Professional Documents
Culture Documents
1b. Jurnal PLTA 1eng - REvisi
1b. Jurnal PLTA 1eng - REvisi
Judul Artikel :
FEASIBILITY AND SENSITIVITY ASSESSMENT OF VARIOUS HEAD FOR MICRO
HYDRO POWER PLANT DESIGN IN JEMBER
Pengusul:
Wiwik Yunarni Widiarti, S.T., M.T., NIDN 0013067001
Ririn Endah Badriani, S.T., M.T., NIDN 0028057202
Nov Dion Fuadillah, NIM 171910301049
Muhammad Abdi Illahi Al'furqoni, NIM 171910301049
FAKULTAS TEKNIK
UNIVERSITAS JEMBER
KEMENTERIAN PENDIDIKAN DAN KEBUDAYAAN
APRIL, 2021
SURAT PERNYATAAN
HIBAH REWORKING SKRIPSI/TESIS MAHASISWA
LP2M UNIVERSITAS JEMBER
Saya menyatakan bahwa semua yang terlibat sebagai penulis telah menyetujui untuk dipublikasikan pada
jurnal yang dimaksud.
N
Kegiatan Mei Juni Juli Agustus
o
1 Survei dan inventarisasi data baru
2 Pengolahan dan analisis
3 Writing + Proof reading
4 Submit and review
Wiwik Yunarni Widiarti1, Ririn Endah Badriani1, .Nov Dion Fuadillah1, Muhammad Abdi Illahi Al Furqoni1
1
Departement of Civil Engineering, Jember University, Jember, Indonesia
Abstract. Provision of a low-cost renewable power generation system is a good alternative in supplying electricity in
various regions. Jember Regency is a mountainous area with abundant water resources that can build a micro hydro-
power plant. The purpose of this study is to assess the financial feasibility of a design with a variety of potential
discharges and head of a micro-hydropower plant (MHP) to provide electrical energy in off-grid managed areas in
villages in Jember District. The development of these 4 cases uses 2 MHP locations with different discharges and
altitudes, and each location is simulated with a variation of the turbine. The performance of four different cases is
simulated through a feasibility and sensitivity analysis to obtain the most optimal design. The parameters of the financial
feasibility analysis used are NPV, BCR, and IRR. Whereas in the sensitivity analysis, the changes that plan are changes
in interest rates, operating life, and river flow discharge. The MHP plan that yields the most benefits is case 4, which has
a large head with a choice of turgo turbines. Financial feasibility obtains NPV = $ 192,089.97; BCR = 2.74; IRR =
21.36%. The sensitivity analysis results in changes in the maximum interest rate are 21.35%, the minimum operational
time for MHP is five years, and the minimum flow rate is 0.062 m 3/s. These results can be used as a reference in
determining the type of turbine.
1. Introduction
Electrical energy is an essential requirement for The availability of discharge and head in the rural
Indonesia, especially for household, agricultural and areas of Jember Regency can provide renewable power
industrial activities. The growing demand for plants through micro-hydro. The first research site is in
electricity in Indonesia, this level of demand the Poreng River in the Rawatamtu sub-watershed,
influences the increasing problems of the government Jember Regency, East Java with latitude -8.539167
to meet the demand for electricity supply because the coordinates and 113,0904167 longitudes (Aldio,
dependence of community activities on electrical 2021). The second site is in the Jamintoro Village
energy is quite significant. (Andriani et al, 2016; Watershed, Sumberbaru Sub-district, Jember District,
Kumar, 2009). Indonesia is estimated to experience an with latitude -8,33064 and longitude 113,214181
increase in electricity demand, amounting to 6.42% per (Santoso, 2021). Based on these two studies, the
year (RUPTL, 2019). provision of a proper micro-hydro is a challenge to
Increasing the need for electrical energy in research.
everyday life is a significant problem now and in the Several studies examining feasibility have been
future. Therefore, it is necessary to use energy conducted. Based on the feasibility analysis conducted
resources, especially renewable energy sources, by Nair (2016) in Pulau Tioman, Malaysia, the optimal
because of their high potential, micro-hydropower mini hydro design can save costs, efficiency,
plants (National Information System for Energy, operations, and capacity factors by simulating planning
2016). Micro hydro-power plants (MHP) are electricity through the various turbines used. From this study, the
generators from alternative energy that is NPV generated was $ 612.106 and a payback period of
environmentally friendly by utilizing river discharge 10.8 years in the construction of a micro hydro-power
velocities with a certain height with a generating plant on Tioman Island, Malaysia. Based on the results
capacity ranging from 5 kW to 100 kW (Morales et al. of the NPV, planning at the location using a Pelton
2015; Hussein et al., 2010). The relationship between turbine is the turbine that produces the most electrical
power, discharge, and headwater is directly power. Andriani (2016) conducted a study on the
proportional. The greater the velocity and the higher analysis of costs and benefits of MHP in Tanjung Tiga
the flow will, the greater the electrical energy watershed with the results of the research, namely, the
generated from the MHP (Garg, 2005; Hosseini et al, benefits obtained were $ 23.105 for 12 years and six
2008). With the availability of discharge data, the months. The amount of costs that villagers must pay
selection of the head according to the planned for electrical energy sources that do not come from
discharge can be made in accordance with the MHP is $ 50.506. The discharge from the Enim
availability of the existing flow. watershed can still be used for MHP in the next few
years until the source of electrical energy is replaced After analyzing the costs required based on the 4
by the state electricity company. cases, then doing a cost flow analysis to determine
This research aims to examine the feasibility of how much profit will be obtained when this MHP
planning an MHP financially and analyze the operates per year. The annual yield can be found by
sensitivity with several parameters on the Poreng River calculating the power multiplied by the cost of goods
and the Jamintoro River with different head and sold.
