You are on page 1of 12

ENGINEERING

GEOLOGY
ELSEVIER EngineeringGeology46 (1997) 93 104

Geological conditions, seepage grouting, and evaluation of


piezometer measurements in the abutments of an earth dam
E.C. Kalkani
Faculty of Civil Engineering, National Technical University of Athens, Patission 42, Athens 10682, Greece
Received 6 February 1996; revision 5 September 1996; accepted 5 September 1996

Abstract

The geology of the abutments of the Bakoyianni earth dam in Greece, and the seepage problems of the abutments
are described. The driving of grouting and drainage adits was intended to seal and drain the middle and lower
conglomerate layers in the abutments. At both abutments and at the middle conglomerate the piezometric levels are
higher upstream from the adits than downstream, while at the lower conglomerate a smaller drop in piezometric
pressure is present. The behaviour of the abutments of the dam with a reservoir level at an elevation of 275.5l m is
satisfactory, and the same is expected for reservoir levels up to 284 m. Hence, a complete control of the abutment
seepage that will contribute to the safety of the dam is under way.

Keywords: Seepage; Leakage; Grouting; Piezometers; Abutments

1. Introduction 1959). The project was commissioned in 1966. It


has a peaking capacity of 437 MW, mean annual
The earth dam for which seepage measures and firm energy generation of 958 GWh, and a reser-
the evaluation of piezometric measurements is voir volume of 4.75 billion m 3.
presented is the Bakoyianni dam (formerly The dam is a zoned earthfill dam with a volume
Kremasta dam) in Greece, which belongs to the of 8.1 million m 3, the crest length is 460 m, and
Public Power Corporation. It is located in a narrow the maximum height is 160 m. The upstream slope
gorge on the Acheloos river, 55 km north of the of the dam is 2.5:1.0, and the downstream slope is
town of Agrinion, and 300km north-west of 2.0:1.0 (horizontal to vertical). The foundation
Athens. The reservoir is a multi-purpose storage rocks are interbedded siltstone, conglomerate, and
reservoir, serving mainly hydro-power, but also sandstone. A plan of the general arrangement,
irrigation and flood control. indicating the diversion tunnel, the dam embank-
The history of the project goes back to 1960, ment, the power intakes, power tunnels, and pow-
when the Public Power Corporation of Greece erplant, is shown in Fig. 1.
engaged Engineering Consultants, Inc., as project The geological conditions, the dam foundation
consultants to prepare the final design, the supervi- grouting, all the remedial grouting, the effect on
sion and inspection of the construction activities, leakages, and the processing and evaluation of
and the purchase of major equipment (Ebasco, piezometer measurements are presented.

0013-7952/97/$17.00© 1997ElsevierScienceB.V. All rights reserved


PHS0013-7952(96)00101-9
94 E.C. Kalkani ' Engineering Geo/o,e ' 46 (1997) 93 104

ACCESS

SPILLWAY

~s -_ " TUNNELS
AD#T C _'% 1!/

150 - - -
/) % /'
1UNNELPLUG /
/' J '
/ I .:
, i
INTAKES" "
!
RESERVON
\. OlVERS~n.~EL ~ ' ",
/~/' '
•4" (' "/i <,
LEFT ABUTMENT
!
o.... m ,,~o
~ . .,4,

Fig. 1. Plan of the general arrangement, with indications of the diversion tunnel, the dam embankment, the power intakes, the power
tunnels and powerplant, and the existing faults in the area.

2. Geology and tectonism the siltstone and the conglomeratic siltstone are
about equal in thickness to the conglomerate and
The site is in the Pindos mountain range, which sandstone sections and occur mainly in the upper
was thrown up during the Tertiary period. The two-thirds of the abutment sections. Near the toe
range continues into the Balkan countries with a of the dam the stream channel was confined in a
north-northwest to south-southeast trend. It con- very narrow gorge cut into very compact
sists mainly of an ophiolite series, with an abun- conglomerates.
dance of mesozoic sediments, mainly limestone. A vertical section on the centerline of the dam
More specifically, the project is situated in the embankment indicating the three levels of con-
rock formation known as the G a v r o v o zone of the glomerate (upper, middle and lower) and the cross-
Upper Cretaceous to Tertiary Age. The formation sections of the structures (spillway, diversion
includes flysch that consists of cherts, shales, and tunnel, and headrace tunnels) is shown in Fig. 2.
limestones. The three strata of conglomerate present stand out
The types of sedimentary rock at the abutments as cliffs along the canyon, as these rocks are more
of the dam are interbedded siltstone, conglomerate, resistant to weathering than the others, but are
and sandstone. The dam is positioned in a narrow more susceptible to seepage.
canyon with both abutments rising on a slope of The conglomerates are composed mainly of
1.5:1.0 to the top of the dam. Along the dam axis, limestone cobbles in a dense calcareous matrix and
E. C Kalkani / Engineering Geology 46 (1997) 93-104 95

