Professional Documents
Culture Documents
LTD
2.2 Condensate and Feed Water Systems 2.0a Location Plan of Engine Room - Floor Level
2.10 Inert Gas Generator 2.0b Location Plan of Engine Room - 4th Deck Level
2.2.1 Main and Auxiliary Condensate Systems 2.0c Location Plan of Engine Room - 3rd Deck and Steering
2.2.2 Distilled Water System Gear Room Level
2.2.3 Boiler Feed Water System 2.11 Soiled and Waste Water and Deck Scupper System 2.0d Location Plan of Engine Room - 2nd Deck Level
2.2.4 Boiler Water Blowdown, Sampling and Treatment System 2.0e Location Plan of Engine Room - Upper Deck Level
2.0f Tank Capacity Tables 1
2.0g Tank Capacity Tables 2
2.1.1a Main Steam System
2.1.1b Desuperheated Steam System
2.1.2a Bleed Steam System
2.1.3a Sootblowing and Dump Steam System
This manual is provided with a system of issue and update control. Controlling WORLDWIDE MARINE TECHNOLOGY LTD.
documents ensure that:
For any new issue or update contact:
• Documents conform to a standard format;
The Technical Director
• Amendments are carried out by relevant personnel; WMT Technical Office
The Court House
• Each document or update to a document is approved before 15 Glynne Way
issue; Hawarden
Deeside, Flintshire
• A history of updates is maintained; CH5 3NS, UK
Document control is achieved by the use of the footer provided on every page
and the issue and update table below.
In the right hand corner of each footer are details of the pages section number
and title followed by the page number of the section. In the left hand corner
of each footer is the issue number.
Details of each section are given in the first column of the issue and update
control table. The table thus forms a matrix into which the dates of issue of the
original document and any subsequent updated sections are located.
The information and guidance contained herein is produced for the assistance
of certificated officers who, by virtue of such certification, are deemed
competent to operate the vessel to which such information and guidance
refers. Any conflict arising between the information and guidance provided
herein and the professional judgement of such competent officers must be
immediately resolved by reference to Golar Technical Operations Office.
Issue and Updates Nov. 2004 2.8.1 Central Fresh Water Cooling System Nov. 2004 2.1.4a 10 Bar Steam System Nov. 2004
Mechanical Symbols and Colour Scheme Nov. 2004 2.8.2 Cargo Machinery Fresh Water Cooling System Nov. 2004 2.1.5a 6 Bar Steam System Nov. 2004
Electrical and Instrumentation Symbols Nov. 2004 2.8.3 Domestic Fresh Water System Nov. 2004 2.1.6a Steam Drain and Deoiler System Nov. 2004
Distributed Control System Operation Guide Nov. 2004 2.8.4 Purifier Operating Water System Nov. 2004 2.1.7a Turbine Exhaust Steam System Nov. 2004
Heat Balance and Flow Diagrams Nov. 2004 2.9 Compressed Air Systems Nov. 2004 2.1.8a Clean Steam Drains System Nov. 2004
Introduction Nov. 2004 2.9.1 Control Air System Nov. 2004 2.1.9a Safety Valves and Exhaust Steam System Nov. 2004
1.1 To Bring Vessel into Live Condition Nov. 2004 2.9.2 Working Air System Nov. 2004 2.2.1a Main Condensate System Nov. 2004
1.2 To Prepare Main Plant for Operation (Raising Steam) Nov. 2004 2.9.3 Starting Air System Nov. 2004 2.2.1b Auxiliary Condensate System Nov. 2004
To Prepare Main Plant for Manoeuvring from In Port 2.10 Inert Gas Generator Nov. 2004 2.2.2a Distilled Water System Nov. 2004
1.3 Nov. 2004
Condition
2.11 Soiled and Waste Water and Deck Scupper System Nov. 2004 2.2.3a Boiler Feed Water System Nov. 2004
1.4 To Change Main Plant from Manoeuvring to Full Away Nov. 2004
2.12 Exhaust Gas Systems Nov. 2004 Boiler Water Blowdown, Sampling and Treatment
2.2.4a Nov. 2004
To Change Main Plant from Full Away to Manoeuvring System
1.5 Nov. 2004 2.12.1 Boilers, Generator and Incinerator Exhaust Gas System Nov. 2004
Condition
2.3.1a Main Turbine Lubricating Oil System Nov. 2004
2.12.2 Boiler Sealing Air System Nov. 2004
1.6 To Secure Plant at Finished with Engines Nov. 2004
2.3.2a Stern Tube Lubricating Oil System Nov. 2004
2.12.3 Nitrogen Generator Nov. 2004
1.7 To Secure Plant for Dry Dock Nov. 2004
2.3.3a Lubricating Oil Purifying System Nov. 2004
2.13 Steering Gear Nov. 2004
Text
2.3.4a Lubricating Oil Filling and Transfer System Nov. 2004
2.14 Electrical Power Generators Nov. 2004
2.0 Location Plans and Tank Capacity Tables Nov. 2004
2.4a Fuel Oil Viscosity - Temperature Graph Nov. 2004
2.14.1 Turbine Generators Nov. 2004
2.1 Steam Systems Nov. 2004
Fuel Oil Bunkering and Transfer System - Engine
2.14.2 Diesel Generator Nov. 2004 2.4.1a Nov. 2004
2.1.1 Main Steam System Nov. 2004 Room
2.14.3 Emergency Diesel Generator Nov. 2004
2.1.2 Bleed Steam System Nov. 2004 2.4.1b Fuel Oil Bunkering and Transfer System - Deck Nov. 2004
2.15 Electrical Power Distribution Nov. 2004
2.1.3 Dump Steam Control System Nov. 2004 2.4.2a Boiler Fuel Oil and Fuel Gas System Nov. 2004
2.15.1 Electrical Equipment Nov. 2004
2.1.4 10 Bar Steam System Nov. 2004 2.4.3a Generator Engine Fuel Oil System Nov. 2004
2.15.2 Main Switchboard and Generator Operation Nov. 2004
2.1.5 6 Bar Steam System Nov. 2004 2.4.4a Incinerator Waste Oil System Nov. 2004
2.15.3 Electrical Distribution Nov. 2004
2.1.6 Steam Drain and Deoiler System Nov. 2004 2.5.1a Main Sea Water Circulating System Nov. 2004
2.15.4 Shore Power Nov. 2004
2.1.7 Turbine Exhaust Steam System Nov. 2004 2.5.2a Auxiliary Sea Water Cooling System Nov. 2004
2.15.5 Main Alternators Nov. 2004
2.1.8 Clean Steam Drains System Nov. 2004 2.6.1a Engine Room Bilge System Nov. 2004
2.15.6 Emergency Alternator Nov. 2004
2.1.9 Safety Valves and Exhaust Steam System Nov. 2004 2.6.2a Forward Bilge System Nov. 2004
2.15.7 Preferential Tripping and Sequential Restarting Nov. 2004
2.2 Condensate and Feed Water Systems Nov. 2004 2.7a Ballast System Nov. 2004
Uninterruptible Power Supplies (UPS) and Battery
2.2.1 Main and Auxiliary Condensate Systems Nov. 2004 2.15.8 Nov. 2004 2.8.1a Central Fresh Water Cooling System (1) Nov. 2004
Systems
2.2.2 Distilled Water System Nov. 2004 2.8.1b Central Fresh Water Cooling System (2) Nov. 2004
2.15.9 Cathodic Protection System Nov. 2004
2.2.3 Boiler Feed Water System Nov. 2004 2.8.2a Cargo Machinery Fresh Water Cooling System Nov. 2004
2.16 Accommodation Systems Nov. 2004
Boiler Water Blowdown, Sampling and Treatment 2.8.3a Domestic Fresh Water System Nov. 2004
2.2.4 Nov. 2004 2.16.1 Domestic Refrigeration System Nov. 2004
System
2.8.3b Fresh Water Generator (Condensate Cooled) Nov. 2004
2.16.2 Accommodation Air Conditioning Plant Nov. 2004
2.3 Lubricating Oil Systems Nov. 2004
2.8.4a Purifier Operating Water System Nov. 2004
2 16.3 Auxiliary Air Conditioning Plant Nov. 2004
2.3.1 Main Turbine Lubricating Oil System Nov. 2004
2.9.1a Control Air System Nov. 2004
Engine Control Room and Main Switchboard Room Air
2.3.2 Stern Tube Lubricating Oil System Nov. 2004 2.16.4 Nov. 2004
Conditioning Units 2.9.1b Cargo Machinery Room Control Air System Nov. 2004
2.3.3 Lubricating Oil Purifying System Nov. 2004
Workshop and Boiler Water Test Room Air Conditioning 2.9.2a Working Air System Nov. 2004
2 16.5 Nov. 2004
2.3.4 Lubricating Oil Filling and Transfer System Nov. 2004 Units
2.9.3a Starting Air System Nov. 2004
2.4 Fuel Oil and Fuel Gas Service Systems Nov. 2004 2 16.6 Incinerator and Garbage Disposal Nov. 2004
2.10a Inert Gas Generator System Nov. 2004
2.4.1 Fuel Oil Bunkering and Transfer System Nov. 2004 Illustrations
2.10b Inert Gas Cooling System Nov. 2004
2.4.2 Boiler Fuel Oil and Fuel Gas System Nov. 2004 2.0a Location Plan of Engine Room - Floor Level Nov. 2004
2.11a Soiled and Waste Water and Deck Scupper System Nov. 2004
2.4.3 Generator Engine Fuel Oil System Nov. 2004 2.0b Location Plan of Engine Room - 4th Deck Level Nov. 2004
2.12.1a Boilers, Generator and Incinerator Exhaust Gas System Nov. 2004
2.4.4 Incinerator Waste Oil System Nov. 2004 Location Plan of Engine Room - 3rd Deck and Steering
2.0c Nov. 2004 2.12.2a Boiler Sealing Air System Nov. 2004
Gear Room Level
2.5 Sea Water Systems Nov. 2004
2.12.3a Nitrogen Generator Nov. 2004
2.0d Location Plan of Engine Room - 2nd Deck Level Nov. 2004
2.5.1 Main Sea Water Circulating System Nov. 2004
2.13a Steering Gear Fluid Flow Nov. 2004
2.0e Location Plan of Engine Room - Upper Deck Level Nov. 2004
Auxiliary Sea Water Cooling System (Including Fresh
2.5.2 Nov. 2004 2.14.1a Turbine Generators - Schematic Nov. 2004
Water Generators) 2.0f Tank Capacity Tables 1 Nov. 2004
2.14.3a Emergency Diesel Generator - Schematic Nov. 2004
2.6 Bilge Systems Nov. 2004 2.0g Tank Capacity Tables 2 Nov. 2004
2.15.1a Main Electrical Network Nov. 2004
2.6.1 Engine Room Bilge System Nov. 2004 2.1.1a Main Steam System Nov. 2004
2.15.2a Switchboard Generator Control Panels Nov. 2004
2.6.2 Forward Bilge System Nov. 2004 2.1.1b Desuperheated Steam System Nov. 2004
2.15.2b Generator Control/Power Management System Module Nov. 2004
2.7 Engine Room Ballast System Nov. 2004 2.1.2a Bleed Steam System Nov. 2004
2.15.2c Switchboard Control Nov. 2004
2.8 Fresh Water Systems Nov. 2004 2.1.3a Sootblowing and Dump Steam System Nov. 2004
2.15.3a Main 440V Distribution Nov. 2004 3.2.1b Engine Control Room Console Nov. 2004 Fire Detectors and Alarms - E and F Accommodation
5.4d Nov. 2004
Decks
2.15.3b Main 440V Switchboards: Group Starters Nov. 2004 3.3.1a Main Boilers Nov. 2004
Fire Detectors and Alarms - G Accommodation and
2.15.3c Main 220V Distribution Nov. 2004 3.3.2a Atomising and Purge Steam System Nov. 2004 5.4e Nov. 2004
Navigation Bridge Decks
2.15.3d Cargo 6,600V and 440V Distribution Nov. 2004 3.4.1a Main Turbines Nov. 2004
Fire Detectors and Alarms - Bow Thruster Room and
5.4f Nov. 2004
2.15.3e Emergency 440V and 220V Distribution Nov. 2004 3.4.2a Main Turbines Control System Nov. 2004 Bosun’s Store
2.15.4a Shore Power Nov. 2004 3.5a Bow Thruster Control System Nov. 2004 Fire Detectors and Alarms - Engine Room Floor and
5.4g Nov. 2004
4th Deck
2.15.5a Main Alternators Nov. 2004 Text
Fire Detectors and Alarms - Engine Room 3rd Deck and
2.15.6a Emergency Alternator Nov. 2004 4.1 Flooding in the Engine Room Nov. 2004 5.4h Nov. 2004
Steering Gear Room
2.15.7a Preferential Tripping Nov. 2004 4.2 Steaming on One Boiler Nov. 2004
5.4i Fire Detectors and Alarms - Engine Room 2nd Deck Nov. 2004
2.15.7b Sequential Restart ‘A’ Pumps Nov. 2004 Emergency Operation of the Main Turbines (Solo
4.3 Nov. 2004 5.4j Fire Detectors and Alarms - Upper Deck Nov. 2004
Running of High Pressure or Low Pressure Turbine)
2.15.7b Sequential Restart ‘B’ Pumps Nov. 2004 5.4k Fire Detectors and Alarms - Cargo Machinery Room Nov. 2004
Steaming with One Forced Draught Fan (Port or
2.15.8a Emergency Battery Charging and 24V Distribution Nov. 2004 4.4 Nov. 2004
Starboard) Out of Use 5.5a Fixed Gas Detection System Nov. 2004
2.15.9a Cathodic Protection System Nov. 2004 5.5b Portable Gas Detectors Nov. 2004
4.5 Emergency Steering Nov. 2004
2.16.1a Domestic Refrigeration System Nov. 2004 Fire Fighting Equipment - A and B Accommodation
4.6 Emergency Boiler Operation from Boiler Local Panel Nov. 2004
5.6a Nov. 2004
2.16.2a Accommodation Air Conditioning Plant Nov. 2004 Decks
4.7 Fire in the Engine Room Nov. 2004
2 16.3a Auxiliary Air Conditioning Plant Nov. 2004 Fire Fighting Equipment - C and D Accommodation
4.8 Fire Control Station Nov. 2004 5.6b Nov. 2004
Decks
Engine Control Room and Main Switchboard Room Air
2.16.4a Nov. 2004 Dead Ship Starting with the Main Diesel Generator Out
Conditioning Units 4.9 Nov. 2004 Fire Fighting Equipment - E and F Accommodation
of Service 5.6c Nov. 2004
Decks
2.16.6a Incinerator System Nov. 2004
Illustrations Fire Fighting Equipment - G Accommodation,
Text 5.6d Nov. 2004
4.3a Emergency Operation of the Main Turbines Nov. 2004 Navigation Bridge and Compass Decks
3.1 Distributed Control System (DCS) Nov. 2004 Fire Fighting Equipment - Bow Thruster Room and
4.4a Operation of the Forced Draught Fan Crossover Flaps Nov. 2004 5.6e Nov. 2004
3.1.1 Distributed Control System Overview Nov. 2004 Bosun's Store
4.6a Boiler Local Panel Nov. 2004
3.1.2 Operator Stations Nov. 2004 Fire Fighting Equipment - Engine Room Floor and 4th
4.8a Fire Control Station Nov. 2004 5.6f Nov. 2004
Deck
3.1.3 Screen Displays, Alarms and Monitoring Nov. 2004
Dead Ship Starting Sequence with the Main Diesel Fire Fighting Equipment - Engine Room 3rd Deck and
4.9a Nov. 2004 5.6g Nov. 2004
3.1.4 Control and Operation of Equipment Nov. 2004 Generator Out of Service Steering Gear Room
3.1.5 UMS Watch Call System and Alarms Nov. 2004 4.9b Electrical Load for Dead Ship Starting Nov. 2004 5.6h Fire Fighting Equipment - Engine Room 2nd Deck Nov. 2004
3.2 Centralised Control Room, Console and Panels Nov. 2004 Text 5.6i Fire Fighting Equipment - Main Deck Nov. 2004
3.2.1 Engine Control Room Nov. 2004 5.1 Fire and Wash Deck System Nov. 2004 5.6j Fire Fighting Equipment - Upper Deck Nov. 2004
3.3 Main Boilers Nov. 2004 5.2 CO2 Flooding System Nov. 2004 5.7a Lifesaving Equipment - Main Deck Nov. 2004
3.3.1 Main Boilers Description Nov. 2004 5.3 Quick-Closing Valves and Fire Dampers System Nov. 2004 Lifesaving Equipment - A and B Accommodation
5.7b Nov. 2004
3.3.2 Boiler Control Systems Nov. 2004 5.4 Fire Detection System Nov. 2004 Decks
3.3.3 Boiler Operating Procedures Nov. 2004 5.5 Fixed Gas Detection System Nov. 2004 Lifesaving Equipment - C and D Accommodation
5.7c Nov. 2004
Decks
3.3.4 Sootblowers Nov. 2004 5.6 Fire Fighting Equipment (Illustrations Only) Nov. 2004
Lifesaving Equipment - E and F Accommodation
3.4 Main Turbines Nov. 2004 5.7 Lifesaving Equipment (Illustrations Only) Nov. 2004 5.7d Nov. 2004
Decks
3.4.1 Main Turbines and Ancillaries Nov. 2004 5.8 Emergency Escape from Engine Room Nov. 2004 Lifesaving Equipment - G Accommodation Deck and
5.7e Nov. 2004
3.4.2 Main Turbines Control System Nov. 2004 5.9 High Expansion Foam Fire Extinguishing System Nov. 2004 Navigation Bridge Deck
3.5 Bow Thruster Nov. 2004 5.10 First Aid Fresh Water System Nov. 2004 5.7f Lifesaving Equipment - Engine Room 2nd Deck Nov. 2004
Illustrations 5.11 Personnel Protection Equipment Nov. 2004 Lifesaving Equipment - Engine Room 3rd Deck and
5.7g Nov. 2004
Steering Gear Room
3.1.1a Distributed Control System Overview Nov. 2004 5.12 Water Spray System Nov. 2004
Lifesaving Equipment - Engine Room Floor and 4th
3.1.1b DCS Uninterruptible Power Supply Distribution Nov. 2004 5.13 Dry Powder Fire Extinguishing System Nov. 2004 5.7h Nov. 2004
Deck
3.1.2a DCS Human Interface Station Keyboard Nov. 2004 5.14 Oil Mist Detection System Nov. 2004 5.7i Lifesaving Equipment - Upper Deck Nov. 2004
3.1.2b Human Interface Command Station Keyboard Keys Nov. 2004 Illustrations 5.8a Emergency Escape from Engine Room Nov. 2004
3.1.2c Human Interface Command Station Keyboard Keys Nov. 2004 5.1a Fire and Wash Deck System Nov. 2004 5.9a High Expansion Foam Fire Extinguishing System Nov. 2004
3.1.3a DCS Screen Display Nov. 2004 5.1b Engine Room Fire Main System Nov. 2004 5.12a Water Spray System Nov. 2004
3.1.3b Machinery Screen Display Hierarchy Nov. 2004 5.2a CO2 Flooding System Nov. 2004 5.13a Dry Powder Fire Extinguishing System Nov. 2004
3.1.4a DCS Faceplate Window: Motor and Valve Control Nov. 2004 5.3a Quick-Closing Valves and Fire Dampers System Nov. 2004 5.13b Dry Powder Release Cabinet Nov. 2004
3.1.4b Faceplate Windows: PID Controller Nov. 2004 5.4a Fire Detection Panel Nov. 2004 5.14a Oil Mist Detection System Nov. 2004
3.1.4c Trending Diagram Nov. 2004 Fire Detectors and Alarms - A and B Accommodation
5.4b Nov. 2004
Decks
3.1.5a UMS Watch Call System Nov. 2004
Fire Detectors and Alarms - C and D Accommodation
3.1.5b Wheelhouse Responsibilities Graphic Nov. 2004 5.4c Nov. 2004
Decks
3.2.1a Engine Control Room Nov. 2004
Spray Line
Cylinder Operated With
Butterfly Valve Positioner Control Y-Type Strainer FB Foam Box
Superheated Steam
Screw Down Non-Return W Wax Expansion Type Steam Trap With Strainer
Control Valve Accumulator
Valve and Drain Cock Desuperheated Steam
Lift Check Non-Return M Electric Motor Driven Sounding Head With Not Connected Exhaust Steam
Valve Filling Cap Crossing Pipe
Air
Needle Valve / 'V' Port Valve Weight Observation Glass Orifice
Heavy Fuel Oil
Emergency Shut-off Valve Centrifugal Pump Deck Stand (Hydraulic) Overboard Discharge Lubricating Oil
Refrigerant Liquid
3-Way Cock Float Type Air Vent
Rose Box
(L-Type/T-Type) (With Flame Screen)
Electrical Signal
Hand Operated (Locked Open)
Mud Box Flexible Hose Joint
Hand Operated (Locked Shut) Instrumentation
MODE VOLUME
OFF
ON
ENG
TRACK BALL
/ MODULE
SHIP FEED MAIN FO & GAS WATER FO, DO & COMPRESSORS NITROGEN
STEAM BOILERS LO SYSTEMS CARGO BALLAST SAFETIES MISCELL
OVERVIEW SYSTEMS ENGINE SYSTEMS SYSTEMS & HEATERS & INERT GAS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
WHEELHOUSE
ELECTRICAL ALTERNATORS MISCELL SAFETY
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
_
+ ~
ESC 1 2 3 4 5 6 7 8 9 0 - = ' \` BS
{ }
TAB Q W E R T Y U I O P [ ] DEL
CTRL ALT
SHIFT SPACE ALT CTRL EXT CL
YOKOGAWA
TRIP - JCW TEMP HIGH HIGH OIL MIST HIGH JWC PRE-HEAT UNIT FAILURE GENERATOR ST-BY FAIL AVERAGE EXHAUST 364 c
1TSHH4026
1XS5531
3XS4005 1XS4040 TEMPERATURE
OIL MIST DETECTOR FAILURE
TRIP - JCW TEMP HIGH HIGH 1XS5530 SAFETY STOP CIRCUIT FAIL GENERATOR START FAIL
Alarms Area
1PSLL4072 LUB OIL FILT. DIFF. PRESS. HIGH 1XS4014 1XS4041 T.C EXH GAS OUT TEMP
TRIP - ENGINE OVERSPEED 1DPSH4070
CONTROL POWER FAILURE GENERATOR PLC SYS ERROR 402 c 1TI4020
1SSH4002 PRE LUB OIL LEVEL LOW 1XS4015B 1XS4042
T.C EXH GAS IN TEMP
1LSL4070
TRIP - OIL MIST HIGH HIGH GENERATOR CYL LUB N-FLOW
1XSS531B
GENERATOR JET SYSTEM FAILURE 1/2HA4015
STAND BY FAILURE
1XS4043 444 c 1TI4019
1XS4028A
GENERATOR EM'CY STOP GENERATOR TACHO FAILURE GAS OIL LEAK
1XS4039 1LSH4061
1XS4028B
GAS OIL 4.1 bar WINDING TEMPS 35 c 343 c 371 c 383 c 341 c 380 c 373 c 361 c 360 c SHUTDOWN
1PI4061 R S T
1TI4111/A/B/C 53 54 55 c
1TI4021 52 c AIR TEMP
ON LOAD DIESELGENERATOR
715 RPM
1SI4002
83 A CURRENT 66 c Related Temperature
87 c 1TI4025
1TI4030
751 kW LOAD Read Out
Bearing Temperature
Read Out
60 c FW OUTLET TEMP
1TI4031
0.79 PF POWER FACTOR 10219 RPM
1 2 3 4 5 6 7 8 1SI4001
WATER LEAKAGE
1LSH4025
TURNING GEAR
MOTOR
Shortcut Soft Key Icon to M
Supply System Screen Mimic CENTRAL F.W FW INLET PRESS 4.89 bar 1PI4025
(Central Fresh Water Cooling) COOLING 1K4050
Shortcut Soft Key Icon to No.2 TURBO No.2 TURBO DIESEL EMERGENCY NO.1 TURBO NO.1 TURBO
Related System Screen Mimic ALT.MONITOR ALT.SERVICE ALTERNATOR D/G ALT.MONITOR ALT.SERVICE
Related Equipment
(Cylinders Lubricating Oil Pump) Control Mode
Icon - Access to Control Faceplate
External Desuperheaters
Loss
Vacuum Pump
Sootblowers Q0 Q 865
Q0 62.5/16.5 LP Turbine
PRV
HP Turbine
Steam to Burners 722mmHg
Q 460 Q 94,420 Q 83,415 Q 73,975 Q 64,915 Vacuum Q 71,405
P 62.5 E 823.6 E 543.6 Main
Main Boilers T 515 P 61 T 32.6
Fuel Oil Tank M Condenser
Heater T 510 Main Condensate
Q 870
M Pump
62.5/16.5
PRV Q 1,765
Boiler Fuel Oil Q 7,545
Q 450 P 19.3
Heater P 6.0
E 757.9 Q 130 E 695.5
E 740 Q 9,060 No.2
Lubricating Oil Purifier Q 110 P 1.4 Distilling Plant
Heater Q 100 E 780 E 637.7 Q 2400 Q0
Q0 Q 6,550 Turbine
Generator
Q 6,440
16.5/5.9 E 823.6
E 582 Q0
PRV P 61
Calorifier T 510 5.9/0.7
Q 100
PRV
Q 3,550
Q 2,400
Q 1,065
16.5/11
Forcing Vaporiser PRV 5.9/2.8 PRV No.1
Q0 Q 30 Distilling Plant
E 734.1
Q 3,795
Q 2,930 Q0
E 695.5 E 823.6
Low Duty Heater Q 3,560 3.2/722 MMHG
Q0 P 61 E 734.1 Q 50
Q 94,420 T 510 Boiler Feed Water PRV
P 2.8
T 145 Pump Turbine
External Desuperheaters
Loss
Vacuum Pump
Sootblowers Q0 Q 875
Q0 LP Turbine
62.5/16.5
PRV HP Turbine
Steam to Burners 720 mmHg
Q 300 Q 95,490 Q 83,865 Q 73,820 Q 64,720 Vacuum Q 71,800
P 62.5 E 823.6 E 543.6 Main
Main Boilers T 515 P 61 T 32.6
Fuel Oil Tank M Condenser
T 510 Main Condensate
Heater Q 870
M Pump
62.5/16.5
Boiler Fuel Oil PRV Q 2,260 Q 7,655
Heater Q 185 P 19.3 P 6.0
E 757.9 Q 130 E 795.8
E 740 Q 9,100 No.2
Lubricating Oil Purifier Q 110 P 1.4 Distilling Plant
Heater Q 100 E 780 E 637.5 Q 2400 Q0
Q0 Q 7,140 Turbine
Generator
16.5/5.9 Q 7,030
E 823.6 Q0
PRV E 582.9
P 61
Calorifier T 510 5.9/0.7
Q 100
PRV
Q 3.590
Q 2,400
16.5/11 Q 1,100
Q 4,670 Q 50 Exhaust
Air Conditioning Unit
Q0 E 727 E 648.6
11/7PRV Vent
Deoiler
T 70 Q 71,800 T 50.4
Drain Cooler Q0
Q 2,285 Deaerator T 100.5 T 47.6
E 668.6 Q 95,490 P 2.5
1st Stage Feed Q 10,240 Gland Steam
E 127.2 Water Heater Condenser Q 2,400
E 129 T 90
Auxiliary Steam 3rd Stage T 76
Feed Water Heater Boiler Feed Water
Desuperheater Q 325 Pump Q 2,965
T 129
Q 2,965 E 138.7 Q0
T 138.7
Q 1,175 Q 12,640
Q 1,960 Make-Up Atmospheric Drain Design Base
T 35 T 87.3 Q 320
Inspection Tank E 757.9 Q 1,155 Tank Main Turbine Non Extra Steam Rate 2.34 kg/ps.h
(1.5m3) T 70 T 90 Boiler Efficiency 86.3 %
Q 1,130 Q 16,420
Turbo Generator Load 1,770 kW
T 91 T 79
Key Evaporator Load 45 Ton/Day
Atmospheric Drain Sea Water Temperature 27 ºC
Desuperheated Steam Tank Pump Air Temperature 45 ºC
Fuel Oil High Heat Value 13,280/10,280 kcal/kg
Superheated Steam E: kcal/kg
Air Conditioning Plant (Cooling) In Use
Exhaust Steam P: kg/cm2 Main Condenser Scoop Cooling
Ship Condition - 90% MCR (Dual Burning)
Main Feed Water Pump Load 140m3/h X 865mth
Feed Water and Condensate Main Turbine Shaft Horse Power - 31,950 SHP(PS) 82.1rpm
T: ºC Boil-Off Rate 0.15 %/Day
Nominal Fuel Rate - FO: 3,881.3 kg/h
FG: 2,058.9 kg/h SG of Cargo 0.46 Ton/m3
Feed Water/Distilled Water
External Desuperheaters
Loss
Vacuum Pump
Sootblowers Q0 Q 880
Q0 LP Turbine
61.5/15.5
PRV
HP Turbine
Steam to Burners 720 mmHg
Q0 Q 84,985 Q 73,430 Q 64,375 Vacuum Q 71,635
Q 96,820 E 543.6
E 823.6 Main
Main Boilers P 62.5 T 32.6
Fuel Oil Tank P 61 M Condenser
Heater T 515 Main Condensate
Q 870 T 510 M Pump
62.5/16.5
PRV Q 3,610
Boiler Fuel Oil Q 7,815
P 19.2
Heater Q0 P 6.1
E 757.7 Q 130
E 696.4 No.2
E 740 Q 9,055
Lubricating Oil Purifier Q 110 Distilling Plant
P 1.4
Heater Q 100 E 780 E 637.3 Q 2,400 Q0
Q0 Q 7,320 Turbine
Generator
16.2/5.9 Q 7,210
E 823.6 Q0
PRV E 583.3
P 61
Calorifier T 510 5.9/0.7
Q 100
PRV
Q 3,635
Q 2,400
Q 1.180
16.5/11
Forcing Vaporiser PRV 5.9/2.8 PRV No.1
Q 1,555 Distilling Plant
Q 30
Q 3,635 E 733.9
Q 3,605 Q0
E 823.6 E 733.9
Low Duty Heater 3.2/722 MMHG
Q 1,580 P 61 P 2.8 Q 50
T 510 Boiler Feed Water PRV
Pump Turbine
Q 96,820 Q 3,000
Q 4,785 Q 50 Exhaust
Air Conditioning Unit T 145 E 696.3
Q0 E 724.7 E 648.6
10.8/6.8 Vent
PRV
Deoiler
T 70 Q 71,635
Drain Cooler Q0
Q 4,205 Deaerator T 100.5 T 50.4 T 47.6
T 668.6 Q 96,820 P 2.5 1st Stage Feed Gland Steam
E 127.2 Q 10,240
E 129 Water Heater Condenser Q 2,400
T 90
Auxiliary Steam T 76
Boiler Feed Water
Desuperheater Q 595 Pump Q 3,000
E 129
Q 3,000 E 138.7 Q0
E 138.7
Q 880 Q 12,640
Q 3,610 Make-Up Atmospheric Drain Design Base
T 35 T 87.3
Inspection Tank T 757.7 Q 970 Tank Q 320 Main Turbine Non Extra Steam Rate 2.34 kg/ps/h
(1.5m3) T 70 T 90 Boiler Efficiency 83.9 %
Q 3,235 Q 18,045
Turbo Generator Load 1,815 kW
T 90.5 T 80.6
Key Evaporator Load 45 Ton/Day
Atmospheric Drain Sea Water Temperature 27 ºC
Desuperheated Steam Tank Pump Air Temperature 45 ºC
Fuel Oil High Heat Value 13,280 kcal/kg
Superheated Steam E: kcal/kg
Air Conditioning Plant (Cooling) In Use
Exhaust Steam P: kg/cm2 Main Condenser Scoop Cooling
Ship Condition - 90% MCR (BOG Burning) Main Feed Water Pump Load 140m3/h X 865mth
Feed Water and Condensate Boil-Off Rate
T: ºC Main Turbine Shaft Horse Power - 31,950 SHP(PS) 82.1rpm 0.13 %/Day
Feed Water/Distilled Water Nominal Fuel Rate - 179.6 G/ps.h 5,738.2 kg/h SG of Cargo 0.46 Ton/m3
Shut the drum vent when steam issues from it, at 3.3.3
approximately 2kg/cm2.
Fill a boiler to 80mm below normal water level,
3.3.3 Open the steam inlet and drains to one fuel oil heater
using the auxiliary feed water pump.
and allow the fuel temperature to rise.
As the steam pressure rises, use the electric feed Isolate the atomising air supply.
pump to maintain the boiler water level. 3.3.3
With the boiler now being fired on HFO, the fuel
pressure will require adjusting to maintain a steady
and safe pressure rise rate.
Ensure that the DCS has taken the control of the boiler 3.3.2
out of the flashing ramp to the normal control mode.
When the boiler pressure is at approximately 15kg/cm2, The boiler should now be providing normal steam
ensure that the drains pump system is operating to 2.2.1 pressure to the turbine generator / main feed pump /
the deaerator. and fuel oil heating etc.
Put one main feed pump into operation to maintain
the boiler level. 3.3.3
Bring the boiler up to working pressure.
The turbine exhaust will dump to the auxiliary
condenser.
Start the main turbine turning gear. 3.4.2 Open the valves for the sea water cooling supply to
one vacuum pump cooler. 2.5.1
Open the air inlet valve to vacuum pump diffuser from
the main condenser.
Start the vacuum pump and start raising the
Start the gland condenser exhaust fan. 3.4.1 main condenser vacuum.
Once the vacuum has been raised, change over all
exhaust dumps to the main condenser.
Open the gland steam make-up and spill inlet and 3.4.1
outlet valves. Adjust the controller set steam pressure.
Ensure that if any burners are off, they are in place and
ready to be used.
Allow main engine revolutions to increase as per the Pump the contents of the bilge tank overboard through 2.6.1
timed program, which will open the manoeuvring the oily water separator unit.
valve a set amount over a period of time until it is
fully open. This will take approximately 40 minutes 3.4.2
from full ahead manoeuvring revolutions to full sea
revolutions.
At manouevring rpm, the astern guardian valve When the bridge notifies the engine room of end of
opens and the turbine drains set opens. passage, record the following:
Approximately 24 hours before manoeuvring Time
operations are to commence, run up the standby Main engine revolution counter
turbine generator. 2.14.1. Fuel oil counter
(Note: Trips may be tested at this time. Fuel oil settling tank levels
When the unit is up to speed, parallel with the unit As the turbine rpm continues to fall, the main Diesel oil service tank level
already on the main switchboard.) condensate recirculation valve will open. Fuel and diesel oil bunker tank levels
This allows condensate to return to the main Distilled and FW tanks levels
condenser hot well, ensuring a level is maintained for Gas meter reading
the condensate pumps. .
When all movements of the main engine are Close the main turbine steam stop valve T645V from
completed, the bridge will transfer the control of the the boilers, HP and LP turbine ahead valves and open 3.4.2
main engines to the engine room and place the the warming through valve T644V.
telegraph at FWE.
Switch the auto-spin system off and trip the turbine. 3.4.2
Vessel Is at Finished With Engines When the main condenser has cooled, the sea water 2.5.1
And In a Live Condition circulating pump can be stopped and all valves closed.
Close the steam valve T325V to the cargo system. 2.1.4 Allowing the other boiler automatic controls to take
Stop and isolate the fresh water cooling booster pumps 2.8.2 more of the load. When the second boiler has taken 3.3.2
the entire load, the first boiler can be tripped.
Shut down the LO purifiers. 2.3.3
Ensure that the main feed pump gland seal water and
all other spray or cooling condensate water is 2.2.1 Isolate the fuel oil and the atomising steam valves at
Start up the diesel generator and connect it to the supplied from the atmospheric drains pumps system. the burner rail. Shut off the steam to the air heater.
switchboard in parallel with the in-use turbine generator. 2.14.2 Stop the FD fan and close the vanes.
Ensure the main boiler steam stop valves T601V and Stop the in-use main condensate pump. Allow the shut down boiler pressure to fall away,
602V and warming through valve T644V are shut and 2.1.1 Close the main condensate recirculating valve, to 2.2.1 opening the drum vent when the pressure is 3.3.1
open the drain valves T646V and T647V. prevent any water returning to the main condenser. approximately 5kg/cm2.
Shut off the steam supply to the in-use boiler fuel oil
heater. When the fuel temperature falls to Isolate the fuel oil and the atomising steam valves at
approximately 90°C, open the fuel supply to the boiler the burner rail. Shut off the steam to the air heater.
fuel pump from the gas oil service tank and close all Stop the FD fan and close the vanes. Unload the diesel generator from the switchboard, allow it
valves from the fuel oil service tanks. to run light to cool down before stopping. Engage the
turning gear and close the air start valve A48V. Open 2.15
Change the atomising steam supply over to atomising
air supply, from the general service air system, to the ACB LL1 and LL2 to isolate the 6,600V main switchboard. 2.9.3
in-use boiler. Stop the in-use main feed pump and close all valves. 2.2.3 Start the emergency diesel generator to supply the
emergency lighting.
As gas oil is used throughout the system, the HFO will With the boiler shut down, there should be no more Stop the main turbine and turbine generator turning gear.
be replaced by the gas oil. This will be required in drains returning to the atmospheric drains tank. Stop the main turbine and turbine generator LO pumps. 2.3
preparation for the flash-up cycle when no heat will 2.4 Shut the deaerator outlet valve to the main feed pump 2.2.1 Close valve L20V to the LO gravity tank.
be available for the HFO. suction. Stop the stern tube seal LO pumps and close valves
Allow the DO to flow through both fuel heaters, and Shut the in use distilled tank outlet valve to the L333V and L334V on the stern tube aft seal LO tank.
through the recirculation rail at the burner registers. make-up line.
Illustrations
2.0c Location Plan of Engine Room - 3rd Deck and Steering Gear Room Level
Cofferdam
Atmospheric
Drain No.1 and 2 Distillate Plant
Tank Sea Water Feed Pumps
Sea Water Hydrophore
No.2 Bilge, Fire and General Service Pump
and Fire Main
Dehumidifier Pressurising Pump
Bilge Well
No.2 No.1
UP
Main LO No.3 Ballast Pump
UP Pump
UP
No.2 Auxiliary LO Pump Low Duty Condenser Pump
No.1 No.2
Condensate Cooled
Grease
Extractor Auxiliary Condenser
Distilling
Plant
DN
DN
Central FW Cooling
Emergency ICCP Temperature Control Valve
Escape Panel
Stern Tube DN Central Cooling
UP Lubricating Oil UP Elevator Fresh Water Pumps
Gravity Tank DN
Lift Heatless Air Dryers
Space Deoiler
for Engine Room
UP Control System
Inspection
Tank and Heatless Air Dryers
Drain for Cargo Control
UP
Vent UP Cooler System
Vent
Working Air Control Air Reservoir
Control Air Compressor
Compressors Working Air
Reservoir
Illustration 2.0d Location Plan of Engine Room - 2nd Deck Level Membrane Unit for
Nitrogen System No.2 440/230V Transformer
Accommodation
Air Conditioning Nitrogen Buffer Tank
Compressor Units Inert Gas Generator
Diesel Oil
No.2 No.2 Service Tank Heavy Fuel Oil
Oil Storage Auxiliary
Exhaust Fan Air Conditioning Nitrogen Generator Room Bunker Tank (P)
Compressor Units
No.1
Nitrogen Air
No.1 Compressors
Vent Vent DN
Vent Vent
Removable
Plate for
Forced Draught Fan
Standby Forced
Draught Fan Engine Room
Standby Forced
Control Panel Hatch
Boiler Vent Draught Fan
Hood Room
UP
No.1
Control Panel for
Starboard Boiler Forced Draught Fan
Starboard Boiler
Forced Draught Fan
Incinerator
Starboard Boiler
Economiser
Vent Vent
Incinerator Room
No.1 Cargo Tank 34,671.9 34,628.6 34,290.765 33776.404 37.349 81.200 22.885 Domestic FW Tank (Starboard) 17 - 25 289.2 289.2 -122.216 20.362
No.2 Cargo Tank 34,671.9 34,628.6 34,299.926 33785.427 37.346 36.200 22.885 Domestic FW Tank (Port) 17 - 25 289.2 289.2 -122.216 20.362
No.3 Cargo Tank 34,671.9 34,628.6 34,307.559 33792.946 37.367 -8.800 22.885 Distilled Water Tank (Starboard) 9 - 17 231.5 231.5 -127.772 20.399
No.4 Cargo Tank 34,671.9 34,628.6 34,281.634 33767.409 37.355 -53.800 22.885 Distilled Water Tank (Port) 9 - 17 231.5 231.5 -127.772 20.399
Aft Fuel Oil Tank (Starboard) 77 - 82 1253.3 1190.3 1178.7 -70.282 16.108 Heavy Fuel Oil Overflow Tank (Port) 69 - 77 122.7 121.5 -81.035 12.242
Aft Fuel Oil Tank (Port) 77 - 82 1253.3 1190.3 1178.7 -70.282 16.108 Bilge Holding Tank (Centre) 25 - 36 150.3 150.3 -114.119 1.871
Forward Fuel Oil Tank (Starboard) 115 - 131 974.1 925.4 916.2 109.310 18.999 Oily Bilge Tank (Centre) 36 - 39 53.6 53.6 -109.476 2.846
Forward Fuel Oil Tank (Port) 115 - 131 968.4 920.0 910.8 109.341 19.000 Stern Tube Cooling Tank (Centre) 10 - 25 220.5 220.5 -122.632 4.862
Heavy Fuel Oil Settling Tank (Starboard) 77 - 80 479.1 455.1 450.6 -74.943 16.108 Total 547.1 547.1
Heavy Fuel Oil Settling Tank (Port) 77 - 80 479.1 455.1 450.6 -74.943 16.108
WATER BALLAST TANKS (Specific Gravity = 1.025) GAS OIL TANKS (Specific Gravity = 0.850)
Fore Peak Tank (Centre) 139 - F.E. 1978.6 2028.1 130.157 12.184 Gas Oil Storage Tank (Starboard) 69 - 73 91.9 87.3 74.2 -82.700 18.807
No.1 Side Tank (Centre) 115 - 131 2879.9 2951.9 109.495 8.342 Gas Oil Storage Tank (Port) 69 - 73 91.9 87.3 74.2 -82.700 18.807
Generator Engines
No.2 Side Tank (Starboard) 108 - 115 2343.9 2402.5 86.265 10.860 73 - 77 49.1 46.6 39.7 -79.500 24.714
Gas Oil Storage Tank (Starboard)
Inert Gas Generator
No.2 Side Tank (Port) 108 - 115 2343.9 2402.5 86.265 10.860 Gas Oil Storage Tank (Port) 73 - 77 99.2 93.3 79.3 -81.009 24.714
No.3 Side Tank (Starboard) 104 - 108 4234.5 4340.4 58.513 13.751 Total 331.1 314.5 267.4
No.3 Side Tank (Port) 104 - 108 4234.5 4340.4 58.513 13.751
Illustrations
T132B TX
T655V T615V Ahead Manoeuvring Valve T711V
TX TX
To 3rd Stage
DCS
Feed Water Heater
T309V (Section 2.1.2a)
I Control
T711V P Air
60.3/15.5 bar
Pressure Reducing Valve
Control Air LP Bleed
To Sootblowers DCS I From 3rd Stage
For Solo Running P
T715V T716V T717V (Section 2.1.3a) of LP Turbine
of the HP and LP Turbine T44V (Section 2.1.2a)
4.9 bar/230mmHg Set at
T718V 1.0 bar
Pressure Reducing X11V To SW Cooled
Valve Evaporator
From
DCS Main Condensate (Section 2.1.7a)
DCS
Control I
System X15V X14V X13V X18V
From Air P To Condensate
Main Condensate Control I No.1 Excess Cooled Evaporator
P
System Air Steam Dump (Section 2.1.7a)
T45V
To LS Valve Control Air
DCS I
Auxiliary P
Condenser X43V T226V T726V
No.1 External DCS
From Desuperheater 2.2 bar/722mmHg
DCS Control Air From
Main Condensate DCS I Vacuum
No.2 Excess S P Main Condensate
System Control Valve Dump
To LS Control I Steam Dump 4.9/1.8 bar System
P Air Locked Valve
Main No.2 External Air Valve T216V Pressure Reducing Valve
Condenser Open To Main Condenser
X42V Desuperheater LS
(Section 2.1.7a)
X51V X52V X53V X27V X28V X27V X31V
DCS
T227V T728V T730V T719V
To Auxiliary Condenser
I DCS
Control Air P T46V X83V X32V
(Section 2.1.7a)
15.5/10 bar Control I
Air P
Pressure Reducing Valve From
Main Condensate System To Main Turbine
To Deaerator
Gland Steam
T328V T327V T301V (Section 2.1.7a)
To Inert Gas
Generator Dryer
T357V
DCS
To Boiler Burner From Main Feed
Control I T313V GS Atomising Steam Pump Exhaust
P 10.0/6.0 bar Set at
Air Pressure Reducing Valve Air 6.6 bar
(Section 2.1.7a) Key
T314V T356V T406V
System To Engine Room
Desuperheated Steam
T401V T402V T403V
and Accommodation
Auxiliary Steam Heating
Desuperheater
T404V Condensate
To Cargo Steam System and Forward HFO Tank Heating
T325V
Air
To Boiler Fuel Oil Heaters and Boiler Flame Steam Smothering
• 10.0 bar range - main turbine gland sealing, inert gas generator • 2.2 bar/722mmHg range dump valve X28V Pressure transmitters that are duplicated and have their outputs processed via
dryer heater, burner atomising and via an external desuperheater, two transmitters will not present a failure if one fails. An alarm will sound and
• 4.9/230mmHg range valve X14V.
to the burner flame steam smothering, generator turbines’ gland the healthy transmitter will take over automatically as the input signal for the
sealing, cargo system, fuel oil heating and the 6.0 bar range. control loop.
b) Open the steam and condensate return valves on the selected
• 6.0 bar range - air conditioning units heating, various tank HFO tank.
heating, FW calorifier, purifier heaters. 15.0 bar Range
c) Open the drain trap inlet and outlet valves on each range,
• 4.9 bar range - 3rd stage feed water preheater, boiler air allowing drains to pass to the atmospheric drain tank. At full away conditions at sea the 15.5 bar range is supplied by the HP bleed
heaters. steam from the HP turbine. When the HP bleed is not available or when the
• 1.8 bar range - excess steam dump to main or auxiliary d) Open the drain trap inlet and outlet valves on the burner vessel is manoeuvring and the HP bleed pressure is insufficient, the pressure is
condensers and make-up to deaerator heating steam. atomising steam pipe lines, allowing drains to pass to the maintained from the desuperheated steam system via pressure reducing control
atmospheric drain tank. valve T707V.
• 230mmHg range - evaporator heating steam.
e) Slowly open the 60.3/15.0 bar range control valve warming A pressure control loop controls the two control valves in a split range, with a
During normal full away at sea conditions, steam is provided by the HP, IP through/bypass valve T709V to admit steam into the system. single pressure transmitter providing the measured value to the loop. The range
and LP bleed steam from the main turbine. Any deficiency due to high steam provides make-up steam to the lower pressure ranges and boiler sootblowers.
demand will be made up from the desuperheated system. During manoeuvring f) As the pipeline temperature reaches the operating range, the set
or stopped conditions, where HP, IP and LP bleed steam is not available, point on the 60.3/15.0 bar range control valve can be manually (Note: If the pressure reducing control valve T707V fails, it will revert to the
steam will be supplied by the desuperheated steam system. increased from 0 bar to 15 bar over a period of time. open position. A failure of the control system that opens the valve will
not have a significant effect, other than to lift the safety valve T132V
The desuperheated steam system can be controlled and monitored from the As the pressure approaches the set point on each pressure range, the control on the 15/4.9 bar range. When steam is being supplied by the high
DCS graphic screen T30-407-01 DESUPERHEATED STEAM SYSTEM. By valves will begin to close and eventually control the pressure. Any further pressure bleed, a fault in the DCS which causes the valve to adopt
clicking on the faceplate of the various control valves. This opens the faceplate increase will cause the dump valve T28V to open. the closed position will not present a problem as the valve is used to
and allows the valve to be controlled manually if required. control make-up steam which, under optimum conditions, should be
minimal.)
