Professional Documents
Culture Documents
كشكول محترف إدارة المشاريع
كشكول محترف إدارة المشاريع
PMP P
اﻹﺻﺪار v6
2020
PMP P
أﺣﻤﺪ ﺑﻦ ﺳﻠﯿﻤﺎن اﳌﯿﻤﺎن
ﮐﺸﮑﻮل
PMP ﻣﺤﺘﺮف إدارة اﳌﺸﺎرﯾﻊ
Project Manager Professional
رﺳﺎﻟﺔ اﻟﮑﺎﺗﺐ
أﺷﺮف اﻟﺤﻤﺪ ﻟﻠﻪ رب اﻟﻌﺎﳌﯿﻦ ،واﻟﻌﺎﻗﺒﺔ ﻟﻠﻤﺘﻘﯿﻦ ،واﻟﺼﻼة واﻟﺴﻼم
آﻟﻪ وﺻﺤﺒﻪ أﺟﻤﻌﯿﻦ ،أﻣﺎ ﺑﻌﺪ؛ اﻷﻧﺒﯿﺎء واﳌﺮﺳﻠﯿﻦ ،ﻧﺒﯿﻨﺎ ﻣﺤﻤﺪ و
...
ﺣﻘﯿﻘﺔ اﻷﻣﺮ ﻟﻢ أﻗﺪم ﺷﯿﺌًﺎ ﺟــﺪﯾﺪًا ﺳﻮى أﻧــﻲ ﻟﺨﺼــﺖ ﻣــﺎدة ﻓﺈﻧﻲ
اﻻﺧﺘﺒﺎر ﻣﻦ ﺧﻼل ﻗﺮاءﺗـــﻲ ﻟﺒﻌﺾ اﻟﮑـــﺘﺐ وﺣــﻀﻮري ﻟــﺒﻌﺾ اﻟــﺪورات
واﳌﺤﺎﺿﺮات ﻟﺸﺮح ﻣﻨﻬﺞ »ﻣﺤﺘﺮف إدارة اﳌﺸﺎرﯾﻊ .« PMPوﻻ ﯾﺨﻔـﯽ
ﻣﻘﺮّر اﻟﺸﻬﺎدة ﻣﺪى دَﺳﺎﻣﺘﻬﺎ وﺗﺸﺎﺑﮑﻬﺎ وﺗﺮاﺑﻂ ﺟﻤﯿــﻊ ﮐﻞﱢ ﻣَﻦ اﻃﱠﻠﻊ
ﻓﺼﻮﻟﻬﺎ ،ﻓﮑﺎن هﺬا اﻟﮑﺸﮑﻮل اﻟﺬي ﺟﻤﻌﺘﻪ ﻟﻲ وﻟـﺰﻣﻼﺋـﻲ ﻣﺮﺟﻌًﺎ ﻧﺴﺘﺬﮐﺮُ
اﻷﺳﺎﺑﯿﻊ اﻷﺧﯿﺮة ﻗﺒﻞ ﻣﻮﻋﺪ اﺧﺘﺒﺎرﻧﺎ . ﻣﻦ ﺧﻼﻟﻪ اﳌﻨﻬﺞ
ﻟﮑﻞ ﻣﻦ أراد اﻻﺳﺘﻔـــﺎدة ﻣﻦ هﺬا اﻟﮑﺸﮑﻮل ﻗﺪ ﻗﻤـﺖ ﺑﮑﺘﺎﺑﺘــﻪ ﺑﺄﺳﻠــﻮب ﺗﻮاﺻﻞ ﻣﻌﻲ ﻋﺒﺮ
Linkedin
ﮐﻞ ﻣﻦ أراد ﻣﺮاﺟﻌـــﺔ اﳌﻨﻬﺞ واﺳﺘﺬﮐـــﺎرﻩ ﺑﻘﺮاءة أﻗــﻞ ﻋﺪد ﯾﺴﻬﻞ
ﮐﻠﻤﺎت ﻣﻤﮑﻨﺔ ،ﻣﺸﯿﺮًا إﻟﯽ أهﻢ اﻟﻌﺒﺎرات )اﳌﻔﺎﺗﯿﺢ( ﺑﺎﻟﻠﻮن اﻷﺣﻤﺮ .