3o0-- ~, F SRU.WAY U DAM CREST,a. 287m / ,~_


~o ~ " ! .... ' ~ 1 - t~I~4.0MERATE

2> ~ ~ - ' - . . . . * : . : . . . . : , . , . o , °.' ". .~~ ." ~F' " " "*'° ''*°" Lo ~

sol " '/" ....... "t- A~__ XI~_TELYLI~IT . J


UP GkNTF.:RGROUT LI~E ....

Fig. 2. Vertical section o n the centerline o f the d a m e m b a n k m e n t a n d g r o u t curtain (not in scale), i n d i c a t i n g the three levels o f
conglomerate (upper, middle and lower).

small amounts of flint or chert cobbles. These are the east with the result that the left abutment
dense rocks with a high modulus of elasticity, layers are slightly lower in elevation than those of
which grade into weaker conglomeratic siltstones the right abutment.
in which the matrix changes to marls and siltstones. Several near-vertical faults striking parallel to
The sandstone members are calcareous, dense, the dam axis are present, designated with the
and hard. The thickest occurs at the river level on letters A, B, C, D, E, F in Fig. 1. In most fault
the dam axis; however, it is transposed below zones there is topsoil and overburden, so that the
stream by a fault towards the left abutment. Lenses scarcity of exposed rock surfaces and of fault
of sandstone as well as thin beds occur through traces makes it difficult to correlate the faults.
the siltstone and conglomerate layers. Fault A upstream of the dam and fault E down-
The siltstone layers are present in the gentle stream have throws in the order of 25 m, while
slopes of the valley and weather very rapidly at faults B - F have smaller throws or indicate highly
the surface. The rock is always dense and compact fractured fault zones instead of clear rock displace-
when fresh and unweathered. Laminations and ment. The character of the faults changes from
fissile features similar to shale are present. The one abutment to the other, while most of them
cementation is made by a marly material. have side branches. The fault fissures range from
Saturation creates a reduction of strength, and a few millimeters to some meters wide, and the
yielding takes place under prolonged loading and filling material varies from gouge, clay, silt, and
saturated conditions (ECI, 1974a). sand to broken rock (ECI, 1974b).
Folding at the site is of the Miocene age, with The water tests indicated that the faults are
intensity decreasing from east to west. One major impermeable in siltstone but pervious in the con-
fold traverses the area parallel to the Acheloos glomerate. Fault A upstream of the dam is at the
river and to the west of the reservoir. Neither the natural entrance of water from the reservoir, while
fold nor the faults at the project area are of recent fault F downstream acts as natural drainage. Fault
origin. Since most of the earthquakes occurring in D with a downstream throw of 2-3 m, has infilling
the area are due to subsidence of rift valleys, the material of loose sand, and smaller amounts gravel,
design earthquake at the site was taken as a factor silt, and broken rock in a wide zone of disturbance,
of 0.1 × g for the horizontal acceleration from and Fault E with a downstream throw of 2 m, has
seismic waves. a wide zone of broken material extending deeply
A broad fold is present a short distance down- into both abutments. These are the main leakage
stream from the dam site in the form of an carriers (ECI, 1968).
anticline, with the downstream limb dipping south Vertical jointing is present in the conglomerate
in the downstream direction. The dam axis is along and sandstone striking north 70 ° west. Jointing is
the upstream limb of this fold. Hence the beds are less obvious in the siltstone, and discontinuities
dipping upstream by 4 ° at the axis and are steeper, are tight or sealed with carbonates. Strong vertical
up to 15°, 1 km upstream. Also, there is a dip to jointing striking northeast and northwest is evident
96 E. C. Kalkani ,. Engineering Geology 46 i 1997) 93 104