To 3rd Stage
DCS
Feed Water Heater
T309V (Section 2.1.2a)
I Control
T711V P Air
60.3/15.5 bar
Pressure Reducing Valve
Control Air LP Bleed
To Sootblowers DCS I From 3rd Stage
For Solo Running P
T715V T716V T717V (Section 2.1.3a) of LP Turbine
of the HP and LP Turbine T44V (Section 2.1.2a)
4.9 bar/230mmHg Set at
T718V 1.0 bar
Pressure Reducing X11V To SW Cooled
Valve Evaporator
From
DCS Main Condensate (Section 2.1.7a)
DCS
Control I
System X15V X14V X13V X18V
From Air P To Condensate
Main Condensate Control I No.1 Excess Cooled Evaporator
P
System Air Steam Dump (Section 2.1.7a)
T45V
To LS Valve Control Air
DCS I
Auxiliary P
Condenser X43V T226V T726V
No.1 External DCS
From Desuperheater 2.2 bar/722mmHg
DCS Control Air From
Main Condensate DCS I Vacuum
No.2 Excess S P Main Condensate
System Control Valve Dump
To LS Control I Steam Dump 4.9/1.8 bar System
P Air Locked Valve
Main No.2 External Air Valve T216V Pressure Reducing Valve
Condenser Open To Main Condenser
X42V Desuperheater LS
(Section 2.1.7a)
X51V X52V X53V X27V X28V X27V X31V
DCS
T227V T728V T730V T719V
To Auxiliary Condenser
I DCS
Control Air P T46V X83V X32V
(Section 2.1.7a)
15.5/10 bar Control I
Air P
Pressure Reducing Valve From
Main Condensate System To Main Turbine
To Deaerator
Gland Steam
T328V T327V T301V (Section 2.1.7a)
To Inert Gas
Generator Dryer
T357V
DCS
To Boiler Burner From Main Feed
Control I T313V GS Atomising Steam Pump Exhaust
P 10.0/6.0 bar Set at
Air Pressure Reducing Valve Air 6.6 bar
(Section 2.1.7a) Key
T314V T356V T406V
System To Engine Room
Desuperheated Steam
T401V T402V T403V
and Accommodation
Auxiliary Steam Heating
Desuperheater
T404V Condensate
To Cargo Steam System and Forward HFO Tank Heating
T325V
Air
To Boiler Fuel Oil Heaters and Boiler Flame Steam Smothering
The system is supplied from the 15.5 bar range via pressure control valve and Two transmitters are used for control, indication and alarm and provide the
is described in section 2.1.4 10.0 bar Steam System. measured value for the pressure control loop. The output from the loop is also
used to control the 4.9/1.8 bar make-up/dump control valve X52V and the
6.0 bar Range dump control valve X28V.
The system is supplied from the 10.0 bar range auxiliary desuperheater via
pressure control valve T402V and is described in section 2.1.4 6.0 bar Steam 0.1 bar Range
System. This range is supplied by reduced steam from the 4.9 bar range via the pressure
reducing valve X14V and LP bleed steam from the LP turbine when at full
A safety valve is fitted downstream of the pressure reducing valve T402V and away conditions. The range supplies the evaporators’ heating steam and a
is set at 6.6 bar. single pressure transmitter provides the measured value to the control loop
which controls valve X14V.
4.9 bar Range
The supply is reduced from the 15.0 bar range by the pressure reducing valve
T307V before supplying the 3rd stage feed water preheater, boiler air heaters
and the 1.8 bar and 0.1 bar ranges. At full away conditions at sea the 5.0 bar
range is supplied by the IP bleed steam from the HP/LP turbine crossover
pipeline, which can be isolated by the motorised valve T102V. Two transmitters
are used for control, indication and alarm and provide the measured value for
the pressure control loop. The output from the loop is also used to control the
5.0/1.8 bar make-up/dump control valve X52V. The loops controlling pressure
reducing valves T307V and X52V are arranged so that make-up and dump do
not take place at the same time, unless both the 5.0 bar and 1.8 bar pressure
ranges are low.
A safety valve is fitted downstream of the pressure reducing valve T307V and
is set at 6.5 bar.
The 4.9/1.8 bar make-up/dump control valve X52V initially controls the IP
bleed steam pressure. If the IP/4.9 bar range pressure rises above the set point
the control valve X52V will open and dump steam into the 1.8 bar range. The
valve will also open if the pressure in 1.8 bar range reduces to below the set
point for that system.
TX
From
15.0/4.9 bar TI
Pressure Reducing LP
DCS
Valve (Section 2.1.4a) Turbine TX TI
DCS
To Deaerator and TIAH
TI DCS
Key Fresh Water
DCS
Generators
(Section 2.1.7a) I Control
P
Superheated Steam Air
M TX TI PI
PI
DCS
Desuperheated Steam
T142V T102V T101V PX DCS
To
Condensate Desuperheatered T144V
Steam System Gland Steam Receiver PX
(Section 2.1.3a) T143V
Air
PI From
From DCS
PX PI
Electrical Signal 0.1/-0.9 bar 10bar
Boilers Internal
Desuperheaters To Steam
Instrumentation (Section 2.1.1a) Atmospheric T131V
System
10.0/0.1 bar
Drain Tank (Section
T711V (Section 2.1.8a) 2.1.4a)
HP
Turbine
T709V Flash
T706V
To Chamber
Safety
T363B
61.5/15.5 bar Manifold
T365B T365B T269B PRV (Section
T707V 2.1.9a) T645V
DCS P
I
T708V
T114V
From
TI Control Distilled
Starboard Boiler Set at
PI PI Control M T110V Air Water Tank
Air Heater 25 bar PI
Air T132V
Section 2.2.2a)
TI
TI
T268B To Deck
To 15.0/10 bar
Pressure Scupper Portable Pipe, (Normally taken Off) for Solo Running
Reducing Valve Fitted to Allow Desuperheated Steam
(Section 2.1.4a) to be Supplied to the HP and LP Turbine Superheated Steam
Supply from Boilers
The bleed steam system can be controlled and monitored from the DCS graphic
Level Controls for First and Third Stage Feed Water Heaters
screen T30-407-01 DESUPERHEATED STEAM SYSTEM. By clicking on
The levels are controlled by the DCS which operates a regulating valve on
the faceplate of the various control valves opens the faceplate and allows the
the condensate outlet line from the heater. This ensures that the heating steam
valve to be controlled manually if required.
gives up its maximum possible enthalpy to the feed water, rather than passing
out of the heater in a similar condition. The condensate level is monitored by
High Pressure (HP) Bleed Steam the DCS which responds accordingly.
At full away conditions at sea the HP bleed steam supplies the 15.5 bar range.
The HP bleed supply pipeline can be isolated by the motorised valve T110V, The two level controls are pure PID level controllers for controlling the
which is manually opened but closed automatically by the bleed steam pressure condensate levels within the respective heaters. Adjusting the level will have a
transmitter responding to predetermined bleed steam pressures. When the beneficial effect on the outlet feed water temperature and the subsequent effect
vessel is manoeuvring and the HP bleed pressure is insufficient, the pressure on the overall plant efficiency.
is maintained in the 15.5 bar range from the desuperheated steam system via
reducing control valve T707V. This function is accessed from DCS graphic screen T30-412-02 CONDENSATE
SYSTEM for the first stage heater and graphic screen T30-453-01 FEED
(Note: A failure of the control system that opens the valve will not cause WATER SYSTEM for the third stage feed heater. There should be no need
the main turbine to trip or cause a reduction in turbine power. When for the operator to make changes to the level control unless it is necessary
steam is being supplied by the high pressure bleed, a fault in the DCS to manually control the valves.
which causes the valve to adopt the closed position will prevent steam
being available to the steam ranges. This should not present a problem
as steam demand will be met by make-up steam via valve T707V.
A similar situation will exist should the motorised valve T110V
inadvertently close when supplying HP bleed steam.)
R8 R8
R7 R7
DCS
R6 R6
DCS From
Main Condensate
System
S Control I
To 61.5/15.5 bar Control P
R5 R5 Air
Pressure Reducing Valve Air T216V
T707V
R4 R4
R3 To Safety R3
Manifold No.1 Excess
Steam Dump
(Section 2.1.9a) Valve DCS
T702V
From No.1 External
R2 R2 Valve Locked Open
Boilers Internal LS PI Desuperheater TX TI To Main or
Desuperheated Auxiliary
Steam System Condenser
(Section 2.1.1a) T719V T730V T726V T727V T226V
R1 R1 (Section 2.1.7a)
DCS
Control TX PI PX PS
I
T720V T724V Air P PI
L2 L2 T701V
T711V
TIAH PIAH Dump
T721V T725V DCS
Control I DCS DCS Valve
P DCS
Air Interlock
L1 Control Control L1
Air Air
To Main Turbine No.2 Excess From
Steam Dump No.2 External Main Condensate
210V Solo Running Valve
T213V Desuperheater System
LS LS LS LS
T728V T729V T227V
T211V T285B T285B T214V DCS
Control I PI
T212V T215V Air P From Main
Condenser
Pump
To Atmospheric Discharge
Drain Tank (Section 2.2.1a)
To Bilge Holding Tank (Section 2.1.8a)
(Section 2.6.1)
1. Steam flow - from both boilers Two transmitters are provided to measure the 1.8 bar system pressure.
The loop controlling the 4.9/1.8 bar make up/dump control valve and the 1.7
bar dump control valve is arranged so that make-up and dump do not take place
at the same time. Valves X52V and X28V operate in split range with a dead
central band.
The system can be viewed and access to the valves gained through graphic
screen T30-407-01 DESUPERHEATED STEAM SYSTEM.
The system should always be available while the plant is on line. The following
valves in the excess steam dump system are controlled by the DCS.
The following valves should be manually set up prior to using the system.
All valves in the system after the excess steam dump valves have sealing water
supplied from the main condensate system to prevent loss of vacuum through
leaking glands.
The system can be viewed and access to the valves gained through the graphic Two transmitters measure the gland steam sealing pressure and provide control,
screen T30-407-01 DESUPERHEATED STEAM SYSTEM. The pressure indication and alarm and the measured value for the loop. Split ranging is
control valve is accessed by clicking on the faceplate which allows manual carried out between the two valve positioners outside the DCS. Any loss of air
operation if required. supply, or signal from the DCS to the valves, will cause the make-up valve to
open and the dump valve to close. Excess steam will be applied to the glands,
A safety valve T323V is fitted downstream of the auxiliary steam desuperheater but will not result in a turbine shutdown.
and is set at 11.0 bar.
TI TI TI
PIAL Main Auxiliary No.1
To Air Condition
DCS DCS Air Condition Air Condition
Safety Incinerator Waste Incinerator Waste S Unit for
Unit Unit
Manifold Oil Settling Tank Oil Service Tank MSB Room/ECR
From
Control I PX PX PI T424V
P
Air System
10.0/6.0 bar Set at No.2
Pressure Reducing 6.6 Bar T467V
From T423V TI Air Condition
Valve T406V T422V Unit for
10 bar T455V
Steam MSB Room/ECR
S
System T401V T402V T403V
T46
(Section T463V TI
To Deck 4V
2.1.4a)
T404V
Scupper Setting
To For Tank Cleaning HFO Settling Tank
65°C
Atmospheric Engine Casing (P)
For Tank
TI T436V Drain Tank
Cleaning T437V T438V
3rd Deck (Section 2.1.8a) Drains
Low Sulphur FO Tank (S) T414V Inspection Tank T440V
T448V
T426V
TI
To Deoiler TI T441V
Backflushing HFO Bunker Tank
TI Generator Turbine
(Section 2.1.6a) T407V (P)
LO Settling Tank
LO Sludge Tank T425V TI
Engine Room
T410V
Forward
TI For General Service
Bulkhead
For Tank Cleaning 2nd Deck (P) T428V
Purifier Room Generator Engine
T431V
LO out LO Settling Tank Calorifier
Set at T435V
TI
85°C T425V For 2nd
No.2 Lubricating Oil Deck (S) TI
T471V
Purifier Heater T413V T412V Low Sulphur FO T465V
Tank (P) Setting HFO Settling Tank
TI
65°C (S)
T451V
LO out Main
T429V T430V
Set at LO Settling Tank
85°C To Heavy Fuel Oil Transfer T432V
No.1 Lubricating Oil T427V
Purifier Heater Pump and Jacket Heating System
T417V T416V T408V
T433V
For 4th HFO Bunker Tank
For Tank Cleaning Deck (S) T434V (S)
For Tank T470V T439V
Cleaning 4th Deck (P)
TI TI TI T442V
T454V Floor Aft TI
For Sea Chest Engine Room
Oily Bilge Tank Bilge Holding Tank For Sea Chest For Sea Chest Steam Blowing
Main LO T456V Forward TI
T409V Steam Blowing Steam Blowing Bulkhead
Sump Tank
T420V T421V
HFO Overflow Tank
Key
T452V T450V T449V T447V T443V
Desuperheated Steam Sea Water
TI
HSC for For Tank Cleaning
Air Electrical Signal SW Service HSC for LSC for LSC for Floor Forward (P)
& Ballast T444V
Main Main SW Service FO Drain Tank
Condensate To Drain Cooler Instrumentation System (S) Condenser Condenser & Ballast
and Deoiler (S) (Middle) System (P) T446V
Introduction
The system is supplied from the 10.0 bar range auxiliary desuperheater via
pressure control valve T402V and supplies the following services:
• Main and auxiliary air conditioning units
• Fresh water calorifier
• Lubricating oil purifier heaters
• Sea chest de-icing connections
• Heating coils in the following tanks:
• Incinerator waste oil settling and service tanks
• Generator turbines’ lubricating oil settling tank
• Diesel generator engine lubricating oil settling tank
• Main lubricating oil sump tank
• Main lubricating oil settling tank
• Lubricating oil purifiers’ sludge tank
• Heavy fuel oil bunkering and settling tanks
• Heavy fuel oil overflow tank
• Heavy fuel oil drain tank
• Low sulphur fuel oil storage tanks
• Oily bilge tank
• Bilge holding tank
• Drains inspection tank
Two transmitters are used for control, indication and alarm and provide the
measured value for the pressure control loop.
The system can be viewed and access to the valves gained through the graphic
screen T30-407-01 DESUPERHEATED STEAM SYSTEM. The pressure
control valve T402V is accessed by clicking on the faceplate which allows
manual operation if required.
Incinerator
Waste Oil T501V
Settling Tank
Incinerator T539V
Waste Oil TI
T502V From/To
Service Tank
T541V Central FW
Drain Cooler
Cooling System Set at
Main (Section 2.81a) 4.55kg/cm2
Lubricating Oil TI
T503V PI TI
Settling Tank T540V
T549V T548V
From Atomising Burner Sampling Pressure 0.3-3kg/cm2 For
And Blowing Steam Drain Filter PI
Sampling Cooler
Back Deoiler
Inspection Tank (1.5m3) Flush (5.5m3/h)
No.2 Boiler Fuel PI
Oil Heater Flushing Line
T509V
T551V T537V
T515V M-42V
No.1 Boiler Fuel T513V
Oil Heater
T506V T511V
T517V
T514V
T512V From 6 bar For Oil
Low Sulphur Steam System Reservoir Back Key
FO Tank (P) T510V
T516V (Section 2.1.5a) Flushing
Heavy Fuel Oil Fuel Oil Drain Lubricating Oil Main Lubricating Bilge Holding
Overflow Tank Tank Sludge Tank Oil Sump Tank Oily Bilge Tank Tank
f) Close the bypass valve T544V and divert drain returns into f) On completion of the 3rd stage back wash, open the air vent
Oil Content Monitor the deoiler. Close each drain valve on the deoiler as clean cock and drain valve on each stage element and the inlet
Maker: Fellow Kogyo Co. Ltd condensate is observed flowing out of the drain pipe. valve T526V.
No. of sets: 1
g) Clean drains will now flow through the deoiler and out of the g) Close each drain valve when the discharge is clean.
Measuring accuracy: 15ppm every 17 seconds
drain valve T546V to the save-all. Once the drains are observed
Type: Fogas - 1500C to be clean, open the discharge valve T547V to the inspection h) Open the discharge valve T545V and the sample cooler inlet
Capacity: 5.5m3/h tank and close the drain valve. valve T548V and close the bypass valve T544V. Switch on
the oil content monitor.
h) Open the sample cooler inlet and outlet valves and switch on
the oil content monitor. The deoiler is now back in normal use.
The control valve X52V provides 5.0 bar bleed steam pressure control and
make-up to maintain the 1.8 bar exhaust steam system at the designed pressure.
If the control valve X52V fails it will revert to the open position which would
raise the 1.8 bar exhaust steam system to a pressure of 5.0 bar. This would
increase the backpressure on the feed water pump turbine exhausts and the
pressure in the deaerator. However, the deaerator relief valve is set at 3.0 bar,
which will maintain the pressure below the feed water pump turbine exhaust
backpressure trip setting of 4.2 bar. Also, the dump valve X28V to the main
condenser would open and control the pressure at 1.8 bar.
If the control valve fails to the open position, the backpressure on the feed
water pump turbine exhaust may drop and the steam to the deaerator may also
drop, but there will be no immediate effect.
The control valve X28V provides the 1.8 bar exhaust steam pipeline with
pressure relief to the main condenser, to maintain the 1.8 bar exhaust steam
system at the designed pressure. If the control valve X28V fails it will revert to
the closed position and the 4.9/1.8 bar pressure reducing control valve X52V
will try to control the pipeline at 1.8 bar. However, the excessive pressure in
the pipeline will be relieved by the deaerator safety valve, which is set at 3.0
bar and is below the turbine backpressure trip setting of 4.2 bar.
T578V
Distilled Water
Exhaust Steam
Desuperheated Steam
The drains now become part of the auxiliary feed water system (section 2.2.1)
Introduction and are pumped from the atmospheric drain tank by the drain tank pumps,
through the grease extractors, to return to the feed water system via the
Auxiliary Condenser deaerator.
Maker: Donghwa Entec
No. of sets: 1
Type: Tubular
Serial number: C19120-A
The system consists of the following return drains that are from systems
which do not contain hydrocarbon and other contamination, or have passed
through the deoiler and the oil content monitor:
• Drains inspection tank outlet
• Air conditioning heating coils
• Fresh water calorifier heating
• Inert gas generator atomising steam and dryer heater steam
pipeline drain
• Main turbine gland steam supply pipeline drain
• Cargo steam system
• Intermediate pressure (IP) bleed steam pipeline drain
• Fresh water generator heating coils drain
• 5.0 bar pressure range pipeline drain
• 61.5 bar pressure desuperheated steam range pipeline drain
• First stage feed water heater to flash chamber pipeline drain
• Gland steam condenser pipeline drain
• Boiler water analysis unit drain
• Boiler water analysis unit cooling water outlet
• Cargo compressor room return drains
• Feed water system safety valves discharge pressure buffer
chamber drain
The returns do not need cooling and go directly to the atmospheric drain tank,
bypassing the auxiliary condenser. Only the generator turbines’ exhaust and the
1.8 bar exhaust steam pipeline dump, which have been diverted from the main
condenser, are cooled in the auxiliary condenser.
The auxiliary condenser has a pressure switch fitted that will prevent the dump
steam control valve X28V operating if the pressure in the condenser is too
high.
Weather Shield
Funnel
Safety Manifold
Key
Superheated Steam
Steam Drum Safety Valves The safety valve exhaust steam is led away to the funnel top by pipelines
specially constructed so that they are not in contact with the safety valve
Maker: Fukui Seisakusho Co. Ltd
outlet elbow. They are of a larger bore than the safety valve seat and are
Type: Full bore suspended from pipe hangers which allow for:
Opening pressures: 76.5 and 76.0 bar
• Safety valve discharge reaction
Closing pressures: 71.14 and 70.5 bar
• Exhaust pipe vibration
Seat diameter: 38mm
Disc lift: 8.3mm • Relative expansion between the safety valve and the exhaust
pipeline due to temperature change
Relieving capacity: 30,400kg/h
The drains from the exhaust pipelines are directed to the bilge holding tank.
Superheated Steam Outlet Safety Valve
Maker: Fukui Seisakusho Co. Ltd To distinguish between the boiler safety valves’ exhaust and the lower steam
pressure range’s safety valves in the engine room, the exhaust pipelines are led
Type: Full bore to the aft end of the funnel. These systems include the following:
Opening pressures: 63.5 bar
• Deaerator safety valve
Closing pressures: 59.1 bar
Seat diameter: 38mm • 10.0 bar range safety valve
Disc lift: 8.3mm • 6.0 bar range safety valve
Relieving capacity: 18,050kg/h • 15.0 bar range safety valve
• 15.5 bar range safety valve
• 4.9 bar range safety valve
• 3rd stage feed water heater safety valve
• 0.1 bar range safety valve
Issue: 1 Section 2.1.9 - Page 2 of 2
2.2 Condensate and Feed Water Systems
Illustrations
LAH
S153V S154V M102V Atmospheric LS
DCS
M106V M104V Drain Tank
M146V (8m3)
Key
Booster Pump
Condensate M128V LAL
PI PI PI LS DCS
Distilled Water
Condensate 138V
Dump Drain Pump
Air 2 1 Drain Pumps
(80m3/h x 95mth)
(25m3/h x 85mth)
Sea Water
CI CI CI
Electrical Signal
Ion Exchange Unit
HCL (4m3/h) NaOH Instrumentation M101V M105V M103V
To Deck Scupper
The DCS controls the operation of the pumps when in Remote mode at the b) Set the system to now fill and maintain the level in the
The deaerator is situated at a high point in the engine room to provide a suction main switchboard, the operation of the level controllers and also monitors the deaerator. From DCS graphic screen T30-412-01 AUXILIARY
pressure for the feed pumps greater than the saturation pressure of the water pressure, temperature and salinity of the system. The main condensate and CONDENSATE SYSTEM, set the deaerator level control valve
at the suction. This prevents the water boiling at the feed pump suction and drain pumps may be operated in manual or automatic modes. M108V to AUTOMATIC and the ADT level to NORMAL. Set
causing cavitation. the system valves as follows:
If Selector Switch is Changed to Local
Manual operation of each pump is restricted to local start and stop operations
being carried out as required.
LAH
S153V S154V M102V Atmospheric LS
DCS
M106V M104V Drain Tank
M146V (8m3)
Key
Booster Pump
Condensate M128V LAL
PI PI PI LS DCS
Distilled Water
Condensate 138V
Dump Drain Pump
Air 2 1 Drain Pumps
(80m3/h x 95mth)
(25m3/h x 85mth)
Sea Water
CI CI CI
Electrical Signal
Ion Exchange Unit
HCL (4m3/h) NaOH Instrumentation M101V M105V M103V
To Deck Scupper
The condensate will now recirculate back to the condenser until the level in e) Change the dump steam over to the auxiliary condenser.
c) Start one of the condensate drain pumps.
the condenser rises and the recirculation valve closes in.
The level in the deaerator will now begin to rise. As this happens the level in f) Change the 1.8 bar dump steam range over to the auxiliary
h) Open the inlet and outlet valves and close the bypass as condenser.
the ADT drops and it will be necessary to stop the pump periodically until the
required for the following heat exchangers:
ADT catches up due to the smaller bore make-up line.
g) Stop the main engine, shut the steam stop valves, engage
Position Description Valve the turning gear and do not put on the main turbine warming
To Prepare the Main Condenser for Operation Open No.2 evaporator inlet and outlet valves M27V, M28V through steam.
d) Establish the main sea water circulating system through the Close No.2 evaporator bypass valve M12V h) Shut down the gland steam system.
main condenser and lubricating oil cooler (see 2.5.1 Sea Water
Circulating System). Open Gland steam condenser inlet and outlet valves VK19, VK20
i) Allow the main turbine to cool down before stopping the main
Close Gland steam condenser bypass valve VK21 SW circulating pump.
e) Fill the condenser hotwell with distilled water from the distilled
water storage tanks. The valves, M124V and M125V, are Open Ist stage feed heater inlet and outlet valves
j) Stop the main SW circulating pump, jack and lock the main
situated on the tank discharge line after the make-up valve Close Ist stage feed heater bypass valve
condenser inlet and overboard valves.
M120V. It will be necessary to close valve M123V make-up
to the ADT isolating valve. Open the make-up bypass valve
i) Open the services to the following items as required. k) Stop the vacuum pumps if entry is required into the condensate
M122V and allow the condenser hotwell to fill to slightly above
side of the main condenser.
normal level. Observe the ADT level during this operation and
re-open valve M123V to allow make-up to take place. When the Description Valve
If checking for leaking tubes, leave the vacuum pumps on and use cling film
condenser hotwell level is satisfactory, close valves M124V and Evaporator desuperheater spray valves M50V, M51V on the tube plate to locate the damaged tube. This check can also be made
M125V and restore the make-up to normal operation.
Deoiler sample cooler valves M13V, M14V the conventional way, by filling the condensate side with a water/fluorescein
mixture and checking the tube plate with a fluorescent lamp from the sea water
f) From graphic screen T30-412-02 CONDENSATE SYSTEM Boiler chemical feed tank valves side.
set the condenser recirculation valve to AUTOMATIC and the
condenser hotwell level to NORMAL. Boiler water analysis unit for cooling M9V
When using a water/fluorescein mixture, the condenser must be thoroughly
Boiler water analysis unit for sampling
rinsed out before returning to service, in order not to contaminate the boilers.
g) Open the condensate pump suction valves. Start one of the
No.1 and No.2 external desuperheater spray water valves M15V and local
condensate pumps, probably the low duty pump at this stage.
No.1 and No.2 main feed water pump valves (Note: Before entering the sea water or the condensate side of the condenser,
Slowly open the pump discharge valve and allow the pump to
open the doors and use a portable fan to aerate the chamber, leaving
gain suction and discharge into the main condensate line. Mechanical seal cooling/flushing valves M15V and local the forced ventilation in place during the time that personnel are
inside.)
DCS M123V
M12
FW12V FW11V 1V M115V
M39V M113V
FW13V M130V FW14V
M122V M116V M118V
M132V MAKE UP SPILL
M119V M119V
M131V DCS
Control I
M140V P
Air
Distilled Water
Air
Electrical Signal
Ion
Exchange Unit Instrumentation
HCL (4m3/h) NaOH
DCS DCS
M114V
DCS DCS
I I
P P
PI
M M
Set at Set at
From 95.6 bar 3B 20B 26B 1B 1B 26B 20B 3B 95.6 bar
CI PX
Auxiliary Economiser Economiser
TI Condensate Systems
(2.2.1a) 13B
Deaerator M852V 13B M853V
PI
(30m3) DCS
LS
Level for Boiler Boiler
Main Feed Water Gauge 4B 12B 11B 11B 12B 4B Gauge
PIAH PIAH
TI Board PI PX PX
DCS DCS
PX PX PI Board
Pump Turbine
Trip
FS FS
LIAHL RWLI DCS FWR Steam Drum Steam Drum FWR DCS RWLI LIAHL
FS DCS DCS FS
M201V M202V
To
Emergency Boiler Feed Water M69B M69B M69B M69B
Suction From 206V Analysis Unit (2.2.4a) TI
Distilled Water M817V
Tanks
(2.2.2a) 3rd Stage Feed
Water Heater
From Auxiliary Feed Water Line M829V
Chemical
Feed Pump (2.2.4a) TI DPX DPX DPX For DPX
M302V For
M818V Control Control
For For
Main Feed Water Line Spray Water
To Alarm Alarm
To External
Turbine Driven M832V M833V Desuperheaters
Feed Water Pump M804V M802V M808V M806V M814V M812V
Remote Control Turbine Driven
M825V System M803V M801V M807V M805V Boiler M813V M811V From
Feed Water Pumps Condensate
M826V LS PI (140m3/h x 865mth) PI Drains Pump (Section 2.2.1b) Key
M824V S From Electric PI For Boiler Water Filling PX PX PI
Control Motor Driven PS Run Signal PS Run Signal
Air Boiler Feed Water Electrical Signal
M823V System Pump M 810V M816V
(6m3/h x 860mth) PIAH Condensate/HP Feed Water
DCS
DCS
CI PI PI For
Distilled Water
Feed Water
Control Compressed Air
M210V M211V M213V
Instrumentation
DCS DCS
M114V
DCS DCS
I I
P P
PI
M M
Set at Set at
From 95.6 bar 3B 20B 26B 1B 1B 26B 20B 3B 95.6 bar
CI PX
Auxiliary Economiser Economiser
TI Condensate Systems
(2.2.1a) 13B
Deaerator M852V 13B M853V
PI
(30m3) DCS
LS
Level for Boiler Boiler
Main Feed Water Gauge 4B 12B 11B 11B 12B 4B Gauge
PIAH PIAH
TI Board PI PX PX
DCS DCS
PX PX PI Board
Pump Turbine
Trip
FS FS
LIAHL RWLI DCS FWR Steam Drum Steam Drum FWR DCS RWLI LIAHL
FS DCS DCS FS
M201V M202V
To
Emergency Boiler Feed Water M69B M69B M69B M69B
Suction From 206V Analysis Unit (2.2.4a) TI
Distilled Water M817V
Tanks
(2.2.2a) 3rd Stage Feed
Water Heater
From Auxiliary Feed Water Line M829V
Chemical
Feed Pump (2.2.4a) TI DPX DPX DPX For DPX
M302V For
M818V Control Control
For For
Main Feed Water Line Spray Water
To Alarm Alarm
To External
Turbine Driven M832V M833V Desuperheaters
Feed Water Pump M804V M802V M808V M806V M814V M812V
Remote Control Turbine Driven
M825V System M803V M801V M807V M805V Boiler M813V M811V From
Feed Water Pumps Condensate
M826V LS PI (140m3/h x 865mth) PI Drains Pump (Section 2.2.1b) Key
M824V S From Electric PI For Boiler Water Filling PX PX PI
Control Motor Driven PS Run Signal PS Run Signal
Air Boiler Feed Water Electrical Signal
M823V System Pump M 810V M816V
(6m3/h x 860mth) PIAH Condensate/HP Feed Water
DCS
DCS
CI PI PI For
Distilled Water
Feed Water
Control Compressed Air
M210V M211V M213V
Instrumentation
In the event that the steam demand from the boilers is small and the vessel Open Feed pump recirculating controller valves M823V, M825V
is in manoeuvring mode, the feed pump recirculation valve is automatically Closed Feed pump recirculating controller bypass valve M826V
opened.
(Note: The lubricating oil pressure will be zero which would normally cause (Note: If a ‘stop’ command is issued at any time or a trip condition occurs, the
a trip, but the system is arranged to allow a trip reset and pump start feed pump is stopped by stopping the auxiliary LO pump (if running)
before the lubricating oil trip becomes active.) and closing the steam inlet valve.)
d) When all the above conditions are met, the operator may request
a pump start from graphic screen T30-453-01 FEED SYSTEM. With the system now operating normally it is important to make regular checks
The following sequence is started: of the feed pumps paying particular attention to the following:
• The DCS checks that the conditions are correct (see above) • LO level and drainage of water from the sump
• A pulse signal sets a block and passes a continuous signal • Leakage from the mechanical seals
to the ‘Standby’ selector, to ensure that it is set to ‘Manual’ • Correct flow of cooling water to the mechanical seals
(or sets it to ‘Manual’ if not), and to the trip circuit to inhibit
the low LO trip during this starting period. • Offline feed pump is not rotating backwards due to exhaust
leakage
• A pulse signal START command is sent to the auxiliary
LO pump via a gate which inhibits this signal if a stop or
trip command is issued. A timed alarm circuit is initiated
to indicate a failure of the pump to start in a predetermined
time. In this event, the system sends a ‘stop’ command to
the LO pump starter for safety, and resets the start block
thus cancelling the start command. If no further action takes
place the starting of the feed pump will be deemed to have
failed. This situation will remain until reset by the operator.
Under normal conditions i.e. no failure, the LO pump
starts.
M114V
Steam Drum Steam Drum
15B 16B 15B 16B
PI 62B 61B 62B 61B
From
Auxiliary
Condensate Systems
CI PX
(Section 2.2.1a)
TI No.2 Main No.1 Main
Key Port Boiler Starboard Boiler
Deaerator PI
(30m3) DCS
Electrical Signal
From
To
Main Condensate
Distilled Water
Pumps
Make-up/Spill
M203V Line
Sample From
M205V M303V Main Condensate
Pumps (Section 2.2.1a)
M204V Set at
5Bar
M
M206V M901V
M M Hydrazine
Mixing LS
LS LS Tank
Chemical Chemical
(0.3m3) LI
Tank Tank
Emergency LI (0.15m3) (0.15m3) LI
Suction From M902V
Distilled Tanks M302V
To
Turbine Driven
Feed Water Pump TI TI
Remote Control
M TI TI
825V System
M
LS Cooling From
M82 PI PI
M824V S From Chemical Main Condensate
6V Pumps (Section 2.2.1a)
Control Chemical Injection
Air Injection Pumps C C
M823V Pumps (3.5L/h
System
(15L/h x 80 bar) x 8 bar) PH PH PH PH
C C
From
Boiler Feed Water
Pumps Recirculating Hydrazine Injection Unit
To Boiler Water Chemical Injection Unit Boiler Water Analysis Unit
Line
Boiler
Feed Water To Atmospheric Drain Tank
Pumps (Section 2.1.8a)
d) Check the thermometer in the line to ensure that the sample is at b) For bottom blowdown slowly crack open the secondary valve
the correct temperature. A sample taken while the temperature Hydrazine Dosing Unit
M64B. Adjust the secondary valve to control the blowdown
is too high may not be tested satisfactorily, as the test chemicals rate. For a surface blow of the boiler steam drum slowly crack
themselves are only rated at certain temperatures. The hydrazine dosing unit should be operated continuously to maintain a
constant hydrazine reserve with little fluctuation. The capacity of the tank is open the secondary valve M61B. Adjust the secondary valve to
such that a full tank will continuously dose the system for approximately three control the blowdown rate.
e) Once the line has cleared and the temperature is correct, the
bypass valve may be closed and the valve to the test analyser days. The concentration of hydrazine should be varied depending upon the
results of the tests. c) As the blowdown progresses, continually monitor the boiler
units opened. Check individual flow meters to ensure correct water level and ensure this is being maintained and the feed
water flow through the sensors. pump discharge is coping with the extra load.
Dosing Unit Operation
f) Manual samples may be taken from the bypass line. d) When the blowdown is to be stopped, close the secondary and
a) Fill the dosing tank with water from the main condensate
discharge, piped to the filling valve. primary blowdown valves, then the ship’s side valve.
CAUTION
Boiler water samples are taken from the water drum and are therefore at (Note: More frequently, boiler impurities are discharged overboard via the
b) Add the hydrazine to be dosed to the tanks, based on the results
a high pressure and temperature. Great care should be taken whenever scum valves on the steam drum. As this line is relatively small in
of the condensate and boiler tests.
these valves to the sample unit are opened. This must be done slowly. diameter it is easier to control the flow so that this system can be used
c) Open the tank outlet valves, the pump’s discharge primary with the boiler on higher loads. However, it is less effective because a
If any samples are also to be taken from the analyser unit meters, then lot of the water removed is fresh feed having just entered the drum.)
and secondary valves and the boiler drum chemical injection
clean dry flasks with stoppers are to be used. The flask should be filled to
primary and secondary valves. Ensure that the dosing pump
overflowing and sealed to prevent any ingress of oxygen while the flask is WARNING
crossover valve is closed. Open valve M301V on the main
standing waiting testing. Never open the water wall header drain valves with the boiler under
condensate to the deaerator line.
pressure. If possible fit blanks to these lines which are removed only if
Boiler Compound Injection Unit (Note: It is possible to inject the hydrazine into the feed pump recirculation the boiler is shut down and being drained.
line during initial plant flashing. Ensure that after this the hydrazine is
Chemicals are injected into the boiler steam drum under its water level. This injected into the main condensate to the deaerator line. The feed pump
is done so the natural water circulation system within the boiler will move the recirculation valve is closed when the boilers are sufficiently loaded
chemicals around the boiler and ensure an even distribution. and therefore the hydrazine will not enter the feed system if injected
into the recirculation line.
Illustrations
TX TIAH
PI PI DCS L209V
L206V
Intermediate
Bearings TX
L207V
To Lubricating
2 1 Oil Drain Tank
Engine Driven TIAH TIAH TIAH TIAH L208V
Lubricating DCS DCS DCS DCS
Oil Pump PI
TI TI
(150m3/h x 3bar) TIAH TIAH TIAH
TI TI
DCS DCS DCS
Astern
Guard L219V L220V
L216V Valve From/To Central
DPX DPIAH Fresh Water
TX TX TX Operating DCS
PI TX TX Mechanism Cooling System
PI
TX TX (2.8.1a)
TIAH
DCS
L217V L218V
TIAH
DCS TX
TX TX TX
TI TIAH
TX
LP Turbine TX
DCS
TIAH TIAH Astern W67V W65V
DCS DCS TIAH TX
Main Thrust
TX
DCS Manoeuvring DCS
Valve PI PI
Bearing
TIAH Operating TI TI
I
DCS P
From Mechanism
Purifier P
TIAH Ahead Nozzle P
From DCS TIAH Valve Operating L215V L213V
Storage DCS
Mechanism
Tank TIAH
TX No.2 Main No.1 Main
DCS
TX Turbines Turbines
TIAH TX
DCS PI
2 Control LO Cooler LO Cooler
TIAH
TX Air
DCS LS
TX
TX HP Turbine L214V L212V
L47V L53V LO
1 Temperature
TIAH
DCS Control
L204V TX TIAH
Valve
DCS DPX
TX TX TI TI
PS Turning
TIAH
To LO Gear TIAH TIAH TX
DCS
PI PI
Transfer Pump DCS DCS W68V W66
PS Control
and Purifier
Oil Pumps
DPIAH
L201V DCS I DCS
(2.4m3/h x
L48V
TIAH
TX P 15kgcm2)
L202V DCS
P Pressure
PI PI TX TX TX P Key
Control Control
Auxiliary Lubricating Air TIAHL
TI TX
DCS
Fresh Water
2 1 Oil Pumps TIAH TIAH TIAH
FLG DCS DCS DCS
(150m3/h x 3.5bar) Lubricating Oil
LIAHL Air
LX
Main Lubricating DCS
Oil Sump Tank Electrical Signal
(69.4m3) LAL
LS Instrumentation
DCS
To Lubricating
Oil Drain Tank
TX TIAH
PI PI DCS L209V
L206V
Intermediate
Bearings TX
L207V
To Lubricating
2 1 Oil Drain Tank
Engine Driven TIAH TIAH TIAH TIAH L208V
Lubricating DCS DCS DCS DCS
Oil Pump PI
TI TI
(150m3/h x 3bar) TIAH TIAH TIAH
TI TI
DCS DCS DCS
Astern
Guard L219V L220V
L216V Valve From/To Central
DPX DPIAH Fresh Water
TX TX TX Operating DCS
PI TX TX Mechanism Cooling System
PI
TX TX (2.8.1a)
TIAH
DCS
L217V L218V
TIAH
DCS TX
TX TX TX
TI TIAH
TX
LP Turbine TX
DCS
TIAH TIAH Astern W67V W65V
DCS DCS TIAH TX
Main Thrust
TX
DCS Manoeuvring DCS
Valve PI PI
Bearing
TIAH Operating TI TI
I
DCS P
From Mechanism
Purifier P
TIAH Ahead Nozzle P
From DCS TIAH Valve Operating L215V L213V
Storage DCS
Mechanism
Tank TIAH
TX No.2 Main No.1 Main
DCS
TX Turbines Turbines
TIAH
DCS
TX
PI
2 Control LO Cooler LO Cooler
TIAH
TX Air
DCS LS
TX
TX HP Turbine L214V L212V
L47V L53V LO
1 Temperature
TIAH
DCS Control
L204V TX TIAH
Valve
DCS DPX
TX TX TI TI
PS Turning
TIAH
To LO Gear TIAH TIAH TX
DCS
PI PI
Transfer Pump DCS DCS W68V W66
PS Control
and Purifier
Oil Pumps
DPIAH
L201V DCS I DCS
(2.4m3/h x
L48V
TIAH
TX P 15kgcm2)
L202V DCS
P Pressure
PI PI TX TX TX Control P
Control Key
Auxiliary Lubricating Air TIAHL
TI TX Fresh Water
2 1 Oil Pumps TIAH TIAH TIAH DCS
FLG DCS DCS DCS
(150m3/h x 3.5bar) Lubricating Oil
LIAHL Air
LX
Main Lubricating DCS
Oil Sump Tank Electrical Signal
(69.4m3) LAL
LS Instrumentation
DCS
To Lubricating
Oil Drain Tank
(Note: It is assumed that all turbine and gearbox system lubricating valves are
left open.)
(Note: If the oil temperature of the oil is low, steam heating must be applied
whilst the oil is circulating in order to raise the temperature to an
acceptable level.)
(Note: When the turbine is operating at full sea conditions the main LO pump
will be supplying LO to the system, the running auxiliary LO pump
will be stopped and the LO pressure control valve will be fully closed.
The standby LO pump remains in standby mode.)
During operation of the main LO system overflow from the gravity tank may
be observed at the overflow sight glass situated near the gravity tank. The
gravity tank inlet valve L209V is adjusted and locked in position, to maintain
the LO system pressure and ensure that there is a quantity of oil overflowing
from the gravity tank.
Stern Tube
Lubricating Oil
Gravity Tank
(100 Litres) LAL
Key LS
DCS
L331V
TI TI-31
PI PI-31
LAL To be closed in L324V
DCS
Stern Tube Lubricating
dry dock Oil Pumps 1 & 2
L305V
(Stern Tube Bearing) (1.0m3/h x 2.5 bar)
LS LAHL
TIAH LS L304V L302V
Lubricating L340V DCS
DCS
Oil Forward Aft Seal
PI PI 4-DPS
Seal Tank Lubricating -112
(20 Litres) TX
L333V Oil Tank
2 1 DPS DPS
(50 Litres)
4-DPS
L334V CI CI -111
L335V
TIAH
DCS
L303V L301V
(Stern Tube
Forward To be closed in
1 2 3R 3 L306V
Bearing) case of damage of
Stern Tube sealing ring no.3 L325V
1 2 3R 3
To Oily Bilge Tank
To LO Purifier Supply Pump (Section 2.6.1)
or LO Transfer Pump
(Sections 2.3.3a and 2.3.4a)
From
Main LO
L51V Storage Tank
(Section 2.3.4a)
Stern Tube
Lubricating Oil
Gravity Tank
(100 Litres) LAL
Key LS
DCS
L331V
TI TI-31
PI PI-31
LAL
DCS
To be closed in Stern Tube Lubricating L324V
dry dock
L305V Oil Pumps 1 & 2
(Stern Tube Bearing) (1.0m3/h x 2.5 bar)
LS LAHL
TIAH LS L304V L302V
Lubricating DCS L340V DCS
Oil Forward Aft Seal
PI PI 4-DPS
Seal Tank Lubricating -112
(20 Litres) TX
L333V Oil Tank
2 1 DPS DPS
(50 Litres)
4-DPS
L334V CI CI -111
L335V
TIAH
DCS
L303V L301V
(Stern Tube
Forward
1 2 3R 3 To be closed in L306V
Bearing) case of damage of
Stern Tube sealing ring no.3 L325V
1 2 3R 3
To Oily Bilge Tank
To LO Purifier Supply Pump (Section 2.6.1)
or LO Transfer Pump
(Sections 2.3.3a and 2.3.4a)
From
Main LO
L51V Storage Tank
(Section 2.3.4a)
c) Set valves as in the following table: The stern tube LO system is now operational and ready for the ship to
put to sea.
Position Description Valve
Oil samples should be taken for analysis at regular intervals.
Open No.1 stern tube LO pump suction valve L301V
Open No.1 stern tube LO pump discharge valve L302V System temperatures, tank level alarms and the pump operating modes are
displayed on the graphic screen T30-446-01.
Open No.2 stern tube LO pump suction valve L303V
Open No.2 stern tube LO pump discharge valve L304V The differential across the pump filters are to be checked during rounds and if
found to be high, the pumps are to be changed over. The filter is then isolated
Open Stern tube LO cooler inlet valve L308V
and cleaned immediately.
Open Stern tube LO cooler outlet valve L309V
Closed Stern tube LO cooler bypass valve L310V
Open Stern tube LO cooler FW cooling inlet valve W117V
Open Stern tube LO cooler FW cooling outlet valve W118V
As required Gravity tank three-way valve L331V
Open Stern tube LO inlet valves L339V, L327V
Closed LO inlet chamber drain valve L338V
Locked closed LO sample valve L337V
Locked closed Stern tube LO drain valve L336V
Open After seal LO tank inlet valve L334V
Open After seal LO tank outlet valve L333V
Closed After seal LO tank outlet valve to lip seals L335V
Closed After seal LO tank filling valve L305V
Closed After seal LO vent valve L340V
d) Set the three-way valve L331V for the fully loaded or ballast
operating condition. Open the valve L311V when in ballast and
close when loaded.
TI TI PI TI TI PI
The lubricating oil purifiers are supplied by dedicated lubricating oil supply i) Check that the No.1 LO purifier supply pump suction strainer is
b) Ensure valves in the purifying system are closed.
pumps, one pump for each purifier, which pass the lubricating oil through a clean.
heater before it enters the purifier. The steam for the heaters is supplied from c) Open the control air valve A136V and operating fresh water
the 6 bar range. j) Start the No.1 LO purifier supply pump locally. Oil will bypass
supply valve D101V, situated below the plates on the outboard
the purifier by means of the three-way valve. It will be drawn
side.
from the main LO sump tank and flow back to the main LO
sump tank.
TI TI PI TI TI PI
r) Check that the purifier is operating correctly and that there is Open Outlet valve from main LO sump tank L48V Open Purifier heater bypass valve L105V
adequate throughput. Closed Main LO settling tank quick closing outlet valve L32V Open Control air valve A136V
Open No.1 purifier LO supply pump suction valve from Open Operating water valve D101V
s) Ensure that there is no abnormal discharge from the sludge
discharge. the LO sump tanks and main settling tank L102V Operational No.1 purifier three-way valve
Closed Crossover suction gate valve L118V Open Line valve to LO settling tanks and generator sump L111V
t) Check that LO is being drawn from the LO circulation tank and
Closed No.1 purifier LO supply pump suction valve from Open Line valve to LO settling tanks L41V
being returned to the LO circulation tank.
the generator LO system L101V
Open Main LO settling tank inlet valve L29V
Open No.1 purifier supply pump discharge valve L104V
To Stop the Purifier : Closed Return line valve to LO deaerator tank L112V
Open No.1 main LO purifier steam heater inlet valve L124V
a) Close the steam valve T416V to the heater. Closed Main LO sump tank inlet valve from purifier L53V
Open No.1 main LO purifier steam heater outlet valve L106V
b) Press the STOP pushbutton on the control panel. Closed Deaerator outlet valve to LO drain tank L113V
Open Purifier heater bypass valve L105V
Closed Crossover valve between No.1 and No.2 purifiers L110V
The purifier will commence the shut down sequence and then stop. Operational No.1 purifier three-way valve
Open No.1 purifier clean oil outlet valve
Open Line valve to LO settling tanks and generator sump L111V
c) Shut off the operating water supply valve D101V (only if the
other purifier is not in use). Open Line valve to LO settling tanks L41V
Open Main LO settling tank inlet valve L29V
TI TI PI TI TI PI
Lubricating oil may be taken from the generator turbine sumps or the generator Open No.2 main LO purifier steam heater inlet valve L109V
turbine LO settling tank using No.1 LO purifier. Purified oil may be returned Lubricating oil from the generator turbine LO settling tank may be returned Open No.2 main LO purifier steam heater outlet valve L121V
either to the generator turbine sump from which it has been taken, to the to a generator sump via No.1 purifier. The procedure is the same as for using
No.1 purifier to purify LO from No.1 generator turbine sump back to the same Open Purifier heater bypass valve L120V
generator engine LO settling tank or to the main LO settling tank.
sump except for the valve settings. Operational No.2 purifier three-way valve
The procedure is the same as that for purifying LO from the main sump back
If LO was to be taken from the generator turbine LO settling tank, the tank Closed Line valve to generator engine LO settling tank L127V
to the main sump apart from the setting of the valves. The setting of the valves
below is for purifying LO from No.1 generator turbine sump using No.1 LO quick-closing outlet valve L17V would need to be open and the outlet valve Open Line valve to generator engine LO sump tanks L125V
purifier and returning the purified oil back to No.1 generator turbine sump. from the generator turbine sump valve closed (L37V in the above example).
