You are on page 1of 4

2020 IEEE Region 10 Symposium (TENSYMP), 5-7 June 2020, Dhaka, Bangladesh

Over-Frequency Mitigation Using Coordinated


Generator Shedding Scheme in a Low Inertia Power
System
Md. Nahid Haque Shazon, Hasin Mussayab Ahmed and Nahid-Al-Masood*
Department of EEE, Bangladesh University of Engineering and Technology, Dhaka-1205, Bangladesh
shazon.buet.eee@gmail.com, punnohasin@gmail.com, nahid@eee.buet.ac.bd (*Corresponding author)
Abstract—The objective of this paper is to mitigate over- over-frequency in an area which has been separated from
frequency problem of a low inertia power system using adjacent area because of interconnection line trip. For
coordinated Over-Frequency Generator Shedding (OFGS) instance, South Australian power system is a low inertia
scheme. Recently, prolific amount of wind resources has been power system under credible risk of experiencing over-
introduced in many power systems around the world. These frequency problem in islanded condition [14].
variable speed wind power plants cannot contribute to system
inertia unlike traditional synchronous generators. This leads The most convenient method for over-frequency
to insufficient system inertia and the system can be termed as mitigation is generator shedding when the frequency
low inertia power system. If an area is transporting crosses a predetermined threshold [4]. The trivial range for
significant amount of power to adjacent area, then tripping of a generator to operate properly is when system frequency is
interconnection line can cause excess power thus to increase between 47 Hz- 52 Hz [14]. If system frequency goes
the system frequency in that area. This research work beyond 52 Hz, over-speed protection relays of generators
proposes a method to mitigate this problem using over- disconnect them from grid and system eventually leads to
frequency generator tripping scheme. Results show that blackout. The most crucial decision about generator
tripping wind turbine generator provides the best system shedding is which generator is to be shed first. Because,
response if single generator tripping scheme is undertaken. In effects of tripping steam turbine generator, hydro turbine
case of double generator tripping scheme, wind-hydro
generator and wind turbine generator can be contrasting in
combination tripping demonstrates the lowest frequency
terms of frequency peak and ROCOF following the
summit, lower Rate of Change of Frequency (ROCOF) and
faster settling time. Finally, generators having different
generator trip [5]. The difference in operational mechanism,
inertia constants are tripped to portray that generators inertial behavior and dynamic response of these different
having lower inertia constant should be tripped first. turbine generators cause the system to act differently. The
result is more interesting when a combination of them is
Index Terms— Over-frequency generator shedding, inertial tripped to mitigate over-frequency problem. Tripping more
response, low inertia power system, frequency summit, rate of generation than reduced load causes the system to suffer
change of frequency. from substantial under frequency load shedding to resettle
system frequency.
I. INTRODUCTION
Various methods and coordination of generator
Interconnected multi-area power system has become shedding scheme have been reported in literature [6]. [7]
inescapable with the increase in size and capacity of denotes, preferred option for generator tripping scheme is
modern power system. The interconnectivity and to trip those generators which are close to the primary node
complicacy in modern power system can enhance the risk of disturbance. Coordination of over-frequency generator
of over-frequency problem in a power grid [1]. Especially, tripping in small capacity grids are discussed in [8].
when an area is sending large amount of power to its Applying proper delay timing, proper capacity generation
adjacent area, an interconnection trip can cause an tripping and escaping under frequency load shedding have
undesirable over-frequency situation in that area. Because been given priority for over-frequency mitigation in [8]. A
of loss of load, the excessive power, which was previously control methodology of virtual power plants using decision
being sent to its neighboring area, can cause over-voltage tree aided active power control provision is described in
and over-frequency problem. The severity of these [9]. Potential application of active power reduction of
problems depends on overall system configuration, system distributed generator in a microgrid is denoted in [10] and
inertia and type of generator turbines available on that [11]. Grid connected wind farm tripping can be
system. instrumental for over-frequency mitigation according to
In previous years, wind power generation has been [12]. However, coordinated tripping of hydro, wind and
prolific throughout the world. According to [2], worldwide steam turbine can bring further improvement in over-
wind energy generation in 2018 was 563 GW. Wind frequency mitigation in a low inertia grid. To
penetration has a significant impact on system inertia. The comprehensively investigate the over-frequency
inertial behavior of these wind turbine generators is management strategy, this paper proposes a coordinated
different than that of conventional synchronous generators. tripping scheme including hydro, wind and steam turbine
Type III (Doubly-Fed Induction Generator: DFIG) and type generator tripping. Furthermore, effect of inertia constant of
IV (Full-Scale Converter: FSC) wind turbine generators the tripped generator on the frequency response has also
(WTGs) are predominantly deployed among four type of been investigated in this research work.
wind turbine generators around the world. As they are Remaining of the paper is structured as follows:
connected to the host grid via power electronic converters, Methodology and execution of OFGS is narrated in section
they cannot participate in frequency regulation [3]. Thus, II, network overview is given in section III, simulation
abundance of wind penetration can enhance the risks of