in the sandstone and the conglomerate. Many of ment of the clay layers at the core. Additional
the joints are closed or healed with calcite deposits. grout holes were placed in case of high grout takes.
Small local sulphurous springs existed in both In all grout holes, packer grouting was used from
abutments near the river level with moderately the bottom upwards, while grout pressures varied
warm water seeping t¥om fractures and joints in according to the locations of the packers. Mixtures
the conglomerate and sandstone, and these were of Portland-type cement was used containing 10%
successfully sealed by the grouting program under pozzolan, with water-cement ratios from 10:1 to
the dam ( ECI, 1968). 0.8:1 depending on the grout takes (but seldom
Solution channels evident at several positions, lower than 1:1 ). After the completion of parts of
with irregularities in size, shape, and alignment, the curtain, water pressure tests at holes drilled
are found more frequently in the lower conglomer- indicated tight rock formation.
ate or in the siltstone beds with overlying conglom- In the siltstone zones the grout takes were
erate. After the impoundment of the reservoir generally low. Large grout takes occurred in the
these channels indicated that they extended middle conglomerate layer. Because the grout cur-
through great distances and could carry water tain was located between two faults (D and C) in
from the reservoir downstream from the abutments a relatively undisturbed area (Fig. 1), the grout
of the dam. take was relatively smaller than that in the remedial
At the location of the dam, a concrete cutoff works carried out in the fault zones. Along the
was constructed at the core foundation shown in headrace and the diversion tunnels grouting was
Fig. 2, to penetrate the upper portion of the clay performed to consolidate a ring of sealed rock at
material, which was a product of the siltstone the position of the grout curtain. High takes were
weathering. The sandstones and conglomerates experienced in the locations of solution channels
and some of the conglomerate siltstones were well and faults.
cemented, and very little excavation was needed The fractured zone of fault E in the right
for the cutoff trench. abutment contained numerous voids in the middle
and lower conglomerate, the lengths of which (as
measured along the drill holes) ranged from a few
3. Dam foundation grouting centimeters to a few meters. During grouting oper-
ations the clay filling of the fissures was washed
The foundation treatment under the dam away when flushing the drill holes. The filling
included the cleaning of overburden under the core material consisted of clay, silt and sand.
and rock excavation to sound rock (ECI, 1968). In the right abutment, fault caves associated
The rock surfaces were cleaned before placing the with fault F were present in the lower conglomer-
clay material. A slab of concrete was placed on ate. The caves were explored by drilling and found
heavily broken rock, and contact grouting between to have irregular shapes. They were formed by
concrete and rock followed. The warm sulphurous water flow in a number of major fractures and
springs were grouted with a water-cement mix were encountered during the driving of the adit G.
containing bentonite. The major fractures associated with the caves
The grout curtain under the dam, shown in contained calcite, clay-like material, and fine sand.
Fig. 2, was designed as a vertical extension of the Solution channels were also present.
centerline of the core of the dam. This was con- The permeability of the rocks in the undisturbed
structed as a single line of grout holes to varying state was extremely low. Hence, the secondary
depths. The upper 20 m of the grout curtain was permeability through open discontinuities and
complemented with additional line holes on either joints, fractures, and solution channels and faults
side of the curtain to increase the sealing capacity is significant. From water tests in drill holes it was
of the grout curtain immediately under the core. observed that permeability ranged from zero to in
The grouting was performed from the river excess of 0.5 c m s I in the conglomerates and
channel upwards and was followed by the place- sandstones. Permeability in siltstone was in the
E.C. Kalkani / Engineering Geology 46 (1997) 93 104 97

