance of taking up the actual
erection work and bring to the notice of Engineer-in-Charge discrepancies, if
any. In case of minor variations in levels etc. the Contractor shall carry out the
necessary rectifications to the foundations within his quoted price.
65.2 The Contractor shall also be responsible for checking with templates, wherever
necessary, the disposition of foundation bolts with the corresponding bases of
structure and shall effect rectifications, as directed, within his quoted rate.
66.1 The Contractor shall maintain wherever required an air-conditioned room for
the storage of the instruments as well as for calibration and testing of the
instruments at his own cost. The contractor shall provide these facilities within
the quoted price.
68.1 Contractor shall at his own expense arrange, secure and maintain insurance
208 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 48 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
68.2 The schedule of insurance cover for free issue materials given above shall be as
follows:
69.2 Any loss or damage to the equipment during ocean transportation, port/custom
clearance, inland and port handling, inland transportation, storage, erection and
commissioning till such time the Work is taken over by Employer/Consultant,
209 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 49 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
69.3 Statutory clearances, if any, in respect of foreign supply required for the
purpose of replacement of equipment lost in transit and/or during erection, shall
be made available by the Employer/Consultant. Contractor shall, however, be
responsible for obtaining requisite licenses, port clearances and other
formalities relating to such import. The risks that are to be covered under the
insurance shall include, but not be limited to the loss or damage in handling,
transit, theft, pilferage, riot, civil commotion, weather conditions, accidents of
all kinds, fire, war risk (during ocean transportation only) etc. The scope of
such insurance shall cover the entire value of supplies of equipments, plants
and materials to be imported from time to time.
69.4 All costs on account of insurance liabilities covered under this Contract will be
to Contractor’s account and will be included in Contract Price. However, the
Employer/Consultant may from time to time, during the currency of the
Contract, ask the Contractor in writing to limit the insurance coverage risk and
in such a case, the parties to the Contract will agree for a mutual settlement, for
reduction in Value of Contract to the extent of reduced premium amounts.
69.5 Contractor as far as possible shall cover insurance with Indian Insurance
Companies, including marine Insurance during ocean transportation.
70.1 The Contractor shall at his own cost arrange, secure and maintain separate
insurance cover from the reputable insurance companies, for all such amounts
and for such periods as may be necessary to protect the works, Contractor and
sub-contractor’s personnel and the interests of the Employer/Consultant as per
applicable laws of land.
210 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 50 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
70.2 The form and the limit of insurance cover taken by Contractor shall be
satisfactory to Employer/Consultant and one copy of all insurance policies and
related documents shall be submitted to Employer/Consultant, immediately on
execution. Contractor shall inform Employer/Consultant at least 60 days
before any insurance policies expire or are cancelled or changed.
71.1 The provision relating to submission of Bank Guarantee from any Nationalized
Bank wherever appearing in above documents stand replaced by the following:
i) Bank guarantees towards Bid Security from any Indian scheduled bank or a
branch of an International bank situated in India and registered with Reserve
Bank of India as scheduled foreign bank in case of Indian bidder and from any
reputed International Bank or Indian scheduled bank in case of foreign bidder,
may be accepted. However, other than the Nationalized Indian Banks, the
banks whose BGs are furnished, must be commercial banks having net worth in
excess of Rs.1000 Million and a declaration to this effect should be made by
such commercial bank either in the bank guarantee itself or separately on a
letter head.
ii) Similarly, bank guarantees towards Performance and Advance Payments may
be accepted from any Indian scheduled bank or a branch of an International
bank situated in India and registered with Reserve Bank of India as scheduled
foreign bank in case of Indian bidder as well as foreign bidder. However, other
than the Nationalised Indian Banks, the banks whose BGs are furnished, must
be commercial banks having net worth in excess of Rs.1000 Million and a
declaration to this effect should be made by such commercial bank either in the
bank guarantee itself or separately on a letter head.
72.1 The Contractor shall shoot, prepare and submit coloured photographs (B5 size)
in 2 sets alongwith softcopies to MECON site office along with monthly
progress report covering all the activities (minimum 10 nos of photographs
covering various phases of each activities) of pipeline constructions
highlighting the progress or other areas of work. Similarly photographs for
211 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 51 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
Deleted
74.0 VIDEOTAPE
74.1 Contractor shall develop and submit (in CD / Pen Drive) a videotape of three
hours duration covering the construction activities showing the nature and
magnitude of the work. The tape shall be shot and edited to Indian broadcast
standards. Videotape recorded in field shall be shot by professional
camerapersons and shall meet the technical standards of the Hi-8 format or
better. Tape shall cover, but not limited to the following construction activities:
74.2 Videotape shall also have coverage on new/special techniques used in the
Contract and major problems encountered, if any, and the measures taken to
resolve them. The tape shall be supplemented with suitable narration and
subtitles explaining the job, techniques and methodology, etc. The video shall
be prepared with two narration tracks, one in Hindi one in English. Professional
212 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 52 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
narrators shall voice both. The script shall include explanations of job
activities, techniques used methodologies etc. Elements of the video
programme sequencing and editing techniques shall be discussed with
Employer/Consultant and mutually agreed to before videotaping begins.
75.1 Contractor for the purpose of qualification of welding procedure may use the
pipes issued by Employer/Consultant. However, accounting of such pipes shall
be done within the unaccountable wastage and scraps limit as per Annexure-8
to SCC enclosed with the bidding document.
75.2 The contractor shall bear all cost towards lifting, carting from issue point to
work site/Contractor’s store, custody, handling, insurance and levies etc. and
return of surplus/scrap materials to employer designated storage point. No
separate payment shall be made for such expenditure.
76.0 SPARES
76.1 Contractor shall procure and supply all spare parts required during
commissioning of the various items / materials supplied by him as enumerated
in the Bidding Document. The quoted lump sum prices shall be deemed to have
been inclusive of all such provision of commissioning spares, required till
commissioning of such items. Contractor shall make available all the
commissioning spares required at site at least 4 (four) weeks before start of
commissioning. However, listed spares not used during commissioning shall be
handed over to Employer at their designated place. Contractor shall also supply
commissioning spares not listed but required during commissioning within the
contracted price.
76.2 In addition to above, special tools & tackles required, if any, for operation &
maintenance shall also be supplied by the Contractor and the quoted prices
213 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 53 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
c. Cess as per the prevailing rate, shall be deducted at source from bills of the
SUB-CONTRACTOR by the engineer-in-Charge of the contract and remitted
to the “Secretary, Building and Other Construction Workers Welfare Board” of
the concerned State. The SUB-CONTRACTOR shall be responsible to submit
final assessment return of the cess amount to the assessing officer after
adjusting the cess deducted at source.
78.1 Contractor shall adhere to meet the intermediate construction mile stone
enclosed as Appendix-I to Particular Job Specification. Contractor shall be
responsible for close monitoring and completion of intermediate construction
milestone.
79.1 The entire work as per scope of work covered under this contract shall be
214 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 54 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
80.1 The Clause 27.3 of GCC for Bonus for early completion shall not be applicable
in this Contract.
DELETED
DELETED
The contractor shall not, save with previous consent in writing of the Engineer-
in- charge, sublet, transfer or assign the contract or any part thereof or
interest therein or benefit or advantage thereof in any manner whatsoever.
Provided, nevertheless, that any such consent shall not relieve the
contractor from any obligation, duty or responsibility under the contract.
However, subletting of WHOLE WORKS is prohibited. Vendor/ Contractor
shall submit undertaking to this effect along with each invoice/ bill."
215 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 55 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
85.1 Measurement shall be recorded as per the methods of measurement spelt out in
Specification/Contract Documents. The PMC/GAIL site engineer/DGM/CM
will check the measurement as recorded in the Measurement Books/Bills
87.0 WAY BILL / ROAD PERMIT: Shall be issued by GAIL only for
transportation of free issue material from one state to another.
216 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 56 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
Contractor shall ensure that all its personnel deployed under this contract have
obtained additional insurance coverage under the Pradhan Mantri Suraksha
Bima Yojana (PMSBY) and Pradhan Mantri Jeevan Jyoti Bima Yojana
(PMJJBY) through the participating banks and submit the proof of such
insurance coverage to the satisfaction of GAIL. The cost of the insurance
premium amount for both the above schemes shall be borne by the contractor
giving evidence/proof to GAIL in this respect and Contractor shall suitably
consider the same in their bid.
Both the schemes are to be regulated continuously on yearly basis and the same
should be renewed on each successive relevant date in subsequent years.
93.0 E-MEASUREMENT
GAIL will process the Bills with MB through E-Measurement Portal available
in GAIL INTRANET under Project Department. Accordingly Contractor is
required to forward the RA Bills in E-Measurement Portal through
PMC,CIC/EIC/SIC whichever is applicable.
217 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 57 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
This atlas is one of its kind single point source for the various stakeholders
including policy makers, administrators, municipal commissioners, urban
managers, engineers, architects, planners, public etc. to ascertain proneness of
any city/location/site to multi-hazard which includes earthquakes, winds, floods
thunderstorms, cyclones and landslides. While project formulation, approvals
and implementation of various urban housing, buildings and infrastructures
schemes, this Atlas provides necessary information for risk analysis and hazard
assessment.
The Vulnerability Atlas of India has been prepared by Building Materials and
Technology Promotion Council under Ministry of Housing and Urban Affairs,
Government of India and available at their website www.bmtpc.org.
It is mandatory for the bidders to refer Vulnerability Atlas of India for multi-
hazard risk assessment and include the relevant hazard proneness specific to
project location while planning and designing the project in terms of:
218 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM –ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL
(INDIA) LIMITED MECON LTD,
DELHI
E-tender Page 58 of 58
TITLE No.:8000018761 SPECIAL CONDITIONS OF CONTRACT REVISION 0
219 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.:8000018761 ANNEXURES TO SCC Page 1 of 48
TITLE
REVISION 0
ANNEXURES TO SCC
220 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 2 of 48
TITLE
REVISION 0
CONTENTS
221 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 3 of 48
TITLE
REVISION 0
SCOPE OF WORK
(ANNEXURE-1 TO SPECIAL CONDITIONS OF CONTRACT)
222 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 4 of 48
TITLE
REVISION 0
ANNEXURE-1 TO SCC
223 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 5 of 48
TITLE
REVISION 0
SCOPE OF SUPPLY
(ANNEXURE-2 TO SPECIAL CONDITIONS OF CONTRACT)
224 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 6 of 48
TITLE
REVISION 0
ANNEXURE-2 TO SCC
Free Issue Materials shall be issued to the Contractor from the designated store(s) of
Owner. Contractor shall be responsible for lifting the free issue materials from
Owner’s storage point(s) and transporting the same to work site(s) at his own cost.
GAIL’s designated store and dumpyard for this project shall be located as follows:
ii. Section-II: Odisha , Ch.110 Km from Tap-off Point (IP-04 , SAPL - Part A)
(Within 10-15 Km from chainage location)/ Odisha , Ch.170 Km
from Tap-off Point (IP-04 , SAPL - Part A) (Within 10-15 Km from
chainage location)
iii. Section-III: Odisha , Ch.170 Km from Tap-off Point (IP-04 , SAPL - Part A)
(Within 10-15 Km from chainage location)
iv. Section-IV: Odisha , Ch.170 Km from Tap-off Point (IP-04 , SAPL - Part A)
(Within 10-15 Km from chainage location)
Any other nearest designated store shall be provided based on the availavility.
225 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 7 of 48
TITLE
REVISION 0
All materials except what is under Owner’s scope of supply as mentioned in Clause
No. 1.1 above, and required for successful completion of works in all respects shall
be supplied by the Contractor and the cost of such supply shall be deemed to have
been included in the quoted price without any additional liability on the part of Owner.
Surplus material after execution of work shall be returned back to following locations:
Sl. No. Section Location
226 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 8 of 48
TITLE
REVISION 0
COMPLETION SCHEDULE
(ANNEXURE-3 TO SPECIAL CONDITIONS OF CONTRACT)
227 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 9 of 48
TITLE
REVISION 0
ANNEXURE-3 TO SCC
b) Completion of Drying,
Commissioning and Gas-in -01
(One) month after Mechanical
completion
Notes:
1. The completion schedule as mentioned above is for the total scope of work (ie; each
section individually or in combination) including closure of contract (work order) as
mentioned in the bidding document and includes the one month mobilization period.
2a). Mechanical Completion shall mean completion of all works related to buried pipeline
system, aboveground terminal / station piping works and associated works including
EGP, pre-commissioning and making the system ready to start commissioning
activities.
2b). Completion of all balance associated works shall mean all works related to Civil,
Architectural, Structural, Fire fighting, Electrical, Instrumentation and
telecommunication in all respects and commissioning assistance during
commissioning.
2c). Commissioning shall mean activities including final drying, filling the nitrogen (if
required), commissioning with gas, testing of golden tie-ins, and acceptance of final
dossier. It also includes all works related to Civil, Structural, Cathodic Protection,
Instrumentation and Telecommunication.
3). Plots for SVs / IPs / Receiving Terminal / Despatch Terminal etc. shall be handed
over progressively. However, in case of delay in handing over of plot by owner for
SVs / IPs / Receiving Terminal / Dispatch Terminal etc., the following completion
schedule shall be applicable:
a) 2 months for each SV Station from the date of plot handing over for mechanical
completion (station piping works, piping / valve support, etc.).
228 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 10 of 48
TITLE
REVISION 0
b) 3 months for each IP / Receiving / Despatch Station from the date of plot handing
over for mechanical completion (station piping works, erection of scrapper trap,
piping / valve support, telecom works and civil /structural works etc.).
4. Overall contract completion period shall be reckoned from the date of making the
pipeline ready for gas in (as certified by the Engineer-In-charge). For all contractual
matters including but not limited to applicability of PRS, the overall contract
completion period shall be considered.
5. The completion certificate will be issued by the EIC only after liquidation of all Punch-
list points.
________________________________
(STAMP & SIGNATURE OF BIDDER)
229 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 11 of 48
TITLE
REVISION 0
MEASUREMENT OF WORK
(ANNEXURE-4 TO SPECIAL CONDITIONS OF CONTRACT)
230 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 12 of 48
TITLE
REVISION 0
ANNEXURE-4 TO SCC
MEASUREMENT OF WORK
1.0 GENERAL
1.2 Payment will be made on the basis of joint measurements taken by Contractor and
certified by Engineer-in-charge. Measurement shall be based on “Approved for
Construction” drawings, to be the extent that the work conforms to the drawings and
details are adequate.
1.5 The weights mentioned in the drawing or shipping list shall be the basis for payment.
If mountings for panels etc. are packed separately, their erection weights shall
include all mountings.
1.6 Welds, bolts, nuts, washers etc. shall not be measured. Rates for structural steel
work shall be deemed to include the same.
1.7 No other payment either for temporary works connected with this Contractor or any
other item such as weld, shims, packing plates etc. shall be made. Such items shall
be deemed to have been included for in the rates quoted.
1.8 Measurement will be made for various items under schedule of rates on the following
basis as indicated in the unit column.
i) Weight : MT or Kg
ii) Length : M (Metre)
iii) Number : No.
iv) Volume : Cu.M
v) Area : Sq.M
1.9 All measurements shall be in metric system. All the works in progress will be jointly
measured by the representative of the Engineer-in-charge and the contractor's
authorized agent progressively. Such measurements will be either recorded/typed by
the contractor in the numbered measurement sheets to be supplied by Engineer-in-
Charge / Owner or computerized by Contractor themselves. The measurements shall
231 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 13 of 48
TITLE
REVISION 0
2.0 PIPING
2.1 Length of pipes shall be measured along the curvilinear centre of the pipelines laid/
installed and shall include all types of specials, fittings, mitre bends etc. but excluding
all types of valves. Length of valves shall be excluded from piping measurement and
shall be considered on number basis.
2.2 All Socket weld fittings & hot/cold bends, reducers etc. for size 1½" and below shall
be fabricated and erected as per requirements by the contractor at no additional cost
and his rates for piping of size 1½" and below shall be inclusive of this work.
2.3 Vents and drains shall be measured from O.D. of pipe lines and shall be paid for at
the corresponding unit rates for similar sizes of pipe. Other piping attachment such
as couplings, earthing lugs etc. shall be supplied & erected by the contractor within
his quoted rates for piping.
2.4 Fabrication of spool pieces for temporary use to aid Contractor's work such as
fabrication, erection, flushing and testing of piping etc. shall be done by Contractor as
part of piping work and no separate payment shall be made for this.
2.5 In case of branch piping, the measurement shall be made from outer surface of the
main line except in case of equal size branches, in which case measurement shall be
made from centre line of the branching header.
Erection of all types of valves such as gate/ globe / check / plug / needle/ ball /
control/ safety valves etc. will be paid on number basis at the rates given separately
in the Schedule of Rates. Any dismantling and re-erection of the valves required for
the purpose of testing, calibration etc. will be carried out by the contractor within his
quoted rates.
Fabrication of all types of pipe supports, provided as per drawings & instructions
of the Engineer-in-Charge, will be paid on weight basis. Bolts, nuts and washers
including U-bolt will be supplied by contractor. Weight of bolts, nuts and clamps
etc. shall not be added to the weight of pipe support for payment purpose.
Erection of all types of supports, spring supports and turn buckles, including
grouting of supports, if required, shall be carried out by the Contractor as part of
piping work and no separate payment will be made for it.
While fabricating the supporting elements, the contractor will ensure that the
dimensions shown in the drawings match with site conditions. No payment shall
232 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 14 of 48
TITLE
REVISION 0
Additional supports as necessary with the site condition shall be fabricated and
erected in accordance with the standard engineering practices and instructions of
Engineer-in-charge.
Payment for radiography shall be made on the basis of circumferential joints for
different pipe dia. Repeat radiography due to defective films or on repaired joint due
to Contractor's fault or for additional radiography necessitated due to poor
performance of Contractor's welder will be done at Contractor's cost.
4.1 Payment for steel work shall be made on basis of admissible weight of the
structure accepted, the weight being determined as described below.
4.2 The weight for payment will be assessed from the approved fabrication
drawings and the respective bill of materials prepared by the contractor and
approved by the Engineer-in-Charge. The weight of structural material/ Plate
shall be calculated wherever necessary on the basis of IS Hand Book. If
spreads are different from IS spreads, then Manufacturer Hand Book shall be
referred to.
4.3 Spreads built out of plates/structural shall be paid on the actual weight
incorporated except for gussets which will be paid on the weight of the
smallest rectangle enclosing the shape.
4.4 Gratings shall be paid on the basis of calculated weights as determined from
the dimensions given on the design drawings/ bill of materials. Full deduction
shall be made for all opening above 300 mm size and skews.
4.5 Welds, bolts, nuts, washers etc. shall not be measured. Rate of structural
steel work shall be deemed to include the same.
4.6 No other payment either for temporary works or for any other item such as
welds, shims, packing plates etc., shall be made. Such items shall be deemed
to have been included in the rate quoted for steel work.
5.1 Cables
233 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 15 of 48
TITLE
REVISION 0
The measurement for cable laying shall be made on the basis of length
actually laid from lug to lug including that of loops provided and paid
accordingly.
5.2 The weights mentioned in the drawing or shipping list shall be the basis for
payment. If mountings are sent separately (for panels etc.) to facilitate
transportation then erection weight shall be inclusive of all mountings. For
structural steel measurements/payment shall be made as per finished items.
6.2 Air lines and any other utility lines will be measured from end to end including
valves and pipe fittings.
6.3 Copper tube measurement will be taken between the two fittings of the
copper tube.
6.5 Muticore cables/multi-tubes will be measured between the junction box and
its termination inside the control room."
6.6 Two/Three core cables shall be measured between two end terminals.
6.7 No separate payment will be made for receiving, handling and transportation
of owner issued materials from owner's / MECON storage points to
contractor's store/workshop and the same are deemed to be included in the
unit rates for the respective item of work."
The weights mentioned in the drawings or shipping list shall be the basis of
payment. If mountings are sent separately (for panel etc.) to facilitate
transportation then erection weight shall be inclusive of all such mountings.
For structural steel, measurements / payment shall be made as per finished
items."
234 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 16 of 48
TITLE
REVISION 0
a) EQUIPMENTS
II) Piping shall be measured along the centre line through all types of
fittings and flanges.
III) Rates for painting of pipes shall be inclusive of painting of all types of
pipe supports, flanges, guides, shoes, saddles, clamps, etc. and also
all types of fittings except valves (2" and above) which shall be paid
separately on number basis.
235 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 17 of 48
TITLE
REVISION 0
TERMS OF PAYMENT
(ANNEXURE-5 TO SPECIAL CONDITIONS OF CONTRACT)
236 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 18 of 48
TITLE
REVISION 0
ANNEXURE-5 TO SCC
TERMS OF PAYMENT
TERMS OF PAYMENT
Pending completion of the whole works, provisional progressive payments for the part of
work executed by the contractor shall be made by Owner on the basis of said work
completed and certified by the Owner’s representative as per the agreed milestone payment
schedule and the percentage break-ups given below.
Contractor shall submit his invoices to the Owner’s representative fortnightly in the manner
as instructed by Owner. Each invoice will be supported by documentation acceptable to
Owner and certified by the Owner’s representative. Payments made by owner to the
contractor for any part of the work shall not deem that the Owner has accepted the work. All
payments against running bills are advance against the work and shall not be taken as final
acceptance of work / measurement carried out till the final bill. Owner will release payment
through e-payments only as detailed in the bidding document.
237 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 19 of 48
TITLE
REVISION 0
4. Mobilization and placement of Drilling Rig (HDD M/c) at site along with 2%
all the accessories and consumables
Note: - Failure of activities ie; Pulling, Gauging, Post Hydro testing etc. shall be
responsibility of Contractor and no payment on account of any such activity shall be
payable to contractor, moreover earlier successive payment made through RA bills shall
also be recovered. Loss of free issue material occurred due to failure shall be treated in
line with the provision of reconciliation of free issue material.
1.3 Crossing & Other items not covered above or elsewhere in the Tender
238 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 20 of 48
TITLE
REVISION 0
as per Specification
2. Supply & Erection of blowing pit every km, duct : 25% progressively
jointing for testing & termination of duct in the pit
with end cap
239 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 21 of 48
TITLE
REVISION 0
240 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 22 of 48
TITLE
REVISION 0
b) 10% on testing.
c) 10% on completion of all activities and their acceptance, submission of final
documents, final bill and acceptance of these by owner thereafter for successful
closure of work order. In case of SCADA related works, final payment of 10% shall
be released after completion of all wiring and demonstration by laying contractor for
all the signals. Wiring up to TIC panel to be simulated and demonstrated to
GAIL/PMC by laying vendor and jointly certified in the format in Appendix- I.
For all lumpsum items included in schedule of rates, contractor shall furnish price
break-up for quoted lumpsum prices for the approval of Engineer-in-charge. Payment
for such item shall be made accordingly. In this regard decision of Engineer-in-
charge shall be final and binding to the bidder.
3.11 Supply of Materials and All Other Works (not mentioned under 3.1 to 3.10)
Note: Any further breakup of each activity for the payment purpose can be done
depending upon the site situation/requirement and Recommendation by
Engineer-In-Charge and Approval of Construction-In-Charge.
4.1 The contractor shall raise invoices on fortnightly basis. Bidder shall enclose all
documents as per check list issued by PMC/GAIL. However, EIC may authorize
payments for bills more frequently i.e. periodicity of less than fortnight, depending on
site requirements.
241 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 23 of 48
TITLE
REVISION 0
4.2 After receipt of complete RA Bill as per terms and conditions of the contract and duly
certified by Engineer-in-Charge (EIC)/PMC, on-account payment equivalent to seventy
percent (70%) of the net payable certified amount of the RA Bill will be released to the
contractor within a period of 07 working days from submission of certified bill by PMC to
GAIL. The balance amount will be released within a period of 15 days from submission
of certified bill by PMC to GAIL”
.
4.3 GAIL has introduced the computerized Bill Watch system whereby the contractor will
be issued a receipt at the time of the submission of the bills. The contractor can see
the status of their bill on GAIL’s website.
4.4 Employer will release payment through e-payments only as detailed in the Bidding
Document.
4.5 Further break-up of Lumpsum Prices, if deemed necessary for any progressive
payment of individual item may be mutually arrived at between Engineer-in-Charge
and the Contractor.
4.6 All payments against running bills are advance against the work and shall not be
taken as final acceptance of work / measurement carried out till the final bill.
4.7 Bills shall be raised by contractor in line with check list attached in Tender document.
4.8 Contractor shall submit No Claim Certificate, No Dues Certificate and Indemnity Bond
along with final bill. The Format for No Claim certificate and Indemnity Bond are
enclosed elsewhere in the tender.
242 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 24 of 48
TITLE
REVISION 0
SPECIFICATION
FOR
QUALITY ASSURANCE SYSTEM REQUIREMENTS
(Annexure - 6 to SCC )
(For Details – Refer our Technical Specification No.
MEC/S/05/62/66 of the same enclosed in Vol-II of the Tender)
243 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 25 of 48
TITLE
REVISION 0
STANDARD SPECIFICATION
FOR
HEALTH, SAFETY AND ENVIRONMENTAL (HSE)
MANAGEMENT AT CONSTRUCTION SITES
(ANNEXURE – 7 to SCC )
(FOR DETAILS – REFER OUR TECHNICAL SPECIFICATION NO.
MEC/S/05/21/65 OF THE SAME ENCLOSED IN VOL-II OF THE TENDER)
244 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 26 of 48
TITLE
REVISION 0
245 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 27 of 48
TITLE
REVISION 0
ANNEXURE-8 TO SCC
Whenever any material is issued by Owner, following conditions for issue of material
in addition to other conditions specified in the contract shall be applicable:
1.1 Necessary indents will have to be raised by the Contractor as per procedure laid
down by the Engineer-in-Charge from time to time, when he requires the above
material for incorporation in permanent works.
1.2 Materials will be issued only for permanent works and not for temporary works,
enabling works etc. unless specifically approved by the Engineer-in-Charge and the
same shall not be taken into account for the purpose of materials reconciliation.
1.3 The Contractor shall bear all other cost including lifting, carting from issue points to
work site/Contractor's store, custody and handling etc. and return of
surplus/serviceable scrap materials to Owner's storage points to be designated by the
Engineer-in-Charge etc. No separate payment for such expenditure will be made.
1.4 No material shall be allowed to be taken outside the plant without a gate pass.
1.5 The Contractor shall be responsible for proper storage, preservation and watch &
ward of the materials.
1.6.1 All unused/scrap materials shall be the property of the Owner and shall be returned
in good and acceptable condition size wise, category wise by the Contractor at his
own cost to Owner's Store(s).
1.6.2 No credit will be given to the Contractor for return of scrap. The Contractor should
quote the rates accordingly.
1.6.3 In case the Contractor fails to return unused/scrap materials, then recovery for such
quantity of materials, not returned by the Contractor shall be affected at following
penal rates from the Contractor's bills or from any other dues of the Contractor to the
Owner. Contractor shall make his own arrangements for weighing the off cuts to be
returned to Owner's stores.
246 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 28 of 48
TITLE
REVISION 0
(b) Penal rates for non return of Twice the Issue Rates
Unused material/excess scrap or Twice the Landed Rates (in
case Issue Rates are not
indicated in the Contract)
NOTE: 1) Landed Rate shall be arrived from the latest Purchase Order
of respective material received at site by Owner/MECON.
2.1 All pipes shall be issued in available lengths/shapes and no claims for extra
payments on account of issue of non-standard length & shape will be entertained.
Pipes shall be issued on linear measurement basis. All valves, flanges, fittings etc.
shall be issued on number(s) basis. Contractor shall store the materials in such a
way so as to avoid mixing of different types of material and shall maintain complete
identification and traceability at all times.
2.2 The scrap allowance for pipes issued by the Owner shall be 3% (2½% accountable +
½% non accountable) of the actual consumption as incorporated in the works.
2.3 All pipes in length of 2 meters and above shall be considered as serviceable material
provided the material is in good and acceptable condition and has clear identification
and traceability (Manufacturer’s name, heat number/batch number and test
certificates). Pipes in lengths less than 2 M shall be treated as scrap.
2.4 For the non account of pipes drawn by the Contractor over and above the actual
consumption as determined by the Engineer-in-Charge, plus 3% (2½% accountable +
½% non accountable) thereof to cover the scrap allowance, recovery at penal rate
shall be effected from the Contractor's bill(s) or from any other dues of the Contractor
to the Owner.
247 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 29 of 48
TITLE
REVISION 0
2.5 All unused/scrap pipes, valves, flanges, forged fitting like elbows, reducers tees shall
be returned by the Contractor category wise duly cleaned, greased and spec. marked
at his own cost to Owner's stores. In case the Contractor fails to do so then recovery
for such quantity of pipes not returned by the Contractor at the penal rates shall be
effected from the Contractor's bill(s) or from any other dues of the Contractor to the
Owner.
3.0 EQUIPMENTS
4.0 CABLES
4.1.1 All the surplus and serviceable cables out of the cables quantity(ies) issued by the
Owner to the Contractor shall be returned by the Contractor to the Owner's store in
good condition and as directed by the Engineer-in-Charge.
4.1.2 The Contractor shall be allowed a cutting/wastage allowance of 1.5% for power
cables and 3% for the control cables. This cutting/wastage allowance shall be
computed on the length of cables actually laid, measured and accepted.
4.1.3 All cables being returned to store should carry Aluminium sheet tags indicating the
size & type of cable. Cables of less than 15 meters length will be termed as scrap.
Cables of lengths 15M and above shall be termed as serviceable material & shall be
returned size wise and category wise to the Owner's store in wooden drums. Cables
of serviceable length being returned to stores in drum(s) shall be accepted only after
Megger value continuity test and physical measurement is carried out by the
Contractor to the satisfaction of Engineer-in-Charge. Empty cable drums and major
packing material (as decided by Engineer-in-charge) shall be Owner’s property and
shall be returned to Owner’s Store/designated place without any additional cost.
4.1.4 While carrying out material appropriation with the Contractor, the above points will be
taken into account. All serviceable materials returned by the Contractor (size wise &
category wise) shall be deducted from the quantity(ies) issued to the Contractor for
the respective sizes. Scrap generated for power cable and control cable shall also be
returned to Owner’s store on Lot basis.
248 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 30 of 48
TITLE
REVISION 0
4.1.5 Material appropriation shall be done & allowable scrap quantity calculated. The
wastage generated by the Contractor in excess of the allowable percentage shall be
charged at the penal rates.
5.1 All coated line pipes as per Line Pipe specifications shall be issued on linear
measurement basis. The line pipes shall be issued in available lengths and shapes
and no claim for extra payment on account of issue of non-standard length and
shape will be entertained. Contractor shall store and maintain the line pipes in proper
manner to avoid mixing of different classes of pipes. Contractor shall maintain
complete identification and traceability at all times. All cut pieces when returned to
Owner's storage points after bevelling, shall be considered as serviceable material
provided:
5.1.2 Pipe pieces have pipe specifications, manufacturer’s logo/name and heat number
duly authenticated with hard stamp of the authorised inspector as per approved
procedure.
All cut pieces of pipes measuring less than 2 M will be treated as wastage/scrap.
5.2 For the purpose of accounting of coated line pipes, following allowances shall be
permitted:
a) Unaccountable wastage
- Upto 100Km 0.1%
- 101 to 500 Km 0.07%
- Beyond 500 km 0.05%
b) Scrap (All cut pieces of pipes measuring 0.25%
less than 2 Meter)
c) Serviceable materials (All cut pieces of pipe 0.5%
measuring 2 Meter and above)
The percentage allowance shall be accounted on the basis of pipe book chainage for
main pipeline
5.2.1 Material appropriation shall be done & allowable scrap quantity calculated. The
wastage generated by the Contractor in excess of the allowable percentage shall be
charged at the penal rates as given in the contract.
249 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 31 of 48
TITLE
REVISION 0
For the purpose of accounting of optical fibre cable, all cut pieces measuring in
length of 40 m and above when returned to Owner's storage points shall be treated
as serviceable materials. All cut pieces of cable measuring less than 40 M will be
treated as scrap.
Cables returned in original drum (measuring 750m and above) with Optical Time
Domain Report (OTDR) shall be considered as unused material.
For the purpose of accounting of OFC (Optical Fibre Cable) following allowances
shall be permitted:
Material appropriation shall be done & allowable scrap quantity calculated. The
wastage generated by the Contractor in excess of the allowable percentage shall be
charged at the penal rates as given in the contract.
The Contractor shall make a schedule for use of cable jointing kits and get the same
approved from Engineer-In-Charge. The quantity mentioned in this schedule shall be
termed as ‘planned’ usage quantity which shall be issued to the Contractor. However,
any jointing based on site requirements as decided by Engineer-In-Charge shall be
included in planned quantity.
Any unplanned jointing required to be carried out by the Contractor due to reasons
not attributable to Owner/PMC shall be issued from spare quantity, if available with
Owner. Such unplanned OFC jointing kits shall be charged from the Contractor at
penal rates as per clause 1.6.4 above.
250 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 32 of 48
TITLE
REVISION 0
251 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 33 of 48
TITLE
REVISION 0
ANNEXURE-9A TO SCC
252 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 34 of 48
TITLE
REVISION 0
253 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.:8000018761 ANNEXURES TO SCC Page 35 of 48
TITLE
REVISION 0
ANNEXURE-9B TO SCC
CATEGORY-1
254 of 896
LAYING AND TERMINAL WORKS
FOR SRIKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 36 of 48
TITLE
REVISION 0
CATEGORY-2
Notes:
1) For equipments under Category-1: Bidders are required to submit the documentary evidence
for Ownership/ Hiring/ Lease of equipments listed in this category.
a) For Hired/ Lease Equipments: The documentary evidence shall be MOU from the
hiring/ leasing agency of the equipment. Bidder shall be responsible for timely
delivery of these equipments at the site at stipulated time.
b) In case, some equipment under Category-1 are owned by the bidder then the proof
of ownership to be submitted will be as stated in Annexure-9A.
2) For equipments under Category-2: No documents are required to be submitted along-with the
bid. However Bidder to indicate equipment as owned or hired for deployment purpose.
4) Based on availability of ROU / front & line pipe, Contractor shall propose minimum
equipment to be deployed and the same shall be finalized by construction-in-charge of
GAIL/ PMC on monthly/quarterly basis. Further, Bidder shall be required to augment the
above list with additional numbers/ categories of equipments, tools, tackles, as required
and directed by Engineer-In-charge to complete the work within the completion time
schedule and quoted price.
255 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 37 of 48
TITLE
REVISION 0
256 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 38 of 48
TITLE
REVISION 0
ANNEXURE-10 TO SCC
REQUIREMENT
SL.
DESCRIPTION
NO. Section I Section II Section III Section IV
1. Construction Manager 1 1 1 1
2. Planning engineer 1 1 1 1
3. QA/ QC engineer 1 1 1 1
4. Safety officer 1 1 1 1
5. Qualified Surveyor 1 1 1 1
6. Welding/ NDT engineer 1/1 1/1 1/1 1/1
7. Discipline Engineers
1/1/1 1/1/1 1/1/1 1/1/1
(Civil/ Mech./ Elec.)
8. Foreman / Supervisor 4 8 4 4
9. Civil surveyor / liaison
1/1 1/1 1/1 1/1
team
10. Document controller /
Account Officer (for line 1/1 1/1 1/1 1/1
pipe)
11. Store keeper / store in-
1/1 1/1 1/1 1/1
charge
12. Welder (Manual / Semi-
8 16 8 8
automatic)
13. Fitter 8 16 8 8
14. Grinder 8 16 8 8
15. Machine operator As
As Required As Required As Required
Required
16. Blast cleaning crew 1 2 1 1
17. Electrician / Machine As
As Required As Required As Required
mechanic Required
18. Rigger 2 4 2 2
19. Drivers As
As Required As Required As Required
Required
20. Pipe bending crew 1 1 1 1
21. Thrust/ Hor. Auger
As required As required As required As required
Boring crew
22. X-ray / Gamma Ray crew 1/1 2/1 1/1 1/1
23. Hydro-testing crew 1 1 1 1
24. Field joint coating crew 1 2 1 1
25. Holiday testing crew 1 2 1 1
26. HDD crew As
As required As required As required
required
(Refer (Refer Note (Refer Note
(Refer
Note 1) 1) 1)
Note 1)
257 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 39 of 48
TITLE
REVISION 0
REQUIREMENT
SL.
DESCRIPTION
NO. Section I Section II Section III Section IV
27. OFC jointing crew 1 1 1 1
28. Civil survey crew (with
1 1 1 1
equipment)
29. Station civil works
As
(carpenter/bar- As Required
Required
As Required As Required
bender/mason/fitter etc.)
30. Unskilled workers 10 20 10 10
31. Station mechanical, pre-
fabrication / erection 1 1 1 1
crew
The above proposed list of skilled manpower is the minimum to be deployed by Contractor.
NOTES:-
(1) HDD equipment and Crew as required shall be deployed as per requirement/SOW
finalized and as per instruction of EIC.
(3) For Magnetic cleaning and EGP, adequate equipment and crew shall be mobilized to
complete the activity within the given time schedule and as approved by Engineer-in-
charge.
(4) The Manpower as identified above should have required qualification and adequate
relevant experience.
258 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 40 of 48
TITLE
REVISION 0
Bidder shall be required to augment the above list with additional manpower,
as required and directed by Engineer-In-charge to complete the work within the
completion time schedule and quoted price.
Note: These manpower are to be mobilized within 30 days of Go ahead given or as per
written instruction from Engineer-in-Charge. Demobilization of these manpower shall be with
approval of Engineer-in-Charge.
259 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 41 of 48
TITLE
REVISION 0
ANNEXURE-10A TO SCC
1. The Bidder must provide a detailed organisational chart indicating the organisation or
personnel and equipment for each phase of the Works. CVs of main key persons
shall be submitted by the Contractor along with bid and replacement of any of these
key persons after LOA issuance shall be approved by Owner / Owner's
representative. Key persons shall be deployed during the entire duration of the work
till completion of all works. Non deployment of key persons will be subject to recovery
as defined elsewhere in the bid.
260 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 42 of 48
TITLE
REVISION 0
2. This description is only binding upon the Contractor. He must provide, at his own
expense, all the necessary equipment, machinery and personnel even in addition to
those indicated in the offer.
261 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 43 of 48
TITLE
REVISION 0
262 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 44 of 48
TITLE
REVISION 0
1. The labour rates are “all inclusive”. These rates include but are not limited to all payroll
costs and allowances, payroll taxes, fringe benefits, protective and/or special clothing,
construction supplies required for work of a nature included in this contract, overhead, profit
insurance, transportation and travel time.
2. The rates are inclusive of providing hand tools and consumables such as electrodes, filler
wire, gases, grinding wheels where the concerned category of labour is expected to use in
execution of the job but exclusive of all major equipment and machineries.
3. The normal time labour rates shall apply for all hours worked upto eight (8) hours in a day
and overtime rates shall apply for all hours worked in excess of eight (8) hours in one
working day, Sunday and Public Holidays. The payment for part of the day shall be made
on prorata basis.
___________________________________________________________________________
263 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 45 of 48
TITLE
REVISION 0
_______________________
(SIGNATURE OF BIDDER)
NOTES:-
a) For Sl. No. 1-38; the rates provided above plus 20% (twenty percent)
b) For Sl. No. 39 & 40; the rates provided above plus 50% (fifty percent)
264 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 46 of 48
TITLE
REVISION 0
265 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 47 of 48
TITLE
REVISION 0
ANNEXURE – 12 to SCC
HIRING / RECOVERY RATE FOR EQUIPMENTS
HIRING/ R ECOVERY
SL RATE (NOTE-2) (IN INR)
NO DESCRIPTION OF EQUIPMENT RATE / DAY
1 Pipe Layer / Side Boom – 70 T & Above Capacity Rs. 9500.00
2 Pipe Layer / Side Boom - 60 T and above (but below 70 T) Rs. 8500.00
3 Pipe Layer / Side Boom - 40 T and above (but below 60 T) Rs.8000.00
Excavator / Back Hoe-Series Ex 280/300 or Equivalent or
4 above Capacity Rs. 7500.00
5 Excavator / Back Hoe- Series Ex 200/260 or Equivalent Rs. 7000.00
6 Rock Breaker attachment Rs. 5600.00
Mono Drill Crawler Mounted/ Hand Drill (Pneumatic) for rock
7 Rs. 3000.00
blasting
8 Pipe Bending Machine- For all sizes Rs. 7000.00
9 Dozer With Ripper - D8 Or Equivalent Rs. 7500.00
10 Dozer - D7 / D6 Or Equivalent Rs. 4500.00
11 Horizontal Auger Boring Machine-For all sizes Rs. 3500.00
12 Auto Welding Unit-with operators & technicians Rs. 75000.00
Pipe facing (Beveling) machine (appropriate size)
13 for Automatic Welding Rs. 3000.00
14 Bevel Cutting Machine (Manual) Rs. 600.00
15 Grinding machine Rs. 200.00
16 Gas cutting set with cylinders Rs. 350.00
17 AUT Machine with 2 operators Rs. 15000.00
18 Semi Auto Welding Machines Rs. 2000.00
19 DG Welding Machines(SMAW) Rs. 1140.00
20 D.G. Sets : 62.5 KVA to 200 KVA (inclusive of generators) Rs. 3000.00
21 Induction/Resistance Heating Equipment Rs. 3000.00
22 Pipe Clamp (Pneumatic/Hydraulic)- Internal Rs. 1000.00
23 Pipe Clamp – External Rs. 500.00
24 X-Ray M/C – Internal Crawler Rs. 2500.00
25 X-Ray M/C – External Rs. 1800.00
26 Gamma Source Rs. 760.00
27 Manual UT Machine with 2 operators Rs. 500.00
28 Tyre Mounted Cranes (20 - 40 MT) Rs. 4500.00
29 Hydra (8 – 10 MT) Rs. 3500.00
HDD Rig with All Equipments & Accessories (Capacity 150 T
30 and above) Rs. 50000.00
266 of 896
LAYING AND TERMINAL WORKS
FOR SRIKKAKULAM-ANGUL
OIL & GAS SBU PIPELINE PROJECT (PART B) OF M/S
GAIL (INDIA) LIMITED MECON LTD,
DELHI
E-tender No.: ANNEXURES TO SCC Page 48 of 48
TITLE
REVISION 0
HIRING/ R ECOVERY
SL RATE (NOTE-2) (IN INR)
NO DESCRIPTION OF EQUIPMENT RATE / DAY
32 Air Compressor – (300CFM) Rs. 2000.00
33 Air Compressor - (450/600/800 CFM) Rs. 2500.00
34 Air Compressor - (1100 CFM) Rs. 2800.00
35 Water Lifting Pumps (400 m3/hr and above) Rs. 850.00
36 Filling Pumps (400 m3/hr to 1000 m3/hr) Rs. 900.00
Rs 12500.00
37 Mud Mat (for working in Monsoon season)
(per piece of min. size 4 m x
38 Tyre Mounted Cranes (75 MT & above) Rs. 7500
39 Pressurization Pump – Motorized Rs. 3000
40 Pipe Trailers (FB / Semi Low Bed) Rs. 3500
41 Hand drill(pneumatic)for rock blasting Rs. 2000
42 Dozing Pump Rs. 250
43 Dewatering Pump Rs. 800
44 Holiday Detector Unit Rs. 400
45 Dead WT Tester Rs. 200
46 Dumper / Tippers Rs. 1500
47 Pipe locator Rs. 500
48 Cable Cranes Rs.8000
49 Pipe Trailer for Coated Line Pipe Rs. 3000
50 Rock Breaking Machine with Excavator Rs. 5600/-
51 Trucks with driver Rs. 2000/-
52 Car/Jeep with driver Rs. 800/-
53 Tractor with trolley Rs. 600/-
54 Tripod with 5 Tons Chain Pulley Block Rs. 300/-
55 Pneumatic Drill (Tractor mounted for blasting) with Compressor Rs. 3500/-
NOTES:-
1. In case of foreign bidder, conversion rate applicable on one day prior to price bid
opening date published by the State Bank of India will be considered.
2. Rates are inclusive of operators / drivers and POL.
3. Rates are inclusive of contractor’s overheads & profit.
4. The recovery rates shall be the rates provided above plus 20% (twenty percent).
268 of 896
PARTICULAR JOB SPECIFICATION
269 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM- ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL (INDIA)
LIMITED MECON LTD,
DELHI
CONTENTS
SL.NO. DESCRIPTION
1.0 INTRODUCTION
270 of 896
Annexures to PJS
♦ Annexure-I : Cathodic Protection Works
♦ Annexure-II : Corrosion Monitoring System Works
♦ Annexure-III to V : Civil, Architecture & Structural Works
♦ Annexure-VI : Instrumentation Works
♦ Annexure-VII : Telecommunication Works
♦ Annexure-VIII : Electrical Works
♦ Annexure-IX : Fire Protection Works
♦ Annexure-X : Pipeline Information Management System
271 of 896
1.0 INTRODUCTION
1.1 GAIL (India) Limited, a public sector under Petroleum ministry, intends to develop
Natural Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh)
to Angul (Odisha) Natural Gas Pipeline Project and its Spurlines in the state of
Odisha and Andhra Pradesh for industrial consumers as well as City Gas Distribution
System (CGD).
M/s GAIL (INDIA) LIMITED has awarded MECON LIMITED, the project management
consultancy services of laying 24”/18”NB x 423 Kms (approx) Mainline (Part-A) from
Angul to Srikakulam along with its 18”/12”NB x 322 Kms (approx) Spurlines (Pat-B)
for transportation and distribution of Natural Gas in the state of Odisha & Andhra
Pradesh.
1.2 Present tender envisages laying of 18”/12” NB x 322 Km (approx.) spurline . Pipeline
will originate from IP Station-04 ( Srikakulam – Angul Pipeline –Part A at Ch. 341.0
Km) cum Dispatch Terminal at Ch. 0.00 Km to Receiving Terminal at Utkal Alumina
at Ch.190.8 Km and 12’’ NB dia x 68.3 Km ( approx.) & 62.97 Km ( approx.)
Consumer connectivity pipeline will originate from SV-06S & SV-07S Cum Dispatch
Terminal to consumers Vedanta and Nalco respectively..
1.3 This document covers details of work tendered, scope of work, scope of supply and
other requirements pertaining to pipeline and associated facilities. All works and
clauses of this document shall be applicable to all sections unless specifically
mentioned otherwise.
272 of 896
2.1.1 The brief scope of work for Part- B, broadly consist of Laying, Testing and
Commissioning of 18”NB x 48 Kms (approx) and 12”NB x 274 Kms (approx)
pipeline in the state of Odisha & Andhra Pradesh including all associated works for
transportation of Natural Gas (dry)/ R-LNG.
The said work has been divided into following Four (04) sections as given below:
The brief scope of work includes supply of materials (other than free issue material),
pipe laying work including but not limited to Construction Management, HSE & Quality
Management, Survey, ROU management, clearing of ROU, grading, stringing,
bending, welding (manual / Semi-automatic/ Automatic), trenching, joint coating,
lowering, crossings, crossings by HDD (wherever specified), Tie-ins, NDT and
destructive testing, backfilling, laying of pipeline along-with OFC & HDPE ducts, TCP
works, site restoration, hydro-testing, dewatering, swabbing, MGP & EGP, drying, pre-
273 of 896
commissioning, commissioning and Gas-in of 18”/12” Dia. pipeline including, Cathodic
protection, Corrosion monitoring works, Electrical works &Telecom works, Pipeline
information Management System (PIMS) , Videography including all associated work
274 of 896
- Entire works at SV Cum Dispatch Station including installation of scrapper
trap, insulating joints, flow tee, all valves, equipment, fittings, metering facility
( as required), all piping works and other facilities and all associated
mechanical, civil [including building works, Brick boundary wall , Guard
room (Porta Cabin Type), Pavement and supports etc], Architectural and
structural works, instrumentation, telecom works , Fire fighting works,
Corrosion monitoring works , Cathodic protection etc.
- Dumpyard management for linepipes @ Rs. 10,500/- per day (Excl. GST)
after completion of paid period of respective line pipe suppliers for dumpyard
maintenance
- All works related to HDPE duct laying and optical fibre cable (OFC) blowing.
The number of construction fronts required for successful completion of work as per
completion schedule or as per instruction of EIC is to be mobilized by contractor for
275 of 896
the entire pipeline length of each Part/Pipeline.
Fully equipped (as per Annexure-9B to SCC), maintained and functional fronts (team
of equipments, manpower & Resources) are required to be mobilized by the
Contractor to complete installation of facilities covered under each parts as a
minimum. All the construction fronts shall work simultaneously. In addition,
contractor shall deploy separate crews for rail, road, water crossings and restricted
areas. Contractor shall also mobilize separate teams for mechanical works at
Despatch Terminal, Receiving Terminal, Tap-off point & SV Stations.
2.3 Successful Bidder is required to submit detailed methodology for working in rainy
season before start of the work.
2.4 Contractor shall adopt suitable method of construction/ execution of work for
restricted ROU/ Common ROU and deploy adequate equipment & manpower etc. as
required. CONTRACTOR shall provide complete details of manpower, equipment etc.
to be deployed.
2.5 For execution of the pipeline work in the narrow ROU space in forest areas, the
CONTRACTOR shall consider the special requirements/ measures and shall deploy
adequate amount of manpower and equipment for performing the work.
The Contractor's Scope of work for the pipeline shall consist of, but shall not be
limited to, supply (as required), fabrication, installation, testing, swabbing, drying,
EGP, pre-commissioning and commissioning of the proposed pipeline system
including terminal piping works and hook-up works at terminal along with all
associated mechanical, civil, architectural, structural, electrical, instrumentation,
telecom, Corrosion Monitoring Works , fire fighting works etc. All such works that are
not indicated here below but are otherwise required to complete the work in all
respects shall form part of Contractor's Scope of Work.
The scope indicated below shall be read in conjunction with Schedule of Rates as
applicable, drawings, standards, specifications and other documents forming part of
the Contract document.
The detailed scope of work shall be in general but not limited to the following:
276 of 896
3.1 Main pipeline
3.1.2 Carrying out inspection of COMPANY supplied line pipes and pipe corrosion coating at
the time of receiving and taking-over for all defects etc. in the presence of
Company’s representative.
3.1.3 Carrying out repairs (including supply of all materials) of line pipe and pipe coating
not attributable to COMPANY which will include repair of all defects/ damages
occurring during transportation and/ or handling after receiving and taking over.
3.1.4 For pipes where cutting out involves more than 25mm from pipe ends, ultrasonic
inspection shall be carried out at pipe ends for line pipe and including supply of all
equipments. Contractor shall take prior approval from Company for the agency
engaged for carrying out ultrasonic inspection.
3.1.5 Loading, unloading, handling, stacking, storing and transportation to workshop/ work
site of all materials (other than bare and corrosion coated line pipes) that may be
used for the construction of pipeline system either supplied by COMPANY at their
designated storage yard/ store and/ or by CONTRACTOR as the case may be. All
Company supplied materials (ie; line pipe, Barrel, skid, IJ, other piping material
including flange & fittings as per schedule of rate) shall be issued to Contractor from
Company’s designated store.
3.1.6 Preparation of bevel end and coating edge of line pipes for welding.
3.1.7 Contractor shall incorporate the crossing details in the as-built alignment sheet after
completion of work.
3.1.8 Carrying out all additional topographic and/ or geotechnical survey as required for
277 of 896
local detours, detours at crossing locations during execution.
3.1.9 Geo-technical investigation and hydrological survey of all major water body crossings
and topographical survey for all plots are being carried out by the Company and the
same shall be provided to the contractors during execution of the contract. However,
contractor shall verify the authenticity of the data provided during execution and if
required, additional geo-technical investigation & hydrological survey shall be carried
out by the contractors for HDD crossings without any cost and time implication.
3.1.10 Carrying out thorough internal cleaning of all pipes to remove debris, shots, grits etc.
to the satisfaction of Engineer-in-charge.
3.1.11 Mobilizing and providing all equipments, manpower (skilled and unskilled),
consumables and other resources etc., as required for the execution of complete
work and thereafter demobilizing the same upon completion of work.
3.1.12 Obtaining all necessary approvals and work permits from concerned authorities
having jurisdiction, as applicable for performing the work including shifting/
relocation and restoration of telephone/ electrical poles and underground pipes and
other utilities etc., as required by local authorities and as directed by COMPANY.
Contractor shall also obtain all necessary approvals and work permits from concerned
authorities having jurisdiction for crossing underground utilities/ pipelines wherever
encountered along the pipeline route.
3.1.13 Cutting/ uprooting of trees within ROU, counting the number and type of trees to be
cut (before cutting) during pipeline laying works in presence of DFO/ concerned
authorities keeping record thereof and handing over the cut trees as directed by
concerned authorities/ COMPANY.
3.1.13A The Pipeline corridor shall be kept as narrow as possible at all times. The pipeline
shall be fully buried. Wherever possible vegetation along the centre line of the pipe
shall be uprooted carefully, with soil and roots intact, so that it can be used in the
reinstatement. During the excavation of the pipeline, trench top soil and subsoil
material shall be kept separate and backfilled in the same order where possible
imported backfill material shall be avoided and a selective backfill method used. The
Trench shall be opened and closed as quickly as possible. Safe exit routes/ramps
from the trench shall be provided for wildlife if a trench is left open overnight. The
Pipeline shall not alter the drainage characteristic of the land. Clay Stopper bungs will
be used as required.
3.1.14 Staking, clearing, grading of Right of Use (ROU) as required, trenching to all depths
in all types of soils including soft and hard rock, including blasting, controlled
278 of 896
blasting, chiseling, or otherwise cutting etc. to a width to also accommodate the
OFC/ cable duct as per relevant standards, drawings, specifications etc., stringing,
aligning, bending, welding, NDT by X-ray, field weld joint coating including supply of
all materials, protective coating of long radius bends and buried fittings/ valves
including supply of materials, providing sand/ soft soil padding, rock shield in the
trench wherever required including supply of sand/ soft soil, laying and lowering of
the pipeline including locating existing pipeline using pipe locator, wherever
applicable and maintaining the specified minimum spacing from existing pipeline(s),
back filling including supply of select backfill material where required, carrying out
rail, road, river, canal, drain, utility and submerged minor and major water course
crossings including installation of carrier pipe inside casing pipe at cased crossings
wherever required, providing two component epoxy coating on inner surface of
casing pipe wherever required by statutory authority, bank stabilization of water
course crossings as required, arranging all additional temporary land/ area required
for construction purposes. Supply and installation of anti-buoyancy measures viz.
continuous concrete coating, geo-textile gravel filled bags, extra cover, select backfill
etc. on pipeline, installation of supports wherever required, tie-in/ hook-up with
pipeline/ piping installed by others including cutting of temporary test headers, if
any, re-beveling, NDT, fit-up, welding, radiography etc.; clean-up, ROU restoration,
pigging, flushing, gauging, hydrostatic testing with the quantity of corrosion inhibitor
as required, dewatering with the addition of approved chemicals to neutralize the
effect of inhibitor added during hydro test at required dosage, swabbing, drying, pre-
commissioning and commissioning of pipeline including supply of all materials such
as required type and quantity of pigs, manpower, equipment, consumables and
carrying out all associated works as per relevant specifications, standards and
approved drawings enclosed with the Contract document.
Bifurcation of Soil & Rockey strata shall be done based on the equipments
used in trenching the pipeline section. For Rockey strata contractor have
to use rock breaking tool / rock hammer or other equivalent tools for
preparation of trench with due approval of EIC. Supply and installation of
rock shield as per specification including padding through sand/soft soil is
included in SOR item.
3.1.14A Owner’s scope shall be restricted to publishing of 3(1) and 6(1) Gazette notification
under P&MP act 1962 for acquiring ROU free of any encroachments/
temporary/permanent structures. Assistance in Liasioning during ROU
opening/Laying and getting permission from the statutory authorities shall be
279 of 896
included by Contractor in the rates quoted for Pipeline Laying & Installation works
under relevant SOR item.
3.1.15 All welding and NDT shall be carried out as per welding specification and as per
welding specification charts enclosed in the bid document.
Notes:
a) 18” & 12” (X-70) Main Pipeline welding shall be carried out by Manual/ Manual
+ Semi-Automatic welding process and NDT for all sizes of mainline shall be
carried out by X-Ray.
b) It shall be the discretion of the contractor to use any welding process for
18”/12” pipes. However no extra payment shall be made on account of re-
beveling of pipe ends, use of semi-automatic welding. The same shall be
deemed to be inclusive in the respective SOR item of mainline.
3.1.17 Welding of all tie-in joints including tie-in joints and bends on either side of major
river/ canal/ road/ rail crossings/ other facilities as required including adjoining
pipeline spreads, cutting of test header, re-beveling and tie-in with adjacent pipeline
segments.
3.1.18 Carrying out welding including cutting, edge preparation (inclusive of grinding the
edges of pipe, fittings, flanges, etc. to match with the matching edges of different
thickness wherever required), fit-up, bending, pre heating wherever required, NDT
including radiography and other non-destructive tests as specified. NDT requirements
for process and other piping shall be in accordance with relevant specifications
enclosed with the Bid document.
3.1.19 Field weld joints coating and corrosion coating of Long Radius (LR) bends etc. by
Heat Shrink Sleeve. 100% solid high build epoxy (minimum 500 micron thk.) shall be
280 of 896
applied for underground piping & valves.
3.1.20 Installation of all in-line insulating joints, valves, appurtenances, online instruments
etc.
3.1.21 Providing slope breakers in steep slope areas including supply of all materials,
wherever required. Contractor shall carry out slope breaker survey and slope breaker
shall be installed (before backfilling) as per standard after approval of Engineer-In-
charge.
3.1.22 Sand/soft soil padding of minimum 150 mm thickness around pipe wherever required
in areas where trenching has been done in rock or gravel or hard soil including
supply of sand/ soft soil. The pipeline trench shall not be filled with gravel and large
stones or boulders. Supply and installation of rock-shield in addition to 150 mm of
sand/soft soil padding around the pipe in rocky areas. The rock shield shall be of
minimum 6 mm thick polyethylene mat as per COMPANY specifications. Contractor
shall furnish all details of proposed rock shield to be used, for COMPANY’s approval.
3.1.23 Providing engineered select backfill consisting of loosely compacted cohesion less soil
like sand (for the areas prone to seismic activity) including supply of cohesion less
soil like sand for a distance of 1 km on either side, as per job standards. The pipeline
shall be surrounded by at least 0.6 m of select backfill. Extra digging of trench shall
be carried out to comply with above requirement.
3.1.24 The list of crossings indicating crossing methodology is enclosed as APPENDIX VIII to
PJS.
Listed crossings methodology as per APPENDIX VIII shall be followed until there is
no change in execution methodology. Moreover for the crossings beyond APPENDIX
–VIII shall be jointly deliberated and recorded for further payment through adopted
methodology by respective SOR item.
3.1.25 Carrying out National highway /State Highway, Expressway, railways and major road
crossings by conventional/ boring/ Jacking/ HDD method with casing pipe (Refer
281 of 896
Appendix – VIII- List of Crossings indicating Proposed Methodology).
3.1.26 Supply and Installation of 168 mm (6”) CS conduit for OFC cable/ HDPE duct for all
crossings with HDPE sub ducted in CS conduits (with proper end-sealing and
arrangement of wire etc for pulling OFC).
3.1.27 Supply and Installation of warning mesh over entire pipeline as per relevant
specification/ standard. Warning mesh shall be laid 300 mm above the top of
pipeline. The material of warning mesh shall be of high density polypropylene and
non- biodegradable type. It shall have non-toxic and anti-rodent properties.
3.1.28 Providing all necessary barricading material, safety signboards, warning lights etc to
safeguard the pipeline against accidents during construction of line in city area.
3.1.29 Localized purging/ inertisation including supply of nitrogen during hook up with
existing Pipeline/ piping at existing terminal, if any.
3.1.30 Loading, unloading, handing over and transportation of all surplus COMPANY
supplied free issue materials including line pipe to COMPANY designated stores and
stacking of the same. Stacking of surplus pipe & other material shall be inclusive of
supplying of sand bags etc.
3.1.31 Long radius bends shall be provided to the contractor if available. However for
supply of LR bends, Bare pipe made available to the contractor as free issue material
from Company designated storage yard. Transportation of free issue bare line pipes
from Company’s designated storage yard to fabrication shop of bends manufacturer
and fabrication of long radius bends from free issue line pipes for installation in
terminals/ other areas. Fabrication of long radius bends shall be performed by
induction process as per specifications enclosed with the Bid document by COMPANY
approved fabricators only. As far as possible, COMPANY will endeavor to supply pipes
of same dia. and thickness from same heat of steel for fabrication of bends. However
the same is not guaranteed. LR bends shall be installed only those locations shown in
alignment sheets and approach drawings. Transportation of pipes from place of issue
to the bend manufacturer’s plant and transportation of fabricated bends from the
bend manufacturer’s plant to work site(s), return of surplus pipes/ material/ bends
etc. to storage yard/ work site/ Company’s store shall be in Contractor’s scope.
3.1.32 Carrying out cleaning, flushing, swabbing (as applicable), dewatering, testing and
pre-commissioning of pipeline and associated facilities at Dispatch Station &
Receiving terminal up to the respective battery limits. Locating all major and minor
leaks during hydro-testing, if any.
282 of 896
3.1.33 Repair of leaks/ burst, not attributable to Contractor, occurring in Company supplied
material, shall be carried out by the contractor and the Contractor shall be
compensated as per provisions of the contract. However Contractor shall carry out
repair of defects attributable to Contractor at no extra cost to Company. Contractor
shall submit a report for failure to Company.
3.1.34 Carrying out magnetic cleaning (pigging with the help of magnetic pig to remove
steel debris), electronic geometric pigging (caliper pigging) for each pipeline section
including supply of all types of pigs, pig locating and tracking device, spares,
consumables, manpower etc. as per specification enclosed with bid/ contract
document.
3.1.35 Carrying out repair of all defects found during electronic geometric pigging including
locating, digging, cutting, welding, NDT etc.
283 of 896
Record (PQR).
• Approved Alignment Sheets / Crossing Sheets
• HSE Reports
• Material Reconciliation Report
• Status report of contractor bought out items including relevant documents
(QAP,TC, etc.)
• Data for Preparation of Pipe Book
• Technical documents of bought out items (MDS, QAP, QA, Inspection Report,
etc.)
• All As-Built Documents
3.1.38 Final clean-up and restoration of ROU and other conveniences like temporary
approach roads/ temporary works, barren land, road, rail, canals, water crossings,
cultivable land etc. to original condition as per specification and drawings to the
entire satisfaction of COMPANY and/ or authorities having jurisdiction over the same,
including disposal of surplus construction materials to Company’s designated stock
yard(s) or as directed by Engineer-in-charge. CONTRACTOR shall restore stones laid
to mark the boundaries of adjoining fields to original conditions. Contractor shall
arrange necessary clearance from all concerned authorities/ land owners to the
effect that ROU has been restored back to the original condition.
3.1.40 Idle time preservation by filling Nitrogen at a positive pressure of 2 bar (g) as per
specification, if required including supply of Nitrogen.
3.1.42 Taking over surplus bare and coated pipe from coating contractor at storage yard
after completion of work, loading, unloading, transportation and handing over of all
surplus Company supplied free issue material including short length of pipes to
Company’s designated Storage yard as directed by Engineer-in-charge.
3.1.43 In case any activity though not specifically covered in schedule of rates description
but same is covered under scope of work/ Specification / drawings, it is understood
that the contractor shall do such performance & provisions so mentioned without any
time & cost implication.
3.1.44 Any other works not specifically listed herein but are required to be carried out to
284 of 896
complete entire work related to pipelines and the associated facilities.
3.1.45 Installation of casing pipes (by open cut/jacking/ boring/ any other trenchless
technique) assembly, including supply of all materials, casing insulators and end
seals, vents and drains etc. complete, at cased crossings.
Supply of CS conduit 168 mm OD, IS: 3589, 6.4 mm thk steel conduit with HDPE
inter duct for laying of OFC at crossings
3.1.46 Providing loosely compacted cohesion less soil like sand, murrum, silty sand for
specified distance in seismic prone areas.
3.1.48 HDD works shall be carried out in accordance with specification enclosed with bid
package. For directionally drilled crossing, following shall be performed:
a) Carrying out all surveys and collection of data, as may be required for the
design and construction of the crossings.
285 of 896
b) Carrying out all engineering, design calculations and preparing all
construction drawings for laying of pipeline and optical fibre cable inside steel
pipe as per requirements for installation of river crossings by HDD method.
c) All construction activities required for installation of the crossings viz. site
preparation, preparation of pipe string, repair of damages to corrosion
coating, field welding, NDT including radiography, pretest of complete string,
corrosion coating of field joints, holiday testing of complete pipe string,
drilling in all types of soil including gravel, boulders and disintegrated and
hard rock, installation of pipeline, post installation hydro-testing of the
crossing section, capping, providing and installing markers at crossings.
d) Field joint coating shall be carried out by Dirax heat shrink sleeves by
Covalence Raychem (Berry Plastics Corporation) or TBK heat shrink sleeves
by Canusa-CPC or equivalent.
e) Supply of 6" NB, 6.4mm W.T.,IS: 3589, 300 micron epoxy coated steel
conduit, with inter duct of flexible HDPE/plastic corrugated tubing for laying
of OFC cable, preparation of steel conduit string and corrosion coating of
weld joints.
f) Installation of pipeline and 6" NB steel conduit for OFC (together in a single
drilled hole or separately in two independent drilled holes).
h) Testing and jointing of OFC at either ends with OFC in main pipeline trench.
3.1.49 Clean-up and restoration of ROU and other conveniences like road, rail, canals,
cultivable land, water facilities, irrigation facilities, boundary wall/fence etc. to
original condition as per specification and drawings to the entire satisfaction of
Company and/or Authorities having jurisdiction over the same, including disposal of
surplus excavated soil and other construction materials to a location identified by
Contractor approved by local authority without causing any disturbance to
environment and to the entire satisfaction of Company.
Contractor shall arrange necessary clearance from the concerned authorities/ land
owners to the effect that ROU/ ROW has been restored back to original condition.
286 of 896
Contractor shall carry out joint survey with representative of Competent Authority
(CA) and will obtain clearance in writing from CA that ROU has been restored to
original condition. Necessary clearance from statutory authority / NOC for restoring
the ROU to original condition shall be in Contractor’s scope. Necessary proof of
restoration i.e. through photographs and video recordings will have to be submitted
by the contractor where ever NOC is not available.
3.1.50 Fabrication of long radius bends from Free Issue line pipes by induction process,
carrying out corrosion coating of bends by heat shrink sleeve as per specification
enclosed with bid package.
3.1.51 Tie-in with the pipeline at rail, road, river and other crossings including cutting of test
headers as required and tie-in with terminal piping & with existing facilities as
applicable.
3.1.52 At all pipeline tie–in locations, the trench shall be excavated further wherever
possible and permanently lubricated HDPE duct shall be laid away (approx. 1 meter)
from the pipeline to avoid damage to the HDPE conduit and to the pipeline.
3.1.53 Preparation of video films with audio commentary covering all aspects of pipeline
construction annotated as required, conversion of the same to video CD/DVD ROM
format, submitting three (3) sets of the same.
3.1.54 All incidental and associated works and any other works not specifically listed herein
but are required to be carried out to complete entire work related to pipelines and
the associated facilities and making the entire pipeline system ready for operation.
3.1.55 Liasoning before preconstruction survey, opening of RoU and upto completion of
entire Mainline works (including CP and Telecom works); all type of Liaoning &
coordination with local people / Farmers / authorities for ensuring hindrance-free
construction works at site; obtaining NOC from respective land owner / farmers as
and when required; submitting request for authority permission (after obtaining the
letter from client), follow-up, assisting in site inspections/ route survey/ site report &
drawing preparation and submitting to owner for approval, re-submission after
incorporating comments (if any), modification if required. Liasoning with any
statutory authorities i.e., NHAI, PWD, Railways, Irrigation, Forest, Municipal
Corporation etc. Obtaining work permits / NOC from various statutory authorities
having jurisdiction for execution of the work and complying with all stipulations/
conditions/ recommendations of the said authorities.
287 of 896
3.2.1 Installation of casing pipes(by open cut/ jacking/ boring) assembly, including
transportation of casing pipe from company store and supply of all materials, viz.
casing insulators and end seals, vents and drains etc. complete, at cased crossings.
In case, coated casing pipe is supplied as free issue material, then the contractor
shall remove coating before installation.
3.2.2 Supply and installation of all types of pipeline markers including their painting
suitable for normal corrosive environment as per specification and all associated civil
works.
3.2.3 Tie-in/ hook-up of pipeline at Despatch / Receipt Terminal and existing facilities, if
any, is in the scope of Contractor.
Preliminary equipment layouts/ Plot plans & P&ID for the terminals/ stations are
enclosed with this Bid. These drawings are indicative only and are enclosed to enable
the Contractor to understand the nature of work involved. Issued for Construction
(IFC) piping General Arrangement Drawings (GADs) shall be progressively furnished
to the Contractor, at an appropriate time at project execution stage.
Contractor shall carry out all works strictly in accordance with the Issued for
Construction (IFC) drawings and reference specifications/ standards, documents, data
sheets etc. enclosed with this Bid document and instructions of Company/ Engineer-
in-Charge and other provisions of Bid document.
The Contractor’s Scope of Work for the work tendered shall consist of, but not be
limited to, supply (as indicated in Scope of Supply), installation, testing, pre-
commissioning and commissioning of terminal piping complete, with all associated
mechanical, civil, architectural, structural, electrical, instrumentation, telecom, fire
fighting works etc. as applicable including all such works which though specifically not
indicated here but will otherwise be required to complete the work in all respects.
The scope indicated below shall be read in conjunction with Schedule of Rates as
applicable, drawings, standards, specifications and other documents forming part of
288 of 896
the Contract document.
3.3.1 “Receiving and Taking over” as defined in specifications of all Company supplied
materials including equipment from the Company’s designated place(s) of issue
defined elsewhere, transportation including loading, unloading, handling from
Company’s designated place(s) of issue to Contractor’s own stock yard(s)/ work
site(s)/ workshop(s), including arranging all necessary intermediate storage area(s)
thereof till the materials are installed in permanent installation.
3.3.2 Procurement and supply of all materials, equipments that are included in the scope
of supply of Contractor, transportation of all materials from manufacturer’s works
including loading, unloading, handling, storing and transportation to work
site(s)/work shop(s) including arranging all necessary intermediate storage area(s)
thereof, as required.
3.3.3 Fabrication, erection, testing of all above-ground/ buried piping system including
installation of metering skid, scrapper trap etc. consisting of pipes, valves (manual
and actuated), flanges, fittings, flow tees, pig signalers, insulating joint etc; carrying
out all applicable works associated with buried pipeline within the Terminal boundary
wall/ fence (wherever applicable), carrying out welding, NDT including radiography;
weld repairs/ retesting, cleaning/ flushing hydro testing, dewatering, functional
testing, cutting of mainline and beveling (if required), excavation in all types of soil
for installation of piping and pipe supports, pre-commissioning, providing
commissioning assistance(wherever required) and commissioning including supply of
all materials and manpower that are required during pre-commissioning and
commissioning and all associated works.
3.3.4 Installation of Sectionalizing Valve stations in all terrains/ soils including all above
ground/ underground piping at all elevations and depths including all civil works, viz.
filling and compaction of valve station areas, excavation of pits, gravel filling,
construction of supports, foundations, construction of access road to installation from
nearest metalled road, installation of all valves and valve actuators and all fittings/
piping works.
3.3.5 Preparation of isometric and/or fabrication drawings required for the purpose of
fabrication during execution of work.
3.3.6 Obtaining all necessary approvals and work permits from concerned local authorities
having jurisdiction including hot work permit as applicable for performing the work in
existing terminal facilities. Arranging of adequate fire-fighting equipment viz. fire
brigade, fire extinguisher, shielding from existing facilities, oxygen mask etc. for
289 of 896
carrying out the work safely to the satisfaction of COMPANY.
3.3.7 Carrying out welding including cutting, edge preparation (inclusive of grinding the
edges of pipe, fittings, flanges, etc. to match with the matching edges of different
thickness wherever required), fit-up, bending, pre heating wherever required, NDT
including radiography and other non-destructive tests specified. NDT requirements
for process and other piping shall be in accordance with relevant specifications
enclosed with the Contract document.
3.3.8 Installation of all types of valves (manual/ actuated), all types of inline/ online
instruments such as PSVs (other than those covered separately), safety valves,
tapping for thermowells, sample connections, pressure gauges, corrosion monitoring
system etc. for all sizes and ratings including fixing of gaskets, bolts, studs and nuts
of all sizes, ratings and materials.
3.3.10 Installation of all in-line and on-line instruments including Skin Temperature
measurement assemblies.
3.3.11 Void
3.3.12 All associated civil works, viz. levelling, filling and compaction of station areas as
required, necessary stone pitching at the sides of earth fill (if required), excavation of
pits, gravel filling, paving as required, access road to installation from nearest
metalled road, etc.
3.3.13 All associated structural and mechanical works including supply of all materials
required, unless covered separately elsewhere in the Bid document, including
construction of foundations (PCC/ RCC works) for equipments and pipe supports and
sleepers, fabrication and erection of supporting structural elements for piping such as
shoes, clamps, anchors, guides, insert plates, brackets, structural column, valve
operating platforms, pipe crossovers etc. Contractor shall provide grating as per
details currently included in the tender document or as per details furnished
subsequently.
3.3.14 Supply of bolts, nuts, gaskets, washers, U bolts, clamps, clips, gaskets for supports
for all piping works.
3.3.15 Supply, fabrication and erection of supporting structural elements for piping such as
shoes, clamps, anchors, guides, insert plates, brackets, structural column etc.
3.3.16 All associated structural, instrumentation, telecom, mechanical and civil works
including supply of all material required, covered separately elsewhere in the Bid
290 of 896
document.
3.3.17 Hook-up of piping with equipments and vessels and hook-up of all piping at the
battery limit with the pipeline/ piping including cutting of temporary test header, re-
beveling, NDT, fit-up, welding, radiography etc. including interface/ coordination as
required with other Contractor(s)/Agencies.
3.3.18 Painting of above ground piping (including supply of materials), structural steel
elements, for pipe supports, all equipments and all related miscellaneous items as
required and as directed by Engineer-in-charge. Paint shall be suitable for normal
corrosive environment in accordance with specification. Wherever touch up/ repair of
primer is required, high build epoxy zinc phosphate primer shall be used.
3.3.19 Protective coating of 100% solid high build epoxy minimum 500 micron thk for all
underground piping, valves, fittings, etc..
3.3.20 Corrosion protection coating of all field weld joints for buried piping of all sizes
including supply of all materials.
3.3.21 Cleaning (card board blasting), Hydro testing, dewatering and drying of piping
system of all sizes as per specifications enclosed.
3.3.22 Final clean up and restoration of site, facilities etc. as per the requirement of
COMPANY/ Engineer-in-Charge including filling (wherever required) and grading of
areas around stations for avoiding any local flooding of area.
3.3.23 Transportation and stacking of all surplus COMPANY supplied free issue material to
Company’s designated store after completion of works or as directed by Engineer-in-
Charge.
3.3.24 Preparation of as-built drawings, documents and project records as per instructions
of Engineer-in-Charge.
3.3.26 Obtaining all statutory clearances, approvals, permissions and hot work permit for
the works as required.
3.3.27 Fabrication and erection of piping supports and change of existing support/
additional supports installed by others as directed by Engineer-in charge.
291 of 896
3.3.28 Idle time preservation of mainline and terminal piping with positive pressure 2 bar
(g) for specified period.
3.3.29 Any other works not specifically listed herein but required for completion of the
works in all respects.
3.4 All construction works shall be carried out as per “Approved for Construction”
drawings, procedures, specifications and applicable codes and standards. Any
changes at site shall also need prior approval from the COMPANY and revision of
drawings.
Temporary Cathodic Protection works shall be carried out as per the scope detailed
in particular job specification enclosed as Annexure-I and SOR enclosed elsewhere
with the tender.
Corrosion Monitoring System works shall be carried out as per the scope detailed in
particular job specification enclosed as Annexure-II and SOR enclosed elsewhere
with the tender.
Civil works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-III and SOR enclosed elsewhere with the
tender.
Architectural works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-IV and SOR enclosed elsewhere with the tender.
Structural works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-V and SOR enclosed elsewhere with the tender.
Instrumentation works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-VI and SOR enclosed elsewhere with the tender.
292 of 896
Telecommunication works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-VII and SOR enclosed elsewhere with the tender.
Electrical works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-VIII and SOR enclosed elsewhere with the
tender.
Fire Protection works shall be carried out as per the scope detailed in particular job
specification enclosed as Annexure-IX and SOR enclosed elsewhere with the tender.
Pipeline Information management system shall be carried out as per the scope detailed
in particular job specification enclosed as Annexure-X and SOR enclosed elsewhere
with the tender.
Company shall supply the following Pipeline/ Terminal piping materials required for
permanent installation to the Contractor at an appropriate time during the execution
stage as free issue materials:
Line Pipes:
Entire required quantity of bare/ coated line pipes of all thickness and dia shall be
supplied by Company. Line pipes (bare/ coated) shall be made available to the
Contractor at designated storage yards. Transportation of the line pipe from
designated storage yards in to work site shall be in the scope of the CONTRACTOR.
Further the CONTRACTOR has to ensure safe storage.
a. Bare Line Pipes X-70 for 18” x 11.13 mm, X-70 for 12’’ x 7.9 mm shall be used for
above ground piping in front of scrapper trap by the respective Contractor.
b. The quantities of coated and bare line pipes indicated in the bid document are
approximate and may vary. The exact quantity shall be intimated to the Contractor
after award of work.
c. Contractor to note that quantities of line pipe indicated in the bid document includes
293 of 896
contingency/ extra length over and above the actual requirements. Surplus pipes
shall be taken over by the Installation contractor from the coating contractor at
storage yard after completion of Installation works. It is the responsibility of
installation contractor to return surplus pipes to the COMPANY designated storage
yard as per instructions of Engineer In-Charge after completion of installation works.
d. Receiving and taking over of bare and coated line pipes at Storage yard including its
inspection. All trucks / trailers for transportation of line pipes from storage yards to
site/ ROU/ Contractor’s storage Yard shall be supplied by contractor.
e. Contractor to note that quantities of line pipe indicated in the bid document includes
contingency/ extra length over and above the actual requirements. Surplus pipes
shall be taken over by the Installation contractor from the coating contractor at
storage yard after completion of Installation works. It is the responsibility of
installation contractor to return surplus pipes to the COMPANY designated storage
yard as per instructions of Engineer In-Charge after completion of installation works.
f. Void
g. Transportation of pipes and other free issue material from place of issue is in
Contractor’s scope. Contractor shall note that the prices indicated in the Schedule of
Rates shall be inclusive of taking the delivery and transportation of line pipes and
other material from the storage yard/ stockyard to work place(s).
h. Bevel Protectors of the line pipes shall be the property of the pipeline installation
Contractor. He has to collect and dispose off the bevel protectors. Contractor shall
quote accordingly.
i. For Fabrication of LR bends, Contractor shall arrange all transportation from Pipe
Storage Yards to bend fabricator’s shop and work site.
i. Scrapper traps including handling devices, pig signalers, quick opening closure
and pressure safety valves.
ii. Insulating joints
iii. Flow tees
294 of 896
iv. All types of valves (ball, plug, globe etc.). Wherever required, actuators shall be
supplied along with valves.- as per scope.
v. Quick Opening End Closures of all sizes for blow down lines.
vi. All types of fittings such as elbows, tees, reducers, weldolets, sockolets etc. – as
per scope
vii. Flanges/ blind flanges/ spectacle blinds/ spacers & blinds
viii. Metering skids
ix. Casing pipe for bored crossings, if available
x. Assorted Pipes, if available
xi. LR Bends, if available
xii. CS Conduit , if available
The Company shall make above free issue materials available at the GAIL store
locations as indicated in Annexure-2 to SCC
Contractor shall arrange all trucks/ trailers, cranes etc. for transportation of above
materials including loading at Company store, unloading at contractor’s storage yard/
work site, arrangement of cranes, handling etc.
Contractor shall return all surplus material to company designated storage yard as
decided by Engineer- In- charge.
i. The Contractor shall be responsible for taking over of the material and
subsequent handling, hauling, transportation to the actual work
site(s)/fabrication yard(s) and storage & safe keeping of the materials.
Contractor shall arrange all equipment/ cranes etc. for loading of these
materials on their truck/trailers for transportation.
ii. The Contractor shall inspect all COMPANY supplied free issue materials at the
time of taking over from the COMPANY and defects noticed, if any, shall be
brought to the notice of COMPANY/ COMPANY representative and jointly
recorded. Once the material has been taken over by the Contractor, all the
responsibility for safe keeping of the materials shall rest with the Contractor.
iii. Every month the Contractor shall submit to the COMPANY an account for the
material issued to the Contractor in the Performa prescribed by Engineer-in-
Charge.
295 of 896
iv. On completion of the works, Contractor shall submit a “Material Appropriation
Statement” for all materials supplied by the COMPANY as free issue materials.
vi. All unused and scraps material shall be the property of the COMPANY and
shall be returned by Contractor to COMPANY at COMPANY’s designated
storage point(s) including transportation of the same from Contractor’s stock
yard(s)/worksite(s)/work shop(s) to the COMPANY’s designated storage
point(s). Contractor shall be responsible for the proper measurements of the
unused/ scrap materials to be returned to the COMPANY.
The procurement and supply, in sequence and at appropriate time and place,
including inspection and expediting, of all materials and consumables required for
completion of the work as defined in this bid document except the materials
specifically listed under para 4.1 above as COMPANY free issue material, shall be
entirely the CONTRACTOR's responsibility and the item rates quoted for the
execution of the WORK shall be inclusive of supply of all these materials. All
materials supplied by the CONTRACTOR shall be strictly in accordance with the
requirements of relevant COMPANY material specifications enclosed with the
Contract document. All equipments, materials, components etc. shall be new and
specifically purchased for this job from Company approved vendors, duly inspected
by third party inspection agency(shall be 3.2 certified--refer APPENDIX-VI – Third
Party Inspection Agency).Only manufacturer certificate shall not be adequate. As a
minimum, the materials to be supplied by CONTRACTOR may include but shall not
be limited to the following.
ii. All materials for all types of pipeline markers including cement, sand,
reinforcements, structural steel etc. and paint conforming to normal corrosive
environment as per specification enclosed with the bid documents.
iii. Casing insulators and end seals and materials for casing vents and drains as
per drawings.
296 of 896
iv. All materials required for continuous concrete coating/ gravel filled geo-
textile bags for providing negative buoyancy to the pipeline wherever
required. Contractor shall take prior approval of COMPANY and furnish all
details including design calculations in case of use of purpose built geo-textile
bags. For river crossings, only continuous concrete coating shall be provided
for negative buoyancy.
v. Supply of warning mat. The material of warning mat shall be of high density
polyethylene and non-biodegradable type. It shall have non-toxic and anti-
rodent properties.
vi. Supply and installation of warning mesh over entire pipeline as per BS
EN:12613 (latest edition). The material of warning mesh shall be made from
virgin quality polyethylene (PE)/ polypropylene (PP) and shall have UV
resistant, non bio-degradable, non-hazardous type in accordance with BS
EN:12613. It shall have non-toxic and anti rodent properties.. Rate for supply
and installation of warning mesh shall be included in the relevant SOR items
of Schedule of Rates (SOR) Mainline Works.
The total minimum width of the same shall be as follows:
- For 12” Pipeline – 600 mm ( Width for supply in single part)
- For 18” Pipeline – 400mm + 450 mm ( Width for supply in two parts)
Warning mesh shall have golden yellow colour and printed warning
text shall be in red colour and non deletable type with high abrasion
resistant
vii. Supply of all materials for installation of wind-shock and safety signboard at
different stations.
viii. All materials and consumables required for external corrosion coating and
concrete coating (where required) of field weld joints.
ix. All materials required for field joint coating, corrosion coating of LR bends
and repair of damaged corrosion coating of line pipe. Contractor shall confirm
that proposed field joint coating material is suitable for type of terrain
encountered along pipeline route. Contractor shall take prior approval from
COMPANY for field joint coating material to be used. The cut back length
shall be 150 mm + 20 (-0) mm.
x. All material, equipment & consumables for HDD works including Dirax heat
shrink sleeves by Covalence Raychem (Berry Plastics Corporation) or TBK
297 of 896
heat shrink sleeves by Canusa-CPC or equivalent.
xi. All materials required for sand/ soft soil padding around pipeline and optical
fibre cable, select backfill of approved quality, slope breakers, bank
stabilization of water crossings etc.
xii. For rocky areas, rock shield shall be provided in addition to sand/ soft soil
padding. Rock shield shall be of high density extruded polyethylene mesh
with following properties:
Contractor shall obtain prior approval from Engineer-in-charge for rock shield
material & its application procedure.
xiii. All materials including consumables, nitrogen etc. required for hook-up with
existing facilities and equipments.
xiv. Long radius bends (R=6D) of all angles and wall thickness fabricated from
COMPANY supplied free issue line pipes.
xvi. All safety tools, tackles, devices, apparatus, equipment etc. including ladders
and scaffolding complete as required.
xvii. All stud bolts, nuts, jack screws, all type of gaskets (metallic spiral wound
gaskets) in required quantities to be used for permanent installation into the
system for all sizes and ratings of flanges and flanged valves, equipment
etc., including nuts, bolts, gaskets, washers, U bolts, clamps, clips etc. for
pipe/ equipment supports. All materials for supports shall be in contractors
account.
xviii. All types of coating and painting materials including primer and paints
suitable for normal corrosive environment for painting above ground piping
and 100% solid high build epoxy (minimum 500 micron thk.) for
underground piping/ valves, etc.
298 of 896
xix. All pipes, fittings, flanges, blind flanges, gaskets, nuts, bolts, clamps,
strainers, equipment/ consumable, metallic blinds, temporary gaskets as
required for filling, pressurizing, hydrostatic testing and dewatering,
swabbing etc. including test headers for pigging and hydro-testing.
xx. All materials such as cohesion less soil/ sand required for installation of
pipeline in seismic active zones.
xxi. All materials, equipments, consumables etc. required for magnetic cleaning
and caliper pigging of pipeline.
xxii. All materials required for civil, structural and general civil works including
structural steel, cement, reinforcement, concreting, grouting etc. in facilities
like despatch terminal and receiving terminal including all types of equipment
and material required for excavation/ construction of pits for equipment and
instrument installations and steel/ structural steel materials of all types.
xxiii. All materials required for repair/ restoration of pavements, roads, bunds,
walls, other structures affected/ damaged by Contractor’s construction
activities. Materials shall be equivalent/ superior to those used for original
construction of the facility.
xxiv. All equipment and consumables required for hydrostatic testing like pumps,
pressure and temperature gauges, test water and corrosion inhibitors for test
water for hydrostatic testing.
xxv. Supply of CS conduit pipe,168 mm OD, 6.4 mm wall thickness CS conduit for
OFC for all cased/ bored crossings and where ever main pipeline is installed
by HDD method including supply of insulators, end seals etc. CS conduit of
168 mm dia. for OFC shall also be used in open cut river crossing by
strapping with concrete coated line pipe.
xxvi. All materials, consumables and equipment required for welding and for all
types of tests and NDT such as radiography, ultrasonic testing, magnetic
particle, dye penetrate examination etc. including radiography film, X-ray/
gamma ray machines, developing equipment and consumables, Ultrasonic
equipments etc.
xxvii. All safety tools, tackles, devices, apparatus, equipment etc. including ladders
and scaffolding complete as required.