978-1-7281-7366-5/20/$31.00 ©2020 IEEE


560

Authorized licensed use limited to: California State University Fresno. Downloaded on June 23,2021 at 16:37:59 UTC from IEEE Xplore. Restrictions apply.
scenarios are depicted in section IV, section V contains
simulation results and analyses and section VI presents
concluding remarks and comments.
II. OVER-FREQUENCY GENERATOR SHEDDING OPERATION
Interconnection line trip can cause loss of load in an
area which in turn increases the system frequency. When
the system frequency crosses a certain threshold then over-
frequency generator shedding relay directs the circuit
breaker to open. Basic operation of OFGS is illustrated in
Fig. 1. According to Fig. 1(a), interconnection line trip
occurs at 2 second as a result frequency starts to rise. This
deviation in frequency initiates governor response and
generator power output begins to reduce as shown in Fig.
1(b). When frequency crosses 51.25 Hz, the power output
becomes zero drastically because of the generator shedding
scheme.

Figure. 2 Frequency response and power output for double tripping

III. NETWORK OVERVIEW


The test power system has been constructed based on
South Australian 14 generator model. The test network
is depicted in Fig. 3. The steam turbine generators are
located at PLANT-1 and hydro turbine generators are
located at PLANT-2. The information needed for dynamic
simulation, nameplate data, unit capacity, unit MVA rating
and unit inertia constant are available in Table II.
From the network diagram it is apparent that wind
turbine machines are located at bus 18 and 19. 70% of the
total wind generation is concentrated at bus 18 and rest of
the wind generation is located at bus 19. Area A is
Figure. 1 Frequency response and generator output power after OFGS connected with adjacent area B through a 275KV HVAC
scheme
transmission line which normally transfers 200 MW power
from Area-A to Area-B.
The Upper threshold frequency, relay pick-up time and
TABLE II. SYNCHRONOUS GENERATOR INFORMATION
breaker time is illustrated in Table I [13]. Lower threshold
Power Unit Unit MVA Unit inertia
frequency has been set to zero because under frequency station
No. of
capacity rating constant (s)
generator tripping is not considered in this research work. units
name (MW) (MVA)
PLANT_1 2 200 250.0 4.00
TABLE I. RELAY SETTING FOR GENERATOR TRIPPING PLANT_2 2 150 166.6 4.00
Description Value
1. Upper Threshold frequency (Hz) 51.25
2. Lower Threshold Frequency (Hz) 0
3. Relay Pick-up time (seconds) 0.00005
4. Breaker time (seconds) 0.083

Circumstances can arise where single generator tripping


scheme is not enough for frequency regulation. Multiple
generator tripping is more convenient for these situations.
As an illustration, Upper threshold frequencies for those
generators can be 51.00 Hz and 51.25 Hz respectively. Fig.
2(a) and 2(b) show hydro turbine generator has been
tripped at first at 51.00 Hz. As it is not enough to stop the
frequency rise, steam turbine generator is tripped at 51.25
Hz which is shown in Fig. 2(c).

Figure. 3 Network diagram of test system

561

Authorized licensed use limited to: California State University Fresno. Downloaded on June 23,2021 at 16:37:59 UTC from IEEE Xplore. Restrictions apply.
IV. SIMULATION SEQUENCE Therefore, wind turbine generator tripping, which lefts
Simulation sequence explored in this research work is steam and hydro turbine generators in the system, shows
illustrated in Fig. 4. At first, effect of single generator trip best frequency response following a contingency. This is
on the system is investigated for three types of turbine because hydro and steam turbine generators have inertial
generator. Double generators shedding scheme is inspected response as well as governor response which Type-III wind
for available three combinations afterwards. Finally, single turbine generators lack. For all cases the settling frequency
generator tripping is investigated by tripping generators remains above 50 Hz which implies that single generator
having different inertia constants. This analysis gives an trip is not enough to restore the frequency to nominal value.
insight about which generator unit should be tripped first
for better system frequency response.