order of less than 10 -5 c m S -1. This tightness of tation, review, and evaluation of all the available
siltstone prevented water communication between information.
the upper and lower conglomerate layers. The review of abutment leakages (ECI, 1968)
Substantial grout takes in the sandstone and con- included the design, application of measures, con-
glomerate confirmed the water pressure test results. clusions, and recommendations of a program of
In siltstone the grout take was low, except where long-term control work. The control measures
disturbed rock was present in fault zones. were necessary to reduce leakage from the abut-
ments, and a system of piezometers and measuring
installations was planned before grouting and
drainage works in both abutments was carried out.
4. Remedial grouting Besides drainage in the left abutment to relieve
pressure in the area of the powerplant, the main
The construction of the dam ended in July 1965, grouting and drainage program started in July
and the diversion tunnel was closed in the same 1971 and ran until April 1973. The reservoir eleva-
month. As the reservoir was impounding in August tion during the remedial work was retained below
of the same year, leakages were noticed down- an elevation of 273.6 m.
stream from the toe of the dam in both abutments. The general remedial measures included the
In the spring of 1966 the abutment leakages drain curtains at the left and right abutments,
reached their greatest extent at both abutments positioning leakage measuring structures, placing
(500 1 s-~ right abutment, 400 1 s-1 left abutment). foundation instrumentation, and grouting with the
An initial treatment program started as soon as proper grout material and mixes (including tests).
the leakages appeared, and a program of addi- To varying degrees, each stage of the work
tional grouting was undertaken in early 1966 (ECI, depended on the previous stage. The source and
1968). The program included an extension of the direction of major leakage was found to be through
grout curtain into the abutments and grouting at faults D and E, as shown in Fig. 3.
fault D. In 1966, an access adit and two cross After the construction of the drainage system in
adits were constructed in each abutment to drain the left abutment, and the leakage measuring struc-
the rock mass in order to perform additional tures in 1968, and after the placement of the initial
grouting downstream of the grout curtain. The piezometers in 1969 and the piezometers in
grouting of the sources of water while driving the 1971-73, measuring flow rates from drain holes
left abutment adits in the vicinity of fault D and piezometric levels at regular time intervals was
facilitated the driving of the adit. The positions possible.
of adits A, B, J, RDT, G, and K at the right The cumulative water flow, water test results,
abutment, and adits D, C, E, I, H, LDT, and F and grout takes were plotted against the cumula-
at the left abutment are shown in Fig. 3. tive length of grout holes, and charts were kept
The construction of the adits and the supplemen- for each grout hole in the middle and the lower
tary grouting in June 1966 resulted in a decrease conglomerate. As the grouting progressed, the
of leakage but not to an acceptable level (half or water flow from the grout holes was reduced.
less). In August 1967, the short side adit E was There was, as well, a reduction of water take and
constructed from adit LDT. Drain holes upward grout take.
into the middle conglomerate produced large flows
under pressure.
A review of the leakage problem in 1967 5. Effect on leakages
included the assessment of sealing measures for
the l-year period. The initial treatment work had Each leakage point was measured daily, and
limited success, and water flows were present in charts were kept to check the effect of grouting in
the adits. Further actions were decided upon after relation to the reservoir level. After the completion
an overall review including correlation, documen- of grouting work in the middle conglomerate of
98 E. U. Kalkani / Engineering Geology 46 (1997) 93 104

SOURCEANDDIRECTIONOFMAJOR LEAKAGE
GROUTI'IGREQUIRED, - . . . . GROUTINGNOTREQUIRED
ORAqNAGE
~, MC WORKTOBEPERFORMEDIN MIDDLE~OMERATE
~:~Otl F - "~l" " "~ LC WORKTO8E PERFORMEDIN LOWERCONGLOMERATE

</"~ ~~. / '.~ ~ ~ .O/()


~ O~o~ / _._~ ~_
T6 BE pROTECTED ~ t\

"&J-Ltj r ~, ~ :' "" - ADITK

Fig. 3. Position of the grout and drainage adits, the source and direction of major leakage, and indication of areas to be protected.

both abutments, there was a significant reduction control works as well as the reservoir levels.
in the rate of leakage, in the left abutment, after Towards the completion of grouting, the difference
the completion of grouting, the flow from the in piezometric levels across the grout curtain
drainholes was reduced to 45%, and the rate increased.
changed from 1.751s-~ for a l-m change in the The piezometric levels recorded after the com-
reservoir level to 0.651s -~ per 1-m change in pletion of the control work showed a nearly linear
reservoir level. Leakages in the right abutment variation with reservoir levels. Hence, for compari-
emerged from the middle conglomerate, when the son reasons, extrapolation of the measurements
reservoir level was above an elevation of 247 m. was made to assign values at a reservoir level of
After termination of the grouting work, there was 266 m, although the highest level up to 1973 had
no leakage from the reservoir for levels up to been 257 m. The residual hydrostatic levels down-
257 m, and the conglomerate outcrops were com- stream from the grout curtains are caused mainly
pletely dry. by flows bypassing the end of the grouted area
The underground water velocity was measured and by flows entering the protected blocks through
with dye tests, performed before and after the ungrouted areas. This phenomenon is present at
grouting and drainage measures. In most cases the the right abutment and at the lower conglomerate
dye would not pass through the completed curtains from flows bypassing the downstream end of the
at all. Since the rate of underground water veloci- grout curtain through the zones of fault E and the
ties were significantly reduced, the erosion was no fault E caves.
longer sustained due to the protection of the grout In the lower conglomerate of the left abutment,
curtains. the drain holes of the diversion tunnel drain the
The piezometer levels for each of the conglomer- seepage flows from the lower conglomerate. The
ate layers were regularly recorded. The lowering residual underground flows in the middle conglom-
of the piezometric levels indicated the effect of the erate of the right abutment are low enough to be
E~C Kalkani / Engineering Geology 46 (1997) 93 104 99