299 of 896
xxviii. Steel materials such as structural steels, reinforcement steels and steel for all
types of supports, foundations, ladders, platforms, etc.
xxix. All steel materials such as structural steel, reinforcement steel, shims,
wedges, packing plates (machined wherever required), pipes, nuts & bolts,
washers, U-bolts, anchor bolts, clamps, clips, pipe saddles/ shoes etc. as
required for the fabrication of structural supports and supports basements/
foundations, platforms etc. Pipes supplied by COMPANY shall not be used for
fabrication of supports and support saddles etc.
xxx. All materials for corrosion protection of buried piping, pipe fittings, valves,
casing pipes, etc.
xxxi. All materials and equipments related to blasting of rock/ controlled blasting
for excavating trench, grading of ROU, pipeline & pipe laying/ installation and
other works.
xxxiii. Mobilizing Pipe/ cable locator for locating existing pipelines/ cables
xxxv. Sand ridges (sand, polyethylene sheets etc.) and other materials for stacking
of surplus pipes at Company’s designated storage yard.
xxxvi. Corrosion inhibitor, oxygen scavengers and bactericides for water used for
hydrostatic testing including water for testing.
xxxvii. Required quantities of nitrogen for idle time preservation and pre-
commissioning of Pipeline and associated facilities, if required.
xxxix. All pigs for cleaning, gauging, filling, dewatering, swabbing, drying, pre-
commissioning and commissioning of the pipeline.
xl. All materials i.e. fittings, flanges, valves, blind flange etc. required for
isolation and nitrogen purging for pipe section, manpower, equipment, pigs,
consumables, nitrogen required for carrying out commissioning of pipeline
300 of 896
along with necessary piping and instrumentation connection for monitoring
flow rate, pressure, temperature etc. providing temporary facilities for
venting/ flaring along with necessary piping, valves and instrumentation etc.
shall be in contractor’s scope.
xli. All other materials not specified above but required for successful completion
of the entire work whether temporary or permanent in nature.
The item rates quoted for the execution of the work shall be inclusive of supply of all
materials mentioned above unless specifically covered otherwise under schedule of
rates. The quantities indicated in schedule of rates under Contractor’s scope of
supply are approximate. Contractor shall carryout MTO of all materials required
based on IFC general arrangement drawings, P & IDs and firm up the actual
requirement of materials. All escalation/ extra materials procured by Contractor for
contingencies shall be Contractor’s property and no payments shall be made for such
materials. Payment shall be made for actual materials installed by the Contractor as
a part of permanent installation.
In case, any item is covered in scope of work but is not present in Schedule of Rates
(SOR), it will be assumed that bidder has included cost implication of those items in
their total price.
4.3.1 All materials shall be preserved against deterioration and corrosion due to poor or
improper storage while under the custody of the Contractor.
4.3.2 All materials shall be duly protected by the CONTRACTOR at his own cost with the
appropriate preservatives like primer, lacquer coating, grease etc. and shall be
covered with suitable material to prevent them from direct exposure to sun, rain,
wind and dust.
4.3.3 Whenever applicable, pipes shall be stacked according to the identification marks and
stacks shall be arranged on sleepers/ sand pads at least 300 mm above ground.
4.3.4 The CONTRACTOR shall check that valves, fittings, specials etc. are not subjected to
corrosion from hydrostatic test water remaining in the packing. Any such condition
when detected should be brought to the notice of Engineer-in-Charge and remedial
measures taken as directed.
4.3.5 All machined surfaces shall be properly greased and should be maintained and
protected from damages.
301 of 896
4.3.6 Openings of equipment, machinery, valves etc. shall be kept blocked/ covered with
blinds to prevent entry of foreign matter.
4.3.7 As far as possible materials shall be transported to the site of erection only just prior
to the actual erection and shall not be left lying around indefinitely on ground but
kept on packing/ sleepers etc. to maintain the minimum distance from the ground as
specified and/ or as per directions of Engineer-in-Charge.
Contractor shall adhere to meet the indicative construction mile stone enclosed as
Appendix-I to Particular Job Specification. Contractor shall be responsible for close
monitoring and completion of indicative construction milestone.
Detailed scope of work and scope of supply covered in this document given above is
pertaining to pipeline laying and associated pipeline terminal/ station piping works
only. Detailed scope of work related to civil, architectural, structural, electrical,
instrumentation, telecom , Corrosion Monitoring works and fire fighting works are
covered in separate documents in detail and the same are enclosed elsewhere with
the Bid document. All these documents shall be read in conjunction with this
document and shall form an integral part of the overall Scope of work of the
Contractor(s).
7.1.1 All piping/ pipeline works shall be carried out as per following:
302 of 896
The alignment sheets including plan and ground profile details are enclosed along
with the bid document for contractor’s reference and information only.
Further, successful contractor(s) after award of work shall immediately carry out
topographic survey and geotechnical investigation of all crossings other than those
provided by the company in the pipeline route and prepare crossing drawing for
each crossings. The drawing shall be submitted for Company’s approval. IFC
alignment sheet shall be issued based on the input of above crossing drawings.
The formats for crossing drawing to be used are enclosed with the bids. Contractor
shall also incorporate the crossing details in the as built alignment sheet after
completion of work.
Contractor shall also perform any additional topographic surveys and geotechnical
investigations that may be required for local detours or at crossings or at any other
location during execution of the project without any extra cost to the COMPANY.
Pipeline alignment shall be marked on village maps by CONTRACTOR wherever
detouring is beyond existing ROU. CONTRACTOR shall be deemed to have
considered such eventualities while formulating his bid.
Surveyor Alignment Sheets and crossing drawings are included in the Bid package.
The details of class location, crossings details are separately enclosed. These
drawings/ details are indicative only and are furnished to enable to estimate the
quantum of work and to quote a firm price for the work.
Typical station drawings are also included in the Bid package .These drawings are
marked as “Tender Purpose Only”.
The IFC (Issued for Construction) drawings issued during project execution stage
may vary from the drawings included in the Bid Package. CONTRACTOR shall carry
out all works in accordance with these IFC drawings at no extra cost to the
303 of 896
COMPANY.
The proposed 18”/12” Dia pipeline in Odisha & Andhra-Pradesh originated from 18’’
NB dia Despatch (cum Receiving Terminal) at IP-04 of SAPL-Part A. Entire Pipeline
has been divided in 04 ( Four Sections) based on location, dia …etc. For details refer
Pipeline Network Schematic Diagram No. MEC/23V9/05/28/M/000/0022 Rev-0.
7.4.2 The number of crossings and features along the pipeline route described above are
approximate. CONTRACTOR shall not be entitled for any compensation in terms of
time and cost in case of variation in the above. Contractor shall verify the above data
and carry out pipeline installation works without any extra cost & time to COMPANY.
Survey reports as available are enclosed with bid document. Such data is issued to
CONTRACTOR for his reference purposes only. It shall be Contractor’s responsibility
to verify the data and satisfy himself with regard to accuracy and utility of data.
CONTRACTOR shall carry out any additional soil data/ investigation required for
installation. CONTRACTOR shall not be entitled for any compensation in terms of time
or cost in case of any variation in actual site conditions from the data furnished in the
bid package. It shall be Contractor's responsibility to familiarize himself with sub-soil
conditions along the pipeline route and workout the lengths of pipeline to be laid in
different subsoil conditions including the quantum of rock excavation that would be
necessary. Unit rates quoted shall also be inclusive of all rock excavation. No extra
compensation shall be payable to CONTRACTOR for any rock excavation whatsoever.
Contractor shall carry out construction work within the width of pipeline ROU as
made available to them with no time and cost implication to the Company. The
Contractor shall arrange any additional ROU requirement for construction purposes. It
shall be Contractor’s responsibility to make arrangement for any additional land
required for fabrication, construction, storage and all other work areas. In certain
restricted areas such as private holdings, congested and plantation areas etc. ROU
may be restricted to a width of 1-5 meters. In forest areas only 10 m ROU will be
made available to the contractor. Contractor shall propose suitable execution
methodology and time schedule for construction/ execution of work at areas of
restricted ROU and deploy adequate equipment & manpower etc. as required.
304 of 896
Contractor shall also arrange additional land during installation of Pipeline by HDD.
Wherever the detouring is carried out beyond ROU during pipeline installation, the
detoured pipeline alignment shall be marked on village maps by the pipeline
installation Contractor.
In case the pipeline passes through city areas, it will be laid generally in the carriage
way. Wherever it is not possible to lay the pipe line on the carriage way for any
reason whatsoever, the pipeline will be laid on service road / footpath. It will be the
responsibility of the Contractor to identify all the underground utilities after
surveying the area along the gas pipeline route and lay the pipeline with clear
distance of 20 cm from other existing utilities like cable, water pipeline etc. In
case of hydrocarbon pipeline the clear distance shall be 50 cm.
• The contractor shall finalize the alignment of pipeline by making the trial pits
at regular intervals in order to ensure the location of existing underground
utilities.
305 of 896
to work during monsoon season. Thus for such areas the contractor shall
plan his work accordingly and submit his schedule to relevant authorities
without any time as well as Cost implication.
• The authorities may impose stringent conditions for laying the pipeline in
certain areas like limited length of working section, night work shift only
etc. Thus the contractor must submit his working methodology to relevant
authorities in order to obtain the necessary permission for laying the pipeline
prior to commencement of work.
• To comply with the agreed work schedule, the contractor may work in
shift or extended hours.
• The contractor shall be responsible for overall entire quality control activities
for the present project.
306 of 896
• Contractor proponent shall have to take prior approval of concerned
Government agencies while carrying out blasting wherever required.
• Contractor proponent shall have to take preserve top soil dug and shall be
restored to original condition on completion of the work.
• While carrying out the laying activities any damage to other utilities to be
repaired by the contractor to the full satisfaction of the utility agency. Any
claim arises out of damage of other utilities shall be borne by the contractor.
• Contractor proponent shall construct the pipeline and other infrastructure and
adopt safety measures as per the standards & specification laid down by the
concerned agencies from time to time.
The overall duration of the works at every point of the pipeline route, from the
opening of the working area to lowering of pipeline and trench backfilling shall not
exceed the permit condition of relevant authority.
No ROU exist for the city portion line along the authority land. Working strip may be
available along the road side for the construction site. Contractor should deploy
suitable equipment and adopt his working methodology accordingly.
Contactor shall not be compensated for any reduction in the width of working strip.
307 of 896
7.7.6 REVERSE OF THE WORKING STRIP
No fencing of any kind along the pipe route is essential to be provided. However, it
remains the responsibility of the Contractor to barricade the area of open trenches so
that no untoward accident takes place.
Crossing of utilities will be done by invariably going below the utilities maintaining a
clear gap of minimum 20 cm except hydrocarbon pipelines. From hydrocarbon
pipelines, clear gap of minimum 50 cm shall be maintained. If due to site constraint
it is not possible to lay the pipeline as per the above cover requirement, Contractor
shall initiate the proposal for approval of Deviation and obtain written permission
from EIC.
7.7.9 DELETED.
7.7.10 MARKERS
For urban Agglomeration (UAs) / Towns having a population of 1 lakh or more, the
warning marker shall be installed at least at every 50 meters and if required
additional markers shall be installed where there is possibility of damage or
interference.
Aerial markers shall in general be installed along the pipeline at every kilometers
intervals and at places specified by COMPANY. The aerial kilometer marker having
the warning details can also be treated as warning marker.
Kilometre markers shall in general be installed along the pipeline between the aerial
markers at every one (1) kilometre interval. A kilometre marker is not required if the
relative length between its location and any pipeline warning sign is less than 200
308 of 896
metres.
Right-of-Way boundary markers shall be installed at every 250 metres interval along
the entire pipeline route. These shall be installed on either side of the pipeline
alignment to define the ROW boundary limits. These shall also be installed at pipeline
turning points to maintain the continuity of the ROW limits.
In urban agglomerates (UAs)/ towns having a population of 1 lakh or more, pipeline
route marker shall be installed at least at every 25 meters.
Special Marker shall be installed at Location where the following changes takes
place:
The above data may be provided on other types of marker (except RoU boundary
marker), if the relative distance between the two does not exceed 100 m.
7.7.11DIRECTIONAL MARKERS
Direction markers shall be installed to identify the significant turning points of the
pipeline during aerial traverse. One direction marker shall be installed at each turning
point, in addition, two more direction markers shall be installed along the pipeline
alignment, one on either side of the turning point at 150m from the turning point.
309 of 896
they enable the watering of the trees. No excavated material shall be piled up
in the road crossings. It may be insisted upon by the authority to remove
all the excavated materials immediately after trenching.
• To prevent the excavated stone and earth from falling into the trench, a strip
20cm shall be left clear between the edge of the trench and the bottom of
the pile of excavated earth. This width may be increased, according to
the nature of the ground and the atmospheric conditions.
• Each site shall be provided with an identification board mentioning the reason
for the work and the names of the Company, the Contractor and the
Consulting Engineer, as stipulated in the special specifications.
• At both ends of the trench, the Contractor shall install 2 traffic and warning
signs, and Display board one immediately close to the trench and the other
ahead, as required by the Engineer-In-Charge.
• The Contractor shall install lights and warning lights around all working areas,
in accordance with the special specifications. The voltage shall conform to the
safety regulations in force.
• The Contractor shall install barricading and lighting of all trial-holes, trench
sections and other excavations.
• The Contractor shall provide watchmen wherever deemed necessary for the
safety of the public and of the workers, in particular as regards working sites,
on site material stockage, temporary dumping yards, etc.
7.7.14 BARRICADING
310 of 896
The contractor shall provide the barricades of size 2m wide X 1.5m high of
wooden/plastic/steel with necessary supports along the open trenches to
protect/caution the public about the digging work without any cost to owner.
The barricades shall be painted as per the requirement of authority with the
owner’s/Consultants/Contractor’s details, job being carried out, cautions,
inconvenience captions, etc also needs to be provided.
Bidders are advised to make site visits to familiarize themselves with all the salient
features of subsoil, terrain and available infrastructure along the pipeline route.
Contractor shall be deemed to have considered all constraints and eventualities on
account of site conditions along pipeline route while formulating his bid. Contractor shall
not be eligible for any compensation in terms of cost and/ or time, on account of site
conditions along pipeline route varying to any extent from whatever described in the
Bid Package and the drawings furnished along with the Package.
COMPANY shall supply bare, externally corrosion coated with 3-layer polyethylene
coating and internally epoxy coated line pipes.
Contractor shall receive and take over the pipes progressively as per construction
requirements at designated place of issue in presence of Company’s representative.
At the time of taking-over, Contractor shall perform inspection of pipes and pipe
coating for all defects in the presence of Company’s Representative. COMPANY shall
be liable for repair defects and damage to pipe coating noticed at the time of taking
over. However installation Contractor shall repair all defects to pipe and pipe coating
occurring after taking over including those during transportation and handling.
Rebuffing for dents (in bevels) less than 1 mm in depth shall be carried out by
Contractor ahead of welding in the field at no extra cost to COMPANY. Contractor
shall take-over the entire quantity of bare and coated line pipe from storage yard
after completion of installation works. Return of surplus line pipe material to
Company’s designated storage yard is in installation Contractor’s scope including
loading, transportation, unloading, handling, stacking of pipes at storage yard and
getting the pipes inspected to Company’s representative at storage yard.
CONTRACTOR using suitable material compatible with parent coating system shall
311 of 896
carry out any repairs to 3-layer polyethylene coating. The coating repair material and
procedure for application shall be submitted to COMPANY for approval prior to start
of construction.
The COMPANY shall obtain a general permission from the various authorities having
jurisdiction over the area as necessary for construction of the pipeline. CONTRACTOR
shall obtain the necessary permits like work permit/ excavation permit/ trench
opening permit etc for all works from the authorities having jurisdiction before the
actual execution of various phases of the works and all stipulations/ conditions/
recommendations of the said authorities shall be strictly complied with at no extra
cost to COMPANY. CONTRACTOR shall also obtain all necessary permissions from the
concerned authorities for installation of pipeline at railways, roads, water crossings
and at places where blasting is required. COMPANY may, however, assist
CONTRACTOR in obtaining such permissions, wherever required, by issuing
recommendation letters etc. In case of damage to other utilities/ infrastructure,
Contractor shall be responsible and the required compensation as per the directions
of concerned authorities/ COMPANY shall be paid by the Contractor. After completion
of work, Contractor shall obtain a certificate from the concerned authorities that the
job has been completed as per their requirement and the area/ land has been
restored to their satisfaction.
In case blasting is required for making of trench for laying pipeline, it shall be
responsibility of the contractor to ensure safety of pipeline while carrying out
blasting operations. The controlled blasting procedure shall be subject to approval of
Company.
7.12.1 While working in plantation areas, Contractor shall take due care to minimize the
damage of trees. The number of trees felled shall be restricted to minimum based on
working requirement for pipeline installation. In the paddy field area, Contractor shall
exercise maximum care not to damage the crop outside the ROU. The compensation
of damage of crop outside ROU, if any, shall be to Contractor’s account. Damage to
any obstruction, temporary/ permanent structure, boundary walls etc. within ROU
shall be repaired, restored and shall be to Contractor’s account.
312 of 896
7.12.2 During ROU clearance, the vegetation shall be cut off at ground level leaving the
roots intact to the extent possible. Only stumps and roots directly over the trench
shall be removed for pipeline installation.
7.12.3 Intake and discharge of water required/ used for line flushing and testing should not
cause unacceptable environmental disturbance. During dewatering process, proper
drainage arrangement shall be made to discharge the hydro-test water to avoid
flooding of the nearby area.
7.12.4 As far as possible, the contractor shall ensure that river and stream crossings are
done during dry season to avoid disturbance of breeding grounds and soil erosion.
The riverbed, embankments and dykes shall be restored adequately after installation
of crossings.
7.12.5 The contractor shall exercise adequate care while working, in order to avoid damage
to forests and wildlife.
a. Backfill for pipeline trench at locations where the pipeline crosses the faults
should be provided with loosely compacted (unit weight<1.8 t/m³) cohesion
less soil for a distance of 1 km on both side of such crossings. The angle of
friction of cohesion less soil to be used for backfilling should not be more than
25º.
In case the dug out soil of the trench is clayey in nature (undrained shear
strength greater than 0.5 T/m²), the local soil shall be replaced by
engineered (cohesion less) backfill as mentioned in previous paragraph.
Otherwise, the same dugout soil can be used as backfill. The recommended
backfill shall be at least 600 mm thick all around the pipeline. Extra digging
of trench shall be carried out to provide 600 mm cohesion less soil all around
the pipeline.
b. If the fault crossing zone, the pipeline is in rocky terrain, the following
recommendation is made.
When the pipeline is to be laid on a rocky terrain, the stones/ boulder/ rock
dugout from the trench should be crushed such that maximum size of stone/
boulders is limited to 20 mm. The crushed stone should be mixed with locally
available soil, before using as backfill.
313 of 896
Alternatively, 150 mm sand padding shall be provided all around the pipeline
before crushed boulders/ stones are placed over the sand padding. In this
case the size of boulders can be increased up to 100 mm.
The pipeline shall be buried normally at a depth of 1.2 meter except river/ rail/ road/
canal/ water crossings where cover shall be as given below or as per the
requirements of statutory/ local authorities whichever is more stringent. Increased
wall thickness (as indicated in alignment sheets) and cover shall be provided at
critical locations and at crossings.
The pipeline, in general shall be laid underground with minimum cover as given
below.
Sl.
Location Minimum Cover (m)
No.
Areas of agricultural, horticultural activity,
1 limited or no human activity, industrial, 1.2
commercial and residential area.
2 Rocky terrain 1.0
3 Drainage, ditches at roads/ railway crossings 1.2
Minor river crossings / canal / drain / nala /
4 1.5
ditches
5 Major river crossings ( below scour level) 2.5
314 of 896
In case, any private dwelling, industrial building or place of public assembly falls
within 15m of pipeline, additional cover of minimum 300 mm shall be provided
over and above the cover indicated in the above table. Additional soil cover other
than specified above shall be provided at locations indicated by statutory/ local
authorities as per agreements between COMPANY and authorities.
7.15 Crossings
Pipeline at railway crossings shall be provided with a casing pipe. The casing pipe
shall be three nominal pipe sizes larger than carrier and shall be installed by boring/
jacking. Internal of Casing pipe shall be coated with two-component epoxy coating
wherever required by statutory authorities. It should be noted that the extent of
casing pipe generally specified by Railways, is 14.0 m beyond centerline of the
outermost tracks on either side or 0.6 meter beyond the ROU limits of Railways on
either side, whichever is more. All railway crossings shall be cased crossings. The
railway crossing shall comply with the requirements of API 1102 and Indian Railways
regulations. The crossing angle shall be as close to 90° as possible. Cover of casing
pipe for railway crossings shall be minimum 1.7 m wherever railway track is on
embankment. Care shall be taken to isolate the pipeline crossing installation from
aerial electrical wires and shall be suitably insulated from underground conduits
carrying electrical wires. The casing pipe shall be provided with minimum 50 mm
diameter vent pipe. Casing vent pipe shall be at least 1.2 m away vertically from
aerial electrical wires and shall be suitably insulated from underground conduits
carrying electrical wires on railway land. Casing pipe should be so placed and
oriented so as to prevent any leakage inside railway boundary except through the
vent pipes. The casing pipes shall be installed with even bearing throughout the
length.
For all rail, road, canal, river & other water crossings, Contractor shall liaison with
relevant authorities and intimate them well in advance about the schedule and
methodology of crossing. It shall be obligatory on the part of the laying Contractor to
ensure that Authorized Representative of the authority under whose jurisdiction the
crossing falls should be made available at site by the Contractor at the time of
making crossing. After completion of works and complete restoration of ROU,
Contractor shall provide NOC from the relevant official pertaining to complete
restoration to their satisfaction and certification in respect of no other damage
caused to the their property outside the earmarked ROU.
315 of 896
i. The method of crossing of roads such as open cut/ boring/ trench-less shall
be firmed up by CONTRACTOR in consultation with concerned authorities and
COMPANY. The CONTRACTOR shall also take due care to identify and take
due precautions so as not to disturb or damage the utilities like cables, water
lines and other structures.
ii. After laying the pipeline in a road crossing by open cut method, the
CONTRACTOR shall completely restore the road to its original condition.
iii. While laying the pipeline in road crossings by open cut method the
CONTRACTOR should ensure that the traffic is not stopped during the
execution of work. This may be done by cutting half of the road at a time so
as to enable the traffic to pass on the remaining half of the road.
Alternatively, the CONTRACTOR can provide diversion roads to maintain the
flow of traffic. For NH crossings, traffic of both sides shall not be disturbed.
iv. The CONTRACTOR shall provide proper caution boards during daytime and
danger lights during night time when the cutting operation of the road is
going on.
v. For cased crossings, the pipeline should be taken through the casing pipe, the
top of which should be at least 1.2 metres below the road top as specified or
as per the requirements of the local authorities, whichever is higher. All
National Highways as indicated in relevant drawings/ alignment sheets shall
be cased crossing installed by trenchless method. In state highways,
crossings shall be installed by open cut method, however, trenchless method
shall be used wherever required by authorities.
vi. For National Highways/ state highways, crossing shall not be too near the
existing structure on the NH maintaining a minimum distance of 15 meters or
as specified by Highway Authority.
vii. The National Highway crust shall be built to the same strength as the existing
crust on either side of the trench or to thickness and specification stipulated
by Highway Authority. Care shall be taken to avoid the formation of a dip at
the trench.
i. Canal and other water crossings shall be carried out by open cut/ boring/
trench less technology method. CONTRACTOR shall firm the method of
crossing in consultation with concerned authorities and COMPANY.
316 of 896
ii. HDD method shall be adopted for river/water/ canal crossings that are
specifically mentioned in this document or decided at site by Engineer-in-
charge. These crossings shall be installed and paid separately as per
schedule of rates.
iii. No damage should be caused to any irrigation sources, while laying the
pipeline through canal crossings.
iv. The flood banks of the River/ Canal should be brought to the original
condition, if they are damaged by the laying of the pipeline. Stabilization of
banks shall be carried out as per requirements of concerned authorities.
v. The detailed construction methodology/ plan and time etc. shall have to be
finalized by CONTRACTOR in consultation with concerned authorities having
jurisdiction over canals/ rivers. COMPANY shall provide assistance by
providing introductory letters.
a. Contractor shall restrict the pipeline laying activities within the ROU
acquired. No additional land in forest area shall be used. Contractor shall
clear only the minimum width required for laying of pipeline. Number of
trees/ plants felled shall be kept a minimum based on construction
requirements. ROU width in forest area is 10 m.
b. Full care shall be taken to ensure that no damage is caused to the adjoining
forest area while carrying out the work. However, in case of any damage,
Contractor shall be liable to pay suitable compensation as per requirements
of Forest Department.
At all crossing locations (viz., rail, road, canal and minor water course crossings) the
optical fibre cable shall be installed inside a HDPE Telecom Duct to be installed by the
CONTRACTOR.
At all such crossings where the carrier pipe is installed by open-cut of the facility
crossed, HDPE duct shall be installed along with the pipeline for installation of the
Optical Fibre Cable. At river crossings where anti buoyancy measures are provided for
the carrier pipe, HDPE duct shall be placed inside a CS casing pipe and shall be
strapped to the mainline at 5m interval using high strength PE straps. Net specific
317 of 896
gravity of pipe in empty condition should not be less than 1.2.
7.19.1 Pipelines
Hydrostatic testing of mainline shall exclude valves at terminals and facilities that are
to be installed as a part of the scrapper stations. Temporary test headers shall be
provided and the mainline shall be hydrostatically tested between the temporary test
headers only.
The highest point of the test section shall be subjected to the minimum test
pressure as specified below. The minimum hydrostatic test pressure in the pipeline
during testing shall be as follows:
The maximum hydrostatic pressure shall not however exceed the pressure required
to produce hoop stress equal to 95% of SMYS of pipe material based on the
minimum wall thickness in the test section. The test duration shall be 24 hrs. Hydro
test shall be done with corrosion inhibitor, wherever required. Mainline valves shall
be installed after successful completion of hydrostatic pressure testing.
Station piping to be tested hydrostatically for minimum 6 hours at pressure 1.5 times
MOP (design pressure).
318 of 896
Contractor shall de water the pipeline as per the directions of Engineer-in-charge.
For HDD, Pre-hydrotest, Post-hydrotest and pipeline final hydrotest, contractor has
to arrange soft water in view of alkalinity/ Salinity in the river water.
In no case shall the pipeline be kept empty i.e. without nitrogen filling.
Transfer of test water from one test section to another section may be considered,
however dosing additional quantity of corrosion inhibitor shall be done.
The products to be used for corrosion inhibition of the water used for hydro testing
and their dosage shall be as specified in Hydro test specification.
Contractor (not the inhibitor manufacturer) shall get the inhibitor tested for
corrosion inhibition and microbiological control efficiency from competent Govt/ PSU
Laboratory. The test report shall be submitted to COMPANY for approval prior to
undertaking hydro testing works.
The dosage as recommended by COMPANY shall only be adopted.
Necessary records for dosing of inhibitor should be maintained by the laying
Contractor and such records should be handed over to COMPANY.
Piping facilities between the insulating joint and hook up point/ battery limit and all
319 of 896
above ground facilities installed by Contractor shall be hydrostatically tested to a test
pressure equivalent to 1.5 times design pressure as per “Flushing and Testing of
Piping System” enclosed with the Contract document. All valves in the piping
network being hydro tested shall be kept in the crack open position. Holding time
shall be minimum six hours.
7.19.5 Preservation
The positive pressure shall be maintained at 2 bar (g) in the pipeline during
preservation. The necessary arrangements like valves, fittings, manpower etc. shall
be kept for maintenance of pressure in the pipeline during idle time.
CONTRACTOR shall submit a detailed procedure for leak detection during hydro test.
Such method of detection shall consume minimum possible time to complete the
hydro test activity within contractual completion schedules. This procedure needs
approval of the Engineer-in-charge.
All works for locating and repair of major leak/ burst attributable to COMPANY
(occurred during hydrostatic testing) including necessary repairing/ replacing/ cutting
and removing out defective pipe length as defined in the specification and shall be
payable as per relevant items of schedule of rates.
All works for locating and repair of minor leak attributable to COMPANY (occurred
during hydrostatic testing) which require sectionalizing of pipeline shall be payable as
per relevant items of schedule of rates.
Contractor shall carry out repairing/ replacing of defective pipe length including
cutting and removing of defective pipes, pre testing of replacement pipe for 24 hours
and welding into main line, NDT of the welds, coating of the weld joints, clean up,
re-testing of pipeline including providing all equipments, manpower & consumables.
320 of 896
electronically on a web-based format for Company / Consultant to monitor
progress on a daily basis.
The individual contractor shall carry out magnetic cleaning and caliper pigging of the
pipeline system being installed by him. Contractor shall engage a specialized agency
that have previously carried out such operations (magnetic cleaning and caliper
pigging) and shall develop procedures, supervise and monitor the entire operations,
coordinate with other Contractor(s) as required. Rectification of defects observed
during caliper pig run, shall be carried out by individual section contractor including
digging, cutting, replacement, repair, welding, NDT etc.
7.25 Commissioning
Contractors shall mobilize all equipment, consumables and manpower for carrying
out pigging, drying, inertization and commissioning activities.
Contractors shall engage a specialized team/ agency who have previously carried out
such operations and shall develop procedures, supervise and monitor the entire
operations, coordinate with other Contractor(s) as required till the time
commissioning operations are completed. Contractor shall mobilize all equipment,
materials, consumables including pigs, nitrogen and manpower etc for
commissioning activities. All necessary piping connection as required shall be carried
out.
321 of 896
Commissioning activities shall be carried out as per applicable specifications enclosed
with Contract.
7.26 Priorities
COMPANY may, at its sole option, assign priority of construction to any part of the
total pipeline or terminal works. Contractor shall comply with such priority of
execution without any time and cost implication to the COMPANY.
The construction work shall be carried out based on Issued for Construction (IFC)
drawings issued to Contractor at the time of construction. The final IFC drawings
issued during execution stage may vary to some extent from the drawings included
in the Bid Package. CONTRACTOR shall carry out all works in accordance with the
IFC drawings and reference specifications/ documents with the Contract at no extra
cost to the COMPANY.
The piping fabrication, erection, welding, flushing and hydro testing and painting
works shall be carried out as per standard piping specifications enclosed with
Contract. The hydro test duration shall be minimum 6 hours.
For pipeline installation work within existing terminal facilities which are under
operation, Contractor shall obtain all necessary permissions for working in/ around
the facility including hot work permit as applicable and shall be fully responsible for
the safety of the existing facilities/ areas during all phases of work and shall fully
abide by and comply with the restrictions and conditions of COMPANY/ concerned
authorities imposed on Contractor from time to time. Providing all safety appliances,
gas detectors required during execution of the work, arranging of adequate fire
fighting equipment viz. fire brigade, fire extinguisher, shielding from existing facilities,
oxygen mask etc. for carrying out the work safely to the satisfaction of COMPANY
shall be done by the Contractor.
Contractor may be permitted to work for limited hours in such places. For working on
Sundays/ Holidays, the required permission may be obtained well in advance. During
any emergency, work shall be suspended till further permission is obtained by
Contractor. Idle period in case of interruption shall not be compensated to
Contractor.
The structure/ electric poles/ telegraph poles existing in the vicinity of proposed
pipeline shall be properly taken care so that the stability of structure is not affected
322 of 896
during construction.
7.30Technical Requirement
The technical requirements for the pipeline laying as well as terminal works as
defined herein shall be read in conjunction with Schedule of Rates, specifications,
standards, drawings and other applicable documents enclosed with the Bid
document. All piping/pipeline works shall be carried out as per following:
323 of 896
b) Drawings AutoCAD
For the purpose of preparation of as-built drawings, Contractor shall update the
"Issued for Construction" drawings provided by the Company. For drawings where
electronic copies are available for IFC drawings, Contractor shall provide as built
drawings in electronic form as well as in hard copies. Where only hard copies are
available for IFC drawings, Contractor shall prepare and submit as built drawings in
hard copies.
10.1 Owner shall furnish piping and Instrumentation diagrams (P & I D), preliminary plot
plan along with the tender. Owner shall also supply design & engineering drawings and
construction drawings including general arrangement drawings for piping, mechanical &
instrumentation systems and other related/ required systems, at appropriate times and
as requisitioned by contractor in his time schedule.
10.2 Contractor shall prepare isometric drawings & bill of materials and submit the same for
Owner/ Consultant’s approval/ record.
Contractor shall prepare drawing for utilities line as required as per SOR and submit
the same for Owner/ Consultant’s approval/ record.
10.3 No construction small or big shall be carried out without proper construction drawings
duly approved by Owner's Engineers at Delhi or site office or Owner's representative
duly authorized to do so.
For Mainline, route survey alignment sheets and crossing survey details shall be
furnished along with bid by Owner. However, detail-crossing drawings with crossing
methodology shall be submitted by Contractor for prior approval. Any additional survey
and data required to complete above should be done by Contractor without any extra
cost.
324 of 896
Terminals P&ID, layout drg., piping GAD, Isometric, all electrical & instrumentation drg,
all civil drawings. For final submission only 4 sets of documents plus the original
transparencies shall be handed over by Contractor. Any construction done by
Contractor without duly approved drawings shall be wholly at his risk and cost.
Contractor shall also submit soft copy of pipe book in excel along with hard copy.
Soft copy of all as-built drawings shall be also submitted in AutoCAD. Videography/
photograph of all major activities/ milestone achieved shall also be arranged and
submitted by the Contractor. For details of documentation to be submitted for
mainline and terminal refer enclosed specification for documentation for pipeline
construction Specification No. MEC/S/05/21/69 enclosed elsewhere with the tender.
10.5 Specifications
The work shall be carried out by CONTRACTOR strictly in accordance with the
specifications enclosed in Volumes II &III of this document.
"Casing insulator shall be made of HDPE, modular type, offering a high impact
strength and low coefficient of friction. Each casing insulator element shall represent
a flexible section containing a toothed male butt strap at one end and an
appropriately toothed female slot on the other end. No metallic parts or attachments
should be considered in the casing insulator element assembly. The design of casing
insulator should allow for onsite adjustments for any variances within the allowable
O.D. range of pipeline and should grip the pipe firmly without any chances of
horizontal movement or breakage of the insulator rings during installation. The
insulator rings should be fastened onto the carrier pipe with the appropriate tool to
be provided by the casing insulator manufacturer."
325 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM- ANGUL PIPELINE
OIL & GAS SBU PROJECT (PART B) OF M/S GAIL (INDIA)
LIMITED MECON LTD,
DELHI
In case of any conflict between the requirements for casing insulator as mentioned
above and technical specification enclosed elsewhere in the bid document, the
requirements mentioned above shall supersede.
326 of 896
10.7.1 Contractor to note that the minimum requirements of inspection and testing of the
bought-out items shall be governed by attached QAP with the tender document.
However, contractor shall submit their QAP in line with the requirement specified in
attached QAP for Owner’s/ PMC’s approval.
10.7.2 Contractor to note that all the documents/drawings submitted by them as a part of
bid shall be considered only to assess Bidder’s technical capability and shall in no
way absolve them from complying with all the requirements of the Tender. All works
to be performed by the Bidder shall be strictly in accordance with tender conditions.
10.7.3 Contractor shall submit duly signed & stamped hard copies of all required
documents/ drawings/ data sheets etc to MECON for their review & approval as per
terms & condition of tender documents. The date of receipt of these documents/
drawings/ data sheets etc at MECON shall be deemed as the date of submission. If
any documents/ drawings/ data sheets etc require re-submission due to any error/
deficiency noticed during review/ approval stage, in that event the additional time
required by the contractor to get the revised document/ drawing reviewed/approved
by MECON shall be solely to contractor’s account and in no case contractor shall be
entitled for any time or cost benefit.
10.7.4 The drawings/documents/ data sheets etc shall be reviewed, checked, approved and
duly signed/stamped by successful contractor before submission. Revision number
shall be changed and revisions shall be highlighted by clouds during submission of
revised documents/drawings/data sheets by the successful contractor. Whenever the
successful contractor require any sub-supplier drawings to be reviewed/approved by
MECON, the same shall be submitted by the contractor after review/ approval and
stamped by the Contractor. Direct submission of the sub-supplier’s
drawings/documents/data sheets etc without contractor’s approval shall not be
entertained.
10.7.5 Review/Approval of the contractor’s submitted drawings/ documents/ data sheets etc
by MECON would be only to review the compatibility with basic design and concepts
including mainline work procedure and in no way absolve the successful contractor
of his responsibility/contractual obligation to comply with tender requirements,
applicable codes, specifications and statutory rules/regulations. Any error/deficiency
327 of 896
noticed during any stage of manufacturing/execution/installation shall be promptly
corrected by the contractor without any extra cost or time, whether or not comments
on the same were received from MECON during the drawing review stage.
10.7.6 Contractor shall make & maintain their own suitable sized Storage yard/ area
(covered as well as open space) to store Free Issue Materials (FIM) in proper
manner. Contractor shall also maintain the FIM in good condition during entire
storage period by using all type of servicing/overhauling such as cleaning , greasing,
protecting from rusting/ pitting etc.
Storage Yard/ Area shall have proper motarable approach, adequate indoor &
outdoor area lighting, potable & service water, proper rack & wooden sleeper etc. for
staking/ storing the material, availability of material handling equipment of adequate
capacity etc.
Owner/PMC’s Site In-charge shall visit & inspect the Contractor’s Storage Yard/ Area
and upon his concurrence only, the FIM shall be stored by the Contractor at the
particular Storage Yard/ Area.
Delay in issuance of FIM due to non acceptance of Contractor’s Storage Yard/ Area
(i.e mainly because of non compliance of the minimum condition as mentioned
above for Storage Yard/ Area) shall not be attributable to Owner/PMC.
328 of 896
11.0 INDICATIVE CONSTRUCTION
MILESTONE -
(Appendix-I to Particular Job Specification of Work)
329 of 896
LAYING & CONSTRUCTION OF STEEL GAS PIPELINE ALONG WITH ASSOCIATED
FACILITIES FOR SRIKKAKULAM-ANGUL PIPELINE (SAPL) PROJECT (PART B)
ZERO DATE
DURATION MONTHS
Sl.
Activity Description (IN
NO.
MONTHS)
1 2 3 4 5 6 7 8 9 10
AWARD OF CONTRACT
1 MOBILIZATION 1.0
4 FIT-UP,WELDING,NDT 6.5
Note:
1. The schedule of station work e.g. mechanical, civil & structural, telecom work shall be in line with the schedule indicated above meeting the
schedule requirement for mechanical completion and commissioning, as mentioned in bid document.
2. Commissioning shall include drying & commissioning of all associated works.
331 of 896
12.0 DATA SHEETS FOR MECHANICAL
ITEMS ETC.
(Appendix-II to Particular Job Specification of Work)
332 of 896
DATA SHEETS FOR MECHANICAL ITEMS
CONTENTS
I. Valves - Deleted
II. LR Bends
333 of 896
DATA SHEET FOR LONG RADIUS BENDS
1) LR BEND MFR.
2) PURCHASER SPECIFICATION NO. MEC/TS/05/21/015 Rev 0
3) MANUFACTURING CODE MSS-SP-75/ ASME B16.49
4) DIMENSIONAL TESTING REQUIRED AS PER SPEC.
Charpy V-Notch Test required at temp. 0 0C for set of three transverse specimen.
Value shall be Minimum Avg. - 55J, Individual Minimum - 44J
DESTRUCTIVE TESTING
5) YS: 485 - 605 MPa, TS: 570 - 760 MPa
(TENSILE / CHARPY /HARDNESS)
YS/TS = 0.9 Maximum, Elongation - 20% Minimum
Hardness Value shall be 248 HV10 Maximum
6) NON-DESTRUCTUVE TESTING Required as per Mecon's Technical Specification no. MEC/TS/05/21/012B
7) PIGGING Required as per Note-3 below
196 Kg/cm2 (for 18" OD x 11.13 mm WT Pipe)
8) HYDROSTATIC TEST PRESSURE (For PQT Bend) 215 Kg/cm2 (for 12" OD x 8.6 mm WT Pipe)
Note: All the inspection & tests shall be performed as per Tech. Spec. & QAP attached with the tender.
TABLE-I
Sl. Details of free issue P/L material Bend End Type Qty. Angle Straight
No. NB Thk. Material Radius (Nos.) Length
mm (R) after
curvature (mm)
*
BE = "D" - denotes nominal dia. of pipe
@ = Bevel End
D = Vendor to indicate
= Straight length after curvature will be minimum 500mm.
Note:
1) Test Bend shall be of 90°
2) Quantity & angles of LR Bends shall be finalized during detailed engineering activities
3) A check shall be performed on each bend by passing gauging pig consisting of two discs of Aluminium/MS Plate having a diameter equal to 95% of the nominal internal
diameter of the pipe, connected rigidly together at a distance equal to 500mm. Details of the gauging pig, including its dimensions shall be approved by Purchaser.
4) Out of Roundness shall not exceed 2% of nominal OD
5) Tolerance in Bend Angle shall be ± 0.5° of the specified angle
6) Tolerance in Bend Radius shall be ±1% of the nominal bending radius.
7) Bend off-plane shall be maximum (θ/90) x 10 mm, where θ = Bend angle
334 of 896
13.0 QAPs FOR BOUGHT-OUT ITEMS
(Appendix-III to Particular Job Specification of Work)
335 of 896
QAP FOR MECHANICAL ITEMS
CONTENTS
A. QAPs
I. Assorted Pipes
II. LR Bends
B. ITPs
I. Assorted Pipes
II. CS Conduit
336 of 896
FORM NO. 11.20(4.4)F-09 REV-0
INSTRUCTIONS FOR FILLING UP : CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS :
1. QAP shall be submitted for each of the equipment separately with break up Code Description Code Description Code Description Code DOCUMENTS:
of assembly/sub-assembly & part/component or for group of equipment 1. Visual 20. Dust/ Water Ingress Test 36. Spark Test for Lining D1. Approved GA drawings
having same specification. 2. Dimensional 21. Friction Factor Test 37. Calibration D2. Information and other
2. Use numerical codes as indicated for extent of inspection & tests and 3. Fitment & Alignment 22. Adhesion Test 38. Safety Device Test reference drg/ stamped
submission of test certificates & documents. Additional codes & description 4. Physical Test (Sample) 23. Performance Test/Characteristic 39. Ease of Maintenance drgs released for mfg.
for extent of inspection & tests may be added as applicable for the plant 5. Chemical Test (Sample) Curve 40. Fire Test (Type Test) D3. Relevant catalogues
and equipment 6. Ultrasonic Test 24. No Load/ Free Running Test 41. Charpy V-Notch Test D4. Bill of matl./Item no./
3. Separate identification number with quantity for equipment shall be 7. Magnetic Particle Test (MPI) 25. Load/ Overload Test 42. Operational Torque Test Identification
indicated wherever equipment having same specifications belonging 8. Radiography Test 26. Measurement of Speeds 43. ENP (Electroless Nickel Plating) D5. Matchmarks details
to different facilities are grouped together. 9. Dye Penetration Test 27. Accoustical Test Execution D6. Line/ Layout diagram
4. Weight in kilograms must be indicated under Column-5 for each item. 10. Metallographic Exam. 28. Geometrical Accuracy 44. Painting D7. Approved erection
Estimated weights may be indicated wherever actual weights are not 11. Welder’s Qualification & 29. Repeatability and Positioning 45. Anti-Static Test procedures
available. Weld Procedure Test Accuracy 46. Hydrostatic Double Block & D8. Unpriced sub P.O. with
12. Approval of Test and 30. Proving Test Bleed Test specification and amend-
Repair Procedure 31. Surface Preparation 47. Bend Angle ments, if any
ABBREVIATIONS USED : KEY TO SYMBOLS : 13. Heat Treatment 32. Manufacturer's Test Certificates 48. Pneumatic Double Block & D9. Calibration Certificate of
MFR : MANUFACTURER * : THIRD PARTY INSPECTION AGENCY APPOINTED BY VENDOR 14. Pressure Test for bought-out items Bleed Test all measuring instruments
H : HOLD # : TEST TO BE PERFORMED, AS APPLICABLE {UT(6*) - HFW/ERW, 15. Leakage Test 33. IBR/ Other Statutory agencies 49. Proof Test (Type Test) and gauges
R : REVIEW RT(8*) - LSAW} 16. Balancing compliance certificate 50. Dielectric Test D10. X-Ray Reports
W : WITNESS ** : Sample shall be drawn from intrados, extrados & transition zone of Bend 17. Vibration Test 34. Internal Inspection Report 51. Bending parameter
RW : RANDOM WITNESS ## : Test ring shall be removed from the centre of the Bend & Transiti 18. Amplitude Test by Contractor 52. All Weld Rensile Test
P : PERFORM Zone and test sample shall be drawn from each quadrant during MPQT 19. Sponge Test 35. Hardness Test 53. Guided Bend Test of weld
(Hardness Test for each bend shall be carried out at extrados
& intrados of each bend with the help pf portable hardness tester)
EQUIPMENT DETAILS INSPECTION AND TESTS Test Certificates & Acceptance Criteria REMARKS/
Sl. Description (with equipment Identification Quantity Unit Manufacturer's Expected Manufacturing Procedure Qualification Test Final Inspection/ Test by Documents to be Standards/ IS/ BS/ SAMPLING PLAN
No. heading, place of use and brief No. No./M Weight Name and Address Schedule of (MPQT) submitted to MECON ASME/ Norms and
CLIENT/
MFR TPIA* CLIENT/MECON MFR TPIA*
specifications) (MR Item No.) (Kg) Final Inspn. MECON Documents
P W W P W RW
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1.0 LR BEND As per 1, 2, 4**, 5, 1, 2, 4**, 5, 1, 2, 4**, 5, 1, 2, 6#, 1, 2, 6#, 1, 2, 6#, 1, 2, 4, 5, 6#, 7, D1, D2, MECON's 100%
MR/SOR 6#, 7, 8#, 10, 6#, 7, 8#, 10, 6#, 7, 8#, 10, 7, 8#, 35, 7, 8#, 35, 7, 8#, 35, 8#, 15, 35, 41, 47, Tech. Spec., Data (As per Technical
15, 35##, 41, 15, 35##, 41, 15, 35##, 41, 51 51 51 51, 52, 53, D9, D10 Sheets & Relevant Specification & Data
47, 51, 52, 53 47, 51, 52, 53 47, 51, 52, 53 Standards Sheets of LR Bends)
Special considerations for Bending Parameters during production with respect to MPQT: Notes: 1. Physical , Chemical, Impact & Hardness Test results shall conform to the requirements of Mecon's Technical Specification for Line Pipe.
1) Forming Temperature shall not vary more than ±25°C. 2. Manufacturer shall submit marking scheme along with the QAP for approval.
2) Forming velocity shall not vary more than ±2.5 mm/minute 3. Bending parameters established during MPQT shall be maintained for regular production of LR Bends.
3) Temperature of cooling water shall not vary more than ±15°C. 4. Visual, Dimensional and other parameters shall be complaint to Technical Specification & Data Sheets, MR & Notes to MR of LR Bends.
4) Flow rate of cooling water shall not vary more than ±10%. 5. Any indication observed on MPI shall be verified by MUT.
5) Induction Heating frequency shall vary more than ±20%. 6. Mettalographic Examination shall be performed in line with the requirements of mother Line Pipe.
7. Bends shall be dispatched with both ends provided with metallic bevel protectors.
Any change in above parameters shall be cause for rejection of that Bend and the cost towards the pipe used 8. If results of MPQT does not meet the requirements, vendor shall provide justification and remedial measures and reperform MPQT.
for fabrication of that rejected Bend shall be recovered from vendor's account with a rate specified elsewhere Repeated failure of MPQT shall be taken up by the purchaser to initiate suitable action. Cost towards using of additional pipe length for reperforming MPQT
in the Tender Document. shall be recovered from vendor's account with a rate specified elsewhere in the Tender Document.
9. The Bend number shall be placed by cold rolling or low stress dot marking on the outside surface of the Bend at an
approximate distance of 50 mmfrom both ends.
10. Bend ends shall be tested by MUT for any lamination at the ends.
337 of 896
INSPECTION AND TEST PLAN
FOR
STANDARD SPECIFICATION NO.
ASSORTED PIPES MEC/TS/05/62/59A
Page 1 of 3
FOR
ASSORTED PIPES
Rev.
Date Purpose Prepared Checked by Approved by
No.
338 of 896
INSPECTION AND TEST PLAN
FOR
STANDARD SPECIFICATION NO.
ASSORTED PIPES MEC/TS/05/62/59A
Page 2 of 3
SCOPE OF INSPECTION
Relevant Code
As per code & Mill test
(i)Chemical One sample &
Testing Technical Certificate/ H R R
Composition: CE per heat Technical
Specification report
Raw material Plate/Sheet/ Specification
1.0
inspection Strip
Relevant Code
(ii)Mechanical As per code &
One sample & Inspection
properties Testing Technical H R R
per heat Technical report
YS,UTS,EL Specification
Specification
Welding Speed, Relevant Code
Manufacturing,
Current, Voltage, Record of 100% by & Internal
2.0 welding Pipe Approved WPS P R R
Frequency, Offset, Parameter Vendor Technical report
(HFW & SAW)
Height of Flash & Trim Specification
Tensile, Flattening,
Reverse Bend, Relevant Code
Mechanical Properties As per code &
Hardness, Impact One sample & Lab
3.1 Destructive Testing Pipe & Macro Technical W W W
per heat Technical Report
Specification
Chemical Specification
Chemical Properties
Composition
Inspection
UT/RT or as per Relevant Code As per code &
Non Destructive Surface & Internal 100% by Report/
3.2 Pipe code & & Technical Technical W R R
Testing Inspection Vendor Internal
specification Specification Specification
Record
ITP No. : 05/21/012E/001
339 of 896
INSPECTION AND TEST PLAN
FOR
STANDARD SPECIFICATION NO.
ASSORTED PIPES MEC/TS/05/62/59A
Page 3 of 3
SCOPE OF INSPECTION
METHOD OF QUANTUM REFERENCE ACCEPTANCE
SL.NO. STAGE COMPONENT CHARACTERISTICS RECORD
CHECK OF CHECK DOCUMENTS NORMS
Manufacturer TPIA Client/Mecon
Stress Relieving,
Relevant Code & Relevant Code &
Heat Treatment Normalizing, Temperature
3.3 Pipe Each Pipe Technical Technical HT Chart P R R
(As Applicable) Tempering, Solution Recording
Specification Specification
Annealing etc.
Inspection
Relevant Code & As per code &
Report,
4.0 Hydrostatic test Pipe No leak Visual Each Pipe Technical Technical W W RW
Hydraulic
Specification Specification
Graph
Straightness, Outer
Diameter (Pipe Body,
Pipe Ends), Out of Relevant Code & As per code &
Visual, 100% by Inspection
5.0 Final inspection Pipe Roundness, Thickness, Technical Technical W W RW
dimensional vendor Report
Length, Surface Specification Specification
Lamination, Root Face,
Bevel Angle
Legends/Notes:
340 of 896
INSPECTION AND TEST PLAN
FOR
STANDARD SPECIFICATION NO.
CONDUIT PIPES MEC/TS/05/62/59A
Page 1 of 3
FOR
CONDUIT PIPES
Rev.
Date Purpose Prepared Checked by Approved by
No.
341 of 896
INSPECTION AND TEST PLAN
FOR
STANDARD SPECIFICATION NO.
CONDUIT PIPES MEC/TS/05/62/59A
Page 2 of 3
SCOPE OF INSPECTION
Relevant Code
As per code & Mill test
(i)Chemical One sample &
Testing Technical Certificate/ H R R
Composition: CE per heat Technical
Specification report
Raw material Plate/Sheet/ Specification
1.0
inspection Strip
Relevant Code
(ii)Mechanical As per code &
One sample & Inspection
properties Testing Technical H R R
per heat Technical report
YS,UTS,EL Specification
Specification
Welding Speed, Relevant Code
Manufacturing,
Current, Voltage, Record of 100% by & Internal
2.0 welding Pipe Approved WPS P R R
Frequency, Offset, Parameter Vendor Technical report
(HFW & SAW)
Height of Flash & Trim Specification
Tensile, Flattening,
Reverse Bend, Relevant Code
Mechanical Properties As per code &
Hardness, Impact One sample & Lab
3.1 Destructive Testing Pipe & Macro Technical W W R
per heat Technical Report
Specification
Chemical Specification
Chemical Properties
Composition
Inspection
UT/RT or as per Relevant Code As per code &
Non Destructive Surface & Internal 100% by Report/
3.2 Pipe code & & Technical Technical W R R
Testing Inspection Vendor Internal
specification Specification Specification
Record
342 of 896
INSPECTION AND TEST PLAN
FOR
STANDARD SPECIFICATION NO.
CONDUIT PIPES MEC/TS/05/62/59A
Page 3 of 3
SCOPE OF INSPECTION
METHOD OF QUANTUM REFERENCE ACCEPTANCE
SL.NO. STAGE COMPONENT CHARACTERISTICS RECORD
CHECK OF CHECK DOCUMENTS NORMS
Manufacturer TPIA Client/Mecon
Stress Relieving,
Relevant Code & Relevant Code &
Heat Treatment Normalizing, Temperature
3.3 Pipe Each Pipe Technical Technical HT Chart P R R
(As Applicable) Tempering, Solution Recording
Specification Specification
Annealing etc.
Inspection
Relevant Code & As per code &
Report,
4.0 Hydrostatic test Pipe No leak Visual Each Pipe Technical Technical W RW R
Hydraulic
Specification Specification
Graph
Straightness, Outer
Diameter (Pipe Body,
Pipe Ends), Out of Relevant Code & As per code &
Visual, 100% by Inspection
5.0 Final inspection Pipe Roundness, Thickness, Technical Technical W RW R
dimensional vendor Report
Length, Surface Specification Specification
Lamination, Root Face,
Bevel Angle
Legends/Notes:
343 of 896
14.0 SCHEMATIC ROUTE DIAGRAM
(Appendix-IV to Particular Job Specification of Work)
344 of 896
345 of 896
15.0 VIDEOGRAPHY SURVEY
(Appendix-V to Particular Job Specification of Work)
346 of 896
APPENDIX V – VIDEOGRAPHY SURVEY
1.0 INTRODUCTION
The purpose of video survey is to capture before starting construction activities the
ground realities along the pipeline route and to co-relate the same with digitized maps of
Survey of India. Moreover, during construction activities the Contractor shall video report
at least once a week all site activities.
Contractor or the approved agency (by Owner / Engineer) shall carry out the videography
along the route of the pipeline.
347 of 896
Phase1: Videography of the entire pipeline route prior to any construction
activities
A) The contractor shall capture the video for the following areas but not limited to:
1. Pipeline route
2. Location of various Stations and Tap Off points.
3. Major features such as water bodies, plantation, flora & fauna, forest & rocky area
4. All Crossings like road, railways, river, canal, khadi as applicable
5. The photographs of the crossing both upstream and downstream of the pipeline. The
photographs and video should cover the type of soil and terrain condition, obstacles,
rocks etc.
B) The identified locations on digitised map of Survey of India shall be interfaced with
Videography through software whereby one can access both simultaneously and match
the two. The identified locations like
Crossings: National Highways, State Highways, Rivers, Major Canals, Hills, Major Khadi
Areas: Rocky, Marshy, Forest, Plantation.
The digitised map shall be procured from Survey of India by the Contractor. Digital the
odolite shall be used for all surveys. However, GAIL will provide all possible help in
collection of required map, and Authorisation letter required, if any to contractor.
During construction, the Contractor shall video survey all distinct / main activities under
progress alongside the entire pipeline routing.
The purpose of this survey is to get a complete videography of the construction site at
different stages of the construction.
This includes all main activities as per phased working procedure. Each phase of the
construction shall be at least surveyed at 5 different locations distributed equally along
the pipeline routing.
Each Natural Gas station will be also surveyed on the same way. Contractor shall submit
his planning and his methodology to Owner /Engineer approval right after the LOA.
3.1 The proper log of the location, landmark, crossings, town, districts and important
comments will be embedded.
348 of 896
3.2 The search will be text based and it will retrieve the relevant video segment along with
textual / visual data for reference.
3.3 A special programme will be written which will help create interface through which the
video of important landmarks can be searched /viewed.
3.4 Narration in back side of video will be provided along the route.
4.0 ASSISTANCE
The Contractor to indicate in detail the information and assistance as required from client
to execute the survey.
Contractor to quote for each phase its lump sum fee on per Km of route survey basis.
The fees shall include all expenses and cost of facilities used to carry out the scope
covered in clauses above. Contractor to quote separate item as stated in Schedule of
Rates (SOR).Price will be indicated under Schedule of Rate (SOR).
349 of 896
16.0 THIRD PARTY INSPECTION AGENCY
(Appendix-VI to Particular Job Specification of Work)
APPENDIX - VI
350 of 896
THIRD PARTY INSPECTION AGENCY
Contractor shall appoint anyone of the following TPIA for inspection purpose, wherever required
as per tender document. Contractor has to propose minimum 4 nos. of below listed agencies to
be approved by GAIL / MECON:
Apart from inspection by TPIA, inspection may also be performed by MECON / GAIL’s personnel.
351 of 896
17.0 SUPPLY AND INSTALLATION OF
PORTA CABINS
352 of 896
APPENDIX- VII TO PARTICULAR JOB
SPECIFICATION
SCOPE OF WORK FOR SUPPLY & INSTALLATION
OF PORTA CABINS
353 of 896
ARCHITECTURAL WORKS
SCOPE OF WORK
M/s GAIL has awarded M/s MECON Limited project management consultancy (PMC) services
for Angul-Srikakulam pipeline. The brief scope of work for Part- B, broadly consist of Laying,
Testing and Commissioning of 18”NB x 48 Kms (approx) and 12”NB x 274 Kms (approx)
pipeline in the state of Odisha & Andhra Pradesh including all associated works for
transportation of Natural Gas (dry)/ R-LNG.
M/s MECON Ltd has been engaged by M/s GAIL to carry out design, engineering, procurement,
inspection & Project Management Consultancy Services required transportation and distribution
of Natural Gas.
The scope of work includes the design, fabrication, supply, loading, transportation
including unloading and installation at site Porta Cabins of following clear inside
dimensions and technical specifications as detailed below:
1. PCP cum Guard Room – 10.0 m (L) x 3.0 m (W) x 2.5 m (H) consists of
equipment room, battery room, guard room including toilet block & overhead
tank.
2. Guard room - 4.0 m (L) x 3.0 m (W) x 2.5 m (H) consists of guard room
including toilet block & overhead tank.
The porta cabins shall be as per Technical Specification and drawings, including
provisions of installation of air conditioning, mounted electrical work and required
furniture. The Porta Cabin shall have supporting structures for installation of solar
panels at SV stations only. Foundation base shall be constructed up to a height of
300mm (as mentioned in drawings) from finished ground level for installation of Porta
Cabin as per civil details.
No leakages, seepages through walls, roof shall be permitted. All joints between wall
panels, roof level shall be properly sealed by the successful bidder after erection of
walls to avoid ingress of water/insects/reptiles etc. PCC protection shall be provided
at base of Porta Cabin all around.
TECHNICAL SPECIFICATION
1.0 FLOOR
354 of 896
The floor shall be covered with cement fiber board of 18-20 mm thickness fixed with
fasteners and finished neatly with:
• 600 mm X 600 mm vitrified tiles in Equipment Room and Guard Room. Vitrified
floor tile shall be 1st quality of approved make, size 600 X 600 X 9 mm (min.)
with water absorption less than 0.08% and conforming to IS:15622 of approved
quality, shade, range and pattern, fixed using chemical tile adhesive & epoxy and
joints pointed with tile jointing compound of approved make.
• 300 mm X 300 mm acid resistant tiles in Battery Room. Acid and/or alkali
resistant tiles shall be of approved make and colour, size 300 X 300 X 12 mm
conforming to IS:4457 fixed using chemical tile adhesive.
• 300 mm X 300 mm anti skid ceramic floor tiles in Toilet. Ceramic floor tiles shall
be anti-skid matt finish (300 X 300 X 7.7 mm minimum) conforming to IS:13754
and of approved quality, shade, range and pattern, fixed using chemical tile
adhesive & epoxy and joints pointed with tile jointing compound of approved
make.
2.0 WALLS
Wall frame, outer finish and insulation shall be as per structural TS.
Inner walls sections shall be bended sections made from 1.6 mm Corrugated GI
sheets. Inner wall paneling shall be done with 9 mm thick HMR grade pre-laminated
MDF (medium density fibre boards) confirming to IS: 14587 of approved make and
shade.
All partition walls shall have 9 mm thick HMR grade pre-laminated MDF boards duly
supported by structural steel members.
In Battery Room the internal walls shall have cement fiber board, on which acid /
alkali resistant tiles shall be fixed using chemical tile adhesive.
Internal walls in Toilet shall be finished with 4mm moisture resistant bakelite sheet
paneling.
All vertical & horizontal corners in all rooms shall be neatly finished with Anodized
Aluminum Angles / PVC beadings.
3.0 ROOF
Roof frame, outer finish and insulation shall be as per structural TS.
355 of 896
Roof shall be extended by minimum 300mm on all sides to provide rain/ sun
protection to doors and windows. Gutters shall be provided at eaves and connected
with uPVC rain water downtake pipes which shall be connected to nearest drain. Rain
water pipes shall be of 110 mm diameter conforming to IS: 13592 Type A fixed on
wall and jointing with seal ring.
MS catladder shall be provided for roof approach for Cleaning & Maintenance of
Solar panel.
Internal ceiling shall be provided with internal paneling 9mm HMR grade pre-
laminated MDF boards confirming to IS: 14587 of approved make and shade
supported by MS framework.
• Doors: All doors shall be of aluminum extruded sections (Powder Coated) with
partly glazed portion (from lock rail level to top rail; with 8 mm toughened glass)
356 of 896
and partly with 10mm thick cement bonded prelaminated particle board panel/
aluminium louvers and wire mesh (from bottom rail to lock rail level). Toilet door
shall be fully paneled with cement bonded laminated particle board.
The doors shall be complete with necessary fittings and fixtures like mortice lock,
handles, tower bolt, floor mounted double action floor spring hinges etc. The
peripheral edges of the door shall be provided with rubber seal to prevent ingress
of water and dust. The doors shall be provided with manually operating type
locking arrangements from both internal and external side. All aluminium doors
shall be complete with all bye works including fittings and fixtures like handles,
door springs, door closers, locking arrangements, etc.
Double shutter door size shall be 1500 mm X 2100 mm and single shutter door size
shall be 1000 mm X 2100 mm and 900 mm X 2100 mm as shown in drawing.
• Aluminium Sections
Sliding window
2 track Frame Top 20829 61.85 x 31.75 x 1.5 0.784
and Side
2 track Frame 20830 61.85 x 31.75 x 1.5 0.909
Bottom
Shutter Top and 20736 40 x 18 x 1.55 0.547
Bottom
Shutter Side 20738 40 x 18 x 1.55 0.547
Shutter Interlock 20737 40 x 18 x 1.45 0.607
357 of 896
SUNSHADES/ CHAJJAS
Suitable sunshades made out of CGI/PGI sheets and angle iron frame shall be
provided to all external windows, ventilators and doors. The min projection for the
sunshades shall 600mm / 450mm (as mentioned in drawings) from the wall and 300m
wider than the opening as marked in the drawing supported over angle iron fame work
and fixed on wall using nut/bolts.
5.0 TOILET
Toilet shall be provided along with Guard Room. The toilet cubicle shall be having 1
No of western closet with flushing units, 1 No of wash Basin, 1 No of Urinal, mirror,
all faucets, liquid soap dispenser as shown in drawing & necessary water piping and
floor traps for outlet.
White glazed vitreous china sanitary fittings will be provided in toilet of approved
model and make. Standard chromium plated brass plumbing fittings and fixtures from
approved manufacturer will be provided. 18 mm thick granite stone slab of approved
shade, table rubbed, edges rounded and polished of size 75x50 cm deep and 1.8 cm
thick shall be fixed for urinal partitions.
All appliances, fixtures and fittings shall be provided with all such accessories as are required
to complete the item in working condition. Accessories shall include proper fixing
arrangements, brackets, nuts, bolts, washers, screws and required connection pieces.
For sewerage system, connection to soak pit and septic tank shall be made (construction of
soak pit and septic tank shall not be in the scope of bidder).
Plumbing fittings:
358 of 896
Pillar Cock CON-CHR-021KN of Jaquar or equivalent.
Angle Stop Cock CON-CHR-059KN of Jaquar or equivalent.
Liquid Soap Dispenser ACN-CHR-1135N of Jaquar or equivalent.
Coat Hook ACN-CHR-1161N of Jaquar or equivalent.
Mirror 5.5 mm thick float glass frameless mirror of size 600 mm
X 900 mm fixed with stainless steel studs
Wash basin drain pipe PVC
Floor Trap SS
Eye Wash in Battery Room S99 of Tobit Engineers or equivalent.
6.0 FURNITURE
GUARD ROOM
359 of 896
Vertical Filing Cabinet (4-drawer)
• Size of 4 Drawer VFC shall be 1320mm(H) X 470mm(W) X 620mm(D) approx.
• It should have 1 Point Locking Mechanism and a Rigid Knock Down CRCA
Construction.
• Easy to grip Full length Recess Handle shall be integrated into Metal Drawer for
easy pull out convenience.
• There shall be a Snap on type plastic label holder on Drawer Fronts.
• The Centralized locking System shall be provided along with Shooting Bolt
Mechanism and 10 Lever Cam Lock.
• The VFC should have anti-tipping arrangement which ensures that when one
drawer is opened for use, it does not allow other drawers to be opened.
• The High Quality Precision Ball Slide shall be provided with Drawer Load
capacity of max 40 kg and UDL for 75,000 cycles (BS).
• Plain Triangular plate pop should be riveted at the bottom corners for rigidity.
• Model No. VFC-4 drawer of Godrej or equivalent make.
360 of 896
LIST OF APPROVED MANUFACTURERS / MAKES
The makes and manufactures shall be preferably from the following list. In case some of the items
not available in the market or some of the particular products are not producing by the following
manufacturer or in case of change in trade name etc. equivalent makes or re-designated product shall
be used conforming to the specific IS codes with the prior approval of Client/Consultant.
361 of 896
FABRICATION AND
FIXING OF WINDOWS
20 CERAMIC TILES KAJARIA/ HR JOHNSON/ ASIAN
GRANITO/ ORIENT BELL/ SOMANY
21 VITRIFIED TILES KAJARIA/ HR JOHNSON/ ASIAN
GRANITO/ ORIENT BELL/ SOMANY
22 ACID RESISTANT TILES HR JOHNSON ENDURA/
KAJARIA/UNITILE
23 TILE ADHESIVE BASF / SIKA / CICO / BELL / PIDILITE /
LATICRETE
24 STONE ADHESIVE FERROUS CRETE (FERRO-113)/ARDEX
ENDURA (DIANMOND STAR)/PIDILITE
(ROFF STONE ADHESIVE)
25 EPOXY GROUTING MYK LATIKRATE / DUBOND /
SEMITRONE
26 POLYSULPHIDE SEALANT BASF / PIDILITE/ FOSROC/ CHOKSEY/
CICO /SIKA
27 FURNITURE FEATHERLITE/GODREJ/ HNI-INDIA/
DURIAN
28 EYE WASH TOBIT ENGINEERS / EURONICS / HAWS
29 GLASS : MIRROR MODIGUARD / SAINT GOBAIN/ ASAHI
INDIA SAFETY / MODI FLOAT
30 SANITARYWARE JAQUAR / HINDWARE / CERA / ORIENT
BELL
31 C.P. FITTINGS & ACCESSORIES JAQUAR / HINDWARE / CERA / ORIENT
BELL
32 TOILET ACCESSORIES JAQUAR / HINDWARE / CERA / ORIENT
BELL
33 STAINLESS STEEL CP GRATING CHILLY / CAMRY / GMGR / SFMC
34 G.I. PIPES /M.S. PIPES IS 1239/3589 TATA STEEL / SAIL
35 G.I. FITTINGS (MALLEABLE CAST ZOLOTO-M / SWASTIK / JINDAL HISSAR
IRON) / UNIK
36 SOIL, WASTE WATER PIPES & NICO / SFMC PVC UPVC PIPE / KAGECO
FITTINGS- / FINOLEX
37 SOIL, WASTE & RAIN WATER SUPREME / SFMC / FLOW GUARD /
PIPES & FITTINGS –UPVC. FINOLEX
38 PVC WATER TANK SINTEX / SUPREME / FINOLEX
362 of 896
TECHNICAL SPECIFICATION FOR PORTA CABINS
c. Design of all structural members (columns, rafters, Floor and Roof Beams column
bracing system, base plate, anchor bolts, and any other components shall be provided in
excel sheet (editable form including formulas with ref. to relevant codal clauses) as per
relevant IS Codes.
d. Preparation and submission of 3 nos. (Three) hard & soft copies (editable excel form
including formulas with ref. to relevant codal clauses) of Design calculations &
drawings for approval of the Consultant.
e. Preparation and submission of design calculations for typical connection details etc. for
approval of the Consultant.
363 of 896
1.02 LOADING AND CODES:
a. All dead loads shall be considered in accordance with IS: 875 (Part-1)
-1987.
b All live loads shall be considered in accordance with IS: 875 (Part-2)-1987.
c. Wind loads shall be in accordance with IS: 875(Part-3) and any other
Consideration specific to the site.
d. Seismic loads shall be in accordance with IS: 1893 – 2002.
e. Electrical loads shall be as per Electrical Lighting Fixture drawing.
f. False Ceiling load as per architectural specification.
In absence of any other provision for design loads, any other recognized code of practice may
be followed with prior approval of the consultant.
1.05 MATERIAL:
The structure of prefabricated porta Cabin (i.e. Base frame, Top frame, Side
frame etc.) shall be tubular/Hot Rolled structural steel sections conforming to
IS:4923 & IS: 2062-2011.
Exterior Cladding on Wall shall be 1.2 mm thick and Roof 1.2 mm GI Sheets of
120 to 150 GSM duly corrugated of standard size confirming to IS/ASTM
Standard. This corrugation version acts as stiffeners and increase strength to
weight ratio. cladding sheet shall be welded to the external superstructure. All gaps
are sealed to avoid any water leakage, ingress of insects and moisture.
Insulation for Roof & Wall cladding shall be 80mm thick Bonded Mineral wool
(ROCKWOOL)of density 96-100 kg/m3 conforming to IS: 8183 -1993. Under side
of insulation shall be covered reinforced aluminum foil.
Gutter on roof shall be 0.5 thick CGI sheet and down take shall be heavy duty
uPVC pipe with all accessories.
b. Finishing paint: Two (2) coats of Acrylic Polyurethane (DFT 40µ) each coat
364 of 896
c. Skid Structures /Base Frame(Under Side) :Above a,b including Two
coats of wear resistant bituminous paint (DFT 75 μ /coat).
All painting shall be done by spray painting only. Paint damaged during transportation
and handling shall be repaired in good condition. Final colour of paint shall be approved
by client/Consultant
Galvanized Iron
3 TATA, JINDAL, ESSAR
(GI) Sheet
Insulation (Rock Lloyd Insulation, Minwool Rock Fibres Ltd, Insulation, Dhanbad
4
wool) rock wool Insulation pvt Ltd., Rock wood India Limited
5 Paint Akzo-Nobel, Asian Paint, Kansai Nerolac Paints, Berger Paints
365 of 896
GAIL (INDIA) LIMITED
SRIKAKULAM - ANGUL PIPELINE PROJECT
(ELECTRICAL SECTION)
MEC/23V9/05/E9/E/001 0 30.07.2021
366 of 896
ELECTRICAL WORKS FOR PORTA
MECON LIMITED CABIN AT PCP STATIONS
Electrical Section, Delhi
DELHI
Contents
Sl. No. Description
1.0 GENERAL
2.0 SCOPE
367 of 896
ELECTRICAL WORKS FOR PORTA
MECON LIMITED CABIN AT PCP STATIONS
Electrical Section, Delhi
DELHI
1.0 GENERAL
1.1 Introduction
The intent of this specification is to define the requirements for the supply of equipment and
materials (as required), erection, testing and commissioning of Porta cabin at PCP station
locations along the SAPL pipeline.
The work shall be carried out in the best workmanship – like manner, in conformity with these
specifications, approved drawings and the instructions of the Engineer-in-charge from time
to time.
1.2 Standards
The work shall be performed in conformity with, standard specifications and installation
standards enclosed and code of practices of the Bureau of India Standards. In case of any
conflict, the stipulations under this specification shall govern.
In addition, the work shall also conform to the requirements of the following:
The Indian Electricity Act, and the rules framed there under
The fire Insurance Regulations
The regulations laid down by the Chief Electrical Inspector of the state government / Central
Electricity Authority (CEA).
The regulations laid down by the Factory Inspector.
The regulations laid down by the Chief Inspector of Explosives.
Any other regulations laid down by the Central, State or Local Authorities from time to time
during the pendency of this contract.
M.B.Lal Committee recommendations for electrical design & installation.
1.3 Guarantee
The above guarantee shall be applicable for the quality of work executed as well as for the
equipment / cable / fittings/ other material supplied by the contractor.
The equipment offered and the installation shall be suitable for continuous operation under the
following site conditions.
2.0 SCOPE
The scope of work includes the design, fabrication, supply, loading, transportation including
unloading and installation at site Porta Cabins of following clear inside dimensions and
technical specifications as detailed below:
1. Guard room – 4.0 m (L) x 3.0 m (W) x 2.5 m (H) consists of Guard Room & Toilet
2. PCP & Guard room – 10.0 m (L) x 3.0 m (W) x 2.5 m (H) consists of PCP room, Guard
Room & Toilet
The porta cabins shall be as per Technical Specification and drawings, including provisions of
installation of air conditioning, mounted electrical work and required furniture. Foundation base
shall be constructed up to a height of 300mm (as mentioned in drawings) from finished ground
level for installation of Porta Cabin as per civil details. No leakages, seepages through walls,
roof shall be permitted. All joints between wall panels, roof level shall be properly sealed by the
vendor after erection to avoid ingress of water/insects/reptiles etc. PCC protection shall be
provided at base of Porta Cabin all around. Pre-fabricated porta cabins comprising of MS
structure, walls, roof, insulation, doors/ windows, chajja / canopy, flooring, ceiling, electrical
installations, furniture, plumbing works are part of scope of work.
a) Power shall be distributed from the main LDB (MLDB) located in the equipment/electrical
room. (This MLDB shall be supplied by the Main line contractor)
b) One additional wall mounted LDB shall be provided in the cabin to distribute the power to
Electrical room, Battery room, Guard room and Toilet. LDB shall consist of 32 RCCB (100mA
369 of 896
ELECTRICAL WORKS FOR PORTA
MECON LIMITED CABIN AT PCP STATIONS
Electrical Section, Delhi
DELHI
sensitive) and 10A DP MCB (4 nos.) and 16 A DB MCB (2 nos.). This LDB shall be prewired
and factory fitted in the Porta cabin.
c) LDB shall be pre installed in the Cabin (Make_ Havells or equivalent) and provision shall be
provided to terminate the cable from MLDB to the LDB through junction box, PVC conduit
shall be provided from LDB to junction box.
d) Cabin shall be supplied prewired from electrical points as per the drawings consist of wiring
from LDB to switch board, switch board to the electrical points and LDB to the Junction box.
Owner will provide only power connection (3 Phase+N) to the Junction Box/LDB.
e) Electrical Junction box with terminals (4+1 Power terminals rail mounted) shall be provided
near to the trench location to terminate the Cable from the Owner’s end (Cable size 4Cx 2.5
Sqmm)
f) Wiring Specification_ 1.5 Sqmm FRLS PVC Multi-stranded flexible wire in PVC conduits for
point wiring and 2.5 Sqmm from LDB to the SSB and SSB to the Power points.
h) PVC Conduits_ Recess mounted in the cabin wall & roof as per the location of electrical point
and switch sockets and junction boxes.
Electrical point wiring and conduits shall be done at the factory works with 1.5/ 2.5 Sqmm Cu wire
(FRLS-PVC Insulation) and PVC conduits shall be recess mounted with 1.0 Sqmm earth wire to all
the electrical points. (Refer electrical points details in the drawing)
f) Electrical Luminaries - 1x20W of LED EPFL 120 of M/s Baliga Make (Flame proof type) or
M/s Sudhir make or equivalent.
g) Exhaust Fan – 12” Flame proof type, 1 nos (MS) of M/s Baliga Make (Flame proof type) or
M/s Sudhir make or equivalent.
h) Switch Board_ Electrical points of Battery room shall be powered by Equipment room. (2 nos.
6A switch shall be provided in the switch board of equipment room)
Electrical point wiring and conduits shall be done at the factory works with 2.5 Sqmm Cu wire (FRLS-
PVC Insulation) and PVC conduits shall be recess mounted with 1.0 Sqmm earth wire to all the
electrical points and shall be terminated in switch board in equipment room. (Refer electrical points
details in the drawing)
Electrical point wiring and conduits shall be done at the factory works with 1.5/ 2.5 Sqmm Cu wire
(FRLS-PVC Insulation) and PVC conduits shall be recess mounted with 1.0 Sqmm earth wire to all
the electrical points and shall be terminated in switch board in Guard room. (Refer electrical points
details in the drawing)
Electrical point wiring and conduits shall be done at the factory works / pre-wired with 1.5/2.5 Sqmm
Cu wire (FRLS-PVC Insulation) and PVC conduits shall be recess mounted with 1.0 Sqmm earth
wire to all the electrical points and shall be terminated in Junction Box in Guard room. (Refer
electrical points details in the drawing)
3.6 TOILET
Electrical point wiring and conduits shall be done at the factory works with 1.5/2.5 Sqmm Cu wire
(FRLS-PVC Insulation) and PVC conduits shall be recess mounted with 1.0 Sqmm earth wire to all
the electrical points and shall be terminated in Switch board in Toilet. (Refer electrical points details
in the drawing)
Note_ Prices of all internal wiring including conduits, Switch sockets, Switch boards, Fixtures
and luminaries, Fans are included in the price quoted for the finished cabin by the Porta
Cabin Manufacturer.
Equipment room-
a) Supply, Installation, testing and commissioning of MLDB (I-LDB of existing SOR) in the
equipment room.
b) In the equipment room electrical trench of 800 mm width and 400mm depth shall be provided
to mount the electrical panels in the room as details provided in the civil drawings with one
371 of 896
ELECTRICAL WORKS FOR PORTA
MECON LIMITED CABIN AT PCP STATIONS
Electrical Section, Delhi
DELHI
300mm ladded type cable tray. MS angle, MS edge cover to trench and insert palate shall be
provided in the equipment room. (Refer attached drawing)
c) Cable entries to the equipment room shall be provided with cable pit (1000x1000mm)
adjacent to the building and all entries to be sealed properly with foam sealing to avoid the
insect and rodent movement in the trench. (Refer attached drawing)
d) 01 nos of GI conduits (150 mm) shall be laid from the trench of equipment room to the battery
room for Battery cable. (Refer attached drawing)
a) Earth Pit- 02 nos with each Cabin, Maintenance free, 3.0 mtr long earth electrode.
b) Lighting rod- 01 nos with each cabin and 01 no of earth pit, 1.0 mtr long on the corner of the
cabin (diagonal) with provision to connect 25x3 mm GI Strip and its termination to the earth
pit.
c) Supply, fixing, laying and termination of GI earth strip of 25x3mm in cable trench.
d) Supply, fixing, laying and termination of 300 mm ladder type Galvanised (min. 80 micron)
cable tray in cable trench.
a) 3.5Cx 35 Sqmm cable as per SOR from SFU to Electrical Power distribution panel in
Equipment room in Buried Cable trench.
b) 4Cx 2.5 Sqmm cable as per SOR from Electrical Power distribution panel to Junction box in
Porta Cabin Equipment room and from Electrical Power distribution panel to independent
Guard room.
c) Wall/Recess/Structure mounted Main Switch Fuse unit Box TPN, 63 Amp, 415 V to receive
power from Electricity board of M/s HPL/Havells/ANCHOR Make or equivalent with cable
gland to terminate 3.5Cx35 Sqmm Cable.
a) Preparation of buried cable trenches, including, back filling, compacting providing of brick
protection by second-class bricks, spreading of fine river sand, including all supplies.
b) The job includes repairing of all civil works damaged during installation of electrical facilities.
c) The scope of work under this contract shall be inclusive of breaking of walls, floors and
chipping of concrete foundations necessary for the installation of equipment, materials, and
making good of the same.
d) Minor modifications wherever required to be done in the owner free supplied equipments /
devices to enable cable entry, termination, etc.
e) Sealing of opening made in the walls / floors for cables trays, cables, bus ducts, etc using
acceptable practice and standards.
f) Supply and installation of all other accessories not specifically mentioned herein, but never
the less necessary for completion of the job.
372 of 896
ELECTRICAL WORKS FOR PORTA
MECON LIMITED CABIN AT PCP STATIONS
Electrical Section, Delhi
DELHI
All equipments / materials supplied by the contractor shall be as per the list of approved makes
enclosed with this document subject to submission of Certification and approvals.
4.1 The equipments / materials to be supplied by the contractor shall conform to the requirements
of the applicable specifications. Also the installation of various material / equipment shall
conform to the installation standards /norms.
4.2 The drawings accompanying the tender documents when read with specification shall depict
the electrical system of the Terminal. These are indicative of the nature of work and issued for
tendering purposes only. Purpose of these drawings is to enable the tendered to make an offer
in line with the requirements of the Owner. Construction shall be as per drawings /
specifications issued / approved by the Engineer-in-charge during the course of execution of
work.
4.3 Conduit layout drawing in ceiling, wherever required, to be prepared by the contractor and shall
be submitted for approval.
4.4 After the job completion, contractor shall prepare AS-BUILT drawings and documents, submit
catalogues/manuals (O&M) of major brought out items like Inverter, HT Substation, Lighting
fixture etc. Final certified as built drawings, documents and manuals etc shall be submitted by
the contractor to owner in bound volume with one set in soft copy (CD) plus five sets of prints.
-x-x-x-
373 of 896
DRAWINGS
374 of 896
SCHEDULE OF OPENINGS
S.NO. TYPE MASONRY LEVELS DESCRIPTION NO.
OPENING
WXH SILL LINTEL
aluminium section,partly glazed
1 D2 1000X2100 - 2100 partly panelled (with cement 3
bonded prelaminated particle
board), single leaf door
aluminium section,panelled (with
2 D3 900X2100 - 2100 1
cement bonded prelaminated
particle board), single leaf door
LAYOUT PLAN A EXTERNAL FINISHES & ROOF - CORRUGATED GI SHEET OVER STRUCTURAL MEMBERS AS PER SPECIFICATIONS.
ALL VOIDS BETWEEN EXTERNAL WALL & INTERNAL WALL SHALL BE FILLED WITH INSULATION AS PER SPEC.
NOTES:-
SRIKAKULAM TO ANGUL NATURAL
GAS PIPELINE (PART - B)
375 of 896
SCHEDULE OF OPENINGS
S.NO. TYPE MASONRY LEVELS DESCRIPTION NO.
OPENING
WXH SILL LINTEL
aluminium section,partly glazed
1 D2 1000X2100 - 2100 partly panelled (with cement 1
bonded prelaminated particle
board), single leaf door
Visitor's Chair (non - revolving type) 01 9mm HMR grade pre-laminated Vitrified Tiles Vitrified Tiles
1 GUARD ROOM
MDF board paneling 9mm HMR grade (600X600) (150 mm high)
pre-laminated MDF
4 drawer Vertical Filing cabinet of
01 2 4mm moisture resistant bakelite board paneling Anti-skid Ceramic Ceramic Tiles
size 1320mm(H) X 470mm(W) X TOILET
sheet Tiles (300X300) (150 mm high)
ELEVATION 'C' 620mm(D) (approx.)
Health faucet 01
B B Liquid soap dispenser 01
Urinal Partition 02
GUARD TOILET
X X' X X'
3000
3000
up
ISSUED FOR TENDER PURPOSE ONLY
A ROOF PLAN A
LAYOUT PLAN
EXTERNAL FINISHES & ROOF - CORRUGATED GI SHEET OVER STRUCTURAL MEMBERS AS PER SPECIFICATIONS.
ALL VOIDS BETWEEN EXTERNAL WALL & INTERNAL WALL SHALL BE FILLED WITH INSULATION AS PER SPEC.
NOTES:-
SRIKAKULAM TO ANGUL NATURAL
GAS PIPELINE (PART - B)
GUARD ROOM
LAYOUT PLAN & ELEVATION
376 of 896
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
10000
1 2 3 4 5
2500 1500 4000 2000
B
3000
1000
GUARD TOILET BATTERY
ROOM EQUIPMENT ROOM ROOM
2000
377 of 896
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
10000
5 4 3 2 1
2000 4000 1500 2500
3000
A
1000
378 of 896
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
6000
1 2 3
4000 2000
B 3000
BATTERY
EQUIPMENT ROOM ROOM
up
PCP ROOM
379 of 896
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
4000
1 2 3
2500 1500
GUARD
ROOM TOILET
3000
up
380 of 896
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
200
X
X
X
X
X
X
2500
X
X
X
X
X
X
300
X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X X
X
X
X
X
ELEVATION
X X
FOR TENDER PURPOSE ONLY
381 of 896
PRODUCED BY AN AUTODESK EDUCATIONAL PRODUCT
6000
1 4000 2 3
2000
3000
BATTERY
EQUIPMENT ROOM ROOM
up
2000
PCP ROOM
382 of 896
ANNEXURE - A
Scheme for SAPL (Part A)
Type of Building for PCP Type of Building for Guard
PCP Room with
SN Station Type Station Name State Guard Room Size cum Guard Room (Civil / Room
Guard Room Size
Porta) (Civil / Porta)
1 DT Angul Odisha Existing - Existing
2 SV SV-01 Odisha 10m x 3m Porta
3 SV SV-02 Odisha 4m x 3m - Porta
4 SV SV-03 Odisha 4m x 3m Porta
5 SV SV-04 Odisha 4m x 3m - Porta
6 IP IP-01 Odisha 4m x 3m - Porta
7 SV SV-05 Odisha 10m x 3m Porta
8 SV SV-06 Odisha 4m x 3m - Porta
9 SV SV-07 Odisha 4m x 3m Porta
10 IP IP-02 Odisha 4m x 3m - Porta
11 SV SV-08 Odisha 4m x 3m - Porta
12 SV SV-09 Odisha 10m x 3m Porta
13 SV SV-10 Odisha 4m x 3m - Porta
14 IP IP-03 Odisha - 4m x 3m - Porta
15 SV SV-11 Odisha 10m x 3m Porta
16 SV SV-12 Odisha - 4m x 3m - Porta
17 SV SV-13 Andhra Pradesh - 4m x 3m - Porta
18 SV SV-14 Andhra Pradesh - 4m x 3m - Porta
19 IP IP-04 Andhra Pradesh - 4m x 3m - Porta
20 SV SV-15 Andhra Pradesh - 4m x 3m - Porta
21 SV SV-16 Andhra Pradesh - 4m x 3m - Porta
22 SV SV-17 Andhra Pradesh 10m x 3m Porta
23 RT Srikakulam Andhra Pradesh - 4m x 3m - Porta
For Station Details , Please refer Pipeline Schematic Route Diagram No. MEC/23V9/05/28/M/000/0021 & 0022 for SAPL - Part A & Part B
Note:
respectively enclosed with contract document.