Fig. 5: Frequency response without OFGS scheme

Figure. 4 Schematic view of simulation sequence

For this research work, it has been assumed that total


system load is 1600 MW. Total wind penetration is 1220
MW and number of online synchronous generators are 4
which produces rest of the power. Overview of these
information are illustrated in Table III. Area-B receives 200
MW of power from Area-A in normal operating condition.
Accordingly, an interconnection line trip causes a sudden
reduction of 200 MW in system load. Figure. 6 Frequency response with single generator trip scheme

TABLE III. OVERVIEW OF GENERATION INFORMATION AND SYSTEM


INERTIA B. Double Generator Tripping
Number of Synchronous Wind Total System Tripping a single unit of generator might not be able to
Synchronous generation Penetration Inertia bring back the frequency to its nominal value. To settle the
Generators (MW) (MW) (MWs)
4 380 1220 3667 frequency quickly and to have a settling frequency nearer
to the nominal frequency, double generators both having
100 MW capacity, tripping scheme is undertaken. The first
V. RESULTS AND ANALYSES generator is tripped at 51.00 Hz and second one is tripped
In this section, simulation results are presented and at 51.10 Hz. Fig. 7 shows that frequency peaks after OFGS
analyzed for various tripping scheme. All the simulation scheme are 51.12 Hz, 51.20 Hz and 51.23 Hz for wind-
tasks are executed using PSS®E software in conjunction steam combination, wind-hydro combination and steam-
with Python programming language. This software is well hydro combination respectively.
acknowledged and utilized in many countries for power
system analysis.
A. Single Generator Tripping
When OFGS scheme is not activated then the system
frequency goes above 52 Hz. Thus, system suffers from
cascaded generator trip and blackout which is illustrated in
Fig. 5. When frequency goes above 51.00 Hz, the OFGS
scheme is activated here. Effect of tripping a single
generator having 100 MW capacity is shown in Fig. 6. It
appears that, frequency peak after wind, hydro and steam
turbine generator trip are 51.25 Hz, 51.35 Hz and 51.65 Hz
respectively. ROCOF has been calculated after activating
OFGS scheme taking 100 ms window from 3.15 s to 3.25 s.
The ROCOF values are 0.23 Hz/s, 0.35 Hz/s and 0.48 Hz/s. Figure. 7 Frequency response with double generator trip scheme