drained by drain holes and fractures in the rocks. level in boreholes at the left abutment was also
In the middle conglomerate of the left abutment recorded and used in this study.
the drainage system from the diversion tunnel Plots of the variation of piezometer measure-
takes care of the remaining flows. After the mea- ments versus time are shown in Figs. 4 and 5. At
sures taken in the middle and lower conglomerate, the left abutment, the behaviour of 10 piezometers
the expected behaviour in higher reservoir levels, in adit F and eight piezometers in adit C, and at
such as 282 (maximum power pool) and 284 m the right abutment, the behaviour of 10 piezome-
(top of flood control storage), has to be forecast, ters in adit G, and eight piezometers in adits A
although additional drain holes may be required and B are shown in Fig. 4, at the left and right
in certain areas. sides, respectively. Also, at the right abutment, the
The leakage flows into the diversion tunnel behaviour of seven piezometers in adit D and eight
before the initiation of grouting ranged from 100 piezometers outside the adits, and at the right
to 125 1 s -1 for reservoir elevations between 250 abutment, the behaviour of six piezometers in adits
and 270 m. During grouting the leakage fell to J and RDT and seven piezometers outside the
65 1 s-1 between reservoir elevations of 240 and adits are shown in Fig. 5, at the left and right side,
257 m. The variation of the piezometric levels and respectively. No increase in piezometer measure-
the drainage through adit M indicated that the ments is present, except for adit C at the position
major part of the leakage in the left abutment of PC5, adit J and RDT at the position of PT8,
enters through the upstream ungrouted boundary and adits A and B at the position of PK1, all
and through the lower conglomerate at the right found upstream from the grout curtain.
abutment. The leakage from the right abutment At the left abutment, the variation of water level
was measured with structures at the downstream in nine boreholes drilled for geotechnical and
toe of the dam, which after the impoundment of inclinometer investigations is shown in Fig. 6 (top
the reservoir of the downstream hydro powerplant left). Measurement of flow in adits and tunnels is
were inoperable. Hence, there was no measurement plotted versus time in Fig. 6 (top right).
of the effect of grouting in adit G on the leakage The measurements that correspond to the year
flow of the lower conglomerate. 1978 are low since the reservoir level was at 240 m,
while from 1981 to 1991 there is no significant
variation, with the exception of certain cases where
a considerable increase of the measurements is
6. Processing of piezometer measurements present. The piezometric values at the middle and
lower conglomerate are designated separately. In
The measurements of piezometric levels by the middle conglomerate, in most cases there is a
instruments installed in boreholes within the adits distinct separation of the measurements that corre-
and at ground level at the right and left abutments spond to the piezometers upstream and down-
of the dam, the measurements of the water level stream of the grout curtain, i.e., adits F and C of
in boreholes and of flow rates from adits and the left abutment and adits G, A and B of the
tunnels are recorded regularly. The characteristic right abutment (Fig. 4), while in adits D, J and
reservoir levels and the years to which the record- RDT this separation is not present (Fig. 5). In the
ings correspond are: 271 m in 1974, 240 m in 1978, lower conglomerate, in certain cases there is a
274.25 m in 1981 and 275.51 m in 1991. A complete grout curtain and in others there is not. In all
reference for the piezometer measurements and plots of Figs. 4 and 5, the plots for the piezometer
evaluation is available in a report to the Public measurements in the lower conglomerate versus
Power Corporation (Papaleonardos, 1993). time are all in one group.
From the 70 installed piezometers, only 64 are The flow rate plots shown in Fig. 6 (top right)
included in this study. Those not included are indicate high values of flow from the adit M,
either dry for long periods of time or give the which is found within the lower conglomerate of
same readings as nearby piezomenters. The water the right bank just above the tailrace level. The
100 E, C Kalkani ,' Engineerin~ Geology 46 (1997) 93 104