383 of 896
18.0 LIST OF CROSSINGS INDICATING
PROPOSED CROSSING METHODOLOGY
384 of 896
GAIL (INDIA) LIMITED
PROJECT: SRIKAKULAM ANGUL PIPELINE PROJECT (PART B)
385 of 896
Asphalted Asphalted Road
55 Road 79019.63 (Narasinghmunda- Gunupur) 30.16 OPEN CUT
386 of 896
Asphalted Asphalted Road
117 Road 158446.62 (Rayagada-Dumapal) 16.07 OPEN CUT
118 River 158582.01 River 39.03 HDD LISTED
119 River 159400.45 River 51.23 HDD LISTED
Asphalted Asphalted Road
120 Road 159550.19 (Gumma-Kumang) 9.83 OPEN CUT
Asphalted Asphalted Road
121 Road 160020.86 (Gumma-Kumang) 19.71 OPEN CUT
Asphalted Asphalted Road
122 Road 160139.89 (Gumma-Kuakhal) 10.53 OPEN CUT
123 River 160336.57 River 64.82 HDD LISTED
Asphalted Asphalted Road
124 Road 160453.27 (Gumma-Lellibadi) 11.86 OPEN CUT
Asphalted Asphalted Road
125 Road 165180.65 (Gumma-Porhakana) 16.67 OPEN CUT
126 Nala 165475.46 Nala 28.45 OPEN CUT
Asphalted Asphalted Road
127 Road 166019.5 (Gumma-Minadurga) 11.48 OPEN CUT
128 Nala 168852.43 Nala 34.63 OPEN CUT
129 Nala 169407.22 Nala 24.64 OPEN CUT
Asphalted Asphalted Road (Dangasila
130 Road 174202.68 To Badapukel) 12.43 OPEN CUT
131 Nala 174570.35 Nala 39.52 OPEN CUT
State SH-44 (Rafkana- Kashipur) As per crossing permission from concerned
132 Highway 178433.23 16.75 HDD/OPEN CUT
authority
Asphalted Asphalted Road
133 Road 180349.55 (Anajora-Jarnugurha) 20.91 OPEN CUT
134 Nala 181497.21 Nala 21.97 OPEN CUT
Braud Gauge Railway (East As per Crossing permission from concerned
Cost Railway Line Koraput -
135 Railway 182118.87 209.83 authority
Rayagada)
HDD/CASED CROSSING
136 Nala 182180.47 Nala 209.83
30 Canal 31284.99 Lined Canal 14.69 HDD As per Crossing permission from concerned authority
31 Canal 31357.69 Lined Canal 15.66 HDD As per Crossing permission from concerned authority
387 of 896
42 River 43293.24 Barha Nadi 143.55 HDD LISTED
43 Asphalted 45655.35 Bijepur- Kalyansingpur 11.74 OPEN CUT
Road
44 Concrete 46040.68 Kharjorha-Tentikri 10.22 OPEN CUT
Road
45 River 46305.43 Sana Nadi 159.16 HDD LISTED
46 Nala 51495.2 Pitadar Nala 66.27 OPEN CUT
47 Nala 53832.37 Nala 26.54 OPEN CUT
48 Nala 57803.24 Nala 50.95 OPEN CUT
49 Asphalted 58223.25 Lanjigarh-Bijepur 9.7 OPEN CUT
Road
50 Asphalted 59390.73 Lanjigarh-Bijepur 17.64 OPEN CUT
Road
51 Asphalted 61448.73 Lanjigarh-Bijepur 11.37 OPEN CUT
Road
52 Asphalted 61835.68 Lanjigarh-Bijepur 13.96 OPEN CUT
Road
53 Asphalted 62882.2 Lanjigarh-Bijepur 15.58 OPEN CUT
Road
54 Asphalted 65003.53 Lanjigarh-Bijepur 11.61 OPEN CUT
Road
55 Asphalted 67014.76 Lanjigarh-Hatadahikhal 13.03 OPEN CUT
Road
56 Nala 67058.56 Nala 28.22 OPEN CUT
SECTION - IV (SPURLINE TO NALCO)
1 Asphalted 3128.67 Asphalted Road 25.80
Road (Anajor - Mailigurha) OPEN CUT
2 Nala 3948.26 Nala 24.69 OPEN CUT
3 Asphalted 5816.36 Asphalted Road (Kapatanga - 14.66
Road Harihabhata) OPEN CUT
Nala (Kandabindha
52 Nala 51293.78
Nala)
29.24 OPEN CUT
53 Asphalted 51881.05 Asphalted Road (Bhitaraguda - 15.22
Road Barigurha) OPEN CUT
Asphalted Asphalted Road (Morichomal -
54 Road 52780.98 Barigurha) 15.74 OPEN CUT
55 Nala 54374.56 Nala 29.00 OPEN CUT
56 Nala 54983.43 Nala 86.31 OPEN CUT
388 of 896
57 MDR Road (Damanjodi
MDR Road 57650 - Kakiriguma) 16.27 OPEN CUT
MDR Road (Kakiriguma -
58 MDR Road 59143.17 Damanjodi) 15.00 OPEN CUT
59 Nala 59640.07 Nala 20.05 OPEN CUT
MDR Road (Damanjodi
60 MDR Road 59802.19 - Kakiriguma) 12.09 OPEN CUT
61 Nala 60938.39 Nala 21.19 OPEN CUT
Asphalted Asphalted Road (Damanjodi -
62
Road
62443.89
Ambagan)
10.95 OPEN CUT
63 Asphalted Asphalted Road (Nalco
Road
62486.99
Plant - Ambagan)
12.15 OPEN CUT
Note:
1) Length of crossing shall be as per approved profile.
2) For all crossings, other than above, the proposed crossing methodology shall be by open cut method or as per instruction of EIC.
3) Above mentioned crossing methodology for respective crossing may vary depending upon site conditions during time of execution. In case of
such situation, GAIL/PMC has reserve right to inform contractor about revised crossing methodology to be adopted. The payment will be
regulated based on the actual crossing methodology executed.
389 of 896
19.0 LIST OF APPROVED PARTIES FOR
BOUGHT OUT ITEMS
390 of 896
Appendix-IX
To Particular Job Specification of Work
391 of 896
4. EEWKOREA CO. LTD (GERMANY), KOREA
5. EEW KOREA CO. LTD. (KOREA), KOREA
6. EISENBAU KRAMER GMBH, GERMANY
7. HYUNDAI RB CO. LTD. SOUTH KOREA
8. ILVA LAMIERE E TUBI SRL (ENQ TO ILVA SPA, ITALY
9. INOX TECH. SPA, ITALY
10. ISMT LTD. AHMEDNGR, INDIA
11. ISMT LTD. BARAMATI, INDIA
12. JINDAL PIPES LTD., INDIA
13. JINDAL SAW LTD. (KOSI WORKS), INDIA
14. JINDAL SAW LTD. (NASHIK WORKS), INDIA
15. LALIT PIPES AND PIPES LTD. INDIA
16. MAHARASHTRA SEAMLESS LTD., INDIA
17. MAN INDUSTRIES (I) LTD. (PITHAMPUR), INDIA
18. MUKAT TANKS & VESSELS LTD., INDIA
19. PRATIBHA INDUSTRIES LIMITED, INDIA
20. RATNAMANI METALS AND TUBES LTD., INDIA
21. SIDERCA S.A.I.C (ENQUIRY TOTENARIS), UAE
22. SUMITOMO METAL IND. LTD., INDIA
23. SURYA ROSHNI LTD., INDIA
24. SWASTIK PIPES LTD, INDIA
25. TATA STEEL UK LIMITED (FORMERLY C702)
26. TUBOS DE ACERO DE MEXICO SA (ENQ. TENARIS), UAE
27. TUBOS REUNIDOS SA SPAIN
28. UMRAN STEEL PIPE INC (TURKEY), TURKEY
29. VALCOVNY TRUB CHOMUTOV, CZECH REPUBLIC
30. VALLOUREC AND MANNESMANN TUBES, FRANCE
31. WELSPUN CORP LIMITED (DAHEJ), INDIA
392 of 896
iv) PIPE CARBON STEEL (WELDED) TO ASTM STDS
v) Valve
a) Globe Valves
b) Check Valves
1. M/s Advance Valves Pvt. Ltd., Noida
393 of 896
2. M/s Aksons& Mechanical Enterprises, Mumbai
3. M/s Larsen & Toubro Limited (M/s Audco India Limited, Chennai)
4. M/s AV valves Ltd., Agra
5. M/s BDK engineering India Ltd., Hubli
6. M/s BHEL,OFE&OE Group, New Delhi
7. M/s DatreCoroportion Limited, Calcutta
8. M/s Leader Valves Ltd., Jalandhar
9. M/s Necoschubert&Salzer Ltd., New Delhi
10. M/s Niton Valves Industries (P) Ltd., Mumbai
11. M/s Precision Engg.Co., Mumbai
12. Econo Valves Pvt Ltd, India
13. FouressEngg (I) Ltd (Aurangabad)
14. KSB Pumps Ltd (Coimbattore), India
15. NSSL Ltd. (Neco Schubert &SalzerLtd)
16. Oswal Industries Ltd, India
17. Panchvati Valves &FlangesPvt Ltd, India
18. Petrochemical Engineering Enterprises, India
19. Sakhi Engineers Pvt Ltd
20. Shalimar Valves Pvt Ltd
21. Steel Strong Valves India Pvt Ltd, India
c) Plug Valves
d) Ball Valves
394 of 896
10. M/s Franz Schuck GmbH, Germany
viii) Flanges
395 of 896
25. Pipefit Engineers Pvt. Ltd.
ix) Fittings
1. M/s Commercial Supplying Agency, Mumbai
2. M/s Dee Development Engineers Ltd.
3. M/s Eby Industries, Mumbai
4. M/s Flash Forge Pvt. Ltd., Vishakhapatnam
5. M/s Gujarat Infra Pipes Pvt. Ltd., Vadodara
6. M/s M.S. Fittings Mfg. Co. Pvt. Ltd., Kolkata
7. M/s Stewarts & Lloyds of India Ltd., Kolkata
8. M/s Teekay Tubes Pvt. Ltd., Mumbai
9. M/s Pipe Fit,Baroda
10. M/s Sky Forge, Faridabad
11. M/s S&G, Faridabad
12. M/s Sawan Engineers, Baroda
13. Eby Fasteners, India
14. Leader Valves Ltd, India
15. R.N. Gupta & Co. Ltd, India
16. ExtenEnggPvt Ltd
17. Sivananda Pipe & Fittings Ltd
x) Gaskets
1. IGP Engineers (P) Ltd., Madras
2. Madras Industrial Products, Madras
3. Dikson& Company, Bombay
4. Banco Products (P) Ltd., Vadodara
5. Goodrich Gaskets Pvt Ltd
6. Starflex Sealing India Pvt Ltd, India
7. Teekay Meta Flex Pvt Ltd
8. UNIKLINGER Ltd
9. HEM Engg. Corp.
10. Unique Industrial Packing Pvt. Ltd.
xi) Fasteners
396 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM- ANGUL PIPELINE
OIL & GAS SBU
PROJECT (PART B) OF M/S GAIL
MECON LTD,
(INDIA) LIMITED DELHI
xiii) Miscellaneous
1. Denso GmBH
2. Polyken (Berry Plastics Corporation)
c) PUR Coating
1. Raci, Italy
2. Raychem RPG Limited
e) Casing Insulators
1. Raci, Italy
2. Raychem RPG Limited
3. VeekayVikram
f) Rockshield
397 of 896
g) Warning mesh
B) NDT AGENCY
1. NDT Services, Ahmedabad
2. GEECY Industrial Services Pvt. Ltd., Mumbai
3. Corrosion Control Services, Mumbai
4. Perfect Metal Testing & Inspection Agency, Calcutta
5. Inter Ocean Shipping Co., New Delhi
6. RTD, Mumbai
7. Sievert, Mumbai
8. X-Tech, Vizag
9. Industrial X Ray and Allied Radiographers (I) Pvt. Ltd.
10. Inspection Technology, Mumbai
1) For procuring bought out items from vendors other than those listed above, the same
may be acceptable subject to the following: -
398 of 896
LAYING AND TERMINAL WORKS FOR
SRIKKAKULAM- ANGUL PIPELINE
OIL & GAS SBU
PROJECT (PART B) OF M/S GAIL
MECON LTD,
(INDIA) LIMITED DELHI
b) The vendor / supplier should not be in the Holiday list of GAIL / MECON / other
PSU.
c) Should have supplied at least one single random length (i.e. 5.5 meters to 6.5
meters) for item assorted pipes / tubes and for other items, which are to be
supplied in quantity on number-basis (other than assorted pipes / tubes) minimum
01 (One) number of same or higher in terms of size and rating as required for
intended services.
2) For any other item(s) for which the vendor list is not provided, contractor can supply
those item(s) from vendors/ suppliers who have earlier supplied same item(s) for the
intended services in earlier projects and the item(s) offered is in their regular
manufacturing/ supply range.
The bidder is not required to enclose documentary evidences (PO copies, Inspection
Certificate etc.) along with their offer, however in case of successful bidder, these
documents shall required to be submitted by them within 30 days from date of Placement
of Order for approval to GAIL / MECON.
3) The details of vendors indicated in this list are based on the information available with
MECON. Contractor shall verify capabilities of each vendor for producing the required
quantity. PMC does not guarantee any responsibility on the performance of the vendor. It
is the contractor’s responsibility to verify the correct status of vendor and quality control
of each parties and also to expedite the material in time.
399 of 896
20.0 MINIMUM CONSTRUCTION
EQUIPMENT TO BE DEPLOYED DURING
RE-MOBILISATION
400 of 896
APPENDIX - X to PJS
13 Gamma Source 1 1
Note : The above schedule shall be only considered for the Re-mobilization period of 1 month. Based on
site conditions, revised schedule shall be worked out by GAIL/PMC/Contractor for subsequent months.
The decision of EIC shall be final and binding.
401 of 896
21.0 MINIMUM NO. OF SKILLED
MANPOWER TO BE DEPLOYED
DURING RE-MOBILISATION
402 of 896
APPENDIX - XI to PJS
The above proposed list of skilled manpower is the minimum to be deployed by Contractor.
NOTES:-
(1) The above schedule shall be only considered for the Re-mobilization period of 1 month.
Based on site conditions, revised manpower requirement shall be worked out by
GAIL/PMC/Contractor for subsequent months. The decision of EIC shall be final and binding.
403 of 896
LAYING AND TERMINAL WORKS FOR
OIL & GAS SBU SRIKKAKULAM- ANGUL PIPELINE
PROJECT (PART B) OF M/S GAIL MECON LTD,
(INDIA) LIMITED DELHI
404 of 896
INSPECTION CATEGORISATION PLAN
2.0 Instrumentation
Works
2.1 Instruments (PG, TG,
PT, TT, LEL Detectors, Nos. B B/C B/C
RTD etc)
2.2 Instrument cables Nos. B B/C B/C
2.3 Control panel Nos. B B/C B/C
2.4 Cable Trays Nos. N/A C C
2.5 Junction Boxes , Cable
Nos. N/A C C
Glands
2.6 Tube Fittings , Tube
LS N/A C C
manifolds
2.7 Instrumentation Valves Nos. N/A C C
4.0 TCP
4.1 CP Cables B C C
(1Cx6Sqmm, 1Cx10
Mtrs.
Sqmm, 1Cx25Sqmm &
1Cx35 Sqmm)
4.2 Test Stations (Big &
Nos.
B C C
Small Type)
4.3 Sacrificial Mg & Zn
Nos.
B C C
Anodes
4.4 Spark Gap Arrestor
Nos.
N/A C C
(100 kA)
4.5 Polarisation Cell (Solid
Nos.
N/A C C
State)
405 of 896
4.6 External ER Probe Nos. N/A C C
4.7 CTSU (Computerised B C C
Test Station Unit) & Nos.
CTSU Reader
4.8 Permanent Reference
Nos.
B C C
Cell
4.9 Zinc Ribbon Anode Mtr/Nos. B C C
5.0 CMS
5.1 ER Probe, Access Nos.
Fitting Assembly For B C C
ER Probes
5.2 Transmitter & Receiver Nos. B C C
5.3 Corrosion coupons, Nos.
coupon holder, access
B C C
fitting assembly for
corrosion coupons
5.4 Retriever Kit, Service Nos.
B C C
Valve Kit
6.0 Electrical
6.1 PDB-1/2, I-E LDB, PP
Nos. N/A B B
LDB, OLDB
6.2 FLP Feeder Pillar
(Structure mounted) for Nos. N/A C C
outdoor lighting
6.3 Inverter with tubular
Nos. N/A C C
battery
6.4 Earthing material (Earth
pit with GI Electrode/Cu
plate Electrode,
GI/Copper Strips,GI Nos. B C C
wire, GI Lightning rod,
Advance Maintenance
free earthing system)
6.5 Power & Control Cables
Mtrs. B B C
(HT & LT)
6.6 Lighting fixtures (FLP &
Nos. N/A C C
Non-FLP type)
6.7 Street Light Pole (6Mtr
Nos. B C C
height)
6.8 High Mast & FLP
Feeder pillar panel for Set B C C
High Mast
6.9 Distribution Tranformers
Nos. N/A B B
(11/0.433kV)
6.10 MCCB Enclosure – WP
Nos. N/A B B
Outdoor type
6.11 ACSR weasel
Mtrs. N/A C C
conductor
6.12 Ceiling/Wall mounted
Fans, Exhaust Fans,Air Nos. N/A C C
conditioners,
406 of 896
6.13 Welding socket Nos. N/A C C
6.14 Cable Tray Mtrs. N/A C C
6.15 First Aid box Nos. N/A C C
6.16 Carbon-di-oxide(CO2)
Nos. N/A C C
type fire extinguisher
6.17 Insulating Mat Mtrs. N/A C C
6.18 Telephone/LAN socket,
Nos. N/A C C
LAN Switches
6.19 Telephone/LAN/UTP
Nos. N/A C C
cable
6.20 AVR Nos. N/A B B
LEGEND:
Notes:
407 of 896
Annexure-I
to
Particular Job Specification
(CATHODIC PROTECTION WORKS)
408 of 896
GAIL (INDIA) LIMITED
DESIGN BASIS FOR CATHODIC PROTECTION
SYSTEM
409 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
Contents
1. INTRODUCTION
2. SCOPE
3. CODES & STANDARDS
4. SITE CONDITIONS
5. AREA CLASSIFICATIONS
6. POWER SUPPLY DETAILS FOR CP SYSTEM
7. CATHODIC PROTECTION SYSTEM DESIGN
8. PROTECTION OF PIPELINE AT HT LINE CROSSING
9. CP AT CASED CROSSINGS
10. CATHODIC PROTECTION DESIGN CRITERIA
11. CP CABLES
12. STATUTORY APPROVAL
13. DRWINGS AND DESIGN DOCUMENTS
APPENDIX-I : LIST OF ABBREVIATIONS
410 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
1.0 INTRODUCTION
GAIL (India) Limited a public sector under Petroleum ministry, intends to develop Natural
Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh) to Angul
(Odisha) Natural Gas Pipeline Project and its Spurlines in the state of Odisha and Andhra
Pradesh for industrial consumers as well as City Gas Distribution System (CGD).
This pipeline will connect various RLNG terminals like, Dhamra, Dahej, Ennore,
Gangavaram, FSRU etc. and domestic gas fields of K G basin, Off-shore/On-shore fields to
the customers in Eastern region through JHBDPL and Southern region through KSPL.
Therefore, it will provide connectivity to multiple sources to the en-route customers. In view of
the same it has strategic importance and part of National Gas Grid.
This document presents design criteria for electrical TCP & PCP system for 3LPE Coated
18”/12”NB x 322 Kms (approx) Mainline & Spurlines (Part-B) from IP-4 cum DT (Ch 341.0km
of SAPL Part-A) to RT at Utkal Alumina (Ch 190.8 km) , RT at Vedanta (Ch 68.3 km) , & RT
at Nalco (Ch 62.97 km) for transportation and distribution of Natural Gas in the region.
Part-B pipeline mainly consist of 18”NBx48 Kms (approx) and 12”NBx274 Kms (approx)
pipeline in different districts of Odisha & Andhra Pradesh for transportation and distribution of
Natural Gas.
In case of any conflict between the codes and standards listed, the same shall be brought to the
notice of Owner for final decision, which shall be binding.
2.0 SCOPE
2.1 Survey, Design, detailed engineering, supply, packing, transportation to site, installation,
testing and commissioning of the temporary cathodic protection system using Mg/ Zn galvanic
anodes for design life of minimum 2 years or till the commissioning of PCP system whichever
is later, to protect the external surface of 18''/12” x 322 Kms. (approx.) pipeline from from IP-4
cum DT (Ch 341.0km of SAPL Part-A) to RT at Utkal Alumina (Ch 190.8 km) , RT at Vedanta
(Ch 68.3 km) , & RT at Nalco (Ch 62.97 km) in different districts of Odisha & Andhra Pradesh
against corrosion. ICCP based Permanent Cathodic Protection system is also envisaged for a
service life of 35 years to protect the external surface of Pipeline. TCP & PCP system shall be
designed as per MECON’s standard Specification No. MEC/S/05/E9/016A & 16B for
Temporary & Permanent cathodic protection system respectively & Scope of Work, Data
Sheets & Other relevant standards.
2.2 Electrical continuity between new pipeline segments and existing pipelines segments
(if any-applicable) shall be done by CP contractor to maintain the CP current from
existing CP anode bed/station).At all possible locations, the test stations for new
pipeline need to be installed matching with the test station of existing pipeline, for
bonding purpose.
2.3 The works related to TCP/PCP such as connection of cables to the pipeline, installation
of sacrificial anodes, laying of polarization coupons, reference cells, CTSU, surge
diverter etc. and laying of HDPE sheets between the pipeline under the scope of work
411 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
and other foreign pipelines at the crossing locations for providing electrical isolation
for minimizing the pickup and discharge of the CP System current between the
pipelines shall be completed before backfilling of the trench.
2.4 Disconnection of all the sacrificial anodes before PCP commissioning. After PCP
commissioning TCP may be reconnected, if required at some locations in the event of
detection of localized areas of inadequate protection (hot spot).This will be only as a
temporary measure, till the permanent measures are implemented by the Contractor to
increase the CP potential level at hot spot areas
2.5 CTSU:Computerized test station unit (CTSU) shall have the following feature:
i. Simultaneous recording of 3 No. analogue channels.
ii. Shall be able to generate +ve& -ve sign for recorded PSP values.
iii. Portable Laptop readers shall be supplied with CTSU for Field downloading of Data.
iv.Spare Battery Pack shall be supplied.
v. The CTSU shall provide Battery Low alarm.
The CTSU shall be housed in a PVC enclosure of dimensions 130mm X 130mm
The system design, performance and materials to be supplied shall, unless otherwise
specified, conform to the requirements of the following latest relevant applicable
specifications:
VI) NACE Publication No. 54276 : Cathodic Protection Monitoring for Buried
Pipelines
VII) NACE Standard SP-0572 : Standard Practice for Design, Installation &
Operation of Impressed Current Deep Ground
beds
VIII) NACE Standard SP-200 : Standard Practise for Steel Cased Pipeline
Crossings
IX) NACE Standard SP-0104 : The Use of Coupons for Cathodic Protection
Monitoring Applications
X) BS 7361 Part I : Code of Practice for Cathodic Protection for land
and Marine applications 412 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
XIII) IS: 1554 Part I & II : PVC Insulated heavy duty electrical cables.
3.2 In case of imported equipments standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian standards.
3.3 The equipment shall also confirm to the provisions of Indian Electricity rules and other
statutory regulations currently in force in the country.
3.4 In case of any contradiction between various referred standards/ specifications/ data sheet
and statutory regulations the following order of priority shall govern.
Statutory regulations.
Data sheets.
Scope of Work/ Job specification.
Design Basis.
Standard Specification.
Codes and standards.
413 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
The equipment offered and the installation shall be suitable for continuous operation under
the following site conditions:
Classification of hazardous area will be in accordance with BIS and IS: 5572.
Following selection will be considered for proper selection of electrical equipment for use in
hazardous area:
c) Temperature Classification : T3
All electrical equipment installed in hazardous area will be selected as per IS: 5571.
All the electrical equipment for hazardous areas shall be of Ex-d type suitable for temp
classification T3.
414 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
A. Type Sacrificial
SP104:2014)
Pipe to soil "ON" potential shall not be more negative than (-) 1.2V during TCP.
* Actual current density to be adopted shall be decided based upon soil and other
environmental conditions, proximity of foreign pipelines and structures affecting
interference. Where considered necessary for satisfactory protection of pipeline the
current density shall be suitably increased by contractor. Where operating temperatures
of U/G pipeline is above 30 deg. C, such as CP Stations located near Compressor
stations, protection Current Density shall be increased in minimum by 25% for every 10
416 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
b) Interval for data acquisition/ Once every day (Refer Note below)
storing
M. Acquisition of land or Lease (for By contractor, Installation location shall
99 years) for Anode bed, Anode be decided by CP system contractor
junction boxes and anode based on detailed engineering,
ground bed ROU for cable specification and at availability of power
laying. source & land.
N. Chain link fencing around the Shall be provided
ground Bed
O. Close interval potential logging Shall be carried out
survey
417 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
by the Contractor, Any other proposed location shall be included during detailed
engineering, if required without any cost implication. However PCP system shall be
designed in such a manner that CP stations & anode bed shall be located
coinciding with SV / IP stations, as far as possible.
Note: - For computerized test station: Interval of data acquisition/storing may be kept
for once in every hour. This feature will be helpful for detecting/trouble shooting in
case of encountering any interference. However in normal case, one reading per day
is enough.
Pipeline Interference study shall be carried out by modeling software’s for short term
and long term interferences for safe touch potentials along with AC corrosion study.
Remedial measures shall be implemented in accordance with codes & standards to
bring down the steady state touch voltage on pipeline below 15V (rms) for safety
reasons. In addition, any AC voltage indicating a current density of 30 mA/m2 or
above (assuming 1 cm2 sized area of holiday / defect) shall be grounded through
solid state DC de-coupling device to reduce the AC corrosion and touch potentials.
Where high voltage (66 KV and above) transmission line runs in parallel or crosses
the pipeline, the pipeline shall be grounded through polarisation cells of suitable rating
(solid state) & Grounding (a continuous length of Zn Ribbon Anodes/Copper
conductors with back fill material shall be laid along the pipeline) shall be done at
regular intervals of maximum 1 km where transmission lines run parallel within 1km of
419 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
the pipeline and have separation distance of 50 mtr on both side of the pipeline.
Mitigations resulted from interference study & mitigation report to ground any surges
on the pipeline that would appear in case of transmission line faults shall be
implemented.
If any AC interference is observed along the pipeline due to low voltage electric lines
(below 66kV), its mitigation will be carried out by means of earthing of pipeline through
polarization cell has also been considered.
Interference detection & mitigation due to DC sources (i.e. HVDC transmission lines.
DC traction etc) shall be carried out as per DIN 57150/VDE 0150:Protection against
corrosion due to stray currents from DC installations and other applicable standards.
a) The pipe to soil potential measurements shall be between (-) 850 mV (Off) & (-) 1200
mV (Off) polarized potentials with respect to a copper/ copper sulphate reference
electrode.
c) As such there is no limit for maximum "ON" negative potential; however, in general, it
should not be more negative than -2500 mV (Cu/CuSO4). If any special
circumstances exist where an “ON” potential of more than -2500 mV (Cu/CuSO4) is
required to be applied, then it shall be brought forward for GAIL approval with proper
justification supported by the pipeline coating Manufacturer's recommendations.
420 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
CPPSM/TR unit shall be properly interfaced with SCADA RTU through Hardwired link
for various analogue and digital signals. Details of SCADA monitoring signals are
given below-
Sl MONITERING/ ANALOUGE
DESCRIPTION
No. CONTROL /DIGITAL
1 CP TR/CPPSM OUT PUT M AI
VOLTAGE
2 CP TR/CPPSM OUT PUT M AI
CURRENT
3 PIPELINE OVER M DI
PROTECTED
4 PIPELINE UNDER M DI
PROTECTED
5 PIPE TO SOIL M AI
POTENTIAL
8 UNIT WORKING IN M DI
MANUAL MODE
9 AC INPUT FAIL M DI
1 AI: Analogue monitoring signal from Equipment to PLC/Telemetry interface cabinet (TIC)
421 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
11.0 CP CABLES
TCP Cables
TCP Cables shall be annealed high conductivity, tinned, stranded copper conductor, XLPE
insulated 650/1100 V grade, armoured/un-armoured, PVC sheathed. The size of the copper
conductor shall be 6 sq mm for anode cable from anode to buried junction box, 10 sq mm
from junction box to test station, 10mm² from test station to pipeline. The size of the
conductor shall be 6 sq mm for potential measurement, 10 sq mm for current measurement
and 25mm² for bonding, polarization cell / grounding cell/Earthing and surge diverter
connection purpose. The anode cable from anode to junction box (buried) shall be
unarmoured. The length of anode tail cable shall be sufficient enough to reach junction box
(buried) in case of temporary CP anodes and up to test station in case of permanent CP
sacrificial anodes. PE Sleeves shall be provided for unarmoured cables.
Note- Underground buried junction box shall be provided only at locations where more
than two (02) nos. of anodes required for the pipeline protection.
PCP Cables
Anode tail/lead cable shall be 1Cx10 Sqmm size, annealed high conductivity tinned stranded
copper conductor (7 Strands), PVDF insulated (Thickness 0.040 Inch), HMWPE
sheathed/Jacket (Thickness 0.065 Inch), un-armoured.
ii) Anode & Cathode Header Cable- (Size 1Cx35 Sqmm)-
Anode & Cathode Header Cable shall be 1Cx35 Sqmm size, annealed high conductivity
tinned stranded copper conductor, XLPE insulated, PVC sheathed, FRLS, 1.1kV Grade
armoured cable as per IS: 7098.
TR/CPPSM Input Power Supply Cable shall be 3Cx10 Sqmm size, annealed high conductivity
tinned stranded copper conductor, XLPE insulated, PVC sheathed, FRLS, 1.1kV Grade
armoured cable as per IS: 7098 for Single Phase TR Units and 4 core type for 3 phase TR
units.
iv) Measurement cable & Permanent Reference cell tail cable- (Size 1Cx6 Sqmm)-
Measurement cable & Permanent Ref cell tail cable from Pipe/Tank/Bullet/Vessel to CJB &
CJB to TR/CPPSM Unit shall be 1Cx6 Sqmm size, annealed high conductivity tinned stranded
copper conductor, XLPE insulated, PVC sheathed, FRLS, 1.1kV Grade armoured, screened
cable as per IS: 7098 or Multi-core signal cable of suitable pair shall be considered for the
measurement cable & reference cell cable from CJB to TR unit. (For this bidder may consider
8/12 pair, Multi-core, FRLS, 2.5 Sqmm, 8/12 pair, twisted pair, shielded, armoured, signal cables
422 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
as per IS/BS).
v) The colour of outer sheath of the cables shall be as per the PJS/Scope of work/Design Basis
and outer sheath should have marking of “CP system Cable” in each one meter interval by
black colour for identification purpose.
vi) The cables for connecting various transducers from TR unit/ CPPSM to telemetry interface
junction box shall be twisted pair with individual pair shielded and overall shielded with
aluminium backed by mylar/polyster tape, PVC sheathed, armoured, PVC over all sheathed
type.
CABLING SYSTEM
The submission of application on behalf of the Owner to Govt. Authority/ Central Electricity
Authority, if required along with copies of required certificates complete in all respects, shall
be done by the contractor well ahead of time so that the actual commissioning of project are
not delayed for want of approval from authority. The actual inspection of work by the Govt.
inspector shall be arranged by the Contractor and necessary coordination and liaison work in
this respect shall be the responsibility of the contractor. However any fee paid to the Govt.
Authority in this regard shall be reimbursed by the Owner on submission of bills with
documentary evidence.
The Inspection and acceptance of the work as above shall not absolve the Contractor from
any of responsibilities under this contract.
13.1 The following documents shall be submitted along with the offer:
13.2 The following drawings (in three sets) & documents shall be submitted for approval within 3
weeks of award of contract.
a) Pre‐design cathodic protection site survey shall which includes detailed layout drawings of
pipeline / facilities, reflecting all foreign pipeline / Overhead power transmission lines
crossings & parallelism, river, railway, existing CP facilities (such as transformer rectifiers,
anode ground beds, test facilities etc.), soil resistivity survey locations,423 road crossing
of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
locations, etc
b) Various Procedures of CP system Installation Like- Soil survey (TCP & PCP), Thermit
weld, Pin Brazing, Sacrificial anode (Zn/Mg/Ribbon) installations, Test stations & Junction
Boxes installation, Cable laying, Installation of polarization cell, External ER probe, Surge
diverter & grounding cell, connection & sealing of sacrificial anode, Earthing of above
ground pipeline, anode ground bed, CP units etc.
c) Soil survey report and chemical analysis report with marked location vulnerable area.
d) QA & QC Procedures.
e) List of two years operation and maintenance spare.
f) Basis of system design and design calculations, equipment selection criteria and sizing
calculations, formulae used
g) Detailed design calculations of TCP & PCP system (Complete Design Package).
h) Equipment layout, Cable layout & schedule.
i) Construction drawing for fencing of anode bed & AJB.
j) Colour code identification for the various CP System cables used in the system
k) Procedures for Various Post commissioning surveys (CPL, CAT, CAT Frame ‘A’ DCVG &
coating conductance etc).
l) Procedure for AC & DC interference detection & mitigation.
m) Procedure for field testing, pre-commissioning & commissioning of TCP & PCP.
n) Procedure for Monitoring & maintenance of CP system.
o) Detailed design of Anode ground bed, typical lay out drawings for Anode bed connection &
installation for CP system.
p) Equipment layout, Cable layout & schedule.
q) TLP’s & junction boxes installation & erection details drawings.
r) Incorporation of Anode bed, Polarisation cell, surge arrester, TLP, Junction boxes & other
relevant feature in CP system design in Alignment sheet, pipeline route diagram & Plot
plan.
s) G.A. of TR/CPPSM unit.
t) Schematic
u) Wiring diagram for reference.
v) Tentative Bill of Material
13.3 After the job completion, contractor shall prepare AS-BUILT drawings/data sheets and
documents, submit catalogues/manuals (O&M) of major brought out items. Final certified as
built drawings, documents and manuals etc shall be submitted by the contractor to owner in
bound volume with one set in soft copy (CD) plus five sets of prints to owner & one set to
MECON..
Other drawings and documents shall be submitted by contractor along with AS-BUILT
Drawings/Datasheets-
a) Original deed OR Lease agreement for acquired/leased land (In favour of M/s GAIL) for Anode
Bed, ROU for cable laying etc shall be handed over to M/s GAIL.
b) Test documents & drawings for bought out items.
c) Detailed commissioning report of pipeline CP system (Both TCP and PCP).
-x-x-x-
424 of 896
MECON LIMITED Electrical Section, Delhi
SRIKAKULAM - ANGUL
DELHI PIPELINE PROJECT
(PART-B)
APPENDIX – 1
LIST OF ABBREVIATIONS
1) AC –Alternating current
2) CAT –Current attenuation test
3) CJB – Cathode Junction Box
4) CP-Cathodic Protection
5) CPPSM-Cathodic Protection Power Supply Module
6) DCVG –Direct Current Voltage Gradient
7) DC –Direct Current
8) FRLS-Fire Retardant Low Smoke
9) GSM –Global System for Mobile
10) HMWPE – High Molecular Weight Polyethylene
11) MMO–Mixed Metal Oxide
12) NACE- National Association of Corrosion Engineers
13) PCP–Permanent Cathodic Protection
14) PVC – Polyvinyl Chloride
15) PVDF– Polyvinylidene Difluoride
16) ROU – Right Of Use
17) RTU – Remote Terminal Unit
18) TCP–Temporary Cathodic Protection
19) TR- Transformer Rectifier
20) XLPE- Cross Linked Poly Ethylene
425 of 896
SCOPE OF WORKS
FOR
TEMPORARY CATHODIC PROTECTION
WORK
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
426 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
CONTENTS
SL.NO. DESCRIPTION
1. General
2. Project Description
3. Standards
4. Guarantee
5. Site Conditions
7. Abbreviations
15. Construction
16. Documentation
19. Escalation
427 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
428 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
1.0 GENERAL
1.1 Introduction
Special Condition of Contract shall be read in Conjunction with the General Conditions of Contract,
specification of work, Drawing and any other documents forming part of this contract wherever the
context so requires.
Notwithstanding the sub-division of the documents into these separate sections and volumes every
part of each shall be deemed to be supplementary to and complementary of every other part and
shall be read with and into the contract so far as it may be practicable to do so.
Where any portion of the General Condition of Contract is repugnant, to or at variance with any
provisions of the Special Conditions of Contract, unless a different intention appears, the provisions
of the Special Conditions of Contract shall be deemed to over-ride the provisions of the General
Condition of Contract and shall to the extent of such repugnancy, or variations, prevail.
The materials, design and workmanship shall satisfy the relevant INDIAN STANDARDS, the
TECHNICAL SPECIFICATIONS contained herein and CODES referred to. Where the technical
specification stipulate requirements in addition to those contained in the standard codes and
specifications, these additional requirements shall also be satisfied.
Wherever it is mentioned in the specifications that the CONTRACTOR shall perform certain work
or provide certain facilities, it is understood that the CONTRACTOR shall do so at his cost and the
VALUE OF CONTRACT shall be deemed to have included cost of such performance and
provisions, so mentioned.
It will be Contractor’s responsibility to bring to the notice any irreconcilable conflict in the contract
documents at the time of bidding during pre-bid stage. After award of contract, the stringent of
available technical/statutory/specifications/drawings shall be implemented at the no additional cost
to Owner.
In the absence of any specifications covering any material, design of work(s) the same shall be
performed/ supplied/ executed in accordance with Standard Engineering Practice as per the
instructions/ directions of the Engineer-in-charge, which will be binding on the Contractor at no
additional cost and time to Owner.
.
GAIL (India) Limited a public sector under Petroleum ministry, intends to develop Natural
Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh) to Angul
(Odisha) Natural Gas Pipeline Project and its Spurlines in the state of Odisha and Andhra Pradesh
for industrial consumers as well as City Gas Distribution System (CGD).
This pipeline will connect various RLNG terminals like, Dhamra, Dahej, Ennore,
Gangavaram, FSRU etc. and domestic gas fields of K G basin, Off-shore/On-shore fields to the
customers in Eastern region through JHBDPL and Southern region through KSPL.
Therefore, it will provide connectivity to multiple sources to the en-route customers. In view of the
same it has strategic importance and part of National Gas Grid.
429 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
M/s MECON Ltd has been engaged by M/s GAIL (India) Limited to carry out design, engineering,
procurement, inspection & Project Management Consultancy Services required for 18”/12” NB x
322 Kms. (approx.) pipeline (Part-B of SAPL Pipeline) from IP-4cum DT (of SAPL Part-A) at Ch
0.00km to Receiving Terminal at Utkal Alumina (Ch 190.8km), SV-6S cum DT at Ch 158.4km to
RT at Vedanta (Ch 68.3km) and .SV-7S cum DT at Ch 178.4km to RT at Nalco (Ch 62.97km).
This document presents brief scope of work for TCP system for external protection of the pipeline.
It indicates minimum requirements for detailed design of TCP system and equipment.
I) Section-I: From DT at Ch. 0.00 (Tap-off from IP-04 of SAPL -Part A at Ch. 341.0 Km) to
IP-01S ( Ch. 48.0 Km approx.) (18”dia x 48 km approx)
II) Section-II: From IP-01S (Ch. 48.0 Km approx.) to RT - Utkal Alumina ( Ch. 190.8 Km
approx.)
(12”dia x 142.8 km approx)
III) Section-III: From SV-06S (Ch. 158.4 Km approx.) to Consumer Vedanta (Ch. 68.3 Km
approx.) (12”dia x 68.3 approx)
IV) Section-IV: From SV-07S (Ch. 178.4 Km approx.) to Consumer Nalco (Ch. 62.97 Km
approx.) (12”dia x 62.97 km approx)
3.0 STANDARDS
3.1 The work shall be performed in conformity with this specification, standard specifications and
installation standards enclosed elsewhere in this tender and code of practices of the Bureau of
Indian Standards. In case of any conflict, the stipulations under this specification shall govern.
430 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
3.2 The Indian Electricity Act, and the rules framed there under.
The regulations laid down by the Chief Electrical Inspector of the state government/ Central
Electricity Authority (CEA).
The regulations laid down by the Factory Inspector.
3.3 The design, selection and installation of equipment and materials shall also conform to the
requirements of the relevant latest standards of:
BS Specification and codes of practice
OISD Standard 138
IS: 8437 (Part-II)/ 8062 (Part-I)
NACE Standards
DNV Publications
IEEE Publications
4.0 GUARANTEE
4.1 The contractor shall guarantee the installation against any defects of workmanship and
materials (supplied by the contractor) for a period 12 months after successful commissioning (
As per DLP terms & conditions defined in the Contract volume). Any damage or defects
connected with the erection of materials, equipments of fittings supplied by the contractor that
may be undiscovered at the time of issue of the completion certificate, or may arise or come to
light thereafter, shall be rectified or replaced by the contractor at his own expense as deemed
necessary and as per the instruction of the Engineer-in-charge within the time limit specified by
Engineer-in-charge.
4.2 The above guarantee shall be applicable for the quality of work executed as well as for the
equipment/ cable/ fittings/ other materials etc supplied by the contractor.
Equipments installed or commissioned by others within the battery limit. This is for the purpose
of obtaining a comprehensive approval from competent authority.
The equipment offered and the installation shall be suitable for continuous operation under the
following site conditions:
7.0 Abbreviations
CP contractor shall entirely responsible for Co-ordination with other contractors & it should be
ensured that the CP work should be executed simultaneously with laying of pipeline. Contractor
shall mobilize necessary teams in each respective section as per the site organisation chart
(Annexure-C) enclosed with this tender with the key responsibility, education qualification,
designation, experience as defined and shall be responsible for the timely execution of CP work.
If the contractor fails to timely execution of the CP work, mobilization of teams as defined in
tender and it founds delay in the pipeline laying due to of CP work & poor co-ordination with
laying contractor necessary penalty clause shall be applied as per the direction of the Engineer-
in-Charge.
General
Contractor shall execute TCP work simultaneously in coordination with laying contractor when
lowering of the -pipeline is going on. Activities like- Cable to pipe connection, installation of ER
probe, Polarisation cell, Polarisation coupon etc should be completed before the backfilling of the
trench.
432 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Corrosion survey, design, detail engineering, fabrication, supply, installation, testing and
commissioning of the temporary cathodic protection system using Mg/ Zn galvanic anodes to
protect the external surface of 3LPE coated pipeline against corrosion for design life of minimum
2 years or till the commissioning of PCP system, whichever is later. The detailed length of
pipeline is as under-
Maintaining and keeping of PSP value as specified and monitoring at monthly basis of PSP
voltage & AC voltage of the temporary cathodic protection system (As per format Enclosed in
Annexure-B) till commissioning of the permanent cathodic protection system. All work shall be
carried out conforming to the Scope of work, Design Basis, Data Sheets, national & international
standard & as per standard specification No.- MEC/TS/05/E9/016A for temporary cathodic
protection system. Scope shall also include but not limited to the following for completion of
jobs:-
a) Temporary CP system shall be installed immediately of the any lowered section but not
later than 15 days from the time of lowering of pipeline segments. If TCP system is not
provided for any of the lowered section in the specified time, necessary deduction shall be
carried out from the contractor’s head as non-compliance of work. The deduction shall be
1000 rs per day per lowered section in each spread, example_ 1000x nos of days TCP
unprotected x lowered sections.
b) Measurement of soil resistivity along the right of way of the main pipeline (At 500mtr Interval) &
collection of soil & water samples along ROW at depth of 1M, 2M & 3M at every 5 km interval (Min
03 sample at each location) for its chemical & microbial analysis along the pipeline route as per
specification for corrosion survey MEC/TS/05/21/016C & NACE Standard TM0106-2006 for
detection of SRB, ARB, TDS, pH, Rx, Moisture & Total dissolved H2S etc. These sampled shall be
stored in sealed container and stored in the dark place.
c) Collection of additional data related to cathodic protection along the right of way of pipeline as per
standard specifications during the survey.
433 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
e) Total number of anode shall be calculated as per total anode weight requirement & total protection
current required.
f) Supply, Installation, Testing & commissioning of Test stations (Big Size & Normal Size) weather
proof (IP-55) as per specification & enclosed drawings. Selection of TLP size will be as per the nos.
of cables terminating at the station. TLP shall be sealed at both ends by means of foam
sealing/solid sealing. Termination plate inside the TLP should have high insulation level (FRP or
higher grade) to avoid drainage of CP current due to insulation leakage.
All the test-stations and junction boxes shall be provided with shrouded allen screws to avoid
vandalism
g) Supply, installation, testing & commissioning of Mg (Min 5.0 Kg)/ Zn Galvanic anodes/ Mg ribbon
anodes with backfill as per the standard specification- MEC/TS/05/E9/016A. The weight of the
Mg Anode & the total nos. of anodes shall be calculated as per the corrosion survey, soil chemical
analysis, total weight and current requirement of the pipeline section. However, Min one anode is
to be installed at every one KM with test station.
h) Supply, installation, testing and commissioning of 10kg Mg anodes at both side of River
crossings/ HDD, and Road/ Railway/ Nallah crossing (for casing pipe).
i) Cable to pipe connection by thermit welding/Pin brazing (for charged pipeline) for 35, 25, 10, 6
sq.mm copper cable including excavation and exposing piping, recoating with epoxy, testing etc.
j) Supply, laying of HDPE sheets (1200mm wide, 6mm thick) between the GAIL pipeline and
the other CP protected foreign pipelines at the crossing locations for providing electrical
isolation and discharge of the CP System current between the pipelines.
l) Supply, installation, testing & commissioning of one set of Explosion proof type spark gap arrestor
(100 kA@ 10/350 uS rating for lightning protection and 8/20 uS 100kA for surge protection) across
each insulating joint provided at dispatch terminal, receiving terminal, tap-off, SV & various
consumer terminals as per P&ID / specification.
All the monolithic insulating joints (MIJs) on the main line, on the tappings for the instruments viz.
pressure transmitter, densitometers etc. shall be provided with explosion proof surge divertors.
Note 1-Surge diverter cable needs to be terminated without any joints across the IJ. Surge diverter
with its pre‐wired connecting cables with suitable length & size should be provided and installed at
the Isolating joint.
m) CP AT CASED CROSSINGS
i) Casing shall be avoided as far as possible. If cased crossing is unavoidable, Bare casing is
always recommended with selecting higher thickness allowance as per API 1102.
ii) Any type of Casing filler conductive or insulating (wax/bentonite etc) shall not be filled
between annular space of casing and carrier.
iii) No sacrificial anodes (ribbon anodes) shall be used inside casing & carrier annular space.
434 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
n) Where high voltage (66 KV and above) transmission line runs in parallel or crosses the pipeline,
the pipeline shall be grounded through polarisation cells of suitable rating (solid state) & Grounding
(a continuous length of Zn Ribbon Anodes/Copper conductors with back fill material shall be laid
along the pipeline) shall be done at regular intervals of maximum 1 km where transmission lines
run parallel within 1km of the pipeline and have separation distance of 50 mtr on both side of the
pipeline.
The rating of the cell shall depend upon anticipated fault current & ground bed resistance at the
location of installation and the calculation of the same shall be furnished to MECON for review &
selection of rating of the Polarisation Cell. However, the rating of polarisation cell shall not be less
than 3.7 KA @ 30 Cycle & number of 20 kg net weight zinc anode shall not be less than two. Zn
Ribbon anode (Dia min. 12x14 mm with back fill in trench)/ pre-packed AC mitigator wire of
MATCOR make or equivalent also be used for the grounding purpose to get lower grounding
resistance (for soil resistivity higher than 25 Ohm-Cm) as per the direction of engineer in-charge.
The resistance of grounding shall be limited to 2-3 ohms max.
At any location of HT line crossing, zinc anodes (min 2 nos. & max 4 nos.) shall be provided to limit
the grounding resistance to 2-3 ohms max. If the same is not achieved, then Zn Ribbon anode (Dia
15mm with back fill trench) or Cu conductor with backfill shall be used for the grounding purpose.
Calculation for grounding resistance shall be submitted along with design document.
If any proposed additional line of voltage rating 66kV & above is envisaged during construction, the
same shall also be considered in the design document. Contractor shall supply polarization cell
along with necessary grounding system for the same.
If it is observed during the monthly monitoring that the source of the AC interference is due to the
HT lines less than 66kV or LT line, Contractor shall provide the grounding the pipeline through SSD
to lower impact of the AC interference on the pipeline.
o) Supply, installation, testing & commissioning of external electrical resistance Probe (02 nos. probe
with 1 no. ER probe reading instrument for each section) utilizing the electrical resistance
technique shall be provided along the pipeline at marshy / vulnerable locations to monitor the
external corrosion activity on the pipeline. Location of external ER probe shall be decided during
detail engineering.
Care shall be taken during installation of ER probes so that probe element is opposite to pipe (Not
facing the pipeline).
p) Supply, installation, testing & commissioning of Polarisation coupons (As per SOR & Min 1 at every
10 KM of pipeline) each having total area of 100mm x 100mm, one side exposed area of 25 mm x
25 mm with permanent reference cell shall be provided along the pipeline and at additional
vulnerable locations (River crossings, Marshy locations, Interference prone area, stray current
source locations, foreign pipeline crossings/parallel (at every KM in case of parallel), at CP
stations) to monitor the external corrosion activity on the pipeline as per enclosed standard
specification. Location of external Polarisation coupons & Number of magnetic devices for
operation of magnetic switch shall be decided during detail engineering in consultation with
GAIL/MECON.
Permanent Reference cell shall be manufactured & constructed in line with drawing no.
MEC/SD/05/E9/E/CP/1610 Rev-0.
435 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Care shall be taken during installation of polarization coupon so that bare face of polarisation
coupon is opposite to pipe & polarisation coupon shall not be installed between TLP & Pipeline.
The works related to collection of approximately 2-5 m of pipeline material (In pieces of 300 to
1000mm length) for fabrication of Polarisation coupons is in the scope of the Contractor.
i) Bonding of pipelines shall be carried out through bonding stations (variable resistance of
suitable value + shunt + diode, if required). Polarization coupons shall be installed at every test
station in the parallel section and at crossings.
ii) The Contractor shall supply and install bonding stations as provision to bond the pipelines. For
the new pipeline as a provision for interference mitigation Bonding Junction box (BJB) shall be
installed as a minimum at the following locations-
- Where the new pipeline runs parallel to the existing pipelines, at start and end of parallelism
and at every five (5) km intervals. As a minimum, all existing parallel pipelines laid with a
separation distance of 10 m shall be provided with bonding provision.
- Where the pipeline crosses or intersects the existing buried pipelines or buried section of
pipelines / Piping.
iii) BJB shall have provision to terminate 25/35 mm2 bonding cables and a 6 mm2 potential
monitoring cables connected to each foreign pipelines as well as new pipelines. BJB shall be
provided with appropriately rated shunts and resistors for each circuit. Rating of the resistors
shall be calculated based on the mitigation requirement.
r) Supplying, laying, termination, Glanding, ferruling & testing of all the cables of TCP system, Cu-
Conductor, XLPE insulated, PVC sheathed, Armd/Unrmd (1Cx6 mm2, 1Cx10 mm2, 1Cx25 mm2,
1Cx35mm2) as required.
s) Cable coming from 60 Mtr for Current measurement test stations (Type_B) & cables for foreign
pipeline crossing shall be provided with black sleeves for the identification purpose.
t) Calibration factor of similar thickness pipeline section shall be carried out by the Bidder at each
B_Type test stations by arranging separate power source. Bidder shall refer pipe book for the
same.
u) PSP Monitoring on monthly basis of the TCP system till commissioning of the permanent cathodic
protection system including the coupon OFF psp.
v) All civil/ structural & other miscellaneous works related to TCP system including supply of bricks,
cement & steel etc. required for completion of the system.
w) Coating Integrity test of HDD section of the pipeline shall be conducted immediately after the
completion of the HDD of each HDD section by separate temporary power source and anode bed.
436 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Bidder shall submit the procedure as per the NACE requirements for approval along with the
design document.
x) Disconnection of all the sacrificial anodes before PCP commissioning. After PCP commissioning
TCP may be reconnected, if required at some locations in the event of detection of localized areas
of inadequate protection (hot spot).This will be only as a temporary measure, till the permanent
measures are implemented by the Contractor to increase the CP potential level at hot spot areas.
Note-
i) Additional protection of carrier pipe (By Zn ribbon anodes) inside the bare casing is not
required.
ii) 10 kg Mg anodes shall be provided for protection of Casing pipe (external side) wherever
required.
iii) Connection scheme of CP system in TLP boxes shall be permanently fixed inside the test
station box (TLP Box).
Note-2:- Vendor list of Make of CP Materials is enclosed with the tender as appendix-I all CP
material shall be as per the make mentioned in the vendor list.
Note-4: - Localized soil resistivity at 1.5Mtr depth shall be considered for calculation of
number of Anodes.
Tentative bill of material of TCP shall be prepared by the successful contractor for each section as
per the approved design and the same shall be submitted with the detail engineering package for
review.
i) The job includes all civil works including supply of bricks, cements steel etc. connected with
grouting of equipment to be installed. The job includes repairing of all civil works damaged during
installation of electrical and other facilities.
ii) Preparation of buried cable trenches including excavation, back filling, compacting, providing of
brick protection by second-class bricks, spreading of fine river sand, including all supplies.
iii) CP contractor shall provide Colour code identification for the various CP System cables used in the
system with design document for approval.
iv) The scope of work under this contract shall be inclusive of breaking of walls and floors, and
chipping of concrete foundations necessary for the installation of equipment, materials, and making
good of the same. Minor modifications wherever required to be done in the owner free supplied
equipments or devices to enable cable entry, termination, etc.
437 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
v) Checking of all connections, i.e. power, control, earthing and testing and commissioning of all
equipment erected and/or connected under this contract as per testing procedures and instructions
of Engineer-in-Charge.
vi) Armour of the cables of MOV or other cables which creates leakage of the CP currents shall be cut
to prevent the leakage of CP current.
vii) All electrical equipments are to be doubly earthed by connecting two earth wires from the frame of
the equipment to be earth grid. The cable armours will be earthed thro’cable glands.
All non-current carrying metallic parts of electrical equipments such as lighting and power
panels, push button stations, cable trays etc.
viii) Supply and installation of all other accessories not specifically mentioned herein but nevertheless
necessary for completion of job.
ix) Engineering and preparation of specifications, data sheets, procedures and drawings etc required
for procurement & installation of CP System wherever applicable/required by Owner/ MECON and
submit to Owner/ MECON for approval/comments.
xi) Obtaining clearance for energising the complete electrical facilities covered under this tender and
approval of installation/drawings from Govt. authority if required.
xii) Test certificates, catalogues, vendor drawings, installation, operation and maintenance manuals for
all equipment/materials in contractor’s scope of supply.
xiii) All civil work related to the CP work is in scope of the CP contractor.
The entire work as per Scope of Work covered under this contract shall be treated as “Works
Contract”.
All works included in the scope of CP work will be done simultaneously with main pipeline
construction by main pipeline Contractor. Bidder will supply all the materials required for completing
the system and organise manpower & equipments accordingly to meet the requirement of Cathodic
Protection work in time as per completion schedule given in Volume - I.
Supply, testing, Packing, Forwarding, Delivery, Installation and commissioning of all the equipment
covered in this package are included in the scope of the contractor. No equipment will be free
issued by the owner to the contractor.
438 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
9.5.2 Contractor’s scope of supply shall be as mentioned in Cl. No. 9.1 & 9.3.
9.5.3 Bidder shall submit list of two year operational & maintenance spares along with offer.
O&M CP Spares/ Tool / Tackles for CP system like Multimeter, Clamp meter, Portable reference
cell, UT meter, Tool box Complete for each maintenance base etc.
All commissioning & start up spares are in bidder’s scope (Included in this package). Any
commissioning & startup spare consumed during the start up & commissioning is included in the
supply of this package, for which no extra payment is made.
1. Contractor to note that the exact cable routing shall be decided at site based on actual site
conditions. Exact cable quantities/sizes shall be based on actual measured route lengths at site by
Contractor in coordination with Engineer-in-Charge/Client. Contractor shall ensure that there is no
surplus or shortage of cables at site and procure cables accordingly.
2. Contractor to note that all cabling (including supply & laying) & other electrics for the CP System
shall be supplied along with the package and no separate payment shall be admissible for the
same. Owner shall provide only single point power supply for the same.
3. Job is lump-sump basis. Price breakup shall be submitted to the Engineer-In-Charger &
GAIL for approval for payment purpose for TCP work, however the work to be carried out &
material to be supplied for this project which is not covered under this contract the
payment shall be done as per unit price on submission of the back invoices documents &
GST bill.
The submission of application on behalf of the Owner to Govt. Authority/ Central Electricity
Authority/State authority/Private bodies, if required along with copies of required certificates
complete in all respects, shall be done by the contractor well ahead of time so that the actual
commissioning is not delayed for want of approval from respective authority. The actual inspection
of work by the above mentioned authority inspector shall be arranged by the Contractor and
necessary coordination and liaison work in this respect shall be the responsibility of the contractor.
However any fee paid to these Authorities in this regard shall be reimbursed by the Owner on
submission of bills with documentary evidence.
The Inspection and acceptance of the work as above shall not absolve the Contractor from any of
responsibilities under this contract.
The necessary permissions required for the bonding etc for the interference mitigation
(From SEB’s, Water works Departments/ Boards, Railways & Other pipeline owners) shall
be obtain before taking mitigation measures in the scope of contractor & the same will be
hand over to GAIL after commissioning of CP system.
439 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
All the equipment supplied by the contractor shall be inspected by the Owner/MECON and/or their
approved inspection agency (TPI) at the manufacturer’s works prior to despatch. The equipment
will be inspected as per the tests pre-identified in the approved QAP to ensure conformity of the
same with relevant approved drawings, data sheets, specifications, National/International
standards. The TPI shall be arranged by the CP contractor for the testing of the
material/equipments at the vendor works.
11.1 Performance tests of any equipments which cannot be conducted/demonstrated either partially
of wholly at the manufacturer’s work, shall be conducted after erection at site in the presence of
Owner & their inspection agency. In all the cases, prior approval of the approval shall be
obtained.
11.2 In case of waiver category of items, the same shall be pre identified. For such items, the
contractor shall furnish necessary certificates, test reports etc for Review/Approval to
Owner/Inspection agency. The issue of Inspection Certificate/Waiver Certificate for any
equipment or component there of does absolve the contractor from his contractual obligations
towards subsequent satisfactory performance of the equipment at site. Should any equipment
be found defective, In whole or part thereof after receipt at site or during erection/commissioning
and testing shall be Rectified/Changed by contractor free of cost.
11.3 Contractor shall submit test plan for the equipments with four week advance notice.
11.4 The following equipment/items shall be tested and inspected by MECON/ owner at manufacturer’s
works before dispatch. Test certificates duly signed by MECON/ Owner shall be issued by the
contractor as part of the final document.
12.1 The successful bidder shall submit detailed installation, site testing & commission procedure
with time schedules for Review/Approval to Owner/MECON.
12.2 The successful tenderer shall provide adequate supervisory/ skilled personnel and all tools and
tackles, testing equipment and instruments required for complete checking of installations and
testing and commissioning of all equipment and accessories.
12.3 All the tests shall be conducted in the presence of Owner/ MECON/Engineer-in/charge or his
authorized representative unless he waives this requirement in writing.
12.4 The testing and commissioning of all equipment under the scope of the bidder & shall be carried
out in accordance with the latest edition of relevant Indian Standards, International Standard
NACE standards and IE Rules.
12.5 Test reports shall be submitted in required number of copies duly signed by the Bidder to
MECON and OWNER.
440 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
12.6 On successful completion of erection of each item /equipment, a final inspection will be carried
out at site by Owner / MECON, for correctness and completeness of erection.
12.7 After the completion of all tests and rectification of all defects pointed out during final inspection,
start-up trials would be commenced. During the start-up trials contractor shall provide skilled /
unskilled personnel and supervision round the clock at his cost. The number and category of
workmen and duration up to which required, will be decided by the Engineer-in-charge. Any
defects noticed during the start-up trial relating to the equipment supplied and work carried out
by the Contractor, will be rectified by the contractor at his own cost.
12.8 Any work not conforming to the execution drawings, specifications or codes shall be rejected
forthwith and the contractor shall carry out the rectification at his own cost.
12.9 After the operating conditions are fully achieved for CP system and the other requirements as
stated in the General Conditions of Contract are fulfilled, the contractor would be eligible for
applying for a completion certificate.
13.1 The drawings accompanying the tender document are indicative of the nature of work and issued
for tendering purposes only. Construction shall be as per drawings/specifications issued/ approved
by the Owner/ MECON during the course of execution of work.
After the job completion, contractor shall prepare ‘AS-BUILT’ drawings, final certified as built
drawings vendor drawings for bought out equipments shall be submitted by the contractor to owner
in bound volume with one set of reproducible original sepia plus five sets of prints & one set to
MECON.
The equipments/ materials to be supplied by the contractor shall conform to the requirements of
the applicable standard specifications. Also the installation of various material/ equipment shall
also conform to the standard specification.
The purpose of the pipeline alignment drawings, P&IDs & Plot Plan drawings enclosed with the
tender is to enable the tenderer to make an offer in line with the requirements of the Owner.
These are indicative of the nature of work and issued for tendering purposes only. The bidders,
however, shall visit the site before bidding for proper information of site conditions. Construction
shall be as per drawings/ specifications issued/ approved by the Owner/ Consultant during the
course of execution of work and no additional payment shall be made for any changes made
and bidder shall supply the package at no additional cost and time to Owner.
A) SPECIFICATION
441 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
C) STANDARD DRAWINGS
The Contractor shall not recruit personnel of any category from among those who are already
employed by the other agencies working at the sites but shall make maximum use of local
442 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
No water and power will be provided by the owner. It should be the responsibilities of the contractor
to arrange water and power at his own cost.
Owner shall not provide any land for residential accommodation of contractor’s staff and labour.
Space for storage of material is included in contractor’s scope. Contractor shall be responsible for
safety and security of his equipment, supplied material, etc.
b) Time Schedule
The Completion Time Schedule for the work (including mobilization period) as given in VOL-I of in
all respect, from the date of issue of letter/Fax of Intent.
The Bidder is required to submit a Project Time Schedule in Bar Chart Form, along with the Bid.
The Schedule shall cover all aspects like sub-ordering, manufacturing and delivery, indicated in the
Bid Document. The Owner interface activities shall be clearly identified with their latest required
dates. Owner reserves the right to disqualify the Bidder if the above Schedule submitted by the
Bidder is not in line with the over all Project requirement.
The Bidders should describe their system of Project Scheduling and monitoring, the extent of
computerization, level of detailing, tracing methodology etc. with the name of computer package
and sample outputs.
The Contractor shall submit within 2 week of Fax of Intent, a sufficiently detailed over all Project
Schedule in the activity network form, clearly indicating the major milestones, interrelationship/
interdependence between various activities together with analysis of critical path and floats.
The network will be reviewed and approved by Engineer- in-Charge and the comments if any shall
be incorporated in the network before issuing the same for implementation. The network thus
finalised shall form part of the contract document and the same shall not be revised without the
prior permission from Engineer-in- Charge during the entire period of contract.
443 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
The contractor is required to submit within 2 week of award of WORK, the methodology of progress
measurement of sub-ordering, manufacturing/ delivery, sub- contracting construction and
commissioning works and the basis of computation of overall services/physical progress informed.
Owner reserves the right to modify the methodology in part or in full.
c) Functional Schedules
The contractor should prepare detailed functional schedules in line with network for functional
monitoring and control and submit scheduled progress covers for each function viz. ordering,
delivery and construction.
The Contractor shall present the programme and status at various review meetings as required.
Agenda : a) Weekly programme v/s actual achieved in the past week &
programme for next week.
b) Remedial Actions and hold up analysis.
c) Client query/ approval.
This report shall be submitted on a monthly basis within 10 (ten) calendar days from cut-off date,
as agreed upon covering overall scenarios of the work. The report shall include, but not limited to
the following:
444 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
B) Weekly Reports
The report will be prepared and submitted by the Contractor on weekly basis and will cover
following items :
C) Daily Repots
Successful bidder shall submit DPR (Daily progress report) & Monthly Monitoring Report to
the owner/MECON as per the format in Annexure-A & B.
15.5.1 CONTRACTOR shall make every effort to keep the OWNER adequately informed as to the
progress of the WORK throughout the CONTRACT period.
CONTRACTOR shall keep the OWNER informed well in advance of the construction schedule so
as to permit the OWNER to arrange for requisite inspection to be carried out in such a manner as
to minimize interference with progress of WORK. It is imperative that close coordination be
maintained with the OWNER during all phases of WORK.
15.5.2 By the 10th (tenth) of each month, CONTRACTOR shall furnish the OWNER a detailed report
covering the progress as of the last day of the previous month. These reports will indicate actual
and scheduled percentage of completion of construction as well as general comments of interest or
the progress of various phases of the WORK. The frequency of progress reporting by the
CONTRACTOR shall be weekly.
15.5.3 Once a week, CONTRACTOR shall submit a summary of the WORK accomplished during the
preceding week in form of percentage completion of the various phases of the WORK, to the
OWNER.
445 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
15.5.4 Progress reports shall be supplied by CONTRACTOR with documents such as chart, networks,
photographs, test certificate etc. Such progress reports shall be in the form and size as may be
required by the OWNER and shall be submitted in at least 3 (three) copies.
15.5.5 Contractor shall prepare daily progress report (DPR) in the desired format and submit it to
Engineer-in-charge alongwith schedule of next day to Engineer-in-charge.
16.0 CONSTRUCTION
OWNER reserves the right to inspect all phases of CONTRACTOR's operations to ensure
conformity to the SPECIFICATIONS. Owner will have Engineers, Inspectors or other duly
authorised representatives, made known to the CONTRCTOR present during progress of the
WORK and such representatives shall have free access to the WORK at all times. The presence
or absence of a OWNER's representative does not relieve the CONTRACTOR of the responsibility
for quality control in all phases of the WORK. In the event that any of the WORK being done by
the CONTRACTOR or any SUB-CONTRACTOR is found by OWNER's representatives to be
unsatisfactory or not in accordance with the DRAWINGS, procedures and SPECIFICATIONS, the
CONTRACTOR shall, upon verbal notice of such, revise the work in a manner to conform to the
relevant DRAWINGS, procedures and SPECIFICATIONS.
CONTRACTOR shall observe in addition to Codes specified in respective specification, all National
and Local Laws, Ordinances, Rules and Regulations and requirements pertaining to the WORK
and shall be responsible for extra costs arising from violations of the same.
16.2 Procedures
CONTRACTOR shall have at all times during the performance of the WORK, a Competent
Superintendent on the premises. Any instruction given to such superintendent shall be construed
as having been given to the CONTRACTOR.
The CONTRACTOR shall carry out required supervision and inspection as per quality
Assurance plan and furnish all assistance required by the OWNER in carrying out inspection work
during this phase. The OWNER will have engineers, inspectors or other authorised representatives
present who are to have free access to the WORK at all times. If an Owner’s representative notifies
the Contractor’s authorised representative not lower than a Foreman of any deficiency, or
recommends action regarding compliance with the SPECIFICATIONS, the CONTRACTOR shall
make every effort to carry out such instructions to complete the WORK conforming to the
SPECIFICATIONS and approved DRAWINGS in the fullest degree consistent with best industry
practice.
446 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
CONTRACTOR shall be solely responsible for making available for executing the work, all requisite
Construction Equipments, Special Aids, Cranes, Tools, Tackles and testing equipments and
appliances. Such construction equipments etc. shall be subject to examination by owner and
approval for the same being in first class operating condition. Any discrepancies pointed out by
OWNER shall be immediately got rectified, repaired or the equipment replaced altogether, by
CONTRACTOR. OWNER shall not in any way be responsible for providing any such equipment,
machinery, tools and tackles.
The OWNER reserves the right to rearrange such deployment depending upon the progress and
priority of work in various sections.
Tie-end between main line and starting point of terminal is included in the scope of contract, as and
when main line section is available for Tie-ins.
The order in which the WORK shall be carried out shall be subject to the approval of the
Engineer-in-charge and shall be so as to suit the detailed method of construction adopted by the
CONTRACTOR, as well as the agreed joint programme. The WORK shall be carried out in a
manner so as to enable the other contractors, if any, to work concurrently.
OWNER reserves right to fix up priorities which will be conveyed by Engineer-in-Charge and the
CONTRACTOR shall plan and execute work accordingly.
Existing Service
Drains, pipes, cables, overhead wires and similar services encountered in course of the works shall
be guarded from injury by the CONTRACTOR at his own cost, so that they may continue in full and
uninterrupted use to the satisfaction of the Owners thereof, or otherwise occupy any part of the
SITE in a manner likely to hinder the operation of such services.
Should any damage be done by the CONTRACTOR to any mains, pipes, cables or lines (whether
above or below ground etc.), whether or not shown on the drawings the CONTRACTOR must
make good or bear the cost of making good the same without delay to the satisfaction of the
Engineer-in-Charge.
17.0 DOCUMENTATION
17.1.1 The following documents shall be submitted along with the offer:
447 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
17.1.2 The following drawings (in three sets) & documents shall be submitted for approval within 3
weeks of award of contract.
17.1.3 After the job completion, contractor shall prepare AS-BUILT drawings/data sheets and
documents, submit catalogues/manuals (O&M) of major brought out items. Final certified as
built drawings, documents and manuals etc shall be submitted by the contractor to owner in
bound volume with one set in soft copy (CD) plus five sets of prints to owner & one set to
MECON..
Other drawings and documents shall be submitted by contractor along with AS-BUILT
Drawings/Datasheets-
An Appendix-I of approved vendors for various major items is enclosed with this tender
specification. The bidder shall consider such names only as indicated in the aforesaid list and
clearly indicate in the bid the name(s) as selected against these items. For any other item not
covered in the list enclosed with this tender document, prior approval shall be obtained by the
contractor for its make/ supplier’s name.
All inspections and tests shall be made as required by the specifications forming part of this
contract. Contractor shall advise Owner/ Consultant in writing at least 10 days in advance of the
date of final inspection/tests. Manufactures inspection or testing certificates for equipment and
448 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
20.0 ESCALATION
The Rates quoted shall be kept firm till completion of work and no price Escalation shall be paid.
a) Computerized R.A. Bill/ Manual Bill, with IT No./ ST No./ Labour License No. printed
thereon.
b) ESI/ EPF clearance certificates for the last month alongwith R.A. Bills.
c) Insurance Policy as per relevant clauses of Contract Agreement.
d) Attendance Register and Salary Records.
e) Photocopy of the measurement book to be attached with R.A. Bills.
f) Any other document required for the purpose of processing the bills.
g) Registration Certificate with Sales tax authorities of state concerned.
-x-x-x-
449 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
APPENDIX-I
Sheet 1 of 2
1) CABLES
i) Brooks Cables
ii) Nicco Corporation Ltd
iii) CMI Ltd
iv) Delton Cables Ltd
v) KEI Industries
vi) Torrent Cables
vii) Universal cables
viii) Victor Cables
ix) Associated Flexible & Wires Pvt Ltd
x) Asain Cables (RPG Cables)
xi) Fort Gloster (Gloster Cables Ltd)
xii) Finolex Cable
xiii) Rediant Cables
xiv) NETCO Cables Pvt Ltd
xv) Chandresh Cables Ltd
xvi) RR Kabel Ltd,Vadodara
i) Exprotecta, Beroda
ii) Baliga
iii) Flexpro
iv) FFLP Control Gears
v) Sterling
vi) Sudhir
3) SACRIICIAL ANODES
450 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
APPENDIX-I
Sheet 2 of 2
5) Permanent Reference Cell : M/s Borin Manufacturer USA, M/s MC Miller USA , M/s Corrtech
8) Surge diverter (Ex-d) : M/s Dhen, M/s OBO, M/s Corrpro system, USA, M/s Sohne
11) Solid state polaristation cell : M/s Dairyland, M/s Corrpro systems, USA
15) Heat Shrink Cap For Anode : M/s RAYCHEM, M/s MATCOR (USA)
To Cable Joint
16) MCCB/MCB for Power : Siemens, Indo Asian, L&T, Hager, Merlin Gerin
Distribution Board Schneider Electric, AEG, HAVELL’S, ABB, MDS
17) ER- PROBE (External Corrosion : M/s Rose Corrosion Services UK, M/s Metal Samples, USA M/s
Monitoring) Roharbak Cosasco, USA M/s Caproco, UK
17) ER- PROBE & Corrosion Coupon : M/s Rose Corrosion Services UK, M/s Metal Samples, USA
Assembly M/s Roharbak Cosasco, USA, M/s Caproco, UK
18) Proposed CP Contractor : M/s Corrtech (I) Pvt Ltd, Ahmedabad, M/s CCS (B) Pvt ltd,
M/s Raychem RPG Pvt ltd, M/s Consultech, Baroda, M/s
UNDTS, Noida, M/s SARK EPC Pvt Ltd, BSS Technologies
Corrosion Protection India Pvt Ltd, Thane
451 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Note-For any other brought out item(s) for which the vendor list is not provided in the tender , bidders can supply
those item(s) from vendors/ suppliers who have earlier supplied similar item(s) for the intended services in earlier
Oil and Gas projects and the item(s) offered is in their regular manufacturing/ supply range subject to submission
of following documents and their approval.
1) The vendor / supplier should not be in the Holiday list of GAIL/ MECON / other PSU
2) The bidder is not required to enclose documentary evidences (PO copies, Inspection Certificate etc.)
along with their offer, however in case of successful bidder, these documents shall required to be
submitted by them within 30 days from date of Placement of Order for approval to GAIL/ MECON.
Appendix-II
Sheet 1 of 1
Note-Price of these spares shall deemed to be considered in the total price of supply of CP system
quoted by the Bidder.
452 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Annexure-A
Format for Daily Progress report
DAILY PROGRESS REPORT – TCP SYSTEM
PROJECT: PLACE:
PROGRESS (Spreads A, B……)
S.No. ACTIVITY UOM SCOPE Remarks
PREVIOUS TODAY CUMULATIVE
Soil Resistivity &
1
Chemical Analysis
Additional Data
2
Collection
TCP design
3
Document
4 P/L LENGTH KM
5 P/L LOWERED KM
6 TCP PROVIDED KM
7 PSP LEVEL (-V)
S.No. Material Work Description
1 Test station Nos.
2 Mg anode Nos.
3 Zn anode Nos.
4 Zn Ribbon Anode Mtr.
5 No. of Thermit Nos.
5(a) No. of Pin Brazing Nos.
5 Surge Diverter Nos.
6 ER Probe Nos.
Polarisation
7 Nos.
Coupon
8 Polarisation Cell Nos.
9 Cased crossings Loc
10 TCP Cables
1Cx6 mm² Mtr.
10(a)
Armoured
1Cx6 mm² Un- Mtr.
10(b)
Armoured
10(c) 1Cx10 mm² Mtr.
Annexure -B
454 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Annexure-C
Organogram for the TCP work
PROJECT OFFICE
Name:
Address:
Ph No:
E-Mail:
OVERALL PROJECT
INCHARGE
Note-
1. Overall Project In charge should have B.E. in (Electrical, Electronics and Metallurgical Engineering)
& atleast 10 year Experience in the Cathodic Protection Field.
2. Spread In-charge should have B.E. or Diploma in (Electrical, Electronics and Metallurgical
Engineering) & at least 5 year Experience in the Cathodic Protection Field and shall be available at
site office for entire time schedule of the project.
455 of 896
OIL & GAS SBU SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
Annexure-AA
Compliance to Technical Bid (CP System)
-X-X-X-
456 of 896
CONTRACTOR CLIENT: M/S GAIL (India) LTD.
QUALITY ASSURANCE PLAN
FOR PROJECT: Srikakulam – Angul Pipeline
ELECTRICAL EQUIPMENT Project (Part-B)
ORDER NO. & DATE PACKAGE NO. 23VA
SUB-CONTRACTOR PACKAGE NAME TCP system
ORDER NO. & DATE
INSTRUCTIONS FOR FILLING UP : CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS:
1. QAP shall be submitted for each of the equipment separately with break up Code Description Code Description Code Description DOCUMENTS:
of assembly/sub-assembly & part/component or for group of equipment
having same specification. 1. Visual 12. Routine test as per relevant IS 23. Short time rating D1. Approved GA drawings
2. Use numerical codes as indicated for extent of inspection & tests and 2. Dimensional other standard 24. Operational & functional D2. Approved single line/
submission of test certificates & documents. Additional codes & description 3. Fitment & Alignment 13. Type test as per relevant IS/ check schematic diagram
for extent of inspection & tests may be added as applicable for the plant and 4. Physical Test (Sample) other standard 25. Over Speed Test D3. Approved
equipment 5. Chemical Test (Sample)
3. Separate identification number with quantity for equipment shall be (Review of test report only) 14. Impulse Test 26. Flame Proof Test data sheet
indicated wherever equipment having same specifications belonging to 6. Ultrasonic Test 15. Partial Discharge Test 27. Clearance and creepage D4. Approved bill of materials
different facilities are grouped together. 7. Magnetic Particle Test (MPT) 16. Heat run risc test\tempr. Distance D5. Unpriced P.O. copy
4. Weight in tonnes (T) must be indicated under column 5 for each item. 8. Radiography Test 17. Enclosure Protection Test 28. Acceptance Test D6. Calibration Certificate
Estimated weights may be indicated wherever actual weights are not 9. Dye Penetration Test 18. Calibration 29. Material test of all measuring
available. instruments and gauges
ABBREVIATIONS USED : 10. Measurement of IR Value 19. Noise & Vibration 30. Coating Thickness (MMO Anode), Resistivity (MMO
a) Before HV Test 20. Test certificates for bought out Anode) & comsumption rate (For Mg, Zn & Zn Ribbon
CONTR : CONTRACTOR b) After HV Test components Anode only review of Test report)
11. High Voltage test/Dielectric 21. Tank Pressure Test / Pressure 31. Contact Resistance anode to cable Joint
MFR : MANUFACTURER test Test 32. Destructive testing
22. Paint shade verification & 33. Test Station Connection Scheme check, Name plate
Thichness check and terminal check
34. Chemical Composition & Open Circuit Potential (For Zn
Ribbon Anode, Review of Test report only)
EQUIPMENT DETAILS INSPECTION AND TESTS Test Certificates Acceptance REMARKS /
Sl. Description (With equipment Indentificatuin Quantity Manufacturer’s Expected schedule of Raw Material and inprocess stage Final Inspection/Test by & documents to Criteria SAMPLING
No. heading, place of use, and No. Name and Address Final Inspection inspection be submitted to Standards /IS/ PLAN
Breif Specifications) No/M T MFR CONTR/ MECON/ MFR CONTR/ MECON/ MECON BS/ASME/
TPIA GAIL TPIA GAIL Norms and
Documents
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1. CP Cables (1Cx6Sqmm, Meters 1,2,28 - - 1,2,28 1,2,28 R D1, D2, D3, D4, I.S., Approved
1Cx10 Sqmm, 1Cx25Sqmm D5, D6, 20, 13 Data Sheet &
& 1Cx35Sqmm) Specifications
2. Test Stations (Big & Small Nos. 1,2,3,4,22 - - 1,2,3,4, 1,2,3,4, R D1, D2, D3, D4, I.S., Approved
Type) , 29 22,33 22,33 D5, D6, 20, 13 Data Sheet &
Specifications
3. Sacrificial Mg & Zn Anodes Nos. 1,2,5 - - 1,2,4, 5, 1,2,4, 5, R D1, D2, D3, D4, I.S., Approved * on 1%
30, 32* 30, 32* D5, D6, 20, 13 Data Sheet &
Specifications of total
nos. of
anodes
457 of 896
4. Spark Gap Arrestor (100 Nos. - - - - RW R Manufacturer Approved Data
kA) test certificates Sheet &
& Compliance Specifications
Report
6. External ER Probe & Probe Set 1,2,3,5, - - 1,2,3,5, 1,2,3,5, R D1, D3, D4, D5, Approved Data *on one no.
reader 13,29 13*,17*, 13*,17*, D6, 20,12,13 Sheet & of each
21*,24, 21*,24, Specifications
type
29 29
7. CTSU (Computerised Test Nos. 1,2,3 - - 1,2,3, 1,2,3, R D1, D3, D4, D5, Approved Data
Station Unit) & CTSU 22,24,33 22,24,33 D6, 20,12,13 Sheet &
Reader Specifications
9. Mg/Zinc Ribbon Anode Mtr - - - 1,2,30,34 1,2,30,34 R D1, D3, D4, D5, Approved Data
D6, 20,12,13 Sheet &
Specifications
R: Mecon shall issue Inspection Waiver certificate based on TPIA’s Inspection documents , which shall be uploaded by Contractaor in MECON IMS portal for
waiver. Q.A.P. NO.
RW : TPIA shall review MTC & Compliance reports & issued IRN & Inspection Reports. MEC/05/E9/23VA/ QAP/082
REV. 0
For Manufacturer For CONTR For MECON SHEET 2 OF 2
(Stamp & Signature) (Stamp & Signature) (Stamp & Signature)
458 of 896
Annexure-II
to
Particular Job Specification
(CORROSION MONITORING SYSTEM WORKS)
459 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL
PIPELINE PROJECT (PART-B)
GAIL (India) Ltd
MECON LTD, DELHI
TABLE OF CONTENT
460 of 896
JOB SPECIFICATION
FOR
CORROSION MONITORING SYSTEM
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
461 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
CONTENT
1.0 INTRODUCTION
2.0 SCOPE
3.0 SPECIFICATION
7.0 GAURANTEE
13.0 DOCUMENTATION
Rev Description PREPARED BY: CHECKED BY: APPROVED BY: ISSUE DATE :
0 Issued For Tender (Aashish Moyal) (MK Jaiswara) (A.Bhowmic) ISSUE DATE: Nov 2021
462 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
1.0 INTRODUCTION
GAIL (India) Limited a public sector under Petroleum ministry, intends to develop Natural
Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh) to Angul (Odisha)
Natural Gas Pipeline Project and its Spurlines in the state of Odisha and Andhra Pradesh for industrial
consumers as well as City Gas Distribution System (CGD).
This pipeline will connect various RLNG terminals like, Dhamra, Dahej, Ennore,
Gangavaram, FSRU etc. and domestic gas fields of K G basin, Off-shore/On-shore fields to the
customers in Eastern region through JHBDPL and Southern region through KSPL. Therefore, it
will provide connectivity to multiple sources to the en-route customers. In view of the same it has
strategic importance and part of National Gas Grid.
M/s MECON Ltd has been engaged by M/s GAIL (India) Limited to carry out design, engineering,
procurement, inspection & Project Management Consultancy Services required for 18”/12” NB x 322
Kms. (approx.) pipeline (Part-B of SAPL Pipeline) from IP-4cum DT (of SAPL Part-A) at Ch 0.00km to
Receiving Terminal at Utkal Alumina (Ch 190.8km), SV-6S cum DT at Ch 158.4km to RT at Vedanta
(Ch 68.3km) and .SV-7S cum DT at Ch 178.4km to RT at Nalco (Ch 62.97km).
This document presents brief scope of work for ICMS system for internal corrosion monitoring of the
pipeline. It indicates minimum requirements for detailed design of ICMS system and equipment.
1.1 Standards
1.1.1 The equipment/material shall be in conformity with this specifications, data sheet and code of
practices of the relevant Bureau of India Standards, IEC & NACE publications. In case of any
conflict, the stipulations under this specification/data sheet shall govern.
OISD STD: 188 (2000) Corrosion Monitoring Of Offshore & Onshore Pipelines
463 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
PNGRB Guideline’s
The equipment offered and the installation shall be suitable for continuous operation under
the following site conditions.
2.0 SCOPE
2.1.1 Submission of design package, drawings, QAP (Quality assurance plan), data sheets,
specification, equipment selection criteria, calculations & manuals for approval, various work
procedures. Preparation of site engineering drawings, procedures and details for installation works
wherever applicable or required by the Engineer-in-charge, and submits to the Engineer-in-charge
for review and approval.
2.1.2 Correction, updating and submission of all Owner’s drawings for as-built status.
Refer P&IDs (Enclosed with Vol-IV of Bid Document) for the location of the ER Probe & Corrosion
Coupons.
Location/ Fluid Pressu Description of
Location Temp. Thickness
Line No. Flow re CMS
M3/Hr bar (g) °C mm
a. Corrosion
RT at Utkal Alumina Probe
b. Corrosion
Transmitter
Refer Refer Refer
RT at Vedanta Refer P&ID c. Receiver
P&ID P&ID P&ID Refer P&ID
(Corrosion
Meter)
RT at Nalco d. Corrosion
Coupon
464 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
Note: The above data is indicative only. The contractor shall get the necessary data from the
Owner/MECON before placing the order to the manufacturer of CMS system.
The thickness of pipes mentioned in the above columns are tentative & the bidder shall
confirm the thickness of the pipe from MECON where the installation of CMS system take
place before the designing of the length & size of the ER probes, coupons & its fittings etc.
Corrosion coupon & Probes shall be installed at 6 O’Clock position, Spacing & Width,
Length & Depth of pit shall be ensured accordingly for ease of retrieval of Coupons &
Probes.
Minimum separation distance between Corrosion Coupon & ER Probe shall be 1.5 times the
pipeline diameter on which it is installed.