Closed Inlet valve to generator engine LO storage tank L3V
If the remaining valves were set as above, LO would be purified from the
Position Description Valve generator turbine LO settling tank to the sump of No.1 generator turbine. Open Inlet valve to generator engine LO sump tank L19V
Closed Outlet valve from main LO sump tank L48V Closed Crossover discharge valve between No.1 and
No.1 LO purifier may be used for purifying LO from and to the stern tube LO No.2 purifiers L110V
Closed Main LO settling tank quick-closing outlet valve L32V sump tank. The procedure is the same as for other operations except for the
valve settings. No.1 purifier supply pump suction valve has to be open together Closed Crossover suction valve between No.1 and
Closed No.1 purifier LO supply pump suction valve from with the suction valve L51V from the stern tube LO sump tank. No.2 purifiers L118V
the LO sump tanks and main settling tank L102V
Open No.2 purifier clean oil outlet valve
Closed Crossover suction gate valve L118V With these valves set the No.1 purifier pump would supply LO from the stern
tube sump tank. In order to return LO to the stern tube LO sump tank, the line
Open No.1 purifier LO supply pump suction valve from
valve to the settling tanks and generators L111V must be open, together with The purifier is operated as for No.1 purifier with LO drawn from the generator
the generator system L101V
the stern tube LO sump tank inlet valve L52V. engine LO settling tank and passed to the sump of generator engine.
Open No.1 generator turbine sump outlet valve L37V
To purify oil from the LO drain tank the LO drain tank suction valve L49V and
Closed No.2 generator turbine sump outlet valve L36V Operation of No.2 Lubricating Oil Purifier the purifier LO supply pump suction valve L117V must be open.
Open No.1 purifier supply pump discharge valve L104V
The previous descriptions have related to No.1 LO purifier which can be The DCS graphic display screen T30-417-01 for the LO purifying system
Open No.1 main LO purifier steam heater inlet valve L124V operated on the main turbine and generator turbine LO systems. provides information regarding the system temperatures and alarms. The
Open No.1 main LO purifier steam heater outlet valve L106V purifiers can be shut down from the screen by clicking on the SHUTDOWN
No.2 LO purifier is used for the generator engine and stern tube LO systems soft key, which is the only operation which can be conducted remotely.
Open Purifier heater bypass valve L105V
and the LO drain tank. The purifier is identical to No.1 LO purifier and its
Open Control air valve A136V operation and control are the same. The description of the operation of No.2
Open Operating water valve D101V purifier is the same as for No.1 purifier except for the setting of valves. The Procedure for Purifying the Stern Tube Lubricating Oil Sump
example below gives the valve settings for purifying LO from the generator in Port using the No.2 Lubricating Oil Purifier
Operational No.1 purifier three-way valve engine LO settling tank to the generator engine LO sump tank.
Open Line valve to LO settling tanks and generator sump L111V To ensure that the stern tube LO remains in a clean condition, the LO is
Position Description Valve purified at regular intervals when in a loading port.
Open Line valve to the generator turbine LO system L42V
Open Quick-closing outlet valve from generator engine
Open No.1 generator turbine sump inlet valve L18V Set up the valves as follows:
LO settling tank L6V
Closed No.2 generator turbine sump inlet valve L20V
Closed Generator engine sump outlet valve L21V a) Open suction valve L51V from the stern tube sump tank.
Closed Line valve to LO settling tanks L41V
Open No.2 purifier LO supply pump suction valve from
Closed Main LO settling tank inlet valve L29V the generator engine system L116V b) Ensure that the main LO settling tank valve L32V and the main
engine LO sump tank valve L48V are closed and the blank is
Closed Return line valve to LO deaeration tank L112V Closed No.2 purifier LO supply pump suction valve from correctly fitted in the pipeline.
Closed Main LO sump tank inlet valve from purifier L53V the stern tube system L108V
Locked closed No.2 purifier LO supply pump suction valve from c) Open the No.2 purifier supply pump suction valve L108V.
Closed Deaeration outlet valve to LO drain tank L113V
the LO drain tank L117V
Closed Crossover valve between No.1 and No.2 purifiers L110V
TI TI PI TI TI PI
f) Crack open the heater bypass valve L120V to regulate the To Stop the Purifier
flow.
a) Close the steam valve T412V to the heater.
g) Open the control air valve A136V and the operating water valve
D101V b) Press the STOP pushbutton on the control panel.
h) Confirm that the inlet valve to the purifier three-way valve is The purifier will commence the shut down sequence and then stop.
open.
c) Shut off the operating water supply valve D101V (only if the
i) Open the clean oil discharge valve to the purifier. other purifier is not in use).
j) Ensure that the following valves are CLOSED: Allow the supply pump to continue circulating LO through the heater and
back to the sump for approximately one hour to prevent ‘coke’ build up in the
• Cross-connection gate valve L110V, to prevent LO from the heater.
No.1 purifier system going into the discharge line to the diesel
generator engine LO system d) Switch off power to the purifier motor.
• Purifier discharge valve L111V, to the turbine generators LO
sumps, settling tank and storage tank e) Close the clean oil outlet valve.
• Deaeration tank outlet valve L113V to the LO drain tank
f) Stop the supply pump and close the stern tube LO sump suction
• Main engine LO sump filling valves L47V and L53V situated valve L51V.
under plates forward of the supply pumps
• Cross connection gate valve L118V to prevent suction from the g) Close stern tube LO sump inlet valve L52V.
diesel generator engine LO system
h) When the purifier has stopped, apply the brake and dismantle
k) Open the purified oil inlet valve L112V into the deaeration for cleaning if required.
tank.
(Note: Before operating the purifier on another LO system, it is essential that
l) Open the stern tube filling valve L52V. the purifier pipelines are drained of stern tube oil. This can be done
by opening the drain plug on the supply pump suction strainer before
m) Start the LO purifier supply pump on the local pushbutton. closing the pump discharge valve.)
Oil will now be drawn from the stern tube LO tank and returned to the stern
tube LO sump tank.
n) Slowly open the condensate drain valve T534V and the steam
supply valve T412V on the No.2 LO purifier heater.
p) Confirm that the bowl closes under the action of the operating
water.
LAH
DCS
Key
L1V L4V L29V L30V L33V
L10V L11V L14V
LAH Lubricating Oil
Generator LS DCS
Generator LS LS Main LO Main LO Air
Engine LO Generator Turbine LO Generator Turbine LO L15V
Engine LO LAH LS
LAH Settling Tank Storage Tank
Settling Tank L5V L12V Storage Tank Settling Tank (16.5m3) DCS L31V (98.5m3) (98.4m3)
Storage Tank (16.0m3) DCS (16.3m3) Electrical Signal
L2V (20.4m3) L16V 4-LS-25 From Deaeration L34V
Instrumentation
Tank Vent
(2.3.3a)
L3V L6V L13V L17V L32V L35V
L28V
From No.1
L7V LO Purifier L39V
(2.3.3a) L41V
To Bilge Shore Connection
(2.6.1a)
L42V
L58V
From No.2 LO L27V
Purifier (2.3.3a) L25V L26V L40V
From
No.2 LO
PI
Purifier (2.3.3a)
Lubricating Oil
LAL Transfer Pump
LAL
DCS DCS (5m3/h x 4bar)
L20V L18V CI No.1 LO No.2 LO No.3 LO Clean Oil
Daily Tank Daily Tank Daily Tank Tank
LS LS (0.2m3) (0.2m3) (0.2m3) (0.6m3)
No.2 GT No.1 GT L46V L43V
LO Sump Tank LO Sump Tank L45V L44V
L50V
L36V L37V L22V L23V L24V
To No.1 LO Purifier
Supply Pump (2.3.3a) L59V
L60V
To Oily Bilge
(Section 2.6.1a) L54V
From No.1 LO Purifier
L52V
To (2.3.3a) L51V
LAL From LO Purifier No.1 LO
DCS Heater and Coaming To No.2 LO Purifier Supply Purifier Supply
From LO Deaeration Tank Stern Tube
Drain (2.3.3a) Pump (2.3.3a) Pump (2.3.3a)
( 2.3.3a) LO Sump
Gen. Eng. LS L47V L53V Tank
LO Sump From Main LO Gravity Tank To No.1 LO Purifier Supply (7.9m3)
Tank Coaming Drain ( 2.3.1a) Pump (2.3.3a)
L19V L21V L48V
From Main Turbine LO Cooler
and Main Turbine LO L49V Main LO
Coaming Drain (2.3.1a) Sump Tank
From Auxiliary LO
LS
LAH (69.5m3)
LO Drain DCS To No.2 LO Purifier Supply Pump Discharge Line
To Fuel Oil Tank (0.5m3) Pump (2.3.3a) Drain (2.3.1a)
Drain Tank
No.3 LO daily tank 0.2 Location Valve LO transfer pump suction valves from stern tube sump tank L24V, L51V
Clean oil tank 0.6 Main LO and stern tube LO system L24V Turn the spectacle flange in the pipeline
LO drain tank L50V
All outlet valves from large LO storage and settling tanks in the engine room Generator engine LO system L23V From Main Lubricating Oil Settling and Storage Tanks
are remote quick-closing valves with a collapsible bridge, which can be Generator turbine LO system L22V Description Valve
operated from the ship's control station. After being tripped the valves must
be reset locally. Each tank is also fitted with a self-closing test cock to test for LO transfer pump suction from main LO settling tank L24V, L32V
the presence of water and to drain any water present. Tundishes under the self- The system valves in each case allows for suction from the relevant sump tanks, LO transfer pump suction from main LO storage tank L24V, L35V, L39V
closing test cock drain any test liquid to the lubricating oil drain tank. the storage tank and the settling tank, with those tank valves being open.
LAH
DCS
Key
L1V L4V L29V L30V L33V
L10V L11V L14V
LAH Lubricating Oil
Generator LS DCS
Generator LS LS Main LO Main LO Air
Engine LO Generator Turbine LO Generator Turbine LO L15V
Engine LO LAH LS
LAH Settling Tank Storage Tank
Settling Tank L5V L12V Storage Tank Settling Tank (16.5m3) DCS L31V (98.5m3) (98.4m3)
Storage Tank (16.0m3) DCS (16.3m3) Electrical Signal
L2V (20.4m3) L16V 4-LS-25 From Deaeration L34V
Instrumentation
Tank Vent
(2.3.3a)
L3V L6V L13V L17V L32V L35V
L28V
From No.1
L7V LO Purifier L39V
(2.3.3a) L41V
To Bilge Shore Connection
(2.6.1a)
L42V
L58V
From No.2 LO L27V
Purifier (2.3.3a) L25V L26V L40V
From
No.2 LO
PI
Purifier (2.3.3a)
Lubricating Oil
LAL Transfer Pump
LAL
DCS DCS (5m3/h x 4bar)
L20V L18V CI No.1 LO No.2 LO No.3 LO Clean Oil
Daily Tank Daily Tank Daily Tank Tank
LS LS (0.2m3) (0.2m3) (0.2m3) (0.6m3)
No.2 GT No.1 GT L46V L43V
LO Sump Tank LO Sump Tank L45V L44V
L50V
L36V L37V L22V L23V L24V
To No.1 LO Purifier
Supply Pump (2.3.3a) L59V
L60V
To Oily Bilge
(Section 2.6.1a) L54V
From No.1 LO Purifier
L52V
To (2.3.3a) L51V
LAL From LO Purifier No.1 LO
DCS Heater and Coaming To No.2 LO Purifier Supply Purifier Supply
From LO Deaeration Tank Stern Tube
Drain (2.3.3a) Pump (2.3.3a) Pump (2.3.3a)
( 2.3.3a) LO Sump
Gen. Eng. LS L47V L53V Tank
LO Sump From Main LO Gravity Tank To No.1 LO Purifier Supply (7.9m3)
Tank Coaming Drain ( 2.3.1a) Pump (2.3.3a)
L19V L21V L48V
From Main Turbine LO Cooler
and Main Turbine LO L49V Main LO
Coaming Drain (2.3.1a) Sump Tank
From Auxiliary LO
LS
LAH (69.5m3)
LO Drain DCS To No.2 LO Purifier Supply Pump Discharge Line
To Fuel Oil Tank (0.5m3) Pump (2.3.3a) Drain (2.3.1a)
Drain Tank
c) When the required quantity of oil has been transferred, close all
Main Lubricating Oil System valves.
Transferring oil from the LO storage and settling tanks to the main LO sump,
the stern tube LO sump tank and manual oiling valve: d) Check and record the levels in all LO tanks and record the
amount of oil transferred in the Oil Record Book together with
the date, time and personnel involved.
Illustrations
Bu
nk
10,000 er 10,000 10,000
Fu
e lO
il
5,000 5,000 5,000
IF
- 30
4 4 4
FO08V
FO28V FO & GO Drain Transfer Pipe Bosun's Store
FO09V FO07V
Steering Gear
Room Fuel Oil From FO
Under Deck Tank (S) Tank (P)
Aft Peak Passageway FO06V
Tank
Engine Room
FO05V
2
FO04V FO03V
Stern Tube No.1 Water
Cooling Side Water Side Water Ballast Tank (C) 1
Ballast Tank Ballast Tank Fore Peak
Water Tank FO02V FO01V
Void (P) (S) Tank
Pipe Duct
Pipe Duct
FO06V
Fore Peak
Engine Room No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank 2 1
Steering Gear Tank
Room Forward Fuel
Oil Tank (S)
FO08V
FO28V FO & GO Drain Transfer Pipe Bosun's Store
FO09V FO07V
Steering Gear
Room Fuel Oil From FO
Under Deck Tank (S) Tank (P)
Aft Peak Passageway FO06V
Tank
Engine Room
FO05V
2
FO04V FO03V
Stern Tube No.1 Water
Cooling Side Water Side Water Ballast Tank (C) 1
Ballast Tank Ballast Tank Fore Peak
Water Tank FO02V FO01V
Void (P) (S) Tank
Pipe Duct
Pipe Duct
FO06V
Fore Peak
Engine Room No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank 2 1
Steering Gear Tank
Room Forward Fuel
Oil Tank (S)
j) Check that FO is being correctly transferred from the required g) Stop the pump from the pump faceplate when the required f) At the DCS graphic screen T30-415-02 open the filling valve
HFO bunker tank to the designated FO settling tank. quantity of HFO has been transferred. for the bunker tank to which HFO is to be pumped, by clicking
on the valve icon to bring up the valve faceplate and then
k) When the required amount of oil has been transferred stop (Note: This operation requires manual control as the automatic pump stop clicking on the OPEN soft key. If HFO is being taken from the
the pump from the screen faceplate by clicking on STOP. only works with the FO transfer pump.) port tank it will be pumped to the starboard tank, in which case
Alternatively the pump can be allowed to stop automatically valve FO27V must be opened. If HFO is being taken from the
when the tank high level switch is activated. h) Close all system valves and lock the crossover valves closed. starboard tank then it will be pumped to the port tank and valve
FO28V must be opened.
l) Close all tank suction and filling line valves at the end of the i) Record the oil transfer in the Oil Record Book.
operation using their screen faceplates. g) Check the quantity of HFO to be transferred and check that the
CAUTION receiving tank has sufficient capacity.
(Note: The manually operated valves may remain open unless oil is to be Ensure that all fuel oil is flushed out of the gas oil transfer pump prior to
transferred from tanks other than the HFO bunker tanks.) restoring it to gas oil service. This can be achieved by opening the gas oil h) Start the HFO transfer pump at the pump faceplate in the DCS
suction and pumping for a few moments with a discharge to the fuel oil graphic screen T30-415-01.
m) Record the oil transfer in the Oil Record Book. tanks open. Before starting the pump to transfer gas oil, make absolutely
sure that all discharges to the fuel oil system are securely closed. i) When the required quantity of HFO has been transferred stop
the pump at the pump faceplate and close all valves which
Procedure for the Transfer of Heavy Fuel Oil using the Gas had been opened.
Procedure for Transferring Heavy Fuel Oil from the Port to
Oil Transfer Pump Starboard Bunker Tanks, or Vice Versa j) Record the oil transfer in the Oil Record Book.
a) Open the crossover suction valve F10V and the crossover a) Open the HFO transfer pump suction valve F5V and the
discharge valve F11V. discharge valve F12V. Procedure for Transferring Heavy Fuel Oil from the Aft
b) Close the gas oil transfer pump suction valve F32V and
Bunker Tanks to the Forward Fuel Oil Storage Tanks
b) At the DCS graphic screen T30-415-01 close the HFO settling
discharge valves F33V, F34V and F48V. tank filling valves F13V and F15V by calling up the valve Heavy fuel oil may be transferred from the aft bunker tanks to the forward FO
faceplates and clicking on the CLOSE soft keys if the valves storage tanks if required. The procedure is similar to that for transferring HFO
c) Ensure that the FO transfer pump discharge valve F12V is open are open. between the aft bunker tanks as described in the previous procedure steps a) to
together with the suction valve from the selected HFO tank.
j) inclusive except for step f). Instead of opening the filling valves for the aft
c) Open the HFO bunker tank quick-closing valve for the tank from bunker tanks the filling valves for the forward bunker tanks would be opened.
d) At the aft FO storage and transfer system DCS graphic screen which HFO is to be taken, F1V for the starboard bunker tank For the port forward storage tank valve FO09V would be opened at DCS
T30-415-01, open the filling valve for the port or starboard and F3V for the port bunker tank. These valves are normally screen T30-415-02 and for the forward starboard storage tank valve FO08V
HFO settling tank, whichever is to be filled. This is done by open as control of the flow of oil from the tank is controlled by would be opened.
clicking on the valve icon to bring up the valve faceplate and the remotely operated line valve F2V for the starboard tank and
then clicking on the OPEN soft key of the selected valve to F4V from the port tank.
open the valve. Procedure for Transferring Oil from the Fuel Oil Overflow
d) At the DCS graphic screen T30-415-01 open the line suction Tank to the Heavy Fuel Oil Settling Tank
e) At the a DCS graphic screen T30-415-01 open the line suction valve for the tank from which oil is to be taken, by calling up
valve from the port or starboard aft HFO bunker tank, from the valve faceplate and clicking on the OPEN soft key. a) Check the amount of fuel to be transferred and ensure that the
which HFO is to be taken. This is done by clicking on the valve settling tank has sufficient capacity.
icon to bring up the valve faceplate and then clicking on the
OPEN soft key of the selected valve to open the valve. b) Set the HFO transfer pump to operate remotely and manually
from the DCS graphic screen T30-415-01.
Open No.1 boiler FO heater inlet valve F221V Open Boiler FO supply system return valves F189B Open Port HFO settling tank quick-closing outlet valve F203V
Open No.1 boiler FO heater outlet valve F223V Closed Supply from the generator gas oil service tank F206V/F207V
Open No.2 boiler FO heater inlet valve F222V f) Select both boiler FO pumps for remote mode at their local Open Boiler FO pump suction from HFO tanks F205V
selector switches. Open Return line valve to HFO tanks F248V
Open No.2 boiler FO heater outlet valve F224V
Closed Boiler FO heater bypass valve F225V g) At the DCS screen T30-452-01 start one of the boiler FO pumps
c) Start the duty boiler FO pump manually from the DCS screen
manually. Gas oil from the generator engine gas oil tank will be
Open Viscorator inlet valve F232V and circulate heated HFO from the port HFO setting tank. Gas
circulated around the system and recirculated back to the pump
oil in the pump and heater system will flow to the port HFO
Open Viscorator outlet valve F233V suction via valve F237V and the FO return pipe. Select the
settling tank via valve F248V and the open tank filling valve.
Closed Viscorator bypass valve F234V other pump in automatic mode at the DCS screen. This pump
The amount of gas oil is small compared with the amount of
will now act as the standby pump and will cut in automatically
Open Recirculation line valve F237V HFO in the tank and so the dilution effect is negligible.
should the duty pump fail to maintain the desired fuel system
Closed Line return valve to HFO tanks F248V pressure.
d) Gradually supply steam, initially under manual control, to
Open Inlet valve to port HFO settling tank F252V the boiler FO heaters. As the viscorator output steadies, the
The FO return pipe overflows to one of the HFO settling tanks and the inlet
temperature control may be placed in automatic mode..
Closed Inlet valve to starboard HFO settling tank F251V valve to the HFO tank which is in use or to be used must be open. In this case
it will be the port tank which is to be used for supplying HFO to the boiler and
Open FO return pipe pressure release regulating valve F230V e) The boiler fuel oil lines may be purged when the boiler FO
so the inlet valve F252V to that tank must be open. When the boiler control
pump and heater system is being circulated with hot HFO.
Operational FO return pipe pressure release valve F250V system is actuated in order to commence firing on gas oil, the controlled valves
When the boiler control is activated to initiate the flashing
in the FO supply pipes F220B will open and gas oil will flow to the burner
procedure, the valves F220B and F221B will be opened and
supply line, allowing the boiler to be flashed.
No.1 Main Boiler Fuel Oil System heated HFO will flow to the boiler burners. The gas oil in the
lines will be displaced to the operating HFO settling tank.
Open FO supply control valve inlet valve F238V Operation of the burner control system is described in section 3.3.3.
Manufacturer’s instructions regarding the procedure for raising steam from
Open FO supply control valve outlet valve F239V f) When the entire boiler fuel supply system is at the same
cold must be followed precisely.
temperature, the line return valve F248V to the HFO tanks can
Closed FO supply control valve bypass valve F240V
be closed and the boiler may be flashed up on HFO. Atomising
When the boiler has raised steam to sufficient pressure using gas oil, heating
Open Flow meter inlet valve F401V air must be used initially in order to ensure that all gas oil
steam will be available for tank heating, steam trace heating and for the boiler
has been burned. The change to atomising steam can be made
Open Flow meter outlet valve F402V FO heaters. Heavy fuel oil in the settling and bunker tanks must be heated to
when only HFO is reaching the burners.
Closed Flow meter bypass valve F403V the correct temperature to allow for pumping.
Closed Line recirculation valve back to settling tank F244V g) Replace the spectacle blank in the supply line from the generator
WARNING
engine gas oil tank which is located between valves F206V and
Open Boiler burner fuel oil supply valve F273B When using gas oil as the fuel, only atomising air must be used.
F207V.
Open Boiler fuel oil supply system return valve F189B
Procedure for Changing the Boiler Fuel Oil Supply System h) When gas burning commences the burning of fuel oil is reduced
from Gas Oil to Heavy Fuel Oil and may be shut off completely if sufficient gas is available. In
No.2 Main Boiler Fuel Oil System the event of loss of gas during dual firing or 100% gas firing
The description assumes that HFO will be taken from the port HFO settling there is automatic changeover to oil firing. For this reason the
Open FO supply control valve inlet valve F241V
tank and overflow/returns will pass back to that tank. HFO system must be kept in a warmed through condition.
Open FO supply control valve outlet valve F242V
(Note: If the port boiler fails to fire on gas after a shutdown, the starboard l) Select the M icon and double click to start the compressor
boiler will need to be shut down and purged to allow the port boiler to motor.
be reset for gas firing.)
m) The compressor was shutdown in manual mode, so click on
c) With gas available to the system, select DCS screen T30-452- the L/D master icon and on the resulting faceplate, change the
04 PORT BOILER BURNER MANAGEMENT for automatic MAN to AUTO to change over automatic control.
operation of the system from the burner management system.
The gas/FO ratio is now increased in increments of 5% by increasing the
d) Click on the key RESET GAS FIRING and click the ON key. Estimated Natural Boil-Off (ESTIM NBO).
A nitrogen pre-purge will operate to ensure that there are no
pockets of gas in the burner system. n) This can be controlled via the DCS screen T30-452-13 BOILER
OVERVIEW, by clicking on the NBO SELECT icon and
e) Once the purge has been completed click on the gas burner body clicking on MAN. The ESTIM NBO % can then be increased
and the burner will operate. This can be observed via the DCS gradually until a minimum FO consumption of 400kg/h is
screen T30-452-13 BOILER OVERVIEW, which shows the achieved.
burner flames.
As gas demand increases, the LD compressor control loop will open the guide
f) The starboard boiler is prepared for gas burning in a similar vanes up to 50%, the optimum vane position for responsive control, thereafter
way, except the purge sequence has already been carried out it will increase the speed of the compressor to meet the gas demand.
when preparing the port boiler.
(Note: Below a minimum FO consumption of 400kg/h the FO control will not
g) Select DCS screen T30-452-03 STARBOARD BOILER increase the FO to respond the any increase in boiler load.)
BURNER MANAGEMENT for automatic operation of the
system from the burner management system. o) When the burning of gas ends, the automatic nitrogen purge
system operates. This replaces the combustible gas in the
h) Click on the key RESET GAS FIRING and click the ON key. pipework from the master gas valve to the burners with an inert
This time nitrogen pre-purge will not operate. gas.
i) Click on the gas burner body and the burner will operate. This
can be observed via the DCS screen T30-452-13 BOILER
OVERVIEW, which shows the burner flames.
GENERATOR ENGINE
PI CI Generator Engine
Finned Gas Oil
2 Tube Service Tank
F119V Pipe (49.1m3)
F120V
Gas Oil Feed Pumps High Pressure Near 2nd Deck
(2.96m3 x 4kg/cm2) Pipe Cylinder 1 Cylinder 8
F106V
Key
Gas Oil
Air
Electrical Signal
Instrumentation
The gas oil return pipe overflows to the generator engine gas oil service
tank.
Leakage from the generator engine fuel system flows to the FO drain tank.
The generator engine gas oil service tank can also supply the boiler FO pumps
should it be necessary to operate the boilers on gas oil.
The generator engine fuel supply system is manual and has no link with
the DCS.
MS3
Incinerator FNV1
TS H
POV1 (500,000 Kcal/h) F308V Incinerator Waste Oil
Service Tank
(3.0m3)
C5 F316V F313V
PI PU5 CI LS L
RV3
LS H
LS
PU3 M3 From F304V
PS3
PI TR Fuel Oil (26m3/h x 0.4 bar)
TV3
MV8 MV7 Drain Tank
F1 F314V
F305V
MV4
From
F306V
GS Air
317V
System (2.9.2a)
307V
T502V
MS3
Incinerator FNV1
TS H
POV1 (500,000 Kcal/h) F308V Incinerator Waste Oil
Service Tank
(3.0m3)
C5 F316V F313V
PI PU5 CI LS L
RV3
LS H
LS
PU3 M3 From F304V
PS3
PI TR Fuel Oil (26m3/h x 0.4 bar)
TV3
MV8 MV7 Drain Tank
F1 F314V
F305V
MV4
From
F306V
GS Air
317V
System (2.9.2a)
307V
T502V
Open Incinerator waste oil settling tank inlet valve B48V b) Open the incinerator gas oil service tank quick-closing outlet
Open LO transfer pump suction valve from LO drain tank L50V valve F315V.
Closed LO transfer pump suction valve from main LO sump c) Open the incinerator gas oil inlet valve F316V and return valve
and settling tanks L24V F313V.
Closed LO transfer pump suction valve from generator
turbine LO sumps and settling tanks L22V The incinerator gas oil system is now ready for operation.
Closed LO transfer pump suction valve from diesel
d) Open the incinerator waste oil service tank outlet valve F304V
generator LO sumps and settling tanks L23V
and return valve from the milling pump F308V.
c) At the LO transfer pump local selector select REMOTE e) Start the incinerator milling pump and circulate the contents
mode. The pump may also be operated locally by selecting of the waste oil service tank to ensure thorough mixing and an
the LOCAL mode; the pump is then started and stopped by even temperature.
pressing the START and STOP pushbuttons.
f) Open the waste oil inlet valve to the incinerator F307V and
d) At the LO transfer system DCS graphic screen T30-417-02 waste oil return valve F317V.
LUB OIL TRANSFER SYSTEM, click on the LO transfer
pump icon to bring up the pump faceplate. At the faceplate g) Ensure that the crossover valve between the waste oil and gas
click on the START soft key to start the pump. oil systems F306V is closed.
e) When the desired quantity of waste LO has been transferred h) When the incinerator waste oil service tank is at the correct
to the incinerator waste oil settling tank, stop the LO transfer temperature and the incinerator is ready to burn waste oil, open
pump by calling up the faceplate and clicking on the STOP soft the waste oil supply valve to the incinerator F305V.
key.
The incinerator is now able to burn waste oil.
Steam heating is applied to the settling tank in order to assist in the separation
of water from the oil.
a) Open the waste oil settling tank sludge cock F311V and drain
any water present.
b) Open the outlet valve from the waste oil settling tank F312V.
c) When the contents of the waste oil settling tank have drained
to the waste oil service tank, close the outlet valve F312V and
replenish the waste oil settling tank.
2.5.2 Auxiliary Sea Water Cooling System (Including Fresh Water Generators)
Illustrations
Upper Deck
From
Inert Gas Generator
Refrigeration Cooler
and Air Dryer Cooler
S21V
(2.10.1a)
TI Key
TI
Auxiliary LS
M Sea Water
Condenser
S11V Electrical Signal
Instrumentation
S27V
S25V
S26V
LS To
Bilge Holding From
LS
Tank Fresh Water
(2.6.1a) System
S12V (2.8.3a) TI TI PAL
DCS DCS DCS
TX TI TX TI PS
Main Condenser From Auxiliary
Sea Water
S18V S17V Cooling System
S16V (2.5.2a)
Sawdust
Set at 3.3bar
S19V Injection
Tank
(100Litre)
LS
55V
LS
S30V From
To Marine
Main SW LS Growth
Crossover Pipe Main Sea Water LS Protection
(2.6.1a) Circulating Pump S9V System
From (9,000/4,500m3/h S8V S7V S29V
Marine x 5/8mth) S13V FI
Growth PI PI
Auxiliary Sea Water
Protection Scoop
Circulating Pump
System
(9,000/4,500m3/h Inlet
CI x 5/8mth) CI
FI DCS
S6V S5V 31V
M LS
DCS
LS Starboard
Sea Water Crossover Pipe S1V High Sea Inlet
S32V M S2V Chest
Midship Low
Sea Inlet Chest
Upper Deck
From
Inert Gas Generator
Refrigeration Cooler
and Air Dryer Cooler
S21V
(2.10.1a)
TI Key
TI
Auxiliary LS
M Sea Water
Condenser
S11V Electrical Signal
Instrumentation
S27V
S25V
S26V
LS To
Bilge Holding From
LS
Tank Fresh Water
(2.6.1a) System
S12V (2.8.3a) TI TI PAL
DCS DCS DCS
TX TI TX TI PS
Main Condenser From Auxiliary
Sea Water
S18V S17V Cooling System
S16V (2.5.2a)
Sawdust
Set at 3.3bar
S19V Injection
Tank
(100Litre)
LS
55V
LS
S30V From
To Marine
Main SW LS Growth
Crossover Pipe Main Sea Water LS Protection
(2.6.1a) Circulating Pump S9V System
From (9,000/4,500m3/h S8V S7V S29V
Marine x 5/8mth) S13V FI
Growth PI PI
Auxiliary Sea Water
Protection
Circulating Pump Scoop
System
(9,000/4,500m3/h Inlet
CI x 5/8mth) CI
FI DCS
S6V S5V 31V
M LS
DCS
LS Starboard
Sea Water Crossover Pipe S1V High Sea Inlet
S32V M S2V Chest
Midship Low
Sea Inlet Chest
With the system in automatic mode the main SW circulating pump will supply g) To change from scoop to pump mode whilst in manual mode,
cooling water to the main condenser until the conditions for automatic change use the trackball and click on the PUMP MODE soft key in the
to scoop mode are satisfied. The change to scoop mode will be made when the display.
shaft speed is above 53 rpm and the telegraph has been in the AT SEA position
for more than 10 minutes. The change from scoop mode back to pump mode If the shaft speed falls below 42 rpm when in scoop mode and manual mode,
will be made when the engine speed falls below 42 rpm, or when the telegraph an alarm will be activated.
is moved to the MANOEUVRING position from the AT SEA position, or
during a restart following a blackout. In the event of a blackout when in manual mode and scoop mode the system
will automatically revert to pump mode.
Preparation for Manual Operation of the Main Condenser In pump mode and manual mode, the main SW circulating pump may be
Sea Water Circulating System started and stopped manually from the graphic display T30-408-02. This is
carried out using the trackball and clicking on the pump icon to display the
(Note: All operations in this procedure take place at the main sea water pump faceplate. The pump is stopped by clicking on the STOP soft key.
circulating system graphic display T30-408-02.)
Manual mode may be selected at any time but the associated valves and
main SW circulating pump must be in their respective remote and automatic
modes.
a) Ensure that the sea water system is already flooded and vented
and that suction is available at the main SW circulating pump.
(Note: The auxiliary SW circulating pump is only manually operated and The Condenser Sawdust Injection System
does not have an auto/manual selection option.)
In the event of a condenser tube leakage, sawdust is injected into the cooling
Procedure for the Operation of the Main Condenser Sea Water sea water system in order to provide a means by which small leaks may be
plugged. The sawdust box is supplied with sea water from the main sea water
Circulating System using the Auxiliary Sea Water Circulating
cooling system. The outlet from the sawdust box is connected to the scoop sea
Pump water supply pipe near the condenser inlet.
Under normal circumstances the main condenser is supplied with sea water In order to operate the system the sawdust box must be filled with sawdust
by the scoop or the main SW circulating pump. In the event of failure of the and the inlet valve from the cooling sea water system S17V must be opened.
main SW circulating pump, the auxiliary SW circulating pump may be used, The outlet valve from the sawdust box S18V must be opened in order to
however this pump only has manual control and so the automated sequences of supply the mixture of sawdust and sea water to the condenser inlet line. The
the system will not function. The system must be operated in system off mode system may be operated when in scoop or pump mode.
as neither the automatic mode nor the manual mode will operate as they both
require the main SW circulating pump to be operational.
a) At the mode selection panel in the main sea water circulating Directional Flow Lever
system graphic display T30-408-02 click on the SYSTEM OFF
soft key to select system off. The indicator will change colour
to show that system off has been selected.
Electrical Signal
PI PI PI PI S S
Instrumentation
S108V
Fresh Water PI-11 PI-12
TI TI TI TI
PI PI
S148V S149V S150V S151V
LS LS S109V S107V
S152V
Power Supply FS
To Scoop Low Sea Chest S110V
(2.5.1a)
MGPS (SB5K)
S144V S143V
TI TI
S121V S137V S136V
No.2 No.1 S119V
Vacuum Vacuum S117V
Pump Pump
Heat Marine Growth CI Main Cooling PI PI PI PI Distilling Plant
Heat
Exchanger Prevention System Sea Water Sea Water Feed
Exchanger 1 2 2 1
Sea Water Pumps Pumps
Booster Pump (950m3/h x 21mth) CI CI CI CI
(90m3/h x 43mth)
PI
TI TI (18m3/h x 35mth)
S146V S145V
DCS S134V
S114V S135V
S115V
S122V To To
Sea Chest No.1, 2 and 3 Fire, Bilge & GS Pumps DCS
(High) M LS Ballast Pumps And Water Spray Pumps
(2.7a) (2.6.1a and 5.14a) Sea Chest
S101V (Low)
LS M
S105V
To Fire Line
Pressure Pump
B47V (5.1b)
Local manual control is selected at the main switchboard and this allows the
Distillation Plant Sea Water Feed Pump Main Sea Water Cooling Pump Control pump to be started and stopped by means of local pushbuttons situated near
Maker: Teikoku Machinery Works the pumps. Local status is displayed on the DCS graphic screen faceplate for
Control of the main SW cooling pumps is via the DCS at the display screen each pump. The local stop of a pump is always active even when the starter is
No. of sets: 2 T30-408-03. Using the trackball, the relevant operating mode for the pump is selected as remote. If the local stop button is pressed when in remote mode, the
Type: Centrifugal selected at the pump control mode selection faceplate. pump motor is stopped and the DCS control for the pump is reset to local.
Model: 125TVS-Bm
Capacity: 90m3/h at 43mth Each pump and the standby facility have a faceplate allowing the operator
to select the desired operating mode. Automatic mode allows the standby Valve Control
pump to start upon loss of pressure from the duty pump. Automatic operation
Marine Growth Protection System selection is indicated on the DCS graphic screen and is indicated as AUT on The high and low sea chest valves S101V and S105V are controlled from the
Maker: Electrocatalytic Ltd the controller faceplate for the pumps. Manual mode allows the operator to DCS via the ship side valve graphic display screen T30-408-04. Valves may be
start or stop either pump from the pump faceplate at the display graphic T30- opened and closed by means of the trackball, by clicking on the OPEN/CLOSE
Model: SB1K 408-03. soft keys of the valve faceplate in order to open a closed valve or close an open
valve. An illuminated screen indicates if the valve is open or closed. The valves
may be closed, along with all other ship side valves, by activation of one of
Introduction Automatic Mode
the screen emergency close button icons in the ship side valve graphic display
When the standby facility is set to auto the standby pump will start screen. The valves may also be opened and closed locally.
The auxiliary sea water cooling system provides cooling water to the two main automatically upon a start command from the DCS when failure of the duty
central fresh water coolers and the two vacuum pump heat exchangers. The pump is indicated by the duty pump pressure switch. When in auto mode, The overboard discharge valve S152V from the main central coolers, may be
system also supplies sea water as required to the main condenser sawdust box, manual start or stop from the DCS is inhibited. When the standby pump starts opened and closed remotely from the sea water service system graphic display
the sewage treatment plant and the MGPS system, which is also provided with in automatic mode an alarm is generated. The auto condition is indicated on screen T30-408-03, via its faceplate. The valve may also be opened or closed
a booster pump. The two main SW cooling pumps take suction from the sea the DCS screen and as AUT on the controller faceplate. locally.
water suction main which runs across the width of the vessel connecting with
the high and low sea chests. Automatic operation can only be selected if the following conditions apply: All other valves in the system are manually operated locally and must be set
• The standby pump is stopped before the system pumps are activated.
The two distillation plant sea water feed pumps also take suction from the sea
water suction main. These pumps provide sea water feed to the fresh water • The starter is set to the remote position
generators and sea water to operate the brine ejectors.
Electrical Signal
PI PI PI PI S S
Instrumentation
S108V
Fresh Water PI-11 PI-12
TI TI TI TI
PI PI
S148V S149V S150V S151V
LS LS S109V S107V
S152V
Power Supply FS
To Scoop Low Sea Chest S110V
(2.5.1a)
MGPS (SB5K)
S144V S143V
TI TI
S121V S137V S136V
No.2 No.1 S119V
Vacuum Vacuum S117V
Pump Pump
Heat Marine Growth CI Main Cooling PI PI PI PI Distilling Plant
Heat
Exchanger Prevention System Sea Water Sea Water Feed
Exchanger 1 2 2 1
Sea Water Pumps Pumps
Booster Pump (950m3/h x 21mth) CI CI CI CI
(90m3/h x 43mth)
PI
TI TI (18m3/h x 35mth)
S146V S145V
DCS S134V
S114V S135V
S115V
S122V To To
Sea Chest No.1, 2 and 3 Fire, Bilge & GS Pumps DCS
(High) M LS Ballast Pumps And Water Spray Pumps
(2.7a) (2.6.1a and 5.14a) Sea Chest
S101V (Low)
LS M
S105V
To Fire Line
Pressure Pump
B47V (5.1b)
Two fresh water distillation plants are fitted, each with a capacity of 45 tons/
Position Description Valve (Note: Valves are indicated in their normal operating position but if an item day. These units generate fresh water by the evaporation of sea water and
Open No.1 main cooling SW pump suction valve S114V of equipment is not operating, such as a fresh water distillation plant subsequent condensation of the vapour produced by that evaporation. The
or an MGPS unit, the valves for that unit may be closed.) units operate at partial vacuum, allowing for evaporation at lower temperature
Open No.1 main cooling SW pump discharge valve S117V
and increased efficiency.
Open No.2 main cooling SW pump suction valve S115V The auxiliary sea water cooling system is now set and ready for operation.
Open No.2 main cooling SW pump discharge valve S119V Low temperature evaporation also reduces salt scale formation and allows for
Procedure for the Operation of the Auxiliary Sea Water prolonged operation. Operation of the generator is described in more detail in
Open No.1 main central FW cooler inlet valve S148V section 2.8.3 Domestic Fresh water System.
Cooling System
Open No.1 main central FW cooler outlet valve S149V
The sea water supply to the evaporators provides feed water for evaporation,
Open No.1 vacuum pump heat exchanger inlet valve S143V a) Ensure that the system is prepared for operation as described
cooling water for condensing the vapour and driving water for operating
above and that the sea water suction main is flooded.
Open No.1 vacuum pump heat exchanger outlet valve S145V the brine ejectors which remove brine from the evaporator shell. Sea water
is provided by two distillation plant sea water feed pumps, one for each
Open No.2 vacuum pump heat exchanger inlet valve S144V b) Select AUTOMATIC mode at the sea water service system
evaporator. Although each evaporator has its own dedicated pump, these
graphic display screen T30-408-03. Select one of the pumps as
Open No.2 vacuum pump heat exchanger outlet valve S146V pumps are cross-connected by means of valve S125V this allows No.1 pump
the duty pump and start that pump by clicking on the pump icon
to supply No.2 evaporator or No.2 pump to supply No.1 evaporator.
Closed Condenser sawdust box inlet valve S17V to bring up the pump faceplate, then clicking on the START soft
Open MGPS sea water booster pump inlet valve S121V key.
The distillation plant sea water pumps are started and stopped locally and will
Open MGPS sea water booster pump outlet valve S122V be operated when the evaporators are put into operation.
c) Check that pressure is raised in the system and that sea water is
Open Supply and outlet valves for MGPS units SB1K flowing to all selected items with their valves open.
In order to prevent foaming in the evaporator and to restrict the formation of
for auxiliary high and low sea chests scale, chemical treatment is injected into the feed to the evaporation chamber.
d) Start the MGPS sea water booster pump by clicking on the
Open MGPS supply valves to auxiliary high and low sea chests This is achieved by means of a chemical dosing unit.
pump icon in the screen display to bring up the pump faceplate
and clicking on the START soft key. Supply electrical power to
A non-return discharge valve is fitted to the outlet line from each evaporator
the MGPS units. Unit SB1K will operate for the auxiliary sea
brine ejector and the discharges pass to a common overboard discharge valve.
suctions and one of the two SB5K units will be selected for the
main condenser sea suctions.
Illustrations
The bilge well level alarms are monitored by the DCS and displayed on the • Void space stripping ejectors
bilge system graphic screen T30-409-01.
When a probe, located at the top of each of the separator chambers senses oil, m) Switch off the oil content monitoring unit, shut off the separator,
d) Set the valves as in the following table:
the signal is sent to an oil discharge valve, which opens and discharges the close all pump valves and lock the overboard valve B27V.
oil collected at the top of the chamber to the oily bilge tank. When the probe The reclaimed oil will be discharged to the oily bilge tank.
detects the presence of water again the discharge valve is closed.
The clean exit water will be discharged overboard. Oil contamination of 15ppm
Position Description Valve or over will automatically be discharged back to the bilge holding tank until the
The separator works automatically at all times and will operate as long as
there is water being pumped into it. Heating may be applied in order to Closed Separator drain valves water is clean enough to discharge overboard. Any oil collected at the top of the
improve separation but the heater will only operate when the separator is bilge separator will be discharged to the oily bilge tank.
Operational Three-way control valve for discharge
filled. The separator is fitted with sampling valves which allow an oil sample
Open Separator overboard discharge valve B27V The engine room bilge pump may also be used for pumping the contents of the
to be drawn and enable the oil/water interface level to be determined.
bilge holding tank through the oily water separator. In this case the bilge pump
Open Separator 1st stage chamber outlet valve
CAUTION suction valves B33V from the bilge holding tank and the bilge holding tank
Open Separator 2nd stage chamber inlet valve suction valve B22V must be open during that operation.
The oily water separator is designed to separate oil from water, not
water from oil. Therefore if the bilge supply to the separator contains Open Return valve to bilge holding tank B68V
excessive amounts of oil it will render the equipment useless and result The pump sea main suction valve B34V must initially be open when starting
Open Oily bilge pump discharge valve B26V up the oily water separator and then closed as the bilge holding tank suction
in unnecessary maintenance.
Open Bilge holding tank suction valve B24V valve B33V is opened. The engine room bilge pump discharge valve B36V to
The maximum flow capacity should not be exceeded as excess flow will the oily water separator must be open at all times during the procedure. The
Closed Oily bilge pump bilge main suction valve B30V
prevent effective separation. The engine room bilge pump and oily bilge engine room bilge pump will stop when the bilge holding tank level switch
pump suction strainers should be kept clean in order to avoid large solid Open Oily bilge pump suction valve from signals a low level in the tank.
particles entering the separator as these will have a detrimental effect on sea water crossover pipe B70V
separation. Closed Fresh water supply valve to separator
Closed Fresh water supply valve to monitor
Starboard forward bilge well suction valve B15V b) Set the bilge, fire and GS pump discharge valves so that
Port forward bilge well suction valve B16V water is directed to drive the stripping eductor. No.1 pump
valve B12V must be open and for No.2 pump valve B13V
Cofferdam suction valves B19V and B73V must be open.
Starboard middle bilge well suction valve B17V
c) Set the stripping eductor valves as in the following table:
Port middle bilge well suction valve B18V
Bilge well near scoop suction valve B69V Position Description Valve
Main turbine recess forward suction valve B20V Open Eductor driving water inlet valve B71V
Main turbine recess aft suction valve B72V Open Eductor overboard discharge valve B53V
Bilge holding tank suction valve B22V Open Eductor inlet valve from void spaces B52V
Aft bilge well suction valve B21V
Stern tube FW cooling tank suction valve B23V d) Start the selected bilge, fire and GS pump and supply sea water
to drive the eductor.
e) Start the selected bilge, fire and GS pump and pump the e) When the eductor is producing the correct vacuum, open the
contents of the selected bilge overboard. following void space drain valves as required.
(Note: The No.1 fire, bilge and GS pump has a direct suction valve B5V
Description Valve
from the forward port bilge well.)
Void space port drain valve B51V
Void space starboard drain valve B50V
f) When the void spaces are empty, close the void space drain
valves, stop the bilge, fire and GS pump and close the eductor
valves.
a) Start a fire pump to pressurise the fire main system, either by Illustration 2.6.2a Forward Bilge System
locally starting the emergency fire pump (section 5.9) or by
requesting the bridge to start one of the fire pumps (bilge,
fire and GS pumps or fire pump). These pumps are normally
kept ready with valves open so that either of the pumps can
immediately pressurise the fire main. From Fire Main To Hawse Pipes
b) Open the eductor overboard discharge valve BG06. This valve BF14
BG33 BG31 BF03
is operated from the bosun’s store by means of an extended
spindle. Chain
BF10 Bosun's Store
BG30 Lockers
(P & S)
BG10
c) Open the eductor and system valves as in the following tables: BG32
BG09 BF04
Eductor inlet valve (non-return valve set open) BG30 No.1 Water Bow Thruster Room
Ballast Tank BG01
Port chain locker suction valve BG10
Starboard chain locker suction valve BG09 BG13
Illustrations
Key TI PI TI
1
After BA48V PX
Peak Tank
BA46V
From Stripping BA54V
Water Spray Eductors
BA41V Pumps (5.14a) (300m3/h)
DCS
To To or Fire Pumps
Main SW Fire, Bilge & GS Pumps To Evaporator DCS (2.6.1a) BA45V
High Sea B104V Low
Inlet Chest Cooling Pumps and Water Spray Pumps SW Supply Pumps Sea Inlet PI
Emergency (2.5.1a) PX
(Starboard) (2.6.1a and 5.14a) Chest DCS
Bilge
LS M Suction M (Port)
Stern Tube
FW Cooling Sea Water Crossover Pipe 2
S101V To Fire Line S105V BA47V
Tank
Pressure Pump B47V
The pumps can discharge to the following: h) At the DCS Ballast Tank System graphic display screen T30-
• Overboard 433-02, monitor the after peak tank level as required.