ADIt G
280 middle c o n g l o m e r a t e
PIEZOMETERS
upstream grout curtain
ADI1- F PG7
PG3
260 260

middle c o n g l o m e r a t e
240 upstream grout curtain .,-~_~---- ~ PG8
1..240
PF / ;/1-~ ~ PG20
E
,.•'•220 PF5 "--'---~._i~ PG4
PF3 220 PG2
~ q)
d o w n s t r e a m grout curtain E middle conglomerate
; PFll L d o w n s t r e a m grout curtain
200 PF]2 200
(3
ol q~
~'~lo~w ''~ .... PF2
O er c o n g l o m e r a t e PF4
180 PG12
~ c u r t a i n 180 PG15
--, p ¢ . - PGt4
V ~ PF8 lower conglomerate
160 ~ PFIO no grout curtain
160

d o w n s t r e a m grout curtain

140 ~ r, i l l i l l l ii , l l , , r ~ l l . i , I
140 i i , i , i , i i i i , i i ~ , i i-~ i i i m ~
1970 1975 1980 1985 1990 1995 1970 197s 1980 1985 199o 199s
Time (years) Time (years)
PIEZOMEIERS
ADIf A & B
280
PIEZOMETE RS
ADIT C PK1

middle c o n g l o m e r a t e middle c o n g l o m e r a t e
25D 250 upstream grout curtain
upstream grout curtain

240 ~ PC9
PC5
..240
PA4

-.•-•220 middle c o n g l o m e r a t e
d o w n s t r e a m g r o u t curtain
~- 2 2 0
c
~ -~-'~T-~ S6OAD
PA3
PA2
c k_ middle c o n g l o m e r a t e
q) . PC7
k_ d o w n s t r e a m grout curtain
PC 1
E 200 PC6 ~ 200
~ . . . ~ _ ~ ~ PBU
[/1 ~c
aJ 180
180 PB]
PAl
~ / - ~ PC1 I lower c o n g l o m e r a t e
----- ~ PC2 no grout curtain
160 160
..~.~_. _ ~ ~ PC 12
lower c o n g l o m e r a t e

140 , , , ~ , , , , ~ , , , , ~'r--r, , ~9, , T-r-q 140 ~- , , , i , , , , ~ ~ F - ~ r - r q - , , , , , , , ~


1970 1975 1980 1985 t9 0 1995
Time (years) 1970 1975 1980 1985 1990 1995
Time (years)

Fig. 4. M e a s u r e m e n t s o f p i e z o m e t e r s in a d i t F a n d adit C (left a b u t m e n t ) , a n d in a d i t G a n d adits A a n d B (right a b u t m e n t ) .


E. C. Katkani / Engineering Geology 46 (1997) 93-104 101

PIEZOMETERS PtEZOMETERS
ADIT D ADIT J & RDT
260 260

240 240

220 middle conglomerate


220
upstream grout curtain PT8
......... - ~ PD3
qd
PD7
middle conglomerate
E 200 ~-'---"~ ' PD5 E 200 downstream grout curtain
downstream grout curtain •- ~ PT4
01 O3

w 180 w 180
lower conglomerate
no grout curtain PJ2
PRDT2
......... -..., PD2
160 PD4 lower c o n g l o m e r a t e PRD1-7
160
' I ~~ P D t 0 no grout curtain
PD11

140 , ,, ,1, ,,,1 ,,, ,l ,,, ,i ,, ,, i 140 i i I 11 i i i i i i ) i 11 i i i i i i i i1-.- ~


1970 197.5 1980 1985 1990 1995 1970 1975 1980 1985 1990 1995
Time (years) Time (years)

PIEZOMETERS
LEFT ABUTMENT PIEZOMETERS
RIGHT ABUTMENI
260 250 upstream grout curtain
- - G22x