ﺗﻮاﺻﻞ ﻣﻌﻲ ﻋﺒﺮ
ﻓﯿﺎ ﻗﺎرﺋﻲ اﻟﮑﺮﯾﻢ إنْ ﻟﻢ ﺗﻘﺮأ ﻣﻨﻬﺞ اﺧﺘﺒﺎر »ﻣﺤﺘﺮف إدارة اﳌﺸﺎرﯾﻊ « PMP Twitter
ﻣﻦ ﻗﺒﻞُ ،أو ﻟﻢ ﺗﺤﻀــﺮ إﺣﺪى اﻟـﺪورات اﻟﺘﻲ ﺗﺸﺮﺣُﻬــﺎ ،ﻓﻠﻦ ﯾﻔﯿـــﺪك هﺬا
ﻟﻠﻤﺮاﺟﻌــﺔ
اﻟﮑﺸﮑﻮل؛ ﻓﺈﻧﻲ ﻟﻢ أﺗﻄﺮق ﻓﯿﻪ ﻟﺸﺮح اﳌﻨﻬﺞ ،ﻓﻬﺬا اﻟﮑﺸﮑﻮل .
اﳌﺨﺘﺒﺮ واﻟﺮﺟﻮع ﻟﻪ ﻟﮑﺒﺮ ﺣﺠﻤﻪ . ﻓﻘﻂ ،إذ ﺗﺼﻌﺐ ﻣﺮاﺟﻌﺔ اﻟﮑﺘﺎب
وﻟﮑﻤﺎ -زﻣﯿﻼيَ اﻟﻔﺎﺿﻼن -ﻋﻤﺮو اﻟﺼﻌﺮ وﺧﺎﻟﺪ اﻟﺴﻘﺎ؛ ﻓﻠﻮﻻ اﻟﻠﻪ ﺛﻢ إﻋﺎﻧﺘﮑﻤﺎ
هﺬﻩ اﻟﺸﻬﺎدة ،ﻓﺄﺷﮑﺮ وأﺑﺎرك ﻟﮑﻤﺎ وﺗﺸﺠﯿﻌﻲ ﳌﺎ ﺣﺼﻠﺖ
. وﺣﺜﮑﻤﺎ ﻟﻲ
ﺷﻬـــــﺎدة »ﻣﺤﺘﺮف إدارة اﳌﺸﺎرﯾﻊ PMP ﺗﺤﻘﯿﻖ هﺪﻓﻨﺎ ﺑﺎﻟﺤﺼﻮل
»
2020 / 8 / 8
اﻟﻔﻬﺮس
4 3-2-1 اﻟﻔﺼﻞ
6 4 اﻟﻔﺼﻞ
إدارة اﻟﺘﮑﺎﻣﻞ
Integration Management
13 5 اﻟﻔﺼﻞ
إدارة اﻟﻨﻄﺎق
Scope Management
19 6 اﻟﻔﺼﻞ
إدارة اﻟﺠﺪوﻟﺔ
Schedule Management
25 7 اﻟﻔﺼﻞ
إدارة اﻟﺘﮑﺎﻟﯿﻒ
Cost Management
29 8 اﻟﻔﺼﻞ
إدارة اﻟﺠﻮدة
Quality Management
33 9 اﻟﻔﺼﻞ
إدارة اﳌﻮارد
Resource Management
39 10 اﻟﻔﺼﻞ
إدارة اﻟﺘﻮاﺻﻞ
Communication Management
43 11 اﻟﻔﺼﻞ
إدارة اﳌﺨﺎﻃﺮ
Risk Management
50 12 اﻟﻔﺼﻞ
إدارة اﻟﺘﻮرﯾﺪ
procurement Management
55 13 اﻟﻔﺼﻞ
إدارة اﳌﻌﻨﯿﯿﻦ
Stakeholder Management
اﻟﻔﺼﻮل
1,2,3
اﻟﻔﺼﻮل
اﻟﺜﻼث اﻷوﻟﯽ
First three chapters
PMBOK 6 th Ed.
(1-68)
5
General Definitions
PMP
Portfolio
Project and program, sub portfolios and operation.
Achieve strategic objective.
Program
A group of related projects to obtain benefits.
Does not contain operation.
Project
Unique, temporary, drive change, enable Business Value.
Operation
Ongoing productions, Repeated works.
إدارة
اﻟﺘﮑﺎﻣﻞ
Integration Management
PMBOK 6 th Ed.