Following electrical equipment and material are in the contractor’s scope of supply in this tender.
Supply, testing, Packing, Forwarding, Delivery, Installation and commissioning of all the equipment
covered in this package are included in the scope of the contractor. No equipment will be free
issued by the owner to the contractor.
Design, detail engineering, FAT, supply of all materials, preservation at site/storage at site,
fabrication, assembly, erection, installation, testing, commissioning, guarantee, performance
evaluation/test at site with all safety & Personnel protective equipments (PPEs), trained personnel
for installation, supervision & commissioning of corrosion monitoring system, submission of first
trial/commissioning reports and engineering drawings and obtaining approval from GAIL / MECON
for Corrosion Monitoring System as per system description, drawing, specification, standards etc
enclosed with the tender document and as per direction of Engineer-in-charge.
The ER probes and coupons shall be installed at suitable position on the pipeline as decided
during the detail engineering.
Construction of Pit as per Civil drawings (issued during detailed engineering) by GAIL/MECON
shall be in scope of Bidder.
O&M Spares/ Tools/ Tackles for CMS system is in the contractors scope of supply.
List of O&M spares/ Tools/ Tackles is enclosed with appendix-I, shall be supplied at GAIL’s
designated store as decided during detailed engineering.
All commissioning & start up spares are in bidder’s scope (Included in this package). Any
commissioning & start up spare consumed during the start up & commissioning is included in the
supply of this package, for which no extra payment shall be made.
465 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
The scope of supply shall consist as minimum requirement of the following components:
i) All the CMS items for SAPL Part-B project, shall be supplied, installed, tested & commissioned by
successful bidder of Section-II, as per SOR.
The Bidder shall be entirely responsible for Co-ordination with respective Laying Bidders & it
should be ensured that all works related to CMS systems should be timely executed.
ER Probes shall be high-pressure retrievable type, flush mounted, body in SS316 with element of
carbon steel for installation with high-pressure hollow plug access fitting assembly. The probe shall
be suitable for measurement of corrosion rate in the range of 0-10 mpy. The probe element shall
be same as carbon steel of pipeline or API5L Grade B material and element thickness of 20 mils
minimum.
Probe length is to be decided by the vendor as the pipe size varies from location to location.
Note- Thickness mentioned in SCOPE/ SOR is for bidding purpose only, Optimization of
thickness of probe to be done to get higher sensitivity of measurement, Vendor shall
furnish all design calculations for approval for selecting the size of probe. Accordingly the
suitable thickness probe shall be supplied.
Panel Mounted Transmitters -The transmitter shall be panel mounted. The transmitter shall have
valid intrinsically safety certificate from authorized certifying agency for use in Hazardous area as
specified in design basis.
Type – 2 wire
IP-66
Input- ER probe
Output- 4-20 mA
Cable lead- 5’ for ER probe connection and as required for connection to receiver (corrosion meter
in control room).
Power Supply-24 VDC from receiver unit
Mounting-At site near probe by bracket/ yoke support
-Intrinsically safe for Hazardous area specified in area classification
-With safety barrier between transmitter and receiver.
466 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
The access fitting shall be of flare weld Access Fitting Assembly (non-tee), body carbon steel, and
acme thread outlet with hollow-plug assembly in AISI-316 along with heavy duty protective C.S.
cover complete with essential spares. Rating 6000 psi and suitable up to design temperature of -
29 to 65 deg C.
The access fitting should have rust free design and less chances of damage of threads (thread
protection shall also be provided) and should be designed as per the operational & other data
collected in site visit.
All the offered Access fittings should be compatible for insertion of ER Probe/Corrosion Coupon
made by other manufacturers.
a) Corrosion Coupon: The corrosion coupons shall be mild Steel flush disc coupons 1.25”
dia. x 1/8” thickness with one mounting hole of ID 0.312”- The corrosion coupon shall be
made of same pipeline material or API5L Grade B material. The corrosion coupon would be
replaced in every 90 days, after exposure to the fluid in the pipeline.
b) Coupon Holder: Installation locations as mentioned above. The coupon holder shall be
retrievable type made of SS 316.
c) Access Fitting Assembly for Corrosion Coupons –Total Quantity As per SOR.
The access fitting shall be of flare weld Access Fitting Assembly (non-tee), body carbon steel, and
acme thread outlet with solid plug assembly in AISI-316, along with heavy duty protective C.S.
cover complete with essential spares. Rating 6000 psi and suitable up to design temperature of -
29 to 65 deg C.
The access fitting should have rust free design and less chances of damage of threads (thread
protection shall also be provided) and should be designed as per the operational & other data
collected in site visit.
All the offered Access fittings should be compatible for insertion of ER Probe / Corrosion Coupon
made by other manufacturers.
iv) RECEIVER (CORROSION METER): Total Quantity: As per SOR, for ER probes, for locations
connected to UPS (Uninterrupted Power Supply)
the single length cable for the Data Acquisition & Transmission). -Owner will provide
220V AC/24V DC power supply for this unit (Bidder must confirm first from the
MECON, before the submission of offer which type of power supply is
available for the operation of the receiver). The unit shall be suitable to provide
24VDC supply for powering the transmitter is 4-20 mA loop through the two wire
cable.
- The unit shall receive 4-20 mA signal proportional to corrosion rate in mils per year
(MPY) from the transmitter through the same two-wire cable and provide digital
display of corrosion rate through the same two-wire cable. 4-20 mA signals shall
also be available from the transmitter-receiver (corrosion meter) for interfacing with
DCS/SCADA.
- Have feature to download all logged data in disk/ Memory drives.
- The receiver (corrosion meter) shall have valid intrinsically safe certificate from
authorized certifying agency.
The receiver unit (Display unit for CMS system) shall be installed inside the pipeline control
room all the cables, software’s & hardware’s for communication b/w transmitter (installed
outside) are in the scope of vendor. All the required signals of CMS shall be interfaced with
station SCADA / PLC system with serial communication (ModBus RTU protocol) is in the
scope of the vendor including cables, software’s & hardware’s.
Complete with repair and seal kit for ER probes & coupon holders – Rating: 6000 psi. The retriever
shall be manufactured from stainless steel and should have chromium plating for resistance to
mechanical / corrosion damage at high pressure. Retriever, shall works on a pressure-balanced
principle i.e. sudden released of pressure from the system, the retriever will not telescope.
Service valve kit, complete with blanking plug, extension lever, and brass hammer, spare face-to-
access fitting O-ring, heavy duty field service box, essential repair & seal kit.
Retriever & service valve kit shall be designed for operation on all locations for ER probe and
coupons.
Bidder will carry out hydro-test, at Manufacturer’s works prior to dispatch, on all supplied service
valve and retriever tools at 9000psi for duration of min. 30 minutes and above. & the same shall be
witnessed by GAIL/MECON/TPIA.
vii) Access fitting assembly for ER Probes & Coupons, Retriever tool & Service Valve Hydrotest
Certification:
Bidder will carry out hydro-test, at Manufacturer’s works prior to dispatch, on all supplied Access
fitting assembly, service valve and retriever tools at 9000psi for duration of min. 30 minutes and
above. & the same shall be witnessed by GAIL/MECON/TPIA.
468 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
All ER Probes must be supplied with minimum 5 meters length Cable for Connecting to Hand Held
Data Logger/Transmitter/Off line data logger. The Cable must have the required connectors for
connecting the ER Probe at one end & Hand Held Data Logger/Transmitter/Off line data logger at
the other end.
It is must that the designed access fittings, coupons & Probe holders can be used with probes of
other manufacture’s as mentioned in the vendor list. Interchangeability must be guaranteed w.r.t.
Probe & Coupon holders, Probes, Coupons and access fittings.
Similarly it should be applicable to service valves, online retrieval kit, corrosion data logger, online
corrosion meters and hand held meters.
x) TRAINING
Successful bidder will provide classroom training as well as field training to the GAIL’s personnel
for at least of 3 Man days at site i.e. Maintenance base of M/s GAIL. The training will broadly
consist of operation of ICMS system, its working, insertion / re-insertion of Corrosion Coupons/ER
Probes/LPR Probes on the Access Fittings, Collection of corrosion related data, data analysis &
assessment, learning & operation of all software’s and hardware’s provided. The trainer will have
vast experience in corrosion monitoring field and corrosion data analysis and preferably from the
supplier of the ICMS system. The quoted prices are deemed to be inclusive of such charges for
training.
xi) All CMS equipment shall be supplied from the List of Preferred makes. In the interest of
standardization, the Employer reserves the right of selecting particular manufacturer of
CMS items and materials and the Bidder shall supply equipment and materials of the
particular make, if so required.
3.0 SPECIFICATION
Technical Requirements
The electrical resistance (ER) probes and corrosion coupons to be installed at the location as
mentioned above shall be retrievable from the line under the operating pressure and temperature.
The ER probes & coupons shall be flush mounted on the pipeline at suitable position. All the
materials in contact with fluid shall be in accordance with NACE Standard MR-0175. Pipeline inlet
pressure may vary according to pipeline pressure drop due to different flow rate, the corrosion
monitoring system shall be suitable for operation under this fluctuating pressure conditions.
4.1 All the equipment supplied by the contractor shall be inspected by the Owner and/or their
inspection agency at the manufacturer’s works prior to despatch. The equipment will be
inspected as per the tests pre-identified in the approved QAP to ensure conformity of the
same with relevant approved drawings, data sheets, specifications, National/International
standards.
469 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
Vendor shall carry out performance test of CMS system after completion of the installation
& commissioning. The PG test to be demonstrated to Client / Client’s representative to
ensure the correctness of the installed system. If the system performance fails during PG
test the whole system will be rejected and all equipments installed shall be either re-
designed/modified is in the scope of the vendor.
Performance tests of any equipment which cannot be conducted/ demonstrated either partially of
wholly at the manufacturer’s work, shall be conducted after erection at site in the presence of
Owner & their inspection agency. In all the cases, prior approval of the approval shall be obtained.
4.3 In case of waiver category of items, the same shall be pre identified. For such items, the contractor
shall furnish necessary certificates, test reports etc for Review/Approval to Owner/Inspection
agency. The issue of Inspection Certificate/Waiver Certificate for any equipment or component
there of does not absolve the contractor from his contractual obligations towards subsequent
satisfactory performance of the equipment at site. Should any equipment be found defective, In
whole or part thereof after receipt at site or during erection/commissioning and testing shall be
Rectified/Changed by contractor free of cost.
4.4 In case of waiver category of items, the manufacturer shall carry out stage wise inspection and
testing as per relevant standard codes and service requirements of the specification, for all items
of his work prior to shipment. The Manufacturer/contractor shall submit stage wise inspection
documents for review/Approval to the Owner/MECON. Manufacturer’s third party inspector’s test
certificates for finished items in printed format must be sent with the despatch paper of all supply
items.
4.5 Contractor shall submit test plan for the equipments with four week advance notice.
5.1 All items shall be painted and marked as per manufacturer’s standard before shipment. All items
shall be properly packed and protected to avoid damage during shipment. The manufacturer shall
ensure insurance during shipment. If any equipment found defective, In whole or part thereof after
receipt at site or during shipment/erection/commissioning and testing shall be
rectified/changed/supplied by contractor free of cost.
470 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
Supply of Two years O&M spares for CMS systems as per Annexure-II is in bidder’s scope.
Price of 2 years O&M spares (as mentioned in Annexure-II of this document) are inclusive of prices
quoted by the Bidder in the bid.
All commissioning & start up spares are in bidder’s scope (Included in this package). Any
commissioning & startup spare consumed during the startup & commissioning, is included in the
supply of this package, for which no extra payment shall be made.
7.0 GUARANTEE
7.1 The contractor shall guarantee the installation against any defects of workmanship and materials
(supplied by the contractor) for a period of 12 months after successful commissioning at site. Any
damage or defects connected with the erection of materials, equipments, fittings, meters supplied
by the contractor that may be undiscovered at the time of issue of the completion certificate, or
may arise or come to light thereafter, shall be rectified or replaced by the contractor at his own
expense as deemed necessary and as per the instruction of the Engineer-in-charge within the time
limit specified by Engineer-in-charge.
7.2 The above guarantee shall be applicable for the quality of work executed as well as for the
equipment/ cable/ fittings/meters/software’s/hardware’s other materials etc supplied by the
contractor.
i) The job includes all civil works including supply of bricks, cements steel etc. connected with
grouting of equipment to be installed. The job includes repairing of all civil works damaged during
installation of electrical and other facilities.
ii) The job includes any mechanical works including supply of material, pipe, welding etc. required for
completeness of job. The job includes modification in existing pipeline required for completeness
of job. The job also includes repairing of all civil works damaged during installation of CMS system
and other facilities.
iii) Preparation of buried cable trenches including excavation, back filling, compacting, providing of
brick protection by second-class bricks, spreading of fine river sand, including all supplies.
iv) The scope of work under this contract shall be inclusive of breaking of walls and floors, and
chipping of concrete foundations necessary for the installation of equipment, materials, and
making good of the same. Minor modifications wherever required to be done in the owner free
supplied equipments or devices to enable cable entry, termination, etc.
v) Checking of all connections, i.e. power, control, earthing and testing and commissioning of all
equipment erected and/or connected under this contract as per testing procedures and instructions
of Engineer-in-Charge.
471 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
vi) Supply and installation of all other accessories not specifically mentioned herein but nevertheless
necessary for completion of job.
vii) Engineering and preparation of specifications, data sheets, procedures and drawings etc required
for procurement & installation of CMS System wherever applicable/required by Owner/ MECON
and submit to Owner/ MECON for approval/comments.
viii) Correction and submission of all owners’ drawings for as-built status.
ix) Obtaining clearance for energising the complete electrical facilities covered under this tender and
approval of installation/drawings from Govt. authority if required.
x) Test certificates, catalogues, vendor drawings, installation, operation and maintenance manuals
for all equipment/materials in contractor’s scope of supply.
xi) All civil work & Mechanical work related to the CMS work is in scope of contractor.
Hydrocarbon handling areas have been generally classified as zone 1 & 2, gas group IIA/IIB as per
IS: 5572, API RP-500, OISD - 113 and IP Rules. All equipments to be installed in these areas shall
be suitable for the area classification with temperature class T3 (200˚C), CMRI testing and
approved by CCOE, DGFAS and having BIS license.
a) The electrical resistance (ER) probes and corrosion coupons to be installed at the location as
mentioned above shall be retrievable from the line under the operating pressure and temperature.
The ER probes & coupons shall be mounted on the pipeline at suitable position. All the materials in
contact with fluid shall be in accordance with NACE Standard MR-0175. Pipeline inlet pressure
may vary according to pipeline pressure drop due to different flow rate, the corrosion monitoring
system shall be suitable for operation under this fluctuating pressure conditions.
b) Various works covered under this contract like equipment erection, welding, mechanical work, civil
work, cabling and grounding works etc shall be performed in accordance with applicable
specifications / standard practice.
c) The equipments/materials to be supplied by the contractor shall conform to the requirements of the
applicable specifications enclosed in the tender document.
d) Price of erection & commissioning spares and special tools shall be included in the quoted price by
the bidder.
e) The above location & no of ER probes, corrosion coupons, Transmitters & Receivers, Service
valve kit, Access Fitting Assembly for probe & coupon, Retriever Kit etc is indicative (Only for
tender purpose), actual no. of these equipments & their location may changed according to site
condition/in detail engineering, Contractor shall provided these changed no. of quantities as per
unit price quoted in SOR.
472 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
Suggested vendor list for CMS system enclosed with this specification. (See annexure-I)
Bidder will supply and install all necessary software’s and hardware’s required for operation, data
collection, data storage & downloading to Personal computers from hand held meters and should
have features of data analysis, historical data storage & review, report generation etc.
All the software’s will be provided in CD’s with valid key and 02 user licences (Installed 02 nos. of
Personal Computers) and have free updates for future.
The same is inclusive of prices quoted by the Bidder in the bid, for which no extra payment shall
be made.
13.0 DOCUMENTATION
13.1.1 The following documents shall be submitted along with the offer:
13.1.2 The following drawings (in three sets) & documents shall be submitted for approval within 3
weeks of award of contract.
14.1 Contractor shall submit drawings and data sheet as enumerated in this specification of the
equipments / materials to be supplied.
473 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
14.2 After the job completion, contractor shall prepare AS-BUILT drawings and documents, submit
catalogues/manuals (O&M), datasheets, test certificates of major brought out items like
Transmitter & receiver, Service valve kit, Retriever service valve, Access fittings, service valve kit
etc of CMS system. Final certified as built drawings, documents and manuals etc shall be
submitted by the contractor to owner in bound volume with one set in soft copy (CD) plus five sets
of prints & One set to MECON.
Annexure-I
The corrosion monitoring items shall be procured from one of the following manufactures:
All the components including spares shall be purchased from a single manufacturer.
1) M/s TD williamson
2) M/s Posco/Bhotika
Note: For procuring bought out items from vendors other than those listed above, the same may be
acceptable subject to the following-
a) The vendor of bought out item(s) should be manufacturer of said item(s) for intended
services and the sizes being offered is in their regular manufacturing range.
b) The vendor/supplier should not be in the holiday list of GAIL/MECON/ Other PSU.
The successful bidder should submit documentary evidence past track record of vendor (PTR) i.e.
detailed PO/WO copies with Schedule of Rates, Inspection Certificates, Completion certificate &
performance certificate issued by End User / Owner etc for approval.
474 of 896
SRIKAKULAM - ANGUL
OIL & GAS SBU PIPELINE PROJECT
(PART-B)
MECON LTD, DELHI
Annexure-II
-x-x-x-
475 of 896
Form No.11.20 (4.4) F-10
1. QAP shall be submitted for each of the equipment separately with break up Code Description Code Description Code Description DOCUMENTS:
of assembly/sub-assembly & part/component or for group of equipment
having same specification. 1. Visual 12. Routine Test as per relevant IS/other standards D1. Approved GA drawings &
2. Use numerical codes as indicated for extent of inspection & tests and 2. Dimensional 13. Type Test as per relevant IS/other standards Part Indentification No.
submission of test certificates & documents. Additional codes & description 28. Acceptance Test as per relevant IS/other standards D2. Approved single line/
for extent of inspection & tests may be added as applicable for the plant and 3. Fitment & Alignment schematic diagram
equipment 4. Physical Test D3. Approved
3. Separate identification number with quantity for equipment shall be 5. Part Identification data sheet
indicated wherever equipment having same specifications belonging to 6. Tagging & Marking D4. Approved bill of materials
different facilities are grouped together. 7. Pressure Test
4. Weight in tonnes (T) must be indicated under column 5 for each item. 8. Assemble of component
Estimated weights may be indicated wherever actual weights are not 9. Installation Check at workshop on sample D5. Unpriced P.O. copy
available. 10. Raw Material Test Cerificate D6. Calibration Certificate
ABBREVIATIONS USED : 11. Functional test for corrosion meter (Transmitter & receiver) instruments and gauges
12. Welding of all measuring
CONTR : CONTRACTOR 13. Hydrostatic test (@9000psi for 30 minutes)
MFR : MANUFACTURER 14. Packing
TPIA : THIRD PARTY INSPCETION AGENCY 15. Hardenss test
16. MOC
EQUIPMENT DETAILS INSPECTION AND TESTS Test Acceptance Criteria REMARKS /
Sl. Description (With equipment Indentificatuin Quantity Manufacturer’s Expected Raw Material and inprocess stage inspection Final Inspection/Test by Certificates & Standards /IS/ SAMPLING
No. heading, place of use, and No. No/M T Name and schedule of MFR CONTR/ MECON/ MFR CONTR/TPIA MECON/ documents to BS/ASME/ Norms PLAN
Breif Specifications) Address Final Inspection TPIA GAIL GAIL be submitted to and Documents
MECON /
GAIL
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
IWC Set 1,2,5,6, 10,13 - - 1,2,5,6, 10,13 1,2,5,6, 10,13 R D1, D3, D4,D5, Tech. Specification, 13-TPIA SHALL
ER PROBE, ACCESS (1 only),14,16 (1 nly),14,16 (1 only),14,16 D6, 10, 13,16 Approved Drawings WITNESS@9000P
SI AT MFR works
1 FITTING ASSEMBLY FOR & Data Sheets before dispatch-
ER PROBES For Access Fitting
Assembly only
IWC Set 1,2,5,6,8,9,11,1 - - 1,2,5,6,8,9,11,1 1,2,5,6,8,9,11,1 R Tech. Specification,
2 TRANSMITTER & 4 4 4 Approved Drawings
RECEIVER & Data Sheets
CORROSION COUPONS, IWC Set 1,2,5,6, 10,13 - - 1,2,5,6, 10,13 1,2,5,6, 10,13 R D1, D5, D6, 10, Tech. Specification, 13-TPIA SHALL
COUPON HOLDER, (1 only),14,16 (1 only),14,16 (1 only),14,16 12 Approved Drawings WITNESS@9000PSI
AT MFR works before
3 ACCESS FITTING & Data Sheets dispatch-For Access
ASSEMBLY FOR Fitting Assembly only
CORROSION COUPONS
IWC Set 1,2,5,6, - - 1,2,5,6, 1,2,5,6, R D1, D5, D6, 10, Tech. Specification, 13-TPIA SHALL
10,13,14,16 10,13,14,16 10,13,14,16 12,13 Approved Drawings WITNESS@9000PSI
RETRIEVER KIT, SERVICE AT MFR works before
4 & Data Sheets
VALVE KIT dispatch-For
Retreiever Tool &
Service Valve
IWC Mtr 1,2,28 - - 1,2,28 1,2,28 R D3, D4, D5, I.S., Approved Data
5 SIGNAL CABLE D6, 20, 13,12 Sheet &
Specifications
PG (Performance Gaurantee Perform Witness
6
test)
R: Mecon shall issue Inspection Waiver certificate based on TPIA’s Inspection documents , which shall be uploaded by Contractaor in MECON IMS
portal for waiver. Q.A.P. NO.
MEC/05/E9/ 23VA/ QAP/CMS/001
For Manufacturer For CONTR For MECON 476 of 896
REV. 0
(Stamp & Signature) (Stamp & Signature) (Stamp & Signature) SHEET 1 OF 1
Annexure-III
to
Particular Job Specification
(CIVIL WORKS)
477 of 896
SCOPE OF WORK
FOR
CIVIL WORKS
(CIVIL SECTION)
MECON LIMITED
(A Govt. of India Undertaking)
478 of 896
I) GENERAL
M/s GAIL has awarded M/s MECON Limited project management consultancy (PMC)
services for Angul-Srikakulam pipeline. The brief scope of work for Part- B, broadly
consist of Laying, Testing and Commissioning of 18”NB x 48 Kms (approx) and 12”NB
x 274 Kms (approx) pipeline in the state of Odisha & Andhra Pradesh including all
associated works for transportation of Natural Gas (dry)/ R-LNG.
M/s MECON Ltd has been engaged by M/s GAIL to carry out design, engineering,
procurement, inspection & Project Management Consultancy Services required
transportation and distribution of Natural Gas.
The scope of work to be performed under this contract shall include complete civil
works as per plans, equipment layout, drawings & technical specifications.
The contractor shall maintain proper record of all the materials/equipment procured
with respect to their source & specifications with details of their manufacturing and
recycled content etc. and submits along with all supporting documents/
photographs to Client & PMC for record purpose.
The complete work has been divided into 04 (FOUR) Sections. Terminal / Stations
of various sections of the pipeline are as under:
SECTION-I:
DT at Tap-off from IP-04 of SAPL Part-A (Control Room & Guard Room Only)
SV-01S
IP-01S
SECTION-II:
SV-02S
SV-03S
SV-04S
SV-04SA
SV-05S
SV-06S cum Tap Off for Vedanta P/L
SV-07S cum Tap Off for Nalco P/L
RT Utkal Alumina
SECTION-III:
SV-01V
SV-02V
SV-03V
RT VEDANTA
479 of 896
SECTION-IV:
SV-01N
SV-02N
SV-03N
RT NALCO
NOTE:-
Contractor shall procure & supply to site all the materials including cement,
reinforcing steel, steel sections/plates other masonry materials, admixtures &
bonding agents, sealants, sand, etc. and any other construction material / item
required to complete the civil works.
(All enabling works e.g. construction water tank, fabrication yard, electricity, site
stores & office, safety and security measures, coordination with other contractors
working at site etc. shall be Contractor’s responsibility.
Special permits to such as ‘Hot Permit”, “Fire Safety Permit” to work at project site,
if required, shall be contractor’s responsibility.)
The scope of work shall be broadly, but not limited to, the following:
480 of 896
Remote SV stations, 40 m x 40 m for Manual SV Stations and 80m x 80m
for IP Stations, SV cum Tap-off Stations & RT’s as per requirement.
c) Construction of RCC framed Boundary Wall at an interval of 3.0 m or as
specified of height 2.4 m with infill brickwork, PCC Coping, MS Y Angle
Posts and Concertina coil with RBT fencing etc as per drawing.
d) Construction of RCC Framed Control room for Remote SV Stations, IP
Stations and Receiving Terminals.
e) Construction of Porta Cabin foundations for Guard Room and PCP Room
at SV Stations, IP Stations and other room/building as required.
f) RCC cable trenches: complete civil works for cable trench including
providing inserts, conduits (GI, PVC or HDPE etc.) and MS chequred
cover plate/ Pre cast concrete covers as per requirement.
g) Construction of Septic Tank along with Soak Pit and its connections.
h) Storm water drainage system in brick drains with complete civil works as
per requirement.
i) Interlocking / Grass jointed paver block of 60 mm thickness from
approved make over sand cushion over ground / on a PCC base at
locations as specified.
j) PCC Kerbstone of size 125 mm x 300 mm over 75 thick PCC base as
specified.
k) 150 mm thick RCC pavement for process area (Type-I) and construction of
external/internal RCC Roads.
l) Independent RCC foundations for pipe supports, Equipment, Crossovers
foundations etc.
m) Construction of Valve Pit in brick masonry (if required) and valve support
foundations in RCC for SV Stations.
n) Grouting of all base plates/frames of equipment foundations and structural
bases.
o) Construction of Bore well and Hand Pump as per specifications.
p) Earth filling in embankments for external roads wherever required with
provision of RCC Culverts/ Pipe Culvert.
q) Construction of approach road with embankments.
r) Boring and installing cast in situ skin friction/end bearing pile of 500
diameter of 30T capacity, if required as per recommendations in geo-
technical reports.
s) Provision of all inserts, conduits, pre-cast covers, fixing of free issue
items into permanent works etc.
t) Water body bank and bed stabilization as per requirement.
u) Clearing all construction debris and handing over completed work site.
v) Any other work not specifically mentioned but required to make the
terminal & pipeline functional.
481 of 896
w) Marking as-built details/drawings on one set of construction drawings and
return to owner.
x) Photographs during various stages of construction for documentary
evidence.
Civil works shall be carried out for the scope of work listed as above. Bidder
shall understand the scope of work by visiting the work site in advance at his
own expenses if required and required to complete all the civil works as per
specifications, SOR, drawings and as directed by Engineer-in-charge.
All enabling works e.g. provision of site office for Contractor’s personnel,
temporary roads & drains, storage facilities for cement, steel & other
materials, provision of lights, survey work, workshop etc. which are required
for efficient working and timely completion of works.
Testing laboratory at site which is required for carrying out routine tests of
Workmanship as part of Quality Assurance.
Site leveling & micro-leveling after dismantling of all temporary works.
Submission of all original test certificates & records of testing, all warranties,
performance guarantees in favour of GAIL.
Any other works which may be necessary for completion of Construction and
associated works.
1.0 GENERAL
This preamble to the schedule of items is an integral part of the schedule and
shall have as much force as though this is incorporated into the description of
the items themselves.
Contractor's rate for any items of work in the schedule of items shall, unless
otherwise stated, be held to include the cost of all materials, including wastages,
conveyance and delivery, unloading, storing, fabrication, hoisting, all labour for
finishing to required shape and size, tools and plants, power, fuel, consumables,
all taxes royalties, other revenue expenses, temporary facilities like roads, drains
etc., providing temporary storage facilities for cement, steel and other materials
and their subsequent dismantling, scaffolding and other temporary works, setting
out, fitting and fixing in position, site drainage, dewatering, offering samples for
approval, cost of all tests, rectification of all defects, replacement of defective
materials and work, interruptions to work required to accommodate the work of
other agencies working on the site, continuation of work beyond working hour, in
482 of 896
the night and holidays also if situation warrants so, site clearance on completion,
maintenance work during the period of maintenance, bye-work necessary to
complete any particular item of work as per specification and direction of the E-
I/C, overheads, profit and other incidental charges.
2.1 GENERAL
2.1.1 Setting out works, profiles etc. with reference pillars and their removal after
completion of work.
2.1.2 Taking levels and reference axes wherever necessary from reference lines and
bench mark, both for the original ground level as well as for the finished Work as
directed.
2.1.3 Unless otherwise specified site clearance such as clearing of shrubs, green
brush wood, under-growth and small trees not exceeding 30 cm. in girth at one
meter above ground including uprooting stacking the serviceable materials
within any lead and removal of all the rubbish unserviceable materials up to 1
Km lead.
2.1.4 Working in dry, wet and foul condition.
2.1.5 No distinction of rate between the work done manually or mechanically.
2.1.6 Dewatering, wherever necessary.
2.1.7 Costs of all tests necessary and/or directed for the compaction of the filling/back
filling of site leveling works.
3.1.1 Planking and strutting to retain the excavated sides and to protect the adjoining
structures and services including removing the same.
3.1.2 Dewatering of accumulated water from any source till completion of all work
below ground level including provision of surface drains, catchment pits, etc.,
wherever necessary.
3.1.3 Providing adequate protection for safety of labour, materials, adjoining property,
services, structures and equipment and install barriers around the excavation
area, foundation, trenches, pits and red lights during night time, engage night
watchman for safety against risk or accident.
3.1.4 Stacking the excavated materials within the specified leads.
3.1.5 Forming (or leaving) suitable steps on the sides or/and providing adequate and
stable side slopes in case of deep foundation or soft, loose or slushy soil and
removal of steps after measurements.
483 of 896
3.1.6 Removing slips or falls in excavations.
3.1.7 Dressing and trimming to required level, profile and gradient.
3.1.8 Excavation to desired gradients in case of trenches.
3.1.9 Extra excavation beyond drawing/specification for necessary working space, for
safety requirements and other allied works including back filling and compacting
the same.
3.1.10 Removal of the surplus excavated earth, to the specified location as directed
and leveling the same.
3.1.11 Filling with cement concrete (with stone aggregate) and well rammed in position,
all excavation taken down below the proper levels due to carelessness of the
Contractor.
3.1.12 Sprinkling of sand and water over final bed and ramming the same before laying
soling and concrete.
3.1.13 Filling/Back filling with excavated earth or from spoil heaps shall include the
excavation/re-excavation from such sources all /re-handling and removing un-
wanted materials from the soil.
3.1.14 Compacting, leveling, watering, trimming to levels, profiles and gradient as per
drawing, specification and/or as directed.
3.1.15 Cost of all tests, as specified and/or as directed for the filling/back filling works.
3.2.1 Location for disposal of surplus excavated materials will be decided at site
during execution so as to avoid re-handling.
3.2.2 All kinds of soil shall mean ordinary, hard soil and soft/decomposed rock
(including laterite) as per classification of soil mentioned in the Tech. Speci-
fication excepting hard rock to be paid under separate Item.
The rate of the respective item shall also include, but not limited to the following
as described hereinafter in different Sub-Heads.
4.1 CONCRETE
4.1.1 Setting out all works from reference axes and bench marks.
4.1.2 Cleaning, washing and screening of aggregates whenever necessary.
4.1.3 Dewatering of all foundations and areas during concreting.
4.1.4 Cement slurry/cement mortar slurry at construction joints and cold joints.
4.1.5 Provision of Building paper and bearing plaster at bearing of slabs resting over
walls.
484 of 896
4.1.6 All the appropriate provisions as stipulated in the specification of concrete
chapter for materials, Design Mix, Preparatory works/surface preparation for
concreting, facilities for checking, batching, mixing, transportation, placing and
compaction of concrete, requirements in special cases of concreting, appropriate
finishes to exposed surface, curing by appropriate means, all types of testing
including hydraulic testing for Reservoirs, water tank etc. as directed.
4.1.7 Provision of construction joint (water bar excludes) and surface preparation of
construction joint and cold joint, before placement of concrete.
4.1.8 Provision of chases, holes/openings as per drawing and grouting with cement
mortar as directed.
4.1.9 Cleaning all anchor holes and keeping them, covered.
4.1.10 Protection of the structures/premises, foundations till final handing over and
keeping the premises, basement, etc. dry.
4.1.11 The hacking or roughening the exposed surface to receive plaster or where it is
to be joined with brick masonry wall.
4.1.12 Providing moulding, throating, drip course, etc. unless mentioned otherwise in
Schedule of Item.
4.2 REINFORCEMENT
a) Earth Work in excavation including back filling and disposal of surplus earth.
b) Providing shuttering and strutting of all types.
c) RCC M25 as per drawing & specification along with reinforcement (supply of
cement, coarse aggregate, fine aggregate, reinforcement bars), reinforcement
bending, placement, binding/ welding all inclusive & testing of concrete and other
materials.
d) Providing and laying 150 mm thick reinforced cement concrete of (M-25 grade)
with 20mm and down grade crushed stone aggregate in pavement, including
preparation of base (i.e. compacted sub grade, supply and laying 200 thick sand
and 100 thick PCC M-10).
e) Providing pockets if necessary, making recesses, trenches with precast covers/
gratings, fixing inserts, conduit pipes (GI, PVC, HDPE, etc.) laying in alternate
panels, filling the gaps between the panels with bitumen sand mix etc.
f) Provision of chequered plates into permanent works as per SOR item of
Structural works.
485 of 896
g) Making slopes, finishing edges, leaving bars for pedestals & sleepers including
providing sand fill isolation.
h) Providing and fixing reinforcing steel (in one / two layers), curing, chipping and
modification works etc. as specified in any shape, thickness, position and
finishing the top surface smooth as per requirement etc. all complete as per
drawings, specifications and directions of the Engineer-in-charge.
i) Actual work shall be carried out as per certified construction drawings to be
issued to successful tenderer.
Note: Payment shall be made as per net area in SQM as laid at site.
Autoclaved Aerated Concrete (AAC) is a light weight cellular material which is formed
by a chemical reaction between fine grained calcareous and siliceous materials.
Calcareous materials include lime and/or cement whereas siliceous materials generally
used are natural or ground sand and/or industrial by products such as slag and
Pulverized Fuel Ash (PFA). The cellular structure which gives the product good thermal
properties and a high strength density ratio is produced by reaction between alkaline
lime/OPC component and added aluminum powder (foaming agent) to give bubbles of
hydrogen. The curing of this type of concrete is done at high temperature and pressure
in saturated steam (autoclaving).
AAC blocks are used in solid and cavity wall construction, partitions, panel walls, inner
leaf of cavity wall or a backing to brick masonry.
PROPERTIES VALUES
Relevant IS Standards:
486 of 896
BIS - 6041 - 1985: Construction of Autoclaved Aerated Concrete Block Masonry.
BIS - 6441 - 1972: Methods of Test for Autoclaved Cellular Concrete Product.
The blocks shall be stored on the site on a level ground and to be protected against rain
fall and snow fall. .
Polymer modified adhesive shall be used for laying of blocks with adhesive tensile
strength not less than 0.34Mpa as per ASTM C1660.The thickness of mortar bed is
around 2-3mm as per suppliers specification.
These blocks shall not be soaked prior to laying in the wall. Only slight wetting is
required.
The laying of block may be started either at the corners first or it may be started from
one end and proceed to the other direction. The first course of the cellular block
masonry shall be laid with greater care, making sure that it is properly aligned, leveled
and plumbed, as this may assist the mason in laying succeeding courses to obtain a
straight and truly vertical wall.
The design of wall should be such that cutting of blocks is minimized when leaving
space for door and windows.
Design of AAC block masonry is based on the same parameters as that of brick
masonry, as Indian Standard BIS: 1905 (masonry code) applicable to brick masonry is
also applicable with the same provisions to AAC block masonry. Therefore slenderness
ratio of AAC masonry walls shall be as per guide lines of Indian Standard for masonry
walls.
5.7 CHASES
Guide lines for chases is masonry walls as per Indian Standard BIS:1905 need to be
followed. The cutting of chases, recesses etc. should be done with out damage to the
surrounding masonry. It is desirable to use such tools for cutting which depend upon
rotary motion not on heavy impact for cutting action.
487 of 896
5.8 FIXTURES IN AAC:
To avoid Cracks in walls at the corner of doors and windows frames at lintel level or sill
level, it is desirable to provide nominal reinforced concrete bond beam at sill and lintel
level and vertical reinforced concrete stud at either side of vertical members of door &
windows frames which may provide additional anchorage for the holdfast.
Provision of nominal bond beams serves the means of crack control for AAC masonry
work. Nominal bond beam shall be built in the same manner as the structural bond
beam with a minimum reinforcement of two 8mm diameter mild steel bars. In walls
without openings they shall be placed 1200mm apart. In walls with opening it shall be
provided at sill and lintel level.
The laying of block may be started either at the corners first or it may be started from
one end and proceed to the other direction.
The first course of the cellular block masonry shall be laid with great care, making sure
that it is properly aligned, leveled and plumbed, as this may assist the mason in laying
succeeding courses to obtain a straight and truly vertical wall.
The exposed wall shall be inspected closely every year before monsoon and cracks if
any shall be sealed properly with a non-shrink cement grout and painted with two coats
of cement paint.
Complete works for the making and proper functioning of soak pit and septic tank is
included in the scope:
488 of 896
Note:
Soak pit and septic tank shall be provided inclusive of all related works, as per
approved detailed drawings to be issued to the successful tenderer. Offer to be
prepared by the tenderer based on the enclosed drawings and on lump sum
unit rate (per installation)
The rate of the respective items shall be for the complete finished work and shall also
include, but not limited to the following bye works/activities all complete at all levels and
locations and as per specification and as directed by the E-I/C.
489 of 896
SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
DESIGN BASIS
FOR
3 STAGE QUALITY ASSURANCE PLAN
CIVIL SECTION
MECON LIMITED
DELHI - 110 092
490 of 896
Table of Contents
1.0 Introduction
2.0 General Guidelines for Quality Construction
3.0 Stages of Quality Assurance Plan
3.1 Stage-1
3.2 Stage-2
3.3 Stage-3
491 of 896
1.0 INTRODUCTION:
The brief scope of work for Part- B, broadly consist of Laying, Testing and Commissioning of 18”NB x
48 Kms (approx) and 12”NB x 274 Kms (approx) pipeline in the state of Odisha & Andhra Pradesh
including all associated works for transportation of Natural Gas (dry)/ R-LNG.
M/s MECON Ltd has been engaged by M/s GAIL(India) Limited to carry out Design, Engineering,
procurement, inspection & Project Management Consultancy Services required for laying of above
mentioned Mainline Pipelines along with associated facilities.
The scope of work to be performed under this contract shall include complete civil works as per
SOR, technical specifications and drawings.
The basic execution of the civil woks shall be governed by the norms and requirements as per
relevant IS Codes of Practice.
Quality Control QC
Like most other aspects of construction management, Quality control has to be planned. Planning
seeks 'order' and a quality control system for a construction project reflects this sense of order. It
may be seen to be in three basic stages:
Quality Assurance QA
Quality assurance is a mechanism for ensuring that the construction process takes place within the
framework of a quality management system. This suggests that quality assurance defines the
tasks and duties for implementing quality management.
In general, the following guidelines shall be adhered to for achieving Quality Control and Quality
Assurance:
1. Making sure that a set of documents viz. Drawings and Specifications are available at site.
2. Always carrying one small measuring tape, a notebook and pen / pencil at site.
3. Daily reaching site few minutes early to the start of actual construction activities.
492 of 896
4. Making yourself available at site during the closing hour and spend few more time after the
workers have called it a day.
5. Ensuring the availability of construction water and power at site.
6. Checking of layout of whole complex and that of a particular unit before start of actual work.
7. Establishing of permanent benchmark & checking of levels at all important stages of
construction.
8. Special attentions to ensure safety norms are followed at site.
9. Every evening identifying the areas where next day work needs to be carried out.
10. Ensuring proper arrangement of curing is made and personnel identified to do the job.
11. Every morning checking that work / curing envisaged the previous evening is being / has
been carried out.
12. Regularly checking the availability of construction materials and making sure that
availability of material is regular.
13. Checking adequate storage space and making arrangement for proper storage of
materials, cement in particular.
14. Ensuring the incoming materials has been tested for the intended strength and quality.
Accepting the materials only if found OK on physical inspection subject to final approval
based upon lab test as required as per specification.
15. Ensuring that all activities carried out as per specification and established work schedule.
16. Checking of all measurements / dimensions of the various structural elements as per
drawing before executing the works.
17. Maintenance of all the records in a proper way.
18. Sum up all the activities at site during the day in the form of a daily progress report which
shall be forwarded to MECON at the end of the day/next day morning.
19. Always keeping client informed about the site developments by maintaining proper
channels of communication.
20. Be cheerful, sportive and supportive.
3.1 STAGE-1: Quality Assurance and Control Mechanism for Construction materials
• The Contractor shall propose details of all the Construction materials along with their
source of procurement.
• The source of procurement of all the Construction materials shall have to be got
approved by Engineer-in-charge.
• All the Construction materials shall have to be got approved by Engineer-in-charge after
testing as per the Annexure-1 and 2 of Site Quality Plan (Appendix-1) to be witnessed
by Engineer-in-charge as per Inspection Test Plan.
• All rejected Construction materials shall be identified by Engineer-in-charge and
removed immediately from Site by the Contractor and a joint record in this regard shall
be maintained.
3.2 STAGE-2: Quality of Construction, Job procedure and Test Plan to be adopted
493 of 896
• The Contractor shall carry out regular Quality checks by inspection/testing during job
execution and prepare checklists for various Construction activities as per the
Annexure-3 and 4 of Site Quality Plan (Appendix-1) which shall be witnessed by
Engineer-in-charge.
• The same shall have to be got approved by Engineer-in-charge.
• The Contractor shall execute all the routine construction activities as specified in
Technical Specifications. Job Procedures may, however, be submitted for specialized
activities which shall be got approved by Engineer-in-charge.
• The Contractor shall prepare Inspection Test Plans as per the format given in
Annexure-4. The same shall be approved by Engineer-in-charge.
• The Contractor shall carry out recording of workmanship/finish details as per the
Annexure- 4 of Site Quality Plan (Appendix-1) which shall be witnessed by Engineer-
in-charge.
• The same shall be approved by Engineer-in-charge.
• In case of any deficiency in Quality, the same shall be redone / rectified to the
satisfaction of Engineer-in-charge without any additional cost.
494 of 896
APPENDIX-1
th
MECON LIMITED
13 FLOOR, SCOPE MINAR, NORTH TOWER
LAXMI NAGAR, DISTRICT CENTRE,
DELHI-110 092
495 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
A: MATERIALS
1.0 COARSE AGGREGATE
1.1 Specific To be done once per Labora Weigh IS:2386 Package These tests will be
Gravity, source or once for each tory balance, Part III, Contractor carried out while
Density, Voids mix design Test Oven, Jar IS:456, establishing design mix.
IS:383
1.2 Sieve Analysis One sample per 200 M3 Field Sieve set & IS:2386 As per L-04 -do- Mandatory Site Test/OR
(or part thereof) or change Labora weigh Part I, requirement of RMC Manufacturer’s
of source whichever is tory balance IS:383 design mix Report for batch test is
earlier. Test within the limits acceptable.
specified in
relevant IS
Codes.
1.3 Deleterious To be done once per Lab Balance IS:2386 -do- Test will be carried out
Chemicals source Test Sieve & Part II, while establishing mix
Container IS:383 design
(for
acceptanc
e limits)
1.4 Soundness To be done once per -do- Sieve IS:2386 -do- Test will be carried out
source Scales & Part V, while establishing mix
Drying IS:383 design
496 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
Oven (for
acceptanc
e limits)
1.5 Acid & Alkali To be done once per Lab Weigh IS:2386 -do- Test will be carried out
Reactivity source Test balance Part VII, while establishing mix
IS:383 design
1.6 Flakiness To be done once per -do- - IS:2386 -do- -do-
source Part-I,
IS : 383
1.7 Bulk Density To be done once per Oven, Jar & IS:2386 -do- -do-
source or once for each Weigh
mix design balance
2.0 FINE AGGREGATE ( TO BE USED FOR CONCRETE)
2.1 Bulkage One sample for pour Routin Oven, Jar IS : 2386 -do- Mandatory Site Test.
3
Moisture greater than 50 m e and weigh Part-III, IS Volume of sand and
Measu balance : 383 weight of water shall be
rement adjusted as bulkage &
moisture contents.
2.2 Sieve Analysis One sample per 200 m3 Routin Sieve Set, IS : 2386 As per L – 03 -do- Mandatory Site Test.
(or part thereof) or change e Weigh Part-I, IS : requirement of
of source whichever is balance 383 design mix
earlier. within the limits
497 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
specified in
relevant IS
Codes
2.3 Particle Size To be done once per Routin -do- IS : 2386 Particle size -do- To be carried out during
and Shape source and to be repeated e Part-I, IS : shall be mix design.
if source is changed 383 maximum 4.75
mm. Grading
shall be within
the limits of
grading zone –
III for concrete
work and for
mortar and
grout within the
limits of grading
zone III & IV.
2.4 Deleterious -do- -do- Balance, IS : 2386 -do- To be carried out during
Chemicals sieve & Part-II, mix design.
Container IS : 383
498 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
2.5 Soundness -do- -do- Sieve, IS : 2386 - -do- To be carried out during
Scales & Part-V, IS mix design.
Drying : 383 ( for
Oven acceptanc
e limit)
2.6 Acid and Alkali To be done once per -do- Weigh IS : 2386 - -do- To be carried out during
Reactivity source and to be repeated Balance Part-VII, mix design.
if source is changed IS : 383
2.7 Specific To be done once per Measu Weigh IS : 2386 These tests will be
Gravity, source or once for each rement Balance Part-III carried out while
Density, Voids mix design establishing design mix.
2.8 Check Silt and Every 50M3 (or part Measu Jar & Oven IS : 2386 Deleterious - Mandatory Site Test
Clay Content thereof) rement Part-II, IS material not to
: 383 exceed 5%
3.0 CEMENT
3.1 Fineness For each consignment of Labora IS : 4031, Manufactur Manufacturer’s
100T (or part thereof). tory IS : 269, er/ OR certificate to be
Test IS : 1489, Package furnished.
IS : 456 Contractor
499 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
500 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
4.2 Crushing One set of 6 cubes of 150 Measu Compressi IS : 516, Shall be as per Package Three specimens shall
Strength cm. Size per 35 Cum. of rement on Test IS : 1199, IS: 456 Contractor be tested at 7 days and
concrete or part thereof Machine IS : 456 remaining at 28 days.
for each grade of concrete and Mandatory Site Test.
per 8 hours of work or Client’s
portion thereof. specificati
on
4.3 Water Cement At random at the time of Measu Visual As per Package
Ratio batching rement observation approved Contractor
design
mix
5.0 WATER
5.1 Tests for Once for each source of -do- Lab Test IS : 3026 Package During mix design stage
ascertaining supply and Soil Contractor
limits of solid investigati
on record.
5.2 Test of pH -do- -do- PH meter IS : 456 PH value shall Site log -do-
value be less than 6. book
6.0 BRICK
501 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
6.1 Compressive For designation 100, Compr Compressi IS: 1077 As per brick Mandatory Site Test
Strength Every 50,000 or part essive on Testing designation.
thereof. strengt Machine
For designation up to 75, h
Every 100,000 or part
thereof.
6.2 Shape, Size, -do- Visual IS: 3495 Mandatory Site Test
Colour &
measu
rement
for
size.
502 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
6.3 Water One test for each source Lab IS: 3495 Water Lab Test Report shall be
absorption and of manufacturer and every Test absorption: a) submitted by the
efflorescence lot of 200,000. after 24 hours contractor.
not less than
20% by weight
b) after 6 hours
not less than
10% by weight.
c) moderate
degree of
efflorescence
7.0 REINFORCEMENT STEEL
7.1 Tensile (A). Every 20T or every Measu Universal IS : 1608 Manufactur Manufacturer test
Strength consignment purchased rement Testing IS : 2062 er/OR certificate must be
by Package Contractor Machine IS : 1786 Package submitted
Contractor
(B). For procurement of Copy of Manufacturer’s
quantity less than 20T Test Certificate &
------- Certificate No. to be
mentioned in the
invoice.
7.2 Bend Strength -do- -do- IS: 1599 -do- -do-
503 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
504 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
505 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
Width of the
stack shall not
be more than 3
meters
8.2 Reinforcement 100% Visual IS: 4082 Open storage.
Storage Bars of
different
classification
, sizes and
length will
be stacked
separately.
506 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
507 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
508 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 1 MATERIAL TESTS FOR SITES
SL. Component/ Sampling plan with Type Instru- Refer- Acceptance Format Testing Remarks
No Operation basis of ment ence Norm of agency
and check docu- Record
Description ment
of test
509 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 2 TESTING EQIPMENT FOR SITES
1.0 ROUTINE TEST 1.1 Concrete Cube mould Concrete Cubes - IS : 10086 Yes
LAB EQUIPMENT ( 150x150x150) mm
1.2 Compressive strength Concrete Cube Test Crushing strength of cube IS : 2505 Yes
Testing machine
1.3 Concrete slump cone Workability Check Drop in cone height of IS : 7320 Yes
concrete
1.4 Coarse aggregate sieves Sieve analysis Sieving IS : 383 Yes
1.5 Soil Core cutter To test compaction of soil Core cut out of soil and IS : 2720 Yes
density measured
1.6 Fine aggregate sieves Sieve analysis Sieving IS : 383 Yes
2.0 DIMENSIONAL & 2.1 Total Station Levelling, Distance, Angular Measurement and Yes
ALLIED Measurements, Coordinates recording
MEASURING 2.2 Theodolite & levelling Levelling and centre line Measurement and - Yes
EQUIPMENT staff marking and verticality recording
measurement
2.3 Measuring Tape Dimension - - Yes
2.4 Laser Beam apparatus Verticality of structures Centre line alignment - Optional
3.0 PROCESS 3.1 Oven Material Drying for moisture Material to be kept for - Yes
CONTROL control specific duration
ACCESSORIES 3.2 Physical balance Weighing - - Yes
510 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
511 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
2 Concreting (a) Check quality and size of coarse aggregate with special reference to
Works undersize/oversize materials, disintegrated/self materials, earth and
other foreign materials beyond limit, organic impurities.
(b) Silt content, bulkage, foreign materials in sand and verify test report
for fineness modulus.
(c) Check formwork.
(d) Line, level of concrete.
(e) Honeycombed surface in concrete.
(f) Strength of Concrete.
(g) Check Mix Boxes.
(h) Mixing of concrete by hand/machine.
(i) Use of Vibrator.
(j) Slump of concrete.
512 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
513 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
514 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
515 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
516 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
517 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
518 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
6 Flooring Work
6.1 Cement (a) Aggregates, Sand – refer PCC Works.
Concrete Floor (b) Strength.
(c) Thickness.
(d) Hardener type and mix.
(e) Panel size.
(f) Curing arrangement.
(g) Polishing requirement.
519 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 3 WORKMANSHIP CHECKS FOR DIFFERENT SITE ACTIVITIES
7 Painting Work (a) Name of Manufacturer, Specification, Batch Number, Colour, Date of
Manufacture, ISI Marking on Paint Container.
(b) Cracks, voids, pores on masonry surface properly filled.
(c) Soundness and adherence of Old Paint.
(d) Paint quality ( No. adulteration by thinner ) and quality of Primer.
(e) Application of each coat of Paint for uniformity, paint drop, dabs,
brush-marks, waves and variation of colour.
(f) Difficult to reach areas like edges, corners, nuts, bolts etc. are
properly painted.
(g) Spilled Paints on floors & walls properly cleaned.
(h) Painting of fan hooks and exposed surfaces of inserts as per
Specification.
520 of 896
QUALITY ASSURANCE CIVIL ENGINEERING DIVISION
MECON LIMITED, DELHI-110 092
& QUALITY CONTROL
(SITE QUALITY PLAN)
ANNEXURE – 4 FORMATS FOR SITE RECORDS
B) INSPECTION REPORTS/REGISTER
1. INSPECTION REPORT FOR EXCAVATION
2. SEIVE ANALYSIS FOR FINE AGGREGATE
3. SEIVE ANALYSIS FOR COARSE AGGREGATE
4. SLUMP TEST REPORT
5. INSPECTION REPORT FOR REINFORCEMENT BBS
6. ANTI TERMITE TREATMENT CHEMICAL APPLICATION CHECKLIST
7. INSPECTION REPORT FOR CONCRETING
8. TEST REPORT FOR BRICKS
9. INSPECTION REPORT FOR BRICK MASONRY
10. INSPECTION REPORT FOR PLASTERING
11. INSPECTION REPORT FOR PAINTING
12. CUBE TEST REGISTER
13. CEMENT STOCK REGISTER
14. STEEL CONSUMPTION REGISTER
15. LEVEL BOOK
16. MATERIAL TEST REGISTER
17. HINDRANCE REGISTER
18. SITE ORDER BOOK
19. MEASUREMENT SHEET
521 of 896
INSPECTION TEST PLAN FOR
EARTH WORK IN EXCAVATION
CLIENT:GAIL
CONSULTANT : MECON LIMITED
CONTRACTOR:
DOCUMENT NO:
FREQUENCY OF INSPECTION
S.No ACTIVITY REMARKS
CONTRACTOR GAIL/ EIC
1 Ground Levels W RM
LEGEND:
SIGN
NAME
DATE
522 of 896
GAIL
ITP
FOR RCC WORK
Frequency
of Inspection Category
Sr. No. Activity
Inspection/
Testing Contractor GAIL/ EIC
Legend
P Perform R Review of Reports
H Hold Point AP Approval
W Witness
RM Random
523 of 896
GAIL
ITP
FOR BRICK MASONRY
Report No.
Date:
Location:
CLIENT:GAIL
Consultant : MECON LIMITED
Contractor :
DOCUMENT NO:
INSPECTION AND TEST PLAN FOR BRICK MASONRY
524 of 896
GAIL
CLIENT: GAIL
REPORT NO:
CONTRACTOR:
DOCUMENT NO:
DIMENSION (M)
Sr. No DATE LOCATION BOTTOM LEVEL REMARKS
L B D
REMARKS
SIGN
NAME
DATE
525 of 896
GAIL
Contractor : Date
DOC. NO. :
IS SIEVE SIZE WEIGHT RETAINED % WEIGHT CUMULATIVE % CUMULATIVE % GRADING ZONE, % PASSING
(gms) RETAINED RETAINED PASSING AS PER IS 383-1970
10 mm 100
4.75mm 90-100
2.36 mm 75-100
1.18 mm 55-90
SIGN
NAME
DATE
526 of 896
GAIL
Client : GAIL
Contractor : Date
DOC. NO. :
Weight of Sample :
40 mm
100
20mm
95-100
10mm
25-35
4.75mm
0-10
RESULTS :
SIGN
NAME
DATE
527 of 896
MECON LIMITED, DELHI
SLUMP TEST
Item of Work Mix Vibrator Water / Bag Height of Specimen after Mould
Removed (mm) Acceptability Slump
Date and Nominal or Used of Cement
(mm) (mm)
Location Design Yes / No (Ltr.)
Sample - I Sample - II Sample - III
528 of 896
GAIL
INSPECTION REPORT FOR
REINFORCEMENT BBS
CLIENT :GAIL
CONSULTANT : MECON LIMITED.
CONTRACTOR:
DOCUMENT NO:
BBS NO: REPORT NO.:
Location / Type of Structure:
Drawing No.: DATE
Total Unit Total Weight in kg.
Cut Length Total No.
Sl.No. Description Bar Dia Shape of Bar Length Weight Remarks
(m) of Bar
(m) (kg/m) 8mm 10mm 12mm 16mm 20mm 25mm
SIGN SIGN
NAME NAME
DATE DATE
529 of 896
GAIL
Qty required
S. No. Description of Item Oty used Prepared by Checked by Verified by
theoretically
For bottom surface and sides of
excavation upto height of 300 mm 5 litres/ sqm of
1
for cloumn pits, walls, trenches surface area
and basements
15 litres/ sqm of
2 Backfill around columns and walls
vertical surface
Rodding of earth @150 mm 5 litres/ sqm of
3
centres close to the wall surface surface area
Top surface of plinth filling to mm
5 litres/ sqm of
4 to 75 mm deep @ 150 mm
surface area
centres with chemical emulsion
530 of 896
GAIL
1 Alignment
2 Level
3 Plumb
4 Shuttering
5 Reinforcement
6 Concrete quantity
Theoretical cement
7
consumption
8 Availability of material at site
I) Cement
II) Sand
III) Metal no. 1
IV) Metal No. 2
V) Water
9 SIR content in sand
10 % Bulkage in sand
11 Others
531 of 896
GAIL
TEST REPORT
532 of 896
GAIL
INSPECTION REPORT
FOR BRICK MASONRY
CLIENT:GAIL
Consultant : MECON LIMITED Date:
Contractor : Location:
Bottom Level:
Top Level:
533 of 896
GAIL
INSPECTION REPORT
PLASTERING
Client : GAIL
Consultant : MECON LIMITED Report No.
Contractor : Date:
Location:
534 of 896
GAIL
INSPECTION REPORT
WHITE WASHING , COLOUR WASHING, DISTEMPERING,PAINTING & POLISHING
CLIENT:GAIL
Consultant : MECON LIMITED Report No.
Contractor : Date:
Location:
2 Material used
3 Evenness of Surface
535 of 896
GAIL
CUBE TESTING REGISTER
536 of 896
GAIL
CEMENT STOCK REGISTER
Date of Source & Qty. Cumulative Date of Qty. Item of Qty. Total Cumulative Balance Contractor EIC Remarks
Receipt Invoice Received Qty. Issue Issued work for Returned Issues Consumptio (4-10) Sign. Sign. Periodical Checks
1 Ref. 3 Received 5 6 which at the end (6-8) n 11 12 13 HQO-IC
2 4 issued of day 9 10 EIC 14a
14b
7 8
537 of 896
GAIL
STEEL REGISTER / CONSUMPTION STATEMENT
RA BILL NO.
TOTAL (MT)
6 MM 8 MM 10 MM 12 MM 16 MM 20 MM 25 MM 32 MM
(MT)
* Previous RA bills receipt and consumption to be recorded as carried forward
538 of 896
GAIL
LEVEL BOOK
539 of 896
GAIL
MATERIAL TEST REGISTER
Periodical Checking
Date Sent Date of Lab Report Signature of
SI. No. Material Description Result Remarks Signature of EIC Office
to Lab Testing Ref. Site-Engineer
1 2 6 7
3 4 5 8
EIC
9a HQO-IC
540 of 896
GAIL
HINDRANCE REGISTER
Date of Period
Date of Overlapping Net Extension
SI. No. Nature of Hindrance Removal Hindrance Remarks
Occurrence Period Extension Recommended
1 2 4 5 9
3 6 7 8
541 of 896
GAIL
SITE ORDER BOOK
Remark of the Inspecting Officer of Contractor Action Taken & by Whom Remarks
SI. No.
2 3 4
1
542 of 896
GAIL
MEASUREMENT SHEET
543 of 896
Annexure-IV
to
Particular Job Specification
(ARCHITECTURAL WORKS)
544 of 896
SCOPE OF WORK
FOR
ARCHITECTURAL WORKS
545 of 896
I) GENERAL
M/s GAIL has awarded M/s MECON Limited project management consultancy (PMC)
services for Angul-Srikakulam pipeline. The brief scope of work for Part- B, broadly
consist of Laying, Testing and Commissioning of 18”NB x 48 Kms (approx) and 12”NB x
274 Kms (approx) pipeline in the state of Odisha & Andhra Pradesh including all associated
works for transportation of Natural Gas (dry)/ R-LNG.
M/s MECON Ltd has been engaged by M/s GAIL to carry out design, engineering,
procurement, inspection & Project Management Consultancy Services required
transportation and distribution of Natural Gas.
The scope of work to be performed under this contract shall include complete architectural
works as per plans, equipment layout, drawings & technical specifications.
The contractor shall maintain proper record of all the materials/equipment procured with
respect to their source & specifications with details of their manufacturing and recycled
content etc. and submits along with all supporting documents/ photographs to Client & PMC
for record purpose.
The complete work has been divided into 04 (FOUR) Sections. Terminal / Stations of
various sections of the pipeline are as under:
SECTION-I:
DT at Tap-off from IP-04 of SAPL Part-A (Control Room & Guard Room Only)
SV-01S
IP-01S
SECTION-II:
SV-02S
SV-03S
SV-04S
SV-04SA
SV-05S
SV-06S cum Tap Off for Vedanta P/L
SV-07S cum Tap Off for Nalco P/L
RT Utkal Alumina
SECTION-III:
SV-01V
SV-02V
SV-03V
RT VEDANTA
546 of 896
SECTION-IV:
SV-01N
SV-02N
SV-03N
RT NALCO
NOTE:-
1. The scope of work shall be broadly, but not limited to, the following:
Architectural works envisaged in this tender involve plastering, painting, flooring works,
doors/windows, false ceiling, sanitary & plumbing works, and associated works as per
specifications, BOQ, drawings and instructions of engineer in charge required for the completion
of building works.
2. Architectural works shall be carried out for the scope of work listed as above. Bidder shall
understand the scope of work by visiting the work site in advance and required to complete
all the works as per specifications, SOR, drawings and as directed by Engineer-in-charge.
3.1 The drawings included in the Bidding Document provide a general idea about the work to be
performed under the scope of this contract. These are preliminary drawings for bidding
purposes only and are by no means the final drawings or show the full range of the work
under the scope. Work has to be executed according to latest drawings prepared/approved by
the Consultant.
3.2 All specimens and approved samples shall be retained with the Consultant for reference
unless handed over to Contractor for safe custody. The Contractor shall make arrangements
for proper storage of the same.
3.3 Submission of all original test certificates & records of testing, all warranties, performance
guarantees in favour of GAIL (India) Limited.
547 of 896
III) DRAWINGS
The work shall be executed in accordance with the specification and the drawings issued for
construction. Drawings will be issued in stages in close coordination with the availability of data
and sequence of construction. Only latest revisions of the drawings shall be followed. All old
revisions shall be clearly marked ‘SUPERCEEDED’ and kept separately or destroyed as directed
by Consultant.
Records of cement and steel receipts, issue, and consumption shall be scrutinized from time to
time by consultants and Owner. Statement of cement and steel receipts, statement of theoretical
consumption and reconciliation accompany every bill. Records of spot levels jointly recorded
before the start of the work shall form the basis of all measurements.
A high standard of quality is required for all materials and workmanship in construction work.
They shall be best of the kind obtainable indigenously in each case and shall be procured from
manufacturers of repute in order to ensure uniformity of quality and timely supply.
All materials shall be subjected to inspection and testing. The Contractor shall submit samples for
testing as may be required by the Consultant. Sampling and testing shall be carried out in
accordance with relevant IS Standards.
Wherever IS codes are referred, they shall be latest edition/ publication as on date irrespective of
the date of finalisation of the work.
Any material brought to site which, in the opinion of the Consultant is damaged, contaminated,
deteriorated or does not comply with the requirement of this specification shall be rejected.
If the routine tests or random site tests show that any of the materials, brought to site, do not
comply in any way with the requirements of this specification or of IS codes as applicable, then
that material shall be rejected.
The Contractor at his own cost shall remove from site any and all such rejected material within
the time specified by the Consultant.
548 of 896
VII) PREAMBLE TO SCHEDULE OF ITEMS
1.0 GENERAL
This preamble to the schedule of items is an integral part of the schedule and shall have as much
force as though this is incorporated into the description of the items themselves.
Contractor's rate for any items of work in the schedule of items shall, unless otherwise stated, be
held to include the cost of all materials, including wastages, conveyance and delivery, unloading,
storing, fabrication, hoisting, all labour for finishing to required shape and size, tools and plants,
power, fuel, consumables, all taxes royalties, other revenue expenses, temporary facilities like
roads, drains etc., providing temporary storage facilities for cement, steel and other materials and
their subsequent dismantling, scaffolding and other temporary works, setting out, fitting and
fixing in position, site drainage, dewatering, offering samples for approval, cost of all tests,
rectification of all defects, replacement of defective materials and work, interruptions to work
required to accommodate the work of other agencies working on the site, continuation of work
beyond working hour, in the night and holidays also if situation warrants so, site clearance on
completion, maintenance work during the period of maintenance, bye-work necessary to complete
any particular item of work as per specification and direction of the E-I/C, overheads, profit and
other incidental charges.
The rate of the respective item shall be for the complete finished work and shall also include, but
not limited to, the following bye-works/activities all complete at all level and locations and as per
specification and as directed by the E-I/C.
2.1 Preparation of surface to receive plaster/finish etc. cleaning of masonry/concrete surface of all
dust, loose mortar dropping, traces of algae efflorescence and other foreign matter and
roughening by wire brushing or hacking as may be required and raking out of joints where
required.
2.2 Provision for scaffolding wherever required and removing the same.
2.3 Extra provision necessary to provide plastering /finishing in layers, when required.
2.4 All extra provisions necessary for plastering/surface finish in arises, bonds, bends, closing chases,
rounded angles, drip courses, string courses, around openings/holes, and around dissimilar
materials like metallic/timber/asbestos.
2.5 Nominal sprinkling of the cement slurry on the surface for proper grip and satisfactory finishing
of the plaster work, if required.
2.6 Providing richer mortar 1:3 in a width of 75 mm on either sides of arises of all doors and
windows.
2.7 All provisions necessary to achieve levels and true profiles.
2.8 Curing by appropriate means.
2.9 Removal of unused materials, dirts and debris and cleaning of area thoroughly, after completion
of the work in particular area, if required.
549 of 896
3.0 PAINTING
The rate of the respective items shall be for the complete finished work and shall also include, but
not limited to, the following bye-works/activities at all levels and locations and complete in all
respects as per specification and as directed by the E-I/C.
3.1 Preparing the base surface including necessary rectification and treatment.
3.2 Provision of surface ladders, scaffolding etc., wherever necessary.
3.3 Provision of prime coat wherever applicable.
3.4 Curing by appropriate means wherever applicable.
3.5 Cleaning the splashes and drippings on floors, equipments, pipelines, etc.
3.6 Additional work to rectify the improper workmanship especially if final finish is not satisfactory.
3.7 Protection of painted surface during application and till final handing over.
3.8 Provision of brushes, abrasive papers, indigo (neel) and gum.
550 of 896
5.0 WOOD WORKS
The rate shall include, but not limited to, the following:
5.1.1 Making necessary holes/openings in masonry/concrete for fixing and jamming the same with
appropriate materials.
5.1.2 Provision of bituminous coatings or other anticorrosive paint coatings on the surface in contact
with concrete/masonry.
5.1.3 Provision of rawl plugs, screws, nails, pins, adhesives and the like, necessary for joinery and
fixing.
5.1.4 Provision of temporary wooden bracings and their removal.
5.1.5 Provision of rebates, roundings and other type of curvings as per drawing.
5.2 Shutters
5.2.1 Provision of necessary wooden cleats, wooden blocks, with necessary screws, nails, adhesives,
etc.
5.2.2 Provision for mouldings, rebates, roundings and other types of curvings as per drawings.
5.2.3 Provision of all necessary nails, screws, washers, holts, nuts, putties, adhesives, etc.
5.3 General
The rate shall include, but not limited to, the following:
6.1 Making necessary holes/openings in masonry/concrete for fixing and jamming the same with
approved materials.
6.2 Shop fitting, assembly and shop coat of primer.
6.3 Doors, windows, gates, rolling shutters, glazed doors and windows and other items which are
measured in Sq.m shall include all the necessary frames, angles, plates, sheets, holdfasts or lugs,
locking arrangements, handles, bolting devices on both sides, hinges, pivots, guide rails and guide
channels (wherever applicable), roller (wherever applicable), hood (wherever applicable), rubber
linings, gaskets and the similar other fixtures necessary for fixing and locking arrangements
(locks shall be separately paid unless otherwise mentioned in particular schedule of items).
551 of 896
6.4 Glazed doors/windows shall also include the glazing/glass panes glazing beads, glazing clips,
putty, gasket and the like.
6.5 Rectification of damages and/or replacement of defective/rejected works.
6.6 Provision of protective measures till final handing over and protection/maintenance of the same
within the maintenance period. Protection of glass panes/glazing after final hand over shall be the
responsibility of the E-I/C.
6.7 Keeping the entire steel work free from corrosion and scrapping off and cleaning the rust, if any.
This part deals with the general norms/standards requirements of materials for use in
construction work with regard to quality, testing, approval and storage, before they are used on
work.
1. Standard
A high standard of quality is required for all materials used in construction work. They shall
be the best of the kind obtainable indigenously in each case and shall be procured from
m a n u f a c t u r e r s of repute in order to ensure uniformity of quality and assurance of timely
supply.
2. Space Requirements
• Buildings shall accommodate spaces to meet the functional requirements as well as
security/safety, maintenance, statutory (stairs/fire exits etc.), utilities & services
(toilets/AC/Electrics/LAN/health etc.)/ environmental requirements and incorporated in
design & detail engineering drawings/documents.
• Space requirements as indicated are not exhaustive and subjected to finalization by client
during detail engineering stage with modifications required to meet the building
requirements.
3. Design Requirements
• Entry to be provided at proper location.
• Toilet & Overhead water tank to be provided as per NBC guidelines.
• 600 mm projection to be provided over each window & ventilator.
• False ceiling to be considered in toilets for concealing pipes.
• Skirting shall be of same finish as that of floors. Panel dividers shall be provided in
IPS/Heavy Duty flooring.
• All Air-Conditioned areas shall have false ceiling.
• Painting on Internal walls shall be done over wall putty.
• All steel frames, Shutters, Grills etc shall be painted with two or more coats of
approved quality Synthetic Enamel Paint of Approved shade over a coat of
Approved quality red oxide Zinc Chromate Primer.
552 of 896
• False flooring shall be provided in IT/ Server Rooms.
• Samples, colour, finish and make of all materials should be approved by client.
4. Natural Ventilation
The area of windows will be a minimum 17% of the floor area to ensure adequate natural
lighting and ventilation.
5. FLOORING
Polished / glazed Vitrified floor tiles of approved make/ shade/ design/range of size 600mm X
600mm shall be provided in SCADA & Control Room, Telecom Room,Office spaces and
corridors.
Heavy Duty Vitrified floor tiles of approved make/ shade/ design/range of size 300mm X 300mm
and 12mm thickness shall be provided in Electrical Room and Fire Fighting Room.
Ceramic glazed/matte finish wall tile of size 600mm x 300mm of approved make shall be
provided in toilet dado and matt finish/ anti-skid ceramic tiles of size 300mm x 300mm for toilet
flooring.
Kota stone slab flooring of 25mm thickness shall be provided in guard rooms, utility areas, stores,
staircases, window sills, etc.
Acid resistant tiles shall be provided in floor and dado upto lintel level of battery rooms of size
300mm x 300mm.
Acid Resistant Tiles are used in flooring and lining to prevent corrosion of surface by acids and
other chemicals as well as to resist abrasion on floors. These tiles are made up of materials like
clay, feldspar, quartz, and talc and vitrified at high temperatures in ceramic kilns and kept
unglazed to prevent slipperiness when laid on floor. Chemical resistant mortars as per IS 4832 are
used for laying these tiles. Laying and finishing procedure similar to the other glazed ceramic
tiles.
Telecom Room and Control Room may have false flooring as per requirement.
Providing and fixing noncombustible 600mm high false flooring / cavity floor of modular 600 x
600 size and min thickness of 35mm approximate with pre moulded (USF 1000 grade) in filled
access floor tile made from steel and cementitious infill material (M/S Unitile or equivalent), with
edge beading and faced with 2 mm thick antistatic high pressure laminates. The Panels shall
553 of 896
confirm to Class O & Class 1 Fire Ratings tested as per BS 476 and ASTM E84. The panel shall
be designed for minimum concentrated load of 450 kgs, ultimate concentrated load of 1050 Kgs,
Rolling load of 225 kgs.
The other components such as stringers, pedestals, supports, check nuts, etc shall be designed
suitable in-line with the design parameter of the false floor panel.
The panels shall be placed on GI snap lock grid system stringers channels supported over MS
galvanized pedestal supports at 600mm c/c approximate both ways.
Jack heads shall be die formed, out of min 4mm thick galvanized M.S. plate out of 90 mm X 90
mm, electroplated, with die cut notches to hold stringers ‘snap on’ and threaded holes, in addition,
to hold the rigid grid type stringers. The jack heads shall have stud for housing into the pedestal.
The pedestal head shall consist of an anti-vibrational conductive cap
Stringers shall be M.S. rigid grid type minimum 30 mm X 20 mm X 1.2 mm thick tubes and shall
rest on the jack heads notches and shall be fixed by means of screws. The stringers shall be spray
painted with conductive paint or galvanized to prevent rust & corrosion.
The pedestal supports shall be rigidly fixed on to the floor with glue and mechanical fasteners and
shall be made of 150 x 150 mmx 8mm thick base plate with CRC pipe of size 32mm dia X 3mm
and minimum 19 mm thick MS stools with a coupling and check nut for level adjustment. The
sub structure assembly shall be suitably anchored to the floor.
The work includes necessary opening for cables and panel mounting and cutting of tiles to
required size and strengthening of pedestals with 300 x 300 mm RCC pedestal at location of
panals. The floor panels and stringers shall be completely removable and shall remain in position
without screwing. The shade of the flooring material shall be as specified in the drawing or as
directed by Engineer.
6. Finishing
6.1 Plastering on masonry structures shall be of thickness 15 mm on either faces, 12mm on internal
faces & 6mm on concrete faces. The cement mortar shall not be leaner than 1:4.
6.2 Inside surfaces of walls /Ceiling will be provided with 1.5 mm thick plaster of paris / Wall putty
of approved brand over the plastered surfaces.
6.3 All painting on masonry or concrete surface shall preferably be applied by roller. If applied by
brush then same shall be finished off with roller.
6.4 All paints shall be of approved make including chemical resistant paint.
6.5 All internal walls shall be finished with Premium Acrylic Smooth Interior Paint
Minimum 2 finishing coats of paint shall be applied over a coat of primer. Providing and
Applying of painting on internal plastered surfaces with two coats of acrylic emulsion - Eco
friendly paint with low Volatile Organic Compounds ( not exceeding 50 g/L ) of approved
shade & make, over one coat of approved cement primer consisting of volatile organic
compounds less than 50g/L, including preparing the surfaces by applying Wall Care Putty (Fine
finish) or approved equivalent make 1.5 mm thick, surface preparation, cleaning and all bye
works, filling hair cracks with putty approved filler wherever 'required, scaffolding &
cleaning, cost of all materials, labour etc. at all heights and lifts, all as per drawing,
specifications and as directed by Engineer In-charge etc. complete.
6.6 All external walls shall be finished with Premium Acrylic Smooth Exterior Paint
554 of 896
The paint should be applied in minimum 2 coats (Eco friendly paint with low Volatile Organic
Compounds not exceeding 50 g/L) @1.67 litre/10 sqm over and including priming coat of
exterior primer applied @ 2.20 kg/10 sqm, on new plastered surfaces inclusive of all
required tools, material, scaffolding and other painting accessories etc. The paint shall be applied
as per the manufacturer’s specifications and instructions and to the entire satisfaction of
engineer-in-charge. The paint shall have excellent water resistant property.
6.7 For painting on concrete, masonry and plastered surface IS: 2395 shall be followed.
6.8 Surfaces of handrails, balustrades, steel / wooden door frames, rolling shutters, etc. shall be
finished with synthetic enamel paint (eco-friendly paint with low Volatile Organic Compounds)
over a coat of primer of approved shade & make.
For painting on steel work and ferrous metals, BS: 5493 and IS: 1477 shall be followed.
The type of surface preparation, thickness and type of primer, intermediate and
finishing paint shall be according to the painting system adopted.
6.9 For painting on wood work IS: 2338 shall be followed.
6.10 Bitumen primer used in acid/alkali resistant treatment shall conform to IS: 158.
Glazed anodized Aluminium door with Aluminium frame of approved sections at specified areas.
8 - 12 mm thick toughened glass with Etching shall be considered with top & bottom Aluminium
frame. Doors of the building shall be anodized aluminium environmentally compatible products
containing minimum of 15 to 25 % of recycled content of approved coating (colour to be
approved by Designer) fully / partially glazed (float glass panes with thickness as per opening
with/without SHGC 0.25 to 3 and required U Value as per design. Doors shall have 8.0mm
minimum thick float glass(with or without etching design) panels or prelaminated board panels
with decorative lamination on both sides of approved make fixed with C.P. brass / stainless steel
screws hydraulic door closer/ etc. complete as per directions of E-I/C ; frames as per approved
manufacturer's detail. The item shall include heavy duty double action hydraulic floor springs
with stainless steel cover plate of approved make with IS: 6315 mark, pivoting and all other
arrangements including cost of cutting floors, S.S cover Plates with brass pivots etc., complete
and other necessary accessories required for the works to facilitate smooth operation of the door
shutter at all leads and lifts, all as directed by the Engineer- in- charge.
All windows/ ventilators shall be aluminium glazed (min. 5mm thick glass with/without SHGC &
U Value as per design) with anodized aluminium hardware & aluminium grill as per requirement.
The windows/ ventilators shall be partially/ fully openable or sliding windows as per requirement.
All openings for door with aluminium louvers, windows & ventilators shall have high grade wire
mesh/mosquito net. The fixtures like handles, stoppers, stays, etc. shall be of approved make. All
aluminium sections/sheets including louvers shall be of standard make. Aluminium alloy used in
the manufacture of extruded sections shall correspond to IS Designation H E 9 WP of IS 733.
Hollow aluminium alloy sections used shall conform to IS Designation HV9 WP of IS 1285. The
sections shall be polished and anodized with approved colour. The average thickness of anodic
coating shall not be less than 20 microns as per IS: 1868-1982. All work shall be fitted and shop
555 of 896
assembled to a first job, and ready for erection. EDPM performed profiles shall be used for
inserting into extruded pockets of sections. Glazing beads shall also be of EDPM performed
profiles to hold the glass in frame under pressure. Non-metallic setting blocks shall be used to
centralize the glass in frame. All work shall be adequately braced and reinforced as necessary for
strength and rigidity. Stainless steel ball bearings, housed in nylon type nylon rollers, shall be
used. All mechanical connections shall be sealed with silicon sealant. Around all windows,
approved quality sealants shall be run down to make sure of total weather/water sealing.
Casement windows / ventilators, single or composite units with 6.0mm thick float/frosted glass,
frame size of 44mm x 46mm x 1.1mm, weight 0.522 kg/m min. amd middle frame (horizontal &
vertical) 59mm x 38mm x 1.4mm, weight 0.729 kg/m min(approx.), as per approved
manufacturer’s detail. Openable portion, section size 44mm x 46mm x 1.4 mm, weight 0.575
kg/m min. as per approved drawing and as per approved manufacturer’s specification.
Composite sliding windows with fixed and openable portion, fixed to frame size min. 101.6mm
X 44.45mm x 2.01mm, weight 1.605 kg/m (approx.) and 63.5mm x 38.1mm x 1.5mm, weight
0.861 kg/m min. as per requirement. Sliding shutters fixed to frame size 92mm X 31.75mm x
1.5mm min. & weight 1.060 kg/m min and 61.85mm x 31.75mm x 1.5mm, wt. 0.784 kg/m min as
per requirement. Shutter side, bottom and interlock shall be 40mm x 18mm x 1.55mm wt.
0547kg/m min., as per approved drawing and as per approved manufacturer’s detail.
M.S. Rolling Shutter as required to be provided as per IS code and finished with synthetic
enamel paint.
556 of 896
8. FALSE CEILING
All specified spaces shall have false ceiling of eco friendly light weight calcium silicate tiles and
gypsum board false ceiling.
Material
Frame:
The frame work shall consist of G.I. Pre-coated Silhouette Profile ' T ' Sections for Main runners /
Cross runners of size & thickness specified in the item with galvanization of 120 gsm
(minimum),and perimeter w-profile of 0.40mm (minimum thickness) having flanges of size 7mm
+ 7mm+19mm made from precoated polyester baked Coil length of 3.0/3.60M.fixed to the wall
with the help of rawl plugs at 450mm centre to centre with 35x8mm long dry wall wooden screws
with virgin plastic rawl plugs@ 450mm interval. The frame work shall be executed in a manner
so as to form a grid of 600mm x 600mm as specified in the item. The frame work shall be
suspended from ceiling by L shape adjuster hangers made of G.I. sheet of size 85x25x25x2mm
having die cut slit for sliding into main T section, also having precut hole so as the 6mm fully
threaded MS rod can be inserted and pierces into M 6 dash fasteners of 6 mm dia 40mm long,
fixed to the slab/beam and then tightened with check nuts, subsequently the bottom of 6 mm rod
will be tightened with check nuts, for adjusting the line & level, in true horizontal plane.
Ceiling Tiles:
Ceiling Tiles shall be of 15 mm thick Integral densified microlook edged, semi perforated / fully
perforated or with design/ texture as mentioned in item, eco friendly light weight calcium silicate
false ceiling tiles and made from hydrated calcium silicate, reinforcing fibres, natural fillers free
from formaldehyde and other harmful materials, & shall not contain any toxic ingredients and
shall have 52% recycled material, including 23% fly ash.
The tile shall be of size 595 x 595mm having Integral densified reinforced edges of 15 mm
thickness all around with a collar of width 24 mm and 10mm thickness at the centre. The tiles
shall have overall density of 350 kg/m3 in the body and 450kg/m3 at the edges. The tiles shall be
primer coated on both sides and the fair surface shall be having factory finish in two coats of
white dispersion type solvent free paint.
The calcium silicate tiles should be eco-friendly light weight, characterized with 100% relative
humidity resistance, non-combustibility as per BS 476 Part IV, thermal conductivity of < 0.043
w/m°kc as per ECBC Code-2007, light reflectance> 85°/0,and Noise Reduction Coefficient
(NRC) of 0.50 for Spintone / Cosmos /Fine Fissured and NRC of 0.15 for Hexa/Quadra , and
NRC of 0.65 to 0.75 for Globe fully perforated tiles, as per IS-8225-1987. Sound attenuation
STA- 32 dB. The tiles should weigh approx 5.0--5.5 kg/m2.
Suspension Material
G.I. Fully threaded galvanized rod of 6 mm dia. having hot dip coating of zinc 80g/ Sqm, and
tensile strength of 344-413 MPa. The rod should be used in conjunction with L- adjuster, bent at
90°, and check nuts, so as to ensure that there is no disengagement, both at the bottom of rod and
557 of 896
at the top portion which is tightened to M- 6 metal dash fastener, suitably drilled into the
slab/beam.
Precautions
a) All wet trades such as plastering, conduiting, and painting etc be completed prior to start of
false ceiling works.
b) Air Conditioning duct work is to be completed, preferably even before the suspension of the
grid sections.
c) Electrical chasing or drawing lines & cables, etc. are to be in place before start of false
ceiling works.
d) No unauthorized weight is put on false ceiling. Lighting fixtures, diffuser are to be
suspended independently with proper chains/ wire & dash fasteners as directed by Engineer
in Charge.
e) The area should be completely dry, prior to ceiling installation work.
Measurements
Length & breadth of the finished ceiling shall be measured correct to a centimetre. The area shall
be calculated in square meter correct to two decimal places. No deduction shall be made for
making openings for electrical, air conditioning, fire fighting fixtures, nor shall extra payment be
made either for extra materials or labour involved in making such openings.
558 of 896
8.2 Gypsum Board False Ceiling
Providing and fixing 12.5 mm thick moisture resistant gypsum board suspended false ceiling with
M/F Suspended Ceiling Regular System (Single Layer GS-MFSC-4.1) which includes providing
and fixing G.I. Perimeter channels of size 0.55 thick having one flange of 20 mm and another
flange of 30 mm and a web of 27 mm along with perimeter of ceiling, screwed fixed to
brickwall/partition with the help of nylon sleeves and screws, at 610 mm centres. Then supending
G.I. intermediate channels of size 45 mm, 0.9 mm thick with two flanges of 15 mm each from the
soffit at 1200 mm centres with ceiling angle of width 25mmx 10mm x 0.55mm thick fixed to
soffit with G.I. cleat and steel expansion fasteners.
Finally the board are to be jointed and finished so as to have a flush look which includes filling
and finishing the tapered and square edges of the board with jointing compound, paper tape of
best quality and two coats of primer suitable for Gypsum board (as per recommended practices of
Gypsum board or equivalent).The rate shall be inclusive for making necessary opening for light
fittings, grills 15 and cutouts etc. with the frame of perimeter channels of size
20mmx27mmx30mmx0.55mm thick supported suitably and painting the exposed surface of
Gypsum board two coats with plastic emulsion paint of approved brand and shade including
making necessary service door complete in all respect as per manufacturer’s specification as
directed by E-IC.
9.1 Roof drainage system will be provided for quick and efficient draining of rainwater from roof to
avoid seepage and damage to roof. The roof gradient for the roof will not be less than 1 in 100.
Roof System will be designed to handle design requirements for the specific site and will be
in accordance to stipulations of IS:1742 and IS:2527. Roof drains will conduct water to storm
drains through uPVC down take pipes. UPVC Rain water conform to IS : 13592 Type A
including jointing with seal ring conforming to IS : 5382 leaving 10 mm gap for thermal
expansion Single socketed pipes.
9.2 All exposed RCC roofs shall have waterproofing treatment of acrylic base flexible liquid applied
Waterproof cum Insulation Membrane. The surface shall then be finished with crazy ceramic
tiles.
Method of Application
Surface Preparation
Prior to application of Waterproof cum Insulation Membrane, all surfaces must be prepared
properly to avoid failure. The surface shall be cleaned to remove all dust, foreign materials/loose
particles or any deposits of contaminants, which could affect the bond between the original
substrate and the membrane system. This can be done by scarifying, grinding, water blasting,
sand blasting, acid washing or any other approved method. Rectify depression / honey-comb (if
any) in the surface, use mortar ( 1part mortar, 2part cement, 4 part medium washed sand) and
leave it for at least 24 hours before application of Waterproof cum Insulation Membrane.
559 of 896
Treatment of Cracks
If there is any crack up to 2 mm, clean those cracks with vacuum cleaner, to open cracks, pour
waterproof acrylic primer followed by a coat of acrylic along the crack line and leave it to dry for
overnight.
Application of Primer
Though the membrane adheres strongly with most of building materials like cement concrete,
mortar, bricks, woods, metal etc, use of acrylic primer provide better performance of final coating
system. Stir well the Primer and apply it with soft nylon brush or roller over the dry surface.