• Inert gas generator cooling system Stop the pump and close all valves when the aft peak is at the required level.
• Inert gas generator refrigeration condenser cooling
• Inert gas generator air dryer cooler Procedure for Pumping Out the Aft Peak Tank
The tank can be drained to the bilge by means of the self-closing drain valve
Procedure for Filling the Aft Peak Tank with Sea Water B61V should the need arise.
a) Ensure that all suction strainers are clear on the SW suction
(Note: Check with the Chief Officer that all ballast tank valves are closed.)
chests.
a) Ensure all the pressure gauge and instrumentation valves are
b) Ensure all the pressure gauge and instrumentation valves are
open and that the instrumentation is reading correctly.
open and that the instrumentation is reading correctly.
b) At the DCS graphic display screen T30-433-01 BALLAST
c) Determine how much sea water is to be pumped into the aft
PUMP SYSTEM, use the trackball to set up the ballast system
peak tank.
for pumping out the after peak. Select each valve in turn and at
the relevant faceplate and click on the OPEN soft key to operate
the valve.
Key TI PI TI
1
After BA48V PX
Peak Tank
BA46V
From Stripping BA54V
Water Spray Eductors
BA41V Pumps (5.14a) (300m3/h)
DCS
To To or Fire Pumps
Main SW Fire, Bilge & GS Pumps To Evaporator DCS (2.6.1a) BA45V
High Sea B104V Low
Inlet Chest Cooling Pumps and Water Spray Pumps SW Supply Pumps Sea Inlet PI
Emergency (2.5.1a) PX
(Starboard) (2.6.1a and 5.14a) Chest DCS
Bilge
LS M Suction M (Port)
Stern Tube
FW Cooling Sea Water Crossover Pipe 2
S101V To Fire Line S105V BA47V
Tank
Pressure Pump B47V
IG generator overboard I-9V All the cargo hydraulic piston type operating valves have an emergency hand
pump connection. There is a portable emergency hand pump unit available on
Ballast pump overboard BA55 deck for use on the ballast tank valves. The isolating valves on the distribution
Ballast eductor overboard BA54 block are first shut off and the hoses of the emergency hand pump fitted to the
snap-on connectors. Control of direction is via a hand operated changeover
Central cooler overboard S152V control block. The capacity of the sump tank is 6.5 litres.
Ballast eductor overboard BA54
Scoop inlet valve S13V Operating Procedure
Main condenser overboard S15V
a) Check that the emergency hand pump has the sump tank topped
up to the correct working level.
Hydraulic Power Pack Cargo
b) On the cylinder to be operated, isolate the hydraulic supply and
The unit consists of a 1,000 litre oil tank, with the two main and one topping return valves.
up pumps situated on top of the tank. Each main pump has a delivery rate of 54
litres/min at pressure of 130 bar. Suction is through 150 micron filters, before c) Fit the flexible hose snap-on connectors.
passing onto the main rail through individual non-return valves. There is a
bank of eight accumulators of 60 litre capacity each, pressurised to 90 bar with d) Shut the hand pump unloading valve.
nitrogen. Each accumulator has a drain valve, in order to drain down to the
main tank if required. The system is protected by 2 safety relief valves set at e) Operate the direction control valve lever to give the desired
140 bar, which returns to the tank via the main return line. There are no pump movement of the cylinder.
discharge line filters apart from the individual 10 micron paper filters fitted at
each solenoid cabinet station.
Illustrations
W24V W22V
W40V W38V
W6V PI PI
No.2 AC Cooler for Key Main Central W42V W43V
PI PS Main Switchboard Room From From Fresh Water W4V 2 1
Air Engine Room Electrical Signal PI PI
and Engine Control Room Cooling Chemical
Compressors Drain Cooler Pumps 2 Dosing 1 From CI CI
(2.8.1b) (2.8.1b) Instrumentation (1100m3/h x Tank (20L) Fresh Water
W36V Expansion Tank W23V W21V
TI TI
33mth) CI CI
Fresh Water (2.8.1b)
No.1 AC Cooler for W45V Auxiliary Central Fresh Water
W3V W44V
PI PS Main Switchboard Room Air Cooling Booster Pumps
and Engine Control Room W1V
(145m3/h x 25mth)
W35V
TI TI
Central
Fresh Water
Cooling System To Deck Scupper
d) At the fresh water cooling system graphic display T30-410-03 (2.8.1a)
(Note: The duty pump may be started locally, however unless the other pump TI TI
is set to remote, it will not act as the standby pump.) To/From No.1 Control Air
Central Compressor
Fresh Water W119V W123V
g) Ensure that there is an electrical supply at the diesel generator Cooling System
(2.8.1a)
preheater. Key TI TI
Air
To Deck Scupper
i) Check the system for leaks as temperatures rise. To Deck Scupper
FC02
FC02
Position Description Valve g) If the second pump is available it may be set to AUTO to act
as the standby pump.
Open No.1 auxiliary FW cooling pump suction valve FC14
Open No.1 auxiliary FW cooling pump discharge valve FC16 (Note: The duty pump may be started locally, however unless the other pump
Open No.2 auxiliary FW cooling pump suction valve FC15 is set to remote, it will not act as the standby pump.)
Open No.2 auxiliary FW cooling pump discharge valve FC17 h) Check the system for leaks as temperatures rise.
Open Expansion tank outlet valve FC13
i) Test the water daily, using the chemical dosing system to restore
Closed Expansion tank replenishing valve FC11 the level of chemicals in the fresh cooling water system to the
Closed Expansion tank drain valve FC12 level recommended.
Open No.1 cargo machinery cooler inlet valve FC08
FW Filling
Port Starboard Upper Deck
To PI TI
Gland Steam VA-EI-01
FW4V FW3V Condenser PX
Port Starboard
Domestic Domestic Set at 1.0bar
From
Fresh Water Fresh Water Sea Water Cooled
Tank Steering Gear Tank
LIAHL Room LIAHL Fresh Water
(289.2m3) LX LX (289.2m3) Generator M27V
DCS DCS
M12V
D16V
FW5V PI SX Distillate
Port FW6V Starboard M28V
From S Pump
Distilled Distilled
Water Water Main Condensate
Tank Tank Pumps Discharge PI TI
(231.5m3) (231.5m3)
LIAHL LIAHL D17V
LX LX
DCS DCS
TC
From
Control Air
System
Ion S Condensate
Exchanger Pump
PI AGV-80 Type To S
(3,750l/h) PI Atmospheric
M51V Drain Tank
From
Dong-Geon Fresh Water
From S
Mineraliser P PS PI System
DGM-Type I Main Condensate
(3,750l/h) Pumps Discharge TI
X19V TI PI D-57V
To X17V
Sea Water Cooled Chemical
From Fresh Water Dosing
S Exhaust Steam S108V
Generator To Tank
System (2.1.7a) Atmospheric VA-FT-01
D49V Drain Tank
4th Deck 4th Deck
Key
To
Desuperheated Steam Fire, Bilge & GS Pumps 125V PI
(2.6.1a & 5.1a) S137V S136V
Electric Signal To PI Fresh Water PI
Ballast Pumps Generators S110V
Fresh Water (2.7a) Sea Water
CI Supply Pumps CI
Instrumentation
(90m3/h x 43mth)
To To
Condensate SW Suction
Main SW Fire Main
High Sea From DCS Cooling Pumps To ER Bilge Pumps S135V S134V Pressure Pump From DCS Low
Inlet Chest Control Air (2.6.1a) Sea Inlet
(2.5.2a) (5.1b)
(Starboard) Chest
LS M Sea Water M LS (Port)
Sea Water Crossover Pipe
S101V S105V
FW Filling
Port Starboard Upper Deck
To PI TI
Gland Steam VA-EI-01
FW4V FW3V Condenser PX
Port Starboard
Domestic Domestic Set at 1.0bar
From
Fresh Water Fresh Water
Tank Steering Gear Tank
Sea Water Cooled
LIAHL Room LIAHL Fresh Water
(289.2m3) LX LX (289.2m3) Generator M27V
DCS DCS
M12V
D16V
FW5V PI SX Distillate
Port FW6V Starboard M28V
From S Pump
Distilled Distilled
Water Water Main Condensate
Tank Tank Pumps Discharge PI TI
(231.5m3) (231.5m3)
LIAHL LIAHL D17V
LX LX
DCS DCS
TC
From
Control Air
System
Ion S Condensate
Exchanger Pump
PI AGV-80 Type To S
(3,750l/h) PI Atmospheric
M51V Drain Tank
From
Dong-Geon Fresh Water
From S
Mineraliser P PS PI System
DGM-Type I Main Condensate
(3,750l/h) Pumps Discharge TI
X19V TI PI D-57V
To X17V
Sea Water Cooled Chemical
From Fresh Water Dosing
S Exhaust Steam S108V
Generator To Tank
System (2.1.7a) Atmospheric VA-FT-01
D49V Drain Tank
4th Deck 4th Deck
Key
To
Desuperheated Steam Fire, Bilge & GS Pumps 125V PI
(2.6.1a & 5.1a) S137V S136V
Electric Signal To PI Fresh Water PI
Ballast Pumps Generators S110V
Fresh Water (2.7a) Sea Water
CI Supply Pumps CI
Instrumentation
(90m3/h x 43mth)
To To
Condensate SW Suction
Main SW Fire Main
High Sea From DCS Cooling Pumps To ER Bilge Pumps S135V S134V Pressure Pump From DCS Low
Inlet Chest Control Air (2.6.1a) Sea Inlet
(2.5.2a) (5.1b)
(Starboard) Chest
LS M Sea Water M LS (Port)
Sea Water Crossover Pipe
S101V S105V
c) Close the steam valve X19V for the No.1 plant and X24V for Normally one domestic fresh water tank is in use and the other tank is being Water may be taken from a shore supply or a barge by means of water
No.2 plant. filled. Domestic fresh water and distilled water tanks may also be filled at the bunkering lines located on the port and starboard sides of the ship.
same time.
d) Close the desuperheating condensate spray inlet valve M-50V. The water bunkering line connects with the distillate supply line by means of
valve D51V which should normally be closed.
e) Close the feed water treatment valve VA-FT-01.
Procedure for Pumping Distillate to the Distilled Water Tanks
Taking water from a shore supply or barge requires the blank at the port or
a) Operate the evaporator as described above and open the starboard connection to be removed, the pipe attached and the bunkering valve
f) Stop the distillate and condensate pumps.
distilled water tank filling valves as required. There are port opened. Valve D51V must be opened and water pumped to the storage tanks
and starboard distilled water tanks of 231.5m3 each, which are through the silver ion steriliser and mineraliser.
g) Switch off the salinometer.
located in the steering gear room.
h) Stop the SW ejector pump.
Drinking Water System
Procedure for Pumping Distillate to the Domestic Fresh Water
i) Open the air screw valve VA-EI-01. Tanks There are two drinking water hydrophore pumps which take suction from the
domestic fresh water tanks. These pumps deliver fresh water to the drinking
j) Close the SW ejector pump suction valve S134V and discharge a) Operate the evaporator as described above and open the water hydrophore tank which is maintained under pressure by air from the
valve S136V. domestic fresh water tank filling valves as required. There are general service air system. The pressure in the tank controls the starting and
port and starboard domestic fresh water tanks of 289.2m3 each, stopping of the hydrophore pump which is done automatically by the pump
k) Close the brine/air ejector overboard discharge valve S110V. which are located in the steering gear room. control. One of the pumps is set to the run position at the local panel and the
other pump is set to the off or tripped position. The graphic screen T30-410-01
l) Close the valve on the water tank (either FW or DW). b) Open the silver ion steriliser inlet and outlet valves and supply DOMESTIC WATER SERVICES displays the operating status of the pumps
electrical power to the silver ion steriliser unit. and indicates any steriliser fault.
Distillate Transfer System
c) Close the silver ion steriliser bypass valve D49V. As the water is used, the tank pressure drops allowing the duty pump to start
automatically and refill the tank. As the pressure in the system increases to a
Introduction d) Set the mineraliser inlet and outlet valves so that distillate flows predetermined value the pump will automatically stop.
through the mineraliser.
Distillate is pumped from the evaporator by the distillate pump and may Water from the hydrophore tank flows through a cartridge type drinking water
be discharged to either the distilled water tanks or the domestic fresh water e) Open the filling valve to the port (FW4V) or starboard (FW3V) filter and an ultraviolet steriliser before supplying the drinking water fountain,
tanks. Distillate is pumped directly to the distilled water tanks, but if it is to domestic fresh water tank as required. the galley and other drinking water supply outlets. The cartridge filter and
be pumped to the domestic water tanks, it is first passed through the silver ion ultraviolet steriliser may be bypassed if necessary.
steriliser and the mineraliser. (Note: At the branch pipe to the silver ion steriliser and mineraliser there
is a solenoid valve controlled by the silver ion steriliser. This valve
prevents water flowing to the domestic fresh water tanks unless the
silver ion steriliser is operating.)
Valves are shown as open but if the service was not being used the valve would b) After opening the hot water system supply valve from the cold
be closed. In addition to the systems shown above, the FW hydrophore system water system, allow the system to fill from the hydrophore
also supplies the chemical store room shower, the oily bilge separator and the tank.
cooling FW expansion tank.
c) Ensure that the hot water circulating pumps are primed.
The fresh water system will operate as required with the duty pump operating
in order to maintain pressure in the system. d) Start one of the hot water circulating pump at the local starter
panel.
The domestic water services graphic screen T30-410-01 displays the status of
the FW hydrophore pumps and indicates the pump long run alarm. e) Either open the steam supply or switch on the electrical supply
to the calorifier, and set the system temperature.
Domestic Hot Water System f) Check that the system is circulating correctly and that the
temperature is maintained.
The system supplies hot water to the accommodation system, the washbasin
in the workshop, the washbasin for boiler water testing, the washbasin in the
engine room toilet. Procedure for Filling the Stern Tube Cooling Fresh Water
Tank with Fresh Water
Water is circulated continuously by one of the two the hot water circulating
pumps, the water being passed through a calorifier, which can be either steam The tank is filled from either of the FW tanks by means of gravity.
or electrically heated to raise the water to the correct temperature. Top up to
the system is from the hydrophore tank. The pumps can be changed over if a) Check the level of water in the stern tube cooling water tank and
necessary for maintenance. assess the quantity of water needing to be transferred.
Pumps are started and stopped locally and have no connection with the DCS. b) Check the amount of FW in the domestic FW tank to be used
Pumps would be changed over periodically in order to avoid one pump having and ensure that it is sufficient for the purpose.
excessive running hours.
c) Ensure that the hydrophore system is operating correctly and
Procedure for Operating the Hot Water System that one of the domestic fresh water tank outlet valves is fully
open.
a) To operate the FW system set the hot water system valves as
follows: d) Open the filling valve D11V to the stern tube cooling water
tank. Water will flow by means of gravity from the domestic
fresh water tank to the stern tube cooling water tank. When the
Position Description Valve
tank is full close the filling valve D11V.
Open Calorifier supply from cold water system D58V
Open Calorifier outlet valve D43V (Note: The stern tube cooling water tank may be emptied by means of the
bilge pump. See section 2.6.1.)
Open No.1 HW circulating pump inlet valve D38V
Water is supplied to the lubricating oil purifiers for operating the bowls
when sludging and for sealing purposes. This water is supplied from the
FW hydrophore system. In order to ensure that the purifier system operates
correctly it is essential that the FW hydrophore system is operating at the
correct pressure.
Illustration 2.8.4a Purifier Operating Water System
The supply valve D101V to the purifier system, must be open and the
control valve operating correctly. The control valve is operated by means of Control Air
compressed air and is activated from the purifier control system. Each of the
two LO purifiers has an inlet valve which must be open in order to ensure that D101V
the purifier water operating system will function.
The supply valves to individual parts of the purifier system are activated by
the purifier control system. From Domestic Fresh
Water System
S S
Key
Fresh Water
Illustrations
Main Turbine LO Main Turbine Gland HP Turbine Drain Valve 4.9/1.8bar LO Purifier
Temperature Control Valve Steam Control Valve A134V PRV
A156V A140V A136V
A157V
Atmospheric Drain Tank Bleed Steam Drain Valve Spare
Oily Bilge Tank A158V
Level Control Valve A130V
A240V
TCV - T411V Low Pressure FW Heater No.1 Gen. Turbine Gland Main Turbine Astern Spray 4.9/228mmHg Vacuum
A154V
Level Control Valve Steam Controller Water Piston Valve PRV A237V
Bilge Holding Tank A148V A144V A160V A131V
TCV - T415V No.1 FW Generator No.2 Gen. Turbine Gland
A155V Heating Steam Control Valve Steam Controller LP Turbine Drain Valve
Mid Bilge Wells To Funnel A149V A145V A143V
Shut Off Valve (S) PS No.2 FW Generator Central FW Cooling Water
A161V Set at 9.9 bar Heating Steam Control Valve Temperature Control Valve To Accommodation
A150V A138V
Mid Bilge Wells PS Oily Water Separator Air Purge Type LG A213V
A162V Shut Off Valve (P) Solenoid Valve (HFO Overflow Tank)
A142V A238V
A216V For ESDS PS Main Condenser Spare
Level Control Valve PIAL
A159V A151V To Quick-Closing No.2 Air Dryer
PI DCS
Valves System (250nm3/h)
Control Air Reservoir A214V in Fire Control Station Desiccant
PIAL
DCS
PX (7.5m3/h x 9 bar) (5.3a)
Water Separator
PX PI
Main Turbine LO Main Turbine Gland HP Turbine Drain Valve 4.9/1.8bar LO Purifier
Temperature Control Valve Steam Control Valve A134V PRV
A156V A140V A136V
A157V
Atmospheric Drain Tank Bleed Steam Drain Valve Spare
Oily Bilge Tank A158V
Level Control Valve A130V
A240V
TCV - T411V Low Pressure FW Heater No.1 Gen. Turbine Gland Main Turbine Astern Spray 4.9/228mmHg Vacuum
A154V
Level Control Valve Steam Controller Water Piston Valve PRV A237V
Bilge Holding Tank A148V A144V A160V A131V
TCV - T415V No.1 FW Generator No.2 Gen. Turbine Gland
A155V Heating Steam Control Valve Steam Controller LP Turbine Drain Valve
Mid Bilge Wells To Funnel A149V A145V A143V
Shut Off Valve (S) PS No.2 FW Generator Central FW Cooling Water
A161V Set at 9.9 bar Heating Steam Control Valve Temperature Control Valve To Accommodation
A150V A138V
Mid Bilge Wells PS Oily Water Separator Air Purge Type LG A213V
A162V Shut Off Valve (P) Solenoid Valve (HFO Overflow Tank)
A142V A238V
A216V For ESDS PS Main Condenser Spare
Level Control Valve PIAL
A159V A151V To Quick-Closing No.2 Air Dryer
PI DCS
Valves System (250nm3/h)
Control Air Reservoir A214V in Fire Control Station Desiccant
PIAL
DCS
PX (7.5m3/h x 9 bar) (5.3a)
Water Separator
PX PI
Closed 3rd deck (midship) manifold drain valve A217V Open No.2 boiler feed water regulating valve
control air supply valve A185V
Open 4th deck (port) manifold supply valve A124V Open 60.3/15.5 bar PRV control air supply valve A168V
Open No.1 boiler FO pressure control valve
Closed 4th deck (port) manifold drain valve A214V Open 10/6 bar PRV control air supply valve A163V control air supply valve A186V
Open Main turbine gland steam control air supply valve A156V Open 60.3/15 bar PRV control air supply valve A212V Open No.1 boiler feed water regulating valve
Open Atmospheric drain tank LCV control air supply valve A158V Open 15.5/6 bar PRV control air supply valve A189V control air supply valve A187V
S
Engineering Fire CO2 IS Telephone IS Telephone
No.2 High Duty Compressor No.2 Low Duty Compressor
Horn Horn Horn Horn Horn
Bulkhead Seal (PCV6961) Bulkhead Seal (PCV6961) AS03V
No.2 High Duty Compressor No.2 Low Duty Compressor
Bulkhead Seal (PCV6962) Bulkhead Seal (PCV6962) S
Engineering
No.2 High Duty Compressor No.2 Low Duty Compressor Horn
AS22V
Shaft Seal (PCV9605) Shaft Seal (PCV9605)
S
No.2 High Duty Compressor NG901V No.2 Low Duty Compressor
NG801V Bypass Valve (PCV6946) Bypass Valve (PCV6946)
FR I
No.2 High Duty Compressor No.2 Low Duty Compressor P
Guide Vane Valve (PCV6931) Guide Vane Valve (PCV6931) AS06V
Water Drain
Accumulator
FR POS
S S
Control Air from Engine Room (Starboard)
AS08V AS07V
(Note: Valves are shown as open, which is their normal operating condition,
but they will be closed if the service is not being used.)
A37V
A36V
A35V A26V Near Forced Draught Fans
2nd Deck Port
To A32V
Nitrogen To
Generators Engine Room
(Cargo 4.8a) Air Horn Engineer's Store
Near Forward Evaporator A25V
(2nd Deck Aft)
A31V
To Steering
Near Drinking and Fresh Water Hydrophore Tanks Gear Room Workshop (Aft)
A61V
A30V A38V
Engine Room
Near Boiler Burners Aft Bulkhead
A29V
To Burners Atomising (2.1.4a) Workshop (Forward)
A24V
A47V
Near Generator Engine LO Purifiers
A28V A23V
A11V N1
Water
A63V
Separator A62V
A41V A42V
From Control
A19V Air System
(2.9.1a) Key
A37V
A36V
A35V A26V Near Forced Draught Fans
2nd Deck Port
To A32V
Nitrogen To
Generators Engine Room
(Cargo 4.8a) Air Horn Engineer's Store
Near Forward Evaporator A25V
(2nd Deck Aft)
A31V
To Steering
Near Drinking and Fresh Water Hydrophore Tanks Gear Room Workshop (Aft)
A61V
A30V A38V
Engine Room
Near Boiler Burners Aft Bulkhead
A29V
To Burners Atomising (2.1.4a) Workshop (Forward)
A24V
A47V
Near Generator Engine LO Purifiers
A28V A23V
A11V N1
Water
A63V
Separator A62V
A41V A42V
From Control
A19V Air System
(2.9.1a) Key
i) Ensure that remote user outlets are receiving air. Air valves
to user locations should be opened periodically to blow them
through in order to remove condensate and prevent seizure.
PIAL PS
DCS
PX Generator Engine
A48V
A6V
A45V
Key
From
Starting Air Nitrogen System PX
Relief Valve Set at
PIAL 27.5bar
Electrical Signal DCS
PI
A2V
HP Magnetic Valve
LP Magnetic Valve
No.2 Generator Engine
Starting Air Compressor
(25m3/h x 25 bar)
A1V
HP Magnetic Valve
LP Magnetic Valve
Maker: Jonghap The air reservoir is fitted with an automatic drain trap and the valves for this
No. of sets: 2 must be open at all times.
Type: Two stage reciprocating, air cooled
Model: AHV-20 Procedure for Filling the Generator Engine Starting Air
Capacity: 25m3/h at a pressure of 25 bar Reservoir and Supplying the Generator Engine with Starting
Air
Introduction a) Ensure that all pressure gauge and instrumentation valves are
open and that gauges and instruments are reading correctly.
The diesel generator engine starting air system is supplied by two starting air
compressors which provide air to the starting air reservoir. It is also supplied to
b) Check the oil level in the compressors.
the emergency diesel generator starting air reservoir. In an emergency air can
be supplied to the generator engine starting air reservoir from the emergency
c) Check the compressor sumps for water.
air compressor located in the emergency generator engine room.
d) Set up valves as in the following table:
The starting air reservoir is supplied through an oil/water separator situated on
the discharge from each of the compressors. The compressors are each fitted
with two safety valves, one after the first stage compression and the other after Position Description Valve
the second stage compression. A pressure switch connected to the automatic Open No.1 compressor discharge valve A1V
control system stops the compressor should the LO pressure fall below a
Open No.2 compressor discharge valve A2V
predetermined value.
Open Air reservoir inlet valve N1
The bearings are lubricated by a gear pump fitted at the end of the crankshaft.
Open Air reservoir drain valves
A high temperature sensor is located at the compressor outlet and this will trip
the compressor if the air temperature exceeds a predetermined limit. Open Air reservoir outlet valve to the generator engine N2
Closed Air reservoir line valve to the emergency generator
Each compressor has an automatic unloader arrangement which operates Air reservoir
when the compressor starts and stops. This allows the compressor to start and
stop off load, thus reducing the loading on the electric drive motor and the Open Generator engine air supply valve A48V
compressor running gear. The compressors are started and stopped by pressure Closed Air reservoir filling valve from emergency air compressor
switches situated on their respective starting air reservoirs.
e) Check that all automatic drain traps are operational and that the
Switches at the main switchboard starter panel may be set to remote or local.
unloader gear is functioning.
When in the local position the compressor can only be started and stopped from
the local pushbutton panel. When in the remote position the compressor can
f) Check that the starting air reservoir automatic drains are
be operated from the DCS graphic display screen T30-413-01 COMPRESSED
functioning correctly and that the compressor automatic drains
AIR SYSTEMS.
are functioning correctly.
At the graphic display screen the compressor can be selected for automatic
g) Check the compressors and when satisfied set them to REMOTE
operation, in which case it will be started and stopped by the air reservoir
operation at the local control panel and then at the DCS screen
pressure switches. The compressor may also be set to manual operation which
T31-413-01 select them for AUTO operation.
allows for manual starting from the DCS graphic display.
h) Drain any liquid from the reservoirs and oil/water separator.
The compressors will operate and supply air to the starting air reservoir.
Illustrations
Vent
To Funnel
From Side Wall
10bar Steam
Air HIC
System
A37V
PAL S
PS PI
To Inert Gas PI
Generator Gas Oil Test FI Electric
Service Tank Heater
PI
From Inert Gas FX
Generator Gas Oil
PIAH FI Steam
I
Service Tank HC P Heater
Cooler To Funnel
PI AAHL
PS PI No.2
No.1
Dryer
Dryer
TI
F38V
BSA Nitrogen PI TI S
BE Fan To
131V Atmospheric
Drain
SG SG 127V
From Tank
To Fuel Oil Ballast To Auxiliary Condenser
Drain Tank System Overboard Line
Silencer S
S H-2
TAH
TS S
H-17
PI PI
TS TI
From Fresh Water
Hydrophore Unit
D20V
PI
S PX PIC
To
SG S S Engine
To Inert Gas Cooler From MT Room
I Demister S
P MIAH PX PIC 12V
TI TI LAH
LS
H-10
HC PAL
PS
PY
H-11
S
H-5
From No.3
Ballast Pump
(See 4.12.1a) I-10V
PAHL TX Key
PS TX PX
PI
Sea Water Steam
TIAH PIAH
Inert Gas Condensate
Blowers
H-15 Nitrogen Electrical Signal
PAHL I
PS PI
P
PI Air Instrumentation
Inert Gas
To Oily Fresh Water
to Consumer
Bilge Tank
H-14 H-16 Gas Oil
The gas is further dried in one of two desiccant dehumidifiers, using steam Generator Description
Inert Gas Composition or electrically heated air in the regeneration process, before passing into the
Oxygen (O2): 0.5% (by vol) discharge line. The generator consists of the following main items:
Carbon dioxide (CO2): ~14% (by vol) • Oil burner
Carbon monoxide (CO): Max 100ppm The generator is manually started from the control panels mounted locally and
the operation can be monitored and various valves controlled from the DCS • Ignition burner
Sulphur oxides (SOx): Max 2ppm (normal 1ppm)
graphic display T30-430-01 INERT GAS GENERATOR. • Cooling tower
Nitrogen oxides (NOx): Max 65ppm
Nitrogen (N2): Remainder The inert gas generator contains an O2 analyser for the indication of oxygen • Fuel oil system
content in the inert gas. The analyser is fitted with maximum and minimum • Combustion air system
Fuel Oil Pump setting alarms.
• Cooling water system
Maker: Allweiler AG
The gas is led to the deck main via valves H-10 and H-11 depending on the gas • Drain system
Type: Horizontal screw analysis. The valves are normally operated by the O2 and dew point analysers
• Control, monitoring and instrumentation systems
and the gas is led to the dryer line only when the gas analysis meets with the
Sea water consumption: 933m3/h at 2.0 bar requirements. Under all other conditions the gas is blown to the atmosphere
via valve H-2. Oil Burner
Fresh water consumption: 0.6m3/h
Gas oil consumption: 1,178kg/h The fuel oil burner is of the mechanical high pressure atomising type. The
Working Principle gas oil is directed to the burner tip through tangential slots, which cause the
Steam to air dryer: 10.0 bar at 362°C
oil to leave the burner as a thin rotating membrane. Combustion air is also
Inert gas is produced by the combustion of gas oil supplied by the fuel oil supplied tangentially to the burner, but in the opposite direction which causes
Sea Water Cooling Pumps pump with air, provided by the blower, in the combustion chamber of the further atomisation of the gas oil. The main flame is monitored by a photocell
Maker: Teikoku Machinery Works Ltd inert gas generator. Good combustion is essential for the production of a good connected to an electronic flame relay. This relay will shut down the main
Type: 550VCD Am - centrifugal vertical quality, soot free, low oxygen inert gas. burner, via the main programming unit, if the flame is too weak or has gone
out.
Capacity: 2,800m3/h at 9.0 bar (adjusted to 2.0 bar)
The products of the combustion are mainly carbon dioxide, water and small
Speed: 1,200 rpm
quantities of oxygen, carbon monoxide, sulphur oxides and hydrogen. The Ignition Burner
nitrogen content is generally unchanged during the combustion process and the
The fuel oil burner is ignited by a 10 - 15cm long pilot flame from the ignition
General inert gas produced consists mainly of 85% nitrogen and 15% carbon dioxide.
burner which is fitted alongside. The unit consists of an oil atomising nozzle
and electrical glow plug which operates from a 10V AC transformer, which is
Inert gas is used for the inerting and gas freeing of cargo tanks, cargo pipes Initially, the hot combustion gases produced are cooled indirectly in the
activated approximately 40 seconds before the ignition burner fuel oil valve is
and void spaces when required. The inert gas blowers may be used separately combustion chamber by a sea water jacket. Thereafter, cooling of the gases
opened to admit gas oil to the burner.
for the supply of dried air to the cargo tanks and void spaces. The inert gas is mainly occurs at the scrubber section in the cooling tower where the sulphur
produced by removing oxygen from the air by a combustion process. oxides are washed out. The sea water for the inert gas generator is supplied by
one of three sea water ballast pumps.
This process takes place in a combustion chamber where gas oil is used as the
fuel. A pressure control valve located at the dryer outlet maintains a constant
pressure throughout the system, thus ensuring a stable flame at the combustion
chamber.
Inert Gas
Refrigerant Liquid
To Inert Gas
Electrical Signal
Dryer
PT
Compressor Unit Instrumentation
PT PI
Separator
TT
TP
TI To Vent Line
To Funnel Inert Gas Cooler
TP Oil Rectifier TP
TP
130V S
129V TI
PI
PI TI TW
To Auxiliary
Condenser
Overboard 128V Condenser
Line Demister
140V
PI TI
Pilot Receiver
LI TP
TI
An oxygen analyser is installed and monitors the gas after the water • Alarm reset
separator. • Lamp test
Vent
To Funnel
From Side Wall
10bar Steam
Air HIC
System
A37V
PAL S
PS PI
To Inert Gas PI
Generator Gas Oil Test FI Electric
Service Tank Heater
PI
From Inert Gas FX
Generator Gas Oil
PIAH FI Steam
I
Service Tank HC P Heater
Cooler To Funnel
PI AAHL
PS PI No.2
No.1
Dryer
Dryer
TI
F38V
BSA Nitrogen PI TI S
BE Fan To
131V Atmospheric
Drain
SG SG 127V
From Tank
To Fuel Oil Ballast To Auxiliary Condenser
Drain Tank System Overboard Line
Silencer S
S H-2
TAH
TS S
H-17
PI PI
TS TI
From Fresh Water
Hydrophore Unit
D20V
PI
S PX PIC
To
SG S S Engine
To Inert Gas Cooler From MT Room
I Demister S
P MIAH PX PIC 12V
TI TI LAH
LS
H-10
HC PAL
PS
PY
H-11
S
H-5
From No.3
Ballast Pump
(See 4.12.1a) I-10V
PAHL TX Key
PS TX PX
PI
Sea Water Steam
TIAH PIAH
Inert Gas Condensate
Blowers
H-15 Nitrogen Electrical Signal
PAHL I
PS PI
P
PI Air Instrumentation
Inert Gas
To Oily Fresh Water
to Consumer
Bilge Tank
H-14 H-16 Gas Oil
The unit is fitted to the inert gas outlet and is designed for continuous operation e) Open the gas oil valves from the service tank to supply the q) Check that all air has been evacuated from the cooling jacket
using a twin absorber system. One absorber dries the incoming inert gas while fuel pump. Check the oil level in the tank and replenish if outlet by viewing the flow through the sight glass.
the other absorber is regenerated. The dryers are heated either with steam or necessary.
electrical power which is selected by turning a switch on the control panel. The r) Once the cooling SW flow has been established, press the AUTO
air dryers start automatically when the inert gas generator is started. f) Ensure that the DRAIN TO BILGE selector switch on the mimic START pushbutton for the refrigeration plant. The compressor
panel is turned to position 3, EFFLUENT OVERBOARD. will start 30 seconds later. Throttle the suction valve to maintain
(Note: If the inert gas plant has been shut down for a long period, the dryers Valves H-14 and H-16 will open. a suction pressure of 4 to 5 bar and a discharge pressure of less
should be regenerated manually, ideally two days before use.)
Vent
To Funnel
From Side Wall
10bar Steam
Air HIC
System
A37V
PAL S
PS PI
To Inert Gas PI
Generator Gas Oil Test FI Electric
Service Tank Heater
PI
From Inert Gas FX
Generator Gas Oil
PIAH FI Steam
I
Service Tank HC P Heater
Cooler To Funnel
PI AAHL
PS PI No.2
No.1
Dryer
Dryer
TI
F38V
BSA Nitrogen PI TI S
BE Fan To
131V Atmospheric
Drain
SG SG 127V
From Tank
To Fuel Oil Ballast To Auxiliary Condenser
Drain Tank System Overboard Line
Silencer S
S H-2
TAH
TS S
H-17
PI PI
TS TI
From Fresh Water
Hydrophore Unit
D20V
PI
S PX PIC
To
SG S S Engine
To Inert Gas Cooler From MT Room
I Demister S
P MIAH PX PIC 12V
TI TI LAH
LS
H-10
HC PAL
PS
PY
H-11
S
H-5
From No.3
Ballast Pump
(See 4.12.1a) I-10V
PAHL TX Key
PS TX PX
PI
Sea Water Steam
TIAH PIAH
Inert Gas Condensate
Blowers
H-15 Nitrogen Electrical Signal
PAHL I
PS PI
P
PI Air Instrumentation
Inert Gas
To Oily Fresh Water
to Consumer
Bilge Tank
H-14 H-16 Gas Oil
t) Wait until the LED FLAME ON is energised and the plant is c) Ensure that the DRAIN TO BILGE selector switch on the mimic q) If necessary, adjust the O2 content using the manual loading
running with full capacity and with an acceptable O2 content. panel is turned to position 3, EFFLUENT OVERBOARD. station. Opening the valve will decrease the O2 content and
Valves H-14 and H-16 will open. closing the valve will increase the O2 content.
u) Check that the FO return pressure and the plant temperatures
and pressures are normal. d) Start No.3 water ballast pump and adjust the SW cooling The gas will bypass the dryer via valve H-17 until the O2 is within the preset
pressure to 4.8 bar by controlling valve BA-36, using the DCS limits. The dryer will start approximately 3 minutes after the main burner and
v) If necessary, adjust the O2 content using the manual loading graphic display screen (ballast pumps). the bypass valve H-17 will close.
station. Opening the valve will decrease the O2 content and
closing the valve will increase the O2 content. e) Select the blower required by pressing the pushbuttons for Once the acceptable O2 content, dew point and IG outlet temperature has
either SELECT BLOWER 1 or SELECT BLOWER 1 followed been achieved, press the SELECT CONSUMER pushbutton. The inert gas
w) Once the blowers are running and the refrigeration plant outlet by the START/STOP pushbutton. supply main valve H-1 will open, the vent valve H-2 will close and gas will be
temperature reaches 6°C to 8°C, press the AUTO START supplied to the deck.
pushbutton for the dryers. f) Check that there is a flow through the O2 bubbler unit for
cleaning the sample gas.
x) Once the system is operating correctly, press the REMOTE Procedure for Stopping the Inert Gas Plant
CONTROL pushbutton. g) Check that all air has been evacuated from the cooling jacket
outlet by viewing the flow through the sight glass. a) Press the SELECT CONSUMER pushbutton.
In the Central Control Room The system will change from supplying gas to the deck to venting to
h) Wait for approximately 3.5 minutes for the blower to purge the
y) If the O2 and dew point readings are satisfactory, press the system, then start the FO pump by pressing the START/STOP atmosphere, by the valve H-2 opening and the supply valve H-1 closing.
CONSUMER SELECT pushbutton on the DCS graphic display pushbutton.
T30-430-01 INERT GAS GENERATOR to put the IG plant on b) Press the AUTO STOP pushbutton on the generator panel.
line. i) Select the start capacity by pressing the START CAPACITY
pushbutton. The fuel oil recirculating valve will open, the supply valve will close and the
The gas will be directed to the atmosphere via valve H-2 until the O2 and dew pump will stop. The sea water cooling inlet valve H-5 will remain open and the
point are within the preset limits. j) Energise the ignition glow plug by pressing the GLOW ON air blower will remain running for a preset period in order to cool the system
pushbutton. down.
Once the acceptable O2 content and dew point have been achieved, the inert
gas supply main valve H-11 will open, the vent valve H-2 will close and gas k) Wait for approximately 30 seconds before admitting air and FO (Note: The main IG supply valve H-1 is controlled by the O2 content and dew
will be supplied to the deck. to the igniter by pressing the IGN ON pushbutton. point. If the O2 content is too high or too low and the dew point is too
high, the valve will not open. If either the O2 content, the dryer or the
l) Wait for approximately 3 seconds before admitting FO to the refrigeration plant should reach alarm limits during normal operation,
main burner by pressing the VALVE OPEN pushbutton. the vent valve H-2 will open and the supply valve H-1 will close.)
m) Switch off the glow plug by pressing the GLOW ON When the plant is running the operator should check and record all values on
pushbutton. the locally mounted instruments. Any abnormal values should be investigated
and the fault corrected as soon as possible. Should the O2 content alarm sound
the operator must adjust the O2 content at the manual loading station.
Illustrations
HAMWORTHY 0 1
PUMPS & COMPRESSORS LTD.
POOLE DORSET ENGLAND
GO No. Type
DIAGRAM Issue
VOLTS kW AMPS Hz
P1V Skimmer
P2V Sludge Coarse Sewage Treatment Plant
Return Screen Control Panel
PS From Air
VI Compressor
P14V P20V
Plug Overflow
Emergency
Overflow To
P3V Bilge Holding
P7V LS Tank
Settling
3 Stage Tank
Sewage Collecting
Tank (6m3) Level
P8V Control
LS
PI CI D18V
P4V Macerator
Chlorine
Contact Sludge
Aeration
Return
PI CI 27V From
Fresh Water Sewage Treatment Plant
Hydrophore P25V P23V P17V
Unit (60 Persons/Day)
(Section 2.8.3) CI CI
Vacuum Pumps Discharge Pumps
2 1
(10m3 x 26mth)
PI PI
P26V P24V From Auxiliary Key
Escape Elevator Sea Water
Trunk Trunk Cooling Pump Sea Water
P10V (Section 2.5.2)
Fully Loaded
Water Level Fresh Water
P19V Instrumentation
P11V
Ballast Water Level P28V P12V P13V Drains
Bilge Well
Compressed Air
Bilge Holding Tank P29V Near Aft To Tank Top Electrical Signal
Bilge Well
Closed Water supply valve to float cleaning D18V The swimming pool has a drain valve directly connected to the overboard
CAUTION
Raw sewage may only be pumped to sea in waters where such discharge discharge line from the pool overflow pipe.
Sewage Treatment Plant is permitted and permission from the bridge must be obtained before
the discharge takes place.
Open Sewage plant No.1 discharge pump suction valve P23V
Open Sewage plant No.1 discharge pump discharge valve P24V Daily Checks
Open Sewage plant No.2 discharge pump suction valve P25V
Check that the sludge is being returned to the activation compartment from the
Open Sewage plant No.2 discharge pump discharge valve P26V
settling compartment, and that the discharge pump and blower are working.
Open Discharge pump suction valve
from chlorination chamber Check that the chlorine dosing unit is functioning correctly.
Closed Discharge pump suction valve
from activation compartment Check the operation of the air lift and the air diffusers through the compartment
portholes.
Closed Discharge pump suction valve from
settling compartment
Monthly Checks
Closed Discharge pump suction valve from SW system P17V
Check that air flows are correct and that compartment vents are clear. Clean
b) Switch the sewage collecting tank discharge pump to AUTO the blower suction strainer
operation. This pump will operate in response to the level
switches in the sewage collecting tank and discharge the Waste Water System
contents of the tank to the sewage treatment plant.
Waste water is drained directly overboard through dedicated overboard
c) Switch the sewage collecting tank vacuum pump to AUTO discharge valves.
operation. This pump will operate in response to the vacuum in
the vacuum manifold. Waste drains on the port side of the ship drain overboard through the overboard
discharge valve P19V whilst waste drains on the starboard side drain through
d) The sewage treatment unit should be initially filled with water overboard discharge valve P29V. In both of these drain systems the scupper
and activated sludge added if it has been emptied for any reason drain is via a U-bend.
or when commissioning the plant for the first time. This will not
be required when the unit has been operating previously but the The galley waste system drains overboard through the overboard discharge
description is included for completeness. valve P28V.
Illustrations
Funnel Top
G103V
TC
Silencer
SDX SDX
G163V
G104V G105V
Incinerator G154V
SDX SDX
Control Control
Unit Unit
ODX ODX
PX PI PI PX
G158V TAH TAH G160V
TI TS TS TI
DCS DCS
TI TI
PI PI
PX PX
DCS DCS
G157V G159V
PI PI
G164V
TX
TIAH G145V G147V
DCS
Boiler Drain Tank G146V G148V
(6.0m3)
TI
Generator Engine TX
DCS
Key
PI
PX
DCS
Exhaust Gas
G144V
Electrical Signal
To Deck Scupper To Bilge
Holding Tank To Bilge Line Instrumentation
Introduction
The exhaust gas from the boilers, diesel generator engine and the incinerator
are led to the funnel top. Each outlet is fitted to protrude above the funnel top to
be visible in order to determine if the exhaust gas is clear and not discharging
any carbon products into the atmosphere.
The exhaust gas pipes are suitably lagged to maintain the temperature above
the dew point and so prevent corrosion in the internal surfaces.
The exhaust gas pipes are fitted with drain valves which are permanently open
to discharge any water present into seal pots.
The temperature of the exhaust gases from the boilers is monitored on the DCS
graphic screen T30 452-13 and the generator is monitored by the DCS graphic
screen T30 402-01. The incinerator is fitted with a flue gas temperature high
alarm and trip.
The generator exhaust gas pipe is fitted with a silencer in the funnel section
and each boiler exhaust gas is monitored for O2 and smoke content. An audible
alarm operates when the O2 and smoke content levels reach the set point.
G36V
No.2
Smoke Meter Smoke Meter
Seal Air Fans
(8m3/min)
PAL G35V
PS
DCS
R7 No.1 R7
R8 Economiser Economiser R8
R6 R6
R5 R5
R4 R4
R3 R1 R1 R3
No.1 Main Boiler No.2 Main Boiler
L1 L1
R2 R2
L2 L2
MH Observation Observation MH
Holes Holes
Key
MH O O MH
Air
Manhole Manhole
Electrical Signal
MH MH
G40V Instrumentation G51V
Observation Observation
R Stationary Rotary Sootblower
Hole Hole
Ash Door Ash Door
L Long Retractable Sootblower
Introduction
Due to the boiler casing being under pressure from the combustion gases,
the various penetrations require sealing to prevent the gases leaking into
the engine room.
Sealing is achieved by two seal air fans and bleeding air from the forced
draught fan ducts.
Two seal air fans are supplied, one on standby and the other on duty. The seal
air fan provides cooling and sealing air to the burner flame eyes.
The fans are started locally and the seal air pressure is monitored by the DCS;
an audible alarm operates when the pressure falls to below the set point.
The forced draught fans supply sealing and cooling air to the following:
• Furnace observation holes
• Manholes
• Sootblowers
• Furnace ash door
Gaseous Nitrogen
440V, 50Hz 440V, 50Hz Zero
Electric Supply Oxygen Enriched Air Electric Supply (Gas)
From Control
Fresh Water Cooling GS Air System Panel OAHH OAH
(2.9.2) TAH OIT MAH
S
Compressed Air
XA
XV2A
Electrical Signal Calibration
220V, 60Hz TAH TIC IV4A IV5A
Electric Supply MIT
Control
Panel G49V
Zero
440V, 50Hz
VB Electric Supply (Gas)
FW40V
Control
FW38V Panel OAHH OAH
TAH OIT MAH
S
XA
XV2B
220V, 60Hz TAH TIC Calibration
IV4B IV5B MIT
Control Electric Supply
Panel G50V
PCV3B PI
Water PDI PDI TS TE PCV2B FIT
PI PI XV1B
After Cooler Separator 1B S V2B
Feed Air
M Compressor
No.2 V9B V1B TI FCV1B PAL PAH CV1B
Electric
Heater V4B
N2 60m3/h Membrane Unit S
Oil Cooler Start/Stop Start/Stop
PI
S S S System A System B
XV3B
V20B
To Safety Chamber
V5B V6B V7B
PS PT PS PI
S AD4B
29V
PIAL IV9 IV10 IV11 IV12
DCS
PI
FW41V IV14
FX PX PI Set at PSV1
5bar Set at
FW39V To Cargo System DCS 13bar
(6.2.1) FI Buffer V15
DCS Set at 27V PCV4B 26V Tank
28V V16 18m3
From/To 5.5bar
Central Fresh Water 13 bar
Cooling System
Set at V12 V11
PS PI PI 25V 5bar
To
Boiler Burners
PIAL PIAL V13
(2.4.2) PX 24V PCV4A 23V
DCS DCS
High Capacity Unit The gaseous nitrogen generators are operated locally with alarms and system
Oxygen Analyser
Maker: Air Products conditions monitored from the DCS graphic screen T30-431-01 NITROGEN
GENERATOR. The compressors can be stopped by clicking on the STOP icon A fixed O2 content analyser is installed on the package units and is connected
Nominal flow rate: 2 x 60Nm3/h at 97% N2 before the remotely operated three-way valve.
on the screen alternatively they can be stopped locally in the engine room.
Delivery pressure: 6 / 8 bar
Dew point: -70°C The analyser has the following characteristics, O2 range 0 to 25%, with an
Outlet gas composition: Oxygen 3% by volume output signal of 4-20mA for the remote indicator, alarm panel and three-way
valve actuation.
Carbon dioxide < 30ppm
Nitrogen balance to 100%
Illustrations
Hand Pump
Storage
Tank
(3.4m3)
Expansion Tank
(500 Litres)
Low Oil
Level Alarm
with Test Lever
a1 b2
A C
b1 a2
B D
Directional/ Directional/
L L Pilot Valve M M Pilot Valve
Relief PI PI Relief
R Valve
R Valve
Key
Low Oil Low Oil
Level Switch Hydraulic Oil Level Switch
M with Test Lever M with Test Lever
Drain Pipe
Heating Heating
Element Expansion Pipe Element
Instrumentation
M M
In the event of hydraulic pipe failure in the system of an operating pump the
low level switch in the oil tank of the operating pump will initiate an alarm.
