Equipment Productivity
1.1.Compactor 12 Ton (example only)
Specification Width (m) Long (m)
Drum width : 2,13 m' 30 33
Overlap of rolling width : 0,15 m'
Speed average : 500 m/hr
Productivity : (Drum width - overlap) x speed average
: 990 m2/hr

Survey#3 - Stake out for Construction Drawing 2.572,68 m


River Width 30,00 m
Total Area will be compacted 463.082,94 m2
Total Hours Plan Compactor 467,76 hour

2.Activity Productivity
2.1Compacting Sub grade (example only)
Targets CBR 8% for subgrade would achieve by 6 passes of compacting by Compactor 12 Ton for layer thickness 30 cm.

Equipment : Compactor 12 Ton


CBR required : 8%
Thickness layer : 30 cm
Passing required : 6 pass
lane width : 30,00 m
Std. length : 1000 m / km
Quantity ref : (Passing req.) x (Lane width) x (Std. length)
180.000 m2/km
Productivity : (Quantity ref ) / (Equipment Productivity)