(69-128)
7
Initiating Process
INPUT
Business document
Business case (feasibility study).
Benefit management plan.
Project Managers can’t modify, but only recommend to sponsor.
Includes (assumptions, constraints, risks, roles, responsibility, milestones, Stakeholders).
INPUT
Assumption log
Low level detailed assumptions, constraints.
High level of assumptions, constraints are mentioned in business case then in project charter.
OUTPUT
Project charter ﻣﯿﺜﺎق اﳌﺸﺮوع
Project purpose.
Measurable project objective.
High level requirements.
High level descreption Key deliverables.
Overall project risk.
Summary milestone schedule.
Preapproved financial resources.
Key stakeholder list.
Project exit criteria to close.
8
Planning Process
Executing Process
OUTPUT
Lesson learned register ﺳﺠﻞ اﻟﺪروس اﳌﺴﺘﻔﺎدة
All team is working on it.
At the end of a project or phase , the information is transferred to OPA called lessons learned repository.
10
Monitor & Control Process
Reviewing & reporting the overall progress t meet the performance objective.
Allow stakeholders to understand the current state of the project.
Monitor: Collecting and measuring evaluating the performance.
Control: Determine corrective or preventive actions, re-planning & follow up.
Preventive action: Ensure the future performance of project work is aligned with project management plan - Part of Change request.
Corrective action: Re-aligns the performance of project work with project management plan - Part of Change request.
Defect repair: Modifies nonconforming product component stakeholder refused item - Part of Change request.
.
11
Monitor & Control Process
INPUT INPUT
Change management plan Configuration management plan
Direction for managing the Change control process. Describe the configuration items.
How to make Change request.
Responsibilities of the CCB.
Control Scope ﻣﻦ ﻋﻤﻠﯿﺔAccepted deliverables ﻋﻤﻠﯿﺔ اﻹﻏﻼق هﻮ ﺗﺄﮐﺪك ﻣﻦ إﺳﺘﻼم أهﻢ اﳌﻬﺎم اﻟﺘﻲ ﻋﻠﯿﻚ ﻣﻌﺮﻓﺘﻬﺎ
Monitor & Control ﻣﺮﺣﻠﺔ ﮐﻤﺎ أﻧﻪ ﻋﻠﯿﻚ اﻟﺘﺄﮐﺪ ﻣﻦ إﻏﻼق ﺟﻤﯿﻊ اﻟﻌﻘﻮد ﻟﻠﻤﻘﺎوﻟﯿﻦ واﳌﻮردﯾﻦ
اﻟﺨﺎص ﺑﺎﻟﺸﺮﮐﺔOPA اﻟـ ﺳﺠﻠﻬﺎ وﺣﻔﻈﻬﺎ وﻋﻠﯿﻚ أﯾﻀًﺎ اﻟﺘﺄﮐﺪ ﻣﻦ ﺗﺪوﯾﻦ ﺟﻤﯿﻊ اﻟﺪروس اﳌﺴﺘﻔﺎدة
ﻓﺼﻞ
إدارة
اﻟﻨﻄﺎق
Scope Management
PMBOK 6 th Ed.
(129-172)
14
Planning Process
OUTPUT
Scope Management Plan
Process to prepare Project scope statement
Process that enables the creation of WBS
How Scope baseline will be approved
How formal acceptance deliverables will be obtained.
OUTPUT
Requirement Management Plan
How project requirements will be analyzed, documented, and managed.
15
Planning Process
Collect Requirements
INPUTS TOOLS & TECHNIQUES OUTPUTS
Planning Process
Define Scope
INPUTS TOOLS & TECHNIQUES OUTPUTS
OUTPUT
Project Scope Statement
Product scope description.
Acceptance criteria.
Deliverables (summary level, great details , major deliverables).
Exclusions.
Constraints.
Assumptions.
Planning Process
Create WBS
INPUTS TOOLS & TECHNIQUES OUTPUTS
Validate Scope
INPUTS TOOLS & TECHNIQUES OUTPUTS
Formalizing acceptance.
INPUT
Verified Deliverables
Checked in control quality process
OUTPUT
Accepted Deliverables
Deliverable that meet the acceptance criteria and formally signed off and approved by the customer or sponsor.
OUTPUT
Change Request
The completed deliverables have not been formally accepted.