The second pump must be started if not already running and the pump in which
hydraulic failure has occurred must be stopped. The valves connecting the
failed pump to the hydraulic actuator (A and B or C and D depending upon
which hydraulic pump circuit is leaking) must be closed to prevent oil leaking
from the other pump hydraulic system.
The steering gear can continue operating with a single pump. If necessary the
expansion tank must be replenished.
Illustrations
TX
PI PI PI PI
DCS Digital Speed
PI PI Control Panel TI
To/From TI
Alternator Central Fresh Water TI
Air Cooler TIAH
TI TX DCS Cooling System
TX TX
Governor
PS PS PS
Valve PS MPU
Alternator TI
Steam
PIAL TX Stop Valve MPU
PS PI TX
DCS
For T642V
Reduction PI PI
Diesel
Generator TIAL Turbine Gearing TI
DCS
Auto Start
Trip
TX TX
TX Cylinder
Key
TX TX LS LO Cooler for
Over Alternator
Superheated Steam
Speed Bearings
Trip LO Temperature
S PT Desuperheated Steam Control Valve
To DCS
Superheated Trip Solenoid Header PT TI
Steam Lubricating Oil
Valve
From
Main Woodward Electrical Signal
Boilers Governor W
(2.1.1a) Instrumentation
Fresh Water LO
Hydraulic Cooler
Servo Motor Exhaust Steam
TI
LO Pressure TI
T610V Gear Driven Regulating
Main Lubricating Valve
Oil Pump
T609V T643V
To/From
M LO Purifier
Control Air
To Auxiliary M
Condenser
Hand Priming
Pump LI Lubricating
POS POS
From 10 Bar Oil Pump
Steam System M
MAKE-UP SPILL
TX
PI PI PI PI
DCS Digital Speed
PI PI Control Panel TI
To/From TI
Alternator Central Fresh Water TI
Air Cooler TIAH
TI TX DCS Cooling System
TX TX
Governor
PS PS PS
Valve PS MPU
Alternator TI
Steam
PIAL TX Stop Valve MPU
PS PI TX
DCS
For T642V
Reduction PI PI
Diesel
Generator TIAL Turbine Gearing TI
DCS
Auto Start
Trip
TX TX
TX Cylinder
Key
TX TX LS LO Cooler for
Over Alternator
Superheated Steam
Speed Bearings
Trip LO Temperature
S PT Desuperheated Steam Control Valve
To DCS
Superheated Trip Solenoid Header PT TI
Steam Lubricating Oil
Valve
From
Main Woodward Electrical Signal
Boilers Governor W
(2.1.1a) Instrumentation
Fresh Water LO
Hydraulic Cooler
Servo Motor Exhaust Steam
TI
LO Pressure TI
T610V Gear Driven Regulating
Main Lubricating Valve
Oil Pump
T609V T643V
To/From
M LO Purifier
Control Air
To Auxiliary M
Condenser
Hand Priming
Pump LI Lubricating
POS POS
From 10 Bar Oil Pump
Steam System M
MAKE-UP SPILL
a) Open the cooling water valves in and out of the alternator air k) Close the steam line drains.
and bearings cooler and the turbine LO cooler (see section 2.8.1
Central Fresh Water Cooling System). Vent any air from the Having ensured that all operating parameters are correct, the turbine generator
coolers. is now ready to be coupled to the switchboard (see DCS mimic T30-401-02
ELECTRICAL DISTRIBUTION).
h) Turn the engine at least one complete revolution using the f) Open the inlet and outlet cooling water valves on the e) Click on the engine START key, which will start the diesel
turning gear with the cylinder indicator cocks open, or purge alternator. generator engine.
the cylinders by inducing a start procedure.
g) Check that sufficient air is available in the starting air receiver. The diesel generator may now be connected to the main switchboard as
i) Close the cylinder indicator cocks. If not top up by starting the air compressor. described in section 2.15.2. The procedure for starting the diesel generator
from the main switchboard is described in section 2.15.2.
j) Vent the jacket cooling water space.
Under normal circumstances the diesel generator will be started and stopped
The engine oil mist detector samples the atmosphere in each section of
by the power management system as explained in section 2.15.2.
the crankcase and activates an alarm, if the LO mist increases beyond the
allowable concentration, or the detector should fail. The engine will trip if the
Engine Control LO mist concentration reaches the high high level.
The standby status of a diesel generator may be set from its DCS graphic
screen, T30-402-01 if the main switchboard ENGINE CONTROL switch is
Alarms and Trips
in the DCS position. The engine can then be set for either Manual or Auto
The following conditions will activate an alarm on the generator engine safety
start, Manual from the DCS screen and Auto from the PMS system. These
system:
selections are made by activating the soft keys in the graphic display using the
trackball. • Jet system failure
• Tachometer failure
In AUTO the engine is started and stopped as required by the power management
system, with automatic paralleling and removal from the switchboard. • Oil mist high
• Oil mist detector failure
The engine may also be selected for operation from the main switchboard in
which case the ENGINE CONTROL switch is in the MSB position. • Pre-lubrication oil level low
• Engine start failure
The diesel generator will start automatically and close on the switchboard
under the following circumstances: • Safety stop system failure
• Low inlet steam pressure to the running turbine generator (52 • Engine abnormal
bar) • Control power failure
• Low LO pressure to the running turbine generator • Standby engine start
• The governor valve is full open on the running turbine • Fuel leak
generator
• Boiler water low low level alarm
• Boiler water high high level alarm
• Both boilers tripped
Diesel Oil LS LA
Service Tank L
for Emergency
Outside Generator F3V
Emergency (6.0m3)
Generator
Room
F13V
Electric Power Supply Hand Pump
(AC 220V, 2.5KW
Single Phase)
Pressure Cap
0.5bar Coolant Heater
Corrosion (Right Bank)
Resistor (On: 40ºC, Off: 50ºC)
Drain
From To Sludge From
Thermostat Water Manifold Cylinder Head Cylinder Block Emergency Tank Gas Oil
Generator Transfer Pump
(Right Bank) (Right Bank) (Right Bank) (Right Bank)
Water Drain
After Cooler Hole
To Top Tank
(Right Bank)
To Top Tank
After Cooler
TS PS
(Left Bank)
Coolant Heater
Water Pump (Left Bank)
Oil Cooler
Key
Fresh Water
Electrical Signal
Instrumentation
j) When the engine has stopped, check that the heater switch is on, a) Check the level of oil in the engine sump and top up as necessary d) Stop the engine by turning the mode selector switch to
turn the mode selector switch to AUTO operation, and then turn with the correct grade of oil. MANUAL and pressing the STOP pushbutton.
the control panel switch to the AUTO position. b) Check the level of water in the radiator and top up as necessary
with clean distilled water. e) When the engine has stopped, check that the heaters switch on,
turn the emergency switchboard mode selector switch to AUTO
Procedure to Manually Electric Start the Emergency Diesel operation, and then unscrew the shut down knob on the fuel
c) Check the level of diesel fuel oil in the emergency generator
Engine on the Engine Auto Start Control Panel diesel oil service tank and top up as required. pump.
a) Check the level of oil in the engine sump and top up as necessary d) Turn the switchboard mode selection switch to MANU. The engine should to be tested on load every 2 weeks and as there is no means
with the correct grade of oil. of paralleling the emergency generator with the emergency switchboard,
e) On the starboard side of the engine, screw in the red shut down this test has to be initiated by blacking out the emergency switchboard. The
b) Check the level of water in the radiator and top up as necessary knob on the fuel pump. emergency switchboard supplies a number of essential services, such as:
with clean distilled water.
f) On the port side of the engine, press down on the manual 440V Section
c) Check the level of diesel fuel oil in the emergency generator solenoid next to the air starter motor. Release when the engine
diesel oil service tank and top up as required. has fired. • No.2 steering gear
d) Turn the switchboard mode selection switch to the MANU • No.2 central fresh water cooling pump
g) Check that the engine is firing smoothly.
position. • No.1 main sea water cooling pump
h) Check the engine oil pressure, cooling water pressure and rpm.
e) On the engine auto start control panel, turn the selector switch Investigate any abnormalities.
to the MANUAL position. 220V Section
i) Check that the cooling water heaters switch off as the engine • Bridge control console
f) Push the START button. Release when the engine has fired. heats up and that the thermostats operate, to allow cooling water
to flow to the radiator as the engine heats further. • Main turbine remote control system
g) Check that the engine is firing smoothly.
• Engine room gas detection system
j) If required, load the engine, otherwise allow it to run idle for 20
h) Check the engine oil pressure, cooling water pressure and rpm. minutes or stop it. • Radar power supply unit
Investigate any abnormalities.
k) When the engine has stopped, check that the heaters switch on, Due to the fact that the equipment above covers so many areas of the vessel,
i) Check that the cooling water heaters switch off as the engine turn the emergency switchboard mode selector switch to AUTO liaison with various departments/personnel is essential. The load test is only to
heats up and that the thermostats operate, to allow cooling water operation, and then unscrew the shut down knob on the fuel be carried out in open waters and with good visibility.
to flow to the radiator as the engine heats further. pump.
(Note: A blackout of the emergency switchboard will not trip the main turbine
j) If required, load the engine, otherwise allow it to run idle for 20
or cause the bridge control to fail, as this system has dual supplies, ie
minutes or stop it. Procedure for Stopping the Engine after Running on Load from both the main and emergency switchboards.)
k) When the engine has stopped, check that the heater switch is on, a) Shed load from the alternator by opening breaker EG1 and
turn the mode selector switch to AUTO operation, and then turn closing either EB1 or EB2. Procedure to Conduct the Test
the control panel switch to the AUTO position.
b) Allow the engine to idle for 5 minutes before shutting it down a) Ensure that the emergency diesel engine is ready for starting.
to allow the cooling water and lubricating oil to carry away
heat from the combustion chambers, bearings, shafts etc. This b) Advise both the bridge and the Master, to ensure that it is safe
is particularly important for the turbocharger where a sudden to do so.
stop can lead to a 40°C rise, which could damage the bearings
and seals. c) Put the switchboard control to LOCAL on the switchboard.
This will result in the switchboard blacking out and the emergency diesel c) Put the speed selector lever to the STOP position.
generator starting and closing onto the switchboard.
g) After this time, decrease the load to the minimum possible and
open the breaker EG1 and close either EB1 or EB2.
e) Hold down the decompression lever and turn over the engine to
prime the LO system - approximately 10 turns.
2.15.2 Main Switchboard and Generator Operation 2.15.2a Switchboard Generator Control Panels
2.15.7 Preferential Tripping and Sequential Restarting 2.15.3c Main 220V Distribution
2.15.8 Uninterruptible Power Supplies (UPS) and Battery Systems 2.15.3d Cargo 6,600V and 440V Distribution
2.15.9 Cathodic Protection System 2.15.3e Emergency 440V and 220V Distribution
No.2 No.2 No.2 No.1 No.2 No.3 No.4 No.4 No.3 No.2 No.1 No.1 No.1 No.1
6,600/440V 6,600/440V High Duty Port Port Port Port Starbd Starbd Starbd Starbd High Duty 6,600/440V 6,600/440V
MSBD CSBD Comp- Cargo Cargo Cargo Cargo Cargo Cargo Cargo Cargo Comp- CSBD MSBD
Transformer Transformer ressor Pump Pump Pump Pump Pump Pump Pump Pump ressor Transformer Transformer
Key
440 Volts
Air Circuit Breaker
No.2 No.2 No.2 No.1 No.2 No.3 No.4 No.4 No.3 No.2 No.1 No.1 No.1 No.1
6,600/440V 6,600/440V High Duty Port Port Port Port Starbd Starbd Starbd Starbd High Duty 6,600/440V 6,600/440V
MSBD CSBD Comp- Cargo Cargo Cargo Cargo Cargo Cargo Cargo Cargo Comp- CSBD MSBD
Transformer Transformer ressor Pump Pump Pump Pump Pump Pump Pump Pump ressor Transformer Transformer
Key
440 Volts
Air Circuit Breaker
SP: Spare
120: VCB Test Position
121: Generator Running Lamp
SP 123 121 122 125 120 SP: Spare 120 123 121 122 125 166
122: VCB Closed
A2 130 SP 142 131 132 165 A2 130 137 142 131 132 165
120: Ready for Start Lamp 123: VCB Open
SP 137 167 168 139 138 150 SP SP SP 139 138
121: Generator Running Lamp 125: Space Heater Lamp
122: VCB Closed 130: VCB Test Position (TB/TC/TL/DCS)
A1 SY F V 123: VCB Open A1 SY F V 131: DC110V Source
125: Space Heater Lamp 132 DC24V Source
130: VCB Test Position 137: VCB Test Position (TB/TC/TL/SWBD
TL 131: DC110V Source TL 138: DCS Control
W TL TL F V 132 DC24V Source W TL TL F V 139: Local Control
137: Feedback Processing 142: Synpol Fault
138: DCS Control 150: Master Trip
139: Local Control 165: Earthing Switch On
142: Synpol Fault 166: Main Bus Earthing Switch On
161: No.1 Synpol Control Available A1: Excitation Ammeter 0-500A
*
162: No.2 Synpol Control Available *
ERS
Switchboard Generator Section (Diesel Generator) Switchboard Generator Section (Turbine Generator)
@
SYNPOL D
CURRENT POWER
VOLTAGE FREQUENCY
V A Kw
kV kA MW
POWER FACTOR
ALARM
TRIPPED
IMMEDIATE START
Pressing the keys 7 8 9 *
'SHIFT 1' and 'START' 0
STU VWX YZ &
activates an immediate ON/OFF
generator start and START ACTUAL PROG. YES/NO DISPLAY SHIFT
MAN. 4 5 6 BLANK
circuit breaker closure PERCENT EVENT SYNCHRON GRAPH
1 .
IMMEDIATE
JKL MNO PQR /
h) Automatic load sharing is initiated. If the diesel generator fails to start within 20 seconds, fails to synchronise
Procedures for the Automatic Operation of the Diesel
within 60 seconds or the VCB fails to close, an alarm is activated.
Generator and the Main Switchboards A combined diesel generator load shift, disconnection and stop operation is
requested by an operator as follows: (Note: The load percentages and activation times are adjustable via parameters
It is assumed the ship is in normal voyage/in port conditions, ie, at least one on the Synpol unit.)
turbine generator on load and the following conditions are satisfied: a) Select the Electrical Switchboard Control screen, T30-401-01.
• The PMS is switched on. b) Select the relevant VCB to be opened (and therefore the
appropriate generator to be stopped). Click on the VCB icon to
• The diesel generator is switched to AUTO at the MAN/AUTO display the VCB control faceplate window.
selection switch on the generator panels.
c) From the faceplate, select the VCB OPEN function. The
• The switchboard breaker control switches are switched to DCS DCS checks the remaining load will be safely handled by the
control at the CONTROL POSITION selection switches on the remaining generator and sends a stop signal to the Synpol unit.
generator panel.
d) The Synpol unit reduces the load on the generator by lowering
• The diesel generator is ready to start, ie, all engine conditions the generator’s governor until only a small load remains.
are normal. The generator has been selected as standby via the
generator mimic screen. e) The Synpol unit sends an open signal to the generator’s VCB.
The VCB opens.
If the voltage of a generator decreases to between 90% and 95% of the rated c) At 440V switchboard No.1, open the tie breakers LL1 and
value (5,940V to 6,270V) for 5 seconds, the undervoltage tripping device 8. Generator Abnormality Due to Current Differential LB1. The diesel generator DG1 VCB must be open and the
contained in the ACB will operate to trip the breaker. If the current differential on a running generator exceeds 10% of the actual switchboard bus at zero volts.
current for 100msec, the Synpol current differential relay will operate to trip
2. Abnormality Due to Overcurrent (Preference Tripping) the generator VCB. d) At 440V switchboard No.2, open the tie breakers LL2 and
LB2. The diesel generator DG2 VCB must be open and the
If the current on the running generator exceeds 120% of the rated current, ie switchboard bus at zero volts.
439A, for a period of 10 seconds, the PMS will initiate the release of the stage 9. Emergency Generator Overcurrent: (Long Time Delay Trip)
1 preferential trips, thereby providing protection against the overcurrent which If the current on the running emergency generator exceeds 110% of the e) At the emergency switchboard, turn the BUS TIE ACB
would otherwise trip the ACB. If the current still exceeds 120% after a further maximum rated current (1,500A) for 40 seconds the overcurrent relay will CONTROL MODE key switch on the synchronising panel to
5 seconds, the stage 2 preferential trips are released. The preferential trips are operate to trip the generator ACB. the FEEDBACK position.
fully explained in section 2.15.7.
10. Emergency Generator Overcurrent: (Short Time Delay Trip) f) Switch the control position for the bus tie breakers to local by
3. Abnormality Due to Overcurrent (1st Trip) turning the BUS TIE ACB CONTROL SELECTION switch to
If the generator current exceeds 300% of the maximum rated current (4,089A) the ESBD position.
If the current on a running generator exceeds 110% of the rated current, ie the ACB will be tripped almost instantaneously (about 400msec) by the short
403A, for a period of 60 seconds, the Synpol 1st overcurrent trip will operate time delay trip. g) Select which 440V switchboard is to be backfed, No.1 or No.2.
to open the generator’s VCB.
Turn No.1 or No.2 BUS TIE BREAKER CONTROL switch to
11. Emergency Generator Overcurrent: (Preferential Tripping) the CLOSE position. The breakers will close.
If the generator current exceeds 120% of the maximum rated current (1,638A)
for 10 seconds, the emergency switchboard preferential trips will be released.
09.30.2004 19:30 AM
T30-401-01 SWBD CONTROL
GROUP 1 TREND 1 ELECTRICALDISTRIBUTION - SWITCHBOARD CONTROL HIDE
CC2
NR
CC1
CC1,CB2 DCS CC2 & CB2
CB2 CB1 CL1
CL2 DCS DCS CL1
CL2 OPEN
No.2 6.6KV CSBD SWITCHBOARDS NOT IN DCS CTRL No.1 6.6KV CSBD
NO VOLTS
No.2 440V SWBD EM'CY SWBD No.1 440V SWBD
Switchboard Breaker
Faceplate Access
L FEEDBACK L
442 V 439 V Hotspot/Icon
LL2 LB2 LE2 60.0 Hz EB2 EB1 60.0 Hz LE1 LB1 LL1
EG1
NO VOLTS NO VOLTS Switchboard Breaker BREAKER SYMBOL
DCS LOCAL DCS Control Mode Icon AND STATUS
0 A
EG SHORE 0 A
0 kw
SWITCHBOARD POWER MANAG. 6.6 kV SWBD PROTEC. BLACKOUT & BLACKOUT & PMS TRANSF. TEMP
CONTROL SYSTEM CONSUMERS & ALARMS RESTART CTR RESTART SEQ. SEQUENCE INDICATION
b) Turn No.1 or No.2 BUS TIE BREAKER CONTROL switch b) The operator double clicks on the CLOSE or OPEN icon as
to the OPEN position. The bus tie ACB opens and the 440V required. The graphic indication of the breaker flashes until the
switchboard(s) black out. breaker actually closes; the opening of a breaker will be almost
instantaneous and therefore the graphic will not flash (unless
c) At the 440V switchboard generator panel, adjust the frequency there is a fault).
of the running generator to 60Hz by means of the governor
RAISE/LOWER switch on the panel. The network breakers have many interlocks for their switching combinations.
These are fully listed in the DCS manufacturer’s functional specification
d) Turn the CHECK SYNCHRONISER ON/OFF switch to the volume 1, ‘Control of Switchboard Breakers’, section 2, page 7/47.
OFF position.
Local Breaker Operation
e) Turn the diesel generator air circuit breaker ACB CONTROL
OPEN/CLOSE switch to the CLOSE position, the ACB closes The breakers can all be operated locally either with or without the attached
and the generator supplies that 440V switchboard. synchronising equipment. When switched to local operation, the DCS system
has no control of the breaker, however, the DCS system does indicate the
f) Supply consumers as required and return the switchboard and position and status of the network breakers. The DCS will also take corrective
generators to automatic operation, if conditions allow. action in the case of any undesirable situations, provided the DCS has control
of the relevant equipment required. It should be remembered that the DCS will
override a local command, unless the switchboard is set to local control.
Network Circuit Breaker Switching
The normal method of operation for the switchboard breakers and tie breakers
is via the DCS system. The DCS system has all the necessary interlocks
and safety features to ensure safe operation and network power continuity.
Normal operation of the network switching is carried out from the Electrical
Switchboard Control mimic screen, T30-401-01.
Breakers which are not available for DCS control have a small letter ‘L’
(indicating local control) displayed next to the breaker on the mimic.
LL2 LB2 LE2 No.2 440V FEEDER PANEL No.1 440V FEEDER PANEL LE1 LB1 LL1
P-2M-21 Boiler N2H4 Injection Pump P-2M-1 140kW No.2 Boiler FD Fan P-1M-21 No.1 Electric Heater for Steering Gear Room P-1M-1 140kW No.1 Boiler FD Fan
P-2M-22 Vacuum Toilet System P-2M-2 138kW No.1 Windlass/Fwd Winch Hydr. Pump P-1M-22 Panel P2 - Focsle Distribution P-1M-2 138kW No.2 Windlass/Fwd Winch Hydr. Pump
P-2M-23 22kW No.2 Distillate Plant SW Feed Pump P-2M-3 138kW No.3 Windlass/Fwd Winch Hydr. Pump P-P2-1 Focsle Transformer 440/230V 12.5kVA x 4 P-1M-3 138kW No.4 Windlass/Fwd Winch Hydr. Pump
P-P2-2 No.1 Bosun Store Fan
P-2M-24 No.2 Boiler Feed Water Inlet Valve P-2M-4 138kW No.2 Aft Winch Hydraulic Pump P-P2-3 No.1 Forward Fuel Oil Transfer Pump P-1M-4 138kW No.1 Aft Winch Hydraulic Pump
P-P2-4 No.1 Bosun Store Electric Heater
P-2M-25 No.2 Provision Refrigeration Plant P-2M-5 138kW No.4 Aft Winch Hydraulic Pump P-P2-5 No.2 Bosun Store Fan P-1M-5 138kW No.3 Aft Winch Hydraulic Pump
P-2M-26 No.2 Main Air Conditioning Refrigeration Plant P-2M-6 1.3kW Servo Hydraulic Remocon Pump (Aft) P-1M-23 LGSP-1 P-1M-6 1.3kW Servo Hydraulic Remocon Pump (Fwd)
P-EM-25 P-GS3B-11 No.2 Aux. A/C Fan (Emergency Feed) 440 Volts
P3GS3B-12 Spare
LL2 LB2 LE2 No.2 GROUP STARTER PANEL No.1 GROUP STARTER PANEL LE1 LB1 LL1
P-GS2-21 3.7kW Lubricating Oil Transfer Pump P-GS2-1 55kW No.2 Main Condensate Pump P-GS1-21 1.5kW Main Turbine Gland Exhaust Fan P-GS1-1 55kW No.1 Main Condensate Pump
P-GS2-22 0.75kW No.2 Hot Water Circulating Pump P-GS2-2 2.2kW No.2 Recirculation Pump P-GS1-22 0.48kW Main Condenser Sea Water Supply Valve (10V) P-GS1-2 2.2kW No.1 Recirculation Pump
for Main Condenser Vacuum Pump for Main Condenser Vacuum Pump
P-GS2-23 2.2kW Purifier Room Fan P-GS1-23 5.5kW No.1 Domestic Water Hydrophore Pump
P-GS2-24 0.56kW Crossover Bleed Steam Shutoff Valve (102V) P-GS2-3 18.5kW No.2 Condensate Drain Pump P-GS1-24 18.5kW Heavy Fuel Oil Transfer Pump P-GS1-3 18.5kW No.1 Main Condensate Drain Pump
P-GS2-25 0.12kW Auxiliary Condenser Sea Water Inlet Valve (11V) P-GS2-4 2.2kW Main Turbine No.2 Control Oil Pump P-GS1-25 0.75kW No.1 Stern Tube Lubricating Oil Pump P-GS1-4 2.2kW Main Turbine No.1 Control Oil Pump
P-GS2-26 22kW No.2 Boiler Fuel Oil Service Pump P-GS2-5 55kW No.2 Main Condenser Vacuum Pump P-GS1-26 0.37kW No.1 Main FW Pump Turbine Aux. LO Pump P-GS1-5 55kW No.1 Main Condenser Vacuum Pump
P-GS2-27 0.75kW No.2 Stern Tube Lubricating Oil Pump P-GS2-6 250kW Auxiliary Sea Water Circulation Pump P-GS1-27 45kW Main Turbine No.1 Auxiliary LO Pump P-GS1-6 250kW Main Sea Water Circulation Pump
P-GS2-28 0.37kW No.2 Main FW Pump Turbine Auxiliary LO Pump P-GS2-7 80kW No.2 Main Sea Water Circulation Pump P-GS1-28 5.5kW Generator Engine No.1 Start Air Compressor P-GS1-7 7.5kW Fire Line Pressurising Pump
P-GS2-29 100kW
PGS1-31 45kW No.2
Fire Main
PumpTurbine Auxiliary LO Pump P-GS2-8 7.5kW No.2 Boiler Seal Air Fan P-GS1-29 100kW Fire Pump P-GS1-8 7.5kW No.1 Boiler Seal Air Fan
P-GS2-30 5.4kW No.2 Gen. Turbine Exh. Steam Shut-off Valve (41V) P-GS2-9 18.5kW No.2 Auxiliary Central CFW Pump P-GS1-30 0.56kW HP Turbine Bleed Steam Shut-off Valve (110V) P-GS1-9 160kW No.1 Main Central CFW Pump
P-GS2-31 0.06kW Low Sea Chest Valve for Main Circ. System (2V) P-GS2-10 18.5kW No.2 Aux. Central CFW Booster Pump P-GS1-31 0.4kW No.1 Main Feed Water Pump Turbine P-GS1-10 22kW Low Duty Condensate Pump
Steam Inlet Valve (622V)
P-GS2-32 0.82kW Low Sea Chest Valve for GS System (105V) P-GS2-11 1.5kW No.2 Boil-Off Gas Extraction Fan P-GS1-11 18.5kW No.1 Auxiliary Central CFW Pump
P-GS1-32 5.4kW No.1 Generator Turbine Exhaust
P-GS2-33 0.4kW No.2 Main FW Pump Turb. Steam Inlet Valve (633V) P-GS2-12 37kW No.2 Engine Room Supply Fan Steam Shutoff Valve (38V) P-GS1-12 18.5kW No.1 Aux. Cent. CFW Booster Pump
P-GS2-13 37kW No.4 Engine Room Supply Fan P-GS1-33 0.48kW High Sea Chest Valve for Main Circ. System (1V) P-GS1-13 1.5kW No.1 Boil-Off Gas Extraction Fan
P-GS2-34 160kW No.2 Main Central CFW Pump
(Emergency Feed) P-GS1-34 0.82kW High Sea Chest Valve for Aux SW System (101V)
P-GS2-14 5.5kW Diesel Generator Room Exhaust Fan P-GS1-14 37kW No.3 Engine Room Supply Fan
P-GS2-35 5.5kW Generator Engine No.2 Start Air Compressor P-GS2-15 110kW No.2 Bilge, Fire and GS Pump P-GS1-36 1.32kW Generator Engine No.1 Gas Oil Service Pump P-GS1-15 22kW No.1 Engine Room Exhaust Fan
(Emergency Feed)
P-GS2-16 5.5kW MGPS Sea Water Booster Pump P-GS1-35 80kW No.1 Main Cooling Sea Water Pump P-GS1-16 26kW Boiler Cold Start Feed Water Pump
P-GS2-36 1.32kW Generator Engine No.2 Gas Oil Service Pump (Emergency Feed)
P-GS2-17 7.5kW No.2 Fresh Water Hydrophore Pump P-GS1-17 110kW No.1 Bilge, Fire and GS Pump
P-GS2-18 55kW Dump Drain Pump P-GS1-18 0.75kW No.1 Hot Water Circ Pump
P-GS2-19 18.5kW Gas Oil Transfer Pump P-GS1-19 22kW No.1 Boiler Fuel Oil Service Pump
P-GS2-20 5.5kW No.2 Domestic Water Hydro. Pump P-GS1-20 7.5kW No.1 Fresh Water Hydrophore Pump
P-EM-19
P-EM-22 P-EM-26
P-EM-7
EMERGENCY SWITCHBOARD
P-2L-1
17.5kW L-2 Panel in EngineAir
- Control/Working RoomCompressor No.1 P-1L-1 L-1 Panel in Engine Room
P-2L-2 Accommodation 220V AC Feeder Panel P-1L-2 Accommodation 220V AC Feeder Panel
P-4L-1 L4 Accommodation Lighting Panel: A Deck P-3L-1 L3 Accommodation Lighting Panel: Upper Deck
P-4L-2 L6 Accommodation Lighting Panel: C Deck P-3L-2 L5 Accommodation Lighting Panel: B Deck
P-4L-3 L8 Accommodation Lighting Panel: E Deck P-3L-3 L7 Accommodation Lighting Panel: D Deck
P-4L-4 L10 Accommodation Lighting Panel: G Deck P-3L-4 L9 Accommodation Lighting Panel: F Deck
P-4L-5 N1 Navigation Equipment Panel in the Wheelhouse P-3L-5 L11 Accommodation Lighting Panel: Nav. Deck
P-4L-6 G-3 (Pantry Equipment) Panel P-3L-6 G-2 (Galley and Pantry Equipment) Panel
P-4L-7 Duty Mess/Smoke Room Fan, Garbage Store Fan P-3L-7 Wheelhose Window Defrost Fan (S-13) And Heater
P-4L-8 Cargo Control Console P-3L-8 Power Supply for Cargo Gas Detection System
P-4L-9 Bridge Chart Console P-3L-9 Gas Detection System Extension Alarm Panel
P-4L-10 Rudder Angle Indication System P-3L-10 Accommodation Gas Detection System Alarm Panel
P-4L-11 No.2 6.6kV Cargo Swbd (Space Heater Source) P-3L-11 Motor Room Gas Detection System Alarm Panel
P-4L-12 IS Barrier Signal Convertor Panel P-3L-12 No.1 6.6kV Cargo Swbd (Space Heater Source)
P-4L-13 C-JB-COU For CO2 Alarm System P-3L-13 Main Turbine Remote Control System
P-4L-14 Wheelhouse Window Defrost Fan (S-14) And Heater P-3L-14 Wheelhose Window Defrost Fan (S-15) And Heater
P-4L-15 Spare Key P-3L-15 Spare
P-2L-5 Boiler Local Gauge Board P-1L-7 Switch Box for Main Turbine Bolt Heater
P-2L-7 Switch Box for Main Turbine Bolt Heater P-1L-9 Vibration Measuring Unit
P-2L-15 Spare
P-2L-16 Spare
CC2 No.2 6.6kV CARGO SWITCHBOARD No.1 6.6kV CARGO SWITCHBOARD CC1
No.2 No.2 No.1 No.2 No.3 No.4 No.4 No.3 No.2 No.1 No.1 No.1
6,600/440V High Duty Port Port Port Port Stbd Stbd Stbd Stbd High Duty 6,600/440V
CSBD Comp- Cargo Cargo Cargo Cargo Cargo Cargo Cargo Cargo Comp- CSBD
Transformer ressor Pump Pump Pump Pump Pump Pump Pump Pump ressor Transformer
LB2 LB1
P-2CS-1 280kW No.2 Low Duty Gas Compressor P-1CS-1 280kW No.1 Low Duty Gas Compressor
P-2CS-2 22.4kW No.3 Spray Pump P-1CS-2 22.4kW No.1 Spray Pump
P-2CS-3 22.4kW No.4 Spray Pump P-1CS-3 22.4kW No.2 Spray Pump
P-2CS-4 1.8kW No.2 High Duty Compressor Auxiliary LO Pump P-1CS-4 1.8kW No.1 High Duty Compressor Auxiliary LO Pump
P-2CS-5 1.8kW No.2 Low Duty Compressor Auxiliary LO Pump Key P-1CS-5 1.8kW No.1 Low Duty Compressor Auxiliary LO Pump
P-2CS-8 35kW No.2 Nitrogen Generator Feed Air Compressor P-1CS-8 35kW No.1 Nitrogen Generator Feed Air Compressor
Transformer
P-2CS-9 2.2kW No.2 Under Deck Passage Exhaust Fan P-1CS-9 30kW Double Bottom Pipe Duct Exhaust Vent Fan
P-2CS-10 3kW No.2 Feed Air Heater for Nitrogen Generator System P-1CS-10 2.2kW No.1 Under Deck Passage Exhaust Fan
6,600 Volts
P-2CS-11 3.7kW Top-up Water Ballast Valve Remocon Hydraulic Pump P-1CS-11 3 kW No.1 Feed Air Heater for Nitrogen Generator System
440 Volts
P-2CS-12 37kW No.2 Cargo Valve Remecon Hydraulic Pump P-1CS-12 37kW No.1 Cargo Valve Remocon Hydraulic Pump
P-2CS-13 11kW No.2 Water Ballast Valve Remocon Hydraulic Pump P-1CS-13 7.5kW Top-up Cargo Valve Remocon Hydraulic Pump
P-2CS-14 Spare P-1CS-14 11kW No.1 Water Ballast Remocon Hydraulic Pump
LL2 LB2 LE2 EB1 EMERGENCY 440V SWITCHBOARD EB2 LE1 LB1 LL1
220V SECTION
A W V PSI
PST
WHM
BCS
Key
A: Ammeter
V: Voltmeter
W: Wattmeter
F: Frequency Meter
WHM: Watthour Meter
AS-1: Ammeter Selection Switch
ACB 3P FVS-1: Frequency and Voltmeter Selection Switch
HAT-16(1600AF) BCS: ACB Control Switch
141: Shore Alive Lamp
142: Shore ACB Closed Lamp
143: Shore ACB Open Lamp
VOLTAGE FREQUENCY
TL
F 138: DCS Other POWER FACTOR
W TL TL V Generators
ALARM
139: Local
TRIPPED
SY: Synchroscope
162 161 Lines
W: -4,500-0-4,500 Wattmeter Diesel Engine
F: 55-65Hz Frequency Meter Governor
V: 0-9,000V Voltmeter
Current
LT ES TL: Synchronising Lamps Sensing
COS-P ECS VCS-D COS-P: Generator Control Switch
(Manual/Automatic) 4
ECS: Engine Control Switch (Stop/Start)
2
LT: Lamp Test 22 24 AVR
AS-1 FVS-2 PRE VCS-D: VCB Control Switch 26 3 Phase
COS-M DGCS
ES: Emergency Stop 11 25 440V 60Hz Output Alternator Key
AS-1: Ammeter Selection Switch 1. Frame
COS-M: Breaker Control Switch: 2. External Equipment Housing
SWBD/DCS 8 3. Earthing Terminal
CTT PTT1 VR FVS-2: Frequency/Voltmeter Switchboard 4. Housing Cover
Selection (Off/R.S/S.T/T.R/Off) 5. Shaft: Prime Mover
DGCS: Governor Control Switch 6 6. Fan
Excitation 15 7. End Shield
COS-VR MVR SHS
PRE: Pre-excitation Button 16 8. Air Guide
7
CTT: Current Test Terminals - Current on Gen. Side 9. End Shield
137 9
COS-VR: Voltage Control (Manual/Automatic) 10. Stator Core
GL MVR: Manual Voltage Regulator 21 11. Stator Winding
PTT1: Potential Test Terminals - Potential AC110V (Gen) 12. Rotor Core
DG1
24 21
SHS: Space Heater Switch 23 13. Damper Winding
14. Rotor Winding
15. Exciter Stator Core
16. Exciter Stator Winding
17. Exciter Rotor Core
18. Exciter Rotor Winding
Alternator AVR 19. Rotating Rectifier
Excitation Supply 20. Rectifier Lead to Rotor Winding
AVR 23 21. Sleeve Bearing
22. Air/Water Cooler
23. Protection Cover
5 17 24. Generator Side Automatic
(Construction of
1 14 13 3 10 12 20 19 Voltage Regulator
Diesel and Steam Turbine 18
Alternators is Virtually Identical) 25. Current Transformers
Switchboard Generator Section (Diesel Generator) 26. Air Opening
Hyundai Alternator
Two main steam turbine alternators and one main diesel generator are fitted. The alternators have a pre-excitation facility which can be used in exceptional
They are all of the totally enclosed, cylindrical rotor, self-excited, brushless circumstances if the alternator rotors lose their residual magnetism and do not
type fitted with an integral air to fresh water cooler. automatically excite on running up. This applies 24V DC directly to the exciter
stator to excite the rotor.
Generator cooling is provided by passing air over the integral fresh water
cooler, using a closed circuit air supply. The cooling air temperature can be The current transformers (CTs) used for monitoring and also as current/load
monitored via the DCS system generator screen mimic. The cooler is fitted reference for the Synpol units are also located within the main top cover.
with double-walled tubes to reduce the chances of leakage. The space between
the tubes drains to a chamber where a leak detector will activate an alarm if The electrical power network fed by the generators is designed with
water is detected. discrimination on the distribution system, so that the generator breaker is the
last to open if any abnormalities occur.
Space heaters are fitted which are energised when the generator circuit breakers
are open. These protect against internal condensation during shut down periods. One steam turbine generator normally provides electrical power under normal
There are 6 embedded PT100 sensors fitted to monitor the stator temperature conditions at sea and in harbour, with the diesel generator on standby. During
in each phase winding, 3 are in use and there are 3 spare. These temperatures standbys, manoeuvring or cargo operations, 2 turbine generators should be on
can be monitored from the DCS screen mimics and will raise alarms when the load supplemented by the diesel generator if required.
temperature set points are exceeded.
In any of the above cases where two or more generators are on load, one
The screen mimics are T30-402-01 for the diesel generator and T30-404-01/2 generator has enough capacity to supply the total load after the operation of
for No.1 steam turbine generator and T30-404-03/04 for No.2 steam turbine the preference trips.
generator.
EMERGENCY SWITCHBOARD
The generator’s automatic voltage regulator (AVR) is fitted within the c) The emergency generator operation switch is set to AUTO at the
alternator terminal cover. There is a potentiometer inside the generator cubicle generator engine control panel.
to enable the voltage to be manually adjusted.
d) At the generator panel of the emergency switchboard, the
The generator ACB’s undervoltage trip (UVT) has an energising key switch operator turns the ENGINE CONTROL switch to the START
fitted inside the generator cubicle which will close the undervoltage trip and position. The emergency generator engine starts via its electric
enable the ACB to be closed under certain fault conditions. starter motor.
The generator is fitted with a space heater to prevent condensation when the The sequence now follows e) and f) as before.
generator is stationary or idling. The heater is interlocked with the generator
ACB.
The generator has sufficient capacity to enable the starting of the required
machinery to power up the vessel from a dead condition.
EMERGENCY SWITCHBOARD
Ensure the emergency generator is set up for automatic start. The bus tie breaker EB1 or EB2 will open and the emergency switchboard
will black out. The emergency generator will start automatically and the
generator ACB will close to feed the emergency switchboard. The procedure
is as follows:
First Stage P-1M-16 Workshop Unit Cooler Second Stage P-HM1-2 No.1 Ballast Pump
Preference Trips Preference Trips
P-1M-18 No.1 MGPS PSU for Scoop System 15 Seconds P-HM1-3 No.2 Ballast Pump
10 Seconds
P-1M-19 MGPS PSU for General SW System PT2 P-HM2-2 No.3 Ballast Pump
PT1
P-1M-21 No.1 Electric Heater Steering Gear Room P-GS1-17 No.1 Fire, Bilge and GS Pump
P-1M-28 No.1 Provision Refrigeration Plant P-1M-11 No.1 Inert Gas Generator Blower
P-1M-29 No.2 Main Air Conditioning Refrigeration Plant P-1M-12 Inert Gas Generator Fuel Oil Pump
P-2M-9 ICCP System Aft P-1M-14 Inert Gas Generator Air Drying Unit
P-2M-10 ICCP System Forward P-2M-12 No.2 Inert Gas Generator Blower
P-2M-11 P1 Panel E/R Workshop Equipment P-GS2-15 No.2 Fire, Bilge and GS Pump
P-2M-13 Galley, Pantry and Laundry Panel G1 P-GS1-17 No.1 Fire, Bilge and GS Pump
P-2M-14 No.2 Electric Heater for Steering Gear Room P-MCS1-1 No.1 Cargo Pump (Starboard)
P-2M-19 No.2 MGPS PSU for Scoop System P-MCS1-2 No.2 Cargo Pump (Starboard)
P-2M-25 No.2 Provision Refrigeration Plant P-MCS1-3 No.3 Cargo Pump (Starboard)
P-2M-26 No.2 Main Air Conditioning Refrigeration Plant P-MCS1-4 No.4 Cargo Pump (Starboard)
P-2M-34 Boiler Test Room Unit Cooler P-MCS2-2 No.2 Cargo Pump (Port)
P-3L-6 Galley, Pantry and Laundry Panel G2 P-MCS2-3 No.3 Cargo Pump (Port)
P-4L-6 Pantry and Laundry Panel G3 P-MCS2-4 No.4 Cargo Pump (Port)
P-P2-7 No.2 Electric Heater for the Bosun's Store EB2 No.2 Main 440V Switchboard
PT-E
P-P2-8 Electric Heater for the Bow Thruster Room
Preferential Tripping
The power management system matches the generator capacity to the power
requirements of the vessel. However, should an overcurrent occur for any main
generator, non-essential services will be tripped.
If the current still exceeds 132% after a further 5 seconds, the stage 2
preferential trips are released.
When normal conditions resume, the above breakers must be manually reset.
FULL BLACKOUT
(Zero Volts at all Main Switchboards)
TIME STAGE
3 Seconds
5 Seconds
0 Seconds
Main Diesel Generator Engine Main Condenser SW Supply Valve (110V) Close
No.2 Gas Oil Pump Starts Restart No.1 Main CSW Pump
Auxiliary Condenser SW Supply Valve (111V) Close At 31 Seconds Stage 10
Start Generator Engine No.1 Gas Oil Service Pump If Start Fail, Start No.2 Main CSW Pump
At 0 Seconds Restart Engine Room Supply Fan No.2 Stage 1
Start No.2 W.B. Valve Remocon Hydraulic Pump
Main Diesel Generator Engine Starts Start No.2 Cargo Valve Remocon Hydraulic Pump 3 Seconds
Restart No.1 Steering Gear
2 Seconds 3 Seconds
3 Seconds
and the ‘restart after blackout sequence’ is initiated. Restart Engine Room Supply Fan No.1 At 31 Seconds If Start Fail, Start No.1 Main Cent. CSW Pump Stage 10
Restart No.2 WB Valve Remocon Hydraulic Pump
Restart No.2 Cargo Valve Remocon Hyd. Pump
The restart sequence is usually left enabled, however, the operator may disable Restart No.2 Steering Gear 4 Seconds
the sequence from the SWITCHBOARD CONTROL screen mimic, T30-401- i)Restart No.2 Main Condenser Vacuum Pump
3 Seconds ii)Restart No.2 Condenser Drain Pump
01. If the sequence is disabled, an ‘auto start sequence disabled’ alarm is raised. At 35 Seconds Stage 11
Once under way, the restart sequence may be halted by the operator from the At 3 Seconds
Restart No.2 Cargo Motor Room Supply Fan
Restart Engine Room Supply Fan No.4 Stage 2
i)If Start Fail, Start No.1 Main Cond. Vac. Pump
ii)If Start Fail, Start No.1 Cond. Drain Pump
DCS screen. The sequence is automatically halted in the case of another
3 Seconds
blackout. 2 Seconds
i)Restart No.2 Aux. Cent CFW Pump
ii)Restart No.2 Aux. Cent CFW Booster Pump
Once the restart sequence has started it may be stopped in one of two ways: At 5 Seconds Start Starboard Boiler F.D. Fan (Standby Fan) Stage 3 At 38 Seconds iii)Restart No.2 Boiler Seal Air Fan Stage 12
iv)Restart No.2 Stern Tube LO Pump
1. Manually cancelled by an operator from the DCS screen mimic 5 Seconds i)If Start Fail, Start No.1 Aux Cent CFW Pump
ii)If Start Fail, Start No.1 Aux Cent CFW
number T30-401-05 Restart No.2 Main Turbine Auxiliary LO Pump Booster Pump
iii)If Start Fail, Start No.1 Boiler Seal Air Fan
At 10 Seconds Stage 4 iv)If Start Fail, Start No.1 Stern Tube LO Pump
If Start Fail, Start No.1 Main Turbine Auxiliary LO
2. Another blackout occurring during the sequence Pump
3 Seconds
Less important motors that were selected for duty before the blackout will 2 Seconds Restart No.2 B.O.G. Extraction Fan
be automatically returned to duty when power is restored. Similarly, motors Start Port Boiler FD Fan (No. 2 Fan)
At 41 Seconds If Start Fail, Start No.1 B.O.G. Extraction Fan Stage 13
At 12 Seconds Stage 5
selected for standby will automatically return to standby. If the machinery
designated for duty does not restore normal system conditions, such as pressure, 5 Seconds 3 Seconds
within a preset time, the standby motor will cut in automatically. If power is Restart No.2 Engine Room Exhaust Fan
only restored to the emergency switchboard, motors whose supply is from the Start No.2 Control Air Compressor
i) Restart No.2 Control Oil Pump At 44 Seconds Stage 14
emergency switchboard will start irrespective of any previous selection. ii) Restart No.2 Main Condenser Pump
At 17 Seconds Stage 6
i) If Start Fail, Start No.1 Control Oil Pump
ii) If Start Fail, Start No.1 Main Condenser Pump
3 Seconds
Engine Room
DCS
Anode Reference Cell Monitoring Panel Anode Reference Cell Shaft Millivolt
Monitoring Brushes
(Insulated From
Earth/Mounting)
JB JB JB JB
JB JB JB JB
2.16.4 Engine Control Room and Main Switchboard Room Air Conditioning Units
2 16.5 Workshop and Boiler Water Test Room Air Conditioning Units
Illustrations
2.16.4a Engine Control Room and Main Switchboard Room Air Conditioning Units
Key
Refrigerant Gas
Refrigerant Liquid
Lubricating Oil
To/From Provisions Storage Rooms
Fresh Water
Electrical Signal
Instrumentation
ENGINE ROOM
DPS PI PT PI PI PT PI DPS
Oil Oil
Separator Separator
PT PT
Compressor Compressor
Purging Purging
PS PI TI TI PI PS
The evaporators accept the refrigerant, as a supercooled vapour, from their d) Start a central FW cooling pump if it is not already operating.
Introduction
expansion valves. The opening of the expansion valve is controlled by the Open the condenser cooling water inlet and outlet valves (see
The plant is situated on the port side aft on the 2nd deck level. The temperature in the particular chamber serviced by the evaporator. This vapour section 2.8.1) and supply cooling water to the condenser.
refrigeration plant is automatic in operation and consists of two reciprocating is heated as it passes through the evaporator and the hot vapour is then
piston type compressors, two condensers and an evaporator coil in each of returned to the compressor through the non-return valves. e) Purge air completely from the cooling water system by opening
the refrigerating rooms. the air purger on top of the condenser or the air purging valve on
The solenoid valves at the air coolers (evaporator units) are opened and closed the pipeline. Check the compressor’s smoothness by manually
Details of the refrigerated rooms covered are as follows: by the room thermostats allowing refrigerant gas to flow to the evaporator turning it over.
when open. With the solenoid valves closed, no gas flows to the evaporators
Compartment Volume Temperature and so no gas flows back to the compressor suction and the low pressure f) Start the compressor on automatic operation.
Meat room 51.2m3 -25°C switch will stop the operating compressor.
Deep freeze room 36.5m3 -25°C g) Adjust the suction stop valve gradually until fully open.
Vegetable room 36.5m3 +1°C Any leaks of refrigerant gas from the system will result in the system
becoming undercharged. The symptoms of the system undercharge will be The compressor will operate but will stop automatically due to the low
Dairy room 33.4m3 +3°C
low suction and discharge pressures with the system eventually becoming pressure cut-out as no gas is flowing in the system.