562

Authorized licensed use limited to: California State University Fresno. Downloaded on June 23,2021 at 16:37:59 UTC from IEEE Xplore. Restrictions apply.
ROCOF is quantified the same way as single generator and ROCOF after generator tripping. For double generator
tripping scheme and obtained values are 0.15 Hz/s, 0.17 tripping scheme, combination of wind and hydro turbine
Hz/s and 0.22 Hz/s for abovementioned three generators tripping shows the best frequency response. It’s
combinations. because of lack of governor and inertial response from
wind turbine generators and initial power surge
Therefore, tripping wind and hydro turbine generators characteristics of hydro turbine generator.
and keeping steam turbine generator yield the best result.
This is because wind turbine generator has neither inertial Finally, effect of inertia constant of generators in
response nor governor response. Also, the initial power tripping scheme has been illustrated. It reveals that to avoid
undesirable frequency response, generators having lower
surge of a hydro turbine is opposite to that desired which
inertia constant is preferred to be tripped first.
deteriorates system frequency response [15].
C. Tripping Based on Inertia REFERENCES
In this case, three steam turbine generators having [1] Z. Song, Y. Lin, C. Liu, Z. Ma and L. Ding, "Review on over-
inertia constants of 3 s (low H), 6 s (medium H) and 7.5 s frequency generator tripping for frequency stability control," in
(high H) are tripped one by one. For this case, it is Proc. 2016 IEEE PES Asia- Pacific Power and Energy
assumed that synchronous generation is 300 MW and wind Engineering Conference (APPEEC), pp. 2240-2243.
[2] "Statistics Time Series", Irena.org, 2020. [Online]. Available:
generation is 1300 MW. All three generators are of same https://www.irena.org/ Statistics/ View-Data-by-Topic/ Capacity-
capacity and have same type of governor response. Thus, and-Generation/Statistics-Time-Series. [Accessed: 09- Feb- 2020].
only contrasting factor is inertia constant (H). Fig. 8 [3] N. Masood, N. Modi and R. Yan, "Low inertia power systems:
illustrates that for tripping generator with high H and Frequency response challenges and a possible solution," in Proc.
2016 Australasian Universities Power Engineering Conference
medium H lead to blackout and for generator with low H (AUPEC), pp. 1-6.
tripping, the frequency summit is 51.96 Hz. Values of [4] Y. Guo, H. Nan, X. Guan, and L. Wu, “Discussion on the Over-
ROCOF are 0.25 Hz/s, 0.31 Hz/s and 0.38 Hz/s for low H, frequency Generator Tripping Scheme of the Power Grid,” in Proc.
medium H and high H respectively which have been 2018 International Conference on Energy, Electrical and Power
Engineering, vol. 1072, pp. 1-8.
quantified taking a window of 200 ms from 3.25 s to 3.45 [5] F. Yang, Y. Su, S. Zhao, Y. Song, Y. Mei, Q. Wang, and Z. Zhang.
s. “Research on over Frequency Generator Tripping Configuration
Scheme of Regional Grid in Infirm Interconnections and Small
Capacity.” Applied Mechanics and Materials, vol. 336–338, pp.
1174–79, July 2013.
[6] AEMO, “Renewable Energy Integration in South Australia”, Oct.
2014 [Online]. Available: http://www.aemo.com.au [Accessed: 9-
Feb.-2020].
[7] Z. Zhang, X. Li, and Z. Huang, "Simulation and analysis of over
Frequency generator tripping for Guizhou isolated
power system, "Modern Electric Power, vol. 25, pp. 31-34, Aug.
2008.
[8] F. Yang, Z. Zhang, S. Zhao, L. Wu, and J. He, "Configuration
scheme of over- Frequency tripping and coordination with over-
speed protection controller (OPC) of regional grid," Electric Power,
vol. 46, pp. 64-68, Oct. 2013.
[9] P. Moutis and N. D. Hatziargyriou, "Decision Trees-Aided Active
Power Reduction of a Virtual Power Plant for Power System Over-
Frequency Mitigation," IEEE Trans. Industrial Informatics, vol. 11,
no. 1, pp. 251-261, Feb. 2015.
[10] E. Mashhour and S. M. Moghaddas-Tafreshi, "Bidding Strategy of
Virtual Power Plant for Participating in Energy and Spinning
Figure. 8 Frequency response for generator trip having different inertia Reserve Markets—Part I: Problem Formulation," IEEE Trans.
constant Power Systems, vol. 26, no. 2, pp. 949-956, May 2011.
It can be revealed from the results that tripping [11] G. Strbac, N. Jenkins, T. Green, and D. Pudjianto, “Review of
generators having high inertia constant cannot stop the Innovative Network Concepts, DG GRID Project Report,” Petten,
frequency rise. Subsequently it yields unsatisfactory Netherlands, 2006.
frequency response. However, when generators having [12] AEMO, “South Australia- Power System Operation as A Viable
Island”, June 2018 [Online]. Available: http://www.aemo.com.au
same type of turbine and capacity are present, generator [Accessed: 20-Feb.-2020].
with the lowest inertia constant should be tripped for [13] N. Samaan, J. Dagle, Y. Makarov, R. Diao, L. Miller, S. Wang, B.
mitigating over-frequency effectively. Vyakaranam, T. Nguyen, F. Tuffner, M. Pai and M. Vallem.
"Dynamic contingency analysis tool–phase 1." Pacific Northwest
National Laboratory, Richland, Washington report- 24843.
VI. CONCLUSIONS 2015.
This paper extensively investigates the role of over- [14] AEMO, “Update to Renewable Energy Integration in South
frequency generator shedding for mitigating over-frequency Australia”, Feb. 2016 [Online]. Available: http://www.aemo.com.au
[Accessed: 9-Feb.-2020].
problem of a low inertia power system. Combination of [15] N. R. Ullah, T. Thiringer and D. Karlsson, "Temporary Primary
generators having different types of turbine has been Frequency Control Support by Variable Speed Wind Turbines—
tripped to this end and it is found that for single generator Potential and Applications," IEEE Trans. Power Systems, vol. 23,
tripping scheme, tripping wind turbine generator and no. 2, pp. 601-612, May 2008.
keeping hydro and steam turbine generators online yields
the best performance in terms of frequency summit point

563

Authorized licensed use limited to: California State University Fresno. Downloaded on June 23,2021 at 16:37:59 UTC from IEEE Xplore. Restrictions apply.

You might also like