هﺬﻩ اﳌﺮﺣﻠﺔ وﯾﻘــﻮمControl Quality اﻟﻨﺎﺗﺞ ﻣﻦ ﻋﻤﻠﯿﺔVerified deliverables هﺬﻩ اﻟﻌﻤﻠﯿﺔ اﳌﺪﺧﻞ ﺗﺴﺘﻠﻢ
ﻹﻋﺘﻤﺎدهــــــــــــــــﺎ وﻟﺘﺨﺮج ﺑﻌﺪ اﻟﺘﺄﮐﺪ ﻣﻨﻬﺎVerified deliverables اﳌﻤﻮل واﳌﻌﻨﯿﯿﻦ ﺑﺎﻟﺘﺄﮐﺪ ﻣﻦ ﺳﻼﻣﺔ وﺻﺤﺔ اﻟـ
. Closing ﻣﺮﺣﻠﺔ وﯾﻨﺘﻘﻞ ﮐﻤﺪﺧﻞAccepted deliverables ﮐـ
18
Control Scope
INPUTS TOOLS & TECHNIQUES OUTPUTS
Monitoring status of project scope, and managing changes to the scope baseline.
Benefit is to maintain scope baseline
Gold plating: Giving extra features for free.
Scope Creep: Uncontrolled expansion to product or project scope without adjustments to time cost and resources.
OUTPUT
Work Performance Information
Including Categories and analysis for all project measurements from work performance data.
ﻓﺼﻞ
إدارة
اﻟﺠﺪوﻟﺔ
Schedule Management
PMBOK 6 th Ed.
(173 -230)
20
Planning Process
Planning Process
Define Activities
INPUTS TOOLS & TECHNIQUES OUTPUTS
Sequence Activities
INPUTS TOOLS & TECHNIQUES OUTPUTS
Project Management Plan Precedence diagramming method Project schedule network diagram
Schedule management plan Dependency determination and integration Project documents updates
Scope baseline Leads and lags Activity attributes
Project documents PMIS Activity list
Activity attributes Assumption log
Activity list Milestone list
Assumption log
Milestone list
EEF
OPA
External
TOOLS & TECHNIQUES
leads and lags Relationship between project
Lead = Overlap (-). activities & non-project activities.
Lag = Delay (+) waiting time between activities. Outside the project team control
A A Internal
Estimating the number or work periods needed to complete individual activities with estimated resources
The amount of time each activity will take to complete.
Develop Schedule
INPUTS TOOLS & TECHNIQUES OUTPUTS
OUTPUT OUTPUT
Schedule Baseline Project Schedule
Approved version of schedule. Milestone Chart = for Senior Management (low detailed).
Changed through formal CCB. Bar Chart = for team (high detailed) (Gantt Chart).
Basis of comparison.
24
Monitor & Control Process
Control Schedule
INPUTS TOOLS & TECHNIQUES OUTPUTS
إدارة
اﻟﺘﮑﺎﻟﯿﻒ
Cost Management
PMBOK 6 th Ed.
(231 -270)
26
Planning Process
Planning Process
Estimate Cost
INPUTS TOOLS & TECHNIQUES OUTPUTS
Determine Budget
INPUTS TOOLS & TECHNIQUES OUTPUTS
Managment
Reserve
Cost Control
Baseline Accounts
OUTPUT Work Package
Cost Baseline Cost Estimates
Activity
Control Cost
INPUTS TOOLS & TECHNIQUES OUTPUTS
Earned Value (EV) The Value of all the Completed Work (Earned) to a point in time. SV = EV - PV
Actual Cost (AC) The Actual Cost of all the work completed at a point in time. + Ahead of Schedule
- behind Schedule
TOOLS & TECHNIQUES 0 On Schedule
Trend Analysis
EAC = AC + (BAC - EV) Cost Variance
If future work will be accomplished at the planned rate.
CV = EV – AC
EAC = BAC / CPI
+ Under Budget
If CPI is expected to be the same for the remainder or the project.
- Over budget
EAC = AC + [(BAC -EV) / (SPI * CPI)]
0 On budget
If both CPI & SPI influence the remaining work.
EAC = AC + Bottom-up ETC Schedule Performance Index
If initial plan is no longer valid, new estimation is required.