Generally, one coat is sufficient. If the surface is too porous apply two coats of primer. Time gap
between two coats should be 2-3 hours.
Application of Membrane
After the application primer coat allow it to reach touch dry for 2-3 hours. Stir the material to a
homogeneous smooth consistency and apply it horizontally with soft nylon brush, roller or
squeeze to thickness of 125-150 microns in single coat. Allow it to dry for approx. 4-5 hours.
When the applied coat becomes sufficiently dry (no foot print observed) apply second coat
vertically. Two coats are sufficient for general application (150-200 microns DFT) but for severe
conditions, three or more coats are required to achieve desired results.
Precautions
• Reinforcement rods and other sharp materials should not be dragged over the membrane,
as this can puncture the same. The material shall always be used without dilution.
• Do not apply coating thickness more than 200 microns in one go. For higher coating
thickness apply multiple coats.
• There should not be any rain during and after application of final coating for at least 6-8
hours.
• 24 Hours pond test shall be carried out after 72 hour of final coating application
10.1 All staircases and corridors shall have m.s. railings. Handrail shall be of 66x33x3.6 M.S. hollow
section. Balusters shall be 16x16 M.S. square bar and mid rail shall be 25x6 M.S. square bar.
10.2 Polished granite/ kota stone of 250mm wide of approved shades shall be provided for window
sills, coping, etc.
10.3 Drip mould of size 20mm x 8mm shall be provided over cement plastering of chajjas, roof
projections etc.
10.4 Grooves of uniform size 10x10mm shall be formed in plastered surface as per approved pattern.
10.5 The work tops in pantry / basin counters in toilets will be of granite.
10.6 Urinal partitions shall be of granite.
10.7 Providing and fixing 24 gauge Chicken Wire mesh in junction of block work & RCC works at
corner/wall surface as per direction of Engineer-In-Charge.
560 of 896
10.8 Apron 0.90M wide of PCC M-10 grade and PCC peripheral Storm water drains around building
(as per requirements).
10.9 One or more 1000 liters overhead tank “Sintex” or equivalent with necessary GI incoming and
outgoing pipes and fittings along with 0.5 HP pump for pumping water shall be provided for
supplying water in toilets / other areas.
10.10 Providing and installation plastic garbage bins(FRP/HDPE) of min 120l capacity of approved
model of Sintex/Swift/Nutech/Sheetal or approved equ.make, design & spec as per
standard/norms complete with all fitting,fixtures,lids,wheels etc.
10.11 Supplying and fixing min.18 mm thick smooth finish black granite inauguration stone of superior
quality with overall size of 1000X750mm or 2000X1000(as per requirement of client/MECON),
with ornamental edge moulded granite / marble / cement plaster band of approved shape. The
prepared block shall be fixed with cement mortar 1:3 (1 Cement: 3 Coarse sand) in brick
wall/block work with tiles/stone after chased, including finishing and painting all-round the stone
and making aesthetically beautiful. The inauguration stone should contain engraved letters with
chemically printing /stainless steel of approved matter in Hindi & English of required colour and
size etc. and provision of curtain raising/sliding, light and landscaping/area development all
around, complete as approved by GAIL/MECON.
10.12 Providing and making GAIL logo on boundary wall (on alternate panels) with prefabricated
mould to be pressed on the plastered surface within a recess (1200mm x 1500mm x 30mm thk.
deep) while it is green. Necessary, touch ups, etching, chiseling to be done as per requirement for
depicting the exact logo. The dimensions of the logo shall be 900mm X 600mm. The logo shall
be painted with external acrylic emulsion paint in GAIL corporate colours.
11. LANDSCAPING
Areas considered for plantation shall be road / pathway side planting of hedges and organized
planting in vacant areas in front of buildings.
561 of 896
Annexure-V
to
Particular Job Specification
(STRUCTURAL WORKS)
562 of 896
PARTICULAR JOB SPECIFICATION
STRUCTURAL STEEL WORKS
563 of 896
SCOPE OF WORK FOR STRUCTURAL STEEL WORKS
1.0 This Specification shall apply to supply, fabrication and erection of steel structures in
Terminal & laying works and general structural work.
The steel structures shall consist of but not limited to columns, column bracing,
portals, sheds, platforms, crossovers, walkways, stairs, ladders, handrails,
chequered Plate/Grating for platforms, MS Gate for Boundary wall, wicket gate,
emergency gate, monorail beams, chequered Plate on cable trench, chain link
fencing and fencing gate (if required), display sign boards for terminal etc.
This Specification covers the structural steel work mainly mentioned below. The
structural work shall not be limited to the following description but shall be guided by
technical/ technological aspects for the total scope of work.
1.1 Supply, Fabrication and Erection of Mild Steel Gates for Boundary wall
1.3 Supply, Fabrication and Erection of Chain Link Fencing and Gate (as required)
564 of 896
a) Supply, Fabrication and erection of 2.4 m high chain link with 600 mm at top
barbed wire supported on steel posts with other accessories all work as per
specification and drawing.
b) Painting of steel structure as per specification and drawing.
c) Gate of suitable width shall be provided in the direction of chain link fencing. The
mesh and barbed wire used for the fabrication of gate shall be identical in all
respects to that of chain link fencing the door may be single leaf or double leaf
depending on the width of the gate.
d) The gate frame shall be an angle frame with stiffeners at mid height and mid
width. The mesh shall be welded to the gate frame/stiffeners, all work as per
specification and drawings.
The cost & weight of MS bolts (permanent and service), washers, electrodes, putty,
gases, cost of straightening the raw materials, cutting of flats from plates and providing
splices, paints, tools, plants, electric power, water, other consumables, as required for
the work shall be deemed to be included in the quoted rates.
All handling and transport charges of raw materials and fabricated structures including
double handling, as required, for completion of work in accordance with time schedule,
are deemed be included in the quoted rates.
565 of 896
Annexure-VI
to
Particular Job Specification
(INSTRUMENTATION WORKS)
566 of 896
SCOPE OF WORK
FOR
INSTRUMENTATION WORK
567 of 896
CONTENTS
1. INTRODUCTION
2. GENERAL
3. SCOPE OF WORK
6. LIST OF ATTACHMENTS
568 of 896
1. INTRODUCTION:
The Scope of Instrumentation work shall be Installation, field testing/ calibration &
commissioning of the complete instrumentation and control system and supply of materials in
accordance with the “SOR” and other technical documents attached with this Tender
Specification.
2. GENERAL:
2.1.0 The Contractor shall be responsible for complete activities involving all subcontractors under
him and also instrument sub-contractor (if applicable) works under him for the complete
instrument works, as part of his scope.
2.1.1. Scope of work shall be read in conjunction with the SOR, drawings, specifications and other
documents forming a part of the Contract document. Wherever there is a contradiction between
the above, matter shall be referred to CLIENT / MECON and their decision in this regard shall
be final and binding to contractor.
2.1.2. In the control room, the contractor's scope shall include laying, tagging and identification of all
cables connected between the field and the control room, dressing of the same inside the control
room. It is the responsibility of the contractor for proper routing, dressing of cables, terminations
in panels inside the control room and also for loop checking.
2.1.3. Contractor shall quote unit rates for all items covered in the “SOR”.
2.1.4. Contractor shall be responsible for co-ordination during installation, pre commissioning and
commissioning with his Mechanical and other sub contractors for proper installation of line
mounted instruments.
2.1.5. Contractor shall be responsible for installation, field testing, calibration, pre-commissioning and
commissioning.
2.1.6. Contractor shall be responsible for coordination with the various instrumentation vendor for all
kind of works inside the control room i.e. cable laying, tray erection, if any, and for proper cable
terminations and loop checking.
2.1.7. Drawings and Installation Standards enclosed with the tender are only for reference and
indicative of general nature for scope of work. Actual installation shall be carried out based on
final installation standards, Bill of material and vendor’s drawings / documents issued to site and
as per instructions of Engineer-in-Charge.
2.1.8. Instrument items such as tubes, tube fitting, valves & manifold, junction boxes, cables, cable
glands, plugs, adapters, pipe and pipe fittings etc., as required for installation & hook-ups of
instrument listed under SOR shall be supplied from the attached list of Approved Vendor’s only.
Contractor shall take prior approval of make and specification of such items before placement of
order.
569 of 896
2.1.9. Sealing of cable entries into the control room after laying and testing of all cables using MCT
Blocks.
2.1.10. During trial run/start up/commissioning at all the locations, the contractor shall provide skilled
personnel and supervision round the clock at contractor’s cost. Any defect or changes of setting,
recalibration, etc., if any during the above activity shall be rectified/done immediately to the
satisfaction of engineer-in-charge or his representative. The number and category of the
personnel shall be as decided by the engineer-in-charge. The cost of the above is deemed to be
included by the contractor in the rate quoted.
2.1.11. Contractor's scope shall include making holes in the RCC for fixing up of supports for
instrumentation items, trays etc.
2.1.12. Contractor shall note that elbows (if required) shall be installed on the impulse line wherever
required as per instructions of the Engineer-in-Charge even if it is not indicated in the
installation standards.
a) Perforated/Angle/Ladder Trays (Contractor’s supply) for all the cables from the individual
instruments to the respective junction boxes.
2.1.15 The field work shall be carried out under strict safety regulations and work permits as laid
down by the client. The contractor shall take extreme care regarding safety and all safety gear
like helmets; hand gloves, safety belts, spectacles etc. shall have to be provided by the
contractor.
2.1.16 The single pvc sleeve type printed ferule shall be supplied. Ferruling for cables shall be done
with tag no. of instruments for individual pair. Cross ferruling shall be done for cable ferruling
in field and panels as per instruction of the Engineer in charge.
2.1.17 The contractor shall have to assess the actual site conditions/requirements before placement of
order for cable/trays as per the actual site condition. Contractor has to prepare a cable routing
layout as per actual site requirements from field to existing control room and get the approval
before placement of procurement.
2.1.18 Allowable minimum bending radius of multipair / multicore cable shall be 6 times the outside
diameter for unshielded cables and 8 times the outside diameter for shielded cables unless
otherwise recommended by the supplier.
2.1.19 Location and flow direction of on-line instruments shall be checked by the contractor and to be
570 of 896
rectified in case of any discrepancy as per the instruction of Engineer -In-Charge
2.1.20 The cable entry to the Control room shall be through MCT Blocks for all the control rooms,
which shall be installed by the contractor. The installation of the pipe sleeves shall be as
approved by the Engineer-in-charge. Contractor shall run all cables from field to Control
Room. The cables shall run through Tray / Trench / IRC (instrument road crossings) from field
to the control room as per Instrument Layout Drawings (to be furnished during execution).
2.1.21 Wherever trenches of longer/ smaller dimension than the maximum dimension identified in the
SOR, the rate shall be considered as pro-rata basis for increase/ decrease in floor area change.
2.1.22 Welding/NDT, Charpy V-notch, QA/QC requirement etc. shall be as per Piping Material
Specification (PMS), MECON standards & specifications and other requirement attached /
mentioned elsewhere in the tender document. Contractor to also note that 100% MPI shall be
carried out in the entire socket weld joints in the installation of instruments. The SOR price
shall include all the above in the installation of respective instrument/item.
2.1.23 Welding shall be as per welding standard attached elsewhere in the tender document.
3. Scope of Work :
The instrumentation works shall include, but not limited to the following to complete the works
(Scope of work is common for all the terminals of Section I, Section II, Section III & Section
IV and shall be read in conjunction with SOR, Std. drawings, Std. TS and other attachments of tender
document.) :
a) Supply, Installation, testing, calibration & commissioning of all field instruments (as
applicable) like Pressure Gauges, Temperature Gauges, Pressure Transmitters,
Temperature Transmitters, RTD (skin type & Thermowell type), etc. as per P&ID,
Technical Specifications, drawings & Datasheets attached with tender documents.
b) SS Tube Connection, Electrical Termination, Testing and Commissioning of Gas Actuated
Ball Valves (AV) / GOV including the Supply and installation of SS tubes and fittings
along with supports for impulse lines (wherever required), hydraulic testing, hydraulic oil
(if required), painting of supports as per std, manifold/ isolation valves, sockolets etc as
required for tubing of each Valve, as per the direction of Engineer-In Charge but exclusive
of supply of Valves with actuator.
c) Testing & Commissioning of Metering Skids (alongwith Metering Panels, free issued
cables, etc.) including all manpower, tools & tackles, equipments, consumables, etc.
required as per direction of Engineer-in-charge. Scope also includes installation of metering
panel & laying of free issued cables.
d) Testing , Commissioning , Electrical termination, calibration of Non-Intrusive Pig
Page 5 of 9
571 of 896
Signallers including all manpower, tools & tackles, equipments, consumables, etc. required
as per direction of Engineer-in-charge.
e) Calibration of Pressure Safety Valves as detailed in SOR.
f) Design, Engineering, inspection, Supply, Installation, testing & commissioning of Fully
wired Control Panel cum TIC Panel (Free standing type, 2115 (mm) H (including 100 mm
base + 15 mm anti-vibration pad) x 1200 (mm) W x 800 (mm) D) alongwith all accessories
including valve auto-closure as per tender Document s. All the signals of electrical,
instrumentation, RTU/SCADA, CP, metering skid, etc. are to be interfaced through this
Panel and necessary TBs alongwith accessories shall be provided for the same.
g) Design, Engineering, inspection, Supply, Installation, testing & commissioning of LEL
Detection System comprising of Monitoring card (in Control Panel) & LEL Detectors (in
the field) as per tender document (inclusive of supply of yoke, supports, calibration kit, etc)
h) Supply, Installation, testing of instrument valves & manifolds, mounting accessories,
impulse piping/ tubing, pipe/tube fittings, cable glands, identification tags, conduits,
structural material required for instrument and junction box supports, trays and painting
etc. as per P&ID, Technical Specifications , drawings & Datasheets attached with tender
documents.
i) Supply, Laying, testing of earthing cables / strips for instrument cases & junction boxes to
earth grid, GI / copper strips for grounding of racks/ cabinets/ panels in the control room
with earth pit. Separate earthing to be provided for electrical & instrumentation system.
Copper conductor to be considered for lightning arrestor. Earthing of transformer neutral
shall have double earthing.
j) Supply, Installation , testing and commissioning of Multi cable Transit blocks for all the
cables entering in control room of all the stations
k) Supply, Installation, testing and commissioning of Insulated cable glands for all the
instruments and AV of all the SV Terminals. Size of cable gland shall be as per site
requirement.
l) Supply, Installation, testing and commissioning of dielectric fittings for tubing works at all
SV stations.
m) Excavation of trenches for burring the cables, filling with sand, laying of bricks, back
filling and compacting of the excavated earth. Removal of pre-cast concrete slabs (If
required) and sand on the existing concrete trench, and re-filling of RCC cable trenches
with sand & re-fixing back the concrete slabs after laying of new cables.
n) Supply, Laying, testing of all interconnection cabling (single pair & multi pair signal,
572 of 896
alarm, control and power cables and system cables etc.) between instrument items and
junction boxes, instrument items/ junction boxes to Panel & between panels / cabinets /
racks.
o) Dressing, Tagging, lugging, ferruling, glanding, pair/core identification and termination of
all field cables (single pair & multi pair signal, alarm, control, power and system cables
etc.) in the instrument items, junction boxes, Control Panel & other panels / cabinets /
racks.
p) Complete loop checking and megger testing of cables.
q) Supply, Installation, testing of junction boxes, cable glands, plugs and adapters.
r) Supply, Installation of canopies for instruments.
s) Supply, Fabrication, erection, laying & painting of cable trays, perforated/angle trays
including clamping, identifying tags.
t) Calibration of all field instruments.
u) Hydraulic testing of instrument impulse lines (piping/tubing).
v) Commissioning.
w) Documentation.
x) As built drawings.
y) Supply & installation of yoke supports for instruments and junction boxes.
z) Supply & installation of canopies fabricated out of 2 mm thick MS sheet for instruments.
aa) Supply & installation of pipe sleeves for instrumentation cable entry to the control room.
bb) Supply & installation of Rodent repellers.
cc) The quantities given in SOR against individual items are indicative and shall not be
considered to be binding. The quantities may be increased, decreased or deleted at site at
the time of actual execution and as per discretion of owner/engineer-in-charge. The unit
rate shall be operated to work out the final payment due to contractor. The procurement
shall done as per actual site condition, Approved construction drgs. and Instruction of EIC.
dd) All the items required to complete the work shall be the scope of supply of contractor only.
ee) Supply means supply of instruments including all erection accessories as defined elsewhere
in tender document.
ff) Contractor to note that wherever stainless steel is specified it refers to austenitic and / or
ferrite steel.
gg) All cable glands shall be double compression type and shall be provided with PVC hood.
Cable glands shall be suitable for the cable dimensions with ±2 mm tolerance.
hh) For all electrical items supplied by the contractor including junction boxes, cable glands
573 of 896
and accessories supplied for projects in India, certification from CMRS for explosion
proof to IS 2148 suitable for NEC Class -I, Div-1, Group C & D and Weatherproof to IP
55 as per IS 13947 and approval from CCOE (Chief Controller of Explosives, India) shall
be furnished irrespective of place of manufacture.
ii) For instrument material supplied by Contractor such as cables, junction boxes, pipe, pipe-
fittings, tube, tube-fittings, Instrument valves and Manifolds; drawings, data from vendor
shall be furnished as required as per the respective standard specification. Also Contractor
shall furnish:
Note: This list indicates the minimum drawings and document requirements. However, vendor shall
submit a complete list of document and drawing schedule listing all the drawings and
documents to be submitted by them during the course of execution of the job. The schedule
shall list all drawings and documents along with their number and expected date of
submission.
b) Metering Skids
c) Pig Signaller
574 of 896
5. INSPECTION CATEGORIZATION PLAN FOR INSTRUMENTATION ITEMS
1 A - Stage-wise Inspection + Final Inspection + Document Review as per QAP / specification / Drg.
2 B - Final Inspection + Document Review as per QAP / specification / Drg.
3 C - Document Review as per QAP / specification / Drg.
* Items shall be accepted at site based on the TC/IR review as per specification/Drg. Hence, IWC not
required.
6. LIST OF ATTACHMENTS:
Refer the List of datasheets, Standard Specifications, vendor list, standard QAP’s and Standard
Drawings enclosed elsewhere in the tender document.
575 of 896
DATASHEET OF PRESSURE GAUGE
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
1 Type Direct Wetted parts ---
material
2 Mounting Local Element ---
3 Dial size 150 mm Lower body ---
Colour White (Non rusting plastic Non wetted ---
with black engraving) parts
4 Case material SS Process ---
connection
5 Bezel ring Screwed / Bayonet Size ---
6 Window material Shatter proof glass Rating ---
7 Enclosure Min. IP 65 / 66 Facing &Finish ---
8 Pressure element Bourdon tube Capillary ---
material
9 Element material SS 316 Capillary ---
length
10 Socket material SS 316 Flushing & ---
Filling
11 Accuracy 1% FSD Over range 130% of range
16
protection
12 Zero adjustment Micrometer pointer Blow out Required
17
(Internal) protection
18 Options
13 Connections ½” NPT (M) a) Snubber
Conn. Location Bottom b) Syphon
14 Movement SS 304 c) Gauge saver
15 Diaphragm seal --- d) Liquid filled casing
Type --- 19 2-valve, 3-way Required
manifold
20
Make & *
Model
Pressure Design
Tag No. Range Fluid Location Options
Operating Design Temp.
Refer Instrument Index / P&ID
NOTES:
576 of 896
DATASHEET OF PRESSURE TRANSMITTER
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
GENERAL MEASURING UNIT
1 Function Transmit & Indicate 15 Service Pressure
Electronic Smart P
2 Type 16 Element Diaphragm
Based
3 Case Mfg. Std. 17 Body Material Carbon Steel or better
4 Mounting Yoke 18 Element Material SS 316L
Weather proof to
IS2147 Process
5 Enclosure 19 ½” NPT(F)
Explosion proof to Connections
IS2148
Process Conn.
Enclosure class Min. IP 65 / 66 Mfg. Std.
Locn.
Zone-I, Gr.IIA & IIB, Over Range
6 Elec. Area Class. 20 130% of Range
T3, CCOE certified Protection
Intrinsically safe &
7 Required
Flameproof
8 Air supply N.A 21 Output Meter Required (W.P. & Intr. Safe )
22 Mounting Required for 2” Pipe Mounting –
9 Power supply 24 VDC
Accessories Material (SS 316)
Zero elevn. & Required
10 Cable entry ½” NPT(F) 23
suppression
2-valve, 3-way Required
11 Accuracy + 0.075% of SPAN 24
manifold
12 Repeatability + 0.05% 25 Make & Model *
TRANSMITTER
4 – 20 mA DC, Two
13 Output
wire
14 Trans. Power supply 0 - 24 V DC
Design Design
Tag No. Operating Pressure Range Fluid Options
Press. Temp.
0 NB VJ RKS
INSTRUMENTATION DATASHEETS
MECON LTD. DELHI
DS No: MEC/STD./
Rev. Prpd. By : Chkd. By : Appd. By : 577 of 896
05/E5/I/DS
Page 2 of 13
DATASHEET OF TEMPERATURE GAUGE (with Thermowell)
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
GENERAL FILLED SYSTEM
1 Type FILLED SYSTEM / BIMETALLIC 15 SAMA Class VB
2 Well REQUIRED Compensation CASE
ADJUSTABLE
3 Mounting LOCAL 16 Bulb type
UNION
4 Dial size 150 mm Bulb material 316SS
WHITE (Non rusting plastic with
5 Colour 17 Bulb union threaded to ½” NPT(M)
black figs.)
DIE CAST ALUMINIUM
6 Case material 18 Extension type RIGID
(EPOXY PAINTED)
7 Window material SHATTER PROOF GLASS 19 Bulb dia 8 mm (Min)
8 Conn. Location BOTTOM 20 Capillary material
9 Accuracy 1% FSD Armour Flexible
WEATHER PROOF
10 Enclosure Armour material
TO IS2147
Enclosure class Min. IP 65 / 66 Capillary length
MICROMETER POINTER
11 Zero adj. Screw 21 Overrange protection 130% OF RANGE
(Internal)
BIMETAL THERMOWELL
12 Stem: 22 Material SS 316
DRILLED BAR
Type 23 Construction
STOCK
Material 24 Process connection 1 ½” FLANGED
578 of 896
DATASHEET OF TEMPERATURE GAUGE (SKIN TYPE)
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
GENERAL FILLED SYSTEM
1 Type FILLED SYSTEM / BIMETALLIC 15 SAMA Class VB
2 Well REQUIRED Compensation CASE
ADJUSTABLE
3 Mounting LOCAL 16 Bulb type
UNION
4 Dial size 150 mm Bulb material 316SS
WHITE (Non rusting plastic with
5 Colour 17 Bulb union threaded to ½” NPT(M)
black figs.)
DIE CAST ALUMINIUM
6 Case material 18 Extension type RIGID
(EPOXY PAINTED)
7 Window material SHATTER PROOF GLASS 19 Bulb dia 8 mm (Min)
8 Conn. Location BOTTOM 20 Capillary material
9 Accuracy 1% FSD Armour Flexible
WEATHER PROOF
10 Enclosure Armour material
TO IS2147
Enclosure class Min. IP 65 / 66 Capillary length
MICROMETER POINTER
11 Zero adj. Screw 21 Overrange protection 130% OF RANGE
(Internal)
BIMETAL THERMOWELL
12 Stem: 22 Material -
Type 23 Construction -
Material 24 Process connection -
Size 25 Gauge connection -
13 Stem diameter 26 Thermowell as per drg -
14 27 Options a) LIQUID FILLED
28 Make & Model *
Well
Temperature ( C) Flange
Dimensions
Tag No. Range Location Remarks
Rating/Face/
Operating Design U T Material
Finish
Refer Instrument Index / P&ID
Note:
1. ‘*’ Information to be supplied by the Vendor / Contractor.
2. Make of the TG shall be from approved vendor list of Mecon /Client.
3. Detailed technical catalogue for offered model to be submitted by vendor/contractor during approval.
4. Mounting Pad to be provided with TG.
5. Offered Model shall meet the tender requirement.
579 of 896
DATASHEET OF RTD (SKIN TYPE)
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
GENERAL 13 Cable entry ½” NPT (F)
1 Assembly as per Drg. enclosed 14 No. of entries Single
drg. 15 Enclosure type Weather proof to Min. IP 65 / 66, Ex-
proof (CCOE certified)
ELEMENT THERMOWELL
3 No. of elements Simplex 16 Material --
4 Calibration As per DIN 43760 17 Construction --
5 Element material Platinum (Pt 100) 18 Process --
connection
6 Resistance at 0C 100 ohms 19 Inst. connection --
7 Leads Standard 20 Thermowell as --
8 Sheath per drg
O.D. 6 mm TRANSMITTER
Material SS 316 21 Quantity -
9 Nipple & Union SS 316 22 Input
-
Material
10 No. Of wires 4 Wire 23 Output --
HEAD 24 Power Supply --
11 Head Cover type Screwed cap & SS chain 25 Mounting --
12 Material Cast Aluminium 26 Enclosure class --
27 Make & Model
*
No.
NOTES:
580 of 896
DATASHEET OF RTD (with Thermowell)
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
GENERAL 13 Cable entry ½” NPT (F)
1 Assembly as per Drg. enclosed 14 No. of entries Single
drg. Enclosure type Weather proof to Min. IP 65 / 66, Ex-
15
proof (CCOE certified)
2 Type RTD (4 wire, 1/5 DIN)
THERMOWELL
ELEMENT
3 No. of elements Simplex 16 Material SS 316
4 Calibration As per DIN 43760 17 Construction Drilled bar stock
5 Element material Platinum (Pt 100) 18 Process connection 1 ½” Flanged
6 Resistance at 0C 100 ohms 19 Inst. connection ½” NPT (F)
7 Leads Standard Thermowell as per Drg. Enclosed
20
8 Sheath drg
O.D. 8 mm TRANSMITTER
Material SS 316 21 Quantity
9 Nipple & Union SS 316
22 Input
Material
10 No. Of wires 4 Wire 23 Output
HEAD 24 Power Supply
11 Head Cover type Screwed cap & SS chain 25 Mounting
12 Material Cast Aluminium 26 Enclosure class
27 SS Tag Plate Required
Make & Model *
28
No.
Well
Temperature Flange
Dimensions
Tag No. Range Fluid Qty
Rating/Face/
Nor Design U T Material
Finish
Refer Instrument Index / P&ID
NOTES:
1. ‘*’ Information to be supplied by the Vendor / Contractor.
2. Make of the RTD shall be from approved vendor list of Mecon /Client.
3. Detailed technical catalogue for offered model to be submitted by vendor/contractor during approval.
4. Wake frequency calculation of offered Thermowell to be submitted by the Vendor / Contractor during approval.
5. CCOE Certificate for offered RTD to be submitted by the Vendor / Contractor during approval.
6. Offered Model shall meet the tender requirement.
581 of 896
DATASHEET OF TEMPERATURE TRANSMITTER
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
GENERAL
1 Function Transmit & Indicate
Electronic Smart P
2 Type
Based
3 Case Mfg. Std.
4 Mounting Yoke
Dual Chamber, Weather
proof to IS2147
5 Enclosure
Explosion proof to
IS2148
Enclosure class Min. IP 65 / 66
Zone-I, Gr.IIA & IIB,
6 Elec. Area Class.
T3, CCOE Certified
Intrinsically safe &
7 Required
Flameproof
8 INPUT FROM RTD
9 RFI / EMI Protection Required
10 Cable entry ½” NPT(F)
11 Accuracy + 0.1% of FSD
12 Linearisation Upscale
13 Load Driving Capability 600 Ohms at 24 V DC
4 – 20 Ma DC, Two
14 Output
wire
15 Trans. Power supply 0 – 24 V DC
16 Cold Junction Compensation *
17 Required (W.P. & Intr.
Output Meter
Safe)
18 Required for 2” Pipe
Mounting Accessories Mounting –
Material (SS 316)
19 Make & Model *
Design Design
Tag No. Operating Pressure Range Fluid Options
Press. Temp.
NOTES :
582 of 896
DATASHEET OF LEL DETECTION SYSTEM
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
SERVICE To detect the presence of Natural Gas in the various
locations in Terminal area.
Qty. of Detectors with single channel Refer SOR / MR
Monitoring cards
Qty. of Controller Rack Refer SOR / MR
ALARMS To be available in the respective Control Rooms.
RELAY CONTACT FOR EACH Required
CHANNEL
RELAY CONTACT FOR GROUPING Required
SENSOR
Make *
Model No. *
TYPE Poison resistant, infrared absorption type for combustible
gas or vapours. (Non-selective)
CONSTRUCTION Explosion proof, SS 316 body with stainless steel flame
arrestors, dust cover, weather proof as per NEMA 4X or
Min. IP 65 / 66 (NOTE-3).
0 NB VJ RKS
INSTRUMENTATION DATASHEETS
MECON LTD. DELHI
DS No: MEC/STD./
Rev. Prpd. By : Chkd. By : Appd. By : 583 of 896
05/E5/I/DS
Page 8 of 13
shall be offered.
POWER SUPPLY 24 V DC Monitor / Controller shall supply power to
sensor.
RANGE AND METER Adjustable between 0-100 % LEL
CALIBRATION
INDICATORS Required 0 –100 % LEL
INDICATOR LIGHTS Power on by a confidence flash for every 2 seconds.
(Separate for each channel) 20 % LEL
40 % LEL
Malfunction (malfunction shall include short cut. Line
breaking, over range and earth fault.)
OTHER FEATURES a) Dual adjustable set points for gas level alarm.
b) SPDT latching type relay contacts shall be provided
for following:
i) 20 % LEL (each channel)-alarm high (adjustable)
ii) 40 % LEL (each channel)-alarm very high (adjustable)
iii) Malfunction (common)
iv) High (Common)
v) High High (Common)
c) Relay contacts shall be suitably rated for the specified
power requirements.
d) Reset push button (common)
e) Sensor calibration without alarm outputs shall be
achieved by inhibit switch on relevant channel.
MOUNTING Monitors / Controllers shall be supplied mounted in 19”
racks with screwed terminals at the back. However 19”
racks shall be fully wired-up in ready to use condition.
Dummy plates shall be provided on spare channel slots
wherever required (20 % spare slot shall be provided
wherever applicable).
CALIBRATION KIT Set of fully equipped calibration gas kit consisting of at
least a cylinder / bottle of calibration gas for minimum 6
months use (of known mixture of air and gas ) , a
pressure regulator with gauge , flexible tube / hose ,
adapter cap (to fit sensing head ) shall be supplied to
enable online calibration of LEL detectors.
NOTE :
1. ‘*’ Information to be supplied by the Vendor / Contractor.
2. Make of the LEL Detection System shall be from approved vendor list of Mecon /Client.
3. Splash guard & weatherproof cap for protection against dust and rain shall be provided.
4. The junction box shall be weatherproof to IP 55 and certified to Explosion proof.
5. CCOE Certificate for offered LEL Detection System to be submitted by the Vendor / Contractor during approval.
6. Detailed technical catalogue for offered model to be submitted by vendor/contractor during approval.
7. RS-485 port shall be provided for provision of interfacing with RTU/SCADA.
584 of 896
8. Offered Model shall meet the tender requirement.
585 of 896
DATASHEET OF INSTRUMENTATION CABLES
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
Description 1PX1.50SQ.MM- 1TX1.50SQ.M 1QX1.50SQ.MM-ARM 6TX1.50SQ.MM- 6PX0.50SQ.MM- 3CX1.50SQ.MM- 12CX1.50SQ.MM-
ARM CABLE M-ARM CABLE CABLE ARM CABLE ARM CABLE ARM CABLE ARM CABLE
Make * * * * * * *
As per site / As per site /
As per site / tender As per site / tender As per site / tender As per site / tender As per site / tender
Order Quantity(M) tender tender
requirement requirement requirement requirement requirement
requirement requirement
General Cable Type Armoured Armoured Armoured Armoured Armoured Armoured Armoured
Voltage Grade(V) 1100 1100 1100 1100 1100 1100 1100
No of Cores NA 3 4 18 NA 3 12
No of Pairs 1 NA NA NA 6 NA NA
No of Triads NA 1 NA 6 NA NA NA
CONDUCTOR
Conductor Size (SQMM) 1.5 1.5 1.5 1.5 0.5 1.5 1.5
Electrolytic Electrolytic Electrolytic Electrolytic Electrolytic Electrolytic
Electrolytic Annealed
Conductor Material Annealed Tinned Annealed Annealed Tinned Annealed Tinned Annealed Tinned Annealed Tinned
Tinned Copper
Copper Tinned Copper Copper Copper Copper Copper
Conductor Type Multi Strand Multi Strand Multi Strand Multi Strand Multi Strand Multi Strand Multi Strand
Core Dia of Strand 0.53 0.53 0.53 0.53 0.2 0.53 0.53
(Before Stranding)(mm)
Core No of Strands 7 7 7 7 16 7 7
AS PER IS AS PER IS AS PER IS AS PER IS AS PER IS AS PER IS
Conductor Ref Standard AS PER IS 8130/1984
8130/1984 8130/1984 8130/1984 8130/1984 8130/1984 8130/1984
Insulation
586 of 896
(%)
COMMUNICATION PAIR
Overall Shielding
NA NA NA Yes Yes NA NA
Requirement
Overall Drain wire Annealed Tinned Annealed Tinned
NA NA NA NA NA
Material Copper Copper
Overall Drain Wire Size NA NA NA 0.5 0.5 NA NA
(SQMM)
Overall Drain Wire Type NA NA NA Multi Multi NA NA
Overall Drain Wire No of
NA NA NA 7 7 NA NA
Strand
Overall Drain Wire NA NA NA 0.3 0.3 NA NA
Diameter of Strand
(Before Stranding) (mm)
Overall Shielding
Overlap (%) & Coverage NA NA NA 25 & 100 25 & 100 NA NA
(%)
Overall Shielding Tape
NA NA NA Al Mylar Tape Al Mylar Tape NA NA
Type
Overall Shielding Tape NA NA NA 0.075 0.075 NA NA
Thickness (mm)
Inner Sheath
Inner Sheath Material Extruded HR FRLS Extruded HR Extruded HR FRLS PVC Extruded HR FRLS Extruded HR FRLS Extruded HR FRLS Extruded HR FRLS
PVC ST2 FRLS PVC ST2 ST2 PVC ST2 PVC ST2 PVC ST2 PVC ST2
Inner Sheath Ref. AS PER IS AS PER IS AS PER IS 5831/1984 AS PER IS AS PER IS AS PER IS AS PER IS
Standard 5831/1984 5831/1984 5831/1984 5831/1984 5831/1984 5831/1984
Inner Sheath Thickness
* * * * * * *
(Minimum) (mm)
Dia Over Inner Sheath
* * * * * * *
(mm)(Nominal)
Inner Sheath Color BLACK BLACK BLACK BLACK BLACK BLACK BLACK
Rip Cord PROVIDED PROVIDED PROVIDED PROVIDED PROVIDED PROVIDED PROVIDED
Armour
Armour Material Galvanized steel Galvanized Galvanized steel AS Galvanized steel AS Galvanized steel AS Galvanized steel AS Galvanized steel AS
AS PER IS-3975 steel AS PER PER IS-3975 PER IS-3975 PER IS-3975 PER IS-3975 PER IS-3975
IS-3975
Armour Type & size * * * * * * *
Extruded HR FRLS Extruded HR Extruded HR FRLS PVC Extruded HR FRLS Extruded HR FRLS Extruded HR FRLS Extruded HR FRLS
PVC ST2-Anti FRLS PVC ST2- ST2-Anti Rodent and PVC ST2-Anti PVC ST2-Anti PVC ST2-Anti PVC ST2-Anti
Rodent and Anti Rodent Termite PROPERTIES Rodent and Rodent and Rodent and Rodent and
Outer Sheath Material
Termite and Termite Termite Termite Termite Termite
PROPERTIES PROPERTIES PROPERTIES PROPERTIES PROPERTIES PROPERTIES
Outer Sheath Material AS PER IS AS PER IS AS PER IS AS PER IS AS PER IS AS PER IS
AS PER IS 5831/1984
Ref. Standard 5831/1984 5831/1984 5831/1984 5831/1984 5831/1984 5831/1984
Outer Sheath thickness * * * * * * *
(Minimum) (mm)
587 of 896
Outer Sheath Color LIGHT BLUE LIGHT BLUE LIGHT BLUE LIGHT BLUE LIGHT BLUE BLACK BLACK
Dia Over Outer Sheath
* * * * * * *
(mm)(Nominal)
ADDITIONAL DETAILS
1T 1.5SQMM
1P 1.5SQMM 1Q 1.5SQMM 1100V 6T 1.5SQMM 6P 0.5SQMM 3C 1.5SQMM 12C 1.5SQMM
1100V FRLS
Printing Text 1100V FRLS MFR. FRLS MFR. YEAR OF 1100V FRLS MFR. 1100V FRLS MFR. 1100V FRLS MFR. 1100V FRLS MFR.
MFR. YEAR OF
YEAR OF MFG. MFG. YEAR OF MFG. YEAR OF MFG. YEAR OF MFG. YEAR OF MFG.
MFG.
NOTES :-
1. ‘*’ Information to be supplied by the Vendor / Contractor.
2. Make of the Cables shall be from approved vendor list of Mecon /Client.
588 of 896
INSTRUMENTATION SECTION
TECHNICAL SPECIFICATION
FOR
CONTROL PANEL & ACCESSORIES
MECON LIMITED
DELHI - 110 092
0 20.01.10
589 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
SPECIFICATIONS
FOR
CONTROL PANEL & ACCESSORIES
GENERAL
Site of Installation
Scope of Work :
a) Supply of Control Panel (free standing, cubicle type) along with all accessories like
Power Supply Distribution Box (PDB), Lamps, MCBs, Relays, Barriers / Isolators,
Selector Switch, Signal Multipliers (SDC), etc. as per this Technical specification.
b) Client will provide 230 VAC, 50 Hz. at control room for Control panel and utilities
respectively. Further distribution and necessary surge protection device shall be part of
panel vendor.
c) Separate Terminal Blocks shall be provided for RTU signals with 20% spare
terminals. All the signals shall be available at RTU TBs.
d) Quantities of control panel accessories (Push Buttons, Lamps, Relays, Zener Barriers,
and SDC Cards etc.) shall be as per the Technical Requirements during drawing
approval/detail engineering.
e) Mounting heights :
590 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
3. Ventilation : Required with louvers backed by wire fly screen & fan. Fan
Failure alarm required
4. Doors : Required.
5. Door width : Each max. of 600mm and shall suit width of the panel.
Panel width is indicative only. The sizes shall be sufficient
to accommodate the required hardware specified in MR.
However the depth and height shall be 800 & 2200
respectively.
6. Cable Entry : Bottom, Cable Glands shall be double compression type for
external armoured cables. All unused entries shall be
plugged.
10. Name Plates : Front of Panel Instrument name plates shall be black
laminated plastic with white core. Nameplate shall be
provided on the rear of the panel also.
Page 3 of 11
591 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
Note :
Page 4 of 11
592 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
12 WIRING
b) Wiring details
c) Signal Wiring
f) Power Indication Lamps : 230VAC UPS – Red color, 230VAC NUPS – Red Color
24VDC – Green Color
593 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
2. Output : 24 V
3. Rating : By Vendor
594 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
1. MCB
Make : HAVELL’S/ INDO ASIAN/ MDS.
Qty. : As required + 20% spare
2. Lamps
Type : LED Clustered Type
Voltage : 24 VDC
Make / Model No. : SIEMENS / L & T
Quantity : As required + 20% spare
3 Relays
Type : Plug in relays
Contact Type : Potential free contact
Contact No. : 3 NO. + 3 NC
Rating : 24V DC, 5.0 A
Make / Model No. : OEN/ OMRON.
Quantity : As required + 20% spare
4. Space Heater
Rating : 60W, 230 V AC with Thermostat.
Make : KEC
595 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
* - BY VENDOR
596 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
597 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
598 of 896
MECON LIMITED SPECIFICATION FOR CONTROL PANEL & ACCESSORIES
DELHI
599 of 896
LIST OF VENDORS FOR BOUGHT-OUT ITEMS
1) M/s MTL
2) M/s P & F
Page 1 of 4
600 of 896
IV) PRESSURE TRANSMITTERS & TEMPERATURE TRANSMITTERS
VII )A SS TUBE
1) M/s EX-Protecta
2) M/s Flameproof Control Gears
3) M/s Baliga
4) M/s Flexpro Electricals
Page 2 of 4
601 of 896
IX) PUSH BUTTONS/LAMPS:
1) M/s L&T
2) M/s Siemens
X) MCB’S:
1) M/s Havell’s
2) M/s Indo Asian
3) M/s MDS
XI) RELAYS:
1) M/s OEN
2) M/s Jyoti
1) M/s Elnova
2) M/s Aplab
XIV) INDICATORS
1) M/s ABB
2) M/s Eurothern
4) M/s Tata Honeywell
5) M/s Masibus
XVI) RTDs :
Page 3 of 4
602 of 896
XVII) PRESSURE GAUGES, TEMPERATURE GAUGES :
Note-1
For procuring bought out items from vendors other than those listed above, the same
may be acceptable subject to the following: -
Note-2
For any other item(s) for which the vendor list is not provided, bidders can supply
those item(s) from reputed vendors/ suppliers who have earlier supplied same item(s)
for the intended services in earlier projects and the item(s) offered is in their regular
manufacturing/ supply range.
The bidder is not required to enclose documentary evidences (PO copies, Inspection
Certificate etc.) along with their offer, however in case of successful bidder these
documents shall be required to be submitted by them within 30 days from date of
Placement of Order.
Page 4 of 4
603 of 896
QUALITY ASSURANCE PLAN QAP OF PRESSURE GAUGE General Instrument Consortium
Sub Contractor:-M/s.
Project :- * Alpha Instrumentation & Allied Services Ref No:-PO NO. GENERAL-TOLANI-CAUVERY/PO-VEND/18-19/350 Dtd: 22.02.2019
Project :
Client :- * EVACUATION OF GAS FROM ONGC MADANAM FIELD & INJECTION INTO
W.O.No. DFDAPG13475
GAIL'S CAUVERY BASIN NETWORK AT SV-2 (MEMATHUR)
Contractor :- *
End Client :M/s. GAS AUTHORITY OF INDIA LIMITED
FOA
PMC: M/s.
No.Mecon
:- * Ltd.
Contractor : M/s. TOLANI PROJECTS (PVT.) LTD.
Item Description : Bourdon Sensing Pressure Gauges SHEET : 1 OF 1 DOC NO. QR/QC/014-PG
REFERENC
Srl. COMPONENT CHARACTERISTICS CATE- TYPE/METHOD EXTENT OF CHECK ACCEPTANCE FORMAT Agency REMARKS
E
No. OPERATION CHECKED GORY OF CHECK DOCUMENT NORM OF PLAN
P W P W R
1 Raw material a) Chemical Analysis MA Chemical / PMI sample - Spec. / Drg Spec. / Drg T.C 3 - 4,1
2,1
P.O.
2 Final Assembly b) Dimensions MA Mechanical 100% 5%
10% P.O. Approved T.C 2 1 4,1
2,1
Approved
c) Marking, Tagging, MA Visual 100% 100%
10%
5% Approved Approved T.C 2 1 4,1
2,1
Name Plate, Tag Plate, Spec. / PO Spec. / PO
Workmanship, Sr. No.,
Make, Model No.
Category CR : Characteristics affecting safety of equipment & personnel For Purchaser Approved by
MA : " " Performance *Contractor to provide the details. Checked by
Note :-
MT : " " Appearance 1. W/R by Contractor for all tests. Prepared by
P - Perform 1] Purchase
TPI / Insp. Authority 2. All the Internal Test reports, etc. shall be reviewed by TPI. Rev II
W - Witness Manufacturer
2] General Instruments Consortium For Instrument Consortium Rev I
R - Review 3] Lab Report / PMI Report Rev 0 26.02.2019
4] End User / MECON Plan No. QAP-13475
604 of 896
QUALITY ASSURANCE PLAN
QAP OF TEMPERATURE GAUGE GENERAL INSTRUMENTS CONSORTIUM
Sub Contractor:-M/s.
Project :- * Alpha Instrumentation & Allied Services
Project
Client: EVACUATION
:- * OF GAS FROM ONGC MADANAM FIELD & INJECTION INTO GAIL'S CAUVERY
BASIN NETWORK AT SV-2 (MEMATHUR)
WO. NO. DFDAGT02688
Contractor :- *
End Client :M/s. GAS AUTHORITY OF INDIA LIMITED
FOA No. :- *
PMC: M/s. Mecon Ltd.
Contractor : M/s. TOLANI PROJECTS (PVT.) LTD.
Item Description : Tempearture Gauges SHEET : 1 OF 1 DOC NO. QR/QC/014-TG
Srl. COMPONENT CHARACTERISTICSCATE- TYPE/METHOD EXTENT REFERENCE ACCEPTANCE FORMAT Agency REMARKS
No. OPERATION CHECKED GORY OF CHECK OF CHECK DOCUMENT NORM OF PLAN P W R
1.0 Rawmaterial Chemical MA Lab Chemical /PMI Sample App. Spes. / App. Spes. / T.C. 3 - 4,1
1,2
(Case, Tube etc) Composition Drg. Drg.
2 Final Assembly Visual & Dimensions MA Measurement 2-100% App. Spes. / App. Spes. / T.C. 2 1 4,1
1,2
1-10% Drg. Drg.
Name Plate, Tag Plate, 2-100% APP. SPEC/
DRG.
2 1 4,1
Workmanship, Sr. No., 1-100%
Make, Model No.
3 Calibration Accuracy & MA Testing 2-100% App. Spes. / App. Spes. / T.C. 2 1 4,1
1,2
Over Range 1-10% Drg. Drg.
Catagory CR : Characteristics affecting safety of equipment & personnel *Contractor to provide the details. Approved by
Note :-
MA : " " Performance 1. W/R by Contractor for all tests. General Checked by
MT : " " Appearance 2. All the Internal Test reports, etc. shall be reviewed by TPI.
Instruments Prepared by
Legend : P-Perform 1) Client
TPI / Consultant / Inspection agency/TPI Consortium Rev II
R - Review Manufacturer
2) M/s. GIC. Rev I
W-Witness 3) Lab Report / PMI Report Rev 0 26.02.2019
4] End User / MECON Plan No. QAP-02688
605 of 896
QUALITY PLAN GENERAL INSTRUMENTS CONSORTIUM
QAP OF THERMOWELL
Sub Contractor:-M/s. Alpha Instrumentation & Allied Services
Project :- *
Project : EVACUATION OF GAS FROM ONGC MADANAM FIELD & INJECTION INTO GAIL'S CAUVERY BASIN
NETWORK AT SV-2 (MEMATHUR)
WO. NO. DFDAGT02688
Client :- *
End Client :M/s. GAS AUTHORITY OF INDIA LIMITED
Contractor :- *
PMC: M/s. Mecon Ltd.
Contractor
FOA No. : M/s. TOLANI
:- * PROJECTS (PVT.) LTD.
Item Description : THERMOWELL SHEET : 1 OF DOC NO. QR/QC/014-TW
Srl. COMPONENT CHARACTERISTICS CATE- TYPE/METHOD EXTENT REFERENCE ACCEPTANCE FORMAT Agency REMARKS
No. OPERATION CHECKED GORY OF CHECK OF CHECK DOCUMENT NORM OF PLAN P W R
1 RAW MATERIAL CHEMICAL MA ANALYSIS RANDOM APP. SPEC. TO APP. TEST 3 - 4,1
2,1
OF THERMOWELL COMPOSITION SAMPLE SPECS. REPORT
606 of 896
QAP OFQUALITY
RTD PLAN
Project :- *
RECEIVING TERMINAL AT PANKHAITI, GUWAHATI FOR BARAUNI (BIHAR) TO
P.O.No.: GENERAL/TGSPL-PRECISION/PO-VEND/19-20/064 dtd 22/06/2019.
Client :-Project
* GUWAHATI (ASSAM) PIPELINE
End Client
Contractor :- * M/s. GAIL (India) Ltd. W.O.No. DFDBRT03784
1 RTD a) ACCURACY TEST MA TESTING 100% 10% IEC 751 IEC 751 TEST REP. P W R See note below * *
ASSEMBLIES
b) IR AT AMB & MA TESTING 100% 10% Mfg. STD. To Mfg. STD. TEST REP. P W R I.R. at Amb
AT 500 VDC * greater than
100 M Ω
c) N2 TEST MA TESTING 100% 10% Mfg. STD. To Mfg. STD. TEST REP. P W R No leakage at
40 Kg/cm2
for 30 seconds
d) RESPONSE MA TESTING 100% 10% Mfg. STD. To Mfg. STD. TEST REP. P W R Less than 15 sec.
TIME TEST *** for 6mm dia sheath
without thermowell
e) DIMENSIONS/ MA MEASUREMENT 100% 10% APP. SPEC/ TO APP SPEC TEST REP. P W R
CONNECTION DRG. / DRG.
607 of 896
QAP OF TEMPERATURE TRANSMITTER
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
Activity Characteristics Checked Type of Quantum of Reference of Documents Scope of Inspection Remarks
check Check GAIL/
1 2 *Contractor to
MECON
provide the details.
1) Visual Name Plate, Tag Plate, 100%
Workmanship, Sr. No., Make, Visual Approved Data Sheet P W R Note :- W/R by
Model No. Contractor for all
100% by
1) Cable Entry vendor & 10% tests.
Mmt by TPI Approved Data Sheet P W R
100% by
2) Power On check vendor & 10%
Mmt by TPI Approved Data Sheet P W R
2) Functional
100% by
3)Configuration/Calibration/Accu vendor & 10%
Mmt by TPI Approved Data Sheet P W R
racy/Linearity/
608 of 896
QAP OF PRESSURE TRANSMITTER
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
Activity Characteristics Checked Type of Quantum of Reference of Documents Scope of Inspection Remarks
check Check GAIL/
1 2 *Contractor to
MECON
provide the details.
Name Plate, Tag Plate, 100%
1) Visual Workmanship, Sr. No., Make, Visual Approved Data Sheet P W R Note :- W/R by
Model No. Contractor for all
100% by
1) Cable Entry vendor & 10% tests.
Mmt by TPI Approved Data Sheet P W R
100% by
2) Power On check vendor & 10%
Mmt by TPI Approved Data Sheet P W R
2) Functional
100% by
3)Configuration/Calibration/ vendor & 10%
Mmt by TPI Approved Data Sheet P W R
Accuracy/Linearity/
609 of 896
QAP OF LEL DETECTION SYSTEM
Project :- *
Client :- *
Contractor :- *
FOA No. :- *
Inspection
S. No. Description of inspection or Test Quantam Check Reference
Vendor TPIA GAIL/MECON
Visual check of all material including Make, Model
1 100% Approved datasheet P W R
No. , Sr. No., Tag Plate Marking of Gas Detectors
2 Dimensional, Cable Entry 100% by vendor & 10% by TPI Approved datasheet P W R
610 of 896
QAP OF CABLES
Project :- * QUALITY ASSURANCE PLAN (QAP) QAP No. : TCL/18-19/TSPL/267621-266000/
QAP for : PVC Insulated, FRLS Sheathed Cables (Signal & Screened Control cables) QA/0374
Client :- * THERMO CABLES LIMITED Date : 08.02.2019
Contractor
Address ::- * Contractor : M/s. Thermosystems Pvt. Ltd., Hyderabad Rev No. :2
Unit-I : D-44, 45, 48, 49 & 50, Phase V, IDA, F.O.A. No. : 05/51/23QB/GAIL/DIBIYAPUR/001/SS/FOA, dated 23.12.2017 Rev date : 01.03.2019
FOA No. :- *Jeedimetla, Hyderabad-500 055 Project : REVAMPING OF FIRE FIGHTING SYSTEM AT DIBIYAPUR COMPRESSOR STATION,
Email : kmurali@thermocables.com & Client : GAIL (India) Limited, Consultant : Mecon Limited
achinababu@thermocables.com
Unit-II : Plot No G1, G2, (A), Green Industrial Park, Jadcherla, Mahaboobnagar (Dt)-509 301
Email : csurendra@thermocables.com & bsavairam@thermocables.com
Inspection
p Agency
g y
Quantum of Format of
Sl. No. Components Characteristics Class Type of check Reference documents Acceptance norms TD GAIL/ Remarks
check record V VQC TPI
MECON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
1.0 Raw materials & bought out items
1.1 Copper rod 1 Dimensions Major Measurement Each Coil ASTM B-49 ASTM B-49 FF 143 √ H P R R
2 Conductivity Major Electrical 1 Sample in ASTM B-49 ASTM B-49 FF 143 √ H P R R
3 Tensile strength Major Mechanical every 10 coils ASTM B-49 ASTM B-49 FF 143 √ H P R R
4 Elongation Major Mechanical ASTM B-49 ASTM B-49 FF 143 √ H P R R
5 Purity of copper Major Chemical Each Coil ASTM B-115 ASTM B-115 Supplier T.C √ - R R R
6 Chemical composition Major Chemical ASTM B-115 ASTM B-115 Supplier T.C √ - R R R
12
1.2 PVC Compound 1 Tensile strength Major Mechanical 1 Sample per 5831-1984
IS 5831 1984 5831-1984
IS 5831 1984 FF 144 √ H P R R
2 Elongation at break Major Mechanical each batch IS 5831-1984 IS 5831-1984 FF 144 √ H P R R
3 Thermal stability Major Thermal IS 5831-1984 IS 5831-1984 FF 144 √ H P R R
4 Volume resistivity Major Electrical IS 5831-1984 IS 5831-1984 Supplier T.C √ - R R R
Fire performance 5 Oxygen index test Major Fire ASTM D2863 - 2017 Approved data sheet Supplier T.C √ R R R R
tests 6 Temperature index test Major Fire ASTM D2863 - 2017 Approved data sheet Supplier T.C √ R R R R
FR-LSH 7 Smoke density rating Major Fire ASTM D2843 - 2016 Approved data sheet Supplier T.C √ R R R R
8 Test for halogen acid gas evolution Major Chemical IEC 60754-1 - 2011 Approved data sheet Supplier T.C √ R R R R
1.3 Aluminium mylar 1 Tape thickness Major Measurement 1 Sample Approved data sheet Approved data sheet FF 146 √ H P R R
tape 2 Tape width Major Measurement Approved data sheet Approved data sheet FF 146 √ H P R R
1.4 Galvanised 1 Dimensions Major Measurement 3 Samples/lot IS 3975 - 1999 IS 3975 - 1999 FF 145 √ H P R R
steel armour 2 Tensile strength Major Mechanical IS 3975 - 1999 IS 3975 - 1999 FF 145 √ H P R R
3 Elongation at break Major Mechanical IS 3975 - 1999 IS 3975 - 1999 FF 145 √ H P R R
4 Torsion test on wires Major Mechanical IS 3975 - 1999 IS 3975 - 1999 FF 145 √ H P R R
5 Winding test on strips Major Mechanical IS 3975 - 1999 IS 3975 - 1999 FF 145 √ H P R R
6 Uniformity of zinc coating Major Chemical IS 2633 - 1986 / IS 3975 IS 2633 - 1986 / IS 3975 FF 145 √ H P R R
7 Mass of zinc coating Major Chemical IS 4826 - 1979 / IS 3975 IS 4826 - 1979 / IS 3975 FF 145 √ H P R R
8 Resistivity test Major Electrical IS 3975 - 1999 IS 3975 - 1999 FF 145 √ H P R R
1.5 Wooden drums 1 Dimensions Major Measurement 1 Sample Mfr T.D Mfr T.D TCL/F/15 - H P - -
flanges 2 Surface finish Major Visual Mfr T.D Mfr T.D TCL/F/15 - H P - -
2.0 In process inspection
2.1 Conductor 1 Wire diameter Major
j Measurement 1 Sample
p per
p Approved
pp data sheet Approved
pp data sheet Mfr ITR - - P - -
2 Annealing test Major Mechanical each setting Plant standard Plant standard Mfr ITR - - P - -
3 Persulphate test (Tinning) Major Chemical Plant standard Plant standard Mfr ITR - - P - - If applicable
4 Direction of lay Major Visual Plant standard Plant standard Mfr ITR - - P - -
5 Lay length Major Measurement Plant standard Plant standard Mfr ITR - - P - -
6 Conductor resistance Minor Measurement Approved data sheet Approved data sheet Mfr ITR - H P - -
7 Cross sectional area Major Measurement Approved data sheet Approved data sheet Mfr ITR - H P - -
Legends : V - Vendor(Thermo cables), VQC - Vendor Quality Control, W - Witness, R - Review, P - Perform, TPI - Third party inspection agency,
H - Hold point (Vendor/VQC may not proceed the work until it has been inspected by the VQC/C/TPI) √-Documents to be submitted
611 of 896
Page 1 of 5
QAP OF CABLES
Project :- * QUALITY ASSURANCE PLAN (QAP) QAP No. : TCL/18-19/TSPL/267621-266000/
QAP for : PVC Insulated, FRLS Sheathed Cables (Signal & Screened Control cables) QA/0374
Client :- * THERMO CABLES LIMITED Date : 08.02.2019
Contractor
Address ::- * Contractor : M/s. Thermosystems Pvt. Ltd., Hyderabad Rev No. :2
Unit-I : D-44, 45, 48, 49 & 50, Phase V, IDA, F.O.A. No. : 05/51/23QB/GAIL/DIBIYAPUR/001/SS/FOA, dated 23.12.2017 Rev date : 01.03.2019
FOA No. :- *Jeedimetla, Hyderabad-500 055 Project : REVAMPING OF FIRE FIGHTING SYSTEM AT DIBIYAPUR COMPRESSOR STATION,
Email : kmurali@thermocables.com & Client : GAIL (India) Limited, Consultant : Mecon Limited
achinababu@thermocables.com
Unit-II : Plot No G1, G2, (A), Green Industrial Park, Jadcherla, Mahaboobnagar (Dt)-509 301
Email : csurendra@thermocables.com & bsavairam@thermocables.com
Inspection
p Agency
g y
Quantum of Format of
Sl. No. Components Characteristics Class Type of check Reference documents Acceptance norms TD GAIL/ Remarks
check record V VQC TPI
MECON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
2.2 Insulation system 1 Type of material Major Physical 1 Sample per Approved data sheet Approved data sheet Mfr ITR - - P - -
2 Surface finish Major Visual each setting - - Mfr ITR - - P - -
3 Core identification i.e; Major Visual Approved data sheet Approved data sheet Mfr ITR - - P - -
colour & number printing
4 Thickness of insulation Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
5 Dia over insulation Minor Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
6 Volume resistivity test Major Electrical Approved data sheet Approved data sheet Mfr ITR - H P - -
7 Spark test Major Electrical 100% Approved data sheet Approved data sheet Mfr ITR - H P - -
2.3 Pairing & 1 No. of twists per metre Major Measurement 1 Sample per Approved data sheet Approved data sheet Mfr ITR - - P - -
Pair 2 Drain wire size Major Measurement each setting Approved data sheet Approved data sheet Mfr ITR - - P - -
shielding 3 Aluminium mylar tape thickness Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
4 Tape coverage & overlap Major Measurement Approved data sheet Approved data sheet Mfr ITR - H P - -
5 Dia over twisted pair Minor Measurement Plant standard Plant standard Mfr ITR - - P - -
2.4 Overall shielding 1 Lay length Minor Measurement 1 Sample per Plant standard Plant standard Mfr ITR - H P - -
& Laying 2 Lay direction Major Measurement each setting Plant standard Plant standard Mfr ITR - - P - -
3 Drain wire size Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
4 Aluminium mylar tape thickness Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
5 Tape coverage & overlap Major Measurement Approved data sheet Approved data sheet Mfr ITR - H P - -
6 Dia over laid up cable Minor Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
7 Insulation resistance test Major Electrical Approved data sheet Approved data sheet Mfr ITR - H P - -
8 High voltage test at room temperature Major Electrical Approved data sheet Approved data sheet Mfr ITR - H P - -
2.5 Inner sheathing 1 Type of material Major Physical 1 Sample per Approved data sheet Approved data sheet Mfr ITR - - P - -
2 Surface finish Major Visual each setting - - Mfr ITR - - P - -
3 Rip cord provision Major Visual Approved data sheet Approved data sheet Mfr ITR - - P - -
4 Colour Major Visual Approved data sheet Approved data sheet Mfr ITR - - P - -
5 Thickness Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
6 Dia over inner sheath Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
7 Insulation resistance test Major Electrical Approved data sheet Approved data sheet Mfr ITR - H P - -
2.6 Armouring 1 Size of armour wire / strip Major Measurement 1 Sample per Approved data sheet Approved data sheet Mfr ITR - - P - -
2 No.
No of wires / strips Major Count each setting Approved data sheet Approved data sheet Mfr ITR - - P - -
3 Dia over armour Major Measurement Approved data sheet Approved data sheet Mfr ITR - - P - -
4 Lay direction Major Visual Plant standard Plant standard Mfr ITR - - P - -
5 Armour coverage Major Measurement Plant standard Plant standard Mfr ITR - - P - -
6 Insulation resistance test Major Electrical Approved data sheet Approved data sheet Mfr ITR - H P - -
2.7 Outer sheathing 1 Type of material Major Physical 1 Sample per Approved data sheet Approved data sheet Mfr ITR - - P - -
2 Surface finish Major Visual each setting - - Mfr ITR - - P - -
3 Colour Major Visual Approved data sheet Approved data sheet Mfr ITR - H P - -
4 Thickness Major Measurement Approved data sheet Approved data sheet Mfr ITR - H P - -
Legends : V - Vendor(Thermo cables), VQC - Vendor Quality Control, W - Witness, R - Review, P - Perform, TPI - Third party inspection agency,
H - Hold point (Vendor/VQC may not proceed the work until it has been inspected by the VQC/C/TPI) √-Documents to be submitted
612 of 896
For Thermo Cables Limited, Hyderabad
Page 2 of 5
QAP OF CABLES
Project :- * QUALITY ASSURANCE PLAN (QAP) QAP No. : TCL/18-19/TSPL/267621-266000/
QAP for : PVC Insulated, FRLS Sheathed Cables (Signal & Screened Control cables) QA/0374
Client :- * THERMO CABLES LIMITED Date : 08.02.2019
Contractor
Address ::- * Contractor : M/s. Thermosystems Pvt. Ltd., Hyderabad Rev No. :2
Unit-I : D-44, 45, 48, 49 & 50, Phase V, IDA, F.O.A. No. : 05/51/23QB/GAIL/DIBIYAPUR/001/SS/FOA, dated 23.12.2017 Rev date : 01.03.2019
FOA No. :- *Jeedimetla, Hyderabad-500 055 Project : REVAMPING OF FIRE FIGHTING SYSTEM AT DIBIYAPUR COMPRESSOR STATION,
Email : kmurali@thermocables.com & Client : GAIL (India) Limited, Consultant : Mecon Limited
achinababu@thermocables.com
Unit-II : Plot No G1, G2, (A), Green Industrial Park, Jadcherla, Mahaboobnagar (Dt)-509 301
Email : csurendra@thermocables.com & bsavairam@thermocables.com
Inspection
p Agency
g y
Quantum of Format of
Sl. No. Components Characteristics Class Type of check Reference documents Acceptance norms TD GAIL/ Remarks
check record V VQC TPI
MECON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
5 Dia over outer sheath Major Measurement 1 Sample per Approved data sheet Approved data sheet Mfr ITR - H P - -
6 Printing / Embossing Major Visual each setting Approved data sheet Approved data sheet Mfr ITR - H P - -
7 Sequential length marking Major Visual Approved data sheet Approved data sheet Mfr ITR - H P - -
3.0 Final inspection
Approved data sheet /
3.1 Routine tests 1 Conductor resistance test Major Electrical 100% Approved data sheet Routine test √ H P R R
IS 8130 - 2013
2 Drain wire resistance test Major Electrical 100% Approved data sheet Approved data sheet report √ H P R R
100%
Approved data sheet/
3 High l
i h voltage test at room temperature j
Major l i l
Electrical dd
Approved h
data sheet √ H P R R
BS 5308 Part 2
BS 5308 (Part 2) - 1986 /
4 Insulation resistance test Major Electrical Approved data sheet √ H P R R
Approved data sheet
BS 5308 (Part 2) - 1986 /
5 Mutual capacitance (Between core-core) Major Electrical Approved data sheet √ H P R R
Approved data sheet
BS 5308 (Part 2) - 1986 /
6 Capacitance between core-screen Major Electrical Approved data sheet √ H P R R
Approved data sheet
BS 5308 (Part 2) - 1986 /
7 L/R Ratio Major Electrical Approved data sheet √ H P R R
Approved data sheet
8 Inductance Major Electrical Approved data sheet Approved data sheet √ H P R R
Approved data sheet /
3.2 Acceptance tests 1 Conductor resistance test Major Electrical 1 Sample per Approved data sheet Acceptance √ H P W W/R
IS 8130 - 2013
2 Drain wire resistance test Major Electrical each size Approved data sheet Approved data sheet test report √ H P W W/R
3 Test for thickness of insulation and Major Measurement Approved data sheet Approved data sheet √ H P W W/R
sheaths
4 Dia over inner, outer sheath & armour Major Measurement Approved data sheet Approved data sheet √ H P W W/R
5 Colour of Insulation & Sheaths Major Visual Approved data sheet Approved data sheet √ H P W W/R
6 Tensile strength and elongation at Major Mechanical √ H P W W/R
IS 5831 -1984 IS 5831 -1984
break of insulation and sheath
BS 5308 (Part 2) - 1986 /
7 Insulation resistance test Major Electrical Approved data sheet √ H P W W/R
Approved data sheet
BS 5308 (Part 2) - 1986 /
8 Mutual capacitance (Between core-core)
core core) Major Electrical Approved data sheet √ H P W W/R
Approved data sheet
BS 5308 (Part 2) - 1986 /
9 Capacitance between core-screen Major Electrical Approved data sheet √ H P W W/R
Approved data sheet
BS 5308 (Part 2) - 1986 /
10 L/R Ratio Major Electrical Approved data sheet √ H P W W/R
Approved data sheet
11 Inductance Major Electrical Approved data sheet Approved data sheet √ H P W W/R
Approved data sheet/
12 High voltage test at room temperature Major Electrical Approved data sheet √ H P W W/R
BS 5308 Part 2
Legends : V - Vendor(Thermo cables), VQC - Vendor Quality Control, W - Witness, R - Review, P - Perform, TPI - Third party inspection agency,
H - Hold point (Vendor/VQC may not proceed the work until it has been inspected by the VQC/C/TPI) √-Documents to be submitted
613 of 896
Page 3 of 5
QAP OF CABLES
Project :- * QUALITY ASSURANCE PLAN (QAP) QAP No. : TCL/18-19/TSPL/267621-266000/
QAP for : PVC Insulated, FRLS Sheathed Cables (Signal & Screened Control cables) QA/0374
Client :- * THERMO CABLES LIMITED Date : 08.02.2019
Contractor
Address ::- * Contractor : M/s. Thermosystems Pvt. Ltd., Hyderabad Rev No. :2
Unit-I : D-44, 45, 48, 49 & 50, Phase V, IDA, F.O.A. No. : 05/51/23QB/GAIL/DIBIYAPUR/001/SS/FOA, dated 23.12.2017 Rev date : 01.03.2019
FOA No. :- *Jeedimetla, Hyderabad-500 055 Project : REVAMPING OF FIRE FIGHTING SYSTEM AT DIBIYAPUR COMPRESSOR STATION,
Email : kmurali@thermocables.com & Client : GAIL (India) Limited, Consultant : Mecon Limited
achinababu@thermocables.com
Unit-II : Plot No G1, G2, (A), Green Industrial Park, Jadcherla, Mahaboobnagar (Dt)-509 301
Email : csurendra@thermocables.com & bsavairam@thermocables.com
Inspection
p Agency
g y
Quantum of Format of
Sl. No. Components Characteristics Class Type of check Reference documents Acceptance norms TD GAIL/ Remarks
check record V VQC TPI
MECON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
13 Printing / Embossing on cable Major Visual 1 Sample per Approved data sheet Approved data sheet Acceptance √ H P W W/R
14 Continuity check Major Electrical each size - - √ H P W W/R
test report
15 Dimensional check Major Measurement Approved data sheet Approved data sheet √ H P W W/R
16 Visual check Major Visual Approved data sheet Approved data sheet √ H P W W/R
17 Uniformity of galvanisation on armour Major Chemical 1 Sample per Type IS 2633 - 1986 / IS 3975 IS 2633 - 1986 / IS 3975 √ H P W W/R
18 Hot deformation Major Thermal IS 5831 -1984 IS 5831 -1984 √ H P W W/R
1 Sample per lot
19 Heat h k
H t shock Major Thermal 1984
IS 5831 -1984 1984
IS 5831 -1984 √ H P W W/R
20 Shrinkage Major Thermal IS 5831 -1984 IS 5831 -1984 √ H P W W/R
21 Spark test Major Electrical BS 5099 BS 5099 √ H P W W/R
22 Bending radius Major Mechanical Approved data sheet Approved data sheet √ H P W W/R
23 Electrostatic noise rejection ratio Major Electrical 1 Sample per P.O. Approved data sheet Approved data sheet √ H P R R
24 Anti rodent & termite repulsion test Major Chemical 1 Sample per lot Mfr. Procedure Mfr. Procedure √ H P W W/R
Fire performance 25 Oxygen index test Major Fire ASTM D2863 - 2017 Approved data sheet √ H P W W/R
tests on sheath 26 Temperature index test Major Fire ASTM D2863 - 2017 Approved data sheet √ H P W W/R
FR-LSH 27 Test for smoke density Major Fire ASTM D2843 - 2016 Approved data sheet √ H P W W/R
28 Test for halogen
g acid gas
g evolution Major
j Chemical IEC 60754-1 - 2011 Approved
pp data sheet √ H P W W/R
/
29 Flammability test Major Fire IEC 60332 (Part 1) Approved data sheet √ H P W W/R
3.3 Type tests a For Conductor 1 Sample per Type test
(As applicable) 1 Conductor resistance test Major Electrical P.O. Approved data sheet Approved data sheet report √ H P R R
2 Persulphate test (Tinning) Major Chemical IS 8130 - 1984 IS 8130 - 1984 √ H P R R If applicable
3 Annealing test Major Mechanical IS 1554 (Part 1) - 1988 IS 8130 - 1984 √ H P R R
b For Armour Wires / Formed Wires
4 Measurement of dimensions Major Measurement IS 3975 - 1999 IS 3975 - 1999 √ H P R R
5 Tensile test Major Mechanical IS 3975 - 1999 IS 3975 - 1999 √ H P R R
6 Elongation test Major Mechanical IS 3975 - 1999 IS 3975 - 1999 √ H P R R
7 Torsion test Major Mechanical IS 3975 - 1999 IS 3975 - 1999 √ H P R R
8 Winding
Wi di test
t t M j
Major M h i l
Mechanical IS 4826 - 1979 IS 4826 - 1979 √ H P R R
9 Uniformity of zinc coating Major Chemical IS 2633 - 1986 / IS 3975 IS 2633 - 1986 / IS 3975 √ H P R R
10 Mass of zinc coating test Major Chemical IS 4826 - 1979 / IS 3975 IS 4826 - 1979 / IS 3975 √ H P R R
11 Resistivity test Major Electrical IS 3975 - 1999 IS 3975 - 1999 √ H P R R
Legends : V - Vendor(Thermo cables), VQC - Vendor Quality Control, W - Witness, R - Review, P - Perform, TPI - Third party inspection agency,
H - Hold point (Vendor/VQC may not proceed the work until it has been inspected by the VQC/C/TPI) √-Documents to be submitted
614 of 896
Page 4 of 5
QAP OF CABLES
Project :- * QUALITY ASSURANCE PLAN (QAP) QAP No. : TCL/18-19/TSPL/267621-266000/
QAP for : PVC Insulated, FRLS Sheathed Cables (Signal & Screened Control cables) QA/0374
Client :- * THERMO CABLES LIMITED Date : 08.02.2019
Contractor
Address ::- * Contractor : M/s. Thermosystems Pvt. Ltd., Hyderabad Rev No. :2
Unit-I : D-44, 45, 48, 49 & 50, Phase V, IDA, F.O.A. No. : 05/51/23QB/GAIL/DIBIYAPUR/001/SS/FOA, dated 23.12.2017 Rev date : 01.03.2019
FOA No. :- *Jeedimetla, Hyderabad-500 055 Project : REVAMPING OF FIRE FIGHTING SYSTEM AT DIBIYAPUR COMPRESSOR STATION,
Email : kmurali@thermocables.com & Client : GAIL (India) Limited, Consultant : Mecon Limited
achinababu@thermocables.com
Unit-II : Plot No G1, G2, (A), Green Industrial Park, Jadcherla, Mahaboobnagar (Dt)-509 301
Email : csurendra@thermocables.com & bsavairam@thermocables.com
Inspection
p Agency
g y
Quantum of Format of
Sl. No. Components Characteristics Class Type of check Reference documents Acceptance norms TD GAIL/ Remarks
check record V VQC TPI
MECON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
c For PVC insulation & PVC Sheath 1 Sample per Type test
12 Test for thickness Major Measurement P.O. Approved data sheet Approved data sheet report √ H P R R
Tensile strength & elongation tests before
13 Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
ageing & after ageing
14 Ageing in air oven Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
15 Shrinkage test Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
16 Hot deformation test Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
17 Loss of mass test Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
18 Heat shock test Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
19 Thermal stability test Major Thermal IS 5831 - 1984 IS 5831 - 1984 √ H P R R
20 Oxygen index test Major Fire ASTM D2863 - 2017 Approved data sheet √ H P R R
21 Temperature index test Major Fire ASTM D2863 - 2017 Approved data sheet √ H P R R
22 Smoke density test Major Fire ASTM D2843 - 2016 Approved data sheet √ H P R R
23 Test for halogen acid gas evolution Major Chemical IEC 60754-1 - 2011 Approved data sheet √ H P R R
d For completed cables
Insulation resistance test (volume resistivity
24 Major Electrical IS 5831-1984 IS 5831-1984 √ H P R R
method)
25 High voltage test at room temperature Major Electrical IS 1554 (Part 1) - 1988 IS 1554 (Part 1) - 1988 √ H P R R
26 High voltage test (Water immersion) Major Electrical IS 1554 (Part 1) - 1988 IS 1554 (Part 1) - 1988 √ H P R R
27 Electrostatic noise rejection Major Electrical Approved data sheet Approved data sheet √ H P R R
e Flammability test √ H P R R
28 Flammability test (Bunched cable) Major Fire IEC 60332 (Part 3) Cat B IEC 60332 (Part 3) Cat B √ H P R R
29 Fire resistance As per Swedish Std Major Fire SS 424 1475 (F3) SS 424 1475 (F3) √ H P R R
4.0 Packing and preservation : Cables are packed in suitable wooden drums
Legends : V - Vendor(Thermo cables), VQC - Vendor Quality Control, W - Witness, R - Review, P - Perform, TPI - Third party inspection agency,
H - Hold point (Vendor/VQC may not proceed the work until it has been inspected by the VQC/C/TPI) √-Documents to be submitted
Note :-
1. W/R by Contractor for all tests.
615 of 896
Page 5 of 5
Annexure-VII
to
Particular Job Specification
(TELECOMMUNICATION WORKS)
616 of 896
SCOPE OF WORK FOR TELECOMMUNICATION
FOR
TELECOMMUNICATION WORKS
MECON LIMITED
(A Govt. of India Undertaking)
DELHI - 110092
Supply and laying of 40mm Dia HDPE duct as per the specification Optical Fiber Cable laying, jointing &
termination. Optical Fiber Cable 24 fiber as per ITU-T 652D shall be laid by blowing technique in 40 mm PLB
HDPE Telecom duct to be laid along with pipeline in same pipeline trench. At crossing, rivers, canals additional
duct has to be provided for future use.
The entire pipelines Scope of work will be distributed refer mechanical main line work for details.
24 fibers armored Optical fiber cable shall be laid in self-lubricated 40mm HDPE Telecom Duct / Conduit
along with the pipeline to facilitate proper operational & management control of the pipeline and dedicated
Telecommunication system. The entire work related to OFC & HDPE Duct Supply, laying, Termination,
Testing and Commissioning will be in the scope of the Bidder.
Bidder has to lay the OFC inside the HDPE duct. At each SV / IP / DT/ RT location, spare 30 mtrs OFC loop
shall be kept inside Control room in wire mesh after laying and terminate to FTC .
As per terminal philosophy all even numbered SVs shall be remotely operated whereas, all odd
numbered SVs shall be manually operated. At manually operated SVs, control room is not envisaged,
hence, OFC will not be terminated in the FTC and shall be through in respective SV without any
termination. However a loop of at least 150 meters shall be kept in a blowing Pit /jointing Pit. The
blowing Pit/ Jointing Pit shall be provided at each manually operated SVs as per planning or to be
installed near entry of the SV with identification jointing / blowing post for any future termination of
OFC in control room if required. In addition, blowing Pit/ Jointing Pit shall be provided at each station
(SV, IP, DT, RT). At the stations where control room is available, the length of OFC loop in blowing Pit/
Jointing Pit shall be provided such that it is sufficient to take the OFC from the blowing Pit/ Jointing Pit
to the control room and terminate the OFC in the FTC.
End to End OFC testing shall be done by installing the FTC in control room (if available) or installing FTC in
field in weather proof Junction Box (if control room is not available) as applicable or as per the direction of
Engineer In-charge. FTC, if required, shall be supplied and installed as per the direction of EIC. In case of
any conflict, decision of the Engineer In-charge shall be final and binding.
The Scope defined in this document covers the Complete Telecommunication Scope of work for all the SECTIONS.
The scope of work related to telecommunication work (but not limited to) shall include all the necessary work for
supply and laying of self – lubricated HDPE duct (including HDPE Duct accessories as required) along with new
pipeline in same pipeline trench (As mentioned in SOR), OFC supply and laying by blowing technique in HDPE Duct
and Termination of OFC (24 fiber) for all terminal stations as per the scope of pipeline laying plan in same pipeline
trench and in separate trench inside the terminals (as applicable) including supply of OFC, Blowing of OFC in
Duct, Supply of OFC accessories like Joint Closure, Electronic marker, Electronic marker locator, Erection of
OFC accessories, supply and erection of Blowing Pit/Jointing Pit, Supply of FTC, wire mesh, Erection of FTC,
wire mesh, Testing of HDPE duct, Termination & Testing of OFC, including any minor civil work,
commissioning, Quality assurance and Control, Documentation and any other job as per direction of Engineer In-
charge required for completion and hooking up of OFC based telecom system. The GPS location and the chainage of
all the Blowing and Jointing pits shall be indicated in the OFC blowing report as well as Blowing/ Jointing Pit
installation report. The GPS location and the chainage of all the HDPE duct couplers shall be indicated in the HDPE
duct installation report as well as HDPE duct coupler installation report.
Locations Where CONTROL ROOM IS AVAILABLE - Installation of FTC in control room, installation of wire
mesh below FTC, Loop of 15 Mtrs OFC in wire mesh etc including all the items required for installation of
FTC, Termination of OFC on FTC with Zero Db connector (including supply) and all work as
required(including Civil work) for complete termination of OFC on FTC, splicing with street fibre, Jointing
of OFC as per channeling plan, test of the fibre for the smooth operation system on wavelength,
preparation of reports etc work complete in all respect with all necessary accessories for all location, final
acceptance / Handing over of the same to other contractor and as per the direction of Engineers in charge.
Drawings and documentation shall be as per specification & contract agreement.
For Section – II, the scope of the Section – II contractor also includes installation of blowing pit/
Jointing pit at IP-1S for the OFC laid by the contractor in Section – II, Laying of OFC from blowing Pit/
Jointing pit to the control room, testing and commissioning of the OFC (laid by the contractor in
Section – II) as per the Technical Specification, drawings and documents provided in the tender.
Section – I contractor shall supply and install FTC in the control room at IP-1S. Section – II contractor
shall bring the OFC (laid by the Section – II contractor) till the FTC in the control room, supply and
install wiremesh (near FTC) in the control room and loop the OFC in the wiremesh. Similarly, Section –
I contractor shall bring the OFC (laid by the Section – I contractor) till the FTC in the control room,
supply and install wiremesh (near FTC) in the control room and loop the OFC in the wiremesh. The
OFC (laid by the Section – I contractor as well as Section –II contractor) shall be terminated in the FTC
by Section – I contractor. After termination of OFC in FTC, OFC testing (as per the PJS, TS, drawing and
documents provided in the tender) of respective sections shall be carried out by the respective section
contractor. The methodology described is indicative and shall be subject to change based on site
conditions. Decision of EIC in this regard shall be final and binding.
For Section – III, the scope of the Section – III contractor also includes installation of blowing pit/
Jointing pit at IP-2S for the OFC laid by the contractor in Section – III, Laying of OFC from blowing Pit/
Jointing pit to the control room, testing and commissioning of the OFC (laid by the contractor in
Section – III) as per the Technical Specification, drawings and documents provided in the tender.
Section – II contractor shall supply and install FTC in the control room at IP-2S. Section – III contractor
shall bring the OFC (laid by the Section – III contractor) till the FTC in the control room, supply and
install wiremesh (near FTC) in the control room and loop the OFC in the wiremesh. Similarly, Section –
II contractor shall bring the OFC (laid by the Section – II contractor) till the FTC in the control room,
supply and install wiremesh (near FTC) in the control room and loop the OFC in the wiremesh. The
OFC (laid by the Section – II contractor as well as Section –II contractor) shall be terminated in the FTC
by Section – II contractor. After termination of OFC in FTC, OFC testing (as per the PJS, TS, drawing and
documents provided in the tender) of respective sections shall be carried out by the respective section
contractor. The methodology described is indicative and shall be subject to change based on site
conditions. Decision of EIC in this regard shall be final and binding.
For Section – IV, the scope of the Section – IV contractor also includes installation of blowing pit/
Jointing pit at SV-06S for the OFC laid by the contractor in Section – IV, Laying of OFC from blowing
Pit/ Jointing pit to the control room, testing and commissioning of the OFC (laid by the contractor in
Section – IV) as per the Technical Specification, drawings and documents provided in the tender.
Section – III contractor shall supply and install FTC in the control room at SV-06S. Section – IV
contractor shall bring the OFC (laid by the Section – IV contractor) till the FTC in the control room,
supply and install wiremesh (near FTC) in the control room and loop the OFC in the wiremesh.
Similarly, Section – III contractor shall bring the OFC (laid by the Section – III contractor) till the FTC
in the control room, supply and install wiremesh (near FTC) in the control room and loop the OFC in
the wiremesh. The OFC (laid by the Section – III contractor as well as Section – IV contractor) shall be
terminated in the FTC by Section – III contractor. After termination of OFC in FTC, OFC testing (as per
the PJS, TS, drawing and documents provided in the tender) of respective sections shall be carried out
by the respective section contractor. The methodology described is indicative and shall be subject to
change based on site conditions. Decision of EIC in this regard shall be final and binding.
For Section – V, the scope of the Section – V contractor also includes installation of blowing pit/
Jointing pit at SV-07S for the OFC laid by the contractor in Section – V, Laying of OFC from blowing Pit/
Jointing pit to the control room, testing and commissioning of the OFC (laid by the contractor in
Section – V) as per the Technical Specification, drawings and documents provided in the tender.
Section – III contractor shall supply and install FTC in the control room at SV-07S. Section – V
contractor shall bring the OFC (laid by the Section – V contractor) till the FTC in the control room,
supply and install wiremesh (near FTC) in the control room and loop the OFC in the wiremesh.
Similarly, Section – III contractor shall bring the OFC (laid by the Section – III contractor) till the FTC
in the control room, supply and install wiremesh (near FTC) in the control room and loop the OFC in
the wiremesh. The OFC (laid by the Section – III contractor as well as Section – V contractor) shall be
terminated in the FTC by Section – III contractor. After termination of OFC in FTC, OFC testing (as per
the PJS, TS, drawing and documents provided in the tender) of respective sections shall be carried out
by the respective section contractor. The methodology described is indicative and shall be subject to
change based on site conditions. Decision of EIC in this regard shall be final and binding.
At all the junction location / branching location; jointing pit has to be considered irrespective of distance. At
all locations of Jointing Pit, Joint closures and electronic markers have to be installed as per the
specification or as per direction of Engineer- In charge.
1. Supply and Laying of 40 mm diameter self lubricated HDPE Telecom Ducts & accessories, making records of
test report of material, estimation of quantity, including Storage, Transportation, and unloading at site,
submission of HDPE alignment sheets, planning and schedule preparation for HDPE laying.
2. Erection, testing commissioning and making the work complete in all respect as per specification.
a) Permanently solid Lubricated 40mm diameter HDPE Conduit as per specification along entire
underground pipeline in the same trench including cased crossing for installation of OFC in future.
b) HDPE casing /CS pipe casing for Nallah, River/ Canal, Railways, Major Road Crossing as directed by
Engineer-in-charge wherever required and as directed by Engineer-in-charge in all type of soils
and terrain. Two ducts as per the schematics have to be laid in cased crossing; one duct shall be
used for the present OFC blowing and other will be spare for future use.
c) At all the junction location / branching location; blowing pit has to be considered irrespective of
distance and HDPE duct has to be laid / terminated as per the requirement of site.
3. Supply and erection of cable Blowing pit (RCC pit as per dwg) at every 1 KM distance for BP and every
02 km for JP(Jointing Pit), at every SV location and at every location of FTC installation, at 450mm (min)
away from the main pipeline (the outer wall of Pit shall be min 450mm away from the outer wall of the
pipe); for river crossing and HDD crossing, additional blowing/ jointing pit at both end of the river bank
shall be provided; joint of HDPE conduit, scaling of conduit, HDPE conduit testing after laying as defined
in specification, sealing of HDPE conduit, cased crossing, separate trench & conduit near the terminals,
joints locations marking, back filling, sealing of conduit, providing cable markers, joint markers,
Warning mat/mesh(as procured for Pipeline under mechanical works) etc. as per the MECON
specification. All the accessories must be suitable of 6-8 Kg/cm2 (min.) pressure rating. Testing,
commissioning and handing over of system, drawings & documentation as per contract. The blowing pit
/ jointing pit have to be provided as per the site requirements / at all junction – branching locations.
4. Supply of HDPE accessories required including Plastic Couplers, End Plugs, Cable Scaling Plugs, End
Caps, etc suitable & sufficient for supplied Duct as defined in SOR.
2. Submission of OFC alignment sheets based on the pipeline alignment sheet, planning and OFC
laying schedule preparation, OFC (24 Fiber) testing before and after laying, Laying of armored OFC 24
fiber by blowing technique, Jointing of OFC by jointing closures, all cable sealing, padding backfilling etc.
using all material including supply and laying of warning mats/mesh(as procured for Pipeline under
mechanical works) etc., termination of cables at FTC with all accessories, cable jointing, commissioning
and making the work complete in all respect as per specification, drawings & documentation as per
contracts & other relevant work specified by Engineer-in-charge.