240 middle conglomerate 240


d o w n s t r e a m g r o u t curtQin middle conglomerate
G17
-..•2 2 0 ...... ~ G19 ,•.,'•2 2 0 ~-- -----. . . . . . . . . .
_ .
G25
G23
G22
. . . . G20 q.I downstream grout curtain
E 200 G21
E 200

ol g
0 180 lower conglomerate 180 G25×
no grout curtain ~: = : : -__ . . . . . . . . t G23x
G20x lower conglomerate
t 60 G29x 160 no grout curtain
G)6x G24
-~ = ~ ' G30x

t40
970 1975 1980 1985 1990 1995 197o 197s 1980 198s 1990 ~99s
Time (years) Time (years)

Fig. 5. Measurements of piezometers in adit D and outside from adits (left abutment), and in adits J and R D T and outside from
adits (right abutment).
102 E. (:: Kalkani ; Engineering Geology 46 (1997) 93 104

BOREHOL£S ADI[ & TUNNEL


LEFTABUTMENT LEAKAGE
280 400

260 350

300
"•240
middle conglomerate G8 ~.25
~: : ..... G9
G3
200
200
aiversion tunnel
o 1B0
lower conglomerate G5 o
L~
*-~ ~ : ........ ~ G4 100 left b a ~
L t .~ ----~ n
160
B ~ a c c e ~ tunnel
15 5O
right drain tunnel
~ teft drain tunnel
140 i i I r i ! i '1 i i ~"T" i i l i ~ 0 ..... ' ' r'r-T i ~ I

1970 1975 19e0 198~ 1~9o 19~s 1970 1975 1980 1985 1990 1995
Time (years) Time (yeors)

LEFTABUTMENT RIGHT ABUTMENT


PIEZOMETERS PIEZOMETERS

500 l 300

275 t 275

upstredm from
._250 ¢~ ~_250 ¢
b grout curtain
E upstream from E
grout curtain
E ~J J
_~ 225 ¢ o~ ~ 225 ~o
,:1)
~ 200 ~ .... downstream 3 E 200 downstream E o

175 upstream ~ 175 I ...... ~upstream ~ -- "o


Co
E ¢~ downstream E
o o
downstream
150
_oo
~g
Ro
125 ~25

100 100 1-r-.~. i i , , , T-r-r ~ i ~FT~--T-r--~., i ,


236 244 252 260 268 276 284 236 244 252 260 268 276 284
Reservoir level (m) Reservoir level ( m)

Fig. 6. Measurements of water levels in boreholes and water flow in tunnels versus time, and trends of piezometer measurements in
the left and right abutments versus reservoir level.
E.C. Kalkani / Engineering Geology 46 (1997) 93-104 103

flow rate is lower at the left bank diversion tunnel MEASUREMENTS FOR
RESEr4VOIRLEVELAT275.51 m
and access tunnel. The left and right abutment
drain tunnels give equivalent rates of water flow, 280 -
which comes from drain holes downstream from UIS = Upstream from Grout Curtoin
DIS = Downstream from Grout Curtain
the grout curtains in the abutments.
260- u/~ \ GIC = On Grout Curtain
The plotting of the boundaries of the measure-
\ RA = I~ght Abutment
ments (maximum and minimum upstream and x k,~ LA = Left Abutment
downstream from the grout curtains at the abut- ,,_,,240 \ ~ MC = Middle Conglomerate
G/C ~ LC = Lower Conglomerate
ments) versus reservoir levels for the middle and E
lower conglomerate is shown in the bottom left
220
and right parts of Fig. 6, for the left and right GIC ~ , ~ M C
E
abutments, respectively. The reservoir, during its
30 years of operation, has never reached the maxi- 200-
DIS ~, - - LA/MC
0
mum levels of the design. The range of piezometer q3 u~IS
measurements expected can be extrapolated from
18o
Fig. 6 (bottom), for increases in reservoir levels to
an elevation of 282 and 284 m. GIC ~ ~~_RAILC
To indicate the effectiveness of the grout curtains 160 DIS ~,
at the right and left abutments, the 64 piezometer DIS ~ I.AILC
measurements and the nine water level measure-
140 i i i f i i i i i i ~ i ~ , I i ; I i I i i i I i