SPI = EV / PV
>1 Ahead of Schedule
TOOLS & TECHNIQUES
Estimate to completion (ETC) <1 behind Schedule
ETC = EAC – AC 1 On schedule
Cost Performance Index
TOOLS & TECHNIQUES
To Complete Performance Index (TCPI) CPI = EV / AC
TCPI = (BAC-EV) / (BAC-AC) >1 Under of budget
A measure of the cost performance that must be achieved with the remaining resources. <1 Over Budget
Expressed as the ratio of the cost to finish the outstanding work to the budget available. 1 On Budget
>1 Harder to complete (bad)
<1 Easier to complete (good)
TOOLS & TECHNIQUES
Variance At Completion (VAC) (>1)
(>1) ( أو أﮐﺒﺮ ﻣﻦ واﺣﺪ+) إذا ﮐﺎن اﻟﺮﻗﻢ ﻣﻮﺟﺐ
VAC = BAC - EAC واﻟﻌﮑـــــﺲ.ﺣﺎﻟﺔ ﺟﯿﺪة ﻓﺎﳌﺸﺮوع
+ under planned cost (good) . TCPI ﻗﺎﻧﻮن
- Over planned Cost (bad)
0 on planned cost
ﻓﺼﻞ
إدارة
اﻟﺠﻮدة
Quality Management
PMBOK 6 th Ed.
(271 -306)
30
Planning Process
OUTPUT
Quality Metrics.
How the control quality process will verify compliance.
Ex: CPI , Failure rate, N. of defects, customer satisfaction rate
31
Planning Process
Manage Quality
INPUTS TOOLS & TECHNIQUES OUTPUTS
Control Quality
INPUTS TOOLS & TECHNIQUES OUTPUTS
هﺬﻩ وﺗﻘــﻮمDirect & Manage Project Work اﻟﻨﺎﺗﺞ ﻣﻦ ﻋﻤﻠﯿﺔDeliverable هﺬﻩ اﻟﻌﻤﻠﯿﺔ اﳌﺪﺧﻞ ﺗﺴﺘﻠﻢ
ﻟﯿﺨﺮج ﺑﻌﺪ اﻟﺘﺄﮐﺪDeliverable أﻧﺖ ﮐﻤﺪﯾﺮ ﻣﺸﺮوع وﻓﺮﯾﻖ اﻟﻌﻤﻞ ﺑﺎﻟﺘﺄﮐﺪ ﻣﻦ ﺳﻼﻣﺔ وﺻﺤﺔ اﻟـControl Quality اﳌﺮﺣﻠﺔ
. ﻟﯿﻘﻮم اﳌﻌﻨﯿﯿﻦ ﺑﻤﻌﺎﯾﻨﺘﻬﺎ واﻟﺘﺄﮐﺪ ﻣﻨﻬﺎValidate Scope ﻣﺮﺣﻠﺔ وﯾﻨﺘﻘﻞ ﮐﻤﺪﺧﻞVerified deliverables ﻣﻨﻪ ﮐـ
ﻓﺼﻞ
إدارة
اﳌﻮارد
Resource Management
PMBOK 6 th Ed.
(307 -358)
34
Planning Process
OUTPUT
Team Charter
Operating as a guideline for the team.
Team value.
Communication guideline.
Decision making criteria and process.
Conflict resolution process.
Meeting guideline.
Team agreement.
35
Executing Process
OUTPUT
Resource requirement
Identify the types and quantities of resources required for each work package.
OUTPUT
Basis of estimate
Clear & complete understanding of how the resource estimate was derived.
OUTPUT
Resource Breakdown Structure (RBS)
Divide project as Categories.
Details are under each category to be used later with WBS.
36
Executing Process
Acquire Resource
INPUTS TOOLS & TECHNIQUES OUTPUTS
Obtaining team members, facilities, equipment, materials, suppliers, to complete project work
Guide the selection of resources and assign them to their activities.
Develop Team
INPUTS TOOLS & TECHNIQUES OUTPUTS
1
Team meets.
TOOLS & TECHNIQUES TOOLS & TECHNIQUES Learn their formal roles.
Communication technology Recognition and rewards
When team moral is low. Not open.
Ex, email, website, video conference.
Storming
TOOLS & TECHNIQUES
2
Individual and team assessments Team not collaborative
Give the PM insights/ideas of Strengths & weaknesses areas to assess the team. Begins to address the
project work.
TOOLS & TECHNIQUES
Influencing
Norming
Gathering information / maintaining mutual trust.
Begin to work together.
TOOLS & TECHNIQUES
Negotiation
Learn to trust.