Lobby 42.2m3 +3°C
ineffective. Bubbles will appear in the liquid gas flow sight glass.
Cooling for the refrigerated rooms is provided by a direct expansion R404A Checklist During Operation
When required, additional refrigerant can be added through the charging
system. Liquid R404A gas is passed to the evaporator coils in the rooms and
line, after first venting the connection between the refrigerant bottle and • Check the inlet and outlet pressure gauges
the expansion valve regulates the amount of gas flowing to the evaporator in
the charging connection, in order to prevent any air in the connection pipe
accordance with the current room temperature. The gas expands through the • Check the compressor oil level
entering the system.
expansion valve and extracts heat from the evaporator over which air from the
room is passed. Air in the cold rooms is circulated through the evaporator coils • Check the system for gas leakages
The added refrigerant is dried before entering the system. Any trace of
by electrically driven fans. The supply of refrigerant to the expansion valve is
moisture in the refrigerant system will lead to problems with the thermostatic
regulated by means of a solenoid valve in the supply line.
expansion valve icing up and subsequent blockage.
c) The thermostatic expansion valves will regulate the flow of gas System Running Checks to be Carried Out at Regular Intervals
to the evaporators. The system will operate automatically with
the compressor stopping due to the low pressure cut-out when • Check the lubricating oil level in the crankcase.
the return gas flow has reduced because the expansion valves
• Check the moisture indicators on the gas flow system.
are closed or the temperature controlled solenoid valve has
closed. • Check the suction and discharge pressure and temperature. Any
unusual variations should be investigated.
d) Open the refrigerant supply valves to the other refrigerated • Check all the room temperatures and evaporation coils for any
rooms until all rooms are in operation. As each room is put sign of frosting.
into service, check the operation of the compressor and the
system, to ensure that the room temperature is falling and that • Check for leaks if the level of gas in the system appears to
no refrigerant gas is being lost from the system. have fallen.
Procedure for Defrosting the Refrigerating Room Evaporator Procedure for Stopping the Plant for a Short Period
The evaporators and drip trays in the refrigerating rooms are fitted with a) Close the liquid supply line valve to the evaporator for 5
electrical defrosting equipment. The frequency of defrosting is chosen by minutes before stopping the plant.
means of a defrosting relay built into the starter panel. The defrosting
sequence is automatic and as follows: b) When the compressor stops on the low pressure cut-out, press
STOP on the control panel.
a) The compressor stops and all the solenoid valves in the system
close. c) When the compressor has stopped, close the suction and
discharge stop valves.
b) The fans in the freezer rooms (deep freeze and meat) stop
working but the fans in the cooling rooms continue the
circulation of the warm air over the coolers, thus keeping the
Procedure for Stopping the Plant for a Long Period
cooling surfaces free from ice.
a) Close the main stop valve after the condenser to evacuate the
evaporators.
c) The electrical heating elements in the refrigerating room are
switched on.
b) Allow the temperature to rise in the evaporators.
d) As long as the coolers are covered with ice, the melting takes
c) When the suction pressure is slightly above atmospheric, stop
nearly all of the heat supplied and the temperature of the
the compressor and close the suction and discharge stop valves.
cooler and the refrigerant is constantly kept near zero. When
The liquid refrigerant gas will be stored in the condenser.
the ice has melted, the refrigerant temperature rises in the
freezer room. When the temperature reaches the set point
d) Stop the condenser cooling water, shut the valves and drain the
(approximately +10°C) of the defrosting thermostat, the heating
water space of the condensers.
elements are switched off.
e) Switch off the main and control circuit electrical supplies.
e) The compressor restarts.
f) Examine the system for leaks by using a gas leak detector.
Lubricating Oil
Fresh Water
Electrical Signal
To Engine S S To Engine
Room Instrumentation Room
Humidity Control
From
6bar Steam
System
Unit 2 Unit 1
T P T P
HT LT OT HP LP OP HT LT OT HP LP OP
Oil Oil
Oil Separator Oil Separator
Separator Separator
HP HP
LP LP
Oil Purifier Oil Purifier
S Compressor S S Compressor S
S EVR S EVR
10 10
BMSL BMSL
Purging 12 Purging 12
PS PI
PS PI
TI TI TI TI
Starting the Air Conditioning Compressor Procedure for Stopping the Compressor for Short Periods e) Close the cooling water inlet and outlet valves and drain the
a) All stop valves, except the compressor suction, in the refrigerant condenser of water.
line should be opened and fully back seated to prevent the a) Close the condenser liquid outlet valve and the outlet from
pressure in the valve reaching the valve gland. the filter. f) The compressor discharge valve should be marked closed and
the compressor motor isolated, in order to prevent possible
b) The crankcase heater on the compressor to be used should be b) Allow the compressor to pump out the system to the liquid damage.
switched on a least 3 hours prior to starting the compressor. receiver so that the low level pressure cut-out operates.
WARNING
c) Isolate the compressor motor. It is essential that no water should be lying in the air conditioning
c) Check that the crankcase oil level is correct.
system as this can become a breeding ground for legionella bacteria
d) Close the compressor suction valve. which can have serious, or even fatal, consequences. The drain should
d) Check the quantity of refrigerant charge.
be kept clear and areas where water can lie should be sterilised at
e) Close the compressor discharge valve. frequent intervals.
e) Start the cooling water supply for the condenser cooling.
The cooling water comes from the engine room central fresh
water cooling system and will probably already be running. f) Close the inlet and outlet valves on the cooling water to the
Ensure that the supply and return valves to the air conditioning condenser.
condensers are open. Check that the supply of water from the
central cooling system is correct. g) Switch on the crankcase heater.
Lubricating Oil
Saturated Steam
Fresh Air Fresh Air
Condensate/HP Feed Water
Fresh Water
Electrical Signal
To Engine S S To Engine
Instrumentation
Room Room
Humidity Control
From Vent to Open Air
6bar Steam
System
HSV32
SCV65
DPS PI DPS PI
PS PS PS PS PS PS PS PS
PT PT
Compressor Compressor
Purging Purging
PT PT
PI TI PI TI
e) Start the cooling water supply for the condenser cooling. The e) Close the compressor discharge valve.
cooling water comes from the central FW cooling system
and will probably already be running. Ensure that the supply f) Close the inlet and outlet valves on the cooling water to the
and return valves to the air conditioning condensers are open. condenser.
Check that the supply of water from the central cooling system
is correct. g) Switch on the crankcase heater.
a) Shut the liquid outlet valve on the condenser and the outlet
i) Adjust the suction stop valve gradually until it is fully open,
from the filter.
when the compressor starts making a knocking noise close the
valve immediately. When the noise stops open the valve again.
b) Run the compressor until the low pressure cut-out operates. The
Repeat this operation until the noises completely disappear.
refrigerant gas will be condensed in the condenser and it will
Compressor Running Checks remain there as the condenser outlet valve is closed.
• Check the inlet and outlet pressure gauges. c) After a period of time the suction pressure may rise, in which
• Check the oil level and pressure. Check for crankcase foaming. case the compressor should be allowed to pump down again,
until the suction pressure remains low and the compressor does
• Check for gas leakages using the appropriate equipment. not start again automatically.
• The lubricating oil pressure should be checked at least daily.
d) Shut the compressor suction and discharge valves.
• The oil level in the crankcase should be checked daily.
• The suction and discharge pressure should be checked twice e) Close the cooling water inlet and outlet valves and drain the
per day. condenser of water.
• The temperature of oil, suction and discharge should be
checked twice per day. A twice daily check on the motor f) The compressor discharge valve should be marked closed and
bearing temperature should also be kept. the compressor motor isolated, in order to prevent possible
damage.
• A check should be kept on shaft seal oil leakage.
WARNING
It is essential that no water should be lying in the air conditioning system
Procedure for Stopping the Compressor for Short Periods as this can become a breeding ground for legionella bacteria which can
have serious, or even fatal, consequences. The drain should be kept clear
a) Close the condenser liquid outlet valve and the outlet from
and areas where water can lie should be sterilised at frequent intervals.
the filter.
Saturated Steam
Fresh Water
Electrical Signal
Instrumentation
To Engine S S To Engine
Room Room
Vent to
Open Air
Humidity Control
From
6bar Steam
S
System TI
S TI
SCV65 EVR32 HSV32
SCV65
EVR32 HSV32
HSV32
SCV65
DPS PI DPS PI
PS PS PS PS PS PS PS PS
PT PT
Compressor Compressor
Purging Purging
PT PT
PI TI PI TI
• The temperature of oil, suction and discharge should be f) The compressor discharge valve should be marked closed and
checked twice per day. A twice daily check on the motor the compressor motor isolated, in order to prevent possible
bearing temperature should also be kept. damage.
• A check should be kept on shaft seal oil leakage.
WARNING
It is essential that no water should be lying in the air conditioning system
Procedure for Stopping the Compressor for Short Periods as this can become a breeding ground for legionella bacteria which can
have serious, or even fatal, consequences. The drain should be kept clear
a) Close the condenser liquid outlet valve and the outlet from and areas where water can lie should be sterilised at frequent intervals.
the filter.
f) Close the inlet and outlet valves on the cooling water to the
condenser.
Boiler Test Room Package Air Conditioning Unit Workshop Air Conditioning Unit Valve
Maker: Century Cooling fresh water inlet valve W73V
No. of sets: 1 Cooling fresh water outlet valve W51V
Model: MP-G3HF5
Type: Heating and cooling with R404A refrigerant unit and Boiler Test Room Air Conditioning Unit Valve
electric heater
Cooling fresh water inlet valve W122V
Heating capacity: 7,740kcal/h Cooling fresh water outlet valve W126V
Cooling capacity: 8,000kcal/h
b) Ensure that cooling water is flowing through the condenser of
the air conditioning unit.
The units are similar in design except that the workshop unit has two
refrigeration compressors, condensers and evaporators. The refrigeration c) Check the level of lubricating oil in the refrigeration compressor
circuits of the workshop unit are separate and the unit may operate with and check that the compressor motor drive is free.
either or both working.
d) Ensure that electrical power to the air conditioning unit is
The refrigeration unit is located at the bottom of the air conditioning cabinet switched on. The power should be turned on for some time
and the evaporator is located above the refrigeration section. Above the before the unit is started in order to warm the lubricating oil.
evaporator coils is the heater and above that the fan. The fan draws air from
the workshop or boiler water test room and passes it over either the evaporator e) Select the desired room temperature at the thermostat.
coils or the heating element, before discharging it back into the workshop or
boiler water test room. A suction filter is fitted at the air inlet to the package f) Press the fan START pushbutton and check that the fan is
air conditioning unit. This filter must be cleaned at frequent intervals in order working correctly.
to ensure that the air flow across the heater/cooler is adequate.
g) At the selector switch select HEAT or COOL as required and
The condenser unit is cooled by water circulating from the central fresh water then press the PA. START pushbutton to start the heating or
cooling system. This system must be operating and the supply and return cooling system operating.
valves opened before the package unit can be put into operation.
The package air conditioning unit will operate automatically and maintain the
The control at the front of the package air conditioning unit contains a switch for desired temperature in the room. Gauges are provided at the front of the unit
selection of heating or cooling, the positions being marked HEAT and COOL. showing the compressor discharge pressure and the evaporator pressure.
A STOP pushbutton allows the unit to be stopped and a START pushbutton
starts the fan. A pushbutton marked PA. START starts the cooling or heating A thermostat regulates the electric heater from overheating and a fuse is fitted
system depending upon which has been selected by the selector switch. to the circuit to protect in the event of excess current.
IL Primary
Combustion Secondary
Combustion PU1
Chamber
POV2 Chamber
POV IL1 TS L
CP2
MS3
Incinerator FNV1
TS H
POV1 (500,000 Kcal/h) F308V Incinerator Waste Oil
Service Tank
(3.0m3)
C5 F316V F313V
PI PU5 CI LS L
RV3
LS H
LS
PU3 M3 From F304V
PS3
PI TR Fuel Oil (26m3/h x 0.4bar)
TV3
MV8 MV7 Drain Tank
F1 F314V
F305V
MV4
From F306V
GS Air
317V
System
307V
T502V
• Wet solid waste must not be put into the primary combustion • Combustion chamber temperature high
(Note: If the DELAY PRIMARY BURNER is switched to the automatic chamber more than one hour before starting the incinerator. • Fan motor trip
position (AUT), the primary burner will operate for 25 seconds to
ignite the sludge burner automatically. If the DELAY PRIMARY • Waste oil pump motor trip
• When burning oil-containing materials, such as filter cartridges,
BURNER is switched to the manual position (MAN) the primary oily cotton waste, and scrapings from the centrifuges, do not • Low combustion air pressure
burner operates all of the time together with the sludge burner.) put more than 5 litres per charge into the primary combustion
• Low combustion chamber negative pressure
chamber.
• Low atomising air pressure
Adding Solid Waste to the Incinerator
• When burning material with high calorific value with explosion- • Feeding door open
Before adding a new charge of solid waste, look through the sight glass to like combustion such as plastic, the maximum charge must
not exceed 3.0kg. • Pre-purge not complete
ensure that the incinerator is ready to receive more waste. Additional solid
waste can only be added when the primary combustion chamber has cooled • Waste oil tank low level
and the temperature interlock on the feeding door has been released. The • DO NOT overload the incinerator with waste. Ensure a
• Waste oil tank high temperature
feeding door is blocked when the primary combustion chamber temperature maximum 70,000kcal per charge or 20% of the volume of the
is above 145°C. primary combustion chamber. The maximum load per charge of • Waste oil tank low temperature
class II solid waste must not exceed 70 litres.
Procedure for Stopping the Incinerator • The feeding door must not be opened unless there is a minimum The following waste oil tank conditions produce an alarm:
of 10mmWG vacuum in the combustion chamber as shown on • Low waste oil tank level
a) Activate the switch INCINERATOR STOP. This automatically the U-tube manometer.
switches the incinerator to the cooling program. • High waste oil tank temperature
• The flue gas uptake damper is set initially and should not • Low waste oil tank temperature
b) When the temperature in the incinerator drops to below 145°C, be tampered with. However, excess draught can cause erratic
the incinerator cooling program stops automatically. • Milling pump motor overload
combustion and increase the heating up time. It may be
necessary to adjust the flue damper to correct erratic combustion • Waste oil tank high level
c) When the incinerator has stopped, switch off the main switch if it is found to be due to the air supply and not to the fuel
on the control panel. burner.
Paper, rags, glass, bottles, crockery and other similar materials are allowed
over 12 miles offshore.
All other garbage including paper, rags etc. are allowed over 3 miles offshore.
Due regard should also be taken of any local authority, coastal, or port
regulations regarding the disposal of waste. To ensure that the annex to
MARPOL 73/78 is complied with, waste is treated under the following cases:
• Food waste
• Combustible dry waste, plastic and others
• Non-combustible dry waste
• Other waste, including oily rags and cans and chemical cans.
Illustrations
RMS Modem
Laser
AAP Printer
FCS Exp. FCS
C-Radio P-CARGO Cabinet S-CARGO
01-64
UMS ACG
01 02
C-SMS
Starboard Port
FCS FCS FCS MARSH MARSH MARSH MARSH MARSH MARSH S-MACH FCS FCS FCS MARSH MARSH MARSH MARSH MARSH MARSH P-MACH
24VDC 24VDC
S-MACH S-BLR S-BMS S-MACH S-MACH S-MACH S-BLR S-BLR S-BMS P-MACH P-BLR P-BMS P-MACH P-MACH P-MACH P-BLR P-BLR P-BMS
1 2 3 1 2 1 2 3 1 2
04 07 08 03 05 06
STARBOARD LOW VOLTAGE SWITCHBOARD ROOM PORT LOW VOLTAGE SWITCHBOARD ROOM
Starboard Machinery Control HIS Alarm Port Machinery Control HIS Report
MACH-ENG EWS Printer Printer
63A CB31 CB32 CB33 CB34 CB35 CB36 CB37 CB38 CB39 CB40 CB41
Central Control Room Console 16A 16A 16A 16A 16A 16A 16A 16A 16A 16A 16A
Wheelhouse Screens
CHIEF Spare
ENGINEERS'
OFFICE
40A 40A 40A 40A 32A 40A 40A 40A 20A 40A 40A 40A 40A 32A 32A 40A 40A 40A 32A 20A 20A 20A
Radio Packaging
F32 F33 F35 F34 F42 (MIKADO)
L - DCS - UPS
Spare Spare F21 F22 F43 F23 F24 F25 Spare F26 F27 Spare F28 F44 Spare F29 F30 F31 F45 F36 F37 F38
FCS EXP
S - CARGO 230VAC
S - CARGO
C - Radio FCS FCS FCS FCS FCS FCS FCS 24VDC
01 - 43 P - CARGO 230VAC/ 230VAC S - MACH P - MACH
P - MACH P - BLR P - BMS 24VDC S - BLR S - BMS
C - SMS 24VDC 24VDC
02 01 - 44 01 03 05 06 P - MACH 04 07 08
CARGO
L L L L L L 24VDC L L
24VDC L
ENGINE
63A CB41 CB42 CONTROL
ECR Console (Starboard) 16A 16A S - MA - HIS PRT
ROOM 19" 19"
01 - 62
40A 40A 40A 32A 40A 40A 40A 20A 40A 40A 40A 40A 32A 40A 40A 40A 32A 20A 32A 20A 20A
R - DCS - UPS F32 40A F33 F35 F34 F36 F42 F37 F38
Spare Spare F21 F22 F43 F23 F24 F25 Spare F26 F27 Spare F28 F44 F29 F30 F31 F45 Spare Spare Spare Spare
230VAC 230VAC
FCS FCS FCS FCS EXP FCS FCS FCS FCS 24VDC
P - MACH P - BLR P - BMS 230VAC P - CARGO S - CARGO S - CARGO 24VDC S - MACH S - BLR S - BMS
24VDC S - MACH
03 05 06 02 P - MACH 04 07 08 24VDC
CARGO 24VDC
R R R 24VDC R 01 R R R R R R
MODE VOLUME
OFF
ON
ENG
TRACK BALL
/ MODULE
SHIP FEED MAIN FO & GAS WATER FO, DO & COMPRESSORS NITROGEN
STEAM BOILERS LO SYSTEMS CARGO BALLAST SAFETIES MISCELL
OVERVIEW SYSTEMS ENGINE SYSTEMS SYSTEMS & HEATERS & INERT GAS
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
WHEELHOUSE
ELECTRICAL ALTERNATORS MISCELL SAFETY
17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32
_
+ ~
ESC 1 2 3 4 5 6 7 8 9 0 - = ' \` BS
{ }
TAB Q W E R T Y U I O P [ ] DEL
CTRL ALT
SHIFT SPACE ALT CTRL EXT CL
YOKOGAWA
Access to Overviews
The GROUP CONTROLLER PAGE key. If the user has accessed a faceplate or controller that has other
Circulate key. controllers within its group, pressing this key displays the other controllers that are part of the group.
Window Erase key. The TUNING PANEL key. When the user has accessed a process controller and called up a faceplate,
this key accesses the tuning panel for that controller. The tuning panel displays the settings and parameters used.
The NO or CANCEL key. Usage example: When the user changes a parameter, the user is asked to confirm Yes/No.
To cancel this request or confirm a NO decision the user clicks on the NO icon or presses this key.
The GRAPHICS/PROCESS key. This key returns the user to the last process display screen.
The YES or ACCEPT key. Usage example: When the user changes a parameter, the user is asked to confirm Yes/No.
To accept this request or confirm a YES decision the user clicks on the YES icon or presses this key.
The ITEM key. When the user is operating a controller on a faceplate, the ITEM (or parameter) may be changed or the
ITEM setting altered using this key. The PROCESS REPORT key. This can be used to produce a report from the DCS system pertaining to the current
screen display process.
The ALARM PAGE key. This key takes the user directly to the alarm page. The key has a red LED
embedded to indicate if an alarm is current. The display indicates the most current alarm at the top
of the page, 20 alarms to each page with a maximum of 200 alarms. A green key signifies that it must be
HELP The HELP key. pressed with another key to carry
out a particular function.
? The OPERATOR GUIDE MESSAGE key. This key is not used in this vessel's application. The TARGET key. This allows the user to change a value on a faceplate.
The ACTION key. This key functions as a DO key, ie, press this key to carry out a highlighted command etc
The UP and DOWN arrow keys. These keys are used to alter a controller set point or operate a faceplate
ON/OFF switch (up or down). These keys are also used in conjunction with the green FAST UP/DOWN keys.
The SCROLL key. This is a 4 way cursor key which will move the cursor around the screen to the next/nearest
available switch, motor or process etc with an accessible faceplate. The faceplate is then displayed by pressing The BACK PAGE key. Allows the user to move backwards through the screen display pages in numerical order.
the ACTION key directly below this cursor key on the keyboard.
The FORWARD PAGE key. Allows the user to move forwards through the screen display pages in numerical order.
SYSTEM The SYSTEM key. This key takes the user to the DCS system page, allowing a view of the status of the system.
CL The CANCEL key. Pressing this key will cancel the current operation and also delete the entry area.
COPY The COPY key. This key is used to send a copy of the left hand screen to the video printer. This key can be used from any ICS.
The CASCADE key. When this key is pressed with the AUTO key, the selected controller's operation
will change to the cascade mode.
The AUTOMATIC key. This key is pressed to change the mode of a controller or pump/motor's control mode to automatic.
Upper Sibling Window call key. This function can also be used with the cascade function.
The STOP/ACKNOWLEDGE flash key. When a process alarm occurs, a box flashes around the alarming parameter,
Parent Window call key. Pressing this key cancels the flashing. If the alarm has cleared, a green box flashes which can also be cancelled with this key.
The ALARM ACCEPT key. When an alarm is raised, the audible alarm will sound. Pressing this key will silence this alarm.
Lower Sibling Window call key.
TRIP - JCW TEMP HIGH HIGH OIL MIST HIGH JWC PRE-HEAT UNIT FAILURE GENERATOR ST-BY FAIL AVERAGE EXHAUST 364 c
1TSHH4026
1XS5531
3XS4005 1XS4040 TEMPERATURE
OIL MIST DETECTOR FAILURE
TRIP - JCW TEMP HIGH HIGH 1XS5530 SAFETY STOP CIRCUIT FAIL GENERATOR START FAIL
Alarms Area
1PSLL4072 LUB OIL FILT. DIFF. PRESS. HIGH 1XS4014 1XS4041 T.C EXH GAS OUT TEMP
TRIP - ENGINE OVERSPEED 1DPSH4070
CONTROL POWER FAILURE GENERATOR PLC SYS ERROR 402 c 1TI4020
1SSH4002 PRE LUB OIL LEVEL LOW 1XS4015B 1XS4042
T.C EXH GAS IN TEMP
1LSL4070
TRIP - OIL MIST HIGH HIGH GENERATOR CYL LUB N-FLOW
1XSS531B
GENERATOR JET SYSTEM FAILURE 1/2HA4015
STAND BY FAILURE
1XS4043 444 c 1TI4019
1XS4028A
GENERATOR EM'CY STOP GENERATOR TACHO FAILURE GAS OIL LEAK
1XS4039 1LSH4061
1XS4028B
GAS OIL 4.1 bar WINDING TEMPS 35 c 343 c 371 c 383 c 341 c 380 c 373 c 361 c 360 c SHUTDOWN
1PI4061 R S T
1TI4111/A/B/C 53 54 55 c
1TI4021 52 c AIR TEMP
ON LOAD DIESELGENERATOR
715 RPM
1SI4002
83 A CURRENT 66 c Related Temperature
87 c 1TI4025
1TI4030
751 kW LOAD Read Out
Bearing Temperature
Read Out
60 c FW OUTLET TEMP
1TI4031
0.79 PF POWER FACTOR 10219 RPM
1 2 3 4 5 6 7 8 1SI4001
WATER LEAKAGE
1LSH4025
TURNING GEAR
MOTOR
Shortcut Soft Key Icon to M
Supply System Screen Mimic CENTRAL F.W FW INLET PRESS 4.89 bar 1PI4025
(Central Fresh Water Cooling) COOLING 1K4050
Shortcut Soft Key Icon to No.2 TURBO No.2 TURBO DIESEL EMERGENCY NO.1 TURBO NO.1 TURBO
Related System Screen Mimic ALT.MONITOR ALT.SERVICE ALTERNATOR D/G ALT.MONITOR ALT.SERVICE
Related Equipment
(Cylinders Lubricating Oil Pump) Control Mode
Icon - Access to Control Faceplate
Feed Systems Main Engine FO & Gas Water Systems FO, DO & LO Electrical Alternators Miscellaneous Safety Wheelhouse
Steam Boilers
OV0004 OV0005 Systems OV0007 Systems OV0009 OV0019 OV0010 OV00011 OV0020
OV0002 OV0003
OV0006 OV0008
Desuperheated Port Boiler Stb'd Boiler Auxiliary Main Engine Forcing Main Circulating Aft FO Storage Electr. Distribution Diesel Steering Wheelhouse
Steam BMS BMS Condensate Sys. Overview Vaporiser Scoop System & Transfer Switchboard Control Alternator Gear Ships Side Valves Screen
T30-407-01 T30-452-04 T30-452-03 T30-412-01 T30-405-07 T30-425-01 T30-408-02 T30-415-01 T30-401-01 T30-402-02 T30-406-01 T30-408-04 T30-439-01
Superheated Port Boiler Stb'd Boiler Condensate Bearing Low Duty Sea Water Bunker Power Management Emergency Domestic Water Foam/ Navigation Engine
Steam Safety Chain Safety Chain System Temperature Heater Service System Loading System Diesel Generator Services Hi Fog System Alarms
T30-407-02 T30-452-10 T30-452-09 T30-412-02 T30-405-01 T30-426-01 T30-408-03 T30-415-02 T30-401-02 T30-403-01 T30-410-01 T30-418-01 T30-439-03
Port Boiler Stb'd Boiler Main Lubricating Oil No.1 Low Duty Lubricating Oil Electr. Distribution No.1 Turbo Alt. Compressed Vap Overview &
Bilge System 3,3Kv Consumers Fire & Safety
Combustion Combustion Condenser System Gas Compressor T30-409-01 Purification System Monitoring Air Systems W/H Authorisation
T30-452-02 T30-412-03 T30-405-03 T30-428-01 T30-417-01 T30-401-03 T30-404-01 T30-413-01 T30-418-02 T30-439-05
T30-452-11
Port Boiler Stb'd Boiler Feed Main Engine No.2 Low Duty Evaporators Lubricating Oil Switchboard No.1 Turbo Alt. Domestic Engine Room
Firing Sequence Firing Sequence System Mimic Board Gas Compressor T30-410-02 Transfer System Protection & Alarms Services Refrigeration Gas Detection
T30-451-03 T30-451-02 T30-453-01 T30-405-04 T30-428-02 T30-417-02 T30-401-04 T30-404-02 T30-414-01 T30-429-02
Stb'd Blr Soot Port Boiler Soot Water Analysis Main Engine Combustion Central FW Blackout & No.2 Turbo Alt.
Blowers Seq. Protection Gas Supply Cooling System Restart Control Monitoring Incinerator Emergency Stops
Blowers Seq. Chemical Injection T30-415-03 T30-445-01
T30-454-02 T30-454-04 T30-452-08 T30-405-05 T30-451-01 T30-410-03 T30-401-05 T30-404-03
Port Blr Warming Main Engine Gas Firing Fresh Water Blackout & No.2 Turbo Alt. Extension Alarm
Stb'd Blr Warming Cooling Bow Thruster
Through Seq. Through Seq. Control Oil System Safety System Restart Seq. Services System
T30-405-06 T30-451-05 T30-410-04 T30-401-06 T30-404-04 T30-420-01 T30-499-01
T30-454-03 T30-454-05
Stern Tube Lub. Oil Fuel Oil Fire Pump Transformer Machinery
Boiler Overview System Service System System Temperature Ind. Ventilation
T30-452-13 T30-446-01 T30-452-01 T30-447-01 T30-401-06 T30-440-02
Boiler Water
Level Control Air Conditioning
T30-452-07 T30-440-04
Boiler Burner
Fuel Oil Backup
T30-451-04
Cargo Ballast Compressors & N2 & Inert Gas Safeties Miscellaneous
Atomising Steam OV0013 OV0014 Heaters OV0015 OV0016 OV0017 OV0018
T30-452-05
Note: To see the graphic display screens available under the above OverView screens see the Cargo Operating Manual Illustration 3.2.3b
3LIC1060
MAIN CONDSR
0% 3LCV1060
LEVEL CONT
GLAND STEAM 3TI1066
CONDENSER 47 c
PPM11B MAIN COND.
AUT
AUTO P/P No.2 NR
REMOTE 2PI1061 500
NORMAL OFF
-300
96.5mm CPLD9C LOW DUTY
3TI1061
c MANU COND. P/P
36 3LIC1060
-500
REMOTE 3PI1061
NORMAL
3AI1061 0.1 PPM
Shortcut Soft Key Icon to FEED MAIN CONDENSATE AUXILIARY WTR ANALYS.
Related System Screen Mimic SYSTEM CONDENSER SYSTEM COND. SYS. & CHEM. INJ.
Certain motors/fans etc will not be allowed to restart until the trip has been
reset. The set value will now be controlled from the MV of the master controller.
The master controller MV and the slave controller SV should be set as
close as possible before changing into cascade mode for a smooth bumpless
Controller Faceplate Windows
changeover.
A typical PID controller is shown in illustration 3.1.4b. From the diagram
it can be seen that the controller is measuring the system temperature and When a controller is in the automatic mode, its graphic has no outline. When a
controlling the valve position with reference to that temperature and according controller is not in the automatic mode its graphic has a white outline.
to the set points.
On the controller faceplate, there are 3 values. The centre of the faceplate is a
solid graph bar, this is the process value (PV). This is the temperature of the
system fluid in this case. The right hand pointer is the set value (SV), this is
the value that the process value is required to be controlled at. The left hand
pointer is the manipulated variable (MV) this is the direct output to the valve,
in this case the percentage open required. It is important that the manipulated
variable is not mistaken for measured value; the term ‘measured value’ should
not be used when referring to the DCS in order to avoid confusion.
To obtain an accurate reading of any of the three values (SV, MV or PV), the
following procedure can be used:
09.25.2004 7:15 AM
TG0604 Block:06 Group:04
9/25/2004 7:11:17 AM
1 200 2 200 3 25.0 4 25.0 5 25.0 6 200 7 14.0 8 200
25.0 1 3TI1067. PV
100%
1ST FEED HTR CON
69 Deg_C
2 3TI1063.PV
20.0 AUX CONDSR COND
34 Deg_C
3 3AI1061.PV
MAIN CONDSR OUT
14.3 ppm
15.0
4 3AI1063.PV
AUX CONDSR OUT
0.1 ppm
10.0 5 3AI1064.PV
CONDST DRN POUT
15.2 ppm
6 3AI1062.PV
5.0 CONDENSATE WATER FLOW
3 us/cm
7 3AI1062.PV
CONDENSATE WATER
9.26 ph
0.0
0%
06:01 8 3AI2102PV
01 18:01 20:01 22:01 00:01 02:01 04:01 BLR FEED WATER FLOW
:24 9:24 9:25 9:25 14 us/cm
1 2 3 4 5 6 7 8
Once the user has accessed the trend screen, a trend group can be selected by
typing in the graphic title (TG0016 for the group shown above) and pressing
the RETURN key or by pressing the PAGE key and the trend number (16)
followed by the RETURN key. The FORWARD PAGE and BACK PAGE keys
could also be used.
RETURN
Officers' Mess Crew Mess Officers' Lounge Crew Lounge Duty Mess Gateway Station
SP
24V DC 24V DC 24V DC 24V DC 24V DC 24V DC
Health 14W 14W 14W 14W 14W 48W
Swimming Officer's Gymnasium Crew's
Room Pool TV Room TV Room
DCS
24V DC
15W
Administration Area Cargo Office Gas Engineer's Cabin 2nd Assistant Engineer 1st Assistant Engineer 1st Engineer Chief Engineer Key
Buzzer
Electrical Signal
MISCELLANEOUS MISCELLANEOUS
CCR SELECT
MANNED C/E 1/E 1/A 2/A
Soft Key Icons to CCR SELECT W/H SELECT CCR SELECT W/H SELECT
Select W/H or CCR W/H CCR W/H CCR W/H CCR W/H CCR ON DUTY
The alarm starts timing automatically in the event of a machinery alarm and The reset pushbuttons are located on all the signal columns in the engine
cannot be cancelled until the initiating alarm has been cancelled in the ECR; room.
otherwise the alarm may be started or stopped by the pushbuttons located at
the CCR, ECR or at the 3 main entrances to the engine room. The alarm status
is indicated at each pushbutton station.
Illustrations
Key
2 - Armchairs
12
Plan View - Engine Control Room 3 - Windows
4 - Desk
5 - Book Case
1
STEAM
ELECTRICAL ALTERNATORS
17 18
BOILERS
MISC.
19
FEED
SYSTEM
SAFETY
20
MAIN
ENGINE
21
FO & GAS
SYSTEM
22
WATER
SYSTEMS
23
FO, DO &
LO SYSTEMS
24
CARGO
25
WHEELHOUSE
BALLAST
10
26
COMPRESSORS
& HEATERS
11
27
NITROGEN
12
28
SAFETIES
13
29
MISC.
14
30
15
31
16
32
12 - Door
33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48
1 2 3 4 5 6 7 8 9 0 ?
Q W E R T Y U I O P
HELP NEXT
A S D F G H J K L
Z X C V B N M
* SYSTEM COPY
15
MISC. 32
ES 14
31
SAFETI
48
N 13
30
25
NITROGE GAS
INERT 47
SORS & 12
29
COMPRES
HEATERS 46
T
&
11
28
BALLAS
45
10
CARGO
27
9 44
&
S 26
DO
43
14 - Smoke Detector
FO,
SYSTEM
LO 8 25
S
WATER
OUSE
42
SYSTEM7
GAS WHEELH
& 24 41
32
FO
SYSTEM6
MAIN 23
ENGINE5 40
27
22 ?
FEED
SYSTEM4 39
S NEXT
21
BOILER
3 SAFETY
38 0
20 CI
STEAM
37 9
2 MISC. P HELP
SHIP IEW
TORS
19 8 COPY
36 O
OVERV 1 M
ALTERNA 7
ICAL
18 I L SYSTE
35 6
21
ELECTR
U K
17
34 5 J
Y
4 M
33 T H
3 N DATA
R G
2 B
E F
1 V E
W D
SPAC
S C
Q
A X
Z ITEM
* PAGE
BS
15 - Thermal Detector
23 23 16 - Sweat Scupper
33 2
4 2 17 - Air Diffuser
14 14 22 18 - Shutter Grill
19 - Louvre
2 17 17
20 - ICCP Remote Monitor Panel
28 - CO2 Extinguisher
31 - Workstations
32 - Printers
Situated on the after bulkhead is a work desk with the DCS port and
Introduction starboard alarm printers secured on top with storage cupboards and drawers
underneath.
The engine control room, situated on the 2nd deck, is where the necessary
equipment and controls are located which to permit the centralised operation Technical manuals are stored in the inboard section of cupboards whilst life
and supervision of the engine room machinery, via the Distributed Control jackets are stowed in the outboard section. Technical test equipment and tools
System (DCS). are kept in the drawers.
The main engine control and operating console includes the following: A desk with the DCS Engineering Work Station (EWS) is situated on the aft
• Two DCS Information and Control Stations (P-MA-HIS and S- bulkhead.
MA-HIS), one for the starboard machinery and one for the port
machinery Notice and information boards are situated on the forward bulkhead.
• Main engine trip cause indicators The engine room toilet is situated in the forward outboard corner.
• Main engine automatic power reduction cause indicators
An Emergency Escape Breathing Device (EEBD) is sited on the port side.
• Main engine telegraph lever and manoeuvring control
indicators
• Main engine and boiler trips
• Fire detection control panel
• Telephone handsets for the automatic, sound powered,
intrinsically safe and common battery systems
• Rudder angle indicator
• CCTV controller
• Ship performance display unit
• Public address system control panel
• Engine room general call/talkback system control panel
• Fire alarm, general alarm, engine call and patrol man system
pushbuttons
Also situated on the forward and inboard bulkheads are panels for the following
systems:
• Signal light column
• Oil mist detection RMUs
• ICCP remote monitor panel
• Cargo machinery gas detection
• Engine room gas detection
• ECR emergency distribution board
9
12 1 10 11 13 23 14 15 16
11
10 2
9 3
8 4
7 6 5
12 24 30 31
1 2 5 6
33 34
18 22
21 29
20 36 37
59 25 26 42 28 35
27
60 17 32 45 28 38
47 61 62 54 55
44 52
3 7 19 53
48 4 8
43 56
49 50 51 57
39
40
FIRE
46
58
41
Key
1 - No.1 CRT for Starboard Machinery HIS 11 - Ship Performance Display Unit 21 - Fire Repeater Panel 31 - Control Mode 41 - General Alarm 51 - Common Battery Telephone
2 - No.2 CRT for Starboard Machinery HIS 12 - Shaft Revolutions Counter 22 - Fire Alarm Panel 32 - Main Turbine Hand Trip 42 - Patrol Man 52 - Automatic Telephone Directory
3 - Keyboard for Starboard Machinery HIS 13 - Shaft Revolutions Indicator 23 - Console Power 33 - Time Schedule 43 - Test 53 - Main Turbine Manoeuvring RPM Table
4 - Trackball for Starboard Machinery HIS 14 - Main Turbine Trip Cause Indicator 24 - Main Turbine Auto Power Reducer 34 - Lever Control 44 - Patrol Call System 54 - Ahead Valve Pushbutton
5 - No.1 CRT for Port Machinery HIS 15 - Ahead Valve Position Indicator 25 - Port Boiler Trip 35 - Main Turbine Power Reduction 45 - Engineer's Alarm 55 - Astern Valve Pushbutton
6 - No.2 CRT for Port Machinery HIS 16 - Astern Valve Position Indicator 26 - Starboard Boiler Trip 36 - Telegraph Lever Matching 46 - CCTV Operation Panel 56 - Control Method
7 - Keyboard for Port Machinery HIS 17 - Spare 27 - Main Turbine Trip Bypass 37 - Turning Gear 47 - No.2 UHF Remote Controller 57 - Telegraph Receiver
8 - Trackball for Port Machinery HIS 18 - Second Adjust Switch for Electric Clock 28 - Control Position 38 - Main Turbine Auto Spin 48 - IS Telephone 58 - Maximum Speed Setter
9 - Electric Clock 19 - Public Address Microphone 29 - Spare 39 - CCTV Camera Directory 49 - No.2 Automatic Telephone 59 - No.1 Generator Turbine Trip
10 - Rudder Angle Indicator 20 - Public Address Controller 30 - RPM Control 40 - Fire Alarm 50 - No.2 Sound Powered Telephone 60 - No.2 Generator Turbine Trip
61 - Buzzer Stop
62 - Flicker Stop
3.3.4 Sootblowers
Illustrations
Riser Pipes
Manhole (Front)
Burner
Manhole
Manhole
Steam Drum
Downcomers
Refractory
Downcomers
Furnace
Superheater
Observation Hole
Rotary Sootblower
Long Retractable
Soot Blower
Manhole
Rear Bank Tube
Water Drum
Steam generated in the boiler tubes enters the steam drum where it is forced to The furnace water wall tubes are backed up with insulation and supporting
Forced Draught Fans
enter a baffle located at the normal water level, before entering the upper part buckstays that allow for expansion. The outer casing is corrugated steel plate
coated with heat resistant paint. Maker: Osaka Blowers Mfg Co. Ltd
of the steam drum. The baffle is intended to reduce the surging of the water
level due to hard steaming, sudden load changes and any vessel movement. Type: TACS - 1080
Saddles Drive motor: 140kW
Before leaving the boiler through the steam outlet nozzle, the steam must pass
Saddles are provided under the water drum and the front and rear water wall
through the dry box located at the top of the steam drum. The dry box separates Three fans are situated on the upper deck platform and are controlled
headers to support the boiler. The rear saddle under the water drum is fixed and
larger water particles from the steam and helps to prevent or reduce carry over by adjustable vanes, automatically positioned by the combustion control
the front saddle has slotted bolt holes, grooves and grease fittings to allow for
of water with the steam. equipment. The outboard fans are arranged to supply their respective boilers.
easy movement and lubrication. Grease fittings are provided on the front and
rear saddles of the water wall header. The grooved saddles are free to move to The centre fan is the standby unit and is put into service on either boiler by
A submerged tube desuperheater is located in the steam drum below the normal manually opening the crossover connections on the air supply trunking.
allow for expansion of the boiler as it warms up.
water level. Superheated steam is fed through the tubes, giving up most of its
degree of superheat to the water within the drum and emerging as reduced heat (Note: Due to the capacity of the individual fans a single fan must never be
(Note: The boiler sliding feet should be inspected and cleaned as frequently
auxiliary steam. used to supply two boilers.)
as possible and should be greased at least every 600 hours. Failure to
do this could result in the sliding feet seizing and subsequent damage
Desuperheated steam is supplied in this way to ensure that there is always a The boiler must be stopped to effect the changeover. Once changed, the
to the boiler as it expands.)
flow of steam through the superheater even when the demand for superheated automatic boiler control system treats the standby fan in the same way as the
steam is low. This ensures that the superheat tubes are not damaged by normal fan i.e. full automatic operation is allowed. Restart after a blackout is
overheating during low steam flow conditions. Superheater
arranged in order to facilitate the automatic restart of the boilers.
The superheater is of the vertical, interbank, convection type and arranged for
The water drum located at the bottom of the boiler, houses a submerged tube multipass steam flow. Control of the fans is from the Forced Draught Fans and Air Heaters faceplate
desuperheater, through which some of the superheated steam is diverted to T30-452-06, from which the seal air fans are also controlled.
control the final superheat outlet temperature. The superheater elements are arranged in groups of six concentric hairpin
loop elements, the ends of which are welded into inlet-outlet headers and
Both steam and water drums are fitted with swinging manhole covers to allow Steam Air Heater
intermediate headers. The arrangement of the elements is such that the
entry and inspection. superheater tubes are parallel to the boiler generating tubes. Maker: Hamon Spiro (France)
Capacity: 0.125m3
Furnace Guide castings are welded to the superheater elements and to the generating Operating pressure: 9 bar
tubes. These sliding supports help to maintain the alignment of the superheater
As previously described, the furnace walls are of the membrane construction. Outlet temperature: 350°C
elements. The superheater inlet, outlet and intermediate headers run parallel to
The tubes forming the furnace sides, floor and roof are of 63.5mm diameter,
the water drum. Each header is separated internally by welded steel diaphragms
whilst the tubes forming the front and rear walls are of 50.8mm diameter. The boiler has a steam air heater to heat the combustion air before entry to the
to direct the steam flow through five passes between the headers. Drainage is
through small openings in the lower edge of the diaphragms. windbox and the furnace. The steam is bled from the main engine crossover
External downcomer tubes are placed outside of the boiler casing and provide when the pressure is sufficient. At other times this system is supplied with
ample circulation of the water from the steam drum to the water drum, bottom make-up steam up from the 5 bar desuperheated steam system.
header and the front and rear water wall headers. Economiser
An extended surface type economiser is placed above the boiler tube bank. The Each air heater has inlet steam isolating valves, T268B and outlet drain
The water cooled furnace floor tubes leave the bottom header to transverse economiser is made up of closely spaced, continuous loop elements, welded isolating valves T365B. The air temperatures can be measured on the DCS
the floor before bending upwards to form the furnace side and roof. They to the terminal headers at each end. Each element tube is 50.8mm diameter screen T30-452-06 Forced Draught Fans and Air Heaters.
terminate in the steam drum. carbon steel with a spiral steel fin, connected by U-bends to form an integral
loop. All the elements are supported at the front and rear side by tube plates.
The furnace front and rear tubes are arranged from the lower to upper water The outside of the terminal headers are provided with hand holes to allow
wall headers. The upper water wall headers are connected to the steam drum access. The economiser is insulated and surrounded by a steel casing with large
by riser pipes. removable access panels.
Boiler Gas Header Room Extraction Fans Various connections are fitted on the steam drum and superheater output
Maker: Daeyang Electric Co. Ltd manifold to accommodate local and remote pressure gauges, control equipment
and sensing points and they all have isolating valves fitted.
Type: LRZ9A/280/450
Capacity: 60m3/min x 40mmWG A steam flow orifice plate is fitted in the superheater outlet pipe. Isolating
Motor: 1.5kW valves are fitted on either side and provide a differential pressure signal to the
steam flow transmitter.
Two extraction fans are situated above the gas header room, aft of the boilers
on the 2nd deck. The fans extract any gas that may leak from the BOG pipes Boiler Parameters
and valves and blow it to atmosphere.
Single Boiler Failure
In port, a flame failure can occur due to the very light boiler loads, the cause
Principal Boiler Mountings
of the failure must be established before attempting to relight the boiler. At sea,
Each boiler is fitted with a non-return stop valve on the superheated steam the cause of a boiler shutdown would usually be of a serious nature and also
outlet manifold. A secondary valve is also fitted after which the steam lines affect the speed of the vessel.
of both boilers become common and lead to the main superheated steam
manifold. The plant must be stabilised by reducing the shaft rpm, which is achieved by
either the bridge changing the telegraph to FULL AHEAD or changing over to
Steam and water isolating valves are fitted to the two water level gauge ECR pushbutton control and reducing to FULL AHEAD. The reason for the
glasses. failure must be fully investigated and rectified before any attempt to relight
the boiler.
Vent valves are fitted at the highest points of the following:
• Steam drum Both Boiler Failure
• Superheater output manifold, this vent is known as the steam If both boilers trip while the engine is in use, it will also trip, in order to
raising circulating valve or superheat vent conserve the remaining available steam. This will mean the loss of the
• Economiser propulsion power. In addition, the standby diesel generator will start and
parallel with the turbine generator in use at the time. Reset the main turbine
Each vent line is fitted with two valves in series. trip by closing the manoeuvring valve, either by using the pushbuttons in the
ECR/CCR or moving the bridge control lever to the STOP position.
There are two safety valves fitted to the steam drum, set to lift at 76.5 bar and
76 bar, with another before the main stop on the superheated steam outlet, set Boiler Water Level Suspect
to lift at 63.5 bar. The economiser is fitted with a safety valve fitted on the
Shut the fires off the suspect boiler and reduce the engine rpm to FULL
water outlet header which is set to lift at 96.5 bar.
AHEAD. Inform the Chief Engineer, bridge and call for assistance. Blow down
the gauge glass and establish the water level. No attempt must be made to flash
Drain valves are fitted at the lowest points of the water drum, water wall
the boiler until the actual water level in both gauge glasses is established.
headers and superheater headers.
The modified signal has the correction for oxygen trim added as well as any The fuel regulating valves and FD fan vanes are operated by the control air. Feed Water Regulator
manual adjustment of the fuel/air ratio. The total fuel energy is fed into the Should the supply of control air fail, the fuel and gas regulating valves will
The feed water control is incorporated into the DCS. The system primarily
circuit and modified according to the boiler load. This is to account for the fact lock in the current position and the FD fan vanes will open fully.
matches the feed water flow to the steam flow and senses the boiler water level
that the excess air requirement alters according to the boiler load. to ensure that it remains at the correct level. In the event of control air failure
The fuel demand signal, derived from the lead/lag arrangement described
the valve will lock in the current position.
The signal from the air/fuel ratio bias passes through another function device, previously, is fed into both the fuel oil control loop and the fuel gas control
adding further refinement based on the proportion of fuel oil to gas and then loop simultaneously, irrespective of which mode is in use.
The level is sensed by two DP level transmitters and two float type switches,
finally passes to the oxygen PID controller as the set point. used to detect an ultra high high level and a very low low level.