ments for the year 1991, for the separate cases of 0 5 10 15 20 25


the right and left abutments and at the middle and Number of measurements
the lower conglomerate, were put in order of Fig. 7. Measurements at the piezometers and boreholes in the
magnitude from higher to lower values and plotted middle and lower conglomerate, at the left and fight abutments
as shown in Fig. 7. (measurements corresponding to 1991, and reservoir level of
To control the erosion due to leakage within the 275.51 m).
middle and lower conglomerate (with a flow of
more than 2 1 s- 1), water is also tested for sediment drop 20-30 m, while at the lower conglomerate
and solubles. the variation of piezometric levels is small com-
pared with that of the reservoir where drops of
piezometric measurements of 20-40 m are present.
7. Evaluation of measurements At the left abutment and at the middle conglom-
erate, the piezometric levels downstream from the
The behaviour of the abutments of the dam adits C and F are 20-30 m lower, which results in
with a reservoir level at an elevation of 275.51 m a drop in the seepage flow under the downstream
is satisfactory, and the same is expected for a shell of the dam, while at the lower conglomerate,
reservoir level of up to 282 and 284 m, since the a drop in piezometric level is present at acceptable
seepage occurs through high strength conglomer- levels due to the drain curtain from the diversion
ate. The drainage of the middle conglomerate at tunnel.
the right abutment and at the region of the adit Leakages at the left and right abutments are no
G, as well as the drainage of the left abutment at longer present since the drain curtains drain the
the region of the adit C, has to be taken care of conglomerate layers. The middle conglomerate at
in the future. the left bank is drained from drain holes made
More specifically, at the right abutment and at from the diversion tunnel. The increasing of the
the middle conglomerate, although most piezome- reservoir level has had, as a result, an increase in
ter measurements upstream from the grout curtain the flow from the middle and lower conglomerate,
in adit G correspond to the reservoir level, down- thus lowering the hydrostatic pressure within the
stream from the grout curtain the measurements strata. The leakages are affected directly by the
104 E. C Kalkani Engineering Geology 46 (1997) 93 104

reservoir variation, while increase of leakages with with a reservoir level at an elevation of 275.51 m
time is only present at adit M and the left bank is satisfactory, and the same is expected for a
sulphur flow. reservoir level of up to 284m. Hence, there is
complete control of abutment seepage and the
certainty of the future stability of the dam.
8. Conclusions

The geological conditions of the abutments of Acknowledgment


the Bakoyianni earth dam in Greece, along with
the leakages, the seepage grouting and the evalua- The author wishes to thank Dr. D.
tion of the piezometer measurements are presented. Papaleonardos for useful discussions and the geol-
Early driving of grouting, and drainage adits were ogists of PPC who assisted with explanations.
intended to reach the conglomerate layers in the Also, the author wishes to thank the reviewers of
abutments and create sealing and drainage cur- the paper for their constructive comments.
tains. Two layers of conglomerate (middle and
lower) drain the water downstream from the grout
curtains. References
At the left abutment and at the middle conglom-
erate, piezometric levels are at high values Ebasco Services Inc., 1959. Kremasta HydroelectricProject of
upstream from the adits indicating a considerable the AcheloosRiver Development, in support of an applica-
tion to the Development Loan Fund for Extension of Credit.
drop within the adits, while at the lower conglom-
Report to the Public Power Corporation of Greece, Ebasco
erate a smaller drop is present downstream from Services Inc., New York, 150 pp.
the grout curtains. At the right abutment and at Engineering Consultants, Inc., 1968. Report on Review of
the middle conglomerate the piezometer measure- Abutment Leakages. Report to Public Power Corporation.
ments indicate that grout adits create a consider- Jan. 1968, 105 pp.
Engineering Consultants, Inc., 1974a. Kremasta Project Report,
able pressure drop downstream, while at the lower
Vol. I, Technical Record of Investigation, Authorization,
conglomerate the piezometric levels have lower Design and Construction of Dam and PowerProject. Report
values downstream from the grout curtains. The to the Public Power Corporation. 213 pp.
water flow from adits responds directly to reservoir Engineering Consultants, Inc.. 1974b. Kremasta Project
variation, while increase of leakage with time is Report, Vol. II, Technical Record of Design and Construc-
tion to Control Abutment Leakages. Report to the Public
present only in adit M and at the left bank
Power Corporation, Denver, Colorado, 85 pp.
sulphur flow. Papaleonardos, D., 1993. Bakoyianni Dam, Abutment Behavi-
The behaviour of the abutments of the dam our. Report to the Public PowerCorporation, Athens, 44 pp.

You might also like