3
Trust and harmony among the team members.
Performing
OUTPUT Team is interdependent.
Team Performance Assessments
Improvement in skills.
Reduce staff turnover.
Work smoothly.
Effectively. 4
Well-organized.
(Can decide if) extra training is required.
(Can decide if) change is needed to improve performance.
(Can decide if) new resources is more suitable for project.
38
Executing Process
Manage Team
INPUTS TOOLS & TECHNIQUES OUTPUTS
Control Resource
INPUTS TOOLS & TECHNIQUES OUTPUTS
Ensuring the physical resources assigned and allocated to the project are available as
planned at the right time and in the right place and are release when no longer needed.
ﻓﺼﻞ
10
إدارة
اﻟﺘﻮاﺻﻞ
Communication Management
PMBOK 6 th Ed.
(359-349)
40
Planning Process
Meetings
Pull
Large volume ﻓﺄﺣﯿﺎﻧــﺎ،ﺗﺄﮐﺪ ﻣﻦ ﻗﺮاءﺗﻚ ﻟﺴﺆال ﻋﺪد ﻗﻨﻮات اﻹﺗﺼﺎل ﺟﯿﺪا
Large audience ﺗﻌﻄﯿﻚ اﳌﺴﺄﻟﺔ ﻋﺪد اﳌﻌﻨﯿﯿﻦ وﻟﮑﻦ ﺑﺪون اﻷﺧﺬ ﺑﺎﻟﺤﺴﺒﺎن
Website ﻓﻔﻲ هﺬﻩ اﻟﺤﺎﻟﺔ،ﻣﺪﯾﺮ اﳌﺸﺮوع ﻓﻠﻢ ﯾﺘﻢ ﻋﺪﻩ ﻣﻦ اﳌﻌﻨﯿﯿﻦ
Dashboard ﻋﺪد اﳌﻌﻨﯿﯿــــﻦ ﺛﻢ إﺗﺒﺎع اﻟﻘــﺎﻧﻮن (1+) ﻋﻠﯿﻚ إﺿﺎﻓﺔ
Lesson learned / opa اﳌﺬﮐﻮر ﺑﺎﻷ
e-learning
41
Executing Process
Manage Communication
INPUTS TOOLS & TECHNIQUES OUTPUTS
INPUT INPUT
Work performance reports Change log
Distributing reports to stakeholders as defined in Communicate changes approved or rejected.
the communication management plan.
Monitor Communication
INPUTS TOOLS & TECHNIQUES OUTPUTS
Ensuring the information needs of the project and its stakeholder are met.
Key benefit : Optimal information flow.
General Definitions
Communication
Formal Reports, memo, letters, formal meeting
11
إدارة
اﳌﺨﺎﻃﺮ
Risk Management
PMBOK 6 th Ed.
(395-458)
44
Planning Process
OUTPUT
Risk management plan ﺧﻄﺔ إدارة اﳌﺨﺎﻃﺮ
Risk Strategy.
Methodology.
Roles & Responsibilities.
Funding.
Timing.
Risk Categories.
Stakeholder risk appetite.
Definitions of risk probability.
Reporting formats.
Tracking.
45
Planning Process
Identify Risk
INPUTS TOOLS & TECHNIQUES OUTPUTS
Accept Accept
Acknowledge Acknowledge
Active acceptance Active acceptance
contingency reserve contingency reserve
Passive acceptance Passive acceptance
Risk register (watch list) Risk register (watch list)
49
Executing Process
Monitor Risk
INPUTS TOOLS & TECHNIQUES OUTPUTS
CCB 4 ﺑﻌﺪ ﺗﺤﻠﯿﻞ اﻹﺣﺘﯿﺎﻃﻲ ﻓﻼ داع ﻟﺘﻘﺪﯾﻢ ﻃﻠﺐ ﺗﻐﯿﯿﺮ وﺑﺈﻣﮑﺎﻧﻚ ﺗﺨﻄﻲ اﻟﺨﻄﻮة رﻗﻢ ﺣﺎل وﺟﻮد ﻣﺒﻠﻎ ﮐﺎ *
ﻓﺼﻞ
12
إدارة
اﻟﺘﻮرﯾﺪ
Procurement Management
PMBOK 6 th Ed.
(459-502)
51
Planning Process
OUTPUT OUTPUT
Procurement management plan Procurement strategy
How procurement will be managed. Delivery methods.