3. All activities pertaining to Blowing / Laying of optical fiber cable in same pipeline trench inside 40 mm
HDPE telecom duct (after testing of OFC drum at site), through CS/ HDPE conduits at crossing, testing of
OFC before and after Blowing/laying, cable sealing etc. using all materials required complete as per
specifications and drawing provided in the bid document & as per direction of EIC. Spare loop of 10
Meter in Blowing Pit at each KM, 150 Meters in Blowing Pit installed at each manual operated SV
location, 20 Meter at Jointing Pit (from each end, total 40 mtrs) & 15 Meter at each station on wire-mesh
(as applicable) shall be provided- No payments for laying shall be made for these spare loops. For OFC
blowing across HDD, OFC shall be laid in both the HDPE ducts for HDD length of 500 mtrs and above.
Also, in that case, 2 different Blowing/ Jointing Pits shall be provided at each end; one each for each run
of OFC.
4. Termination of cables at FTC (24F, 48F, 96F as applicable)(with post in field at locations where Control
Room is Not Available ) with all accessories, cable jointing, commissioning and making the work
complete in all respect as per specification, drawings & documentation as per contract & other relevant
work specified by Engineer-in-charge. The FTC shall be supplied as per the number of OFC runs to the
FTC. At all intermediate locations, min 48F FTC shall be supplied (if 2 nos. of OFC run is there). If more
than 2 runs of OFC is there (for eg. at stations SV-06S and SV-07S), then 96F FTC shall be supplied.
Similar philosophy shall be followed for end stations.
5. If, under the instructions of the EIC, FTC is not required to be supplied (as per the SOR), in that case, the
bidder shall bring his own FTC for testing of OFC. In such scenario, bidder shall terminate the OFC in his
FTC, do complete OFC testing as per the specification, hand over the OFC to client/ other contractor after
successful testing and take back his FTC.
Page 5 of 9 621 of 896
SCOPE OF WORK FOR TELECOMMUNICATION
6. Testing and commissioning of the laid OFC as per specification, testing before and after laying,
identification of fault, rectification of fault, all cable sealing, padding, backfilling etc. using all material
including termination of cables at FTC with all accessories, cable jointing, commissioning and making the
work complete in all respect as per specification, Drawings & documentation as per contracts & other
relevant work specified by Engineer-in-charge. OFC testing shall be done as per the specifications
provided in the tender. If any fault is observed before testing or during testing, the same has to be
rectified. Also, if the test results are not within acceptable limits, the same has to be rectified and
complete OFC shall be re-tested until the test results are obtained within acceptable limits. The OFC shall
be handed over to other contractor (the contractor responsible for executing Telecommunication tender
works) after successful testing. The OFC testing shall be done in the presence of other contractor (the
contractor responsible for executing Telecommunication tender works) . The OFC shall be deemed
handed over only after other contractor (the contractor responsible for executing Telecommunication
tender works) takes over the OFC and accepts the OFC testing. All the responsibility of OFC till handing
over lies with the bidder.
7. The complete responsibility of the OFC lies with the bidder till the handing over of the OFC to client/ other
contractor. Hence, if any fault or damage happens in the laid OFC before handing over, the same shall be
rectified by the bidder without any implication to the client.
2. Supply, Installation, testing and commissioning of “JOINTING CLOSURE” and “FTC” (24F, 48F , 96F) as per
standard specification.
3. Supply of jointing pit. Jointing / splicing of OFC after properly placing it in manholes and providing
protection to spare OFC loop in the jointing chamber.
4. Testing including power testing complete cable section between two stations at 1310 nm & 1550 nm and
testing of end sealing.
5. Providing necessary Testing Tools and power supply at site for end to end splicing and testing etc.
7. The Scope of laying contractor for OFC is upto handing over (after successfully testing as per
specification) to the other contractor. Any rectification work required related to laid OFC during defect
liability period will be in the contractor’s scope as specified in the contract documents.
8. Preparations and submission of As-built drawings with soft copy as per define in the specification.
9. After testing, reports has to be prepared in the format provided in Specification / Procedure for the
Testing of Optical Fiber Cable enclosed with tender, CD (3 sets) of all fiber OTDR traces, power test
results, identification of fiber, loss etc has to be provided.
D. General guidelines for laying of HDPE Duct / OFC for telecommunication system:
1. The procurement of supply items will be done only after taking approval from client/ consultant
/EIC as per the project requirements. SOR quantities may vary as per the actual requirements.
2. Vendor must submit the details of specific experience of the party responsible for OFC, HDPE Duct
laying, jointing, splicing and testing. Sufficient documentary evidences also to be submitted at the
time of submission of bid. The parties having proven experience and track record in respective
field shall be allowed to execute the job.
3. After award of work, Contractor shall supply 2 copies of detailed activity Bar chart, manpower and
machinery mobilization plan, QA/ QC plan and inspection formats, execution procedures for different
type of activities, for review and approval by the Engineer-in-charge within 15 days from the date of FOI
(Fax of Intent) or 7 days of mobilization of work.
4. The OF cable & HDPE Duct alignment sheets (CAS) to be submitted 15 days before final laying to the
Engineer-in-charge for approval which shall indicate various rail, road, canal, river & utility crossing,
location of high tension lines running in parallel with the route of OFC, location of each of jointing
locations & type of cable etc. If contractor will start the work without taking approval of the OFC /
duct alignment sheet then EIC / Client has full right not to accept laying work. The OFC drum
length will be 4 KM + 2.5 %. Same should be cross checked with actual drum length before
finalizing the location of Jointing Pit in CAS preparation. Shorter length drums (less 4 KM - 2.5 %)
if any shall be updated in CAS. After completion of laying vendor shall submit “As Built Drawing” as
define in the specification.
5. Testing of the complete cable section (end to end between two stations) to the satisfaction of CLIENT as
per test schedule mentioned elsewhere in the tender document.
6. The contractor shall bring all duct & OFC laying, jointing, splicing equipment, tools as deemed necessary
for the timely implementation of the work.
7. The Vendor shall use the data provided in the tender for reference purpose only. It shall be the Vendor’s
responsibility to check accuracy and utility of this data.
8. Special care should be taken to avoid any twist or damage of duct / OFC while laying Optical Fiber Cable
under road, Nallah, Railway line, culvert as specified elsewhere in the tender document. At all river
crossing locations, Blowing pit with proper OFC loop length at both the wide river bank end shall be
provided. The jointing of OFC near river bank should be avoided.
9. For payment purpose HDPE casing /CS pipe casing for Nallah, River / Canal, railways, Major Road
Crossing shall be referred in main line section SOR. Two ducts as per the schematics have to be laid in
cased crossing; one duct shall be used for the present OFC blowing and other will be spare for future use.
For payment purpose two ducts for supply measurements and single length for erection measurements
shall be considered. This activity will be done along with the Main line.
10. The cable-blowing pit similar to jointing pit shall be provided at every one KM distance, SV
locations and FTC location. Payment will be made separately for cable blowing pit/ jointing pit as
per SOR. The blowing pit cost at End Locations (in field FTC) shall be included in price of SOR.
11. Jointing, Splicing of OFC in jointing pit, testing, end sealing etc. has to be done. OFC loop should not be left
without proper protection at any place. The OFC loop or surplus cable should be accommodated within
the jointing pit / chamber. At each end the OFC & Duct shall be placed inside the pit with proper care. No
payments (for erection) will be done for the spare loops placed in the Blowing - Jointing pit /
chamber etc. For supply; payment will be made as per SOR rate.
12. If during the course of execution of work any discrepancy or inconsistency error or omission in any one
of the provision of the contract is discovered which needs to be clarified, the same matter shall be
referred to the EIC / Consultants who shall give his decision in the matter and issue instruction then
Page 7 of 9 623 of 896
SCOPE OF WORK FOR TELECOMMUNICATION
accordingly the work is to be carried out. The decision of the EIC / Consultant will be final and binding to
contractor.
13. The payments of supply & erection portion for HDPE Duct and OFC will be done as per contractual
payment terms based on the payment’s milestone defined in the pipeline laying work of the
contract.
14. For the payment for laying, the payable length of optical fiber cable will be the length of pipeline as
per pipeline chainages. As applicable for inside Terminal the actual laid length in separate trench upto
control room will be considered for measurement. Separate rate will be payable for terminal work as
per SOR. OFC route marker has to be provided inside the terminal area. No payments of OFC for erection
will be done for the spare loops placed in the wire mesh etc.
16. Contractor shall take all safety measures required to prevent damage to the cable and accessories. The
contractor shall be responsible for any damage to the cable, accessories and all other free issue items and
existing underground services in route, if any.
17. Inspection of HDPE/ OFC has to be carried out by bidder or bidder’s third party agency before dispatch of
the material as per the approved QAP. Client / Consultant will witness the testing and inspect the
material as per QAP at manufacturer works for respective vendor.
18. As applicable near terminal OFC shall be laid inside duct upto telecom room in separate trench. The entry
point & DUCT has to be properly sealed after laying of OFC to avoid entry of rodent, insect etc.)
At all pipeline tie – in locations, the trench shall be excavated further and duct shall be laid approx 1
meter away from the pipeline to avoid damage to the duct.
20. The Battery limit for the Telecommunication work shall be as defined above in the pipeline
sections covered. This is only for the information purpose, may vary as per pipeline network.
Refer Pipeline Schematic Route Diagram refer mechanical main line works / schematics .Any work not
defined below but required for the completion of Telecommunication work related to OFC laying within
the scope of contractor & as per the instruction of Engineer In charge will be in laying contractor scope of
the particular part.
HDPE Telecom duct and OFC shall be laid in all the sections along the pipelines. At all the intermediate
points / junction points blowing pit / jointing pit has to be provided as required. For HDPE duct testing
and OFC testing as per the scope, planning has to be done as per the requirement at sites.
As applicable in general the laying of OFC will start from the Control room of first station (Ch:0 Km)] to
control room of end station ( Ch : xxx Km)] routed through all the intermediate station control room & SV
stations. Where control room is not available, the scope of OFC work start from blowing pit installed near
to start of pipeline location including termination on field FTC to end location of pipeline upto blowing pit
and termination on field FTC covering all the intermediate station as applicable.
Enclosures:
The common warning mat/ mesh, as provided for Main Pipeline, shall be used for the OFC. Same is
applicable for all the terrain for lying of OFC.
626 of 896
DESIGN BASIS
(ELECTRICAL SYSTEM)
627 of 896
GAIL (INDIA) LIMITED
DESIGN BASIS FOR ELECTRICAL SYSTEM
628 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
Contents
Sl. No. Description
1.0 INTRODUCTION
9.0 CABLES
629 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
1.0 INTRODUCTION
GAIL (India) Limited a public sector under Petroleum ministry, intends to develop Natural
Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh) to Angul
(Odisha) Natural Gas Pipeline Project and its Spurlines in the state of Odisha and Andhra
Pradesh for industrial consumers as well as City Gas Distribution System (CGD).
This pipeline will connect various RLNG terminals like, Dhamra, Dahej, Ennore,
Gangavaram, FSRU etc. and domestic gas fields of K G basin, Off-shore/On-shore fields to
the customers in Eastern region through JHBDPL and Southern region through KSPL.
Therefore, it will provide connectivity to multiple sources to the en-route customers. In view of
the same it has strategic importance and part of National Gas Grid.
This document presents design criteria for electrical system for the Dispatch Station, IP
stations, SV stations & Receiving Station. It indicates minimum requirements for detailed
design of electrical system and equipments for laying of 18”/12”NB x 322 Kms (approx)
Mainline & Spurline (Part-B) from IP-4 cum DT (Ch 341.0km of SAPL Part-A) to RT at Utkal
Alumina (Ch 190.8 km) , RT at Vedanta (Ch 68.3 km) , & RT at Nalco (Ch 62.97 km) for
transportation and distribution of Natural Gas in the region.
Part-B pipeline mainly consist of 18”NBx48 Kms (approx) and 12”NBx274 Kms (approx)
pipeline in different districts of Odisha & Andhra Pradesh for transportation and distribution of
Natural Gas.
In case of any conflict between the codes and standards listed, the same shall be brought to
the notice of Owner for final decision, which shall be binding.
630 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
I) Pole mounted HT substation (11/0.433 KV, LA, DO fuse, Metering etc) for receiving
Grid power from State Electricity Board.
III) 415V Switch Board/PDB for receiving normal power at IP stations / SV cum DT
stations with Energy Saving device, phase selection logic, timer for AC etc.
IV) Parallel Redundant UPS system (7.5kVA /5 kVA) with static by - pass with Ni-Cd type
(Pocket Plate type with 2x50% battery banks) battery bank (for 12 Hours back-up) for
Instrumentation, SCADA and PCP loads at IP terminals / SV cum DT stations with
ACDB for CPTRU, emergency lighting etc.
Size of the UPS shall be considered as per UPS sizing calculations to be submitted
during details engineering to Consultant / Owner for review /approval
VIII) AC- DC converter 230V AC to 48V-0-(-) 48V DC and 24V DC power for telecom &
instrumentation load.
IX) Indoor & Outdoor lighting (Classified and Non-Classified type area & Buildings).
XI) 20Mtr High Mast (8nos. 150W LED Light fixtures) for Area lighting near Process area/
Pole Mounted LED flood lights.
XVII) All panels like Solar Charger, UPS, Switch board shall be equipped for mod bus
communication for remote monitoring.
631 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
1.2.2 SV STATIONS:
I) Pole mounted HT substation (11/0.433 KV, LA, DO fuse, Metering etc) for receiving
Grid power from State Electricity Board.
II) 63KVA, 11/0.433 kV ONAN distribution transformer with HT cable termination box on
primary side & LT cable termination box on secondary side.
III) 415V Switch Board/PDB for receiving normal power at SV stations with Energy Saving
device, phase selection logic, timer for AC etc.
IV) Hybrid Solar power system shall be considered with Ni-Cd type battery bank (Pocket
Plate type with 2x50% battery banks) with 2 days autonomy (for 48 Hours back-up)
for critical load (PCP, Instrumentation, SCADA and telecom) and solar based stand
alone Type Street lighting system for outdoor emergency lights at SV stations.
IX) Indoor & Outdoor lighting (Classified and Non-Classified type area & Building).
X) DC- DC converter (85-135V DC to 24V DC & (+) 48V-0V- (-) 48V DC) required for
supplying various critical load like critical lighting, Telecom, SCADA, Instrumentation
etc.
XVII) All panels like Solar Charger, Switch board shall be equipped for mod bus
communication for remote monitoring.
632 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
I) Pole mounted HT substation (11/0.433 KV, LA, DO fuse, Metering etc) for receiving
Grid power from State Electricity Board.
II) 63 KVA, 11/0.433 kV ONAN distribution transformer with HT cable termination box on
primary side & LT cable termination box on secondary side.
III) 415V Switch Board/PDB for receiving normal power at Receipt stations with Energy
Saving device, phase selection logic, timer for AC etc.
IV) Parallel Redundant UPS system (5 kVA) with static by - pass with Ni-Cd type (Pocket
Plate type with 2x50% battery banks) battery bank (for 12 Hours back-up) for
Instrumentation, SCADA and PCP loads at Receipt terminals with ACDB for CPTRU,
AMF panel, emergency lighting etc.
Size of the UPS shall be considered as per UPS sizing calculations to be submitted
during details engineering to Consultant / Owner for review /approval
VIII) AC- DC converter (230V AC to -48V DC and 24V DC) with UPS system
IX) Indoor & Outdoor lighting (Classified and Non-Classified type area & Building).
XI) 20Mtr High Mast (8nos. 150W LED Light fixtures) for Area lighting near Process area
XVII) All panels like Solar Charger, UPS and Switch board shall be equipped for mod bus
communication for remote monitoring.
Note-1-Spacing of the Electrical panels, Battery Banks shall as per CEA/OISD/IS rules
from the wall as well as spacing with other adjacent equipments.
Note-2-Silent DG set of suitable rating shall be considered for the charging of the
Battery bank charging in case of larger power outage at IP stations.
633 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
Electrical equipment and system design, manufacture, testing, installation and commissioning
will comply with all the latest applicable standards, regulations and codes as mentioned
below:
Note- M.B. Lal Committee recommendation to be followed in all electrical design &
installations.
2.1 In case of imported equipments standards of the country of origin shall be applicable if these
standards are equivalent or stringent than the applicable Indian standards.
2.2 The equipment shall also confirm to the provisions of Indian Electricity rules and other
statutory regulations currently in force in the country.
2.3 In case of any contradiction between various referred standards/ specifications/ data sheet
and statutory regulations the following order of priority shall govern.
Statutory regulations.
Data sheets.
Scope of Work/ Job specification.
Design Basis.
Standard Specification.
Codes and standards.
b) Frequency - 50 Hz +/- 5 %
1 Ph & N (2W)
Total Running load of a Station = 100% of Continuous Load + 50% of the Intermittent Load + 20% of
the Stand-by Load.
Metering shall be provided to keep a record of power consumption and supervision of all concerned
parameters like current, voltage, power, frequency, power factor etc.
Electrical Control
UPS system, Solar charger panels, PDB panels & Generator APFC panels shall be provided with
Hardwired (4-20mA) as well as on serial communication (RS-485 Modbus) . CP Unit shall be
provided with Hardwired (4-20mA) connectivity only, as double monitoring will cause early failure of
Reference cell of CP unit. Different panels will be provided with above mentioned capabilities for
interconnection with OWNER'S Control System at the terminals and RTU at the remote station via
Modbus protocol or TCP / IP communication
4.1 Lux level in the plant area for calculation of lighting fixture is as follow:
Pump Houses (Product Pump 100-150 LED lights With flame proof
Houses), T/W Pumps, Sheds fittings
Main Operation Platform & 60-80 LED lights With flame proof
access stairs (within tank farm) fittings
Switchgear Bldg/ MCC Room/ 150-200 9W, 12W, 18W, 36W LED
DG Room/Shed Lights (Recessed/Surface
fixtures)
Transformer Bay/ Switchyard 100-200 LED Pole Mounted fittings
636 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
Control Room bldg/ Laboratory 400-500 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Charger/UPS room 150-200 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Warehouse 100-150 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Office room 300-400 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Watch room/ Watchman Booth 100-150 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Stairs 50-70 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Corridors 70-100 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Fire House/ Garage 100-150 9W, 12W, 18W, 36W LED
Lights (Recessed/Surface
fixtures)
Factor of Safety-
CFL/LED/Induction - 10%
All electrical fixtures for Hazardous area shall be classified type (Flame proof) as per the Area
Classification given in this document and have approval of respective statutory agency as per
the petroleum Act, 2002.
4.2 Emergency lighting system for indoor & outdoor lighting by separate Inverter system.
b) Relative Humidity : 95 %
c) Altitude above sea level : Less than 1000 M above mean sea level
d) Atmospheric condition : To withstand site condition
(Dry, dust storms during summer, Humid & Heavy
Rainfall during Monsoon)
e) Hazardous area
Classification : Zone-I & II, Gas group IIA & IIB, Temp. Class T3
Classification of hazardous area will be in accordance with BIS and IS: 5572.
Following selection will be considered for proper selection of electrical equipment for use in
hazardous area:
c) Temperature Classification : T3
All electrical equipment installed in hazardous area will be selected as per IS: 5571.
All electrical equipment for hazardous area will have CMRI certification
The electrical equipment installed outdoor will have the following enclosure Protection
- IP 65
The type of enclosure in the plant / process area shall be Flame proof (Ex-d)
8.1 No. of earth pit will be provided as per IS: 3043 and as per site requiement.
8.2 All equipment earthing to be carried out as per IS: 3043, minimum size of GI/Copper earth
conductor to be used will be as given below.
Equipments Earthing Conductor size 638 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
8.3 Earthing Electrode will be GI pipe for electrical system & Copper plate for instrument/ SCADA
& Telecom system.
8.4 Minimum 10 Nos. GI Pipe electrodes for each station will be provided as per IS- 3043 and as
per site requirement. (6 Nos. for equipment , 2 Nos transformer body earthing, 2 Nos.
Transformer neutral earthing).
8.5 Minimum 2 Nos. Copper Plate Electrodes will be provided for RTU / Control Panel at each
station.
8.6 Minimum 2 Nos. Copper Plate Electrodes will be provided for Telecommunication System at
each station.
8.7 Minimum 2 Nos. Copper Plate Electrodes will be provided for UPS system at each station.
8.8 Minimum 2 nos. near Control room building
8.9 Lightning protection system shall be provided as per IEC 62305 and with class II lighting
protection system (LPS) and LPL –II or minimum 2 nos..
8.10 Advanced maintenance free earthing with carbon backfill for process area (min 2 or 4nos )
and non-maintenance free for other than process area.
8.11 Earthing system shall cover electronic equipment earthing system, neutral earthing system,
static & lightning protection. Earthing shall be carried out as per IS-3043
The resistance value of Earthing and Lightning System shall be less than 5 ohm for electrical
earthing and 1 ohm for instrumentation earthing
9.0 CABLES
XLPE insulation
Inner sheath will be ST2
Inner and outer sheath will be extruded.
Steel strip / wire armoured.
Outer sheath of cable will be FRLS PVC, ST2 type.
Voltage grade – 11000 V (UE)
Applicable standard: IS-7098 Part I & II.
XLPE insulation
Inner sheath will be ST2
Inner and outer sheath will be extruded.
Steel strip / wire armoured.
Outer sheath of cable will be FRLS PVC, ST2 type.
Voltage grade – 1100 V
Applicable standard: IS-7098 Part I & II.
1.5 mm2 stranded Copper PVC insulated wire in concealed PVC conduit will be
used in lighting fixtures.
3 core 2.5 mm2 stranded copper cable (YWY) will be used for flameproof
fixtures.
3 core 2.5 mm2 stranded copper cable (YWY) will be used from outdoor lighting
DB to junction box on the lighting poles.
3 core 2.5 mm2 stranded copper cable (YWY) will be used from junction box on
the lighting poles to lighting fixture.
4 core 2.5 mm2 stranded copper cable (YWY) will be used for lighting in shed area.
4mm2 stranded Copper PVC insulated wire in concealed PVC conduit for 5/15 amp
switch socket, 20A Industrial switch socket.
640 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
CABLING SYSTEM
Voltage Drops
Maximum allowable Voltage Drop for feeder under steady state condition at full load as mention
below:
Cable between transformers secondary to PDB - 0.5%
Cable between PDB to Sub DBs - 0.5%
Cable between sub DBs to motors - 5.0%
Cable between Lighting DB to Lighting points - 4.0%
DC Circuit - 3.0%
During Motor start-up - 15.0%
Back – up Time of Ni-Cd Battery - 12 Hrs for UPS/48 Hrs for Solar PV system
Solar Photo Voltaic System - Photovoltaic System (System Capacity Min 10kWp)
11.1 All A.C. will be supplied power 230V, 50 Hz, 1 Ph & N and Control room temperature will be
maintained 24˚ C±2˚C with 8 hrs timer.
641 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
Switch board shall be equipped with energy saving device, and Meters with mod bus
communication. Insulating mats shall be provided in front & rear side of panels
Switchgear and associated equipment fed from generators and transformers shall have rating
at least equal to the rating of respective generators and transformers feeding it, under any
circuit configuration. Generator incomer shall be rated w.r.t. maximum power output of the
generator set over entire operating temperature range. Transformer Incomer feeder’s rating
shall be decided by respective State Electricity Board
Bus tie circuit breakers shall have same rating as the incomer
All other switchgears/switchboards not directly fed from generator and transformers shall have
rating at least equal to the maximum demand under any circuit configuration. Incomers of
these switchgears/switchboards shall be designed to cater to the complete load.
Spare outgoing feeders shall be provided in all LV switchgear/switchboards. For other
switchboards (and where not specifically indicated in SLD), at least one number of each type
of outgoing feeder or 20% of same feeder type.
The following protections shall be provided for safety of electrical system and personnel but
not limited to as below:
- RCBO protection for sensitive earth leakage protection for lighting circuit.
- RCBO shall be provided in AC circuits
- MCB protection for overload and short circuit for UPSDB and SSDB.
- MCCB based incomer for MEDB for short circuit, over current and earth fault release/shunt
trip.
- Bore well pump motor (if any) starter feeder shall incorporate thermal overload, short circuit
protection.
- Outgoing feeders of MEDB incorporating shall have MCCB over current, short circuit and
earth fault leakage protections.
- The Switchboard shall be suitable for bottom entry, if not specifically mentioned in any other
place of the document and shall be provided with removable gland plate.
For SV stations of pipeline, a hybrid solar power system with battery back-up of 48 hours (2
days) considered for power supply to Critical loads (i.e. PCP system, Instrument, SCADA,
Telecom).
A servo stabilizer (Automatic Voltage regulator) is also considered to improve the voltage
level of rural feeder of SEB.
For RT, IP & SV cum DT stations, UPS system (7.5 KVA / 5 KVA) with 12 hr battery backup
has been considered for power supply to Critical loads (i.e. PCP system, Instrument, SCADA,
Telecom).
642 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
14.1 Power connectivity from nearest available power source through Overhead Conductor/Cables
(O/H or U/G) alongwith all requisite materials upto Double Pole structure of GAIL terminal
shall be executed by SEB on depositary basis or by the Contractor (If SEB permits to execute
this work by the Contractor). All the payments towards works executed on depositary basis
shall be paid by the Owner.
14.2 Supply, Installation, Testing & Commissioning works of Distribution Transformer & Double
Pole structure at GAIL terminal shall be executed by SEB on depositary basis or by the
Contractor (If SEB permits to execute this work by the Contractor). All the payments towards
works executed on depositary basis shall be paid by the Owner.
14.3 Contractor shall carry out all the required liasioning with concerned authorities for the above
mentioned works (Sr. no.14.1 & 14.2) including all works related to statutory approvals of the
complete installation, from competent authority like CEA, DGMS, State electricity
Authority/Board etc .
The submission of application on behalf of the Owner to Govt. Authority/ Central Electricity
Authority, if required along with copies of required certificates complete in all respects, shall
be done by the contractor well ahead of time so that the actual commissioning of are not
delayed for want of approval from authority. The actual inspection of work by the Govt.
inspector shall be arranged by the Contractor and necessary coordination and liaison work in
this respect shall be the responsibility of the contractor. However any fee paid to the Govt.
Authority in this regard shall be reimbursed by the Owner on submission of bills with
documentary evidence.
The Inspection and acceptance of the work as above shall not absolve the Contractor from
any of responsibilities under this contract.
15.1 Regulation :
All necessary drawings, calculations, test certificates, etc. as required by Electrical Inspector
/Competent Authority shall be furnished.
16.1 The following documents shall be submitted along with the offer:
a) Filled up data sheet/Checklist.
b) HSE Policy
c) Bar Charts & Project completion schedule
d) QAP
643 of 896
SRIKAKULAM-ANGUL
MECON LIMITED Electrical Section, Delhi PIPELINE PROJECT
DELHI (PART-B)
16.2 The following drawings (in three sets) & documents shall be submitted for approval within 3
weeks of award of contract.
16.3 After the job completion, contractor shall prepare AS-BUILT drawings/data sheets and
documents, submit catalogues/manuals (O&M) of major brought out items. Final certified as
built drawings, documents and manuals etc shall be submitted by the contractor to owner in
bound volume with one set in soft copy (CD) plus five sets of prints to owner & one set to
MECON..
Other drawings and documents shall be submitted by contractor/MECON along with AS-BUILT
Drawings/Datasheets-
644 of 896
SCOPE OF WORK
(ELECTRICAL SYSTEM)
645 of 896
*$,/,1',$/,0,7('
ELECTRICAL SCOPE OF WORKS
65,.$.8/$0$1*8/3,3(/,1(352-(&73$57%
7(50,1$/:25.6
(/(&75,&$/6(&7,21
0(&21/,0,7(''(/+,
'RFXPHQW1R 5HYLVLRQ1R 'DWH
0(&9$((
&RS\ULJKW0(&21/LPLWHG±$OOULJKWVUHVHUYHG
7+,6'2&80(17,67+(62/(3523(57<2)0(&21$1',668(')257+(63(&,),&352-(&70(17,21('+(5(,17+,6,612772%(
&23,('2586(')25$1<27+(5352-(&7681/(66(;3/,&,7/<3(50,77('%<0(&21
646 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
&RQWHQWV
Sl. No. Description
1.0 GENERAL
2.0 SCOPE
5HY1R 'DWH 3UHSDUHG%\ &KHFNHG%\ $SSURYHG%\
$DVKLV0R\DO 0.-DLVZDUD $%KRZPLF
6U0JU 6U0JU *0(OHFW
&RS\ULJKW0(&21/LPLWHG±$OOULJKWVUHVHUYHG
7+,6'2&80(17,67+(62/(3523(57<2)0(&21$1',668(')257+(63(&,),&352-(&70(17,21('+(5(,17+,6,612772%(
&23,('2586(')25$1<27+(5352-(&7681/(66(;3/,&,7/<3(50,77('%<0(&21
647 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
1.0 GENERAL
1.1 Introduction
GAIL (India) Limited a public sector under Petroleum ministry, intends to develop Natural
Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh) to Angul
(Odisha) Natural Gas Pipeline Project and its Spurlines in the state of Odisha and Andhra
Pradesh for industrial consumers as well as City Gas Distribution System (CGD).
This pipeline will connect various RLNG terminals like, Dhamra, Dahej, Ennore,
Gangavaram, FSRU etc. and domestic gas fields of K G basin, Off-shore/On-shore fields to the
customers in Eastern region through JHBDPL and Southern region through KSPL.
Therefore, it will provide connectivity to multiple sources to the en-route customers. In view of
the same it has strategic importance and part of National Gas Grid.
M/s MECON Ltd has been engaged by M/s GAIL (India) Limited to carry out design,
engineering, procurement, inspection & Project Management Consultancy Services required for
18”/12” NB x 322 Kms. (approx.) pipeline (Part-B of SAPL Pipeline) from IP-4cum DT (of SAPL
Part-A) at Ch 0.00km to Receiving Terminal at Utkal Alumina (Ch 190.8km), SV-6S cum DT at
Ch 158.4km to RT at Vedanta (Ch 68.3km) and .SV-7S cum DT at Ch 178.4km to RT at Nalco
(Ch 62.97km).
The intent of this specification is to define the requirements for the supply of equipment and
materials (as required), erection, testing and commissioning of the electrical power distribution
system.
The work shall be carried out in the best workmanship – like manner, in conformity with these
specifications, approved drawings and the instructions of the Engineer-in-charge from time
to time.
In case of any conflict between the codes and standards listed, the same shall be brought to
the notice of Owner/Consultant for final decision, which shall be binding.
1.2 Standards
The work shall be performed in conformity with, standard specifications and installation
standards enclosed and code of practices of the Bureau of India Standards. In case of any
conflict, the stipulations under this specification shall govern.
In addition, the work shall also conform to the requirements of the following:
The Indian Electricity Act, and the rules framed there under
The fire Insurance Regulations
The regulations laid down by the Chief Electrical Inspector of the state government / Central
Electricity Authority (CEA).
The regulations laid down by the Factory Inspector.
The regulations laid down by the Chief Inspector of Explosives.
Any other regulations laid down by the Central, State or Local Authorities from time to time
during the pendency of this contract.
M.B.Lal Committee recommendations for electrical design & installation.
,Q FDVH RI DQ\ FRQWUDGLFWLRQ EHWZHHQ YDULRXV UHIHUUHG VWDQGDUGV VSHFLILFDWLRQV GDWD VKHHW
648 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
DQGVWDWXWRU\UHJXODWLRQVWKHIROORZLQJRUGHURISULRULW\VKDOOJRYHUQ
6WDWXWRU\UHJXODWLRQV
625
6FRSHRI:RUN-REVSHFLILFDWLRQ
'HVLJQ%DVLV
6WDQGDUG'DWDVKHHWV
6WDQGDUG6SHFLILFDWLRQ
&RGHVDQGVWDQGDUGV
1.3 Guarantee
The contractor shall guarantee the installation against any defects of workmanship and
materials (supplied by the contractor) for a period of 12 months from the date of issue of the
completion certificate. Any damage or defects connected with the erection of materials,
equipments or fittings supplied by the contractor that may be undiscovered at the time of
issue of the completion certificate, or may arise or come to light thereafter, shall be rectified or
replaced by the contractor at his own expense as deemed necessary and as per the instruction
of the Engineer-in-charge within the time limit specified by the Engineer-in-charge.
The above guarantee shall be applicable for the quality of work executed as well as for the
equipment / cable / fittings/ other material supplied by the contractor
1.4 Site Conditions
The equipment offered and the installation shall be suitable for continuous operation under the
following site conditions.
b) Relative Humidity : 95 %
c) Altitude above sea level : Less than 1000 M above mean sea level
d) Atmospheric condition : To withstand site condition
(Dry, dust storms during summer, Humid & Heavy
Rainfall during Monsoon)
e) Hazardous area
Classification : Zone-I & II, Gas group IIA & IIB, Temp.
Class T3
BY INVERTER
INSTRUMENTATION 230 V AC, 1 Phase
(UPS) 24 V DC
TELECOM SYSTEM (UPS) 230 V AC, 1 Phase
-48 V DC
SCADA (UPS) 230 V AC, 1 Phase
24 V DC
CP SYSTEM (UPS) 230 V AC, 1 Phase
FA & CO2 FLOODING SYSTEM (UPS) 230VAC
)(3&&79(3$%; 230 V AC, 1 Phase
6&23(
)RU6HF,$OOHOHFWULFDOZRUNVIRUIROORZLQJSLSHOLQHWHUPLQDOVLVLQVFRSHRIFRQWUDFWRU
D 6960DQXDOO\RSHUDWHG
E ,36
)RU6HF,,$OOHOHFWULFDOZRUNVIRUIROORZLQJSLSHOLQHWHUPLQDOVLVLQVFRSHRIFRQWUDFWRU
D 6965HPRWHO\RSHUDWHG
E 6960DQXDOO\RSHUDWHG
F 6965HPRWHO\RSHUDWHG
G 696$0DQXDOO\RSHUDWHG
H 6965HPRWHO\RSHUDWHG
I 696FXP'7IRU&RQVXPHU9HGDQWD
J 696FXP'7IRU&RQVXPHU1DOFR
K 57DW8WNDO$OXPLQD
650 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
)RU6HF,,,$OOHOHFWULFDOZRUNVIRUIROORZLQJSLSHOLQHWHUPLQDOVLVLQVFRSHRIFRQWUDFWRU
)RU6HF,9$OOHOHFWULFDOZRUNVIRUIROORZLQJSLSHOLQHWHUPLQDOVLVLQVFRSHRIFRQWUDFWRU
+RZHYHU6XSSO\,QVWDOODWLRQWHVWLQJ FRPPLVVLRQLQJRI33/'%/7'%2/'%,QYHUWHU6RODU
0RGXOHV6RODU&KDUJHU)&%& %DWWHU\VHWIRU3&3V\VWHPDWWKLVWHUPLQDOLQVLGHSRUWDFDELQ
LVLQVFRSHRIWKLVFRQWUDFWXQGHU&RQWUDFWRU¶VVFRSH,QFRPLQJSRZHUWR/7'%VKDOOEHSURYLGHG
WKURXJK 7KUHH SKDVH /7 FRQQHFWLRQ UDWLQJ DV SHU 625 LQVWDOOHG QHDU *XDUGURRP%RXQGDU\
ZDOODQGVXSSO\ LQVWDOODWLRQRIWKHVDPHLVLQVFRSHRIWKLVFRQWUDFWXQGHU&RQWUDFWRU¶VVFRSH
$OO WKH (OHFWULFDO ZRUNV DW WKHVH WHUPLQDO HDUWKLQJ OLJKWQLQJ SURWHFWLRQ RXWGRRU OLJKWLQJ
V\VWHPFDEOLQJZRUNVLQVLGHWHUPLQDOHWFLVXQGHU&RQWUDFWRU¶VVFRSH
b) 6L[QRV0DQXDO69WHUPLQDOV696696$699699691 691VKDOO
QRWKDYH&RQWUROURRPEXLOGLQJ /7'%FXP2/'%VKDOOEHPRXQWHGLQVLGH*XDUGURRP3RUWD
FDELQW\SH
651 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
6XSSO\,QVWDOODWLRQWHVWLQJ FRPPLVVLRQLQJRI/7'%FXP2/'%LQVLGHSRUWDFDELQLVLQVFRSH
RIWKLVFRQWUDFWXQGHU&RQWUDFWRU¶VVFRSH,QFRPLQJSRZHUWR/7'%FXP2/'%VKDOOEHSURYLGHG
WKURXJK 7KUHH SKDVH /7 FRQQHFWLRQ UDWLQJ DV SHU 625 LQVWDOOHG QHDU *XDUG URRP%RXQGDU\
ZDOODQGVXSSO\ LQVWDOODWLRQRIWKHVDPHLVLQVFRSHRIWKLVFRQWUDFWXQGHU&RQWUDFWRU¶VVFRSH
$OOWKH(OHFWULFDOZRUNVDWWKHVHWHUPLQDOHDUWKLQJ OLJKWQLQJSURWHFWLRQRXWGRRUOLJKWLQJ
V\VWHPFDEOLQJZRUNVLQVLGHWHUPLQDOHWFLVXQGHU&RQWUDFWRU¶VVFRSH
7RWDOQRV69WHUPLQDOVDUHPDQXDOO\RSHUDWHGLQ6$3/3DUW$SURMHFWUHIHU6FKHPDWLF
GLDJUDPIRU6$3/3DUW$
a) )LYHQRV0DQXDO69WHUPLQDOV69696969 69VKDOOKDYHSRUWDFDELQIRU
KRXVLQJ )&%& %DWWHU\ VHW 2/'% &3 8QLWV Supply, installation, testing & commissioning of
CP units, PPLDB, LTDB, OLDB, Inverter etc are not in scope of this contract. Same shall be
supplied, installed, tested & commissioned by other contractor through separate tender.
+RZHYHU6XSSO\,QVWDOODWLRQWHVWLQJ FRPPLVVLRQLQJRI6RODU0RGXOHV6RODU&KDUJHU)&%&
%DWWHU\ VHW IRU 3&3 V\VWHP DW WKHVH ILYH WHUPLQDOV LQVLGH SRUWD FDELQ LV LQ VFRSH RI WKLV
FRQWUDFWXQGHU&RQWUDFWRU¶VVFRSH3OHDVHUHIHU3-6RI6RODUV\VWHPVIRUPRUHGHWDLOV
,QFRPLQJSRZHUWR/7'%VKDOOEHSURYLGHGWKURXJK7KUHHSKDVH/7FRQQHFWLRQUDWLQJDVSHU
625LQVWDOOHGQHDU*XDUGURRP%RXQGDU\ZDOODQGSame shall be supplied, installed, tested &
commissioned by other contractor through separate tender.
$OO RWKHU (OHFWULFDO ZRUNV DW WKHVH WHUPLQDO HDUWKLQJ OLJKWQLQJ SURWHFWLRQ RXWGRRU OLJKWLQJ
V\VWHPFDEOLQJZRUNVLQVLGHWHUPLQDOHWFshall be supplied, installed, tested & commissioned by
other contractor through separate tender.
2.2.1 415V, 30 KA Single Front Indoor LT Panel to receive and distribute power for all stations, LDBs
etc as per SLD no. MEC/23VA/05/E9/E/1081 (A to I).
09 SRZHU DQG FRQWURO FDEOH ;/3( ± LQVXODWHG DUPRXUHG $O&X FRQGXFWRU FRUH
FDEOHV
*, SLSHV *, &DEOHWUD\V DQG DFFHVVRULHV FDEOH PDUNHUV LGHQWLILHU WDJV *, VDGGOHV DQG DOO
RWKHUDVVRFLDWHGDFFHVVRULHVIRUFDEOHOD\LQJ
)/3 &05, 3(62 DSSURYHG W\SH GRXEOHFRPSUHVVLRQ QLFNHOSODWHG EUDVV FDEOH JODQGV
WLQQHGFRSSHUOXJVFODPSLQJPDWHULDOHWFIRUFDEOHWHUPLQDWLRQ
6WUXFWXUDO VKHG WR KRXVH $95 W\SH UDWLQJ DV SHU 625 FRPSOHWH LQ DOO UHVSHFW DW DOO
WHUPLQDOVH[FHSW0DQXDO69VWDWLRQV
652 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
)RU57,369FXP'7695HPRWHO\RSHUDWHG 696WHUPLQDOV
,QGRRU /LJKWLQJ /LJKWLQJ V\VWHP (OHFWULFDO ILWWLQJV ^OLJKWLQJ IL[WXUHV QRUPDO DV ZHOO DV
FULWLFDOH[KDXVWIDQVFHLOLQJIDQVZDOOPRXQWHGIDQVWHOHSKRQHVRFNHWV/$1VRFNHWV0')V
VZLWFKHVVRFNHWVVZLWFKERDUGVDOOWKHZLULQJ FRQGXLWLQJZRUNV39&FRQGXLWWREHODLGLQWKH
FRQFUHWHVODERWKHUFLYLOFRQVWUXFWLRQHWFLQVDIHDQGKD]DUGRXVDUHDIRUILWWLQJVFRPSOHWHLQ
DOOUHVSHFWHWF`LQVLGHRQ&RQWURO5RRPEXLOGLQJ5&&W\SH6WRUHURRPEXLOGLQJ *XDUGURRP
3RUWD FDELQ W\SH VKDOO EH VXSSOLHG LQVWDOOHG WHVWHG FRPPLVVLRQHG E\ OD\LQJ FRQWUDFWRU
WKHVDPHis considered in this tender under scope of laying contractor.
2XWGRRU /LJKWLQJ 6XSSO\ RI RXWGRRU VWUHHW OLJKWLQJ V\VWHP ERXQGDU\ OLJKWLQJ WUDQVIRUPHU
\DUGDUHDOLJKWLQJ$95VKHGDUHDOLJKWLQJ SURFHVVDUHDOLJKWLQJVWRUHDUHDOLJKWLQJFRPSOHWH
LQDOOUHVSHFWis considered in this tender under scope of laying contractor.
)RU0DQXDOO\RSHUDWHG69WHUPLQDOV
,QGRRU/LJKWLQJ/LJKWLQJV\VWHP (OHFWULFDOILWWLQJV^OLJKWLQJIL[WXUHVQRUPDODVZHOODVFULWLFDO
H[KDXVW IDQV FHLOLQJ IDQV ZDOO PRXQWHG IDQV WHOHSKRQH VRFNHWV /$1 VRFNHWV0')V
VZLWFKHVVRFNHWVVZLWFKERDUGVDOOWKHZLULQJ FRQGXLWLQJZRUNV39&FRQGXLWWREHODLGLQWKH
FRQFUHWHVODERWKHUFLYLOFRQVWUXFWLRQHWFLQVDIHDQGKD]DUGRXVDUHDIRUILWWLQJVFRPSOHWHLQDOO
UHVSHFW HWF` LQVLGHRQ *XDUG URRP 3RUWD FDELQ W\SH VKDOO EH VXSSOLHG LQVWDOOHG WHVWHG
FRPPLVVLRQHGE\OD\LQJFRQWUDFWRU WKHVDPHis considered in this tender under scope of
laying contractor.
2XWGRRU /LJKWLQJ 6XSSO\ RI RXWGRRU VWUHHW OLJKWLQJ V\VWHP ERXQGDU\ OLJKWLQJ SURFHVV DUHD
OLJKWLQJ HWF FRPSOHWH LQ DOO UHVSHFW is considered in this tender under scope of laying
contractor.
(DUWKLQJ DQG OLJKWQLQJ SURWHFWLRQ V\VWHP LQFOXGLQJ HDUWKLQJ SLWV HDUWK HOHFWURGHV HDUWKLQJ
VWULSVJURXQGLQJFRQGXFWRURIYDULRXVVL]HV&XVWULSIRUIODQJHMXPSHUDQG&XHDUWKSODWHVHWF
6DIHW\HTXLSPHQWLQWKHVWDWLRQVWHUPLQDOVOLNHVKRFNWUHDWPHQWFKDUWVFDXWLRQERDUGVILUVWDLG
HTXLSPHQWUXEEHUPDWVSRUWDEOHILUHH[WLQJXLVKHUVVDQGEXFNHWHWF
(OHFWULFLOOXPLQDWHGVWDWLRQGHWDLOERDUGDORQJZLWKPRXQWLQJVWUXFWXUH
$PS)ODPHSURRIW\SHZHOGLQJUHFHSWDFOHVHWF
$ VWDQG DORQH GXVNGDZQ VRODU SKRWRYROWDLF VWUHHW OLJKWLQJ V\VWHP IRU RXWGRRU HPHUJHQF\
OLJKWLQJDWYDULRXVVWDWLRQVDVSHUHQFORVHG6253-66RODUV\VWHPDQGVSHFLILFDWLRQ
2.2.13 5/7.5/15KVA UPS system, Rectifier, Battery Bank, ACDB / DCDB & interconnecting cables are
not in scope of this contract. Same shall be supplied, installed, tested & commissioned by other
contractor through separate tender.
However, Contractor scope of work includes incoming cables for UPS & all outgoing cables &
cabling work from various ACDB & DCDBs.
2.2.14 For Remotely Operated SV stations only : Hybrid Solar system (for 800W DC Load), grid
Charger & associated Solar Array/Panels, Anodised Al/Hot dip galvanized MS mounting
structure, Junction boxes, Charge controller, DCDB, Battery bank, DC-DC converter,
653 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
interconnecting cables among - arrays, charge controller, DC-DC Converter, DCDB, Battery
bank, 3Ph charger etc are not in scope of this contract. Same shall be supplied, installed,
tested & commissioned by other contractor through separate tender.
However, Contractor scope of work includes incoming cables for Solar system & all outgoing
cables& cabling work from various DBs.
2.2.15 For Manually Operated SV stations only : Solar system (for PCP system load at locations as
mentioned in Solar PJS), Solar Charger & associated Solar Array/Panels, Anodised Al/Hot dip
galvanized MS mounting structure, Junction boxes, Charge controller, DCDB, Battery bank,
DC-DC converter, interconnecting cables among - arrays, charge controller, DC-DC Converter,
DCDB, Battery bank, 3x1Ph charger etc are in scope of this contract under Contractor’s scope.
Same shall be supplied, installed, tested & commissioned by contractor as per SOR & Solar
PJS as briefed at Clause no. 2.1.4 & 2.1.5 of this document.
The work shall be completed in all respect.
,QYHUWHUIRUHPHUJHQF\FULWLFDOOLJKWLQJ
2.2.20 N9.9$FRSSHUZRXQG'LVWULEXWLRQ7UDQVIRUPHU
'LVWULEXWLRQ7UDQVIRUPHUZLWK'RXEOH3ROH*DQJVZLWFKRYHUKHDG&RQGXFWRURIVXLWDEOHUDWLQJ
DQG DOO QHFHVVDU\ DFFHVVRULHV IRU FRPSOHWLRQ RI ZRUN LQFOXGLQJ WDSSLQJ IURP H[LVWLQJ +7 OLQH
HWF FRPSOHWH DV SHU VSHFLILFDWLRQ 625 DQG UHTXLUHPHQW RI DSSURYDO IURP UHVSHFWLYH
HOHFWULFLW\VWDWXWRU\ DXWKRULW\ $OO HOHFWULFDO ZRUN LH FKDUJLQJ RI WUDQVIRUPHU SROH PRXQWHG
VXEVWDWLRQ WDSSLQJ IURP EDWWHU\ OLPLW RI HOHFWULFLW\ ERDUG VKDOO EH FDUULHG RXW LQ VXSHUYLVLRQ RI
UHVSHFWLYHDXWKRULW\LQFOXGLQJQHFHVVDU\DSSURYDOLIUHTXLUHG
'RXEOHSROHVWUXFWXUHZLWK$%6ZLWFK/LJKWQLQJDUUHVWRUVKRUQJDSIXVHFRSSHUZLUHMXPSHUV
XSWRWUDQVIRUPHU+7WHUPLQDOV
$&65 FRQGXFWRU P 06 MRLQWSROH 3LQ LQVXODWRU DQG *, KDUGZDUH HWF DV UHTXLUHG IURP
UHVSHFWLYHVWDWHHOHFWULFLW\ERDUGEDWWHU\OLPLWXSWRGRXEOHSROHVWUXFWXUHLQVLGH*$,/7HUPLQDO
&DEOHV EHWZHHQ WUDQVIRUPHU /7 WHUPLQDOV RI WUDQVIRUPHU ORDG EUHDN IXVH VZLWFK XQLW FDEOH
VXSSRUWVGRXEOHFRPSUHVVLRQFDEOHJODQGVOXJVHWFDVUHTXLUHG
6XSSO\RI$731$&GXW\0&&%LQRXWGRRUW\SHGXVW ZHDWKHUSURRIVWHHOHQFORVXUH
6XSSO\RI+LJK0DVW/LJKWLQJV\VWHPRQPKLJKSROHFRQVLVWLQJIRUQRVRIOLJKWLQJIL[WXUHV
:/('/DPS )/3W\SH)HHGHU3LOODUSDQHO
7KUHH3KDVH/7'LVWULEXWLRQERDUGFXP2/'%UDWLQJDVSHU625DW0DQXDO69WHUPLQDOVQHDU
ERXQGDU\*XDUGURRPLQVLGH*$,/WHUPLQDO
654 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
6XSSO\RIN9$$95$XWRPDWLF9ROWDJH5HJXODWRU)ORRUPRXQWHG2XWGRRUGXW\,3 ,3
FRQWUROJHDUUDWLQJVDVSHU625FRPSOHWHLQDOOUHVSHFW
)DEULFDWLRQ DQG VXSSO\ RI 06 IUDPHV VXSSRUWV FDQRSLHV DQG EUDFNHWV IRU PLVFHOODQHRXV
HOHFWULFDO HTXLSPHQWV LQFOXGLQJ ZHOGLQJ VXSSO\ RI EROWV QXWV HWF IRU PRXQWLQJ DQG RWKHU
QHFHVVDU\VXSSOLHVDOOLQFOXVLYHRISDLQWLQJDVVSHFLILHG
&DEOH JODQG SODWH RI VXLWDEOH VL]H RI PLQ PP WKLFNQHVV VKDOO EH SURYLGHG IRU FDEOH
WHUPLQDWLRQZKHUHYHUUHTXLUHGIRUDOOWKHHOHFWULFDOSDQHOV3'%/'%2/'%836HWF
If the contractor fails to timely execution of the terminal work, necessary penalty clause shall
be applied as per the direction of the Engineer-in-Charge.
$OOZRUNVUHODWLQJWRVWDWXWRU\DSSURYDOVRIWKHFRPSOHWHLQVWDOODWLRQIURPFRPSHWHQWDXWKRULW\
OLNH&($'*066WDWHHOHFWULFLW\DXWKRULW\%RDUGHWFVKDOOEHLQWKHVFRSHRIFRQWUDFWRU
1RWHSLDs (MEC/23VA/05/E9/E/1081A to I) attached with tender documents are for tender purpose
only. Detailed SLD shall be furnished by the bidder as per the requirements of the system. Any
change, Modifications, Addition/deletion occurs later due to system requirements shall deem to be
inclusive in the price quoted by the bidder, No extra cost shall be paid for the same.
2.3 SCOPE OF INSTALLATION, TESTING & COMMISSIONING
2.3.1 Laying & termination of all MV/HV power and control cables laid in concrete-lined trenches,
buried cable trenches, pipes, road crossings, pipe-racks etc.
2.3.3 Installation, testing & commissioning of Outdoor type pole mounted 11/0.433 kV Transformer
substation.
2.3.4 Installation, testing & commissioning of Distribution Transformer with Double Pole, Gang
switch, over head Conductor of suitable rating and all necessary accessories for completion of
work including tapping from existing HT line etc. complete as per specification & SOR.
2.3.5 Installation, testing & commissioning of 11/0.433 kV, 100/63 KVA copper wound Distribution
Transformer.
2.3.6 Installation, testing & commissioning of Double pole structure with AB Switch, Lightning
arrestors, horn gap fuse, copper wire jumpers upto transformer HT terminals.
2.3.7 Installation, testing & commissioning of ACSR conductor, 7m MS joint/pole, Pin insulator and GI
hardware etc. as required from respective state electricity board battery limit upto double pole
structure inside GAIL Terminal.
655 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
2.3.8 Installation, testing & commissioning of Cables between transformer, LT terminals of
transformer & load break fuse switch unit, cable supports, double compression cable glands,
lugs etc as required.
2.3.9 Installation, testing & commissioning of 250 A TPN, AC-23 duty MCCB in outdoor type dust &
weather proof steel enclosure.
2.3.10(UHFWLRQRIVWUXFWXUDOVKHGWRKRXVH$95W\SH UDWLQJDVSHU625FRPSOHWHLQDOOUHVSHFW
DWDOOWHUPLQDOVH[FHSW0DQXDO69VWDWLRQV
2.3.11 Installation, testing & commissioning of High Mast Lighting system on 20m high pole consisting
for 8 nos. of lighting fixtures (200W LED Lamp) and FLP type Feeder Pillar Panel.
2.3.12 Installation, testing & commissioning of Three Phase LT Distribution board cum OLDB (rating
as per SOR) at Manual SV terminals near boundary/Guard room (inside GAIL terminal)
2.3.13 Installation, testing & commissioning RI N9$ $95$XWRPDWLF 9ROWDJH 5HJXODWRU )ORRU
PRXQWHG 2XWGRRU GXW\ ,3 ,3 FRQWURO JHDU UDWLQJV DV SHU 625 FRPSOHWH LQ DOO
UHVSHFW
2.3.14 Installation, testing and commissioning of outdoor street lighting system & lighting system for
process area.
2.3.15 Installation, testing & commissioning of earthing system & complete lightning protection
system.
2.3.17 Installation testing & commissioning of Oil filled transformer and pole mounted HT substation.
2.3.21 Installation testing & commissioning of Electric illuminated station detail board
2.3.22 Installation, testing & commissioning of Solar system for 200W DC load at Manual SV stations
having PCP units , as per Scope of work, Solar PJS & SOR.
2.3.23 )RU57,369FXP'7695HPRWHO\RSHUDWHG 696WHUPLQDOV
2XWGRRU /LJKWLQJ ,QVWDOODWLRQ WHVWLQJ FRPPLVVLRQLQJ RI RXWGRRU VWUHHW OLJKWLQJ V\VWHP
ERXQGDU\OLJKWLQJWUDQVIRUPHU\DUGDUHDOLJKWLQJ$95VKHGDUHDOLJKWLQJ SURFHVVDUHDVWRUH
DUHDOLJKWLQJFRPSOHWHLQDOOUHVSHFW is considered in this tender under scope of laying
contractor.
)RU0DQXDOO\RSHUDWHG69WHUPLQDOV
2XWGRRU /LJKWLQJ ,QVWDOODWLRQ WHVWLQJ FRPPLVVLRQLQJ RI RXWGRRU VWUHHW OLJKWLQJ V\VWHP
ERXQGDU\ OLJKWLQJ SURFHVV DUHD OLJKWLQJ HWF FRPSOHWH LQ DOO UHVSHFW is considered in this
tender under scope of laying contractor.
656 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
2.3.25 All works relating to statutory approvals of the complete installation, from competent authority
like CEA, DGMS, State electricity authority/Board etc, shall be in the scope of contractor
27+(50,6&(//$1(286:25.6
3UHSDUDWLRQ RI EXULHG FDEOH WUHQFKHV LQFOXGLQJ EDFN ILOOLQJ FRPSDFWLQJ SURYLGLQJ RI EULFN
SURWHFWLRQE\VHFRQGFODVVEULFNVVSUHDGLQJRIILQHULYHUVDQGLQFOXGLQJDOOVXSSOLHV
7KHMRELQFOXGHVUHSDLULQJRIDOOFLYLOZRUNVGDPDJHGGXULQJLQVWDOODWLRQRIHOHFWULFDOIDFLOLWLHV
7KH VFRSH RI ZRUN XQGHU WKLV FRQWUDFW VKDOO EH LQFOXVLYH RI EUHDNLQJ RI ZDOOV IORRUV DQG
FKLSSLQJ RI FRQFUHWH IRXQGDWLRQV QHFHVVDU\ IRU WKH LQVWDOODWLRQ RI HTXLSPHQW PDWHULDOV DQG
PDNLQJJRRGRIWKHVDPH
0LQRU PRGLILFDWLRQV ZKHUHYHU UHTXLUHG WR EH GRQH LQ WKH RZQHU IUHH VXSSOLHG HTXLSPHQWV
GHYLFHVWRHQDEOHFDEOHHQWU\WHUPLQDWLRQHWF
6HDOLQJ RI RSHQLQJ PDGH LQ WKH ZDOOV IORRUV IRU FDEOHV WUD\V FDEOHV EXV GXFWV HWF XVLQJ
DFFHSWDEOHSUDFWLFHDQGVWDQGDUGV
6XSSO\DQGLQVWDOODWLRQRIDOORWKHUDFFHVVRULHVQRWVSHFLILFDOO\PHQWLRQHGKHUHLQEXWQHYHUWKH
OHVVQHFHVVDU\IRUFRPSOHWLRQRIWKHMRE
$5($&/$66,),&$7,21
Hydrocarbon handling areas have been generally classified as zone 1 & 2, gas group IIA/IIB as
per IS: 5572, API RP-500, OISD - 113 and IP Rules. All equipments to be installed in these
areas shall be suitable for the area classification with temperature class T3 (2000C), CMRI
testing and approved by CCOE, DGFAS and having BIS license.
-2%63(&,),&$,7216
Various electrical works covered under this contract like equipment erection, cabling, lighting
and grounding works, etc. shall be performed in accordance with specifications attached with
this tender. (Certain clauses of specifications, which are applicable to equipments or system not
covered under this contract, shall not be applicable).
67$78725<$33529$/2):25.6
All works relating to statutory approvals of the complete installation, from competent authority
like CEA, DGMS, State electricity Authority/Board etc, shall be in the scope of contractor.
The application on behalf of the owner for submission to Electrical Inspector / DGMS etc. along
with copies of required certificates and drawings, complete in all respects, shall be prepared by
657 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
the contractor and submitted to the Engineer-in-charge for onward transmission well ahead of
time so that the actual commissioning of equipment are not delayed for want of inspection by
the Electrical Inspector / DGMS. The actual Liaison work shall be arranged by the Contractor
and necessary coordination and liaisons work in this respect shall be responsibility of the
contractors. However, the Owner on submission of bills along with documentary evidence shall
reimburse any fee paid to the statutory Authority in this regards.
0$.(62)(48,30(176$1'0$7(5,$/6
$OOHTXLSPHQWVPDWHULDOVVXSSOLHGE\WKHFRQWUDFWRUVKDOOEHDVSHUWKHOLVWRIDSSURYHGPDNHV
HQFORVHGZLWKWKLVGRFXPHQWVXEMHFWWRVXEPLVVLRQRI&HUWLILFDWLRQDQGDSSURYDOV
658 of 896
SRIKAKULAM - ANGUL
MECON LIMITED (OHFWULFDO6HFWLRQ'HOKL PIPELINE PROJECT (PART-B)
DELHI
'5$:,1*667$1'$5'63(&,),&$7,216$1',167$//$7,2167$1'$5'6
7KHHTXLSPHQWVPDWHULDOVWREHVXSSOLHGE\WKHFRQWUDFWRUVKDOOFRQIRUPWRWKHUHTXLUHPHQWV
RI WKH DSSOLFDEOH VSHFLILFDWLRQV $OVR WKH LQVWDOODWLRQ RI YDULRXV PDWHULDO HTXLSPHQW VKDOO
FRQIRUPWRWKHLQVWDOODWLRQVWDQGDUGVQRUPV
7KH GUDZLQJV DFFRPSDQ\LQJ WKH WHQGHU GRFXPHQWV ZKHQ UHDG ZLWK VSHFLILFDWLRQ VKDOO GHSLFW
WKHHOHFWULFDOV\VWHPRIWKH7HUPLQDO7KHVHDUHLQGLFDWLYHRIWKHQDWXUHRIZRUNDQGLVVXHGIRU
WHQGHULQJSXUSRVHVRQO\3XUSRVHRIWKHVHGUDZLQJVLVWRHQDEOHWKHWHQGHUHGWRPDNHDQRIIHU
LQ OLQH ZLWK WKH UHTXLUHPHQWV RI WKH 2ZQHU &RQVWUXFWLRQ VKDOO EH DV SHU GUDZLQJV
VSHFLILFDWLRQV LVVXHG DSSURYHG E\ WKH (QJLQHHULQFKDUJH GXULQJ WKH FRXUVH RI H[HFXWLRQ RI
ZRUN
&RQGXLWOD\RXWGUDZLQJLQFHLOLQJZKHUHYHUUHTXLUHGWREHSUHSDUHGE\WKHFRQWUDFWRUDQGVKDOO
EHVXEPLWWHGIRUDSSURYDO
$IWHUWKHMREFRPSOHWLRQFRQWUDFWRUVKDOOSUHSDUH$6%8,/7GUDZLQJVDQGGRFXPHQWVVXEPLW
FDWDORJXHVPDQXDOV 2 0 RI PDMRU EURXJKW RXW LWHPV OLNH ,QYHUWHU +7 6XEVWDWLRQ /LJKWLQJ
IL[WXUHHWF)LQDOFHUWLILHGDVEXLOWGUDZLQJVGRFXPHQWVDQGPDQXDOVHWFVKDOOEHVXEPLWWHGE\
WKHFRQWUDFWRUWRRZQHULQERXQGYROXPHZLWKRQHVHWLQVRIWFRS\&'SOXVILYHVHWVRISULQWV
7(&+1,&$/ &5,7(5,$ )25 $&&(37$1&( (/(&75,&$/ 2) (/(&75,&$/
&2175$&725
&RS\RI(OHFWULFDO&RQWUDFWRU¶VOLFHQVH±*UDGH$IURP(OHFWULFDO/LFHQVLQJ%RDUGIRUN9RU
DERYHHQFORVHG
&UHGHQWLDO RI (OHFWULFDO &RQWUDFWRU ZKLFK VKRZV FRPSOHWLRQ RI +7 3DQHO .9 7UDQVIRUPHU
'*VHW/7SDQHOVOLJKWLQJHDUWKLQJHWF
7KH 0DLQ(OHFWULFDO &RQWUDFWRU VKDOO EH WKH VLQJOH SRLQW UHVSRQVLEOH YHQGRU IRU DOO HOHFWULFDO
HTXLSPHQWVOLNH/7SDQHO7UDQVIRUPHU'*6HWHWF
[[[
659 of 896
OIL & GAS SBU
SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
REVISION 0
TO BE FILLED-UP BY TENDERER
660 of 896
OIL & GAS SBU
SRIKAKULAM – ANGUL
PIPELINE PROJECT (PART-B)
ANNEXURE-A
661 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
(/(&75,&$/
LIST OF SUPPLIERS OF MAJOR BOUGHT-OUT ITEMS
Air Conditioner
1. O General
2. Daikin
3. Hitachi
Page 1 of 9
662 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
Solar PCU/Inverter
1. DELTA ELECTRONICS
2. ABB LTD
3. KACO
4. SMA
5. SCHNEIDER
6. STATECON ENERGIAA PVT LTD
Cable – HT(XLPE)
1. Universal Cable Ltd.
2. KEI Industries Ltd.
3. Industrial Cables
4. NICCO Corporation Ltd.
5. Uniflex
6. Polycab.
7. Torrent cables Ltd.
Page 2 of 9
663 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
9. Ravin
10. Rallison.
11. Suyog
12. Netco
13. Uniflex
14. Paramount
15. Gloster
16. Associated cables Pvt Ltd.
17. CMI
18. Gemscab
19. Industrial cables
20. NICCO
21. Polycab
22. Torrent
Cable – Gland
1. .Baliga
2. .Comet
3. Flexpro
4. Flameproof
5. FCG
6. Electro Werke
7. Dowels
8. CCI
Cable – Lugs
1. Dowels
2. Jainson
3. Ismal
Cable – Tray
1. Ercon Composites
2. Yamuna Power & Infrastructure Ltd.
Page 3 of 9
664 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
Contractors – AC Power
1 Andrew Yule
2 ABB
3 BHEL
4 C&S
5 Havell’s
6 L&T
7 Schneider
8 Siemens Ltd.
9 Telemechanique
Control Transformer
1. AE
2. Indushree
3. Intra Vidyut
4. Kalpa Electrikals
5. Transpower Industries Ltd.
6. Siemens
DG Set
1. Sterling and Wilson.
2. GD ankalesaria.
3. Deev Genset.
4. Jackson
5. Sudheer Gensets.
6. Power Engineering(India) Pvt Ltd.
Earthing Materials
1. Rukmani Electrical & Components Pvt Ltd.
2. Indiana Grating Pvt Ltd.
3. Jef Techno Solutions Pvt Ltd
Page 4 of 9
665 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
2. Sudhir
3. Prompt Engineering Works
4. Flame Proof equipments pvt. Ltd.
5. Baliga Lighting Equipments Pvt. Ltd.
6. Flexpro Electricals Pvt. Ltd.
High Mast
1. Bajaj Electricals Limited
2. Crompton Greaves Limited.
3. Philips India Limited
4. Surya Roshani
Indicating Lamps
1. Alstom Ltd.
2. BCH
3. L&T Ltd.
4. Siemens Ltd.
5. Vaishno Electricals
Indicating Meters
1. ABB
2. AMCO
3. AE
4. Alstom Ltd. (EE)
5. Conzerv/Schneider
6. Elecon Measurement Pvt. Ltd.
7. HPL Electric & Power Pvt. Ltd.
8. MECO Instruments Ltd.
9. Minilec
10. Rishabh Instruments Pvt. Ltd.
11. Trinity energy system
Page 5 of 9
666 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
12. kaycee
13. Salzer
Lighting Fixtures
1. GE Lighting Pvt. Ltd.
2. Bajaj Electricals Ltd.
3. Crompton Greaves Ltd.
4. Philips India Ltd.
Page 6 of 9
667 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
Low Voltage Power Control Center (PCC)/ MCC/ PDB/ MLDB/ LDB
1. ABB
2. BCH
3. C&S
4. Elecmech Switchgear & Instrumentation
5. KMG ATOZ
6. L&T
7. Pyrotech Electronics Pvt. Ltd.
8. Risha control Engineers Pvt. Ltd.
9. Siemens
10. Tricolite Electrical Industries
11. Unilec Engineers ltd.
12. Vidyut Control India Pvt. Ltd.
13. Control and Schematic
14. Zenith Engineering
Push Buttons
1. BCH
2. Alstom Ltd.
3. L&T
4. Siemens Ltd.
5. Telemenchanique & Controls (India) Ltd.
6. Vaishno Electricals
Switches-Control
1. BCH
2. Easum Reyrolle Relays & Devices Ltd.
3. Alstom
4. Kaycee Industries Ltd.
5. L&T
6. Siemens Ltd.
Page 7 of 9
668 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
Solar Modules
1. Tata BP Solar (I) Ltd.
2. REIL, Jaipur.
3. CEIL, Sahibabad.
4. HBL Power
Terminals Blocks
1. Connectwell
2. Controls & Switchgear Co. Ltd.
3. Elmex Controls Pvt. Ltd.
4. Essen Engineering Co. Pvt. Ltd.
Tranformers
1. ABB
2. Andrew Yule
3. Areva
4. BHEL
5. Bharat Bijlee
6. Crompton Greaves
7. EMCO Ltd.
8. Intra Vidyut
Page 8 of 9
669 of 896
SRIKAKULAM – ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
9. Indushree
10. Indcoil
11. Kirloskar
12. Skippers Electricals
13. Transformers & Rectifiers (I) Ltd.
14. Voltamp
GI-Octogonal Pole
1. Bajaj
2. Transrail
3. Wipro
127(,WHP9HQGRUZKLFKDUHQRWOLVWHGDERYHVKDOOEHVXEMHFWWRSULRUDSSURYDOIURP
&OLHQW&RQVXOWDQW
-x-x-x-
Page 9 of 9
670 of 896
QUALITY ASSURANCE PLAN
(ELECTRICAL)
671 of 896
CONTRACTOR CLIENT: M/s GAIL (i) Limited
QUALITY ASSURANCE PLAN
SRIKAKULAM-ANGUL PIPELINE
FOR PROJECT:
PROJECT(PART-B)
ORDER NO. & DATE ELECTRICAL EQUIPMENT PACKAGE NO. 23VA
SUB-CONTRACTOR PACKAGE NAME Electrical System
ORDER NO. & DATE
INSTRUCTIONS FOR FILLING UP : CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS:
1. QAP shall be submitted for each of the equipment separately with break up Code Description Code Description Code Description DOCUMENTS:
of assembly/sub-assembly & part/component or for group of equipment
having same specification. 1. Visual 12. Routine test as per relevant IS 23. Short time rating D1. Approved GA drawings
2. Use numerical codes as indicated for extent of inspection & tests and 2. Dimensional other standard 24. Operational & functional D2. Approved single line/
submission of test certificates & documents. Additional codes & description 3. Fitment & Alignment 13. Type test as per relevant IS/ check schematic diagram
for extent of inspection & tests may be added as applicable for the plant and 4. Physical Test (Sample) other standard 25. Over Speed Test D3. Approved
equipment 5. Chemical Test (Sample) 14. Impulse Test 26. Flame Proof Test data sheet
3. Separate identification number with quantity for equipment shall be 6. Ultrasonic Test 15. Partial Discharge Test 27. Clearance and creepage D4. Approved bill of materials
indicated wherever equipment having same specifications belonging to 7. Magnetic Particle Test (MPT) 16. Heat run risc test\tempr. Distance D5. Unpriced P.O. copy
different facilities are grouped together. 8. Radiography Test 17. Enclosure Protection Test 28. Acceptance Test D6. Calibration Certificate
4. Weight in tonnes (T) must be indicated under column 5 for each item. 9. Dye Penetration Test 18. Calibration 29.Harmonics measurement . of all measuring
Estimated weights may be indicated wherever actual weights are not 10. Measurement of IR Value 19. Noise & Vibration instruments and gauges
available. a) Before HV Test 20. Test certificates for bought out
ABBREVIATIONS USED : b) After HV Test components
11. High Voltage test/Dielectric 21. Tank Pressure Test
CONTR : CONTRACTOR test 22. Paint shade verification
MFR : MANUFACTURER
EQUIPMENT DETAILS INSPECTION AND TESTS Test Acceptance Criteria REMARKS /
Sl. Description (With equipment Indentificatuin Quantity Manufacturer’s Expected schedule Raw Material and inprocess stage inspection Final Inspection/Test by Certificates & Standards /IS/ SAMPLING
No. heading, place of use, and No. No/M T Name and Address of Final Inspection MFR CONTR MECON MFR CONTR/ MECON/ documents to BS/ASME/ Norms PLAN
Breif Specifications) TPIA GAIL be submitted to and Documents
MECON
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1. Power & Lighting Set 1,2,3,4, 24, 27 - - 1,2,3,12, 22, 1,2,3,12, 1,2,3,12, D1, D2, D3, I.S,,Data Sheet, 13* for similar
Distribution Board 24,27 22, 24,27 22, 24,27 D4, D5, D6, 20, Specification, rating
12,13*,16 Approved Drawings
2 LT Power and Control Mt. - - - 1,10,11, 1,2,10,11, R 12,13,28 I.S., Data Sheet, 13* for similar
Cable 12,13, 28 12, 28 D3, D5, D6, Specifications & rating, Inspection to
be done by TPI
Test Certificate
3 Distribution Transformer No. 1,2,3,4, 21,27 - - 1,2,10,11, 12 1,2,10,11, 1,2,10,11, 12,13,20 I.S., Data Sheet, 13* for similar
12,22,27 12,22,27 D3, D5, D6 Specifications & rating, Inspection to
be done by TPI
Test Certificate
4. AVR (AUTOMATIC Set 1,2,3,4, 21,27 - - 1,2,10,11, 12 1,2,10,11, 1,2,10,11, 12,13,20 I.S., Data Sheet, 13* for similar
VOLTAGE REGULATOR) 12,22,27 12,22,27 D3, D5, D6 Specifications & rating,
Test Certificate
5 DG SET with Engine and all Set 1,2,3,4, 24, - - 1,2,3,12,16,2 1,2,3,12, 1,2,3,12, D1, D2, D3, Tech. Specification, 100%
accessories 27,28 4, 28,19, 16,24,28, 16,24, D4, D5, D6, 20, Approved drawings
25,22 19,25,22 28,19, 16, 12,13,19 & Data Sheets
25,22
6 AMF Panel Set 1,2,3,4, 24 - - 1,2,3, 12,24, 1,2,3, 1,2,3, D1, D2, D3, Tech. Specification, 100%
28, 22 12,24, 28, 12,24, 28, D4, D5, D6, 20, Approved drawings
22 22 12,13 & Data Sheets
672 of 896
SRIKAKULAM - ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
Page 1 of 2
673 of 896
SRIKAKULAM - ANGUL PIPELINE PROJECT
(PART-B)
GAIL (I) Ltd MECON LIMITED
-x-x-x-
Page 2 of 2
674 of 896
PARTICULAR JOB
SPECIFICATION
(ELECTRICAL SYSTEM)
675 of 896
GAIL (INDIA) LIMITED
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
MEC/23VA/05/E9/E/004 0 17.08.2021
676 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
CONTENT
1 GENERAL.
2 SCOPE
5 LIGHTNING ARRESTORS
6 AREA CLASSIFICATION
7 JOB SPECIFICATION
677 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
1.1 Introduction
The intent of this specification is to define the requirements for the supply of equipment and
materials (as required), erection, earthing, testing and commissioning of the double pole
mounted 11/0.433kv substation with transformer.
The work shall be carried out in the best workmanship – like manner, in conformity with these
specifications, approved drawings and the instructions of the Engineer-in-charge from time to
time.
The contract shall include clearing of temporary construction, waste materials and loose earth,
which might get collected in and nearby the work site consequent of the execution of work under
this contract.
1.2 Standards
The work shall be performed in conformity with, standard specifications and installation
standards enclosed and code of practices of the Bureau of India Standards. In case of any
conflict, the stipulations under this specification shall govern.
In addition, the work shall also conform to the requirements of the following:
The Indian Electricity Act and the rules framed there under
The fire Insurance Regulations
The regulations lay down by the Chief Electrical Inspector of the state government / Central
Electricity Authority (CEA).
The regulations lay down by the Factory Inspector.
The regulations lay down by the Chief Inspector of Explosives.
IS-9920 Part-I to V
IS-2544/1973- Porcelain post insulators
IS-2633- Galvanization of ferrous parts
IS-9921 Part I to IV
IS-5340 Part-III
M.B.Lal committee recommendations for electrical installations.
PNGRB guidelines (as applicable)
OISD standard (as applicable)
Any other regulations lay down by the Central, State or Local Authorities from time to time
during the pendency of this contract.
1.3 Guarantee
The contractor shall guarantee the installation against any defects of workmanship and
materials (supplied by the contractor) for a period of 12 months from the date of issue of the
completion certificate. Any damage or defects connected with the erection of materials,
equipments or fittings supplied by the contractor that may be undiscovered at the time of issue
of the completion certificate, or may arise or come to light thereafter, shall be rectified or
replaced by the contractor at his own expense as deemed necessary and as per the instruction
of the Engineer-in-charge within the time limit specified by the Engineer-in-charge.
678 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
The above guarantee shall be applicable for the quality of work executed as well as for the
equipment / cable / fittings/ other material supplied by the contractor.
The equipment offered and the installation shall be suitable for continuous operation under the
following site conditions.
11kV Power supply is considered available at IP terminal, SV terminal & Receiving terminals.
2.0 SCOPE
2.1.1 Submission of electrical equipments selection criteria & respective design calculations,
inspection & test plan, installation & commissioning procedures, drawings for Review/Approval,
preparation of site engineering drawings and details for installation works wherever applicable
or required by the Engineer-in-charge & final commissioning reports, submit to the Engineer-in-
charge for Review/Approval.
2.1.2 Selection & design of all HT electrical equipment shall be as per relevant Indian & International
standards & contractor shall submit installation & commissioning drawings for 2-Pole structure &
associated equipments approval.
2.1.3 Correction, updating and submission of all Owner’s/Tender’s drawings for as-built status.
2.1.4 Obtaining clearance for energizing the complete electrical facilities covered under this tender
and approval of installation and drawings from the Chief Electrical Inspector of the State
Government/Central Electricity Authority and other statutory authority as required. This includes
equipments installed or commissioned by others within the battery limit. This is for the purpose
of obtaining a comprehensive approval from competent authority.
679 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
This section covers Design, manufacturing, testing at manufacturer works and supply of 11 KV,
200 Amps, 50HZ triple pole gang operated, outdoor type, single throw, single break tilting type
manually operated AB Switches suitable for vertical mounting. The A. B. Switches offered shall
be complete with all components necessary for its effective and trouble-free operation along
with associated equipment etc. such components shall be deemed to be within the scope of
supplier’s supply, irrespective of whether those are specifically brought out in the specification
and/or in order or not. Also similar parts particularly removable ones shall be interchangeable.
The 11KV A.B. Switch (3 Pin Type) sets shall confirm to the following parameters
a. Number of poles 3
b. Number of Post insulator per pole 3 nos. 12KV post insulator.
c. Nominal system voltage 11KV
d. Highest system voltage 12KV
e. Rated frequency 50Hz
f. System earthing effectively Unearthed.
g. Rated nominal current 200 amps
h. Altitude of installation Not exceeding1000M
The post insulators used in the A.B. Switches shall have the following ratings:-
3.2 General
The 11 KV A.B. Switch Set shall be the gang operated rotating single air break type having 3
post insulators per phase. The operating mechanism shall be suitable for manual operation from
the ground level and shall be so designed that all the three phases shall open or close
simultaneously. The Switches shall be robust in construction, easy in operation and shall be
protected against over travel or staining that might adversely affect any of its parts. The required
base M.S. Channel (hot dip galvanized) phase coupling rod, operation rod with intermediate
guide braided with flexible electrolytic copper, tail piece of required current carrying capacity and
operation mechanism with ‘ON’ & ‘OFF’ positions shall be provided. The operation rod shall be
medium gage of 32mm diameter nominal bore G.I. pipe single length 6 meters. The phase
coupling rod for gang operation shall be of medium gauge 25mm dia nominal bore G.I. pipe.
680 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
The Rating post insulators shall be provide with suitable bearing mounted on a base channel
with 8mm dia thrust collar and 6mm split pin made out of stainless steel. The operating down
rod shall be coupled to the spindle (minimum dia – 32mm) for gang operation through another
suitable bearing by two numbers 10mm dia stainless steel bolts with double nuts. All the
bearings shall be provided with grease nipple. All metal (ferrous) parts shall be galvanized an
polished. The pipe shall be galvanized in accordance with IS-4736/1968.The post insulators
should be fixed with the base channel using Galvanized Nuts and Bolts.
3.3 Mounting
The A.B. Switches shall be suitable for Vertical mounting in double pole sub-station structures.
It shall be made out of electrolytic copper with silver plated. Contractor shall submit its size for
approval. The Switch shall have such a spring mechanism so as to ensure that the speed of the
opening of contact is independent of speed of manual operation.
The Fixed Jaw type female contacts shall be made of electrolytic copper (minimum 99% copper
composition) duly silver coated controlled by stainless steel high pressure spring housed in
robust G.I. Cover. It is essential that provision shall be made in fixed female contracts to take
the shock arising from the closing of move contract blade without the same being transmitted to
the post insulator.
The male and female contacts assemblies shall be of sturdy construction and design to ensure
A set of adjustable arcing horns made from 2 SWG G. I. Wire shall be mounted on each
insulator stack of G.O. Switch. The supplier shall supply a graph showing impulse and power
frequency spark over voltage for various gap settings of arcing horns.
Terminal connectors shall be robust in design. The fixed connector & movable connector shall
be shall be of copper casting with uniform machine finishing duly silver plated made out of
minimum 95% copper composition with 2 nos. 12mm dia holes provided with suitable brass
bolts and double nuts, flat washers & 2 nos. bimetallic solder less sockets suitable upto 80 mm2
conductor.
Contractor shall submit size of fixed connector & movable connector for Approval.
681 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
3.8 Spacing
The minimum clearance between phases to the switch shall be 760mm. The operation down rod
shall be at a transverse distance of 300mm from the outer limb of the switch. The centre
spacing between two post insulator of the same phase shall be 380mm. In the open position of
the A.B. switches the moving blade shall rotate through 90o. This shall be exhibited in the
drawing.
The switches shall be provided with a nameplate, which contains the information in accordance
with IS-9921 (part I to V). The name plates will be weather & rust proof.
All fittings, accessories or apparatus which may not have been specially mentioned in this
specification but which are otherwise necessary for satisfactory working of G.O. switches shall
be deemed to have been included in the scope of supply.
The supplier shall be responsible for suitable packing of all the material and marking on the
consignment to ensure correct dispatch to the destination. All G.O. Switches shall be packed
suitably capable of withstanding rough handling for transportation to the various consignees so
as to avoid any shortage and damage occurring during transit. Separators shall be fixed
between the post insulators and other breakable parts of GO Switch and also between
individual GO Switches so as to prevent relative movement to avoid damage. All the labels used
on each packing shall be of tin securely bounded with wire and shall have the descriptive
marking stamped thereon. All GO Switches damaged during transportation shall be to the
suppliers account.
Type Test
Certificate for the following type tests conducted on a prototype set of A.B. Switch in a NABL
approved test house/CPRI shall have to be submitted along with offer.
Dielectric Test (impulse and one minute were power frequency withstand voltage test.)
682 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
The following routine tests shall have to be conducted on each set by Owner/Third Party agency
of the materials at the works of the manufacturer as per relevant IS/IEC. The supplier shall give
fifteen days advance intimation to the Purchaser to enable him to depute his representative for
witnessing the tests.
The D.O. Fuses are intended for use on Distribution transformers for protection/isolation of the
same during overload or fault conditions of lines. The drop out fuse shall conform to IS: 9385
(Part-I to III) as amended from time to time.
The drop-out fuses shall be expulsion type. The equipment offered by the tenderer shall be
suitable for 11KV, 3 Ph 50 Hz solidly grounded earthed neutral systems. It shall be designed for
a normal current rating of 200 Amps.
The drops out fuses are required with Post Insulators. These shall be suitable for mounting on
the structure. The bracket/channel hardware’s for D.O. Fuses shall be provided with adequate
sizes of nuts, bolts and washer for mounting on the structures of the purchaser.
Each 11 KV D.O. Fuse shall have two nos. 11 KV Post Insulators. The insulators shall conform
to IS: 2544 of 1973 with latest amendments. The porcelain used for manufacture of D.O. Fuse
shall be homogeneous, free from flaws or imperfections that might effect the mechanical or
dielectric strength adversely. They shall be thoroughly vitrified tough and impervious to
moisture. The glazing of the porcelain shall be of uniform brown colour free from blisters, burns
and other similar defects. Insulators of the same rating and type shall be interchangeable.
The porcelains and metal parts shall be assembled in such a manner that any thermal
expansion differential between the metal and porcelain parts through range of temperature
variation shall not loosen parts or create undue internal stresses which may affect the electrical
or mechanical strength and rigidity. Each cap and base pin shall be made of high grade cast
steel or malleable steel casting and they shall be machine faced and smoothly galvanized. The
cap and base shall be properly cemented with insulators to give perfect grip. Excess use of
cement shall be avoided.
Each 11KV Post Insulators should have technical particulars as detailed below:-
11KV
(i) Nominal system voltage KV (rms) 11
(ii) Highest system voltage KV (rms) 12
683 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
As stated above unless otherwise modified in this specification the drop out fuse shall conform
to IS: 9385 (Part-I to III) and as amended from time to time.
The rated lightning impulse withstand voltage for positive and negative polarities shall be as
given below:-
11KV
Rated one minute power frequency withstand voltage (dry and wet) values for the fuse base-
11KV
The rated breaking capacity shall be 8KA (symmetrical). Bidder shall submit type test
reports/certificates of DO fuses along with offer.
The main contacts of the D.O. Fuse shall be suitable for heavy duty, properly aligned, made
from Brass material. These shall have good finish and smooth surface and shall be silver plated.
All the sharp edges shall be rounded off. These contacts shall be so designed to withstand
highest short circuit breaking current that may be encountered during service. In nut-shell the
contact assembly shall ensure:-
i. Electrodynamic withstand ability during short circuit without any risk of repulsion of contact.
ii. Thermal withstand ability during short circuits.
iii. Constant contact pressure even when the lower parts of the insulator stacks are subjected
to tensile stresses due to linear expansion of connected bus bar or flexible conductors either
because of temperature variation or strong winds.
iv. Proper alignment to ensure smooth operation of D.O. Fuse without adjustment.
4.4 CONNECTORS
The connectors shall be made from Brass suitable for ACSR/AAAC Squirrel/Weasel & Rabbit,
Raccoon & Dog. The connectors should be bolted type having 4 bolts & groove to hold the
conductor. All brass parts should be silver plated for corrosion resistance and efficient current
flow. All ferrous parts should be hot dip galvanized as per the latest version of IS: 2633. Nuts
684 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
These shall be provided at both the ends of Epoxy Resin Fiber Glass (ERFG) tube for tightening
the fuse element. The nut shall be provided with one flat washer of 1 mm thickness. The
arrangement shall be made to ensure that the fuse wire runs centrally inside the ERFG tube
after tightening. The fly nuts should have at least 4 threads with adequate wall thickness.
The spring strips shall be of phosphor bronze multi line brush type having a high pressure
contacts and should retain its tension under minimum continuous service current of 200 Amps
at 90◌ْ C.
All fittings, accessories or apparatus which may not have been specially mentioned in this
specification but which are otherwise necessary for satisfactory working of DO fuses shall be
deemed to have been included in the scope of supply.
The carrier tube made of Epoxy Resin Fibre Glass (ERFG) and conforming to the following
specification shall be used for 11KV D.O Sets:-
GENERAL:-
This specification governs the requirement for an electrical grade tube with good mechanical
and high heat resistance properties, made from fine woven glass fibre cloth, impregnated with
epoxy resin. Tube shall be well consolidated of circular cross section and uniform wall thickness
with ends trimmed smoothly at right angles to the axis of the tube. The external surfaces shall
be brown in colour and shall be uniformly finished with polyuret and varnish or epoxy resin. The
tube has a temperature index of at least 155˚C.
The section covers the design, manufacture, shop testing before dispatch, supply, delivery,
erection, testing & commissioning of 9 KV, static class heavy rating, gapless, metal (zinc) oxide
lighting arrestors complete along with clamps, complete fitting and accessories for installation
on outdoor type 11 kV Double pole structure.
System parameters
685 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
The equipment along with all accessories shall be capable of performing intended duties under
specified conditions. The Contractor shall guarantee the reliability and performance of the
individual equipment as well as of the complete system as specified in the bid documents.