The demand goes to two summer units, one on each loop. The summer units
The controller output is modified to give a biasing signal of between 0.9 and are quite complex and are involved in controlling the ratio of fuel to gas. This
The two signals from the level transmitters are compared and an alarm raised
1.1 and then passes through a switch, which disconnects the trim circuit if is dependant upon how the gas demand has been set and whether natural boil-
in the event of any difference. The system checks the milliamp output of the
sootblowing or manoeuvring is taking place. It then passes through an auto/ off (NBO) or forced boil-off (FBO) is being use to supply the gas (see section
transmitters and if one is outside of the 4 to 20mA range it is assumed to be
manual facility which effectively switches the trim out and continues to the 2.4.2). The fuel demand signal is used to control the gas flow, through control
defective.
multiplier, where the air/fuel trim is applied to the combustion air demand of the NBO and/or FBO system as well as the fuel oil system, dependent upon
signal. how the system has been set to operate.
Only the assumed ‘good’ transmitter is then used in the control calculations.
The DCS can be forced to operate on one transmitter only if maintenance is to
For balance purposes, it is also fed back via a dividing relay having the equal There are built in safeguards that ensure that if the settings cannot be achieved,
be performed on the other unit, Boiler Water Level Control mimic. T30-452-
but opposite function to the multiplier, as a correction on the combustion air adjustments to the ratios will be made until the original settings can be restored.
07.
flow signal. In the event of a gas shortage, the gas valve will start to close and the system
can force it to remain open until full firing on fuel oil has been established.
The system includes a number of automatic safety operations relating to boiler
The combustion air demand signal from this part of the program is passed level management and class requirements as follows:
through a switch, which feeds a 25% signal through during the lighting up Superheated Steam Temperature Control
procedure. This is to set the correct air for the lighting procedure only. A • Ultra High Level (+240mm) results in:
Superheated steam temperature control is incorporated in the DCS. The
second switch in the same circuit applies the demand for purge air, which is Alarm, trip of the boiler. This trip will be initiated both from
system controls ensures that the superheated steam temperature at the header
controlled from the burner management system. the level transmitter and the level switch
outlet does not exceed the predetermined limit (normally 515°C).
• Very High Level (+220mm) results in:
From this point the demand signal is compared in a high selector relay which
Under low loads it is unlikely that any control will be necessary because
selects the signal, or the mini air signal (which equates to the minimum Trip of the main engine, trip of the turbo generators (if
the superheat temperature will be below the normal set point. As the boiler
allowable air flow), or a boost signal if the boost system is being instigated. start and paralleling of the diesel generator was successful),
approaches full load the superheated steam temperature will rise and reach a
shutting of the electric feed safety valve
point where cooling is necessary.
Normally the boost signal is zero, but in the event of gas production failure,
• High High Level (+180mm) results in:
which only occurs when 100% gas firing and the gas valve beginning to close,
This is achieved by the control of an attemperation valve fitted in between the Diesel generator starts and main engine slows down
the zero signal increases to the same value as the master signal or to the air
fourth and fifth pass of the superheater. Some of the steam is diverted via this
flow, whichever is less.
valve into the desuperheater within the water drum.
2) The purge sequence finishes after the set time period, the air
register closes and the forced draught fan vanes close. PURGE
COMPLETE is highlighted on the DCS screen.
5) The lighting sequence begins with the air register opening. The
air is supplied at a rate preset within the DCS for lighting up.
The fuel valves open and the fuel recirculation valve closes.
Fuel flow is also preset for lighting up within the DCS. The
igniter is extended into the register and firing should take
place. When the flame is established it is detected by the flame
eyes, the igniter withdraws, and the lighting up procedure is
complete.
If the flame fails to establish, the fuel valves will close and the boiler will go
through a purge sequence to remove any combustible gas and unburnt fuel
from the furnace and uptakes. Having rectified the cause of the failure a further
attempt at lighting up can be made.
These modes are selectable from face plate T30-451-04 Boiler Burner Mode
Selection. Schematic diagrams display the valve positions during changeover
procedures.
d) Open the superheater outlet vent valve and stop the boiler using
the manual trip.
l) Maintain the normal water level at the normal level for the 15
minutes after shutdown, after which time the feed water supply
valves may be closed.
m) When the boiler pressure drops to about 15 bar fully open the
superheater drain valves and desuperheater drain valves.
All the sootblowers are fitted with a local start button for use in the local mode Either of the above conditions will cause all of the long stroke sootblowers to
of operation. In addition, the long stroke blowers are fitted with an emergency Operation of any Automatic Sequence
retract and the system to shut down. The steam valve will not close until all the
retract button for use in any operating mode. All the blowers have a stop long stroke sootblowers are in the retracted position. Any rotary sootblowers All operations are carried out from DCS graphic screen T30-454-01 as
position switch and the long blowers have a reversing switch. will continue to turn until they reach their stop position. follows:
These are fitted for control purposes within the DCS. Motor running, direction The following alarms are also fitted: a) Select DCS on the control mode area of the screen.
and overload conditions are fed back to the DCS for indication, control and
alarm purposes. • Long stroke sootblower time exceeded, due to: b) Select one of the six preset operating sequences:
Forward motor not running • No.1 boiler ECONOMISER SEQ. START
Reverse position switch time out • No.2 boiler ECONOMISER SEQ. START
Retract motor not running • No.1 boiler FULL SEQ. START
Stop position time out • No.2 boiler FULL SEQ. START
• Long stroke sootblower motor overload • Both boilers FULL SEQ. START
• Long stroke stop position abnormal • Both boilers ECONOMISER SEQ. START
• Emergency retract pushbutton operated on the DCS
If a further automatic sequence is selected within the five minute period the
timer is cancelled and the new sequence takes place. When no further sequence
is selected within the five minute end of sequence period, the system shuts
down i.e. the main steam valve closes and the port and starboard drain valves
open.
Local Operation
a) Select LOCAL on the control mode section of the DCS
faceplate T30-454-01.
d) Upon completion the system is shut down from the DCS panel.
This can only be achieved if all the long stroke sootblowers are
fully retracted. Select OFF in the control mode section of the
DCS screen. All the blowers are now locked out. The steam
supply valve is closed and both port and starboard drain valves
open.
Sealing Air
The glands at the boiler casing are sealed by air pressure from the FD fans
trunking.
Illustrations
Oil Pan
Sea Water
Scoop Inlet Sea Water
Pump Inlet
Plan
Low Pressure
Astern Turbine
Low Pressure
Ahead Turbine
Reduction Gear
Generator Turbine Exhaust Steam Inlet
Main Lubricating Oil Pump
Turning Gear
The main thrust bearing is located in a separate casing aft of the main • Transmitters, control valves and pump starters associated with
reduction gear. the LO systems
• Main turbine turning gear
A motor driven turning gear is provided and mounted at the aft end of the
driving shaft, which is connected to the HP first reduction pinion. The primary function of the DCS with regard to the main turbine is purely
alarm and monitoring, either directly from the bearing temperature probes, or
Lubrication as remote monitoring of the package vendor units. This includes monitoring of
the turning gear. Monitoring and alarm functions are provided for the pressure
The lubricating oil system (see 2.3.1 Main Turbine Lubricating Oil System) and temperature sections of the control oil system. Control of the lubricating
consists of one main turbine driven lubricating oil pump, two motor driven oil pressure and temperature is carried out together with the control of the
auxiliary lubricating oil pumps, a main lubricating oil strainer, a pressure lubricating oil and control oil pumps starting and stopping function.
control valve, a temperature regulator, two lubricating oil coolers, an
emergency gravity tank and one lubricating oil pan and sump tank built Gland steam make-up and spill is also controlled by the DCS.
into the hull.
The main turbine driven LO pump supplies the turbine and gearing with
oil when the turbine is manoeuvring. The motor driven LO pump will start
when the revolutions are at 63 rpm for 10 minutes, the oil pressure is low or
an abnormality occurs in the operation of the turbine driven pump. This is
controlled by the DCS graphic screen T30-405-03 MAIN ENGINE LUB OIL
SYSTEM.
g) If the vessel is in Nigerian waters, purify the stern tube LO. The following sequence is necessary to operate in this mode: To avoid thermal stress in the plant/turbines, it is recommended that the turbine
is brought up to full power (84 rpm) over a period of 80 minutes.
(Note: The warming through bypass valve on the ahead turbine nozzle a) Establish communications with the bridge.
and stop valve is not to be opened during a normal port stay. The (Note: If it is necessary to take over pushbutton control during manoeuvring,
emergency stop valve T645V, outside the workshop door, should b) Stop the main turbines. the button marked ECR/CCR should also be depressed, which will
be exercised during the port stay, but it must not be left in the shut necessitate the bridge acknowledging this action by pressing their
position.) c) Change over to machine side control on both the wheelhouse corresponding button. Taking over pushbutton control without
and the ECR/CCR consoles. pressing the ECR/CCR button will result in any bridge telegraph
Any further shutting down depends on the length of time the turbine is to be movements occurring without an audible warning and therefore any
unused and any plans to do maintenance. In many ports the engine is required d) To manoeuvre ahead carry out the following: required movements could go unnoticed.)
to be on ten or thirty minutes notice. • Remove the locking device for the hand wheel which is fitted to
the ahead nozzle yoke linkage The following sequence is necessary to operate in this mode:
Procedure for Manoeuvring the Main Turbine in the Event of • Adjust the hand wheel and align the holes in the linkage and the a) Liaise with the bridge if time allows.
Loss of Automatic Control yoke
• Fit the pins in the linkage, which will enable the AHEAD and b) Select ECR/CCR control.
If the control oil is still available and the manoeuvring or nozzle valves are ASTERN valves to be jacked open and closed
free to operate. c) Open/close the ahead and astern valves by pressing the UP/
DOWN pushbutton as required.
The main turbine can be manoeuvred locally by operating the hand wheels e) To manoeuvre astern carry out the following:
fitted to the ahead and astern manoeuvring valve servo units, provided the • Use the hand wheel on the valve chest to open the astern d) Manoeuvre as instructed by the telegraph.
control oil pressure is maintained. The main turbine trips will still function via manoeuvring valve, ensuring that the astern spray water valve
the control oil system. has opened.
The following are required to be carried out to allow this method of control.
Main condenser high level 300mm above NWL after 10sec delay
Main Steam
Valve Position
Transmitter
Strainer
Governor Emergency Handwheel
Motor
P
Electric Positioner
P
Valve Position with Limit Switch
Transmitter To HP Turbine Nozzles S
P PS
Emergency Handwheel S
Solenoid Valve
(Astern Guard Valve)
Limit Switch
(Valve Open)
M
Key M
Air
Astern Guard Valve
Instrumentation
1. Telegraph power failure. 7. Main turbine emergency trip. See the trip conditions on the previous page.
2. Main turbine remote control system failure. An indication lamp on the 8. Astern guard valve abnormal. The alarm signal is given when the valve is
mimic board will illuminate when the remote control condition check and self not fully open when in the manoeuvring mode or opened in the normal full
check functions detects one of the following an abnormal conditions: away mode. The alarm signal is given in wheelhouse control when the control
lever is moved to the astern position and the astern guard valve is still closed.
• Wheelhouse control lever signal abnormal
• Central control room control lever signal abnormal 9. Safety system power failure.
• Engine control room control lever signal abnormal
10. Electrical power supply failure (AC/DC). The alarm signal is given when
• Ahead nozzle valve position signal abnormal the main AC power and/or the DC battery power fails
• Astern manoeuvring valve position signal abnormal
11. Auto power reduction bypass. The alarm signal is given when the auto
• Propeller shaft revolution signal abnormal
power reduction bypass.
• Main steam pressure signal abnormal
12. Auto spin overspeed. When the shaft revolves at more than 5 rpm.
• Astern water spray valve abnormal
• Central control room speed setter signal abnormal 13. Time schedule bypassed.
• Engine control room speed setter signal abnormal
14. Main turbine remote control auto changeover to the standby CPU or the
• Micro-computer unit temperature high standby CPU fails.
• Remote control system power failure
15. Astern water spray valve is abnormal. The astern water spray valve open
• CPU, A/I(ADC), D/I and D/O failure
signal appears when the astern guard valve is closed and/or the astern governor
valve is at its lower limit.
3. Wrong way - when the control lever or the pushbutton control switch is
operated in the opposite direction to the engine telegraph order. This signal has 16. Main turbine emergency trip bypass switch in the ON position.
a 5 second timer function.
17. Lever control not possible due to remote control system trouble.
4. Main turbine remote control system power failure. The following failures
cause an alarm situation on both the DCS and the mimic board: 18. Auto spin start. The ahead manoeuvring valve has not opened 20 seconds
after the open request signal.
• Power circuit for the dual computer system
• Power circuit for the pushbutton and the common system 19. Main turbine control location changeover unit failure.
• Power circuit for the governor and valve feedback system
20. Overspeed preventer unit fails when on the pushbutton control.
• Power circuit for the governor motor
• Power circuit for the magnet valves 21. Power reduction request (main condenser level high). The alarm signal is
given when the telegraph lever is in the astern position and the power reduction
request is given.
5. Auto spin failure. The following conditions cause an alarm situation:
• Shaft rpm signals more than 5 rpm
• Shaft stops for more than 3 minutes
• The steam valve is in the open position for more than 30
seconds
Illustrations
PI
24V DC
6,600V
No.1 No.2 2,000kW M
Servo 440V Servo Motor
Pump M 6.3kW M Pump Drain from Gear Housing
Motors Blade Angle
440V
Transmitter Air Bleed
440V
Drain from Sealing System
Key
Hydraulic Oil
Electrical Signal
Thruster
Unit Instrumentation
PI
24V DC
6,600V
No.1 No.2 2,000kW M
Servo 440V Servo Motor
Pump M 6.3kW M Pump Drain from Gear Housing
Motors Blade Angle
440V
Transmitter Air Bleed
440V
Drain from Sealing System
Key
Hydraulic Oil
Electrical Signal
Thruster
Unit Instrumentation
4.3 Emergency Operation of the Main Turbines (Solo Running of High Pressure or Low Pressure
Turbine)
4.4 Steaming with One Forced Draught Fan (Port or Starboard) Out of Use
4.9 Dead Ship Starting with the Main Diesel Generator Out of Service
Illustrations
4.9a Dead Ship Starting Sequence with the Main Diesel Generator Out of Service
Operate all ship’s side valves regularly, so that they can be operated easily
Bilge Suction Strainers
when required. Valves such as fire pump suction valves, which are normally
Bilge suction strainers should be checked and cleaned whenever the opportunity
open, should be closed and reopened regularly to prevent a build up of
arises. Frequent checking and cleaning will reduce the risk of a strainer
marine growth.
becoming blocked and difficult to clear due to subsequent flooding.
Before opening sea water filters for cleaning, make sure the shut off valves are
tight by opening the vent in the cover. In any case, break the cover joint before
removing all cover bolts. The same applies when opening coolers and pipelines
anywhere in the system. Care must always be taken when removing covers or
opening any part of the sea water pipe system as valves which are indicated as
being closed may not be fully closed.
Personnel should be familiar with the position of bilge suctions and the pumps
that can be utilised for bilge pumping duties. They should also be familiar
with the position of main sea suction and overboard valves and know which
main suction is currently in use.
Normal evaporation for each boiler is approximately 50,000kg/h for 90% a) Inform the bridge of the problem and reduce the engine speed
g) When conditions have stabilised increase the main turbine
MCR. Individual circumstances will dictate where the steam produced is used, to a rate which maintains steerage way but does not overload
steam supply as required, loading the boiler up to but not
and selected non-essential services should be shut down as required, depending the remaining boiler.
exceeding the maximum firing rate.
upon prevailing circumstances.
b) Isolate the faulty boiler completely including the air heater.
It may be possible to shut down the turbine generator and use the diesel
generator, but in this case the forced draught fan must be on reduced load c) Keep a check on the gas boil-off situation as well as the
and it will not be possible to achieve the maximum steaming rate from condition of the remaining boiler.
the boiler.
d) Shut down as much steam using equipment or systems as
Shut down non-essential heating and evaporators if conditions permit and possible. Reduce the electrical loading.
reduce the electrical loading where possible.
e) Reduce the cargo compressor load and open the mast vents
The main turbines use about 95,000kg/h at 90% MCR. However, this includes if necessary.
bleed steam, which may well have to be isolated due to reduced steaming
conditions. Basically, the circumstances encountered in each particular case (Note: This will not be possible in port due to local restrictions.)
will dictate the steam usage, with priority being given to essential services such
as gland steam, feed pump, turbine generator and boil-off/warm-up heaters. f) Keep the forced draught fan running on the faulty boiler to cool
it down, or allow it to cool down naturally. Either fill the boiler
In the event of a boiler being shut down, planned or otherwise, the bridge must to the top of the gauge glass or empty it out when cool.
be informed immediately.
g) When conditions have stabilised, increase the engine speed
The main turbine must be slowed down sufficiently to enable the remaining as required up to the maximum firing rate on the remaining
boiler to be maintained within its operating parameters. Control of the boiler.
boiler coming out of service will be generally under manual operation and
particular care must be taken to ensure the remaining boiler controls and When a Boiler has to be Shut Down
associated systems function to compensate accordingly. The steaming rate of
the remaining boiler must be maintained below the design maximum.
a) Inform the bridge of the problem and reduce the engine speed
During transition periods vigilance is necessary to ensure safe operation of the to a rate which maintains steerage way but does not overload
plant, particularly with reference to water level control and firing rate. the remaining boiler.
PLAN
NORMAL OPERATION OPERATION WITH LP TURBINE ONLY OPERATION WITH HP TURBINE ONLY
Blank
Expansion Joint Flange (C) Expansion Joint
Blank Flange (A) Blank
Blank Flange (B) Orifice Flange (A)
(Emergency Exhaust Plate U Bolt Emergency Blank Flange (D) Emergency
Inlet) Bracket Steam Pipe (B) Exhaust Pipe
Cross-under Diffuser
Pipe Emergency
Steam Pipe (A)
Emergency
LOOKING FORWARD
Steam Pipe (B)
U Bolt
LP Turbine LP Turbine Bracket LP Turbine
Cross-under
Emergency Emergency
Pipe
Steam Pipe (A) Exhaust Pipe
HP Turbine HP Turbine HP Turbine
Blank
Flange (A)
Steam
Inlet
Bend
a) To avoid turning the HP turbine, disconnect the coupling between HP Turbine in use LP Turbine in use
Operating with the High Pressure Turbine Only
the HP turbine and the first pinion by removing the reamer bolts Steam condition: 15.0 bar at 278°C 3.0 bar at 245°C
from the flange of the claw coupling. Output: 10,805 PS 10,805 PS
See illustration 4.3a
RPM: 56.7 56.7
b) Remove the cross-under pipe.
a) To avoid turning the LP turbine, disconnect the coupling between
the LP turbine and the first pinion by removing the reamer bolts Should a failure occur, it would be most likely that the ship would be at
c) Fit the blank flange (C) to the HP turbine exhaust.
from the flange of the claw coupling. sea. The turbines will therefore be hot and will need to be cooled for some
d) Fit the diffuser to the LP turbine inlet. time before any work can be carried out. Unless internal mechanical damage
b) Remove the cross-under pipe. prevents it, the main turbine should be cooled down with the turning gear in
e) Remove blank flange (A) from the steam inlet bend to the use prior to opening up for internal inspection work.
c) Fit the blank flange (D) to the LP turbine inlet.
turbine nozzle valve chest.
If it is impossible to cool the engine using the turning gear, care must be
d) Remove the blank flange (B) from the main condenser emergency taken when starting the usable turbine. It should be run at low revolutions for
f) Fit the emergency pipes (A) and (B) together with the orifice
exhaust inlet. several hours in order to straighten out any bowing of the rotor which may
plate fitted between emergency pipe (A) and the diffuser.
have occurred during cool down whilst stationary. If vibrations occur when
e) Connect the HP turbine exhaust directly to the LP turbine exhaust increasing speed, decrease the speed until the vibrations stop and allow the
g) Secure the emergency piping using the U bolt bracket.
casing using the emergency exhaust pipe. temperature of the rotor to stabilise. Speed can then be increased slowly to
h) Fit blank flanges to the HP turbine gland steam connections to the maximum permitted value.
f) Manually close the astern guard valve.
prevent the HP rotor overheating.
CAUTION
i) Fit the spool piece to the emergency steam line, situated forward
The LP astern turbine cannot be used so an astern movement is not
of the starboard boiler on the 3rd deck level. See illustration
possible.
2.1.2a for fitting of the portable pipe from the desuperheated
steam system.
g) Fit the spool piece to the emergency steam line, situated forward
of the starboard boiler on the 3rd deck level. See illustration
j) Close the superheated steam valves T601V and T602V and
2.1.2a for fitting of the portable pipe from the desuperheated
open the bypass on valve T711V to warm the pipeline. Once
steam system.
the line is warmed through slowly open valve T711V, close
the bypass and only use desuperheated steam under emergency
conditions.
Crossover Trunking
Normally Open B
A Normally Closed C Normally Open
To Boiler To Boiler
Key
Normal Air Flow
Forced Draught Fans f) Adjust the fuel oil pressure to 4 bar and bring the boiler pressure
Maker: ABB Solyvent - Ventec up to the pressure of the other boiler, at a rate according to the
Type: FL SLIA 120 pressure raising graph.
Drive: 1,785 rpm and 150kW g) When the boiler pressures are equal, change the fuel and air
controls to automatic and close the starting valve.
Three fans are situated on the upper deck platform and are controlled
by adjustable vanes, automatically positioned by the combustion control h) Raise the main turbine load gradually.
equipment. The outboard fans are arranged to supply their respective boilers.
(Note: It may be necessary to increase the frequency of sootblowing for a
If either the port or starboard FD fans fail, the centre fan can be selected to couple of days to clear the boiler tubes, as a result of bad combustion
supply the boiler which has the defective FD fan. The flaps are arranged to conditions during relighting.)
isolate the defective FD fan and open up the common trunking..
(Note: Due to the capacity of the individual fans a single fan must never be
used to supply two boilers.)
Control of the fans is from the Forced Draught Fans and Air Heaters DCS
graphic T30-452-06, from which the seal air fans are also controlled and the
Combustion Control DCS graphic T30-452-11.
The crossover flap B has a limit switch which indicates to the DCS that the
centre FD fan is operating on the port boiler.
a) Change fuel oil and air controls on both boilers from automatic
to manual.
a) On loss of steering gear control from the bridge determine the Instructions must be transmitted to the steering gear room from the bridge by
nature of the failure and if local steering control via the control telephone.
system is possible proceed as follows, if not adopt steering
control using the directional pilot valves. As the pump directional pilot valves are controlled individually by hand it is not
possible to ensure that control of two pumps would take place at exactly the same
b) Establish communication with the bridge via the telephone time and only one pump unit must be operating when in emergency control from
system in the steering gear room. A telephone is located in the the steering gear room. In order to operate the emergency steering system, the
steering gear room. steering control selector switch on the steering gear starter panel must be in the
LOCAL position and the starting and stopping of the pumps takes place in the
Indication of the rudder angle and a compass repeater are provided for manual steering compartment.
control of the steering gear.
c) Select one pump and ensure that the main power switch is Procedure for Emergency Operation of Steering Gear Using
turned to the ON position and the pump starter switch is turned the Directional Pilot Valves
to the START position. Ensure that the control circuit switch is
turned to the NORMAL position. a) On loss of steering gear control from the bridge, establish
communication with the bridge via the telephone system in the
d) Turn the steering control switch on the steering gear starter steering gear room. A telephone is located in the steering gear
panel from the REMOTE to LOCAL control position. room.
Indication of the rudder angle and a compass repeater are provided for manual
control of the steering gear.
AFT (NO.2) BURNER AFT BURNER AFT BURNER AFT (NO.2) BURNER
FO REC HFO BRNR HFO BRNR FO REC
V/V V/V V/V V/V
GAS GAS
START STOP FLAME BRNR BRNR FLAME START STOP
V/V V/V
EMERG BLR ATOM FO GAS ADD FO SHUT ADD FO SHUT GAS FO ATOM BLR EMERG
V CLOSE V CLOSE
TRIP TRIP LOW LOW FIRING FIRING LOW LOW TRIP TRIP
FWC ATOMIZ AIR FLOW FO FLOW FO FLOW AIR FLOW ATOMIZ FWC
MANU AUTO MANU AUTO MANU AUTO MANU AUTO MANU AUTO MANU AUTO MANU AUTO MANU AUTO
OPERATION MODE FO SHUT V/V IGNITER IGNITER IGNITER IGNITER FO SHUT V/V OPERATION MODE
NOR PURGE BURN CLOSE OPEN OFF INSERT SPARK OFF INSERT SPARK LAMP TEST OFF INSERT SPARK OFF INSERT SPARK CLOSE OPEN NOR PURGE BURN
FLUORESCENT LAMP
OFF ON
FO V/V FO V/V FO V/V FO V/V
CLOSE OPEN CLOSE OPEN CLOSE OPEN CLOSE OPEN
FWD (NO.1) BURNER AFT (NO.2) BURNER AFT (NO.2) BURNER FWD (NO.1) BURNER
When the second burner is required, adjudt the FO pressure to more than 11
At the Local Control Panel
bar and repeat the ignition procedure l) and m) above.
a) Turn the OPERATION POSITION switch from the REMOTE
position to the LOCAL position. (Note: If the burner does not ignite or fails after ignition, repeat the purge
procedure from f). The superheat vent valve should be opened as soon
b) Fully close the air flow control valve and start the FD fan. as the first fire is lit.)
c) Open the fuel oil pump discharge pressure control valve to WARNING
50% and start the FO pump and manually adjust the discharge If ignition is lost from both oil/gas burners, the furnace is to be thoroughly
pressure to 15-25 bar. purged of combustion gases before relighting is attempted. When the FO
shut-off valve is closed due to a LOW-LOW drum level alarm, the ADD
d) Turn the OPERATION POSITION switch from LOCAL to the FO SHUT V CLOSE button is to be pressed for 3 seconds to reset the
EMERG position. alarm situation.
(Note: The differential pressure between the wind box and the furnace should To pass control back to the DCS, the boiler pressure should be above 1.5 bar
be above 15mbar. The furnace purge should be conducted until the and one burner in use. To pass control back to the DCS, the OPERATION
PURGE FINISH lamp illuminates.) POSITION switch must be turned to the REMOTE mode and on the DCS
screen T30-452-13, press CONTROL SELECT and click ON.
g) Turn the OPERATION MODE switch from PURGE to the
BURN position.
If a fire should occur in the engine room: b) Sound the evacuation alarm.
l) If any person is seriously injured, request assistance from the
nearest rescue centre.
c) Stop all the ventilation fans.
General
m) Prepare to operate the High Expansion Foam fire fighting
d) Start the emergency generator and put on load.
a) Sound the fire alarm and inform the Chief Engineer and system if necessary, depending on the extent of the fire. The
the bridge. Do not attempt to tackle the fire alone without procedure for this is described in section 5.9. If the fire is not
e) Trip the quick-closing valves and the engine room auxiliary
informing others of the situation. in an area covered by the High Expansion Foam fire fighting
machinery and close all fire flaps and funnel doors.
system, operate the CO2 system. See section 5.2 CO2 Flooding
b) If personnel are missing, consider the possibility of searching System.
f) Count all personnel and ensure that none are in the engine
in the fire area. room.
In Port
c) Determine the location of the fire, what is burning, the direction a) Activate the emergency shutdown system in agreement with g) Start the emergency fire pump and pressurise the fire main.
of spread and the possibility of controlling the fire. Determine if the gas terminal duty personnel and prepare to vacate the
oil or other materials are feeding the fire and take steps to cut off berth if required. h) Prepare to operate the High Expansion Foam fire fighting
the supply of combustible material, eg operate quick-closing or system if necessary, depending on the extent of the fire. The
other accessible valves to shut off oil supply to the fire. b) Conduct a crew check and organise crew for fighting the fire. procedure for this is described in section 5.9.
d) If the fire is in an isolated compartment close the doors to the c) Inform the local fire brigade even though the fire appears to
compartment and shut off ventilation. be under control.
e) If necessary start the emergency generator in order to ensure d) If personnel are missing, consider the possibility of searching
continuity of electrical supply. in the fire area.
5 - Dry Powder Fire Extinguishing System Release Cabinets for Port and Starboard Manifold Monitors
24 22 6 - Emergency Stops for Accommodation, Engine Room and Cargo Ventilation Fans
17 - Automatic Telephone
Upper Upper
Deck 18 Deck
18 - Emergency Breathing Apparatus Cylinders Recharging Compressor
Starboard Accommodation
28 29 31 Alleyway
19 - Emergency Breathing Apparatus Recharging Compressor Start/Stop Pushbuttons Panel
Starboard
17 20 - Gas Detection System Extension Alarm Panel
30 16
21 - Gas Detection System Monitor
Forward 15
14
22 - Engine Room Quick Closing Valves and Fire Dampers Operating Panel
13
23 - Spare CO2 Cylinders for Portable Fire Extinguishers
Start emergency Working or control air compressor start (55kW), Low duty condensate pump start (32A)
diesel generator Battery To be run
only if emergency generator load below 1,300A
(850kW) starting intermittently
(required for control valves on FD fans,
and diesel FO atomising air)
All unrelated equipment Main turbine gland steam exhaust fan start (32A)
should be switched off and
feedback mode to be set
No.2 central FW cooling pump start (230A).
If CFW cooling temperature above 38ºC
Automatic Main condenser vacuum pump start (74A),
start main SW cooling pump (130A) and stop
circuit breaker together with recirculating pump (2.2kW)
when CFW cooling temperature is below 34ºC
closed
Emergency Alternator
Actual Total Total
Rated Rated Actual
Capacity/rating: 450V, 3ph, 60Hz, 850.4kW, 1,364A, 1,063kVA Seq. Machinery List Total Expected Starting Expected Starting Starting
Start Equipment Total Consumption Time Remarks
Consumption Current Current Current Current
0.8pf, 4 pole, IP44 Load (kW) Load (kW) Load (kW) (A) (A) (Sec)
Load (kW) (A) (A)
• The engine room lighting to be restricted to emergency lighting 9 Boiler Burner Ignition (Burner On) and Steam Pressure Raised to Enable Turbine Generator to Start
only
• Domestic, navigation and communication equipment to be 10 Turbine Generator LO Pump 3.7 964.4 3 788.3 5 40 1,344.2 1,379.2 0.5
restricted Turbine Generator
11 2.5 966.9 2 790.3 4 24 1,348.2 1,368.2 0.5
Turning Gear
• No.2 boiler FD fan to be used for boiler cold start
• No.2 central FW cooling pump to be used when required 12 Main SW Circulating Pump 250 310 225 270 400 2,342.2 460.2 2,402.4 2
• All electrical machinery is switched off and will to be manually 13 Condensate Drain Pump 18.5 960.7 15 785.3 25 209.2 1,339.2 1,523.4 1
started when required
14 Control Air Dryer 4 60 4 0.45 5.2 5.2 60.2 60.2 Instant
• The control air and working air reservoirs are fully charged.
They can be topped up by intermittently running an air No.2 Main Central Fresh Auto Transformer
15 160 710 140 585 230 923 984.2 1,677.2 13
compressor Water Cooling Pump 70% Tap
22 If Emergency Generator Load Current is 1,300A or Above, Auxiliary Feed water Pump, Engine Room Vent Fan and Working Air Compressor to be Stopped
BF98 BF97
BF09
Under
BF86 BF85 Deck Passage Bosun's Store BF11 BF03
BF14
BF101 BF77 BF09
BF94 BF83 BF04
Steering Gear
BF78 BF62 Bosun's
Room
B54 BF80 (P) Store BF05
BF79 BF76
BF102 BF75 (S)
BF61 Forward FO
From Water Spray Tanks (P&S)
BF103 BF73 BF74 Emergency Fire Pump
Pumps BF07
Fuel Oil (650/72m3/h x 90/115mth)
Aft Peak Tank Tanks
Engine Casing
BF71 BF72 (P & S) BF08 BF06
For Bilge
Eductor No.1 WB
From BF69 Driving for Tank (C) Fore
Fire Main BF70 Sea Chest Pipe Duct Peak
Stern Tube Pressure
Pump Void Tank
Cooling B10V B11V B40V Pipe Duct
Water Shore
Bilge, Fire & GS Pumps 1 2 Fire Pump
Tank Connection BF43 Bow Thruster and
(245/150m3/h x 30/115mth) (150m3/h x 115mth)
Emergency Fire
BF45 BF41 Pump Room
Fire Hydrant for
BF109 Bow Thruster
BF68 BF62 BF33 BF19 Room
For Emc'y Gen Rm PI BF39
FW Tank BF79
(Outside Room) BF59 BF58
(P&S) BF50 BF28
BF60 BF54 BF49 BF46 BF35 BF31 BF18 BF14
BF26 BF21
BF64
Distilled BF101
BF82 BF80 BF78 BF52 BF16 BF06
Water
Tank BF66 BF37 BF23
From Engine BF05
Room BF02
BF10 BF04
No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
Engine BF20 BF03
Casing Accommodation BF55 BF47 BF29
Bosun Store
BF09
BF102 BF56 BF30
BF11
BF01
To Swimming Pool From Emergency
BF105 BF12
Fire Pump
Distilled
Water BF36 BF25 BF22 BF15
BF81 BF65 BF13
Tank BF104
BF57 BF53 BF51 BF34 BF24
BF63
BF38 Key
BF67 BF61 BF48 BF32 BF27 BF17
Steering Gear BF108
Fire Main
Room
High Expansion Foam BF40
Shore BF44 Sea Water
and CO2 Room Connection BF42
Emergency Fire Pump line pressure pump is normally set for an automatic start and stop operation.
d) The sea water hydrophore tank is now operational and SW can
Maker: Teikoku Machinery Works Ltd be supplied to the fire main by opening valve B43V.
The pump selector switch at the main switchboard is set to REMOTE and
Model: 300-2VSR-Am NV-S automatic operation may then be selected at the fire pump system DCS graphic
e) Select automatic operation for the fire line pressure pump.
Capacity: 650/72m3/h x 90/115mth screen T30-447-01. The pump may be started and stopped manually if required
by calling up the pump faceplate at the DCS screen and clicking on the START
The fire line pressure pump will maintain 1.0 - 2.0 bar pressure in the fire
or STOP soft keys as necessary.
Fire Line Pressure Pump hydrant system.
The main fire pump may also be started and stopped from the DCS screen T30-
Maker: Teikoku Machinery Works Ltd
447-01 provided that the main switchboard selector switch is set to remote. Procedure for Supplying Sea Water to the Fire and Deck
No. of sets: 1 There is no automatic start facility available for this pump nor is there an
Type: Centrifugal
Wash System
automatic start after a blackout.
Model: 32-2MSH-Am The fire and deck wash system may be supplied by the main fire pump, located
Capacity:
3
2m /h at 115mth The fire, bilge and GS pumps may be started and stopped locally if the main in the engine room, and by either of the two fire, bilge and GS pumps, also
switchboard is selector switch is set to local, but when set to remote the pumps located in the engine room. These pumps take suction from the main sea water
are manually started and stopped from the DCS graphic screen T30-447-01 by crossover pipe and so the ship side valves S101V and S105V must be open
Introduction calling up the individual pump faceplates. and operating.
The fire hydrant and deck wash system can supply sea water to: The main fire pump, the fire line pressure pump, water spray pumps and the a) All intermediate isolating valves along the fire main on the
fire, bilge and GS pumps all take suction from the main sea water crossover main deck must be open.
• The fire hydrants in the engine room
pipe. Either the high or low sea chest must be open to this suction main at all
• The fire hydrants on deck times. b) All hydrant outlet valves must be closed.
• The fire hydrants in the accommodation block
c) Set up the valves as shown in the table below:
• Hawse pipes
• Forward bilge eductors It is assumed that the sea water main suction valves at the sea water valve
• The hot foam system chest(s) are open to provide sea water suction.
To
Fire and Wash Deck
System
(5.1a) BF80V
Port Passageway 3rd Deck
Key
BF76V 2nd Deck (Port)
Sea Water 2nd Deck (Starboard)
BF75V
Fire/Deck Water
To
Ion Exchanger
B74V Overboard (Section 2.2.1b)
BA14V
PI B66V
To Ion To Void Space
Exchange Stripping
Eductor PS
Eductor
Fire main pipelines run along the port and starboard sides of the ship in the
under deck passage. Hydrant connectors are provided at strategic positions so
that all parts of the deck may be reached by water spray from the appropriate
hoses. The water curtain is supplied from the fire and deck wash main.
Water from the fire and deck wash main is used for operating the forward bilge
eductors.
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
Cargo Cargo Bow Compressor Emergency
Vent Stop
Vent Stop
Vent Stop
Vent Stop
Vent Stop
Vent Stop
Vent Stop
No.1/2 L/V ,H/V Swtbd
Rooms,Trans Rooms Compressor Switchboard Thruster Motor Generator Paint
and ECR Room Room Room Room Room Store
TD TD TD TD TD TD
P P P P P P
No.1/2 L/V and H/V Switchboard Cargo Switchboard Bow Thruster Room Cargo Compressor Motor Emergency Generator Paint Store
Cargo Compressor Room
Rooms and Transformer Rooms Room Room Room
and Engine Control Room
A A A A A A A
A A
S S
7 Bar 7 Bar
Air Supply Air Supply
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
CO2 Alarm
Cargo Cargo Bow Compressor Emergency
Vent Stop
Vent Stop
Vent Stop
Vent Stop
Vent Stop
Vent Stop
Vent Stop
No.1/2 L/V ,H/V Swtbd
Rooms,Trans Rooms Compressor Switchboard Thruster Motor Generator Paint
and ECR Room Room Room Room Room Store
TD TD TD TD TD TD
P P P P P P
No.1/2 L/V and H/V Switchboard Cargo Switchboard Bow Thruster Room Cargo Compressor Motor Emergency Generator Paint Store
Cargo Compressor Room
Rooms and Transformer Rooms Room Room Room
and Engine Control Room
A A A A A A A
A A
S S
7 Bar 7 Bar
Air Supply Air Supply
(Note: Allow time for structural cooling before opening the engine room and
ventilating the CO2 gas.)
WARNING
Do not enter CO2 flooded space without using breathing apparatus.
In the unlikely event of pilot gas initiation failure, the CO2 system may be
operated from the CO2 room.
c) In the CO2 room manually open the main valve to the area
containing the fire. Turn and pull the valve handle so that it
opens fully for CO2 is to be released into the protected space.
To Funnel Ventilation
Fire Control
F50V Damper (Upper S)
Station To Fire Damper Air Cylinder for Engine Room Ventilation
To Funnel Ventilation
PIAL
PX F51V Damper (Upper P)
DCS
PI
To Funnel Ventilation
225 Litres Damper (Lower S)
9 bar F52V
To Funnel Ventilation
Damper (Lower P)
Main LO Low Sulphur Gas Oil Gas Oil Low Sulphur To Diesel Generator Room
Gravity Fuel Oil Storage Storage Fuel Oil Exhaust Fan Fire Damper
Tank (P) Tank (S) F55V
Tank Tank (P) Tank (S) 3rd Deck
Instrumentation
To Welding Space
Exhaust Fan Fire Damper
Engine room fire dampers are all connected to a three-way operating cock Procedure for Operating the Quick-Closing Valve System
which supplies air to the damper cylinders in order to keep the dampers open.
When the damper cylinder is vented the damper is closed by means of gravity a) At the emergency shut off cabinet, check the quick-closing
acting on a counterweight. Damper cylinders may be vented as a group by valve group in which the valve(s) to be closed is/are located.
means of the three-way supply cock or may be operated individually by a
three-way cock located close to each damper. b) Turn the three-way operating cock lever to supply air to the
quick-closing valves.
Oil Tank Quick-Closing Valves
The quick-closing valves in the selected group will be closed when the air
pressure acts on the valve piston. To open the valve again, the three-way
CAUTION
operating cock must be turned so that the air supply line to the valves is vented.
Some tanks such as lubricating oil tanks do not have quick-closing
The tripped valves must be closed by turning the valve handle and then opened
apparatus fitted. This is because they are normally closed and only
again in order to reset the trip mechanism.
opened for short periods when required. It is important to ensure that
these are always closed when not in use.
To Funnel Ventilation
Fire Control
F50V Damper (Upper S)
Station To Fire Damper Air Cylinder for Engine Room Ventilation
To Funnel Ventilation
PIAL
PX F51V Damper (Upper P)
DCS
PI
To Funnel Ventilation
225 Litres Damper (Lower S)
9 bar F52V
To Funnel Ventilation
Damper (Lower P)
Main LO Low Sulphur Gas Oil Gas Oil Low Sulphur To Diesel Generator Room
Gravity Fuel Oil Storage Storage Fuel Oil Exhaust Fan Fire Damper
Tank (P) Tank (S) F55V
Tank Tank (P) Tank (S) 3rd Deck
Instrumentation
To Welding Space
Exhaust Fan Fire Damper
Engine room fire dampers operate to close ventilation openings in the event a) The main fire damper three-way valve, located at the emergency
of a fire. The dampers are kept open against a closing force (gravity acting shut-off cabinet in the fire control station, must be turned to the
on a counterweight) by means of air pressure acting on the damper cylinder VENT position to actuate all the fire dampers. The dampers
piston. When air pressure is vented the damper or dampers will close. The fire will close under the action of their counterweights when air is
damper pipework is supplied directly from the GS air system main pipe and air vented from their cylinders.
pressure is constantly applied to the system.
b) Returning the three-way cock to the OPEN position will
Activation of the three-way control valve at the fire control station control direct compressed air in to the cylinder pistons and open the
panel will vent the damper air line and cause all fire dampers to close. dampers.
Operation of individual local damper valves will vent each individual damper
as required and allow that damper to close. If dampers for individual locations require closing, the three-way cock
positioned in a safe place near the fire damper must be turned to the VENT
Fire dampers are fitted as follows: position. The damper can be opened again by turning the three-way cock
to the OPEN position.
Item Valve
Funnel vent damper (upper port) A49V
Funnel vent damper (upper starboard) A50V
Funnel vent damper (lower port) A51V
Funnel vent damper (lower starboard) A52V
No.1 engine room supply fan damper
No.2 engine room supply fan damper
No.3 engine room supply fan damper
No.4 engine room supply fan damper
No.1 engine room exhaust fan damper
No.2 engine room exhaust fan damper
Purifier room exhaust fan fire damper A53V
Diesel generator room exhaust fan damper A54V
Oil store exhaust fan damper A55V
Chemical store exhaust fan damper A56V
No.1 boil-off leak gas fan damper A57V
No.2 boil-off leak gas fan damper A58V
Welding space exhaust fan damper A59V
Salwico CS3000
POWER ON
CS3000 CONTROL CHECK
FIRE
DISCONNECTION
6 13 DATE 2004-09-02 TEST......
ALARM TRANSFER
SECTION DETECTOR TIME 08;52;24
EXTERNAL ALARM
MENU DELAY OFF.....
SYSTEM FAULT..
F1 F2 F3 F4 ABNORMAL COND.
ALARM MUTE
ALARMS IN QUEUE 7 8 9 S SECTION EA
EXTERNAL FAULT
ALARM
4 5 6 D DETECTOR EC EXTERNAL
CONTROL
M MUTE
EXTERNAL CONTROL
ALARM RESET ALARM
ACTIVATED 1 2 3 SD
SMOKE
DETECTOR AD DELAY R RESET
SECTION / DETECTOR
NOT RESET 0 ON OFF TIMER LIST
Fire Alarm Panel Return key: The system returns to normal status,
‘Salwico CS30000’ is displayed.
The fire alarm panel is activated when a fire alarm is detected on the system.
S, D, SD, EA, AD: Command keys used to choose the
The FIRE indicator flashes and the section number and detector address in
unit (section/detector no. etc) to
alarm are displayed on the numeric display.
operate.
Different parts of the fire alarm system can be disconnected for instance, Disconnected units can be reconnected from the disconnected list by selecting
sections, detectors, manual call points, section units, alarm devices, external the appropriate disconnection. The status is then changed by pressing the ON
control devices and loops. This can be useful when there is welding in a key or using the same procedure as Disconnection, but press the OFF - ON
particular section or removal of detectors is required due to structural shipboard button.
work etc. A whole section can be disconnected permanently or for a defined
time interval using the timer function. The disconnected section can only be
reconnected from the ‘Disconnections’ list.
When operating the system a mistake can be corrected using the BACK key to
erase one step at a time backwards. To interrupt the disconnection function and
return to normal status, press the RETURN key . The system returns to normal
status and ‘Salwico CS3000’ is indicated.
Disconnection Process
Key
Pushbutton
Thermal Detector
For General Alarm
Pushbutton
Smoke Detector
For Fire Alarm
SP
SP
CO2 Crew's
SP
SP
Dairy Messroom SP
Locker
Emergency Meat Room
Generator Room Room Hospital
SP SP
Crew's
SP Lounge
SP
SP
Vent Vent Vent Vent SP
P.T T.V. Room
Locker SP
Fish SP Spare
Room Crew's Pantry CD
SP
CD SP
Crew (D)
&
SP
& SP
PD
SP PD
SP
Spare
SP
Up Vegetable Crew (C)
Engine Casing Room Engine Casing
SP SP
Dn Up
SP
Dn Up
SP
Dn Dn Spare
Galley
Crew (B)
SP
Lift Gymnasium
Dry Provisions Lift
SP
Store SP
Spare
SP
Locker
Crew (A) Night
SP
SP
SP Pantry
SP
Lkr
Incinerator
SP
Dn Workers Officer's
Room SP CD SP
CD Pantry SP
&
Officer's
SP
SP
& PD Health Room PD
Vent Vent Vent Vent T.V. Room
SP
SP
Duty Officer's SP
Mess Messroom SP
SP
High Expansion Foam
and CO2 Room Swimming Swimming
SP
Pool Tank SP Pool
Officer's
Smoking Lounge
SP
Down Up Up
Down Down
A Deck B Deck
Key
Thermal Detector
Smoke Detector
Pushbutton
For Fire Alarm
Down Up
Dn Up
SP SP SP
1st Engineer's
Day Room
SP Gas Gas
Pumpman Oiler (A) Engineer's Engineer's
Pumpman Day Room
(B) Bedroom
(A)
SP
SP SP
SP
SP
SP SP
SP
Oiler (B)
SP
Assistant Electrician
SP
SP SP
Able SP
Fan Room (Supply) Seaman (B) Oiler (A) Fan Room (Supply) SP
SP
1st Engineer's
SP CD
SP CD Bedroom
SP & SP
SP
SP & SP
SP Assistant PD
SP
PD
SP
SP
SP
Able Oiler (B)
SP
Seaman (A) 4th Officer
SP
SP SP SP
Fan Room SP
(Exhaust) Seaman 2nd Assistant
SP Lift
(B) SP No.1 Oiler Lift Engineer
5th Officer
3rd
SP
SP SP
SP
Drying Assistant
SP
Engineer
Night Room Night
Pantry Bosun Pantry SP
SP
Drying
SP
SP
Crew's Officer's SP
Room Laundry SP
Laundry P.T
CD Chief Officer's
& CD
Fan Room (Supply) PD SP Fan Room (Supply) & Bedroom
Locker SP
SP
SP Steward
SP
PD
SP
SP
SP Locker
SP
SP
SP
SP
SP
Cook (A) 3rd 2nd
Chief
SP
Officer Officer
Seaman Cook
SP
Dn Up
Down Up
C Deck D-Deck
Key
Pushbutton
For Fire Alarm
Thermal Detector
Dn
Smoke Detector
Fan Room
Up Down Up
SP SP Cadet (D) SP
SP
Chief Engineer's
Bedroom Captain's SP SP
CD Bedroom CD Pilot
& &
SP
SP
SP PD Captain's PD
SP SP
Day Room
SP
SP
Chief Engineer's
SP
SP
Day Room SP
SP
SP
CG Locker Electrical
Chief Captain's
Engineer Lift Equipment
Office Lift Room
Office Cadet (B)
SP SP
SP
Night
SP
SP SP
SP SP SP
Pantry
Phone Rm SP
Night
SP
CD SP CD
SP
Pantry SP
Spare &
& PD
Spare Officer (A)
Officer (B) SP
PD Cadet (A)
SP
SP
Up Down Up
To Catwalk
Fan Room
Dn
F Deck
E Deck
Key
Pushbutton
For General Alarm
Thermal Detector
Pushbutton
For Fire Alarm Smoke Detector
Speaker For Fire
SP And Emergency Portable Gas
General Alarm
GD Detector Cabinet
Up Down Down
Cargo Office
SP Wheelhouse
SP
Up
PD
GD SP
SP
SP
Navigation
Dn Up Locker Down SP
SP
Administration Lift SP
Lift Radio
and Central Table
Engine Office Control Rear
SP
Room
SP
SP
CG Lkr
SP
CD
SP
Battery Night
Pantry
Room
Up Down Down
SP
Pushbutton
For Fire Alarm
Smoke Detector
Bow Thruster
and Emergency
Fire Pump Room
Rope
Space
Forward Fuel
Oil Tank Fore Peak Tank
(P&S)
SP
CO2
No 1 W.B.