Pre-qualified sellers. Contract payment types.
Constraints and assumptions. Procurement phases.
Time frame for key procurement activities.
Stakeholders roles regarding procurement.
OUTPUT
Currency. Bid document
Procurement metrics to be used to manage contracts. Request for information (RFI).
Request for quotation (RFQ).
OUTPUT
Request for proposal (RFP).
Procurement SOW
Detailed data which will be sent to contractor.
OUTPUT
Specifications. Source selection criteria
Required quality. Capability and capacity.
Contractor tasks. Product cost and life cycle cost.
Definition for Submission schedule. Technical & management experience.
Key staff qualification.
OUTPUT
Financial stability.
Make or Buy decision
Depends on make-or-buy analysis.
Conduct Procurement
INPUTS TOOLS & TECHNIQUES OUTPUTS
ﺣﺎل وﺟﻮد أي ﺧﻼﻓﺎت أو ﻣﻨﺎﻗﺸﺎت ﺑﻌﺪ ﺗﻮﻗﯿﻊ اﻟﻌﻘﺪ ﻓﺈﻧﻪ ﯾﺘﻢ اﻷﺧﺬ ﺑﺎﻷﺣﮑﺎم واﻟﺸﺮوط اﳌﺬﮐﻮرة ﺑﺎﻟﻌﻘﺪ اﳌﺒﺮم ﺑﯿﻦ اﻟﻄﺮﻓﯿﻦ
ﺑﻐﺾ اﻟﻨﻈﺮ ﻋﻦ ﺳﯿﺎﺳﺎت اﻟﺸﺮﮐﺔ وأﺣﮑﺎﻣﻬﺎAgreement
53
Monitor & Control Process
Control Procurement
INPUTS TOOLS & TECHNIQUES OUTPUTS
OUTPUT
Closed procurement إﻏﻼق اﳌﺸﺘﺮﯾﺎت واﻟﻌﻘﻮد
The project management team should have approved all deliverables prior to closure.
Procurement administrator, provides the seller with formal written notice that the contract has been completed.
Closing process ﻣﺮﺣﻠﺔ اﻹﻏﻼق وﻟﯿﺲMonitor & Control process ﻣﺮﺣﻠﺔ إﻧﻬﺎء اﻟﺘﻌﺎﻗﺪ ﻣﻊ اﳌﻮردﯾﯿﻦ ﯾﺘﻢ
Closing process ﻣﺮﺣﻠﺔ اﻹﻏﻼق وﻋﻠﯿﻚ ﮐﻤﺪﯾﺮ اﳌﺸﺮوع اﻟﺘﺄﮐﺪ ﻣﻦ إﻏﻼق ﺟﻤﯿﻊ اﻟﻌﻘﻮد ﻣﻊ اﳌﻮردﯾﻦ ﻗﺒﻞ اﻟﺒﺪأ
54
General Definitions
Contracts
Fixed Price
FFP إذا ﮐﺎن اﻟﻨﻄﺎق واﳌﺘﻄﻠﺒﺎت واﺿﺤﺔ ﺗﻤﺎﻣﺎ وﺗﺒﺤﺚ ﻋﻦ أﻗﻞ اﻟﻌﻘﻮد ﺧﻄﻮرة ﻓﺄﻓﻀﻠﻬﺎ
CPIF ﺣﺎل ﮐﺎﻧﺖ ﻏﯿﺮ واﺿﺤﺔ ﻓﺄﻗﻞ اﻟﻌﻘﻮد ﺧﻄﻮرة هﻮ و
ﻓﺼﻞ
13
إدارة
اﳌﻌﻨﯿﯿﻦ
Stakeholder Management
PMBOK 6th Ed. (503-536)
56
Initiating Process
Identify Stakeholders
INPUTS TOOLS & TECHNIQUES OUTPUTS
OUTPUT
High
Planning Process
The process of developing approaches to involve stakeholders based on their needs, expectations, interests.
as well as their potential impact on the project.
Stakeholder 1 C D
Stakeholder 2 C D
Stakeholder 3 C, D
OUTPUT
Stakeholder engagement plan ﺧﻄﺔ إﺷﺮاك اﳌﻌﻨﯿﯿﻦ
Identify specific strategies and actions for engaging with individual or group of stakeholders.
To improve stakeholder involvement in decision making.
58
Executing Process