The lighting arrestor shall be provided with line and earth terminals of suitable size & lightning
counter. The line side terminal shall be suitable for AAA conductor or ACSR weasel / rabbit
conductor.
i) The metal oxide gap less Lighting Arrestor without any series or shunt gap shall be suitable for
protection for 11KV side of Distribution Transformers, associated equipment from voltage
lightings resulting from natural disturbance like lightning as well as system disturbances.
ii) The lighting arrestor shall draw negligible current as operating voltage and at the same time
offer least resistance during the flow or lighting current.
iii) The lighting arrestor shall consist of non-linear resistor elements placed in series and housed in
electrical grade porcelain housing / silicon polymeric of specified creep age distance.
iv) The assembly shall be hermetically sealed with suitable rubber gaskets with effective sealing
system arrangement to prevent ingress of moisture.
686 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
v) The lighting arrestor shall be provided with line and earth terminal of suitable size. The ground
side terminal of lighting arrestor shall be connected with 25x6 mm galvanized strip.
vi) The lighting arrestor shall not operate under power frequency and temporary over voltage
conditions but under lighting conditions, the lighting arrestor shall change over to the conducting
mode.
vii) Lighting arrestors shall have a suitable pressure relief system to avoid damage to the porcelain /
silicon polymeric housing and providing path for flow of rated fault currents in the event of
arrestor failure.
viii) The reference current of the arrestor shall be high enough to eliminate the influence of grading
and stray capacitance on the measured reference voltage.
ix) The Lighting Arrestor shall be thermally stable and the supplier shall furnish a copy of thermal
stability test along with the bid.
The arrestors shall be suitable for mounting on 4 pole/2 pole structure used for plinth mounted
transformer and for incoming and outgoing lines.
x) The lighting arrestor shall be complete with insulating bases, fasteners for stacking units along
with clamp & terminal connectors and inbuilt disconnector.
xi) The terminals shall be non-magnetic, corrosion proof, robust and of adequate size and shall be
so located that incoming and outgoing connections are made with minimum possible bends.
The top metal cap and base of lighting arrestor shall be galvanized. The line terminal shall have
a built in clamping device, which can be adjusted for both horizontal and vertical take off.
i) Sectional drawings
ii) Mounting arrangement
All fittings, accessories or apparatus which may not have been specially mentioned in this
specification but which are otherwise necessary for satisfactory working of Lightning Arrestor
shall be deemed to have been included in the scope of supply.
The nameplate attached to the arrestor shall carry the following information:
- Rated Voltage
687 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
DANGER CAUTION BOARDS: The danger of caution boards shall have to be displayed on
pole and transformer
5.9 Tests
The lighting Arrestors offered shall be type tested from NABL accredited laboratory. Copies of
test certificates shall be furnished by the bidder for scrutiny. Routine and Acceptance tests shall
be carried out in accordance with IS: 3070 (Part-3)-1993. The purchaser representative will
witness the acceptance test at the works of manufacturer. The suitability of the Lighting
Arrestors shall also be established from the following:
Metal oxide block shall be tested for guaranteed specific energy capability in addition to routine /
acceptance test as per IEC / IS.
i) The maximum residual voltages corresponding to nominal discharge current of 5 kA for steep
current, impulse residual voltage test, lightning impulse protection level and switching impulse
level shall generally conform to relevant IS.
ii) The suppliers shall furnish the copies of the type tests and the characteristics curves between
the residual voltage and nominal discharge current of the offered lighting arrestor and power
frequency voltage v/s time characteristic of the lighting arrestor subsequent to impulse energy
consumption as per clause 6.6 of IS ; 3070 (Para-3) offered along with the bid.
iii) The lighting arrestor housing shall also be type tested and shall be subjected to routine and
acceptance tests in accordance with IS: 2071.
Hydrocarbon handling areas have been generally classified as zone 1&2, gas group IIA/IIB as
per IS: 5572, API RP-500, OISD - 113 and IP Rules. All equipments to be installed in these
areas shall be suitable for the area classification with temperature class T3 (2000C), CMRI
testing and approved by CCOE, DGFAS and having BIS license.
688 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
Various electrical works covered under this contract like equipment erection, cabling and
grounding works, etc. shall be performed in accordance with specifications attached with this
tender. (Certain clauses of specifications, which are applicable to equipments or system not
covered under this contract, shall not be applicable).
All works relating to statutory approvals of the complete installation, from competent authority
like CEA, DGMS, State Electricity Authority/Board etc, shall be in the scope of contractor.
The application on behalf of the owner for submission to Electrical Inspector / DGMS etc. along
with copies of required certificates and drawings, complete in all respects, shall be prepared by
the contractor and submitted to the Engineer-in-charge for onward transmission well ahead of
time so that the actual commissioning of equipment are not delayed for want of inspection by
the Electrical Inspector / DGMS. The actual Liaison work shall be arranged by the Contractor
and necessary coordination and liaisons work in this respect shall be responsibility of the
contractors. However, the Owner on submission of bills along with documentary evidence shall
reimburse any fee paid to the statutory Authority in this regards.
All equipments / materials supplied by the contractor shall be as per the list of approved makes
enclosed with this document subject to submission of Certification and approvals.
10.1 The equipment shall be inspected by the Owner and/or their inspection agency at the
manufacturer’s works prior to despatch. The equipment will be inspected as per the tests pre-
identified in the approved QAP to ensure conformity of the same with relevant approved
drawings, data sheets, specifications, National/International standards.
10.2 Performance tests of any equipments which cannot be conducted/demonstrated either partially
of wholly at the manufacturer’s work, shall be conducted after erection at site in the presence of
Owner & their inspection agency. In all the cases, prior approval of the approval shall be
obtained.
10.3 In case of waiver category of items, the same shall be pre identified. For such items, the
contractor shall furnish necessary certificates, test reports etc for Review/Approval to
Owner/Inspection agency. The issue of Inspection Certificate/Waiver Certificate for any
equipment or component there of does absolve the contractor from his contractual obligations
towards subsequent satisfactory performance of the equipment at site. Should any equipment
689 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
10.4 Contractor shall submit test plan for the equipments with four week advance notice.
11.1 The successful tenderer shall submit detailed site testing & commission procedure with time
schedules for Review/Approval to Owner/MECON.
11.2 The successful tenderer shall provide adequate supervisory/ skilled personnel and all tools and
tackles, testing equipment and instruments required for complete checking of installations and
testing and commissioning of all equipment and accessories.
11.3 All the tests shall be conducted in the presence of Owner/ Engineer-in/charge or his authorized
representative unless he waives this requirement in writing.
11.4 The testing and commissioning of all equipment under the scope of the tenderer shall be carried
out in accordance with the latest edition of relevant Indian Standards and IE Rules.
11.5 Test reports shall be submitted in required number of copies duly signed by the TENDERER to
MECON and OWNER.
11.6 All equipment after testing shall be energized only after certification by the qualified testing
engineer that the equipment is ready for energisation and with \ the concurrence of OWNER /
MECON.
11.7 After the completion of all tests and rectification of all defects pointed out during final inspection,
plant start-up trials would be commenced. During the start-up trials contractor shall provide
skilled / unskilled personnel and supervision round the clock at his cost. The number and
category of workmen and duration up to which required, will be decided by the Engineer-in-
charge. Any defects noticed during the start-up trial relating to the equipment supplied and work
carried out by the Contractor, will be rectified by the contractor at his own cost.
11.8 On successful completion of erection of each item /equipment, a final inspection will be carried
out at site by Owner / MECON, for correctness and completeness of erection.
11.9 Any work not conforming to the execution drawings, specifications or codes shall be rejected
forthwith and the contractor shall carry out the rectification at his own cost.
11.10 After the operating conditions are fully achieved in the plant and the other requirements as
stated in the General Conditions of Contract are fulfilled, the contractor would be eligible for
applying for a completion certificate.
690 of 896
OIL & GAS SBU SRIKAKULAM - ANGUL PIPELINE
PROJECT (PART-B)
12.2 Following Drawings & Documents shall be submitted after award of contract for approval:
12.3 The equipments / materials to be supplied by the contractor shall conform to the requirements of
the applicable specifications. Also the installation of various material / equipment shall conform
to the installation standards /norms.
12.4 The drawings accompanying the tender documents when read with specification shall depict the
electrical system of the Terminal. These are indicative of the nature of work and issued for
tendering purposes only. Purpose of these drawings is to enable the tendered to make an offer
in line with the requirements of the Owner. Construction shall be as per drawings / specifications
issued / approved by the Engineer-in-charge during the course of execution of work.
12.5 After the job completion, contractor shall prepare AS-BUILT drawings and documents, submit
catalogues/manuals (O&M) of major brought out items like HT Substation, Transformers, LA,
AB switch etc. Final certified As-Built drawings, documents and manuals etc shall be submitted
by the contractor to owner in bound volume with one set in soft copy (CD) plus five sets of
prints.
Training
Contractor shall train the work force of Owner with his technical and supervisory personnel for
safe, efficient operation and maintenance of the equipment and system installed by the
contractor. The Number of personnel to be trained and the duration and structure of the training
shall be mutually discussed and finalized.
-x-x-x-
691 of 896
PARTICULAR JOB SPECIFICATION
FOR
SPV (SOLAR PHOTOVOLTAIC) SYSTEM
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
692 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
TABLE OF CONTENT
693 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
1.0 GENERAL
The intent of this specification is to define the requirements of SPV solar power supply
system and the associated battery sets, charge controller, Grid charger, DCDB etc for Off-
Grid system at PCP stations along the pipeline to feed power to the PCP system. Tenderer's
scope of work includes design, manufacture, testing, packing, delivery to site, installation,
earthing, testing & commissioning of the complete Solar system with solar array, charge
controller, battery banks, Grid Charger for charging battery bank from grid supply/DG supply,
Distribution boards, interconnecting cables etc as per enclosed specification, data sheets
and SOR for Off-grid system.
1.1 Standards
1.1.1 The equipment/material shall be in conformity with standard specifications, data sheet and
code of practices of the relevant Bureau of India Standards & IEC. In case of any conflict,
the stipulations under specification/data sheet shall govern. Refer Technical specification of
Solar PV system for the applicable codes and standards.
The equipment offered and the installation shall be suitable for continuous operation under
the following site conditions.
1 CP SYSTEM 48 V DC
2.0 SCOPE
2.1.1 Submission of solar array sizing calculations, MPPT charge controller size calculations, PCU
sizing calculations, battery size calculations and FCBC Grid Charger (unidirectional/bi-
directional) size calculation for approval Preparation of site engineering drawings and details
for installation works wherever applicable or required by the Engineer-in-charge, and
submits to the Engineer-in-charge for review.
The system shall be designed on the daily Ah requirement considering the max. 30
day cycle i.e. two No SUN DAYS in four weeks, However this cycle depends upon the
Geo Graphical location of the installation & may go below the above consideration.
The excess Ah shall be determined accordingly apart from the daily Ah requirement.
694 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
The result of the survey shall be presented in the graphical format & accordingly the
optimised tilt angle for the installation PV system shall be calculated of each location
for max power output through out the year.
The required nos. of array shall be calculated from the max. Current requirement by the
battery bank during charging & the nos. of series modules shall be calculated as per the
boost voltage of the battery bank.
All solar calculations shall be done on PVsyst 6 software and Bidder shall have valid licence
of the software for the same at the time of Bidding. Bidder shall submit all the reports as per
the software simulations.
2.1.2 The photovoltaic solar array, charge controller shall be sized to meet through battery back-up,
load cycle requirement of connected load with availability of solar energy. However the rating of
solar system & equipments shall not be less than as specified in SOR/MR.
2.1.3 Grid Connected system shall be designed to as per the KWp rating mentioned in the SOR
and the minimum annual generation capacity guaranteed (Mentioned in SOR).
2.1.4 Correction, updating and submission of all Owner’s drawings for as-built status.
Following electrical equipment and material are in the contractor’s scope of supply in this
tender.
2.2.1 Solar Array/Panels, Anodised Al/Hot dip galvanized MS mounting structure on parta cabin/
civil building or on ground, Junction boxes, Charge controller, DCDB, Ni-Cd Battery bank,
DC-DC converter, FCBC Grid charger, interconnecting cables among - arrays, charge
controller, DC-DC Converter, DCDB, Battery bank, Grid charger etc as per enclosed SOR
and specification.
2.2.2 Offered solar PV cells & Modules shall be from existing regular manufacturer’s plant/unit and
have BIS certification of the Solar Photovoltaic Module. IEC/UL/CE certification is also
accepted in case BIS is exempted as per the Indian Gazette order dated 13/07/2018 issued
by MNRE.
2.2.3 A stand alone dusk-dawn solar photovoltaic street lighting system for outdoor emergency
lighting as per enclosed specification and SOR.
2.2.4 MV power and control cable (Cu-Conductor, XLPE – insulated, PVC sheathed,
armoured/unarmoured, FRLS cables as required). Solar grade cable shall be used for the
Module wiring & outdoor cables.
695 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
2.2.5 GI pipes, GI Cable-trays and accessories, cable markers, identifier tags, GI saddles and all
other associated accessories as required for cable laying.
2.2.6 FLP (CMRI, PESO approved) type double-compression nickel-plated brass cable glands,
tinned-copper lugs, clamping material etc. for cable termination.
2.2.7 Earthing including earthing pits, earth electrodes, earthing strips, grounding conductor of
various sizes, Cu strip for flange jumper and Cu earth plates etc as per
specification/standard drawing.
2.2.8 Lightning & Lighting surge protection must be provided for the SPV array and other solar
system components, MPPT/PCU/Charger Input side and Output side as per IEC 62305.
2.2.9 Fabrication and supply of MS frames, supports, canopies and brackets for miscellaneous
electrical equipments, including welding, supply of bolts, nuts etc for mounting and other
necessary supplies, all inclusive of painting etc as required.
2.2.10 Two years operational spares as per list provided in this document.
2.3.1 Delivery to site, storage, Transportation from storage to site, Installation, earthing, testing,
commissioning and performance test at site (full load test) of the complete Solar system with
solar array, charge controller, FCBC Grid Charger, Ni-Cd battery banks, DC-DC Converters,
PCU, Distribution boards, junction boxes, interconnecting cables etc as per enclosed
specification, data sheets and SOR. Tenderer shall submit the sizing calculations for SPV
array, charge controller, battery bank and Grid charger & PCU. However the rating of each
subsystem shall not be less than as indicated in SOR.
2.3.2 Battery capacity test shall be carried out at site of complete bank with arrangement of the
DG sets and resistance load bank as per requirements and all such materials shall be
arranged by the contractor for the commissioning of the battery bank.
2.3.3 Installation, earthing, testing & commissioning of the stand alone dusk-dawn solar
photovoltaic street lighting system including all civil work etc as required for outdoor
emergency lighting as per enclosed specification and SOR.
2.3.4 Installation of earthing material and lightning system, testing and commissioning of complete
earthing and lightning system as per specification and requirement.
2.3.5 Laying, Termination, Glanding, Ferruling of all interconnecting cables between sub array
JBs, Main JBs, Charge controller, Grid charger, Battery Bank and DCDB.
2.3.6 Suitable trench/route/cable-tray shall be made by the solar power system contractor for laying
of cables from solar array to Charge controller/ PCU and PCU to Grid Power connection and
required for all interconnecting cables of the system.
696 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
3.1 Preparation of buried cable trenches, including, back filling, compacting providing of brick
protection by second-class bricks, spreading of fine river sand, including all supplies.
3.2 Bidder scope shall also include taking permission from respective state renewal energy
authority for the SPV system installation and inspection to meet their technical requirements
including all works related to laisioning with the authority & fee as required for completion of
the work including liasioning, net metering system including bi-directional meters, Inspection
etc. Bidder shall provide complete on-grid system with all approvals from authorities and
agreements for same.
3.3 The job includes repairing of all civil works damaged during installation of electrical facilities
and complete solar system.
3.4 The scope of work under this contract shall be inclusive of breaking of walls, floors and
chipping of concrete foundations necessary for the installation of equipment, materials, and
making good of the same.
3.5 Minor modifications wherever required to be done in the owner free supplied equipments /
devices to enable cable entry, termination etc.
3.6 Sealing of opening made in the walls / floors for cables trays, cables, bus ducts, etc. using
acceptable practice and standards.
3.7 Supply and installation of all other accessories not specifically mentioned herein, but never
the less necessary for completion of the job.
Hydrocarbon handling areas have been generally classified as zone 1 & 2, gas group IIA/IIB
as per IS: 5572, API RP-500, OISD - 113 and IP Rules. All equipments to be installed in
these areas shall be suitable for the area classification with temperature class T3 (200˚C),
CIMFR testing and approved by CCOE/PESO, DGMS and having BIS license.
5.1 Various electrical works covered under this contract like equipment erection, cabling,
outdoor lighting (Solar) and grounding works, etc shall be performed in accordance with
specifications attached with this tender. (Certain clauses of specifications, which are
applicable to equipments or system not covered under this contract, shall not be applicable).
5.2 Erection and commissioning of certain special equipments shall be performed in accordance
with supplier’s instructions and directions of the Engineer-in-charges under supervision by
equipment supplier/s.
697 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
5.4 Price of erection & commissioning spares and special tools shall be included in the quoted
price by the bidder.
All equipments / materials supplied by the contractor shall be as per the list of approved
makes enclosed with this document.
The contractor shall carry out all the tests as enumerated in the technical specifications and
as per applicable codes and standards and QAP.
8.1 Contractor shall submit drawings and data sheet as enumerated in the technical
specification of the equipments / materials to be supplied.
8.2 After the job completion, contractor shall prepare AS-BUILT drawings and documents,
submit catalogues/manuals (O&M) of major brought out items like solar system, charge
controller, DCDB, battery bank, DC-DC Converter, junction boxes, Grid charger etc. Final
certified as built drawings, documents and manuals etc shall be submitted by the
contractor to owner in bound volume with one set in soft copy (CD) plus five sets of prints.
Annexure – I
STATIONWISE SOLAR SYSTEM DETAILS (SAPL_PART-A)
S. REQUIRED
No. STATION DESCRIPTION LOCATION LOAD NO. OF SOLAR
SYSTEM
Odisha State
1 SV-1 Odisha State 200 W 1 No.
2 SV-5 200 W 1 No.
3 SV-9 200 W 1 No.
4 SV-11 200 W 1 No.
Andhra Pradesh
5 SV-17 Andhra Pradesh 200 W 1 No.
S. REQUIRED
No. STATION DESCRIPTION LOCATION LOAD NO. OF SOLAR
SYSTEM
Odisha State
1 SV-1S Odisha State 200 W 1 No.
698 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
S. REQUIRED
No. STATION DESCRIPTION LOCATION LOAD NO. OF SOLAR
SYSTEM
Odisha State
1 SV-02,04,06,08,10,12 Odisha State 500VA 6 Nos.
Andhra Pradesh
2 SV-14,16 Andhra Pradesh 500VA 2 Nos.
S. REQUIRED
No. STATION DESCRIPTION LOCATION LOAD NO. OF SOLAR
SYSTEM
Odisha State
1 SV-02S,04S,05S,02V & Odisha State 500VA 5 Nos.
02N
S. REQUIRED
No. STATION DESCRIPTION LOCATION LOAD NO. OF SOLAR
SYSTEM
Odisha State
1 SV-02,04,06,08,10,12 Odisha State 500VA 6 Nos.
Andhra Pradesh
2 SV-14,16 Andhra Pradesh 500VA 2 Nos.
S. REQUIRED
No. STATION DESCRIPTION LOCATION LOAD NO. OF SOLAR
SYSTEM
Odisha State
1 SV-02S,04S,05S,02V & Odisha State 500VA 5 Nos.
02N
699 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
S. REQUIRED
No. NO. OF
STATION DESCRIPTION LOCATION LOAD
SOLAR
SYSTEM
Odisha State
1 SV- Odisha State - 15 Nos.
01,02,03,04,05,06,07,08,09,10,11,12
& IP-1,2,3
Andhra Pradesh
2 SV-13,14,15,16,17, IP-4 & RT Andhra Pradesh - 7 Nos.
Srikulam
S. REQUIRED NO. OF
No. STATION DESCRIPTION LOCATION SECTION LOAD SOLAR SYSTEM
Odisha State
1 SV-01S & IP-1S Odisha SEC-I - 2 Nos.
State
2 SV- SEC-II 8 Nos.
02S,03S,04S,04SA,05S,SV-
06S cum TOP for
Vedanta,SV-07S cum TOP
for Nalco & RT Utkal
Alumina
3 SV-01V,02V,03V & RT SEC-III 4 Nos.
Vedanta
4 SV-01N,02N,03N & RT SEC-IV 4 Nos.
Nalco
Note: For chainages kindly refer Schematic Diagram of SAPL _ Part-A & Part-B.
700 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT
(PART- B)
GAIL (India) Ltd MECON LTD, DELHI
Annexure – II
-x-x-x-
701 of 896
CONTRACTOR CLIENT: M/s GAIL (i) Limited
QUALITY ASSURANCE PLAN Srikakulam-Angul Pipeline Line
FOR PROJECT: (Part-A & B)
ORDER NO. & DATE SOLAR SYSTEM EQUIPMENT PACKAGE NO. 23VA
SUB-CONTRACTOR PACKAGE NAME SOLAR SYSTEM
ORDER NO. & DATE
INSTRUCTIONS FOR FILLING UP : CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS:
1. QAP shall be submitted for each of the equipment separately with break up Code Description Code Description Code Description DOCUMENTS:
of assembly/sub-assembly & part/component or for group of equipment
having same specification. 1. Visual 12. Routine test as per relevant IS 23. Short time rating D1. Approved GA drawings
2. Use numerical codes as indicated for extent of inspection & tests and 2. Dimensional other standard 24. Operational & functional D2. Approved single line/
submission of test certificates & documents. Additional codes & description 3. Fitment & Alignment 13. Type test as per relevant IS/ check schematic diagram
for extent of inspection & tests may be added as applicable for the plant and 4. Physical Test (Sample) other standard 25. Over Speed Test D3. Approved
equipment 5. Chemical Test (Sample) 14. Impulse Test 26. Flame Proof Test data sheet
3. Separate identification number with quantity for equipment shall be 6. Ultrasonic Test 15. Partial Discharge Test 27. Clearance and creepage D4. Approved bill of materials
indicated wherever equipment having same specifications belonging to 7. Magnetic Particle Test (MPT) 16. Heat run test\temp rise. Distance D5. Unpriced P.O. copy
different facilities are grouped together. 8. Radiography Test 17. Enclosure Protection Test 28. Acceptance Test D6. Calibration Certificate
4. Weight in tonnes (T) must be indicated under column 5 for each item. 9. Dye Penetration Test 18. Calibration 29.Harmonics measurement . of all measuring
Estimated weights may be indicated wherever actual weights are not 10. Measurement of IR Value 19. Noise & Vibration instruments and gauges
available. a) Before HV Test 20. Test certificates for bought out
ABBREVIATIONS USED : b) After HV Test components
CONTR : CONTRACTOR 11. High Voltage test/Dielectric 21. Tank Pressure Test
MFR : MANUFACTURER test 22. Paint shade verification
EQUIPMENT DETAILS INSPECTION AND TESTS Test Certificates Acceptance Criteria REMARKS /
Sl. Description (With equipment Indentificatuin Quantity Manufacturer’s Expected schedule of Raw Material and inprocess stage Final Inspection/Test by & documents to Standards /IS/ SAMPLING
No. heading, place of use, and No. Name and Address Final Inspection inspection be submitted to BS/ASME/ Norms PLAN
Breif Specifications) No/M T MFR CONTR MECON MFR CONTR/ MECON MECON / and Documents
TPI ONGC
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
1.0 LT Power and Control Mtr - - - 1,10,11, 1,2,10,11, 1,2,10,11, 12,13,28 I.S., Data Sheet, 12, 13
Cable 12,13, 28 12, 28 12, 28 D3, D5, D6, Specifications & Document to be
reviewed by
Test Certificate MECON
2.0 Solar Array/Module with Nos. 1,2,3,4, - - 1,2,3,12, 1,2,3,12, 1,2,3,12, D1, D2, D3, D4, Tech. Specification, 12, 13
complete hardware (JBs, 24, 27 13, 29 28, 29 28, 29 D5, D6, 20, Approved Document to be
reviewed by
Mounting Structure etc) 12,13,17,29 Drawings, BIS MECON
14286 & Applicable
IS & IEC standards
3.0 Solae charge controller, Set 1,2,3,4, 1,2,3,12, 1,2,3,12, 1,2,3,12, D1, D2, D3, D4, Tech. Specification, ( * ) 12 hour
Grid Charger (FCBC), PCU 24, 27 16, 22, 16, 22, 16*, 22, D5, D6, 20, 12,13 Approved heat run test
12, 13
23,24,27 23,24,27 23,24,27, Drawings & Data Document to be
Sheets applicable IS reviewed by
& IEC standards MECON
4.0 Battery Set-Solar system Set 1,2,3,4, - - 1,2,3,12, 1,2,28 1.2,28 D1, D3, D4, D5, Tech. Specification, 12, 13
24,27 13 D6, 12,13,20 Approved Document to be
reviewed by
Drawings & Data MECON
Sheets Test
certificates
applicable IS &
IEC standards
Q.A.P. NO.
MEC/05/E9/QAP/23VA/078/001
For Manufacturer For CONTR For MECON
SHEET 1 OF 1 R-0
(Stamp & Signature) (Stamp & Signature) (Stamp & Signature)
702 of 896
STANDARD DATA SHEETS
(ELECTRICAL SYSTEM)
703 of 896
OIL & GAS SBU
SRIKAKULAM-ANGUL
PIPELINE PROJECT (PART-B)
704 of 896
REV. : 0
Edition : 1
DATA SHEET
FOR
LV SMALL POWER DISTRIBUTION BOARD
705 of 896
MECON LIMITED STANDARD DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE - I
Switch Board
1.1 Rated voltage and frequency 415V, 3phase, 4 wire, 50Hz
1.2 Maximum voltage 500V
2.0 Continuous current rating at design ambient As per approved SLD at 45˚C
temperature with IP 52 enclosure
3.0 Type of enclosure as per IS 2147 IP 52
3.1 Minimum thickness of sheet steel 2mm
4.0 Applicable standards IS 2147, 8623
5.0 Design ambient temperature 45˚C
6.0 One second short time rating of switch board with As per SLD
minimum busbars, feeder busbars, kA(RMS)
7.0 Dynamic through fault current with complete
busbars, kA (peak)
8.0. The formation (Max.) Max 6
9.0 Maximum No. of cable terminations in each type of
cubicle
9.1 Size and no. As per SLD
10.0 Incoming termination of LT switch board As per SLD
11.0 Incoming termination top/bottom Bottom for cable
Top for busduct
12.0 Outgoing feeder cable entry top/bottom Bottom
13.0 Minimum clearances at front and back of board 1.5m/1m
14.0 Dimensions LxBxH
15.0 Maximum Dimensions of shipping sections 2.5 x 1.5 x 2.4M
LxBxH
16.0 Min. clearances in air in mm
16.1 Between phases 25.4mm
16.2 Between live parts and ground 19.0mm
17.0 One minute PF withstand voltage 2.5kV
18.0 Paint shade 631 of IS-5
Busbars
1.0 Busbar material & cross section
706 of 896
MECON LIMITED STANDARD DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
707 of 896
MECON LIMITED STANDARD DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE – II
PREFERRED MAKES
708 of 896
MECON LIMITED STANDARD DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE – III
The spare parts as listed below shall be quoted for the Electric Panel along with the
offer with item wise unit prices:
NOTE: All spare parts shall be identical to the parts used in the distribution boards.
709 of 896
Rev.: 0
Edition: 1
DATA SHEET
FOR
HIGH MAST
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
710 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
Annexure-I
PURCHASER’S DATA FOR HIGH MAST
711 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
3. FOUNDATION DETAILS
a) Type of foundation Open raft shallow footing
b) Size of foundation As per Design
c) Soil bearing capacity at site To be confirmed by Owner
d) Design safety factor As per IS-456
e) Considered wind pressure (Kg/Mt2) As per IS-875-1987
f) Depth of foundation Min. 1.5 m below FGL
g) Number of foundation bolts As per manufacturer standard
h) PCD of foundation bolts As per manufacturer standard
i) Type of foundation bolts As per manufacturer standard
j) Bolt diameter As per manufacturer standard
4. LANTERN CARRIAGE
a) Material of construction M. S. IS 2062
b) Diameter of carriage ring (mm) As per manufacturer standard
c) Construction As per manufacturer standard
d) Number of joints As per manufacturer standard
e) Buffer between carriage & mast Rubber Padded guide ring provided
f) Load carrying capacity As per manufacturer standard
g) Total weight of assembly with fittings As per qty of luminaries
h) Number of fittings Suitable for up to 12 nos.
i) No. of fittings As per SOR
i) Type of fittings/fixture 400W HPMV/HPSV as per SOR
5. CABLE
712 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
6. WINCH
a) Make of winch Bajaj or equivalent
b) Number of drums/winch Double drum type
c) Gear Ratio 53 : 1
d) Capacity As per manufacturer standard
e) Method of operation Manual/ Electrical
f) Lubrication arrangement Permanent oil bath
g) Type of lubricant SAE 90 /SAE 140
8. POWER TOOL
a) Model Integral
b) Input supply 3 Ph 415V AC
c) Wattage/HP As per manufacturer standard
d) Number of speeds Single speed
e) Operating speed.(Average) 2 M/minute
9. TORQUE LIMITER
713 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
714 of 896
Rev.: 1
Edition: 1
DATA SHEET
FOR
DISTRIBUTION TRANSFORMER
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
715 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
ANNEXURE – I
GENERAL DATA
1 Type of Transformer ONAN, Hermetically sealed type
2 Quantity As per SOR
15 Oil Included
16 Duty Continuous
17 No of Phases 3
716 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
Electrical data
21 Frequency 50 (± 3%)
22 Phase Three
23 Winding Conductor Copper
25 Winding Connection Δ/ λ
26 Vector group DYN 11
27 % impedance 4.5 % (Tolerance as per IS:1180)
28 Insulation class Class A
717 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
718 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
Annexure-II
A) Weights in kg
719 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
3. Radiator W /O oil
4. oil
5. Total Mass
1. Length
2. Breadth
3. Height
4. Paint
5. Paint Shade
6. Roller
720 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
Annexure – III
721 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
EDITION: 1
Annexure-IV
722 of 896
Rev.: 2
Edition: 1
DATA SHEET
FOR
SOLAR PHOTO VOLTAIC (SPV)
POWER SUPPLY SYSTEM
(200W SOLAR SYSTEM AT PCP STATION)
(ELECTRICAL SECTION)
MECON LIMITED
DELHI 110 092
723 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE – I
PURCHASER’S DATA FOR SOLAR PHOTO VOLTAIC (SPV) POWER SUPPLY SYSTEM
1.0 SOLAR SYSTEM
724 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
0.9
2.7 Solar module framing material Withstand up to Min 55 m/s wind velocity and
Temp Range as specified.
2.8 Material of bird spikes N/A
(Adjustable).
c) Interlocking logic between solar charger
controller & FCBC Grid charger to enable
automatic changeover as specification.
4.0 415V 3x1 Ph FCBC CHARGER (Refer Charger Data sheet for more details)
4.1 Type of charger DSP controlled PWM, FCBC (Automatic Float cum
Boost Charging) type
4.2 Rating As per design calculation @ C10 rating
4.3 Arrangement As per drawing
4.3 Charger I/O Potential free contact for charger ‘ON’ and
available power supply Feedback for SCADA
system and other as per charger specification
a) Grid Supply of individual phases
b) Charger ON/OFF
c) I/P Current (R,Y,B)
d) I/P Voltage (R,Y,B)
e) O/P Current
f) O/P Voltage
g) Charger Fail
4.4 Output Voltage 60V/96V DC/ As per design
4.5 Enclosure protection IP 42
4.6 Mounting Floor
4.7 Cable entry From Bottom
726 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
6.0 DCDB
727 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
Efficiency
7.14 Remote Monitoring Built-in meter and data logger to monitor plant
performance through external computer/Laptop
shall be provided.
7.15 Display/User interface LCD
8.3 Mode of arrangement Sub array JBs than Main JB with facility for test
point for quick fault location
9.0 DC-DC CONVERTER (48V)
728 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
729 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE – II
TECHNICAL DATA FOR SPV POWER SUPPLY SYSTEM
(To be submitted up by the successful bidder)
730 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
3.3 Type/Mode
3.4 Interlocking with SPV charge controller
4.0 BATTERY
4.1 Make
4.2 Type (Enclose catalogue) Ni-Cd
4.3 Type of construction
4.4 AH rating Sizing calculation after award of bid
4.5 Battery charge eff.
4.6 Mode of arrangement 2X50%
4.7 Nominal cell voltage 1.2 V / Cell
731 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
7.0 PCU/Inverter
7.3 Rating
732 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE – III
TECHNICAL DATA FOR SOLAR STREET LIGHITING SYSTEM
(To be submitted up by the successful bidder)
733 of 896
MECON LIMITED STANDARD TECHNICAL DATA SHEET
REGD. OFF: RANCHI
834002 ELECTRICAL SECTION, DELHI
ANNEXURE – IV
734 of 896
Rev: 2
Edition: 1
DA
ATA SHEET
S T
FOR
B
BATTE
ERY CHAR
C RGER
(2
200W
W SOL
LAR SY M AT PCP S
YSTEM STAT
TION)
S
SPECI TION NO.: MEC/DS/05/E9/28
FICAT
(OIL
L & GAAS SBU)
MECCON LIMITE
L ED
DELHI 110 0992
735 of 896
MEECON LIMITTED STANDARD TECH
HNICAL SPE
ECIFICATIO
ON
REGD. OFF: RA
ANCHI
4002
834 ELECTRICA
AL SECTION
N, DELHI
AMEN
NDMENT STATUS
S
Sl. Clause / Paragraph
P h/ Pa
age Rev
vision Date By Verified
d
No. Annexure e / Exhibit / No
o. (Name) (Name))
Drawing Amended d
1 Bidirectional FCBC
F - 1 Aug AM MKJ
spe
ecification provided
p 2019
2 Revvised for 20
00W syste
em - 2 Ja
an 2021 AM MKJ
PREPARE
ED BY: CH
HECKED BY: APPROV
VED BY: IS
SSUE DATE :
(A.Moy
yal) (M.K.Jaiswara
a) (D.G.Majumder) ISSUE DATE : Aug. 2018
2
(A.Moy
yal) (M.K.Jaiswara
a) (D.G.Majumder) ISSUE DATE : Aug. 2019
2
(A.Moy
yal) (M.K.Jaiswara
a) (A Bho
owmic) ISSUE DATE : Sept. 2021
2
736 of 896
MEECON LIMITTED STANDARD TECH
HNICAL SPE
ECIFICATIO
ON
REGD. OFF: RA
ANCHI
4002
834 ELECTRICA
AL SECTION
N, DELHI
PURCH
HASER’S DA
ATA FOR BATTERY
B C
CHARGER
1
1.0 415V
V, 3Ph FCB
BC -BATTERY CHARG
GER-Unidire
ectional
1
1.1 Type of cha
arger 415VV 3 Phase Charger
C worrking on Ind
dividual Phasse
with DSP contro
oller
1
1.2 Input Power Supply Line
e voltage - 415Vac ,3 Ph
hase with Neutral,
N 50 Hz
H
330 ~ 460 Vac, 47 ~ 53 Hzz.
Phase Voltage-- 230Vac, 1P
Phase (variiations)
1
1.3 Rating (KW
W) As per
p design calculation
c @ C10 rating g
1
1.4 Output Voltage Booost Mode: Constant
C currrent chargin
ng up to
Vbooost (Voltage level setta
able from 455V – 75 V)
(use e), followed by constant voltage at
er selectable
Vbooost.
Chaarger shall be
b designed d to deliver current
c not less
thann C10/3 wh hen at-leastt single pha ase (180 ~ 250
Vacc) supply is available
a at input terminnals.
Chaarger shall be
b designed d to charge the single bank
b
of Ni-
N Cd batte eries of in b
both manua al boost & auto
a
floa
at mode (useer selectablee).
1
1.6 Battery Spe
ecification Sin
ngle banks of
o 36-40 cellls as per SO OR.
1
1.7 Indications /Annunciatio
ons a) 'R" Phase
P ON
b) 'Y' Phase
P ON
c) 'B' Phase
P ON
d) Charger ON
e) Charger Fail
f) Currrent limit / S
System overr load
g) Boosst charge
h) Floaat charge
1
1.3 Arrangement In 1X
X100%, sha all be conne
ected to both
h battery ban
nks
with provision to
o charge eaach battery bank
b
indiv
vidually.
1
1.4 Charger I/O
O a) Is
solated 4-20
0 MA signals for
i) DC oltage : 0 to 100V DC
C output Vo
737 of 896
MEECON LIMITTED STANDARD TECH
HNICAL SPE
ECIFICATIO
ON
REGD. OFF: RA
ANCHI
4002
834 ELECTRICA
AL SECTION
N, DELHI
g) System
S leve
el: Mode off Operation, Active Fau
ults,
Heat
H Sink/ IGBT tempeerature, Sysstem Mimicc.
1
1.6 Graphical User
U Interfacce(LCD Disp
play) a) Battery
B Side
e: Voltage, Current
b) Grid
G Side: Phase V Voltage, Phase Currrent,
Frequency,
F Power, Power Factor
c) System
S leve
el: Mode off Operation, Active Fau
ults,
Heat
H Sink/ IGBT tempe erature, Sys
stem Mimicc
1
1.7 Protectionss & Alarms (With
( LCD a) Over voltage
b) Under Voltage
V
Display)
c) Over Cuurrent
d) Over Teemperature T Trip (Heat Sink
S Temp.)
e) Over cha arging prote
ection
f) Short cirrcuit
g) Over Teemperature T Trip (Heat Sink
S Temp
h) Earth fault
i) Lightningg surges (in
n both input & output)
j) Manual selection off Float & Boo ost Mode
k) Fuse Faailure
1
1.8 Monitoring signal for re
emote SCA
ADA Alll parameteers of FCBCC shall be available
a allong
monitoring with Solar charge
c conntroller parrameters on a
single MODB BUS RS-48 85 bus. Min nimum required
signals are as
a below-
i) DC output Voltage:
V 0 tto 100V DCC or as per the
t
deesign
ii) DC Outputt Current: 0 to 100A orr as per dessign
iii)) FCBC Input Voltage & Current of
o each phasse
iv) SPV Inputt voltage & Current.
738 of 896
MEECON LIMITTED STANDARD TECH
HNICAL SPE
ECIFICATIO
ON
REGD. OFF: RA
ANCHI
4002
834 ELECTRICA
AL SECTION
N, DELHI
b) Potential
P free
e contacts ffor
i) AC power availability
a o
of each pha
ase (R, Y, B)
B
ii) Charger ON
O
1
1.9 Output Voltage 40-7
75 V DC/ Ass per design
n/Recommen
nded by
Batttery Manufacturer
1
1.10 Enclosure protection
p IP 42
1
1.11 Mounting Floo
or
1
1.12 Cable entryy From
m Bottom
1
1.13 Efficiency >90% (Over all)) @100% lo
oad
1
1.14 Material ussed inside ch
harger All the
t materials for connecctions, cable es, bus bar,
tran
nsformer win nding etc sh
hall be of cop
pper with
suittable rating.
2
2.0 CAB
BLE AND ACCESSOR
A RIES
2
2.1 Interconneccting Cabless Type Cu- conductor XLPE
X Insula
ated, PVC sh
heathed,
armo
oured FRLS S type
2
2.2 Cable gland
d type Double compresssion type
2
2.3 Lugs-type Tinn
ned Cu
2
2.4 Other accesssories As re
equired
739 of 896
Annexure-IX
to
Particular Job Specification
(FIRE PROTECTION SYSTEM)
740 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
FOR
FOR
741 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
CONTENTS
SL.NO. DESCRIPTION
6.0 VOID
14.0 CONSTRUCTION
18.0 ESCALATION
APPENDIX-VII: DRAWINGS
742 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
The job includes design, engineering, supply, erection, testing and commissioning of
clean agent system, fire detection & alarm system with associated civil, electrical and
instrumentation facilities, portable extinguishers, Fire Protection Equipment, First Aid
& Safety Equipment for Terminal works for Srikakulam- Angul Pipeline Project (Part-
B)
The intent of the specification is to cover the design, engineering, supply, manufacture
/ fabrication, procurement, packing, forwarding to site, unloading at site, receipt,
storing, erection, testing, shop painting, commissioning and guaranteed performance of
the following and as outlined in various chapters of the technical specification:
A. Clean Agent System for Ceiling void, Room void & Floor void/cable trenches.
D. Associated Civil & structural works, electrical & instrumentation works including
supply of all materials.
The Control room sizes for clean agent system are indicated in SOR.
The contractor shall include all supports, inserts etc. required for the above system,
instrumentation & electrics of the system and all necessary operating platforms and
ladders, if required, for the safety and maintenance of the equipment and the system
as a whole. Contractor shall consider Clean Agent Suppression System for Cable
Trenches/ Floor void apart from the dimensions mentioned above without additional
cost to the company.
2. 2 The delivery of the items shall be made at site of M/s GAIL at various locations of the
project as elaborated elsewhere in the specification.
2.3 Any additional item/ component that are not specifically mentioned in the specification
but are required to make the system/ equipment complete in all respects for safe
operation and guaranteed performance shall be under the scope of this specification.
2.4 The contractor shall furnish the names of the sub-suppliers, if any, along with the units
/ quantity intended to be procured from them. List of approved makes of materials is
enclosed in the tender document. Only those vendors shall be acceptable for whom the
names are specified against the items. For any other item not mentioned in the list, the
successful party will take prior approval before placement of order.
2.5 Provision shall be made for tripping off the ventilation and A/C system and power
743 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
supply to the fire affected zone automatically along with the discharge of the
extinguishing media after getting the confirm fire signal.
2.6 The fire fighting measures are of paramount importance to safeguard the material,
product / information stored manpower and property from the fire hazards. Fire may
occur inside the plot premises consisting of general technological unit areas, metering &
filtration area, buildings (office block, control room, gate areas, non plant building etc.)
as per the layout drawing at any location or unmanned rooms due to any mishap or
sudden abnormal rise of temperature due to abnormal operating condition. Gas based
fire suppression system has been considered for control room buildings and portable
extinguishers has been envisaged for other area protection.
Depending upon the nature of the units to be protected from fire, fire protection
systems viz. clean agent based Fire suppression system; automatic fire detection-
cum-alarm system, portable fire extinguishers & fire fighting accessories shall be
provided.
However, automatic fire detection-cum-alarm system & fire suppression system shall
be provided in all the electrical rooms, Control / Scada rooms and Battery room as
per Specification.
2.8 The system as a whole along with equipments, components, flow calculation
software etc. shall be approved by UL / FM / ULC / LPCB/VDS.
The work tendered in this bid package consists of Design, supply of materials as
required, installation, testing and commissioning of Fire Protection system including all
Associated Mechanical, Civil, Structural, Electrical, Instrumentation etc.
744 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
2.9 All works of the pipeline & other works included in the scope will be done
simultaneously from the date of issue of FOA. Bidder will organize equipment and
manpower accordingly to meet this requirement as per instruction of Engineer-in-
charge.
The fire protection systems shall be designed taking into account the meteorological
data prevailing at the project site.
The scope of work of the Tenderer shall include supply, erection, testing and
commissioning of clean agent Flooding system and fire alarm system in the control
room, associated civil, electrical and instrumentation facilities at various stations of
the Project.
The tenderer shall furnish the list of commissioning and two (2) years maintenance and
operational spares in the offer. Complete details of all spare parts, their relation to the
equipment and their itemized prices shall be furnished in the tender. Prices shall be
mentioned in the price envelope and item wise list of spares without price shall be
furnished in the unpriced bid.
The bidder must include in the quoted price for the following mandatory spares to be
supplied with the Clean Agent system at each location: The Price for the same shall be
included in the Lump sum price of clean agent system & Fire Alarm system in SOR.
745 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Automatic and Manual release One of each type/size used in the systems
1
system supplied
Cylinder Valve with safety pressure One of each type / size used in the systems
2
relief device supplied.
10% of total nozzles used in each size / type
3 Clean Agent Nozzles
with minimum drill holes.
4 Clean Agent Release Push Buttons 10% of total used of each type etc. (Min, 2 nos)
20 % (Subject to Minimum of 1) of each type,
5 Pressure Gauges
range, MOC, and rating, whichever is higher
6 Solenoid Valves 20% or Minimum 2 numbers of each type used
10% of Panel Mounted items like pushbuttons,
7 Panel Mounted Instruments
lamps, switches
10% or Minimum of 1, whichever is higher of
8 Transmitters
each type, range
4.2 The scope of work and services to be rendered by the Tenderer for installation of fire
fighting system shall include but shall not be limited to the following activities.
ii) Miscellaneous materials and services, if not otherwise specifically asked for, shall
include the following:
- Constructing site office, covered store, open storage at designated place including
supply of construction material and removal of the same on completion of work.
- Site cleaning, removal and disposal of debris, maintaining clean condition in and around
the working place and as instructed by authorized representative of MECON / Owner.
- Distribution of electric power supply for erection work through licensed electrical
contractor / licensed electrician. Construction power shall be made available by Owner
at one place.
- All piping integral to or between any equipment furnished under this specification,
except as otherwise specified.
746 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
- All necessary isolation valves fitting at the tapping points and branch pipes.
- Base plates, thrust blocks, duck-foot bends, matching flanges, supporting materials and
shims.
- All necessary instruments, power and control wiring integral to any equipment furnished
under this specification. This shall include terminal blocks and integral wiring to these
terminal blocks for equipment requiring external connection.
- Initial fill of gas in the cylinder and other fire extinguishing media.
4.3.1 Work permit system in line with OISD: 105 as per GAIL’s HSE Management System
shall be followed.
4.3.2 Permits shall be issued in SAP system and shall be issued to EIC as per GAIL’s
procedure.
4.4 Technical Qualification Criteria for Equipments which are pre-requisite to qualify
technically in the bid are as follows:
4.4.1 All the high pressure Cylinders to be used for the clean agent system shall have
PESO approval in the name of GAIL as per IS: 7285-2 and also shall have approval
from UL/FM/LPCB/VDS as part of complete system in addition to approval from
PESO.
4.4.2 Support letter from OEM from whom the bidder intends to take authorization for the
system, authorizing the bidder for Clean Agent System, for Control Room for design/
engineering/ execution, commissioning & after sales service for specialized systems
such as Clean Agent Suppression system, Fire Detection & Alarm System compatible
to the specifications shall be submitted along with the bid.
4.4.3 System / equipment / component offered shall be strictly in line with technical
specifications defined in the tender document. No deviation to technical specification
shall be permitted. Bidders must note that offer of bidders not matching the
747 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
The Fire system shall deploy High Sensitivity Smoke/ Heat Detectors to allow swift
detection of heat and/or smoke.
The fire alarm should be designed to cut power to air-conditioning system. Second
alarm should cut all the power supply to the control room excluding supply to critical
equipments and the fire suppression system should be triggered off after a pre-set
time interval.
The fire detection & alarm system shall comprise of the following items /
equipments:
- Heat Detectors
- Ionization Type Smoke Detectors
- Photo Electric / Optical Type Smoke Detector
Signal and control shall also be provided on main fire alarm control panel from gas
based fire extinguishing system.
748 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
In cable trenches and below false floors, detection of fire shall be by a highly
accurate & sensitive mechanism which can detect direct & indirect fire exposures.
LHS shall be used for detecting heat from a fire over its entire length. The sensor
cable shall consist of a twisted pair of copper coated steel conductors covered by a
temperature sensitive insulation. The LHS shall be UL/FM/LPCB/VDS approved and
shall be designed for open area as well as proximity detection. LHS shall be
compatible with any fire control panel that is capable of accepting contact closure
type initiating devices.
Linear Heat Detection System shall be used for effective activation of a warning or
alarm signal indicating a condition of excessive heat or fire. In this system, each
discrete addressable LHS cable zone shall report an individual alarm to the
addressable fire control panel. The detector should be capable of detecting fire even
under harsh conditions. The response behavior of the detector shall be precisely
adjustable to suit the environment & small temperature variations caused due to
environmental fluctuations and shall not result in false alarms. The detector unit shall
send fault signal when the LHS is damaged (Cut or damaged).
The parameters as mentioned against each requirement are indicative and bidder
has to submit the data sheet of LHS for approval of MECON during detailed
engineering.
5.1.3 The system shall operate on 230 VAC input and 24 VDC SMF Lead acid batteries for
standby supply with battery backup of 48 hours in normal condition & 1 hour in case of
fire condition.
5.2 Clean Agent Fire Suppression System (Inert Gas High Pressure System)
Fire in strategically important places like computer rooms, control rooms, switch gear
rooms, data storage rooms, server rooms, data storage archives, libraries, laboratories
749 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
etc. is a serious hazard to highly precious and irretrievable items and properties.
Occurrence of fire besides leading to personnel injuries and property damage also leads
to loss of productivity and precious time. The primary cause of fire may be due to short
circuit / overheating of certain components somewhere in the areas. Since most of the
areas are unmanned and completely closed, fire inside is not visible and accessible from
outside till it becomes too big, dangerous and unmanageable.
Fire suppression with water-based systems such as hydrant or sprinkler system can
damage the assets permanently. Therefore for these costly & critical areas, the Fire
Protection System envisaged calls for early detection of fire and quenching the same by
flooding the area with gas based fire suppression system besides giving out an audio
visual alarm. The design shall be strictly as per NFPA standard NFPA 2001.
The suppression system shall provide for high-speed release of Gas based on the
concept of total Flooding protection for enclosed areas with High Pressure clean
agent gas (Inert Gas). A Uniform extinguishing concentration shall be as applicable
and approved by NFPA 2001 of the gas for 70 deg F. The system discharge time shall
be in accordance with NFPA standard 2001.
The Fire Suppression System shall include a detection and control system provision for
both pre-alarm and automatic agent release.
The detection and control system that shall be used to trigger the Fire suppression shall
employ cross zoning of Multi-criteria smoke detectors and other detectors. A single
detector in one zone activated, shall cause in alarm signal to be generated. Another
detector in the second zone activated, shall generate a pre-discharge signal and start
the pre-discharge condition.
The discharge nozzles shall be located in the protected volume in compliance to the
limitation with regard to the spacing, floor and ceiling covering etc. The nozzle locations
shall be such that the uniform design concentration will be established in all parts of the
protected volumes. The final number of the discharge nozzles shall be according to the
OEM’s patented and certified software, which shall also be certifiers such as UL /
FM/LPCB/VDS.
The Gas shall be stored in seamless storage containers complying with the SMPV Rules
set out by Chief Controller of Explosives, Nagpur, India. The Bidder shall be required to
produce a NOC for the Chief Controller of Explosives, Nagpur for the storage containers
against the cylinder identification numbers punched on them. Welded cylinders for
agent storage will not be acceptable
The Gas shall be discharged through the operation of an Electric (solenoid) operated
device or pneumatically operated device, which releases the agent through the
pneumatic operated pressure valve. Systems that employ explosive or pyrotechnic
devices for the discharge shall not be permitted.
The Gas discharge shall be activated by an output directly from the Gas Release control
750 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
All the extinguishers shall conform to relevant IS and also bear ISI marking on their body. All
the extinguishers shall be supplied with mountings, accessories and initial fill. The extinguishers
supplied shall be of reputed make having approval of the Purchaser. Relevant BIS and TAC
approval certificate for all the extinguishers shall be furnished. In addition to the above
751 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
certificates, a certificate from Chief Inspector of Explosives shall be furnished for carbon dioxide
type fire extinguishers.
All the portable extinguishers shall be installed along the column/walls near entry/exit/suitable
locations and at a. height of approx. 1200 mm from the finished floor level and also in
accordance with the requirements laid down in OISD: 189 & 214. The design ,construction
and testing of all types of fire extinguishers shall be specified in accordance with
recognized standards as mentioned below.
All types of fire extinguishers shall ,as far as possible, have a standard & simple
method of operation. Portable fire extinguisher sizes will be selected as small as practical to be
effective and for ease of operator deployment.
Co2 extinguisher sizes will be determined to ensure that leakage or accidental discharge
will not cause a hazardous CO2 concentration.
Dry powder portable and wheeled fire extinguishers shall use potassium based agents and be
compatible with AFFF.
Portable extinguishers located in exposed and naturally ventilated locations shall be stored in
suitable weather proof cabinets as protection from the effects of wind and rain.
a) All portable extinguishers shall be supplied along with mounting accessories, wall
brackets and with initial fill of gas or powder in fully assembled condition.
b) All extinguishers shall be treated with lead tin alloy for anti rust, anticorrosive
treatment by electrolytic process.
c) The extinguishers shall conform to the relevant Indian Standards and shall bear the IS
certification mark on their body.
e) All components shall be manufactured with materials of approved quality and of best
workmanship.
f) All eextinguishers shall be welded construction.
752 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
h) All the components / parts of extinguishers viz. Unions, Caps, inner containers etc
shall be metallic and made of bronze or gunmetal.
i) The Out door extinguishers shall be placed on a fixed or portable stand which can be
firmly placed on the ground. The stand shall have hood above, to protect the
extinguisher against Sun & Rain. The size of the stand and the hood shall be
sufficient enough to keep 1 to 2 extinguishers at any point according to their size &
capacity.
b) The welding process shall be per IS: 2825 and shall have the certification for every
extinguisher.
i. Manufacturer’s name.
ii. Year of manufacturing.
iii. Manufacturer’s serial number.
a) The C02 extinguisher shall conform to the latest IS: 15683-2006 with
amendments.
i. Manufacturer’s name.
ii. Year of manufacturing.
iii. Manufacturer’s serial number.
a) Portable Supporting Stand: The stand shall be fabricated out of 50x50x5 angle
753 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
and painted fire red as per painting spec, and the frame shall be designed to
support 4 Nos buckets filled with sand. The stand frame shall have a top hood,
and sufficient enough to protect the buckets against Rain & Sun and paint finished
b) The fire (Sand) bucket shall be fabricated of MS galvanized sheet 0f 1.0 mm thick
and the size shape & profile shall be as per IS 2546-1974 RA2000 and shall have
10lts capacity. The leakage test shall be as per IS. The painting shall be fire red
externally, white inside and black color for ears & handle etc.
The Safety helmet shall be suitable for personal protection against head injuries
by falling objects and also for firefighting purposes. Helmet shall have suitable
adjustable strap by which it can be secured firmly on the head. The helmet shall
be made of HDPE material. Helmet shall be fitted with suitable cushion inside for
comfortable wearing. The helmet shall conform to IS-2925-1984 RA2000, and
shall bear IS mark on the body. As per purchasers requirement all the helmets
shall be numbered on the front and rear sides. The white in color for the captain
and bright yellow for rest of the crewmembers shall be considered.
Stretcher suitable for an adult of size approx 6 feet x 2 feet and made of
wooden/MS poles/bars and adult size blanket and other features generally
conforming to IS-4037-1967 RA-2001. The canvas shall conform to Variety No. 3
of IS : 1424 –1983 RA2000. The color would be as specified by the purchaser,
The carriers shall conform to channels size 80 x 30 mm of IS : 811-1987.
Spreader and Runner are manufactured from mild steel strips. The wooden poles
shall be given a coat of protective varnish and spray painted to any shade as
required by the purchaser. The testing and QA requirements are as per IS.
The expiry of these items shall be at least 18/12 months from the date of supply.
1. First aid for cuts, buns, sprains (instant relief sprays) – 1 each.
2. Antiseptic lotion, liquids (Dettol / Savlon tincture iodine) - 1 bottle
3. Pain relieving medicines, anti vomiting medicines etc. -2 strips of 10 each.
4. 500 mg Paracetamol I.P - 100 tablets.
5. Anti snake serum bottle - 2 Nos.
6. Band-Aids - 20 pcs.
754 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Hand gloves suitable for handling electrical jobs up to 1100 volts type -2 and
conforming to IS-4770 –1991 RA-2001 shall be supplied.
The gloves shall be made from best quality natural rubber or synthetic rubber or
from a mixture there of. The gloves shall have a smooth finish and the edges
shall be finished with a roll or a reinforcing strip of rubber, unless specified
otherwise. The size & thickness of the glove as specified in IS. The gloves shall
be colour coded as Blue for Type 2 application of the rated potential. The gloves
shall be marked indelibly at the back with the following information:
a) Size and type of glove;
b) Maximum working potential in volts, followed by the word ‘working’
c) Identification mark of manufacture and month and year of manufacture.
The Portable Multi Gas detector supplied shall confirm to the following Data sheet:
755 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
756 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
757 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
The Fire Proximity Suit used for firefighting purposes envisaged in close proximity
with the burning oil fire. The suit shall be supplied as per the following
specification:
a) Imported fire proximity suit having approval from any of these agencies:
- U L of USA, U.S. Coast Guard Spec, U.S. Military, NFPA spec,
b) The fire suit shall be stitched with imported stainless steel thread and
fabricated from imported impermeable aluminized glass fiber fabric, which
shall neither burn nor melt during fire fighting operation and along with
imported thermal insulation felt lining to sustain very high temperature.
c) Fabric shall not react chemically with water, and shall not absorb oil, grease,
petrol etc.
d) The suit shall be flexible, with minimum discomfort fireman shall be able to
climb a ladder or to carry running a pressurized hosepipe when he puts on
the suit.
e) The fire suit shall consist of detachable chest length drape buttoned head
gear with built in industrial helmet and heat reflective dual layer visor,
aluminized gloves.
f) The suit shall include hood, coat, pants, boots, mitts/gloves. Metal zip
fasteners shall be provided for easy donning and removal of the suit.
g) The size of suit shall be of adjustable such that any adult fireman of height
approximately 5’6” to 6’2” can use. The suit must have the provision for
keeping the breathing apparatus at the back. The time required for donning
the suit shall not be more than 1.5 minutes.
i) The suit shall protect & sustain against proximity ambient heat up to 2600 C
and the radiant heat up to 10000 C .
758 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
The Electrical Siren used for firefighting & general purposes shall be supplied
complying to IS: 1941-1976-RA2002 (Part 1)
c) Shall match to the Power rating 3 phase, not > 3.75kw, 50Hz, 415 volts.
f) Shall be suitable for the power line specification available in the state.
h) The electric motor shall be enclosed totally, with sealed greased ball
bearing system and shall conform to IS: 325.
i) The operation controls shall be available both at local point & central
locations.
j) The siren shall be clearly and permanently marked with the following
information:
The Hand Operated Siren used for firefighting & general purposes shall comply
to IS:6026-1985-RA1995.
b) It shall have Siren body inbuilt disc and handle, guard & portable stand.
d) Workmanship
759 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Red and green bright colored flags suitable for the fire drill. Handle shall be made
of hard aluminum tube of size not less than 20 mm dia. The edges shall smooth
finish and have rubber caps. The flag shall have minimum dimensions of 0.6m x
0.4m. The cloth shall be of thick poly mixed cotton & color shall be bright and
long lasting. The flag shall be firmly secured to the handle by the shorter side.
In order to carry the following fire & safety equipment to the place of emergency,
a trolley shall be provided to carry the following items:
The trolley shall be fabricated by using MS channels & angles. The body frame
shall be minimum size of 6.0’x 3.0’ (feet x feet) Supplier can also indicate
different suitable size for the trolley. The compartments shall be fabricated type
by using MS sheets and MS tubes or angles. The compartments shall be sufficient
enough to carry all the above items at one go at any point of time. The inflated
tyre & tube wheels assembly unit shall be fitted to the trolley to pull & push
manually or by towing vehicle. For this purpose the handle and hook
arrangement shall be made. The painting shall be as per painting spec. and
shade shall be fire red color.
6.0 VOID
STANDARDS
760 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
7.1.1 All materials, equipments, piping, valves, fittings etc. dimensional standards, tolerance,
prices of manufacture and testing procedure shall be in accordance with the latest
revision of relevant Indian, British, American standards wherever applicable.
7.1.2 The material used and equipment supplied shall be new and the best of their kind and
shall comply with the latest revisions of all relevant standards. The tenderer shall
indicate in his tender the relevant standards to which the equipment, piping, fittings,
etc. offered by him shall comply with. The latest revisions of applicable standards
indicated in the technical specification shall be used for the design, manufacture,
inspecting and testing of the items covered in this specification. The following codes
and standards shall be considered for design: -
OISD-226
API-25 10 A: Fire protection considerations for design and operation of LPG storage
facilities.
Auto start system with bypass arrangement for jockey pumps in case of pressure
drop in the fire hydrant line.
Foam and Dry Chemical Power extinguishers of capacity as per SOR shall also be
provided and located along with other fire fitting facilities.
Standard for Horizontal Centrifugal Pumps for clear, cold, fresh water IS: 1520-1980
Code of acceptance tests for centrifugal, mixed flow and axial flow pumps IS: 9137-
1978, BS-5316-latest edition, ISO-2548-1973
761 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Sluice valves for water works purpose (50-300mm size) IS: 780-1984
Copper alloy gate, globe and check valves for general purpose. IS:778-1984
Mild steel tubes, tubular and other wrought iron fittings IS:1239, part-1-1990 & Part-
2-1992
Seamless or electrically welded steel pipes for water, gas and sewage IS:3589-1991
Code of practice for laying of electrically welded steel pipes for water supply
IS:5822-1994
Criteria for design of anchor blocks for penstock with expansion joints IS:5330-
1984
Covered electrode for manual metal arc welding of carbon and carbon
manganese steel IS:814-1991
762 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Specification for arc welding of carbon and carbon manganese steels BS:5135-
1984
8.1 The contractor shall adhere to all applicable statutory requirements including TAC,
OISD, Inspectorate of Factories, Indian Electricity Rules and other statutes of Govt. of
India and state government. The contractor shall himself ascertain all applicable
requisite regulations.
8.2 The contractor shall be solely responsible for obtaining necessary clearances from
various statutory bodies including those of Govt. of India / State Govt. and as applicable
during the course of manufacture/ fabrication, testing, transportation and delivery of
plant and equipment.
8.3 Contractor shall keep constant liaison with the local Fire Authority, Electrical Authority
and all other Statutory Authorities whose approval and permissions/ sanctions before
execution of the work are required to be obtained.
8.4 It shall be the Contractor's responsibility to obtain the approvals and permissions,
sanctions, No Objection certificates from relevant Fire Authorities during construction by
him to enable owner to take up the operation of plant. Contractor shall comply with all
763 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
The contractor shall be responsible for handing over the work complete in all respects
and in proper finished condition, on completion of the work. If there is any damage or
disfiguration/ stains on the finished surfaces including on wall, floors, ceiling, columns,
beams etc. due to contractors use, damage or any other reason during the period of
construction, the same shall be rectified suitable by the contractor without any extra
payment.
The quantities of different material, pipes/ fittings, valves, flanges, erection, accessories
etc. Mentioned in the specification and SOR are approx. quantities and any
change in requirements will be as per the finally approved drawings. Any item,
instrument which is not specifically mentioned in the SOR, but required for the
completeness of the system, will have to be supplied and erected by the
contractor and the financial implication shall be built in the testing and
commissioning item.
10.1 Procurement
10.1.1 CONTRACTOR shall procure and supply all the materials other than OWNER
supplied materials, required for permanent installation of terminals in sequence
and at appropriate time. All equipment, materials, components etc. shall be
suitable for the intended service. Approved vendor list has been indicated in the
bid package for various items. For items, which are not covered in the vendor
list, CONTRACTOR shall obtain Owner’s prior approval for the vendor.
Equipment requiring specialized maintenance or operation shall be avoided as
far as possible. Equipment offered shall be field proven.
10.1.3 Material take-off with complete description of size, rating, material, thickness
and specifications.
10.1.4 Only single offer shall be provided by the bidder fully complying with the
specifications/ drawings/ requirements for Owner’s review and approval.
CONTRACTOR shall provide for inspection of the items at vendor's works by the
OWNER/ Owner’s REPRESENTATIVE or by a reputed inspection agency and
764 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
10.1.5 Stores management for contractor supply items as well as free issue materials
including receipt, warehousing, preserving the material in good condition, issue
of material to construction site, reconciling/ handing over surplus material to
OWNER for OWNER supplied items at Owner’s store.
10.1.7 CONTRACTOR shall immediately report to the OWNER of all changes, which will
affect material quality, and recommend any necessary corrective actions to be
taken.
10.1.8 Submit periodic manufacturing progress reports highlighting hold ups and
slippages, if any, to OWNER and take remedial measures.
10.1.9 Interact with authorities such as Sales Tax, Octroi, Excise, Customs etc. as
necessary and arrange for transportation of the materials under his scope of
supply to site.
10.1.11 Compliance with vendor's and supplier's instructions and recommendations for
transportation, handling, installation & commissioning.
10.2 Construction
10.2.1 General
10.2.1.1 All construction works shall be carried out as per Approved drawings,
procedures, specification and applicable codes and standards. Any changes at
site shall also need prior approval from the OWNER and revision of drawings.
Based on system to be proposed by bidder, the contractor shall submit detailed
engineering execution drawings with all calculations for approval of PMC.
.
10.2.1.2 Providing schedules, progress reporting, organization chart at construction site,
quality assurance plan and developing quality control procedures, as per
requirements indicated elsewhere in the bid package.
765 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
10.2.1.6 All Civil / Structural Works, Electrical, Instrumentation Works, laying and
commissioning works shall be performed in accordance with relevant
specifications and requirements enclosed elsewhere in the bid package.
10.2.1.8 Provide, maintain and operate all temporary facilities required for the
construction related works and remove after completion of work.
10.2.1.12 All incidental and associated works and any other works not specifically listed
therein but are required to be carried out to complete entire work related to
pipelines and terminals.
10.2.1.13 Loading, unloading, handling, stacking, storing and shifting to workshop / work
site of all materials that may be used for the construction of ITEMS either
supplied by OWNER at their designated stack yard/ dump site / store and / or
by CONTRACTOR as the case may be.
10.2.3.1 Void
10.2.3.2 VOID
10.2.3.3 Painting
766 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Nil
11.2 VOID
11.3 VOID
11.3.1 VOID
11.3.2 VOID
11.3.3 VOID
11.3.4 Openings of equipment, machinery etc. shall be kept blocked/ covered with
blinds to prevent entry of foreign matter.
11.3.5 All valves, instruments, control valves, actuated valves, pressure gauges,
thermometers etc. supplied alongwith equipment and machinery shall be stored
separately, inside the covered godown on racks.
11.3.6 As far as possible materials shall be transported to the erection site, just prior to
their actual erection and shall not be left laying around indefinitely. Instructions
for the Engineer-in-charge shall be followed strictly in this regard.
The procurement and supply, in sequence and at the appropriate time, of all
materials and consumables required for completion of the work as defined in
this Bid document except the materials shall be entirely the CONTRACTOR'S
responsibility and item rates quoted for the execution of the CONTRACT shall be
inclusive of supply of all these materials. The material to be supplied by the
Contractor shall be as per specification and preferred make as indicated in
Appendix-I or duly approved / recommended for use by GAIL/ MECON.
767 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
11.5 General
11.5.1 All safety tools/tackles, devices / apparatus / equipment etc. including ladders
and scaffoldings etc. complete as required.
11.5.2 Any other material not specifically listed herein, but required for the execution
of
the work.
12.1 Owner shall approve design & engineering drawings and construction drawings
including general arrangement drawings for piping, electrical, mechanical &
instrumentation systems and other related/ required systems, at appropriate
times and as requisitioned by contractor in his time schedule based upon
submission of those drawings by the contractor..
12.3 No construction small or big shall be carried out without proper construction
drawings duly approved by Owner's Engineers at Delhi or site office or Owner's
representative duly authorized to do so.
12.5.1 The drawings accompanying the Bid document are indicative of scope of work and
768 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
issued for tendering / bidding purpose only. These drawings indicate the general
scheme as well as the layout to enable the contractor to make an offer in line with
the requirements of the owner. Final construction shall be done as per Approved
Drawings.
12.5.2 Basic/Detailed drawings shall be made by the contractor and shall be submitted
for Approval.
The Contractor shall not recruit personnel of any category from among those
who are already employed by the other agencies working at the sites but
shall make maximum use of local labor available.
Owner shall not provide any land for residential accommodation of contractors
staff and labor.
14.0 CONSTRUCTION
14.2 Procedures
769 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
CONTRACTOR shall have at all times during the performance of the WORK, a
Competent Superintendent on the premises. Any instruction given to such
superintendent shall be construed as having been given to the CONTRACTOR.
CONTRACTOR shall be solely responsible for making available for executing the
work, all requisite Construction Equipments, Special Aids, Cranes, Tools, Tackles
and testing equipments and appliances. Such construction equipments etc.
shall be subject to examination by owner and approval for the same being in
first class operating condition. Any discrepancies pointed out by OWNER shall
be immediately got rectified, repaired or the equipment replaced altogether, by
CONTRACTOR. OWNER shall not in any way be responsible for providing any
such equipment, machinery, tools and tackles.
The OWNER reserves the right to rearrange such deployment depending upon
the progress and priority of work in various sections.
15.0 VOID
16.1 The order in which the WORK shall be carried out shall be subject to the
approval of the Engineer-in-charge and shall be so as to suit the detailed
method of construction adopted by the CONTRACTOR, as well as the agreed
joint programme. The WORK shall be carried out in a manner so as to enable
the other contractors, if any, to work concurrently.
770 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
16.2.1 Drains, pipes, cables, overhead wires and similar services encountered in course
of the works shall be guarded from injury by the CONTRACTOR at his own cost,
so that they may continue in full and uninterrupted use to the satisfaction of the
Owners thereof, or otherwise occupy any part of the SITE in a manner likely to
hinder the operation of such services.
16.2.2 Should any damage be done by the CONTRACTOR to any mains, pipes, cables
or lines (whether above or below ground etc.), whether or not shown on the
drawings the CONTRACTOR must make good or bear the cost of making good
the same without delay to the satisfaction of the Engineer-in-Charge.
18.0 ESCALATION
The Unit Rates quoted shall be kept firm till completion of work and no price
Escalation shall be paid.
i) Computerized R.A. Bill/ Manual Bill, with IT No./ ST No./ Labor License
No. printed thereon.
ii) ESI/ EPF clearance certificates for the last month alongwith R.A. Bills.
vi) Any other document required for the purpose of processing the bills.
771 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
20.1 General
Inspection & testing of plant & equipment shall be carried out by Purchaser /
Consultant at the works of successful Bidder (Contractor/Sub-contractor)
during manufacturing and on final product to ensure conformity of the same
with the acceptable criteria of technical specifications, approved drawings,
authenticated manufacturing drawings and reference National / International
standards.
Contractor must follow defined quality program in all manufacturing and quality
control activities of the product. Contractor must define and implement the tasks
and controls that will provide needed assurance in case manufacturing of product
is sub-contracted either partly or fully and/or for the procured components of the
product. All bought-out equipment or component shall be procured from approved
list of vendors issued by the project authority.
Purchaser/Consultant reserves the right to verify the quality program and entire
product characteristics to assure the intended and specified quality of the product.
20.3.1 Contractor shall furnish Quality Assurance Plan (QAP) for respective equipment after
completion of detailed engineering and finalization of billing schedule / equipment
identification number for Purchaser / Consultant's approval at least two months
prior to start of manufacturing.
2.3.3 Detailed QAP shall be prepared & furnished in formats in consultation with his Sub-
contractors / Manufacturers to avoid any complication later.
20.3.4 Inspection and test requirements shall be decided with due consideration of factors
like safety, duty cycle, operating conditions, equipment life, environmental
conditions, place of installation and statutory regulations, as applicable, for a
particular equipment. Any additional, special tests & routine tests if found necessary
to establish the intended quality, shall be incorporated in the QAP.
20.3.5 QAP shall clearly indicate the following in the appropriate columns:
a) Range of inspection & tests to be done by Manufacturers and cross
772 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
773 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
- Visual inspection
- Alignment and fitment checking
- Dimensional checking
- Weld inspection - visual and NDT as per design
requirements. Radiographs are to be shown
and reports to be submitted to
Purchaser/Consultant for review during
inspection, if applicable.
- Witnessing of other tests like pneumatic,
hydraulic, no-load running, functional,
balancing, performance, vibration, noise level,
etc. depending upon criticality of the part
item/equipment.
Mechanical
- Flowmeters
- Insulation materials
- Bolts, nuts & washers (Grade 4.6).
20.5.1 All the measuring equipment used for inspection & testing shall be calibrated
and appropriate accuracy class of measuring equipment shall be used.
20.6.1 For each of the items being manufactured, following test certificates and
documents duly endorsed by the manufacturer / contractor shall be
submitted to Inspection Agency.
774 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
xvi) Certificates from competent authority for the items coming under
statutory regulations.
20.6.2 Where physical and chemical test certificates of material are not available,
the Contractor/Sub-contractor shall arrange to have specimens and test
samples of the materials, tested in his own laboratory at his cost and submit
the copies of test results to Inspection Agency for scrutiny and approval.
Number of test samples against each heat/cast/lot or batch of materials shall
be as per relevant Indian or International Standards.
20.6.4 The Inspection Agency shall have the right to be present and witness all tests
being carried out by the Contractor/Sub-contractor at their own laboratory or
775 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
approved laboratories. Also, the Inspection Agency shall reserve the right to
call for confirmatory test on samples, at his discretion.
20.7.1 All contractors shall submit the schedule for manufacturing and inspection
indicating equipment/ components/ sub-assembly/ assembly, date of
approval of drawings/data sheets, address of manufacturer with contact
person and scheduled date of inspection. Such reports shall be submitted to
Purchaser/Consultant's respective Inspecting Offices with a copy to
Inspection Co-ordinating Office once in a month. These monthly reports shall
state the planning for next three months. Submission of first report must
commence one month prior to commencement of manufacturing activities of
the product.
20.8 Internal Inspection by Contractor / Manufacturer
20.8.1 Inspection and tests shall be carried out by Contractor/ Manufacturer in
accordance with approved drawings, T.S., P.O., and approved QAP.
Contractor/ Manufacturer shall maintain record of each inspection and test
carried out and signed documents shall be submitted to Purchaser/Consultant
for verification.
20.8.2 Contractor shall carry out their internal inspection & obtain clearance from
statutory bodies e.g. IBR, CCE, TAC, Weights & Measures, Safety, IE rules
etc. Prior to offering any equipment for Purchaser/Consultant's inspection in
accordance with approved QAP wherever required.
20.8.5 The Contractor shall establish and maintain procedures to ensure that non-
conforming product are prevented from inadvertent use or installation. The
description of non-conformity that has been accepted subsequently by
Designer /Purchaser by concession and/or of repairs shall be recorded.
20.8.6 Contractor / Manufacturer shall not dispatch any equipment before inspection
and issue of Inspection Certificate & dispatch clearance from Purchaser /
Consultant.
776 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Consultant:
(ii) Inspection call shall be floated enclosing all documents like test
Certificates, Internal Inspection Reports, P.O., Sub-P.O., T.S., Approved QAP,
approved GA drawings/ data sheets and manufacturing drawings with a copy
of call letter. Inspection calls without above documents shall be ignored.
20.10.1 The Contractor shall provide all facilities and ensure full and free access of
the Inspection Engineer of Purchaser/Consultant to the Contractor's or their
Sub-Contractor's premises at any time during contract period, to facilitate him
to carry out inspection & testing during or after manufacture of the product.
20.10.3 The Contractor shall comply with instructions of the Inspection Engineer fully
and with promptitude.
20.10.7 The Contractor shall not offer equipment for inspection in painted condition
unless otherwise agreed to in writing by Purchaser/Consultant.
777 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
20.10.8 The Contractor shall ensure that the equipment and materials once rejected
by the Inspection Engineer are not re-used in the manufacture of the plant
and equipment. Where parts rejected by the Inspection Engineer have been
rectified as per agreed procedures laid down in advance, such parts shall be
segregated for separate inspection and approval, before being used in the
work.
For stage inspection & for rejected items/items which do not conform to
Technical Specification in one or more quality characteristics requiring
rectification /rework, Inspection Memo shall be issued in standard form
indicating therein the details of observation & remarks. All the
non-conformities with respect to specification of the product shall be
indicated in the Inspection Memo for further control by Manufacturer.
On satisfactory completion of final inspection & testing, all accepted plant &
equipment shall be stamped suitably and Inspection Certificate in standard form
shall be issued by the Inspection Engineer for the accepted items.
For the waiver category of items pre-identified in the approved QAP, after
scrutiny of Contractor's Internal Inspection Report, Test Certificates and other
Documents as identified in QAP Consultant shall issue Inspection Waiver
Certificate after taking due consent of Purchaser.
20.12.1 Inspection & tests carried out by Purchaser / Consultant shall not absolve the
responsibility of the Contractor/Manufacturer to provide acceptable product
nor shall it preclude subsequent rejection.
Purchaser/ Consultant reserve the right to inspect any product at any stage of
manufacturing without prior notice to Contractor/Manufacturer beyond
pre-identified stages & hold points of approved QAP.
778 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
779 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Appendix-I
i) Pipes (1239/3589)
1. TISCO, Calcutta
2. Jindal Pipes, New Delhi
3. Ajanta Tubes, New Delhi
4. Gujrat Steel Tubes
5. Khandelwal
ii) Valve
a) Globe Valves
b) Ball Valves
780 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
2. Virgo, Pune
3. Microfinish Valves, Hubli
4. Flow Chem, Ahmedabad
c) Check Valves
d) Plug Valves
iii) Flanges
781 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
iv) Fittings
v) Gaskets
782 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
vi) Fasteners
a) Fire Extinguishers
783 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
1. Zenith
2. Minimax
3. Newage
4. HD Fire
5. Vijay Fire
6. Asco Strumech Pvt Ltd, India
7. Brij Basi Hi
8. tech Udyog
9. Gunnebo India Ltd
10. Nitin Fire Protection Pvt Ltd
11. Shah Bhogilal Jethamal & Brothers
12. Venus Pumps & Engineering Works
c) RRL Hose
1. Jayshree
2. Newage
d) Hoses
e) Hose Delivery
784 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
h) Diesel Engines
1. Cummins India
2. Greaves Cotton Limited
3. Kirloskar Oil Engines Limited
B) Instrumentation
785 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
1) M/s MTL
2) M/s P & F
V) RTDs
1) M/s General Instruments Ltd., Mumbai
2) M/s Nagman Sensors (Pvt.) Ltd.
3) M/s Pyro Electric, Goa
786 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
4) M/s Honeywell
X) PUSH BUTTONS/LAMPS:
1) L&T
2) SIEMENS
XI) MCB’S:
1) HAVELL’S
2) INDO ASIAN
3) MDS
XII) RELAYS:
1) OEN
2) JYOTI
1) ELNOVA
2) APLAB
787 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
XV) INDICATORS/CONTROLLERS/RECORDERS
1) M/s ABB
2) M/s YBL
3) M/s EUROTHERN
4) M/s TATA HONEYWELL
5) M/s MASIBUS
1) PROCON
2) IIC
XVII) PLC
1) M/s Siemens
2) M/s Yokogawa
3) M/s ABB
4) M/s Rockwell
5) M/s GE
1) M/s Emerson
2) M/s Yokogawa
3) M/s Fuji
4) M/s Honeywell
5) M/s SB Electronics
6) M/s LEVCON
788 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
7) M/s CHEMTROL
C) ELECTRICAL
Air Conditioner
1. O General
2. Daikin
3. Hitachi
4. Carrier
5. Voltas
Cable – HT(XLPE)
789 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Cable – Gland
1. Baliga
2. Comet
3. Flexpro
4. Flameproof
5. FCG
6. Electro Werke
7. Dowels
Cable – Lugs
1. Dowels
2. Jainson
3. Hex
Cable – Tray
1. Ercon Composites
2. Yamuna Power & Infrastructure Ltd.
790 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Contractors – AC Power
1 Andrew Yule
2 ABB
3 BHEL
4 C&S
5 Havell’s
6 L&T
7 Schneider
8 Siemens Ltd.
9 Telemechanique
Control Transformer
1. AE
2. Indushree
3. Intra Vidyut
4. Kalpa Electrikals
5. Transpower Industries Ltd.
6. Siemens
DG Set
1. Sterling and Wilson.
2. GD ankalesaria.
3. Deev Genset.
4. Jackson
5. Sudheer Gensets.
6. Power Engineering(India) Pvt Ltd.
Earthing Materials
1. Rukmani Electrical & Components Pvt Ltd.
2. Indiana Grating Pvt Ltd.
High Mast
1. Bajaj Electricals Limited
791 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
1. BHEL
2. Siemens
3. Tricolite Electrical Industries
4. Schneider
5. CGL
6. L&T
1. ABB
2. SIEMENS
3. L&T
4. Schneider
5. CGL
6. BHEL
Indicating Lamps
Alstom Ltd.
BCH
L&T Ltd.
Siemens Ltd.
5. Vaishno Electricals
Indicating Meters
1. ABB
2. AMCO
3. AE
4. Alstom Ltd. (EE)
5. Conzerv/Schneider
6. Elecon Measurement Pvt. Ltd.
7. HPL Electric & Power Pvt. Ltd.
8. MECO Instruments Ltd.
9. Minilec
10. Rishabh Instruments Pvt. Ltd.
11. Trinity energy system
12. kaycee
13. Salzer
792 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
Lighting Fixtures
1. GE Lighting Pvt. Ltd.
2. Bajaj Electricals Ltd.
3. Crompton Greaves Ltd.
4. Philips India Ltd.
Motors
1. Siemens
2. ABB
3. CGL
4. Alstom
5. BHEL
6. WEG
793 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
794 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
1. ABB
2. Rockwell Automation
3. L&T
4. Siemens
5. Tricolite Electrical Industries
6. GE
Push Buttons
1. BCH
2. Alstom Ltd.
3. L&T
4. Siemens Ltd.
5. Telemenchanique & Controls (India) Ltd.
6. Vaishno Electricals
Switches-Control
1. BCH
2. Easum Reyrolle Relays & Devices Ltd.
3. Alstom
4. Kaycee Industries Ltd.
5. L&T
6. Siemens Ltd.
Solar Modules
1. Tata BP Solar (I) Ltd.
2. REIL, Jaipur.
3. CEIL, Sahibabad.
4. HBL.
795 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
2. REIL, Jaipur.
3. CEIL, Sahibabad.
4. HBL.
Terminals Blocks
1. Connectwell
2. Controls & Switchgear Co. Ltd.
3. Elmex Controls Pvt. Ltd.
4. Essen Engineering Co. Pvt. Ltd.
Tranformers
1. ABB
2. Andrew Yule
3. Alostom
4. BHEL
5. Bharat Bijlee
6. Crompton Greaves
7. EMCO Ltd.
8. Intra Vidyut
9. Indushree
10. Kirloskar
11. Transformers & Rectifiers (I) Ltd.
12. Voltamp
NOTE:- Item/Vendor, which are not listed above, shall be subject to prior
approval from Client/Consultant.
1) For procuring bought out items from vendors other than those listed
796 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
c) Should have supplied at least one single random length (i.e. 5.5 meters
to 6.5 meters) for item assorted pipes / tubes and minimum 01 (One)
number for other item(s) (other than assorted pipes / tubes) of same
or higher in terms of size and rating as required for intended services.
2) For any other item(s) for which the vendor list is not provided, bidders can
supply those item(s) from vendors/ suppliers who have earlier supplied same
item(s) for the intended services in earlier projects and the item(s) offered is
in their regular manufacturing/ supply range.
3) The details of vendors indicated in this list are based on the information
available with MECON; Contractor shall verify capabilities of each vendor for
producing the required quantity with. PMC does not guarantee any
responsibility on the performance of the vendor. It is the contractor’s
responsibility to verify the correct status of vendor and quality control of each
party and also to expedite the material in time.
797 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
APPENDIX-II
798 of 896
CONTRACTOR
FOR
SUB-CONTRACTOR STRUCTURAL & MECHANICAL PACKAGE No.
EQUIPMENT
ORDER No. & DATE
Annexure-1 PACKAGE NAME
INSTRUCTIONS FOR FILLING UP: CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS :
1. QAP shall be submitted for each of the equipment separately with break-up of assembly / sub-
assembly & part / component or for group of equipment having the same specification. Code Description Code Description Code Description DOCUMENTS
2. Use numerical codes as indicated for extent of inspection & tests and submission of test certificates &
documents. Additional codes & description for extent of inspection & tests may be added as 1. Visual (Welding etc. ) 15. Leakage Test 30. Proving Test D1. Approved GA drawings
applicable for the plant & equipment. 2. Dimensional 16. Balancing test 31. Surface preparation & Painting D2. Information and other
3. Fitment & Alignment 17. Vibration Test 32. Manufacturer’s Test Certificates reference drg. / stamped
3. Separate identification number with quantity for equipment shall be indicated wherever equipment 4. Physical Test (sample) 18. Amplitude Test for bought out items drgs. Released for mfg.
having same specifications belonging to different facilities are grouped together. 5. Chemical Test (sample) 19. Sponge Test 33. IBR / Other Statutory agencies D3. Relevant catalogues
6. Ultrasonic Test 20. Dust / Water Ingress Test Compliance certificate D4. Bill of matl. / Item No. /
4. Weight in tonnes (T) must be indicated under column 5 for each item. Estimated weights may be
indicated wherever actual weights are not available. 7. Magnetic Particle Test (MPI) 21. Friction Factor Test 34. Internal Inspection Report by Identification
8. Radiography Test 22. Adhesion Test Contractor D5. Match mark details
9. Dye Penetration Test 23. Performance Test / 35. Hardness Test D6. Line / Layout diagram
10. Metallographic Exam Characteristic curve 36. Spark Test for Lining D7. Approved Erection
11. Welder’s Qualification & weld 24. No Load / Free running Test 37. Calibration procedures
ABBREVIATIONS USED : procedure Test 25. Load / overload Test 38. Safety Device Test D8. Unpriced sub P. O. with
12. Approval of Test and Repair 26. Measurement of speeds 39. Ease of Maintenance specification and
CONTR : CONTRACTOR procedure 27. Acoustical Test amendments, if any.
MFR : MANUFACTURER 13. Heat Treatment 28. Geometrical Accuracy D9. Calibration Certificates of
14. Pressure Test 29. Repeatability & Positioning all measuring Instruments
Accuracy and gauges
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
799 of 896
ONTINUATION SHEET FORM No. 11.20(DQM) F-09 REV.
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
800 of 896
CONTRACTOR
PROJECT
ORDER No. & DATE QUALITY ASSURANCE PLAN
FOR
SUB-CONTRACTOR ELECTRICAL EQUIPMENT PACKAGE No.