Tank (C)
Key
Cofferdam
Space for Piping
SC
Vent
UP SC
DN
UP
UP
DN
UP
DN UP
DN UP
UP Main LO
Sump Tank
DN UP
UP
SC
DN UP
UP Lift
Lift Space
Space Scoop Inlet
UP
Ahead Stop Valve/
Astern Manoeuvring
Valve
UP UP
Vent
SC Vent SC
DN
SC
4th Deck
Purifier Room Floor
Low Sulphur
Tank (P)
UP
Distilled F.W.
Water Tank
Tank (P&S)
(P&S)
SC
Vent Vent Vent UP UP
UP
UP
Key
Welding
Area
SC SC Signal Column
Workshop
Diesel Oil
Electrical Storage
Workshop Lift Tank (S)
and Store Space
3rd Deck
Key
CO2
CO2
SP Pushbutton
For General Alarm
CO2 Pushbutton
DN For Fire Alarm
Vent Vent Engine
Control
SC Fire Alarm Bell
Room
SP
SP
DN SP
CO2
SC SC SC SC Signal Column
Lift
F Space
Boiler
Elevator SC CO2 SC
UP Smoke Detector
Vent
Hood
Room Thermal Detector
Lift
DN SP
Space
UP Flame Detector
DN
Speaker For Fire
SP
Vent Vent SP And Emergency
General Alarm
Air Horn
F
CO2
Store
GT LO
Settling
Tank
GT LO
Storage
Tank
GE LO
Settling Generator
Tank Main Lubricating Main Lubricating Engine
Oil Settling Oil Storage Diesel Oil
GE LO
Storage Tank Tank Service
Tank Tank
Dn
SP
No.2 Cargo
CO2
CO2 SWBD Room
Rotating (Low)
Light for L Paint General Deck SP
CO2 Alarm R Store Store Store
SP
CO2
Vent Vent
Air Condition Room
SP
Key
Port Boiler
Economiser Pushbutton
SP For Fire Alarm
SP
SP CO2 Thermal Detector
SP
SP
Economiser Up SP
Incinerator Room
Vent Vent
F
SP
SP CO2
SP
High Expansion Foam/CO2 Room
Ships
Laundry SP
No.1 Cargo
SP Fire SWBD Room
Control (Low)
CO2
Station
Key
Pushbutton Air Horn for CO2 Alarm Air Horn for Fire Alarm Smoke Detector Thermal Detector
For Fire Alarm CO2
Main Supply
4-20mA (0-100% System Control Panel)
Standby Supply
Gas Alarm Fault
Reset 30% Alarms & Fault
Motor Room System
4-20mA x 5/Fault Control Panel
3 Flammable
Stop Valve Box 0-100%LEL Supply
Gas Detectors
4-20mA (0-100%)
DCS
BH19 TANKSCAN
(Sample Point Indent) 1 Flammable
4-20mA MOTOR ROOM
31 Sample
GAS DETECTION SYSTEM Bosun Store
Points
Fault
Drain
Vent
4-20mA x 8/Fault FIRE CONTROL STATION 30% Alarms x 5/Fault 30% Trip
EXTENSION
8 Flammable ALARM PANEL ENGINE CONTROL ROOM
Gas Detectors
ENGINE ROOM
GAS DETECTION SYSTEM
30% Alarms x 8/Fault
ACCEPT POWER ON
RESET FAULT
Cargo Machinery
Extension Alarm Panel
TEST GAS/ALARM
System Control Panel
Engine Room Gas Detection System (Fire Control Station)
4-20mA x 5/Fault
Boiler
4-20mA x 23/Fault Control 30% Trip
Panel
22 Flammable
Gas Detectors
Key
ACCOMMODATION 30% Alarms x 23/Fault Electrical Signal
GAS DETECTION SYSTEM
Sample Pipe
Flammable Gas Detector
(Emergency Diesel Generator Room) Accommodation Area Gas Detection System
There are two types of gas detection systems used throughout the ship The panel also has a 220V power supply and a changeover unit, which provides (Note: Only authorised personnel should proceed any further in the operation
covering all the cargo, machinery and accommodation spaces. The systems back-up from the emergency system in the event of a power failure. of the gas detection panel and instructions to do so can be found in the
use the infrared gas analyser method and the catalytic combustion method. manufacturer’s instruction book.)
The two systems are: The system control panel includes:
• Display Screen - provides high and low alarm thresholds for 2. TQ 800 System
1. BH19 Tank-Scan Aspirated System eight sample locations
The system contains of groups of 4-20mA Measurement Cards, each measuring
The system is situated in the cargo control room and the sampling sequence • Keypad - allows the operator to enter commands whilst in a single detector and displaying the reading on the front of the card. They
is automatically controlled by solenoid selection valves, with the sampled gas the Menu screen monitor the atmosphere continuously at the points where sensing heads
being drawn into the panel by pumps, before being passed over an infrared gas • Acknowledge Pushbutton - used to acknowledge an alarm and are fitted and will detect the presence of any combustible gas should it
analyser. to mute the local/internal annunciator accumulate. The sensors provide electrical outputs to the cards, proportional
to the amount of gas present, to alarm and indicating panels.
The system draws samples from the following locations: • Page Pushbutton - will display the next page which shows the
next eight sample locations The front panel of the Measurement Cards display pushbuttons and indicator
• Cargo hold spaces - upper and lower
• Screen Wake-Up Pushbutton - will activate the start-up screen LEDs as follows:
• Cargo tank annular spaces - upper and lower from the screen saver mode
• Vent masts - 4 sets Pushbuttons
• Keyboard Socket - allows the use of an external keyboard
• Double bottom pipe passage - forward and aft when operating the system • SEL - select button
• Under deck passages - port forward and aft, starboard forward • Security Switch - a two way key switch with a removable key. • - Increase
and aft During normal operation the key is in the horizontal position • - Decrease
and the Start-Up screen is displayed. The key can be turned
• Cargo compressor room - upper and lower • SPR - Special function button
to the vertical position to access the Main Menu screen and
• Cargo motor room system functions. The key can also be removed to eliminate
unauthorised access to the system.
The analyser works on the principle that infrared light is absorbed by the
methane gas. Methane gas has a distinctive absorption band in the infrared
spectrum. Therefore if a sample of gas is compared against a reference sample Procedure to Reset Alarms
of air, the difference in output from an infrared sensor will be in proportion
to the gas concentration. The system is reset using the keypad and the screen display as follows:
If the methane concentration of any sample point reaches 30% LEL, an a) With the Start-Up screen displayed, turn the security switch
audible alarm is sounded and the corresponding indicator lamp is lit on the to the vertical position and the screen will change to the Main
panel. Additionally, a gas detection alarm is activated on the DCS graphic Menu display as follows:
screen T30-429-01 CARGO GAS DETECTION and on the extension alarm
1. - View and reset alarms
panel in the fire control station.
2. - Reset concentration alarms
The system also contains an internal gas sensor to detect the flammable gas 3. - Exit
level inside the panel. The unit will shut off the power supply if an internal gas
leak is detected and provide failure alarms, which are transmitted to the DCS
and the extension alarm panel situated in the fire control station. b) By entering number 1, using the keypad, the screen is changed
to the System Alarm Status display, showing the sensor in
alarm condition.
Main Supply
4-20mA (0-100% System Control Panel)
Standby Supply
Gas Alarm Fault
Reset 30% Alarms & Fault
Motor Room System
4-20mA x 5/Fault Control Panel
3 Flammable
Stop Valve Box 0-100%LEL Supply
Gas Detectors
4-20mA (0-100%)
DCS
BH19 TANKSCAN
(Sample Point Indent) 1 Flammable
4-20mA MOTOR ROOM
31 Sample
GAS DETECTION SYSTEM Bosun Store
Points
Fault
Drain
Vent
4-20mA x 8/Fault FIRE CONTROL STATION 30% Alarms x 5/Fault 30% Trip
EXTENSION
8 Flammable ALARM PANEL ENGINE CONTROL ROOM
Gas Detectors
ENGINE ROOM
GAS DETECTION SYSTEM
30% Alarms x 8/Fault
ACCEPT POWER ON
Cargo Machinery
Extension Alarm Panel
RESET FAULT
TEST GAS/ALARM
System Control Panel
Engine Room Gas Detection System (Fire Control Station)
4-20mA x 5/Fault
Boiler
4-20mA x 23/Fault Control 30% Trip
Panel
22 Flammable
Gas Detectors
Key
ACCOMMODATION 30% Alarms x 23/Fault Electrical Signal
GAS DETECTION SYSTEM
Sample Pipe
Flammable Gas Detector
(Emergency Diesel Generator Room) Accommodation Area Gas Detection System
• Bow thruster rooms (Note: Only authorised personnel should proceed any further in the operation
Alarm Points of the gas detection panel and instructions to do so can be found in the
The system has two alarm points (A - High and B - Low) which are set and The motor room system control panel will also stop the ventilation fans. manufacturer’s instruction book.)
each can be configured at any point within the scale. There is also an Alarm
Validation Period (AVP) which is used to prevent spurious alarms. The AVP Accommodation control panel:
is the time (0-60 seconds) that the gas content has to be above or below the • Emergency generator room
alarm set point before the alarm relay operates.
• Main air conditioning air intake
40 60
20 80
8 12
BATT.
4
0 100 20
40 60
80 20
40 60
80
SPAN GAS INLET TOXIC GAS 20
40 60 16
80
(PUSH)
0 100 0 100 DETECT. 0 20
0 100
% O2 BATT
. %LEL %LEL % LEL
0
2 4 6 8
10
BATT
. % LEL
COMB O2
BATT. SPAN 100
100 BATT CO2 PREP
CHECK.
METER LIGHT CO2
10
OFF 20 OFF MEAS
CHG.
COMB OXYGEN
ZERO ADJ. CAL ADJ.
- + - + ALARM RESET
OUT
MODEL NP-237H
RIKEN KEIKI RIKEN KEIKI GX-7 RIKEN KEIKI
a) Notify the Cargo Engineer or Chief Officer (in case of an The vessel is supplied with three types of portable gas detectors:
engine room gas detection alarm, the duty engineer will notify
the bridge or CCR if in port). 1. Detectors which measure the levels of O2 and are used as a personal alarm
instrument. They are usually attached to the officer’s belt during entry to a tank
b) One or more of the above will investigate. or space which has been gas freed prior to entry.
c) Prohibit all normal entry into the space concerned until it has 2. Detectors which measure the level and volume of O2, CO2, CO and CH4
been declared safe. (methane) present in a tank when the tank is being inerted or gassed up.
d) If the alarm requires further local investigation, call the Master 3. Detectors which measure the dew point during the drying process of a tank
and Chief Engineer. or hold.
WARNING
Under no circumstances are local investigations to be carried out by a
single person. The space is to be considered EXTREMELY DANGEROUS
until proved otherwise.
Subsequent Action
Portable Fire Extinguishers Fire Hose Reel With Nozzle Fire Hydrant With Hose Fixed Type Dry Powder
CO2
(6.8kg CO2) F and 18m Fire Hose Connection Powder Fire Extinguisher for Galley
Exhaust Duct
First Aid Hose Box with Fire Hydrant With Hose
D.S Draft Stop
F Hose Reel and Valve Connection
CO2 F
F
E E O
O
Vent Vent Vent Vent Public TV. Room
Locker Phone W
Fish Spare O
Crew's Pantry
Room Crew (D) CD
CD O O
& &
PD O
PD Spare
F
Crew (C)
Up D.S
Vegetable
Engine Casing Room Engine Casing D.S
F
9 Dn Up Dn Up
Dn Galley Dn Spare
O D.S F
9 Crew (B) F
Lift O O Gymnasium
Lift W
Dry Provisions
Store Spare
O Locker
D.S
Crew (A)
D.S
F
CO2
Night
9
O Pantry O
Powder Lkr
Incinerator
Room Davit Suez
Dn Workers O Officer's CD
Room Pantry Health Room
CD & Officer's
& PD PD TV. Room
Vent Vent Vent Vent W
Officer's PT
Duty F Messroom
High Expansion Foam Mess 9
W
A Deck B Deck
W
W
Down Up
Dn Up
F
Oiler Gas Gas F
3rd
Drying Bosun Drying O
Assistant
D.S
D.S
Public
Crew's CD Steward Toilet CD
Officer's
Laundry & &
Fan Room (Supply) Laundry Chief Officer's F
Fan Room (Supply) PD D.S Locker PD
D.S Bedroom
FE Cook Locker W
(A)
E E Chief Officer's
Chief Day Room
Seaman Cook F 3rd Officer 2nd Officer
(A) Cook F
(B)
F
9 9
C Deck
Dn Up
Down Up
D-Deck
W W
E F Portable Foam
Fire Damper For Engine Room 9 Fire Extinguishers (9kg)
Fan Room Fresh Water Spray Nozzle Fire Hydrant With Hose
W
W Connection
O Fire Damper For Other Than Fire Hose Reel With Nozzle
O Engine Room and 18m Fire Hose
W
Up O
F
E 9
Chief Engineer's Captain's
Bedroom CD Bedroom
E O W
&
PD
O
Captain's W Down Up
Day Room O
Chief Engineer's
Day Room F D.S
Funnel Dn Up F
Cadet (D) 9
CD Pilot
F
&
Chief Lift W PD
Engineer Captain's O
Office Office O
D.S
Cadet (C)
D.S
O
Telephone Dn Up
CO2
E Room
F
W CG Locker D.S
Spare Night
E Officer (B) CD Pantry Spare Lift
& Officer (A)
F Electrical
PD 9 Cadet (B) Equipment
Up F Room
Night
Pantry
W
W CD
F &
W Cadet (A) 9 PD
Dn Down Up
W W
To Catwalk
O
O
F Deck
Fan Room
W
E Deck
Key
Repeater Panel Bilge, Fire and GS Pump First Aid Hose Box with Fire Valve With Hose
CO2 Discharge Nozzle R.P.
CO2
M.F.P Start/Stop F Hose Reel and Valve Connection
E Fan Control And Emergency Portable Fire Extinguishers Fire Valve With Hose
Ventilation Fan Fire Pump Start/Stop CO2
Stop Switch For Engine Room F.P (6.8kg CO2) Connection
Fire Hose Reel With Nozzle O Fan Control And Emergency F Portable Foam
Fire Pump Start/Stop D.S Draft Stop
and 18m Fire Hose Stop Switch For Others E.F.P 9 Fire Extinguishers (9kg)
W
Up Down Down W
W
Cargo Office
W
O CO2
Down
O Up W Wheelhouse
W
F PD F
E O
F O
O 9
Navigation
Dn Up R.P. Locker Down CO2
W
W
Lift Lift
and
F Engine Office D.S
D.S
Chart Space C.P.
D.S CO2
CG Lkr CO2
O Central W
CD
Control
W
Battery Room
W
Room
F Night W
9 Pantry W
Up Down Down W
W
Compass Deck
G-Deck
Key
F Portable Foam
9 Fire Extinguishers (9kg)
Bow Thruster
and Emergency
F Fire Pump Room
CO2
CO2
Fore Peak Tank
CO2
F
F
9
9
CO2
CO2
No 1 W.B.
Tank (C)
Bosun's Store
Fire Hose Reel With Nozzle High Expansion System Ventilation Fan
F and 18m Fire Hose F Foam Control Panel
F
9
F
Vent
UP
Boiler
DN
Drain Tank
UP
F
9
F
F 9
9 UP
DN
UP
DN UP
DN UP
A
F UP Main LO
9 Sump Tank
F
DN UP
9
UP
UP
DN F
UP
Lift 9
Lift Space
Space Scoop Inlet
F
UP
9 Ahead Stop Valve/
Astern Manoeuvring
Valve F
9
UP UP
Vent
Vent F
9
F
F
F 9
L/F
DN
Purifier Room
45
F
9 Port Turbine Generator F Semi-Portable Foam
Port
45 Fire Extinguisher (45L)
Boiler
Ventilation Fan
Lift Starboard
Space Turbine Lift
A.P. F Generator Elevator Mach. Foam Generator (60m3/min)
9
Room
F
F F 9
CO2
E
Nozzle For Local Fire Fighting
System
F
9
F
9
Workshop Diesel Oil
Electrical Storage
Workshop Lift Tank (S)
F Space
and Store 9
Low Sulphur
Tank (S)
F
Ventilation Fan
CO2
Vent Vent DN
CO2 CO2
CO2
Fire Hydrant With Hose
Engine Connection
Control
F F
DN Room Fire Hose Reel With Nozzle
9 9
DN F and 18m Fire Hose
F
9 R.P.
F CO2
Lift 9 Foam Generator (18m3/min)
DN
Space CO2
UP CO2 CO2
F DN
9
F CO2 Discharge Nozzle
CO2
Vent Vent
Local Fire Fighting System
L/F Control Panel
F
CO2
CO2
R.P. Repeater Panel
Store
GT LO
Settling
Tank
GT LO
F
Storage
9
Tank
GE LO
Settling Generator
Tank Main Lubricating Main Lubricating Engine
Oil Settling Oil Storage Diesel Oil
GE LO
Storage Tank Tank Service
Tank Tank
Key
Fire Hose Reel with Nozzle Bilge, Fire and General
P Dry Powder Monitor Ventilation Fan (Jet/Spray Combined Type) Service Pump
F and 18m Fire Hose
Fire Hose Reel With O Fire Damper for Other Dry Powder Hose Fire Pump
Nozzle and 18m Fire Than Engine Room with Hand Gun
P
Hose
P Dry Powder Monitor E Fire Damper for Stop Valve for Fire Main Emergency Fire Pump
Release Station Engine Room
Dry Powder Stop Valve for Water
P CO2 Discharge Nozzle Fire Main
Installation Spray Main
CO2
Cargo
X25 Machinery Room X6
CO2 W
P P P P P
W W W W P W W W W W W W W W W
Bow Thruster and
X10 Fire Pump Room
CO2
No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
Cargo
Machinery Room
P P P P P P
F F
P
F F F
F F
F
F F
P O
W W P
P
P
P
W W W W W W W P
P P
P F
E W
W W W W W W W W
P O
W W W W P P
F
W W W W W W W W
W W W W W
P
P
P P
F
9 P
O P P P F
O P
F P W W W W W W P
W 9
F P O
P W P
W W P
X7 X2 X12 X7
W W CO2 W
W
Key
Dn
O
O Ventilation Fan Fan Control And Emergency
CO2 No.2 Cargo Stop Switch For Others
SWBD Room CO2
Paint (Low)
General Deck
W F Portable Foam
Store Store Store 9 Fire Extinguishers (9kg) Spare Charge for all
O Fire Extinguishers
O F
9
CO2 CO2 Discharge Nozzle
Vent Vent CO2
Air Condition Room Valve Box For
Quick-Closing Operation
Fire Hose Reel With Nozzle
Port Boiler F and 18m Fire Hose
Economiser CO2
Bilge, Fire and GS Pump
Fire Hydrant With Hose Start/Stop
O Connection
M.F.P
D.S
Port Boiler O No.2 Cargo Portable Fire Extinguishers Fire Pump Start/Stop
CO2
Forced Draught Fan SWBD Room (6.8kg CO2) F.P
F (High)
O O
O CO2 CO2 High Expansiom Foam
O F System Control Panel Fire Pump Start/Stop
F E.F.P
9
D.S
P.T
Connection
O F O
Foam Generator (18m3/min)
F
Fire Hydrant With Hose
Changing Room
C.G.L Connection
135
Starboard Boiler Incinerator No.1 Cargo O Fire Damper For Other Than
Forced Draught Fan Changing Room SWBD Room Engine Room Fire Hose Reel With Nozzle
F (High) and 18m Fire Hose
F
L/F
9
C.D
9
& First Aid Hose Box with
CO2 CO2
P.D Hose Reel and Valve Repeater Panel
Drying Room F R.P.
CO2
Starboard Boiler F
Economiser Up Locker.
Foam 9
CO2
D.S Draft Stop
Ships No.1 Cargo E Fan Control And Emergency
O
High Expansion Foam/CO2 Room CO2 Laundry Fire Stop Switch For Engine Room Nozzle For Local Fire Fighting
Control SWBD Room
System
Station (Low)
CO2 Master Control For
F CO2
CO2 Discharge
E O W
P CO2
F
M.F.P F.P E.F.P W.S.P
FE R.P.
Key
Immersion Suit
Lifeboat
Embarkation
Ladder B Instruction Plate
LJB
6
LJB
20 B SAFETY
R
J
PLAN
No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
SAFETY
B
R
20 J PLAN
LJB
B
Life Jacket 'B' Class Fire Door
Smoking
Down Up Up
Down Down
A Deck B Deck
Emergency Exit
A
'A' Class Fire Door
M Muster List
Down Up
Dn Up
B Cargo Cargo
Engineer's Engineer's
Pumpman Oiler (A)
Pumpman Day Room Bedroom 2nd Engineer's
(B)
(A) B B Day Room
B B
B Oiler (B)
A
Able B 2nd Engineer's
Assistant Electrician
Fan Room (Supply) Fan Room (Supply) B Bedroom
Seaman B Oiler
(B) (A) CD
CD B &
& A
A PD
PD
Able J
Assistant
Seaman B B Oiler 3rd Engineer
Dn Up
Down Up
C Deck D-Deck
Key
Life Jacket
Emergency Exit
A
'A' Class Fire Door
B
Dn 'B' Class Fire Door
J Method of Donning
Fan Room Life Jacket
M Muster List
Up
B
Chief Engineer's
Bedroom CD Captain's
Bedroom
&
PD A Down Up
Captain's B
Day Room Pilot
Chief Engineer's
Day Room Cadet (D) B
Funnel Dn Up B CD
& A
A A
PD
Chief Captain's
Engineer Lift Office
Office B
Cadet (C)
A
B
Dn Up
B J M B
A Electrical
Telephone CG Locker
B A Equipment
Lift
Night Spare
B Room
Spare Cadet (B)
Officer (B) CD Pantry Officer (A)
& A
A B B A
PD B
Night
Pantry
Up
A
CD
Cadet (A) B &
PD
Fan Room
Down Up
To Catwalk
Dn
E Deck F Deck
Satellite E.P.I.R.B
Radar
Transponder
Lifebuoy with Self
Igniting Light &
Smoke Signal
Fire Axe
Fireproof Clothing
Self-Contained Type
Compressed Air
Down Up Breathing Apparatus
Down
Cargo Office
A Safety Lamp For Three Hours
(Portable, Electric Type)
T Non Conductive Boots,
Up T M J B B.G.H
Gloves and Rigid Helmet
A PD
Fireman's
FE Outfit
Navigation Wheelhouse
T
Locker Safety
B
Down Dn Up SE Equipment
B B A A
Emergency Exit
Navigation Bridge Deck G-Deck
T SOLAS Training Manual
J Method of Donning
Life Jacket
M Muster List
Emergency Escape
Breathing Device
Life Jacket
Boiler
Vent Lift
Hood Space A
Elevator
Room UP
A
A A
A
Lift
DN
Space
UP
DN
Vent Vent
A
Store
GT LO
Settling
Tank
GT LO
Storage
Tank
GE LO
Settling Generator
Tank Main Lubricating Main Lubricating Engine
Oil Settling Oil Storage Diesel Oil
GE LO
Storage Tank Tank Service
Tank Tank
A A A
Boiler Water UP Emergency Escape
F.W. Analyser Breathing Device
Distilled
Water Tank
Tank (P&S)
(P&S)
Inert Gas Generator Cooling Unit Inert Gas Generator Air Dryer
Vent Vent Vent UP UP
UP
UP
Workshop
A Diesel Oil
Storage
Steering Gear Room Electrical Lift Tank (S)
Space
Workshop
and Store
Low Sulphur
Tank (S)
3rd Deck
Key
A
'A' Class Fire Door
Emergency Exit
Heavy Fuel Oil Cofferdam
Overflow Tank
Emergency Escape
Breathing Device
Cofferdam
Space for Piping
Vent
UP
Boiler
DN
Drain Tank
UP
UP
DN
UP
DN UP
DN UP
A
A
UP Main LO
A Sump Tank
DN UP
UP
UP
DN UP
Lift
Lift Space
Space Scoop Inlet
UP
UP UP
Vent
Vent
A
A
DN
Purifier Room
Key
Dn
Emergency Exit
No.2 Cargo
SWBD Room
Fire Axe
Paint (Low)
General Deck
Store Store Store
Fireproof Clothing
Vent Vent
Air Condition Room A Air Compressor with
Charging Manifold
Port Boiler
Self-Contained Type
Economiser
Compressed Air
Breathing Apparatus
A
No.2 Cargo
Safety Lamp For Three Hours
Port Boiler
Forced Draught Fan SWBD Room (Portable, Electric Type)
(High)
Non Conductive Boots,
B.G.H
Gloves and Rigid Helmet
Protective
Standby Forced
Draught Fan
Engine Room
Hatch
Up Dn Up
J PE Equipment
Boiler Vent A
A
Hood Room
M Safety
Dn
Lift SE Equipment
A A A
P.T 'A' Class Fire Door
B A
Change Rm B
C.G.L 'B' Class Fire Door
A No.1 Cargo
Starboard Boiler Incinerator
Forced Draught Fan Change Rm A SWBD Room
(High) Emergency Escape
C.D Breathing Device
&
A P.D
Dry Rm Locker. J Method of Donning
Starboard Boiler
Up
Life Jacket
Economiser
Vent Vent
B A M Muster List
Incinerator Room A
High Expansion Foam/CO2 Room
Ships
Laundry Fire
Control No.1 Cargo
Station SWBD Room
(Low)
X16 PE X3 SE B.G.H X2
An emergency trunking is fitted at the aft end of the engine room to allow
personnel to escape in the event of a life threatening situation. The emergency
trunking leads to the steering gear room, from where a stairway leads to the
aft mooring deck.
AFT MOORING DECK
2nd Deck
The routes to escape from the various deck levels are as follows:
1. Proceed aft to the port side door, which opens on to the aft
mooring deck. This door is normally open when the engine
room is manned and is always closed during UMS conditions. STEERING GEAR ROOM ENGINE ROOM
There are Emergency Escape Breathing Devices (EEBD) situated on all levels Aft Peak Tank
of the engine room, which can be used to protect personnel during the escape
from the engine room. Emergency Trunking
3rd Deck Level, 4th Deck Level and Engine Room Floor Level
• Proceed aft to the ‘A’ class fire door leading into the emergency
trunking and climb the vertical ladder to the steering gear room
level. Enter the steering gear room and proceed up the stairway 4th Deck
to the aft mooring deck. Key
Floor
N.O. A
To Engine C Foam Liquid Tank
PS PI
S (6000L)
Room Alarm
To Local Panels
N.C.
D Deck
Proportioner
60 60
N.C.
B Deck M N.C.
Key
S S S S S S S S S S
Foam N.C. BF105
A Deck J I H G F E D C B A
Sea Water Incinerator
Incinerator Incinerator Inert Gas Diesel Generator Purifier Purifiers Diesel Boiler Vent Engine
Room Main Boilers
Top Room Generator Room Engine Top Room Top Generator Room Hood Room Room
Local To LSC
Electrical Signal Panel Alarms
To Fire Main System
J I H E D A B C G F
Upper Deck
LSC Light Signal Column 60 18
60
60m3/min Foam Boiler
Generator Hood
60 60 60 18
Nozzle
60 18 No.1 HV No.1 No.2 HV No.2 No.1 LV No.2 LV
LSC Engine Switch Main Switch Main Switch Switch Nitrogen
BF09
No.1 No.2 Control Board Trfmr Board Trfmr Board Board Generator
Main Boiler Main Boiler Room Room Room Room Room Room Room Room 2nd Deck
Local To
Panel Alarms
From
Main Control 60 60 60 60 18 18 18 18 60 60 18 60
Cabinet
60 60 60 60 60 60 LSC Inert
Boiler Gas Generator
Engine Room LSC Engine Room Oil Chemical Mechanical Emergency Fire Pump
Diesel Generator Water Test Room
(Starboard) (Port) Store Store Workshop In Bow Thruster Room
Room Room 3rd Deck
(650/72m3/h Power
LSC x 90/115mth) Supply
To Local To
Steering Gear Fire Panel Local To
Smoke Detectors Alarms Purifier Room
Room Alarm Panel Alarms
Flame Detectors Main And Emergency
Panel and Alarm Pushbuttons 60 60 60
Power Supply
4th Deck 440V & 220V
BF07
Local To BF08
Panel Alarms
• Purifier room • The foam discharge alarm will sound in the engine room
WARNING
• Incinerator room • The ventilation fans will stop After the fire has been extinguished and the protected space has cooled
• The emergency fire pump will start down, the protected space must be thoroughly ventilated before any
• Boiler hood room
personnel enter.
• Inert gas generator room • The motorised sea water valve will open
• The foam outlet valve will open (Note: The TEST mode key and switches are used to test the system without
releasing any foam)
Local flooding is provided, via foam nozzles, for the following areas using the • The foam liquid pump will start
main control cabinet in the fire control station and local operating panels:
• The discharge valve to the diesel generator room will open
• Diesel generator room
• Purifier room A time delay will postpone production of the high expansion foam for 120
• Incinerator room seconds and only spray sea water into the diesel generator room.
N.O. A
To Engine C Foam Liquid Tank
PS PI
S (6000L)
Room Alarm
To Local Panels
N.C.
D Deck
Proportioner
60 60
N.C.
B Deck M N.C.
Key
S S S S S S S S S S
Foam N.C. BF105
A Deck J I H G F E D C B A
Sea Water Incinerator
Incinerator Incinerator Inert Gas Diesel Generator Purifier Purifiers Diesel Boiler Vent Engine
Room Main Boilers
Top Room Generator Room Engine Top Room Top Generator Room Hood Room Room
Local To LSC
Electrical Signal Panel Alarms
To Fire Main System
J I H E D A B C G F
Upper Deck
LSC Light Signal Column 60 18
60
60m3/min Foam Boiler
Generator Hood
60 60 60 18
Nozzle
60 18 No.1 HV No.1 No.2 HV No.2 No.1 LV No.2 LV
LSC Engine Switch Main Switch Main Switch Switch Nitrogen
BF09
No.1 No.2 Control Board Trfmr Board Trfmr Board Board Generator
Main Boiler Main Boiler Room Room Room Room Room Room Room Room 2nd Deck
Local To
Panel Alarms
From
Main Control 60 60 60 60 18 18 18 18 60 60 18 60
Cabinet
60 60 60 60 60 60 LSC Inert
Boiler Gas Generator
Engine Room LSC Engine Room Oil Chemical Mechanical Emergency Fire Pump
Diesel Generator Water Test Room
(Starboard) (Port) Store Store Workshop In Bow Thruster Room
Room Room 3rd Deck
(650/72m3/h Power
LSC x 90/115mth) Supply
To Local To
Steering Gear Fire Panel Local To
Smoke Detectors Alarms Purifier Room
Room Alarm Panel Alarms
Flame Detectors Main And Emergency
Panel and Alarm Pushbuttons 60 60 60
Power Supply
4th Deck 440V & 220V
BF07
Local To BF08
Panel Alarms
A time delay will postpone production of the high expansion foam for 120 The system is now operating and discharging foam into the diesel generator Procedure for Cleaning the System After Use
seconds and only spray sea water into the diesel generator room. room. When the fire has been extinguished, stop the pumps and close all the
valves.
When the fire has been extinguished, the system is manually shutdown by
a) Close valves A and B to prevent water entering the foam
WARNING tank.
pressing the OFF pushbutton.
After the fire has been extinguished and the protected space has cooled
down, the protected space must be thoroughly ventilated before any b) Open valve C from the domestic fresh water system.
Operation of the Foam System from the Main Control Cabinet
personnel enter.
in the Fire Control Station c) Supply fresh water for flushing and run the foam liquid pump
for a short time to flush the foam lines.
The system is divided into local fire fighting zones as follows: Procedure for Operation using the Local Operating Panels
• Zone 1 - main boilers There are local operating panels outside the following spaces: d) Stop the foam liquid pump.
• Zone 2 - inert gas generator top • Diesel generator room
e) Continue to run fresh water until it is determined that all foam
• Zone 3 - diesel generator top • Purifier room
has been flushed from the pipelines.
• Zone 4 - lubricating oil purifiers top • Incinerator room
The vessel is fitted with equipment which protects personnel during fire Equipment No. of sets Equipment comprises of a respiratory mask and small air cylinder which
fighting operations. The equipment available and their locations are displayed supplies 10 minutes of air to allow escape to fresh air.
First aid 1
on the ship's safety plan and should be familiar to all the ship's personnel.
There are EEBDs located in the following locations:
Locker - C Deck, Port Side, Access from Pumpman’s Cabin • Bridge - starboard side cupboard
The information regarding locations of equipment available is listed below:
Equipment No. of sets
• G deck - cargo control room, at starboard aft bulkhead
Self-contained breathing apparatus 1
Fire Control Station - Upper Deck, Starboard Side Lifeline with hook 1 • D deck - starboard alleyway area
Equipment No. of sets Safety lamp 1 • Upper deck - fire control station
Self-contained breathing apparatus 2 Fireman’s axe 1
Helmet 1 • Engine room 2nd deck - engine control room (2 sets)
Spare cylinders 3
Lifeline with hook 2 Boots and gloves 1 • Engine room 3rd deck - workshop, at inboard bulkhead
Safety lamp 2 Fireman’s suit 1
• Engine room 3rd deck - aft of port turbine generator
Fireman’s axe 2 Spare cylinders 2
Helmet 2 • Engine room 4th deck - starboard side, aft of auxiliary
Boots and gloves 2 circulating pump
Locker - G Deck, Starboard Side of Central Control Office
Fireman’s suit 2
Air compressor for breathing apparatus 1 Equipment No. of sets
Oxygen resuscitation equipment and antidotes 1 Self-contained breathing apparatus 1
Stretcher 1 Lifeline with hook 1
Protective equipment comprising: 16 Safety lamp 1
protective cloth Fireman’s axe 1
long apron Helmet 1
gloves, footwear and goggles Boots and gloves 1
Safety equipment comprising: 3 Fireman’s suit 1
boots Spare cylinders 3
gloves
eye protection
Navigating Bridge Deck - Wheelhouse, Starboard Aft
Spare cylinders 3
Equipment No. of sets
(Note: The breathing apparatus air compressor must be inspected at least Safety equipment comprising: 1
once a month by a responsible officer and the inspection recorded in boots
the ship’s log. The compressor must also be inspected and tested by an gloves
expert at least once a year.) eye protection
Escape equipment comprising: 1
respiratory mask
Locker - B Deck, Port Side, Forward of Hospital goggles
Equipment No. of sets eye protection
Self-contained breathing apparatus 1 Additional breathing apparatus sets 1
Lifeline with hook 1 Spare cylinders 3
Safety lamp 1
Fireman’s axe 1
Helmet 1
Boots and gloves 1
Fireman’s suit 1
Spare cylinders 2
WS10 WS01
WS15
WS06 WS07
No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
Engine Room
From Water
Spray Pumps
BA53V
Lifeboat B55V
WS27 BA52V BA51V
WS09
PI PI
WS20
WS23 WS07 Water Spray To Main
Pumps Condenser
WS21 (750m3 x 110mth ) Back Flushing
Paint General Deck
From No.4 Cargo Tank No.3 Cargo Tank No.2 Cargo Tank No.1 Cargo Tank
Store Store Store Engine Room PI PI
BA49V
Engine Casing Accommodation BA50V To Fire, Bilge and
GS Pumps (Machinery 2.6.1a)
WS10 WS03
WS18 WS17 WS16 WS13 WS12 WS11 WS04 WS02 M Sea
Chest
High Expansion WS15 WS14 WS05 WS01
(High)
Foam/ CO2 Room WS19 S101V
Fuel Gas Sea M
Master Valve
Chest
WS06 (Low)
S105V To Evaporator To Engine Room
CG875
WS08 SW Supply SW Cooling
WS26 Pumps Pumps
Lifeboat
To
No.1,2 & 3
Ballast Pumps
To To
Fire Main Engine Room
Pressure Pump Bilge Pumps
The water spray pumps supply sea water to the spray nozzles at the following c) Set up the valves as shown in the table below, in this case
locations: using No.1 pump:
• The cargo manifolds water curtain spray system
Position Description Valve
• Accommodation exterior bulkheads
Open Dedicated supply valve to the water spray system BA-3V
• Cargo tank domes
Open Sea water main suction valve BA49V
• Cargo machinery room exterior bulkheads
Open No.1 pump discharge valve BA51V
• Boilers’ fuel gas supply valve on the starboard aft main deck
• Lifeboat stations d) Start the pump from the DCS screen T30-447-01 and supply
water to the water spray system. These pumps must be selected
The water spray pumps, fire pump and the bilge, fire and general service as REMOTE at their local selector switches in order to allow
pumps are located in the engine room and all take suction from the main sea them to be started from the DCS screen.
water crossover pipe. Either the high or low sea chest must be open to this
suction main at all times. The water spray system can also be supplied by the The water spray system is now in use and delivering water to all the spray
fire pump and the bilge, fire and general service pumps via cross-connecting nozzles on deck.
valve B54V.
(Main) (Spare)
Fire Control Station
Remote Release Remote Release
Station for Station for
Monitors Monitors
(Starboard Side) (Port Side)
No.4 Dry Powder Tank Unit Emergency No.2 Dry Powder Tank Unit Emergency
Operating (2000 Litres) Operating
(2000 Litres)
Main Spare Handles Handles
Valve Valve
GS Air GS Air
Connection Connection
Cargo Control Room 9 Nitrogen Cylinders Main Discharge Valve 9 Nitrogen Cylinders Main Discharge Valve
Remote Release Remote Release Upper Deck Passageway (Port Side)
Station for Station for
No.8 No.10 No.12 No.18 No.19 Release Station Release Station No.1 No.2 No.4 No.6 No.17
Monitors Monitors
Hose Station Hose Station Hose Station Hose Station Hose Station for Monitors for Monitors Hose Station Hose Station Hose Station Hose Station Hose Station
(Starboard Side) (Port Side)
Starboard Side
(Main) (Spare)
Main Spare
Valve Valve
No.3 Dry Powder Tank Unit Emergency No.1 Dry Powder Tank Unit Emergency
(2000 Litres) Operating (2000 Litres) Operating
Handles Handles
Key
CO2
Nitrogen
9 Nitrogen Cylinders Main Discharge Valve 9 Nitrogen Cylinders Main Discharge Valve
Introduction Procedure for Operating the Dry Powder System from a Hose 2
or Manifold Monitor Cabinet
The dry powder fire extinguishing system consists of four identical systems,
situated on the port and starboard side of the upper deck passageways, The monitor’s dry powder supply valve should be open and the monitor 6
forward and aft, each supplying one monitor and five hand hose cabinets. The should be secured in a position to direct the dry powder towards the manifold
monitors are situated at the cargo hose manifolds and the hand hose cabinets couplings, as this is the most likely area for a gas leak and subsequent fire.
are strategically situated to cover the cargo deck area.
a) Pull out the full length of hose.
Each system consists of a tank containing sodium bicarbonate and a rack
of 9 cylinders containing N2 gas under pressure. The system is operated by b) Open the door containing the 2.68kg CO2 gas cylinders. 7
releasing the N2 gas into the tank which forces the mixture of powder and N2
gas through the pipelines to the monitor and hose cabinets. c) Open the discharge valve counter clockwise on the 2.68kg CO2 Key
gas cylinders. 1 - Cabinet
The discharge valves on the N2 gas cylinders are designed to be opened
manually or by the CO2 gas pressure from the remote release control cabinet d) Pull the ball valve downward on the CO2 gas discharge 2 - CO2 Cylinder
bottles. Each cabinet contains two 2.68 litre CO2 gas cylinders pressurised to pipeline. 3 - Screw Down Valve
55 bar with one as a spare.
4 - Slow Leak Valve
e) Aim the hand hose nozzle at the fire and open the nozzle valve.
CO2 gas is released to the N2 gas cylinders discharge valve and the selection Be prepared for a recoil reaction from the hose when dry 5 - Pressure Gauge 0-150 bar
valve on the dry powder supply pipe to the hose cabinet or monitor. The dry powder reaches the nozzle. 6 - Ball Valve
powder storage tank is pressurised by the N2 gas and the tank pressure is led,
via a filter, to the operating cylinder for the main valve on the discharge line. (Note: In the event that the system fails to discharge the dry powder, open the 7 - Pipe Fitting
spare CO2 gas cylinder and discharge valve. Allow up to 4 minutes for
The remote release control cabinets are at the following locations: the dry powder to issue from the nozzle.)
• Cargo control room
• Fire control station
• Port and starboard manifolds - 2 sets each, one as spare
• Port and starboard hand hose cabinets - 10 sets each side
(Main) (Spare)
Fire Control Station
Remote Release Remote Release
Station for Station for
Monitors Monitors
(Starboard Side) (Port Side)
No.4 Dry Powder Tank Unit Emergency No.2 Dry Powder Tank Unit Emergency
Operating (2000 Litres) Operating
(2000 Litres)
Main Spare Handles Handles
Valve Valve
GS Air GS Air
Connection Connection
Cargo Control Room 9 Nitrogen Cylinders Main Discharge Valve 9 Nitrogen Cylinders Main Discharge Valve
Remote Release Remote Release Upper Deck Passageway (Port Side)
Station for Station for
No.8 No.10 No.12 No.18 No.19 Release Station Release Station No.1 No.2 No.4 No.6 No.17
Monitors Monitors
Hose Station Hose Station Hose Station Hose Station Hose Station for Monitors for Monitors Hose Station Hose Station Hose Station Hose Station Hose Station
(Starboard Side) (Port Side)
Starboard Side
(Main) (Spare)
Main Spare
Valve Valve
No.3 Dry Powder Tank Unit Emergency No.1 Dry Powder Tank Unit Emergency
(2000 Litres) Operating (2000 Litres) Operating
Handles Handles
Key
CO2
Nitrogen
9 Nitrogen Cylinders Main Discharge Valve 9 Nitrogen Cylinders Main Discharge Valve
a) Proceed to one of the upper deck passageways on the port or The galley ventilation ducting is protected by a dry powder system which
starboard side. consists of a 7kg dry powder cylinder connected to a 5kg CO2 cylinder.
b) At the dry powder unit, at the aft or forward end of the upper System is located in a cabinet in the starboard bulkhead and is activated by
deck passageway, remove an emergency operating handle from opening the CO2 cylinder outlet valve, followed by the dry powder cylinder
the rack and insert it into an N2 gas cylinder discharge valve outlet valve.
operating lever.
The dry powder is injected into the ducting in the deckhead.
c) Push the handle firmly in the direction of the tank to release
the N2 gas in the cylinder. Repeat the operation on the other 8 The deep fat fryer is protected by an R102 refrigerant type wet chemical
cylinders. contained in a high pressure cylinder. It is located near the dry powder system
and is activated by pulling a handle at the bulkhead. The chemical is directed
d) Open the monitor or hose station supply valves as required, by a nozzle on to the deep fat fryer and the effect is to rapidly cool the hot fat
depending on the location of the fire. fire.
The system should be cleaned immediately after use by blowing through the
pipelines with the N2 gas remaining in the cylinders or air from the GS air
system.
SpecVision SpecVision
SpecVision SpecVision
24DC from Engine Room DC24V D1-BD 24DC from Engine Room DC24V D1-BD
1F 1F
OMD Monitor RMU 1 Abnormal OMD Monitor RMU 1 Abnormal
MCPM MCPM
P MACH P MACH
To DCS To DCS
FCS FCS
Boiler FO Boiler FO Inert Gas Main/Aux. No. 1and 2 Solenoid Hydraulic Steering Aft Deck No.2
Transfer Pump Heaters Generator LO Pumps LO Purifiers Valve Power Gear Hydraulic Boiler
Fuel Oil Supply Pumps Stand Pack No.1 Pump Machinery Burners
Pump For Ballast For Cargo (Steering (Steering
LO Purifiers HFO/GO Incinerator No.1 and No.2 Diesel Inert Gas Hydraulic Gear Steering Gear No.1
Transfer Pumps Room Stern Tube Generator Engine Generator Firing Power Room) Gear Room) Boiler
LO Pumps Room Platform Pack No.2 Pump Burners
For Ballast (Steering
Gear
Room)
Introduction Oil mist is continuously drawn through each detector sensing head and the level
System LED
of oil mist density is monitored by the infrared optical sensors. This process is
The oil mist detection system consists of two remote monitoring units (RMU), continuous at each sensor. The signals are fed to the microprocessors, which The system LED indicates that the condition of all the mist sensors are normal
situated in the engine control room, with air sensor units strategically placed are located in the RMUs. and stable. The LED will be extinguished if any of the sensors are contaminated
at potentially hazardous areas around the vessel which include machinery and or there is a communication failure between a detector and the RMU.
pipes containing fuels or oils under pressure. The sensors are mounted so that The detector lenses are cleaned at regular intervals as part of the engine room
they are least affected by the often turbulent atmosphere in various operative routine maintenance schedules. Fan LED
areas under normal working conditions, i.e. air conditioning and ventilation.
The fan LED will be extinguished if there is a failure of a fan at any of the
Remote Monitoring Unit detectors. The failed detector will have its red channel LED lit on the RMU to
The sensors are positioned above the following:
Opacity display: Range 0 - 2.2mg/litre indicate which detector fan has failed.
• Boiler fuel oil transfer pump
Alarm setting: 1.2mg/litre, 2.5%LEL
• Boiler fuel oil heater Alarm Acknowledge Pushbutton
• Heavy fuel oil and gas oil transfer pump Although oil mist samples are measured in milligrams/litre, the reading per This pushbutton is used for acknowledging the alarm. When pressed the alarm
• Inert gas generator fuel oil pump channel is presented as percentage of 1.2mg litre of oil mist, which is 2.5% of is also muted.
the Low Explosive Limit (LEL), or it may be set lower.
• Incinerator room
Alarm Reset Pushbutton
• Main turbine main and auxiliary lubricating oil pumps The RMU front panel is fitted with the following:
This pushbutton is used to change the alarm set point. The adjustment is
• No.1 and 2 stern tube lubricating oil pump • Bar LED indicator with green and red LEDs
carried out by pressing both the ACKNOWLEDGE pushbutton and the
• Lubricating oil purifier supply pumps • 12 channel LEDs RESET pushbutton simultaneously for more than 3 seconds.
• Lubricating oil purifiers • Power LED
• Diesel generator room • System LED Operational Functions
• Solenoid valve cabinet for the ballast valves • Fan LED During normal running the RMU displays the following:
• Inert gas generator firing platform • Alarm acknowledge pushbutton • Power On indicator
• Hydraulic power pack for the cargo valves • Alarm reset pushbutton • Green illuminated indicator beneath the channels numbers
being monitored
• Hydraulic power pack for the ballast valves
Bar LED Indicator • Digital display of the channel with the highest level of oil mist
• Port and starboard steering gear pumps density indicated as a percentage of the preset alarm level
This contains green coloured LED indicators for normal mist concentrations
• Port and starboard boiler burners
and red coloured LED indicators for warning conditions. The red LEDs will These functions remain constant until either:
• Aft deck hydraulic machinery illuminate when any detector senses a mist content above 1.2mg/litre. The
indicator will have a minimum level of 1 bar when the mist content clears. • The alarm sequence is actuated
• A fault develops
Channel LEDs • Operator instigated functions are actuated
The channel LEDs are green during normal operation and are numbered
to indicate their location in the engine room. The LEDs are sequentially
illuminated every second.