Annexure-2
ORDER No. & DATE PACKAGE NAME
INSTRUCTIONS FOR FILLING UP: CODES FOR EXTENT OF INSPECTION, TESTS, TEST CERTIFICATES & DOCUMENTS :
1. QAP shall be submitted for each of the equipment separately with break-up of assembly / sub-
assembly & part / component or for group of equipment having the same specification. Code Description Code Description Code Description DOCUMENTS
2. Use numerical codes as indicated for extent of inspection & tests and submission of test
certificates & documents. Additional codes & description for extent of inspection & tests may be 1. Visual 12. Routine test as per relevant 23. Short time rating D1. Approved GA drawings
added as applicable for the plant & equipment. 2. Dimensional IS / other standard 24. Operational & D2. Approved single line /
3. Fitment & Alignment 13. Type tests as per relevant IS / functional check schematic diagram
3. Separate identification number with quantity for equipment shall be indicated wherever 4. Physical Test (sample) other standard 25. Over speed Test D3. Catalogues / Approved
equipment having same specifications belonging to different facilities are grouped together. 5. Chemical Test (sample) 14. Impulse Test 26. Flame proof Test data sheet
6. Ultrasonic Test 15. Partial Discharge Test 27. Clearance & creepage D4. Approved bill of materials
4. Weight in tonnes (T) must be indicated under column 5 for each item. Estimated weights may be
indicated wherever actual weights are not available. 7. Magnetic Particle Test (MPI) 16. Heat run test / temp. Rise Test distance D5. Unpriced P.O. copy
8. Radiography Test 17. Enclosure protection Test 28. Internal Inspection D6. Calibration Certificates of
9. Dye Penetration Test 18. Calibration report all measuring instruments
10. Measurement of IR value : 19. Noise & Vibration 29. Acceptance Test and gauges
ABBREVIATIONS USED :
a) Before HV Test 20. Test certificates for bought out
b) After HV Test components
CONTR : CONTRACTOR 11. High Voltage test / 21. Tank pressure Test
MFR : MANUFACTURER Dielectric test 22. Paint shade verification
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
801 of 896
CONTINUATION SHEET
EQUIPMENT DETAILS INSPECTION AND TESTS
Acceptance Criteria
Test Certificates & REMARKS/
Description (with Expected Raw Material and inprocess Standards/IS/ BS/
Quantity Final Inspection / Test by documents to be SAMPLING
Sl. equipment heading, Identification Manufacturer’s Schedule stage inspection ASME/ Norms and
submitted to Mecon PLAN
No. place of use & brief No. Name & address of Final Documents
No./M T MFR CONTR. MECON MFR CONTR. MECON
specifications) Inspection
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
No.
For CONTRACTOR / SUB-CONTRACTOR REV.
For MECON (Stamp & Signature) (Stamp & Signature) SHEET OF
802 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
APPENDIX-III
803 of 896
DATA SHEET FOR FOR SCHEDULE 80 SEAMLESS PIPE FOR 80 mmø
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
2.01 MAKE
3.00 MATERIAL
804 of 896
DATA SHEET FOR FOR SCHEDULE 80 SEAMLESS PIPE FOR 40 mmø
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
2.01 MAKE
3.00 MATERIAL
805 of 896
DATA SHEET FOR OPTICAL SMOKE DETECTOR
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
1.01 NAME OF EQUIPMENT PHOTO ELECTRIC SMOKE DETECTOR
1.02 TYPE INTELLIGENT ADDRESSABLE
2.00 MANUFACTURING DETAILS
2.01 MAKE
2.02 DETECTOR MODEL
2.03 MANUFACTURING STD. IS/BS/OTHER EN 54 PART 7 (2000)
2.04 BASE MODEL
3.00 PRINCIPLE
3.01 DETECTION PRINCIPLE LIGHT SCATTERING
4.00 OPERATING
4.01 MAXIMUM STAND BY CURRENT (TYPICAL) 120 A
4.02 MAIXIMUM PERMISSIBLE ALARM CURRENT(LED ON) 50 ma OR 24 VDC (LIMITED BY PANEL)
4.03 OPERATING VOLTAGE 8 to 30 VDC (Nominal 12/24 VDC)
5.00 MATERIAL OF CONSTRUCTION
5.01 BODY BAYBLEND FR110
6.00 OTHER FEATURES
6.01 TYPE OF MOUNTING SURFACE
6.02 DIMENSIONS
6.03 COLOUR PANTONE, WARM GREY 1C
6.04 WEIGHT
6.05 APPLICATION INDOOR
6.06 INDICATION ALARM : RED LED
6.07 HUMIDITY RANGE 5% TO 95% RH (Non condensing)
6.08 TEMPERATURE RANGE -30°C TO + 80°C
6.09 BI-COLOR LED GREEN : NORMAL , RED : ALARM
806 of 896
DATA SHEET FOR MULTI CRITERIA PHOTOELECTRIC SMOKE THERMAL DETECTOR
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
MULTI CRITERIA PHOTOELECTRIC
1.01 NAME OF EQUIPMENT
SMOKE OR THERMAL DETECTOR
1.02 TYPE INTELLIGENT ADDRESSABLE
2.00 MANUFACTURING DETAILS
2.01 MAKE
2.02 DETECTOR MODEL
2.03 BASE MODEL
2.04 MANUFACTURING STANDARD EN54 5:2000
3.00 PRINCIPLE
3.01 DETECTION PRINCIPLE LIGHT SCATTENING & TERMISTOR
4.00 OPERATING
4.01 STAND BY CURRENT 65A @ 24VDC(LED NO BLINK)
4.02 ALARM CURRENT MAX 80mA @ 24VDC (Limited by panel)
4.03 OPERATING VOLTAGE 8 TO 30 VDC (Nominal 12/24 VDC)
5.00 OTHER FEATURES
5.01 TYPE OF MOUNTING SURFACE
5.02 DIMENSIONS VTA
5.03 APPLICATION INDOOR
5.04 INDICATION ALARM CONDITION RED LED
5.05 HEALTHY CONDITION GREEN LED
5.06 HUMIDITY RANGE 5 % TO 95% (NON CONDENSING)
5.07 TEMPERATURE RANGE -30°C TO + 70°C
5.08 WEIGHT
5.09 MAX. WIRE GUAGE FOR TERMINALS 0.75mm2 TO 2.5mm2
6.00 MATERIAL OF CONSTRUCTION
6.01 BODY BAYBLEND FR110
6.02 COLOR PANTONE WARM GREY 1C
807 of 896
DATA SHEET FOR MANUAL CALL POINT
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
1.01 NAME OF EQUIPMENT MANUAL CALL POINT
1.02 TYPE CONVENTIONAL
2.00 MANUFACTURING DETAILS
2.01 MAKE
2.02 MODEL
2.03 MANUFACTURING STANDARD EN54 PART-11
3.00 PRINCIPLE
3.01 MANUAL CALL POINT PRINCIPLE PRESS-TYPE RE-SETTABLE
4.00 OPERATING
4.01 OPERATING VOLTAGE 30VDC MAX
4.02 CURRENT CONSUMTION 2 Amps
5.00 OTHER FEATURES
5.01 TYPE OF MOUNTING SURFACE
5.02 WEIGHT 110G FLUSH , 160G SURFACE
5.03 DIMENSION HEIGHT : 93 MM, BREATH : 89 MM
5.04 OPERATING TEMPRATURE -10Û&72Û&
5.05 HUMIDITY 0-95% NON CONDENSING
5.06 COLOR RED
6.00 APPROVALS / ACCEPTANCES TEST CERTIFICATE
APPROVED REV. 0
CHECKED BY
BY
808 of 896
DATA SHEET FOR MANUAL ABORT
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
1.01 NAME OF EQUIPMENT MANUAL ABORT
1.02 TYPE CONVENTIONAL / DEAD MAN TYPE
2.00 MANUFACTURING DETAILS
2.01 MAKE
2.02 MODEL
2.03 MANUFACTURING STANDARD EN54 PART-11
3.00 PRINCIPLE
3.01 MANUAL CALL POINT PRINCIPLE PRESS-TYPE RE-SETTABLE
4.00 OPERATING
4.01 OPERATING VOLTAGE 30VDC MAX
5.00 OTHER FEATURES
5.01 TYPE OF MOUNTING SURFACE
5.02 WEIGHT 110G FLUSH , 160G SURFACE
5.03 OPERATING TEMPRATURE -10Û72Û&
5.04 HUMIDITY 0-95% NON CONDENSING
5.05 COLOR YELLOW
6.00 APPROVALS / ACCEPTANCES TEST CERTIFICATE
APPROVED REV. 0
CHECKED BY
BY
809 of 896
DATA SHEET FOR HOOTER WITH FLASHER
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
1.01 NAME OF EQUIPMENT HOOTER WITH FLASHER
2.00 MANUFACTURING DETAILS
2.01 MAKE
2.02 MODEL
3.00 OTHER FEATURES
3.01 DIMENSIONS
3.02 OPERATING VOLTAGE 16 TO 33 VDC
3.03 INPUT TERMINAL WIRE GUAGE 12 AWG TO 18AWG
3.04 CABLE ENTRY 20MM DIA
3.05 STROBE FLASH RATE 1 FLASH PER SEC
3.06 COLOUR RED
3.07 TYPE OF MOUNTING WALL MOUNT
3.08 STANDARD OPERATING TEMPRATURE 0Û&72Û&
3.09 HUMIDITY RANGE 10% TO 93 NON CONDENSING
3.10 LOCATION IN DOOR
3.11 AUDIABLE RANGE 88+ dba AT 16 volts
4.00 APPROVALS / ACCEPTANCES TEST CERTIFICATE
APPROVED REV. 0
CHECKED BY
BY
810 of 896
DATA SHEET FOR
FIRE ALARM AND GAS RELEASE PANEL
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
FIRE ALARM AND GAS RELEASE
1.01 NAME OF EQUIPMENT
PANEL
1.02 TYPE ADDRESSABLE
2.00 MANUFACTURING DETAILS
2.01 MAKE
2.02 MODEL
2.03 MANUFACTURING STANDARD
2.04 MIMIC DIAGRAM A3 SIZE
2.05 ONLINE WEIGHING SYSTEM YES
3.00 OPERATING
3.01 OPERATING VOLTAGE AC : 230V
CURRENT IN NORMAL CONDITION 350MA
3.02
CURRENT IN ALARM CONDITION 900MA (WITHOUT LOAD)
3.03 SYSTEM VOLTAGE 24 VDC
5.00 OTHER FEATURES
5.01 TYPE OF MOUNTING WALL
5.02 DIMENSIONS
5.03 COLOR S. GRAY
5.04 PROTECTION AS PER IP52
5.05 CABLE ENTRY BOTTOM
5.06 APPLICATION INDOOR
5.07 HUMIDITY RANGE 85% NON CONDENSING
5.08 TEMPERATURE RANGE MAX 50Û&
6.00 MATERIAL OF CONSTRUCTION
6.01 BODY MILD STEEL
6.02 DOOR THICKNESS 3mm
6.03 GLAND PLATE THICKNESS 3mm
6.04 BODY THICKNESS 2mm
SEMI GRAY, SEMI GLOSS, MATT,
6.05 COLOR
POWDER COATTED PRIOR TO BAKING
811 of 896
DATASHEET FOR 2 x 1.5 MM2 CU. ARMOURED FRLS CABLE
SR.
DESCRIPTION TECHNICAL SPECIFICATION
NO.
1.00 MATERIAL IDENTIFICATION
1.00 MANUFACTURER
2.00 TYPE OF CABLE SIGNAL
3.00 CONDUCTOR TYPE STRANDED PLANE COPPER
APPROVED REV. 0
CHECKED BY
BY
812 of 896
DATA SHEET FOR SAFETY TORCH
813 of 896
DATA SHEET FOR COTTON HAND GLOVES
814 of 896
DATA SHEET FOR EAR PLUG
815 of 896
DATA SHEET FOR EAR MUFF
816 of 896
OWNER: GAIL (India) LIMITED
CONSULTANT: MECON LIMITED
PROJECT:
CONTRACTOR:
DOC. TITLE: TECHNICAL DATA SHEET OF FIRE EXTINGUISHER
1 Name of Supplier :
2 Type of Extinguisher : Portable Low Pressure
3 Capacity : 2.0 Kg.
4 Test Pressure for Extinguisher body : 35 Bar
5 Burst Pressure for Extinguisher body: 55 Bar
6 Whether handle provided : Yes
7 Chemical charge : a) HFC227ea Clean Agent Gas
b) Dry Nitrogen Gas
8 Volume Expansion space provided : Yes -15 kgf/cm²
9 Safety pin provided : Yes
10 Pressure Gauge : 0 to 28kg Rating
11 Material of Construction
a) Cylinder : M.S. Sheet As Per IS:513 Gr.D, 1.5mm Thick
b) Neck Ring : M.S. Seamless IS 1239 Part 1/ IS 2062
c) Squeeze Grip Valve : Brass Forge to Gr. FLB of lS: 6912
d) Control Nozzle : ABS Plastic as per Annex. B of IS 15683
e) Syphon tube : PVC
12 Dimensions
a) Max. Dia of Extinguisher : 108+ 5mm
b) Overall height of Extinguisher : 300+10mm
13 List of Accessories Provided : Wall mounting Brackets and Screws.
14 Necessity and condition of filling : As per IS 2190
15 Codes and Standards followed : IS 15683
16 Max. Effective range when tested
in still air : More than 2 mtr.
17 Duration of discharge - Min period
for which throw of Jet will be
maintained & % of discharge : 8 Seconds & 95% discharged
18 Anti Corrosive Treatment : Phospheting & Powder coating - Inside & Outside
19 Fire Rating : 1A - 8B
Temp Range : -200 to +550
20 Empty Weight : 1.5kg. approx.
21 Weight of One Extinguisher (Filled) : 3.5 Kg. approx.
817 of 896
OWNER: GAIL (India) LIMITED
CONSULTANT: MECON LIMITED
PROJECT:
CONTRACTOR:
DOC. TITLE: TECHNICAL DATA SHEET OF FIRE EXTINGUISHER
1 Name of Supplier :
2 Type of Extinguisher : High Pressure
3 Capacity - Portable : 4.5 Kg.
4 Fire Rating : 21B
5 Test Pressure for cylinder : 250 kgf/cm²
6 Brust Pressure of Hose : 140 kgf/cm² (without control discharge)
7 Gas Storage Pressure : 68 ± 5 kgf/cm²
8 Whether safety release provided : Yes. Safety device inbuilt in discharge valve
conforming to IS 5903
9 Whether handle provided : Yes
10 Chemical charge : Liquefied Co2 gas as per IS 15222
11 Pressure rating of Control Valve : As per IS 3224
12 Volume Expansion Space Provided : Yes
13 Material of Construction
a) Cylinder : Seamless Manganese Steel - as per IS7285
b) Control Valve : Brass as per IS 3224 Sq./ Wheel Grip type
c) Siphon Tube : Aluminium – as per IS 738
d) Discharge Horn : Polythene/ Fiber Glass (Non Electric Conductor)
e) Carrying Handle : M.S.
14 Dimensions
a) Max. dia of extinguisher : 139.0 ± 2 mm
b) Thickness of cylinder shell : 4.0 mm
c) Overall height of the
extinguisher (up to cylinder neck) : 585 ± 10 mm
d) Length of Hose : 1 Mtr
e) Bore of Hose : Not less than 10 mm
f) Filler Opening : 25.4 mm
15 Empty Weight : 11.2 kg. approx.
16 Weight of One Extinguisher (Filled) : 15.7 kg. approx.
17 List of Accessories Provided : Hose with Horn, Handle, Wall mounting Brackets
and Screws.
18 Necessity and condition of filling : As per IS 2190
19 Codes and Standards followed : IS 15683
20 Whether approved by BIS : Yes
21 Filling Ratio : Less than 0.667
22 Max. effective range when
Tested in still air : More than 2 Mtr. & 95% discharged.
23 Effective discharge time : 8 Seconds (Minimum)
24 Anti Corrosive Treatment : Phospheting & Powder coating inside & outside
25 Colour : Red as per Shade No. 536/538 of IS 5
26 Marking : ISI Marked
27 Approval : CCOE Nagpur & BIS Certificate
818 of 896
OWNER: GAIL (India) LIMITED
CONSULTANT: MECON LIMITED
PROJECT:
CONTRACTOR:
DOC. TITLE: TECHNICAL DATA SHEET OF FIRE EXTINGUISHERS
1 Name of Supplier :
2 Type of Extinguisher : Portable Low Pressure
3 Capacity - Portable : 9.0 Kg.
4 Fire Rating : 4A – 34B
0 0
5 Temp Range : -20 Cto +55 C
6 Test Pressure for Extinguisher body : 35 Bar
7 Brust Pressure for Extinguisher body: 55 Bar
8 Whether handle provided : Yes
9 Chemical charge : a) Potassium Bi Carbonate Base dry chemical powder
b) Dry Nitrogen Gas
10 Volume Expansion space provided : Yes
11 Safety pin provided : Yes
12 Material of Construction
a) Cylinder Body : M.S. Sheet –IS 513 Grade D 1.5mm Thick
b) Neck Ring : M.S. Seamless-IS 1239 Part 1/IS 2062
b) Discharge Valve body : Brass Forge to Gr. FLB of IS 6912
c) Siphon Tube : PVC / Aluminium
c) Discharge Hose : PVC Braided Hose
d) Discharge Nozzle : Plastic
12 Dimensions
a) Max. dia of extinguisher : 175 ± 10 mm
b) Overall height of the extinguisher : 530± 25 mm
c) Length of Hose (approx) : 655 ± 25 mm
d) Bore of Hose : Not less than 10 mm
e) Dia of Nozzle : 4mm
13 Pressure Gauge : 0 to 28 Kg Rating
14 Empty weight : 4.2 Kg. approx..
15 Weight of One Extinguisher (Filled) : 13.2 Kg. approx.
16 First Charge of Chemical supplied : Yes
17 List of Accessories Provided : Wall mounting Brackets and Screws.
18 Necessity and condition of filling : As per IS 2190
19 Codes and Standards followed : IS 15683
20 Whether approved by BIS : Yes
21 Max. Effective range when tested
in still air : More than 6 mtrs.
22 Minimum period for which throw as
Jet will be maintained : 8 Seconds & 90% Discharge
23 Colour : Fire Red as per Shade No. 536/538 of IS 5
24 Marking : All fire extinguishers will be marked as per Cl. No. 10.2 of
IS 15683
25 Approval : BIS Certificate
819 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
APPENDIX-IV
820 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
5.39 Fire Water Pumps Electric Driven & Diesel Driven Nos. A N/A B
5.40 Rim Seal Protection for Oil Storage Tank Nos. B N/A B
A - Stage-wise Inspection + Final Inspection + Document Review as per approved MTC / QAP
B - Final Inspection + Document Review as per approved MTC / QAP
C - Document Review as per approved MTC / QAP
821 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
APPENDIX - V
THIRD PARTY INSPECTION AGENCY
Contractor shall appoint anyone of the following TPIA for inspection purpose, wherever
required as per tender document. Contractor has to propose minimum 4 nos. of below listed
agencies to be approved by GAIL / MECON:
Apart from inspection by TPIA, inspection may also be performed by MECON / GAIL’s
personnel.
822 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
APPENDIX - VI
APPENDIX - VII
823 of 896
FIRE PROTECTION SYSTEM
FOR
MECON LIMITED
GAIL ( INDIA) Ltd. SRIKAKULAM - ANGUL PIPELINE PROJECT ( PART-B)
DRAWINGS
824 of 896
825 of 896
826 of 896
827 of 896
828 of 896
829 of 896
830 of 896
831 of 896
832 of 896
Annexure-X
to
Particular Job Specification
(PIPELINE INFORMATION MANAGEMENT
SYSTEM)
833 of 896
PARTICULAR JOB SPECIFICATION (PJS)
PIPELINE INFORMATION MANAGEMENT SYSTEM (PIMS)
834 of 896
CONTENTS
1.0 INTRODUCTION
6.0 PRIORITIES
835 of 896
1.0 INTRODUCTION
1.1 GAIL (India) Limited, a public sector under Petroleum ministry, intends to develop Natural
Gas Transmission & Distribution Networks for Srikakulam (Andhra Pradesh) to Angul
(Odisha) Natural Gas Pipeline Project and its Spurlines in the state of Odisha and Andhra
Pradesh for industrial consumers as well as City Gas Distribution System (CGD).
M/s GAIL (INDIA) LIMITED has awarded MECON LIMITED, the project management
consultancy services of laying 24”/18”NB x 423 Kms (approx) Mainline (Part-A) from Angul
to Srikakulam along with its 18”/12”NB x 300 Kms (approx) Spurlines (Pat-B) for
transportation and distribution of Natural Gas in the state of Odisha & Andhra Pradesh.
1.2 Present tender envisages laying of 18”/12” NB x 322 Km (approx.) spurline . Pipeline will
originate from IP Station-04 ( Srikakulam – Angul Pipeline –Part A at Ch. 341.0 Km) cum
Dispatch Terminal at Ch. 0.00 Km to Receiving Terminal at Utkal Alumina at Ch.190.8 Km
and 12’’ NB dia x 68.3 Km ( approx.) & 62.97 Km ( approx.) Consumer connectivity
pipeline will originate from SV-06S & SV-07S Cum Dispatch Terminal to consumers
Vedanta and Nalco respectively
The schematic of the pipeline network is enclosed as drawing no.
MEC/23V9/05/28/M/000/0022, Rev-0
1.3 This document covers details of work tendered, scope of work, scope of supply and other
requirements pertaining to pipeline and associated facilities. All works and clauses of this
document shall be applicable to all sections unless specifically mentioned otherwise.
Work tendered as a part of this Bid document consists of supply of materials as required,
installation, testing, pre-commissioning of pipeline, preservation, drying and commissioning.
The work includes installation of pipeline and related piping works at despatch terminal,
receiving terminal and all associated mechanical, civil, architectural, structural, cathodic
protection, electrical, instrumentation, corrosion monitoring ,PIMS ,telecom and fire fighting
works at Stations along the route etc.
836 of 896
2.1.1 The brief scope of work for Part- B, broadly consist of Laying, Testing and
Commissioning of 18”NB x 48 Kms (approx) and 12”NB x 274 Kms (approx) pipeline in the
state of Odisha & Andhra Pradesh including all associated works for transportation of
Natural Gas (dry)/ R-LNG.
The said work has been divided into following Four (04) sections as given below:
837 of 896
works for Dispatch station at
SV-07S
Contractor shall be required to deploy separate teams and hardware for each part.
The work includes providing solution and services for implementation of web based and GIS based
Pipeline information management system for pipeline projects of CLIENT including setting up of office
in each part and support offices at Delhi/ NCR along with all requisite equipment/ tools/ consumables,
trained manpower, GIS survey/ mapping, transferring/ conversion of data collected from owner for
pre-construction, construction and post construction activities, as-built drawings of stations and
mainline integration of different activities/ functions in electronic form including training of applications
to owner’s personnel, handing over software/ solution Application developed with requisite license
and use for owner personnel’s complete in all respect as per scope of work/ SCC and as per direction
of Engineer-in-charge.
The scope of work also includes supply of GPS instruments and computer hardware with complete
accessories and peripherals for PIMS application display as per tender including training to owner’s
personnel and final hand over to owner’s personnel.
The Web & GIS based pipeline information management system shall be capable of archiving various
data related to pre-construction, supply, inspection, delivery, construction, hydro testing,
commissioning, as-built drawing for mainline & stations, RoU related data, material management data
in electronic format which can be used in future for the development of maintenance and operation
modules and to respond emergency situation during operation and maintenance.
2.2 Contractor shall deploy separate teams with all equipment/ hardware/ software for each part. Work on
all the parts shall proceed simultaneously. There may be separate laying contractors for each pipeline
as well as their terminals. Though MECON/ CLIENT shall endeavor to facilitate PIMS contractor to
get all the documents from the concerned parties. However it shall be the sole responsibility of PIMS
contractor to obtain all the documents from the concerned parties. The PIMS contractor has to
interact/ liaison with the laying contractors of pipeline, terminals as well as CLIENT & MECON to get
the documents. The complete scope of work tendered has been divided into parts / sections as given
elsewhere in the tender:
2.3 Owner intends to have a Web based and Licensed Arc GIS based management system which can
archive various data related to pre-construction, supply, inspection, delivery, construction, hydro-
testing, and commissioning, as built drawings for mainline and stations in electronic format which can
be used in future for the development of maintenance and operation modules and to respond
emergency situations during operation and maintenance stage.
2.4 The detailed route survey for the pipeline project has already been completed. The scope of
work shall cover development of GIS based management system for above surveyed pipeline
route. The contractor shall carry out development and customization of GIS based
management system for planning, execution, operation and maintenance controls, on a specified
format using standard and approved quality control parameters.
2.5 The scope of work consists of the requirements mentioned in t h i s document, enclosed standard
specifications, Schedule of Rates and as mentioned elsewhere.
838 of 896
2.6 The design of the software & data formats will be done in consultation CLIENT/ MECON at
Delhi office during the process of supply of software. Data input by successful bidder will start only
after finalization of software design & data formats. The Complete package along with data &
Licenses will be handed over to CLIENT after Integration of data into the system.
2.7 Successful bidder will hand over all data to CLI EN T af ter integrating and giving an undertaking
about authenticity of data certifying that all logged in data are as per requirement of the
tender and are 100% true.
2.8 Owner has the right to crosscheck the authenticity of data being uploaded in PIMS & also
check the integration & final presentation of the composite data to his satisfaction, as and when
desired.
2.9 The development of GIS based management system shall be customized to suit owner’s
requirement on technical, organizational, training, operational, information management system
area and integration with existing/proposed organizational systems for planning, control and
information management, using suitable software.
2.10 Carryout interpretation and integration of all physical features. Symbolization/ legend structure,
layering, edge matching, topological integrity, database linking, incorporation of processing
techniques for attribute allocation etc.
2.11 The PIMS agency shall provide the details of the required hardware & software specifications
including but not limited to server, storage, backup infrastructure, licenses, required bandwidth,
monitor, scanner, printer and any other hardware etc. as required for storing the centralized data for
effective functioning of the software application at owner’s place at Noida/ Delhi. Above information
shall be provided keeping in view future scalability of users, data etc. for a minimum of next 5 years.
2.12 PIMS application shall support virtualization platform (Vmware, Hyper V, Citrix etc.)
2.13 Bidder shall provide dedicated application support team, certified database administrator(DBA) during
project implementation, warranty and support phase for any application related issues/ changes,
configurations, database level troubleshoot and day-to-day operation like online data backup/
restoration, Database changes, database migration, database monitoring etc.
2.14 Role base access for the application and database shall be configured to avoid unauthorized access
and which can be used for monitoring and analysis of logs.
2.15 PIMS application shall have multi browser support (ex. Internet Explorer, Google Chrome, Mozilla
Firefox, Opera etc.). PIMS application shall be compatible with SAP system of CLIENT and it shall be
able to integrate with SAP at a later date, if required.
2.16 Application shall support online as well as offline data entry. Wherever connectivity is available user
can enter the data by logging in to the system. In case there is no connectivity, user must be able to
enter data in offline mode and upload the same in the application at later stage when connectivity is
available.
2.17 The Successful bidder should have proper auditable PIMS & IT security system in place. The bidder
shall also provide PIMS system with appropriate IT security in order to protect it against data breach/
pilferage of data through hacking, etc.
839 of 896
3.0 SCOPE OF WORK
The Contractor's Scope of Work for the PIMS shall consist of, but not limited to providing services for
implementation of Web & GIS based Pipeline Information Management System (PIMS). All such
works that are not indicated here below but are otherwise required to complete the work in all
respects shall also form part of Contractor's Scope of Work.
The scope indicated below shall be read in conjunction with Schedule of Rates as applicable,
drawings, standards, specifications and other documents forming part of the Contract document.
All works listed below shall be applicable for all Parts / Sections for Laying of Pipeline and their
associated stations / terminals, unless specifically mentioned otherwise.
The detailed scope of work pertaining to Web & GIS based PIMS shall be in general but not limited to
the following:
3.1 Overview
This document provides the minimum requirement for providing services for implementation of
Web & GIS based Pipeline Information Management System (PIMS).
PIMS is a latest state of art system for electronic documentation and retrieval of Projects as built
information. PIMS provides user-friendly and easy navigation web-based interface for quick
retrieval of pipeline information at anytime from anywhere. This system shall include near real time
uploading of progress and executed data of pipeline & associated works for construction and
material supply.
PIMS solution shall be designed to satisfy the needs across different stages of project life cycle:
• Project Planning
840 of 896
Scope of Services shall also include developing the customized system, deploying required
resources (personnel and machines) at execution site to directly capture & upload executed
progress data from associated execution Contractor(s) and finally handover of complete system
to CLIENT for further use in project during operation and maintenance phase.
Company : CLIENT
PMC : MECON
Contractor : Party appointed for providing services as detailed in the tender.
PIMS : Pipeline Information Management System
GIS : Geographic Information System
AFC : Approved for Construction
MT : Material Tracking
AGIs : Above Ground Installations
DPR : Daily Progress Report
AUT : Automatic Ultrasonic Testing
MUT : Manual Ultrasonic Testing
SV : Sectionalizing Valve
ITP : Inspection Test Plan
MPR : Material Progress Report
LR/ GR : Lorry Receipt / Goods Receipt
NDT : Non Destructive Tests
QC : Quality Control
3.3.1 The solution shall be a Web based system, which is accessible over the Internet to authorized users.
The solution will enable access from geographically distant locations simultaneously.
3.3.2 Online generation of Pipe book at an end of day basis. The pipebook generated by the system will be
hyperlinked to all the daily inspection reports / certificates and will provide snapshot view linking daily
inspection reports like stringing report, welding report, bending report, AUT and MUT reports along
with welder procedure specification,
3.3.3 Real time progress tracking of the construction in the form of web based, user defined progress
reports in the following formats:
• Tabular reports
• Graphical reports
• Cumulative reports (to report day wise progress of each activity)
• Query based information retrieval
3.3.4 Web based reporting module to generate various reports for e.g.;
841 of 896
• Welder's performance report
• Welding progress report giving a snapshot view of total number of welds, kind of weld, tie ins and
open ends in graphical format, on user defined chainage.
3.3.5 Hyperlinked documentation- All the above-mentioned reports will be hyperlinked to the respective
daily inspection reports.
3.3.6 Field data shall be collected and uploaded on PIMS database server at site on every evening by
PIMS contractor so as to generate DPR (Daily Progress Report) by next day 11 AM. Further, days
complete data to be uploaded on PIMS database server at site by next day.
3.3.7 Plot plan of all AGIs like SV/ Intermediate pigging/ terminal stations to be layered on GIS data with
different equipments and facilities on the plot hyperlinked to provide complete traceability and
hyperlinked / integrated to material tracking.
3.3.9 Geographic Information System (GIS) to be used to view Construction progress data, pipe book data,
materials data, alignments sheets (AFC and as-built) data, and all related / hyperlinked certificates/
reports on GIS layer.
3.3.11 The software should be based on Pipeline Open Data Standards (PODS) for future seamless
connectivity to any software like PAMS, IMS, SCADA, Primavera etc.
All activities as per approved ITP are required to be tracked and monitored through PIMS and their
related evidence documents to be uploaded and hyperlinked suitably. Following are major activities to
be covered as minimum:
842 of 896
All activities as per approved ITP are required to be tracked and monitored through PIMS and their
related evidence documents to be uploaded and hyperlinked suitably for following, as minimum
number of free issue / bought out materials :
Owner’s bought out materials for Pipeline Project by their respective vendors as well as bought out by
Laying Contractors shall be monitored in MT system by taking inputs from MPR (Material Progress
Report) issued time to time by respective vendors/ contractors.
The information touch points of MT will be defined from ITPs and range from Manufacturing location
(vendor/ subcontractors/ subcontractors), Land/ Sea dispatch/ receiving points and finally the project
site till the final installation and acceptance.
• Route survey, clearing and grading (all daily progress and inspection reports relating to
the same) & updating the cadastral survey data in GIS.
• Trenching, stringing and bending
• Welding
i. Welding procedures
ii. Welder qualification reports
iii. Daily progress reports
iv. All tests and inspection reports related to welding
843 of 896
• Damaged pipe detail
• Cut pipe detail
• Joint coating
• OFC related test reports
• Padding inspection
• Lowering reports
• Tie-in
i. Welding procedures
ii. Welder qualification reports
iii. Daily progress reports
iv. All tests and inspection reports related to welding
Terminal layouts to be layered over Pipeline GIS system and different blocks/
areas in terminal shall be suitably linked to provide status on following:
844 of 896
• Power Source, SCADA & APPS, Telecom & PCP Works
• Equipment Foundations work progress and related equipments status
hyperlinked to MT.
• Equipment installation, erection related test reports.
• Terminal material's traceability reports.
3.4.4 The software shall be capable to recall all the reports from various work packages and provide all
statistics to the COMPANY which includes:
• Project S-Curve
• Progress
• Material Availability
• Resources Availability
• HSE Reports
• Quality data
• Equipment status (MCEDS reports etc.)
• ROU Availability
• Compensation payment to landowners/ farmers
PIMS application shall include modules for documenting documents related to engineering, material
procurement, construction, Land Management etc.
845 of 896
Land Management Module:
This module shall capture the RoU as well as permanent land acquisition plot details of pipeline route. It shall
cover other important details e.g. details of geography, demography, statutory and administrative boundaries
of entire pipeline route. The application shall include land acquisition data for pipeline construction, survey
data, crossing data including permissions, details of plot purchased/ leased for stations and anode beds. The
module should have the following minimum details:
• ROU Details
The land owner details including permanent and alternative address. Mutation details, land usage details
of the property owner including the crop details. The information on the compensation paid to the owner.
- Notification history.
-Crop Details
-Payment details.
-Alignment sheets, TP/IP’s, Bench Marks/ GPS control points
-Population Density Index
-Alignment sheet
-ROU corridor details
-Crossing Details
-Land details for setting up of SV stations, dispatch, receiving and intermediate pigging stations.
-Environmental Sensitive Locations
-Emergency Details
-Administrative Boundaries
-MOEF clearance and TOR details
-EIA data
• Cadastral Maps
Cadastral maps of the route showing revenue data such as khasra no., etc.
• Permissions
Permissions, clearance and restoration acceptance from applicable statutory authorities such as forest
department, railways, Irrigation, PWD, etc.
It comprises of day wise construction progress including planning, quality and inspection reports activity
details of which are as follows:
846 of 896
• Weld visual
• Random QC test result.
• Weld repair details and results there of Subject to availability of radiography films in a digitized/
scanned soft copy.
- Joint coating
- Concrete Weight Coating
- OFC related test reports
Terminal layouts to be layered over Pipeline GIS system and different blocks/areas in terminal shall be
suitably linked to provide status on following.
- Site Survey & Grading
- Civil works (Foundation, Columns, and Slabs etc.)
- Mechanical works (Fabrication, fit-up, welding etc.)
- Station piping and related test and inspection reports
- Furnishing works (doors, flooring, ceiling, furniture, painting etc).
847 of 896
- Electrical (Power supply systems)
- Instrumentation (Control System setup and erection related test reports).
- Equipment Foundations work progress and related equipment status
- Equipment installation, erection related test reports.
- Terminal material’s traceability reports.
Project Certification System shall be a front end application & should be able to store track and report on the
Completion of a facility, system or sub- system. The purpose of the system shall be to assist in the
management of System Handover for Mechanical Completion, Pre-Commissioning and Commissioning. It
shall enable progressive verification of physical installation work according to the design and specifications of
equipment and systems, providing data traceability against relevant drawings ensuring compliance with
performance standards, specifications, codes and regulations.
In addition, the system shall provide a collaborative real-time environment for fast and reliable tracking,
monitoring and reporting on consolidated Punch list data stage completion.
The certificates and commissioning procedures to ensure project requirements are met for smooth transition
process and turn-over of pre-defined systems and Equipment, stage completion certificates and
Commissioning procedures to ensure project requirements are met for smooth transition process and turn-
over of predefined systems and Equipment.
The system shall be able to generate the completion certificate online through web interface which can be
used by Owner.
This module is dedicated for tracking of procurement and supply of all materials for the project. It shall include
various stages from procurement order, manufacturing, coating- painting, testing, inspection, dispatch and
storage at site of all items used in the project as per OWNER’s approved ITP. Major focus of this module shall
be to access delivery progress of all critical items such as line pipes, valves, etc. including its consumption
and stock availability at store yards. This tracking shall have sequential hyper-linking for upload of documents
by vendors and contractors. The material tracking system shall manage the material status from PO release
to item used. Each material shall be listed with a unique item Code. Planning and scheduling shall be as per
the Quantity required, scheduled PO release, scheduled Delivery date range. The system shall also have a
PO tracking system along with vendor management. Quantity receipt consolidation should be supported by
approved documentation like material receipts and Inspection reports. Appropriate material test certificates
are also uploaded along each delivery.
Recommended Features:
848 of 896
• Tender
• Purchase Order
• Reorder alert report
• Manufacturing status
• Delivery due date list
• Quantity delivered v/s ordered
• Reconciliation statement
All activities as per approved ITP are required to be tracked and monitored through PIMS and their related
evidence documents to be uploaded and hyperlinked suitably.
Relative evidence documents for all items to be uploaded and hyperlinked suitably for following, as minimum
number of materials;
849 of 896
Materials for above packages and items procured by respective vendors and materials procured by
Contractors shall be monitored by taking inputs data from MPR (Material Progress Report) of respective
vendors/ Contractors.
eDMS Module:
This eDMS Module refers database for all discipline wise project data of each package for pre-construction,
construction, post- construction related activities and any other required information but not limited to, as
following:
• Letter of authorization
• Tender document
• Design basis
• Pipe information (Manufacturing history, inspection documents, test certificates of pipes/ plates).
• Pipe reconciliation statement
• Material acceptance (Joint coating material manufacturers test certificates).
• Manufacturers test certificates and site qualification test reports like filler material, electrode etc.
• Procedure reports.
• Approved procedures, job procedures, welding procedures specification and qualification
• Scanning and digitization of gazette notifications
• Design Calculations/ Analysis
• Route maps
• Alignment sheets
• Detailed AFC drawings (road, railway, minor water crossings, major water crossings, etc.)
• Plot plan
• General Arrangement Drawings (GAD)
• Isometric drawings of installations
• Special Installations e.g. hot taps etc.
• Hydro testing and pre-commissioning documents/ data including water filling, pressurization and
hydro test reports, dewatering inspection reports, magnetic cleaning reports, EGP reports drying
inspection reports, inertisation, preservation inspection/commissioning reports.
• HAZOP report
• Emergency Response Plan
• QAP
• As-built drawings and documents
• Vendor / Contractor bills / invoice along with payment history.
Engineering and document and drawing approval status is tracked using this module.
a) PIMS configures the Document/ Drawing list from the Document control log & Material Control Log.
- Document/Drawing Code
- Category
- Sub Category
- Document Name
- Proposed date of Creation
- Estimated date range of Internal Document Control.
- Date range for Submitting to Client for comments
- Date range for incorporating comments
- Date range for Issuing for approval
- Date of Approval (AFC).
850 of 896
b) When a document/drawing is approved, it is scanned and attached.
c) Exhaustive search and summary reports are generated.
d) The document/drawing is uploaded as soon as its status is “approved”.
The eDMS module is searchable using metadata like category, sub category, type of document, vendor,
material, remarks and document number, etc.
All the data related to pre-commissioning and commissioning shall be captured on PIMS. Data
related to PESO/ OISD/ Internal audits shall also be recorded.
Contractor to develop pre-commissioning and commissioning module to control and monitor the pre-
commissioning and commissioning activities through approved pre-commissioning and
commissioning procedures.
Monitoring data capture and then its uploading on PIMS shall be the responsibility of contractor &
PMC. All monitoring data shall be collected on daily basis from respective vendors/ contractors.
Interface document for this shall be prepared and agreed with Contractor after award of PIMS work.
It is responsibility of contractor to ensure complete backup, safety and confidentially of the data. After
commissioning of Project, PIMS contractor shall handover the complete information management
system database with all licensed software (for lifetime) to Company. Handover shall consist of
installation and running of PIMS on Company’s serve to the satisfaction of the Company.
Company shall supply all inputs like construction / supply drawings, documents, data, etc. required
for implementation of Web & GIS based Pipeline Information Management System to the Contractor
at an appropriate time during the execution stage as free issue items on refundable basis.
i. The Contractor shall be responsible for taking over of the material and subsequent handling
during performance of actual work at site & safe keeping of the inputs drawings, documents,
data, etc.
ii. The Contractor shall inspect all COMPANY supplied free issue items at the time of taking
over from the COMPANY and defects noticed, if any, shall be brought to the notice of
COMPANY / COMPANY representative and jointly recorded. Once the item has been taken
over by the Contractor, all the responsibility for safe keeping of the items shall rest with the
851 of 896
Contractor.
iii. Every month the Contractor shall submit to the COMPANY an account for the item issued to
the Contractor in the Performa prescribed by Engineer-in-Charge.
iv. On completion of the works Contractor shall submit “Item Appropriation Statement” for all
items supplied by the COMPANY as free issue items.
The procurement and supply, in sequence and at appropriate time and place, including inspection
and expediting, of all Items and consumables required for completion of the WORK as defined in this
BID document except the Items specifically listed under para 4.1 above as COMPANY free issue
Item, shall be entirely the CONTRACTOR's responsibility and the item rates quoted for the execution
of the WORK shall be inclusive of supply of all these Items. All Items supplied by the CONTRACTOR
shall be strictly in accordance with the requirements of relevant COMPANY specifications enclosed
with the Contract document. All equipment, machines, instruments, components etc. shall be new
and specifically purchased for this job from Company approved vendors, duly inspected by approved
third party inspection agency (Only manufacturer certificate may not be adequate).
4.3.1 All items / materials shall be preserved against deterioration due to poor or improper storage while
under the custody of the Contractor.
4.3.2 All items / materials shall be duly protected by the CONTRACTOR at his own cost.
4.3.3 Openings of equipment, machines, instruments, etc. shall be kept in covered condition to prevent
entry of foreign matter.
852 of 896
3 Co-ordinator 1 Mechanical/ Civil Back Office/
Engineer Camp
Bidders are advised to make site visits to familiarize themselves with all the salient features of site and
available infrastructure along the pipeline route / site. Contractor shall be deemed to have considered all
constraints and eventualities on account of site conditions along pipeline route while formulating his bid.
Contractor shall not be eligible for any compensation in terms of cost and/ or time, on account of site
conditions along pipeline route varying to any extent from whatever described in the Bid Package and the
drawings furnished along with the Package.
7.0 PRIORITIES
COMPANY may, at its sole option, assign priority of work to any part of the total pipeline or terminal
works. Contractor shall comply with such priority of execution without any time and cost implication to
the COMPANY.
In case of any dispute / conflict arises within Particular Job Specification (PJS) and their associated
documents (like Appendix & Annexures), the most stringent requirement will govern. However
engineer-in-charge’s discretion shall also govern on the above issues based on the applicability as
per site conditions.
853 of 896
APPENDIX–I TO PJS
854 of 896
1.0 INTRODUCTION
The Pipeline Information management system is a web based solution, designed to monitor the
construction progress on a real time basis. Data that is entered on daily basis is indexed and linked
with scanned documents that provide validated data. Reports are generated in a telescopic format
that helps to browse from the route map to details of each pipe laid. The solution is designed to
provide real time information about pipeline laying progress alongwith all associated works including
stations/ terminal works during following three stages, project planning, project execution/
construction, pre-commissioning & commissioning, operation and maintenance. Electronic
documentation, graphical reports, pipe book, joint history etc. are some of modules of PIMS.
This document would be the reference document for any details related to the project scope and
implementation procedure.
2.1 The bidder is required to make use of software solution to track construction progress of the project
on a real time basis updated daily. The progress needs to be displayed electronically on a web based
format. Proper secured access is to be provided to the consultant and client enabling review of
construction progress on a daily basis.
2.2 Along with the technical submission, the consultant/ client may call upon the bidder to demonstrate
the software proposed to be used.
2.3 All pipeline construction related documentation (QA/ QC reports, procedures, project planning
documents, test certificates, records of meetings, land records, photographs, inspection material
reports and audit compliance documentation) including the pipe book, weld book are required to be
handed over to the client in an electronic form in appropriate formats and system.
2.4 Apart from storing all paper documentation, the software should have requisite feature/ facility to
generate as-built alignment sheets from varying points of the pipeline ROW. It shall be the
contractor’s responsibility to collect GPS co-ordinates at each weld joint using hand-held portable GPS
co-ordinates.
855 of 896
2.5 The software should also have the feature/ facility that the daily progress can be shown (apart from
tabular reports) on a web, with progress of different activities, geo referenced to the surroundings
land base.
2.6 All NDT test reports are required to be handed over to the client in an electronic format, duly geo
referenced as part of the software archival features.
2.7 The proposed software solution should have search/ query features. The fields may be sorted/
searched by chainages, joint number, etc. It should also have the feature to print the query.
2.8 The software shall have the facility to auto-generate pipe book.
2.9 The software shall have the option of reconciliation of free issue materials, electronic documentation
and material management.
2.10 The contractor will impart training to the client, consultant and laying contractor on usage of the PIMS
solution and its application
2.11 All survey data, engineering documents, construction reports, ROU details, user manuals shall be
uploaded to respective modules (as applicable) of GIS Software developed by CLIENT.
2.12 The Contractor / PIMS service provider shall be solely responsible for arranging all resources, facilities
and logistic supports etc. required to complete the work under this contract. In broad, the contractor
shall be responsible for providing the following:
i) Establishment of offices with proper storage and security arrangement f o r all spreads at suitable
locations in the nearby area of owner’s camp office to carry out his activities in close coordination
and in an efficient manner.
ii) Deployment of requisite manpower for project implementation, providing all qualified
skilled/unskilled personnel to carry out the entire job and facilities required to complete the
job to the entire satisfaction of the owner in accordance with the requirements of the tender
document.
iii) Deployment of all requisite hardware (servers, computers, printers, scanners, UPS, etc.) loaded
with requisite software application to run MS-Office GIS model, other software and applications
required for the project implementation
iv) Insurance o f all his hardware/ software and other equipment a n d personnel deployed for the
execution of the above work.
v) All consumables for scanning, printing, storing, and creation of backup data
856 of 896
vii) Organizing the onsite team’s travel to site for GIS survey
viii) Boarding and lodging for all its personnel deployed for the execution of the above work
ix) Local transport / conveyance for commuting to onsite location from the place of boarding and
commuting on the ROW for the GIS survey
xiii) Right of access for audit of the quality and accuracy of work done.
xv) Arrangements should be made to ensure that all parties involved in the contract are aware of
their security responsibilities.
xvi) The integrity and confidentiality of the Owner’s information assets are to be maintained and
tested.
xvii) Adequate physical and logical controls should be used to restrict and limit the access to the
Owner’s business information to the authorized users.
xix) Owner should have the right to audit/ third party audit the information security management
system of contractor.
xx) Contractor shall be responsible for settling all compensation and disputes arising out of any
damages caused by him or his workmen during the execution of work. Contractor shall carry out all
work in strict compliance with applicable documents enclosed with the tender document and
as per the instructions of owner’s representative. The scope of work shall also include any
other item/work required to complete the work in all respects as per specifications, drawings and
instructions of owner’s representative whether specifically mentioned here in or not, but required
to fulfill the intended purpose of this tender document.
2.13 The software solution chosen by the contractor should have been used and tested on previous
pipeline projects.
857 of 896
3.1 Technical features
a) Security of data base and world class data recovery management
b) Simultaneous monitoring from different locations/ spreads by contractor, CLIENT / MECON.
c) Protection from virus attack and other malignant programs
d) Scale dependent feature drawings and application execution
e) Feature labeling including label collision mediation
f) Fully customizable template driven output
g) True type fonts
h) Map element automation (scale bar , reference map and legend)
i) Thematic mapping using logical or regular expression based classes
j) Support for popular scripting and development environments (PHP, Python, Perl, Ruby, Java and
C# etc.)
k) Cross Platform support
l) Compatible with Linux, Windows, Mac OS, Solaris etc.
m) Remote daily back-up using r-sync or equivalent technology
n) SSH encryption
o) On the fly compression
p) FTP access
q) No data transfer limit
r) Indexing and archive documents online in a searchable format
a) Material management from starting from order placement, manufacturing & inspection at vendor
works, receipt at site, issue to vendor, erection/ commissioning, reconciliation (including test
858 of 896
certificates, inspection certificates, goods receipt voucher (GRV), store issue voucher (SIV),
incoming material inspection report (IMIR), inspection release/ waiver certificate etc.)
b) Document control log
c) Material control log
d) S-Curve to assess the current project status w.r.t planned schedule for each activity as well as
overall (weighted based)
e) Velocity chart : work done for a particular activity in chainage vs week
f) Graphical progress: to give an overview of work done in each chainage
g) Reconciliation of each type of free issue material issued to the pipeline contractor (Refer
Annexure-8 for guidelines on reconciliation)
a) Dynamic generation of DPR with planned time line and asking rate.
b) Real time generation of pipe book with hyperlinked scanned ITR (Inspection test reports)
c) Tie in Chart with complete history (WPS no. , welder details, pipe details, NDT details etc.) of each
activity for each joint.
d) View/ export pipe book in real time, Daily DPR, Activity data sheets, Joint schematic, Station piping
etc.
e) Reports of minimum following activities shall be digitized for monitoring for real time progress
monitoring:
• Clearing & Grading
• Stringing
• Bending
• Trenching
• Welding
• Tie in Welding
• Welding Repair
• Non Destructive Testing – Radiography / AUT
• Non Destructive Testing – Ultrasonic Testing
• Non Destructive – Magnetic Particle testing
• Non Destructive- Liquid Penetration testing
• Joint coating
• Lowering
• Back Filling
• Restoration
• Hydro Testing
• TCP / PCP
• Crossings
HDD
Cased Crossing
Thrust Boring
Open Cut
• Concrete Coating
859 of 896
• Coating Repair
• Cathodic protection system reports
• Station piping fit-up
• Station piping welding
• Station piping NDT
• Station piping Painting
• Civil works (building, road, boundary wall etc.)
• Instrumentation works
• Electrical Works
• Fire-fighting works
• Structural works
• Corrosion Monitoring System Works
• Telecom works
• SCADA works
a) Query for exceptions like joint coating done but NDT not done, lowering done but joint coating
not done etc.
b) Welder performance report
c) Unqualified welder report
d) Duplicate pipe control
a) Exhaustive document/ drawing scanning & indexing with searchable metadata. All pre-
construction, construction, as built and hand over documents must have search/ query options.
There should also be provision to print the queried data.
a) Collection of revenue data such as village maps, Ownership records from concerned Revenue
Department/ client for acquired RoU
b) Scanning, geo-referencing and Digitization of the village map, and transferring the pipeline
alignment and RoU corridor.
c) Preparation of seamless cadastral map (RoU Land map) to the scale of 1:5,000 incorporating
survey number and ownership details with in the acquired RoU. The land details (ownership
details, compensation details etc.) shall also be presentable in graphical mode
d) Conversion of RoU land maps and digitized cadastral records to .shp file.
e) Conversion of already existing cadastral maps/ data to .shp files
f) Collection of available data from CLIENT (soft/ hard copy) pertaining to revenue map, ownership
details of RoU, compensation details etc. and digitizing the same for graphical representation of
data.
860 of 896
3.8 Graphical Representation of survey information
a) Land records
b) Crossing and utilities
c) Location of crossings, SV / IP
d) Photographs of crossings/ mainline activities
e) Crossing drawings
f) Representation of surroundings features
g) Structure and monuments in vicinity
h) Tracking work progress using color codes
i) Generation of web based PIMS alignment sheet using third party application integrated with Arc
GIS.
a) PIMS site engineers shall enter the data from their own camp offices located at site.
861 of 896
b) PIMS site engineer shall collect approved field inspection reports from contractor office daily
in the evening.
c) These reports shall then be entered in the PIMS (PIMS site engineer shall exercise due
diligence to the accuracy of the reports and discrepancy, if any, shall be reported directly to
MECON).
e) Quality Engineer at head office shall verify all reports/ document data by 11.00AM next day.
f) Current information. Next day plan, daily progress report, document status, documents,
procurement status for uploading (preferably in .xls format) shall be provided to PIMS
engineer on a daily basis.
g) Digital Photographs/ videos duly labeled (with chainage/ location) for crossings, stations,
special utilities/ surroundings etc. should be linked to pipe route schematic. These
photographs must be updated as and when progress is done.
h) Deviation reports for route changes, process changes, etc. along with their documents shall be
provided.
i) Comprehensive training shall be imparted by the PIMS Contractor to the Client’s personnel on
usage of PIMS software.
a) The following are the details, information, drawings and documents required for configuring the
PIMS. Only approved for construction information will be digitized.
b) Survey data is required for generating PIMS alignment sheet and route Corridor Manager. Corridor
is generated based on chainages. Survey data has to be digitized on PIMS approved format and
then imported in the solution. The survey data to be included is as follows :
862 of 896
vi. Soil stratification details
vii. Population Density (PDI)
viii. Cadastral records with survey numbers, village, taluka, district, state and maps, referenced
with chainage.
ix. Planned Pipe specifications
d) Project Schedule: Generating project schedule and Gant chart using PIMS tools.
e) Activity Settings: Configuring activity scope and weightages for S-curve generation.
f) Document & Material Control Log: For Indexing the engineering approval status.
A list of different type of defects (Weld Defects) will be configured as per CLIENT Quality records.
A list of different type of bends shall be provided, complete with details of relevant chainage.
863 of 896
5.6 Welder Details
a. Welder ID
b. Qualification Certificates.
c. For evaluating the welder performance, the NDT analysis should reflect or trace the weld
defect to a specific welder.
d. In weld repair, the defect welder should be mentioned.
It is advisable that PIMS imports the pipe-list provided in .xls format by the manufacturer. Apart from
the pipe number, the PIMS system must list the pipe specification, manufacturer, coating company,
dispatch date, manufacturer test certificate.
If any pipe 'X' has Pipe No = "2V07K30779" then no other pipe can have same. PIMS differentiates the
pipes not just by the pipe number, but also compares the heat number and coating number.
PIMS engineers should not enter the pipe number manually throughout the activity of digitization
process (Stringing, Bending, Welding, NDT, Joint Coating etc). They should only select the pipe number
from the drop down pipe list.
If pipe “2V07K30779” is cut into two pup pieces, then both the pieces shall be numbered by suffix. The
terminology will be as per CLIENT’s quality records.
The pipe list report should have a special reconciliation section where pup pipe list should be
elaborated along with their actual length. If a pup pipe's length is less than 2 meter (or as specified in
the specification for reconciliation of free issue material attached elsewhere in the tender), it will be
listed as scrap.
864 of 896
6.0 PIMS Modules
Modules followed for the project shall cover all the aspects of the tender. Indicative diagram / layout
has been shown below:
7.0 REPORTS
Following minimum reports can be uploaded for users to view and download. These are to be sorted
date wise.
865 of 896
f) 3 Months Look Ahead Schedule
g) 6 Weeks Look Ahead Schedule
a) Error Reports for all activities are generated online and will be sent to CLIENT.
b) PIMS generated exceptions for example;
Duplicate Pipe & Joints
Incorrect Pipe number in report
Unqualified welder report
All data entry is verified by PIMS QA Engineer.
c) Visual Inspection of ITR's at site by PIMS engineers for any legibility/ incorrect format / incomplete
entries / ambiguous data etc.
d) Exception reports are submitted to CLIENT along with the feedback form as below.
All pipeline construction activity reports are digitized, scanned and uploaded. The fields needed for
digitization may not be limited to the following;
a) ROW/ Clearing & Grading/Trenching/Stringing
b) Bending
Sl. No Date Chainage in Meters Pipe No. TP No. Bend angle Bend Type Remarks
c) Welding
SI.No. Date Joint Pipe No. WPS Welder Welder Electrode Remarks
No. Pipe no. (Left) (Root/ (Filler/ Batch no
(Right) No.
Hotpass) Capping)
866 of 896
d) Tie-In Welding
SI. No Date Joint No Pipe Pipe No. Cut Pipe WPS Welder Welder Electrode Remarks
no. Details No. (Root/ (Filler Batch no
(Left) (Right) Hotpass) Capping)
e) Welding Repair
Sl. No Date Joint No (R, R2, Segment WPS Welder No. Electrode Batch Remarks
Cut-out) No. No
h) Joint Coating
Sl. No Date Joint No Holiday Average Pipe Average Weld Surface Pre- Peel Remarks
Test Coating Thk Coating Preparatio Heat Test
(on body) Thk n Temp
(on seam)
i) Lowering
867 of 896
Date Joint Section Holiday Northing Easting
Sl. No Joint (From Pipe Cover
(To) Length Check (GPS) (GPS)
j) Back-filling
k) Restoration
l) Hydro-testing
Joint
SI. No Date Joint (To) Attach Documents Remarks
(From)
Hydrotest Plan, Safety Plan, Mechanical
Completion Certificate, Air Cleaning Report,
Brushing Report, Gauge Inspection Report, Water
Filling Report, Thermal Stabilization Report,
Pressurization -50%, 75%, 100% Air Volume
Calculation, Pressure hold 24 Hrs,
Hydrostatic Test Calculation, Hydrostatic Test
Evaluation, De-Pressurization
m) TCP/PCP
i) TLP Installation
Sl. No. Date Report No. Type of TLP Joint No. Chainage in Mtr. Remarks
868 of 896
iii) Anode Bed Installation
n) Concrete Coating
Sl. No. Date Report No. Chainage (from) Chainage (to) Remarks
o) Coating Repair
The weld map updating procedure in PIMS shall consist of digitization the following reports:
a) WPS numbers and respective details and document.
b) Welder numbers and respective WQT or welder card.
c) Welding field inspection reports.
d) NDT inspection reports.
e) Weld repair reports.
a) The welding joint nomenclature shall be as per approved weld joint numbering procedure is as
below:
b) Weld joints on the pipeline shall be numbered consecutively for each kilometer, starting at 0
Chainage.
c) Each Joint shall be Prefix'ed or Suffix'ed with the Letters in Capital as per the approved
methodology with EIC. The indicative description shall be as follows:
869 of 896
T Tie in 5 T 43
FT Final tie in Joints between free 9 FT 82
section ends
GT Golden Joint Golden Joint on hydro 15 GT 83
test section ends
TR Transition Welds Joints with different wall 12 TR 12
thickness
d) The weld number, e.g. 5 M 4L where 5 indicates the 6th kilometers (i.e. between KP 5 and KP
6) and 41 indicates weld number 41.
e) Tie-in welds shall be given the prefix "T" and use the same numbering as the mainline (as
above).
f) FT will indicate joints tied between two sections involving cutting of pipe and stress developed
during fitting of two ends.
h) TR will indicate weld joints performed between pipes with different thickness.
i) If a weld has been repaired it shall retain the original number but followed by the letter RI
(e.g. 5 M 41 RI). If it is repaired a second time the weld number shall be followed by "R2" (e.g.
5 M 41 R2).
j) If a weld has been cut out and replaced by a pup pipe, creating Iwo welds, then the original
weld will be posted in cut-out log having the original number followed by the letters "CO" (e.g.
5 H 4) CO). This joint will not be considered in the pipe book but will be shown in cutout joint
log: The new length of the pipe will be updates for reconciliation. Pipe numbers will be
suffixed with A, B, C and so on.
k) If a good or accepted weld has been cut out and replaced by a new weld, then that weld shall
retain the original number followed by the letter "RW" (e.g. 5 M 41RW).
l) Welds in valve stations shall be given the prefix "S", followed by the station number and then
the weld number (e.g. S 2-21).
870 of 896
8.2 Weld Schematic
The weld schematic is a graphical representation of the weld joints of each chainage. It graphically
represents the following;
a) Each pipe alongwith its number and heat number. Pipe color depicts its thickness. A mouse over
on the pipe displays its details.
b) Each block represents a joint. Its color coding indicates its status, whether welded, NDT done or
rejected, joint coating lowered, backfilled. The letter below each block indicate if the joint is a tie-
in (T), free tie in (FT), re-take (RT), re-weld (RW) etc.
c) Click on any joint displays its weld history with links to inspection reports.
A detailed weld report having all joints welded with their status, welder number, WPS, electrode
number etc. are displayed. A special query is generated for listing the cutout.
a) Error reports for all activities are generated online and will be sent to contractor as well as
MECON.
b) PIMS generated exceptions for example; Duplicate pipe & joints, incorrect pipe number in
report, unqualified welder report.
c) All data entry is verified by PIMS QA engineer.
d) Visual inspection of ITR’s at site by PIMS engineers for any legibility / incorrect format /
incomplete entries / ambiguous data etc.
e) Exception reports are submitted to the contractor alongwith the feedback form as below :
9.0 Crossings
PIMS software shall have details of crossing reports. The following information shall be configured as a
minimum:
871 of 896
a) Crossing No.
b) Crossing Drawing
c) Name of Crossing
d) Type of Crossing (HDD, Thrust Casing, Open Cut)
e) Chainage Point from-to
f) Crossing Width
g) Permission Authority
i) Authority Name
ii) Date of Permission
iii) Expiry of Permission
Generation of station piping DPR requires the following fields from the inspection report of each
terminal;
A joint tie-in chart report represents and gives detail of each joint from welding to backfilling. Tie-in
and free tie-in joints, repaired joints etc. are also represented with respective legend as shown in
below figure. Each joint will have UTM Coordinates.
11.3 S-Curve
Feature to query any left out activity for any joint within a range prior to lowering or hydro testing.
872 of 896
a) Pre-lowering compliance report generation.
b) Pre-hydro test compliance report generation.
Lowering compliance report gives the complete history of joints with the conformation that pre-
selected is ready to lower with the details of calculated section length to be lowered. It gives
exception of activities not performed or not reported.
The pipe tracking report shall have the following minimum fields:
Despatch Receipt Pipe Heat Length Dia Thk. Grade Type Coating Mfg. GRV SIV TC no. Left Right
Date Date No. No. Type Name no. no. Joint Joint
The despatch date shall have the inspection release note/ inspection waiver hyperlinked to it. Also
the GRV no. , SIV no. , TC no. shall have GRV, SIV and TC hyperlinked to them respectively.
Despatch Receipt Item Size Rating Material Mfg. GRV SIV TC no. IRN Remarks
Date Date Description Name no. no. no.
c) Reconciliation Report
The free issue material needs to be reconciled. The reconciliation shall be done as per the
specification for reconciliation of free issue material attached elsewhere in the bid document. The
software solution must have the ability to reconcile all the free issue materials.
The proposed software shall have the capability to auto-generate pipe book from digitized inspection
reports. It should have provision to query fields, chainages and joint number range.
GIS vector / raster images and maps with links of all TP’s having layered details chainage progress till
date, digital pictures / documents / material list of special sections. Links should get dynamically
873 of 896
generated as and when data entry is done. Shape files containing the GIS system shall be handed over
to the client for their reference.
a) Survey Information
i) Land Records
ii) Soil Corrosion Records
iii) Geo References
i) Location of Crossings, SV
ii) Photographs of Crossings
iii) Crossing Drawings
iv) NOC’s Related Documents
d) Pipeline Route
This graphical representation of the route has nodal points referenced against chainages for the
following; SV/ IP station, turning points, crossings, KM posts, warning signs, city / town crossings and
certain important landmarks. These points are hyperlinked to provide more details. Further click on a
point gives descriptions like as date progress, digital video of special sections, IP stations, view related
pipe book page, etc.
The proposed PIMS software solution shall have the ability to generate as-built alignment sheets. The
survey data shall be digitized to generate the alignments sheets. During construction process, the
contractor shall record GPS co-ordinates at each weld joint and based on them generate as-built
alignment sheets. The levels/ cover at each joint should be collected from the laying contractor and
874 of 896
incorporated in the as-built alignment sheet. The mouse tip should display the UTM coordinate of a
particular joint.
The web based, auto generated PIMS alignment sheet shall have all the features of the standard
alignment sheet provided by the survey agency. The data used for generation should also be
tabulated. The information to be shown in the alignment sheet layers is as follows:
a) Planimetry
TP / IP Details
Weld Coordinates, weld chainage
c) Profile
Ground level, pipe cover
e) PDI / Class
f) Pipe Types
g) Soil Resistvity
h) Soil Stratification
All construction reports, progress reports, test reports, specification and procedures etc. should be
linked to the relevant data reports. Each document should be accompanied with unique meta-tags
that can make a specific search easier later. The following aspects should be covered under this
section;
a) Pipe information (Manufacturing history, inspection documents, raw material test certificates,
test certificates of pipes and plates, inspection release note)
b) Other free issue material (valves, IJ, flow tee etc.) information (Manufacturing history,
inspection documents, raw material test certificates, test certificates, inspection release note)
c) Pipe reconciliation statements
d) Material acceptance (Joint coating material manufacturers test certificates).
e) Manufacturers test certificates and site qualification test reports like filler material, electrode,
epoxy etc.
f) Equipment data sheets and test certificates.
875 of 896
g) Procedure reports, Approved procedures, job procedures, welding procedures specification
and qualification, QAP's and ITP's for all pipeline activities including terminals, SV stations, IP
stations etc. Scanning and digitization of gazette notifications from owner. All construction
activity reports including crossings.
h) Cadastral survey documents- Survey numbers, ownership area of affected of survey no. in
ROU. Permanent feature along center of pipeline. Village maps, talukas, districts etc. Nearest
police station with details, hospital, fire station, village panchayat, district authority details.
14.1 Material tracking and ordering reports are generated for both Free Issue Materials for long lead items
and also for procurement related items.
ROU tracking report helps in tracking the ROU / Permission documents, compensation details would
be linked.
a) Mode of Delivery
Data will be submitted in installable CD’s. A platform independent solution, that can be installed on
desktops, servers and accessible through the network will be configured.
b) User Access
Apart from the delivered CD's, as built data can be provided in either of the following methods: a)
Present on Secure Web Space. b) The data with platform independent menu Interface will be installed
on a Server/PC. It can be accessed by users from a URL from other PC's within the network.
c) Interface:
All submitted data can be accessed using menu interface. All data is input from authenticated
Inspection Reports/ Documents. These documents are also linked along each entry. Data generated
using PIMS is exportable to MS Excel and may be used to Interpret with applications as desired by the
client.
a) Pipe-Book:
Complete pipe book with links to each inspection report and single click display of history of
joints.
876 of 896
b) Electronic Documentation:
Approved documents, drawings, test certificates etc. scanned, linked and indexed.
d) Material inventory:
Complete pipe tracking and reconciliation report with details.
17.12 GIS system should have loader module for Survey data to AutoCAD Map based alignment sheet.
17.13 The GIS based management system should be able to handle the following applications:
a) Spontaneous potential graphing
b) Pipeline profiling
c) Handle CAD files which show the piping layout and other plan of the facilities
d) Images and scanned documents
877 of 896
e) Creation of alignment sheet from survey data
g) Inspection and material data updating and listing through a form menu
i) Record update and maintenance
j) Emergency notification lists display
k) Map creation
I) Identification of the pipeline network facilities; tolerance setting for the same
m) Query by location, by attribute, by logical selection (all queries based on logical
selection parameters)
n) Report generation as per user needs
This specification covers the minimum requirements for implementation of GIS for surveyed
pipeline route. This specification deals with data acquisition, data recording, storage
handling, processing and development of GIS on a specified format using standard and
approved quality control parameters and its delivery to owner in a fully customized fashion.
The work shall include but not limited to the following:
18.1 Survey along the pipeline ROW to capture GPS co-ordinates of weld joints, various pipeline markers
(boundary pillars, kilometer post, direction marker, warning signs, etc.), despatch station(s), receiving
station(s), intermediate pigging stations, consumer terminals etc. for preparation of GIS map of ROW.
18.2 Preparation of seamless GIS for the entire pipeline route with video clipping of salient features such
as major crossings (Roads, Railway lines, Rivers, Nalas / Streams, Canals etc.) covering 5 Kms
stretch either side of centre line of surveyed pipeline route. Any drawing/ documents if
additionally required shall be the responsibility of the contractor. Generation of GIS module for
the surveyed pipeline route, shall be capable of featuring the attributes as given hereunder:
a) Retrieve pipeline information like Chainage, Depth of pipeline, Dia. of pipe, coating details, CP
details etc.
b) Route Map showing the alignment of the pipeline including crossings, TPs etc.
c) Major crossings such as National Highway, State Highway, Railways, Canals, Rivers, HDD etc.
878 of 896
d) Mainline Valve Locations, Despatch/ receiving stations
e) GPS coordinates of each weld joint during construction work to be taken immediately
after lowering but before backfilling along with progress of mainline construction.
f) Cadastral Survey information including details of
i) Survey Nos.
ii) Ownership area of affected Survey no. in ROU
iii) ROW Corridor
iv) Permanent feature along 30 m either side of centre line of pipeline
v) Village maps, Talukas, Districts etc.
vi) Present crop details
vii) Land & crop Compensation details
viii) Land use pattern along the route
18.3 Incorporation of all permanent features, such as roads, railway lines/stations, water bodies, fire
stations, important land marks etc. falling within the corridor width of 10 km on either side of
the pipeline centre line. The contractor shall arrange the satellite imageries, if required. Owner
may facilitate the contractor (if required) by issuing authorization letters. However, the satellite
imagery shall be procured by the contractor from authorized agency at his own expense.
18.4 Scanning and digitization of Gazette notifications available with the owner. Scanning &
digitization of EIA/ RA study reports, cadastral survey reports, soil resistivity reports, various
crossing permissions, as built drawings, equipments details etc. Provision shall be kept for
linking additional attributes as and when required in future pertaining to ROU related works.
18.5 The data so collected shall be re-verified to ensure correctness before their processing
for the development GIS map of pipeline ROW, showing pipeline alignment and profile.
18.6 Provision shall be kept for system integration to existing CLIENT’s SCADA network/ WAN.
18.7 All the data shall be uploaded to respective modules of GIS software developed by CLIENT.
18.8 Identification/ Generation of 3-D co-ordinates for turning points/ intermediate points along
surveyed pipeline route, with the help of DGPS.
18.9 Handheld GPS survey instruments with mapping facility, shall be utilized for locating the
intersection points/ turning points and other Geo-references, with its complete accessories of
renowned make, having 1 metre accuracy.
18.10 The contractor shall impart training for operation and maintenance of software developed for
Pipeline information system to two batches of CLIENT personnel, each batch consisting of up to 10
personnel.
18.11 The scope of work shall not be limited only to the work as described above. The contractor shall be
required to execute all works required for generation of GIS module for the surveyed pipeline
routes.
879 of 896
18.12 GIS Surveys
18.12.1 Contractor shall carryout development and customization of GIS for the surveys covered in the
present scope of work that includes:
This GIS is to be developed in such a fashion that there is a complete scope for horizontal and
vertical expansion for the system growth and Integration. Theme coverage/ layers for GIS shall
be as per requirement frozen by owner at the System Design and Customization Stage.
i) The entire system to be geo-referenced, i.e., from the point of dispatch to receipt station including
the facilities at each end as well as en-route, the major crossing, landmark etc. shall be as per
grid and projection system to be approved by the Owner. The GIS application should have pipe
book data, materials data, alignment sheets (AFC and As built) and all related certificates available
spatially on GIS layers in such a way that all the above details can be opened through the GIS
application directly . This shall also involve ( but not limited to) taking GPS coordinates of each
weld joint during construction work immediately after lowering but before backfilling along with
progress of mainline construction. The Pipeline construction activities such as ROW Clearing,
Grading etc should be available spatially as GIS layers so that all the above details can be opened
through the GIS application directly.
ii) The Contractor shall submit a Quality Assurance Plan (QAP) which shall cover details of each
activity, its scope, quality parameters, quality checks, inspection schedules, attributes for
input and output/ deliverables, test check procedures and its correlation with implementation
schedule. The QAP will be scrutinized, commented upon and approved by the Owner for
implementation.
iii) The Contractor shall deploy the best-suited methods, equipment, tools software, personnel, analyst
and surveyors to carry out the development and customization of GIS.
iv) The Contractor shall use the best and the approved quality material for preparation of maps,
reports, software, storage mediums etc. Base maps of all the districts (50 km on both sides of
ROW) are to be supplied & integrated in the system by the bidder & these maps should have
clearance from Ministry of Defence or Survey of India.
880 of 896
v) The Contractor shall confirm having in his possession the requisite tools equipment, know-how
and experience to carry out the development of GIS including facilities to handle, to process and
deliver output from the satellite imageries. In case the contractor decides to tie up with an
associate for this part of scope, the details of such sub-vendor/ associate shall be furnished along
with the offer.
vi) The development of GIS shall be thoroughly customized to suit owner’s requirement on technical,
organization, training, operational information management system areas and integration with
existing / proposed organizational systems for planning, control and information management.
Wherever owner is not in a position to clearly specify any individual attributes/ fields of information
at the execution stage, adequate provision for implementation at a later stage would be
created in the respective system for such cases.
vii) Contractor to comply with Open GIS Consortium (OGC) data standards or as approved by EIC.
viii) Development of GIS package shall be done using standard programming languages like visual basic,
visual C++, java, oracle etc,
ii) Collection of input data, topo sheets, and satellite imageries based surveys maps, reports and
store/handle for further processing with contractor's survey work.
iii) Propose projection parameters, special data parameters, g ri d system, geo-coding and geo-
referencing parameters, output/ deliverable parameters etc., for owner’s approval.
v) Carry out data validation of received input, carry out scanning of topo-sheets, and integrate
the recordings made by GPS/ DGPS and other survey instruments to complete/collate the
input data.
vi) Carry out image processing and generation of rectified image on approved system like
ERDAS IMAGINE or equivalent.
vii) Carry out interpretation and digitization of all physical features symbolization/ legend
structure, layering, edge matching, topographical integrity, mosaic king, database
linking, incorporation of ground truth details, incorporation of processing techniques for
attribute allocation etc. after passing through quality assurance stages as per approved
QAP.
viii) Generation of output maps in specified format and scale as per specification.
881 of 896
ix) In the cross-country zone all information as given in the technical specification shall be
provided. In the densely populated portions all information requirement as per
specification for detailed survey and cadastral survey shall be incorporated such as ward and
property boundaries (house numbers, classification as residential, commercial, government,
number of storeys etc.) roads, landmark features, locality names and connectivity with
proposed facilities, major commercial and industrial establishment being studied as
potential consumers etc.
The data to also include, nallahs, channels, drains, canals, existing electric and
telephone lines, bridges, land crossings, proposed expansion of roads, railways, other
facilities e.g.water supply, sewerage system, telecommunication networks etc.
x) To customize each layer and attribute for present available data and future database as
per requirement of the owner. To design system requirement for operation and
maintenance of GIS package.
xi) To deliver a draft GIS package to the owner along with a detailed demonstration
scrutiny, trial run and observations; load the trial packages on owner’s system and
configure for optimal use.
xii) To modify/ change and update GIS with respect to the finally approved survey reports and
mapping carried out under the overall scope of work. Observation and detailed
comments on submission by contractor at each stage of work, correction/
modifications and addition to route or methodology, etc shall be carried out by
contractor. To provide training to the owner’s engineers on development of GIS as per
approved schedule.
xiii) To deliver the owner the source c o d e of the application package with proper documentation.
xiv) To customize the GIS package as finished products and deliver to Company sets of O&M
manuals and package and provide post delivery support services (software updating
etc.) of operation and maintenance for a period of 3 years from the date of installation
of complete system. For GIS server application server and desktop editing software,
however, the successful bidder will provide one year software product warranty which
includes both software upgrade update and technical support and next two years of
technical support only on need basis (monthly at least) by authorized technical person of
OEM. Maintenance of package during the period shall be provided at no additional cost
to the Owner.
882 of 896
Pipeline Survey & Route mapping
18.13 GIS Management Solution: It should be able to archive the following measurements and details
related to mainline route/ profile/ drawing and pipe books:
a) Horizontal location of pipeline with regard to deviation and permanent grid pillars
b) Vertical level with regard to mean sea level of pipeline and grade
c) Location and type of bends, fittings etc. and grades, points of intersection
d) Changes of wall thickness and materials
e) Location and details of valves insulating joints fencing
f) Location and details of bored/ cased road, railway, water crossing, suspension bridges
g) Location and details of bored crossing pipes, vents
h) Location and type of coating
i) Location and type of weighting, anchoring
j) Location and type of markers
k) Location of further appurtenances (pig-signallers)
l) Location of ROU and end of pipeline with respect to ROU
m) Type of soil
n) Type of rock
o) Type of blasting and ripping
p) Padding
q) Type of road pavement
r) Details of bank protection, number of insulators, seals
883 of 896
18.14 Following layers (but not limited to- only indicative) are to be populated in the GIS solution. The
information contained is also indicated in the layers:
b) Cadastral layer
This layer group contains all map format files, images and tabular data Obtained from local
government or other external sources. All Cadastral Data, Landowner details and compensation to
the farmers shall be Included in this layer.
d) Crossings details
All information regarding pipeline crossings (all crossings like river, HDD, roads, canal, railway line,
foreign pipeline crossing, power transmission line etc.) are stored and presented in this layer group.
Location, type and width of crossing is stored in attribute table of crossing layers.
e) Pipeline Routes
Pipeline routes, IPs, KP markers, history of routes and reroute layers are all collected in this group
layer. TLP points, OFC points, valve location, coat & wrap details, pipe depth, CP details etc. will also
be marked in this layer.
f) Logistics
All approach roads map is scanned, geocoded and imported to GIS, then suitable access routes are
digitized on the map which illustrates an idea of accessibility of site from different access roads.
g) Satellite imageries
All satellite imageries are grouped in this layer group. Different visibility Scales are defined, so that
by zooming in & out suitable satellite imageries become visible.
h) Important details
Plans of detailed survey collected from alignment sheets are put together and presented as a stand-
alone layer which presents useful details of obstacles and features like Police station, post office,
fire brigade, delivery station, major road, minor road, railway pond, river, forest land, CRZ (Coastal
Regulation zone), restricted ROW, Common ROW, marshy areas, rocky areas, in the vicinity of the
884 of 896
pipeline based on detailed survey.
i) Geology
Geological maps, fault maps, hazard maps and other relevant maps from reference books and
journals are to be scanned and geo- referenced.
18.15 An indicative list of requirement from the GIS application is given below as minimum which
should be available in the system :
4. Map integration with pipeline Integration with pipeline digital mapping of the
digital mapping pipeline route corridor and ROW.
5. Integration with Google Viewing pipeline data on top of Google
Map/Earth map/Earth/ Bing Maps etc.
6. Map Overlays Facility to switch ON/OFF pipeline map Overlays
7. Search/Query Features Facility for Search/ Query on Pipeline data
through web interface
8. Scalability Scalable to incorporate new Pipeline Data (
whose data are provided in industry
standard map formats)
9. Modularity Facility to accommodate new
users/groups/pipelines as and when required
10. Flexibility to change CommunicationRequired
Service Provider
11. Facility for updating of data at Required
owner’s end
12. Browser Compatibility Compatible with Web Browser such as
Internet
18.16.1 The software system/package of data information management system shall be able to function
on a LAN/ WAN, restricted to 100 users, with provision of security.
885 of 896
a) Input data validation.
b) Control of internal processing
c) Output data validation
18.16.3 The system shall enable quick retrieval and printing of relevant pipeline data/ as built information
through a suitable application. It shall also be able to provide requisite information in following
formats.
a) Tabular reports
b) Graphical representations of data
c) Image (supporting document) retrieval
d) Geographical information system
e) Query based retrieval
18.16.4 The volume of documents/ information to be scanned and uploaded in the system shall be
decided based on the requirement and shall be finalized in consultation with the Engineer -in -
Charge.
18.16.5 The data captured from the scanned documents and alternate electronic data into the central
database through extensive manual data entry and electronic validations.
a) The GIS module of the application shall also function on a LAN with an Internet connection.
Contractor shall provide license access for this.
18.16.6 Generation of as built alignment sheets based on chainage shall be provided in the scale as
decided by the Engineer in Charge.
18.16.8 Contractor shall be responsible for following up with the owners representative for collection of
various QA/QC documents, daily inspection reports, equipments test certificates, as built drawings
etc. Contractor shall also be responsible for the manual data verification (reports are verified
for general errors like missing pipe number, missing heat number, repeated pipe number,
missing supervisor signatures etc) before making data entry and publication into the system.
18.16.9 Contractor shall provide access of published data to the authorized users of owner over secured
Internet/ WAN Network in the form of web-based reports.
886 of 896
18.16.10 The scanned reports shall be given identification code/ name using a formal coding / naming
convention as agreed upon between the owner and contractor. The reports shall be visually
checked to ensure presence of identified mandatory information.
18.16.11 The data shall be protected through appropriate security systems and access shall be controlled
using access control systems.
18.16.12 The Contractor shall submit along with offer the project organization detail, the plan for
execution of work, execution methodology, quality control plan and project monitoring &
control mechanism details for development of data management system.
18.16.13 The Contractor shall submit a weekly progress report of the work assigned to him for
monitoring the progress of the work
18.16.14 After acceptance of the system all software used in the data management system shall be
supplied in CD/ DVD media and shall be licensed to the owner with certification to this effect.
The owner shall be enabled to access all free downloads/ updates for the software provided as
per contract. The bidder shall ensure registration of the owner of such facility with the
respective software supplier and confirm. The license of the GIS server application server and
desktop editing software should be in the name of CLIENT. If any software media is
damaged / corrupted during the process of installation and commissioning, the contractor shall
ensures replacement of media at his own risk and cost.
19.1 Owner’s responsibility shall be limited to provide/ making available the drawings/ documents/
data required for providing services for implementation of Pipeline Information Management
System. All other resources, logistic support, facilities, etc required to complete the work under the
scope shall be arranged by the contractor himself without any cost to the owner.
The owner may also provide authorization letters, wherever required for collecting information/ data
from Owner/ Owner’s representative and other contractors/ vendors.
20.1 The persons employed by the Contractor / PIMS service provider shall be technically qualified and
trained in development of requisite software and operation of various computer applications. They
should al s o be acquainted with pipeline construction.
20.2 The contractor shall provide boarding & lodging arrangement for his personnel at all locations
during execution of work under the contract. The contractor shall also provide boarding, lodging
and transport arrangement for his personnel during visit to ROW for collection of data for GIS
mapping.
20.3 The contractor shall provide insurance coverage of a l l his personnel employed for implementation
of work under this contract.
887 of 896
21.0 DOCUMENT/ DATA SUBMISSION
21.1 Contents and presentation of GIS Module shall be reviewed/approved by owner in the initial stage
to be prepared by the Contractor. The Contractor shall incorporate all comments / suggestions
given by owner and prepare all documents accordingly.
21.2 Two sets of paper copy of GIS Module developed shall be submitted by the Contractor for
owner’s review in the form of draft report immediately upon start of work. The contractor shall
obtain approval of owner on draft report before final submission. Comments, if any, shall be
incorporated by the Contractor. Report can be demanded in parts and in different phases as per
discretion of the owner.
21.3 All drawings, report, formats etc. forming the part of submission to owner shall be prepared on
electronic media.
21.4 Final drawings/ data / documents after incorporation of comments by contractor shall be
submitted to owner in six sets paper copies and one copy on CD ROM/DVD.
22.0 SECURITY
The network used for data transfer should be secure:
22.1 Bidder should ensure that a clear description of the security attributes of all network services used
is provided.
22.2 The digital signatures and security tokens system should be under hardware warranty and
software support for three years from the date of installation of the complete system.
22.3 The web server should conform to the guidelines issued by “CERT-IN”
22.4 The successful bidder shall develop and install state-of-the-art security systems including all
types of modern protection security systems, like “SSL VPN to protect the software system and
all the data base and confidential information of the CLIENT which would be kept on line to
support the software system. The SSL VPN system should be under hardware warranty and
software support for two years from the date of installation of the complete system.
22.5 It is the responsibility of the successful bidder to ensure that there is no security backdoors and
loopholes existing in the solution that can be exploited. The Contractor shall wholly be responsible
for any breach in security as a result of insecure implementation or loopholes in the solution,
including the operating systems on which the systems are running.
22.6 There should be one time authentication. However, a guest user id may be there through which
any user can see the documents available for public notices.
888 of 896
22.7 Unauthorized user shall not be allowed to access to any of the Data.
22.8 The Contractor shall establish an access control matrix for the system.
22.9 The proposed system shall be equipped with security facilities to prevent data tampering,
data theft, sabotage and virus attack.
22.10 A parameterized, timeout and logout feature may be included for non-active sessions.
22.11 The proposed system shall be equipped with database security access control to ensure the
integrity of data during processing and updating of the database.
22.12 The Contractor shall propose Application level access control to control the user's access to the
application he/ she can access.
22.13 The system shall be capable of invalidating any user after a specific number of attempts to
gain access via invalid passwords.
22.14 There shall be mechanisms to verify the authenticity and the integrity of the network services
from un-trusted sources before the services are used.
22.15 The audit trail solution shall be able to detect attempts of unauthorized access, security
violations, logging staff's activities as well as any suspicious activity and alert the system owner
using appropriate channels such as audible alarm, pager, e-mail or other interactive technology
based on the criticality of the intrusion detected.
22.16 The proposed security implementation shall be easy to administer, verifiable and sustainable.
It shall be able to scale to cater for additional servers for future expansion programs.
22.17 Application Security Assessment (Source code review) of the complete customized application
should be done by CERT-IN empanelled organization (the organization should be in cert-in
panel since 2006) covering OWASP’s Ten Most Critical Web Application Security Vulnerabilities.
A confirmation certificate is to be provided by the auditing organization. The cost of hiring third
party is to be borne by successful bidder.
889 of 896
APPENDIX–II TO PJS
RESPONSIBILITY MATRIX
890 of 896
1.0 Project Responsibility Matrix
RESPONSIBILITY MATRIX
PIMS
Activity CLIENT/ MECON
Contractor
Deployment of manpower for scanning, cataloguing, data entry of all
reports along with GPS coordinates acquisition staff √
Deployment of hardware for the project implementation like desktops,
server and scanner √
Insurance of PIMS contractor’s equipment/ hardware
√
CD’s/DVDs and alternate consumables for backing up of data
√
Consumables for scanning √
Organizing the onsite team’s travel to site √
Application hosting for ensuring availability of information to external
√
users
Desktops for viewing web reports and GIS by the IOCL team
(Standard configuration PC’s with Windows operating systems,
Internet explorer and MS Office). GIS module: 2 machines, Web √
Reports as per owner requirement
891 of 896
RESPONSIBILITY MATRIX
PIMS
Activity CLIENT/ MECON
Contractor
Provision of Internet connection for communication, E- mail and
uploading and downloading of scanned documents √
2.0 Bidder to submit a responsibility matrix covering the complete project implementation and clearly
outlining the scope of work being covered by them.
3.0 Bidder shall procure the satellite imagery for implementation and shall facilitate and manage this activity
as per detailed specification.
892 of 896
APPENDIX–III TO PJS
PROJECT EXECUTION
ORGANOGRAM
893 of 896
PIPELINE INFORMATION MANAGEMENT SYSTEM FOR PIPELINE
PROJECTS
ORGANOGRAM FOR PIMS CONTRACTOR
Team Leader
Co-ordinator-1 no.
Co-ordinator
QA Engineer-1 no.
Surveyor-1 No.s
894 of 896
APPENDIX–IV TO PJS
PIPELINE SCHEMATIC
ROUTE DIAGRAM
895 of 896
SECTION – VII
SCHEDULE OF RATES
Attached Separately
896 of 896