turbine types. A feasibility study with an operational length of
MHP for 15 years can be carried out after knowing the
2. Methodology benefits during the operation of the micro hydro-power
plant (MHP). The four cases will be analyzed based on
2.1 Data and Study Area three parameters: NPV, BCR, and IRR, which then
explores the sensitivity based on changes in interest
Jember Regency is a city with several rivers that can rates, age of MHP, and changes in river flow
be used as micro hydro power plants, for example, the discharge.
Bedadung River and the Jamintoro River. Some of
these river flow coastal communities take advantage of 2.2.1 Financial Analysis
the large river flow discharge to irrigate agricultural
land and daily life from the weirs that have been built A feasibility study with an operational length of a
along the river (Hidayah et al., 2017). micro hydro-power plant for 15 years can be carried
Case 1 and case 2 are located on the Poreng River out after knowing the benefits during the operation of
in the Rawatamtu sub-watershed in Jember District, the MHP. The four cases will be analyzed based on
East Java, with latitude -8,539167 coordinates and three parameters: NPV, BCR, and IRR, which then
longitude 113,0904167. The river has a discharge of explores the sensitivity based on changes in interest
0,897 m3/s and has a fairly low head elevation of 5,54 rates, age of MHP, and changes in river flow
m (Aldio, 2021). discharge.
In case 3 and case 4, the location used is the
Jamintoro river in Jember District with an area of 1. Costflow (CF)
707,035 Ha at the coordinates of latitude -8,33064 and There are 4 (four) main tasks for PLTMH construction
longitude 113,214181. This river has a discharge of that must be completed: civil works, mechanical
0,158 m3/s and a significant head elevation of 59,19 m works, electrical works, and network works for
(Santoso, 2021). interconnection access. These four main tasks
determine the number of investment costs or cost flow
2.2 Method (CF), which consists of 4 (four) costs, namely the cost
of procurement of goods (B1), civil building costs
In this study, the first step in analyzing the feasibility (B2), operational costs (B3), and transportation costs
of planning a micro hydro-power plant (MHP) is to (B4). Mathematically, cost flow (CF) can be expressed
calculate the annual energy production released by an in equations (2) and (3) as follows (NVE, 2016):
MHP. The annual energy produced by a micro hydro-
power plant can be calculated by the amount of
CF 0 =B 1+ B 2+ B 3+ B 4 (2)
electricity generated (kW) and the time required (T) CF=CF 0 +Tax 10 % (3)
for one year (8760 hours), which is deducted first
assuming 24 days of maintenance per year (576 hours). with CF0 is the cost flow before tax and CF is the cost
In theory, we can use equation (1) as follows (Harvey flow after tax. The tax used is 10% of the total planned
et al., 1993): budget.
Table 1. All Case of Micro Hydro Powerplant Design 3.2 Power of Various Case
Discharge Head
Case Location Turbine
(m3/s) (m) The micro hydro-power plant operates continuously in
1 Poreng River Crossflow 0,897 5,54 one year (8760 hours), but in one year, it will be rested
2 Poreng River Kaplan 0,897 5,54
for two days in one month for maintenance so that in
3 Jamintoro River Pelton 0,158 59,19
4 Jamintoro River Turgo 0,158 59,19
one year, it takes about 576 hours to make repairs.
Therefore, equation (1) can be seen in the calculations
in table (2) below.
The case is planned to determine which plan has the
most potential to generate the most optimal profit. The
Based on table 2, it can be seen that case 1 produces According to the calculation results in table 3, there
energy of 321303,84 kWh, case 2 has the energy of are differences in costs in each case required based on
343457,93 kWh, case 3 is 613652.69 kWh, and case 4 the MHP planning design. The most significant
produces a power of 645251,11 kWh. The calculation funding of the four cases is in case 3, planning at $
of energy per year generated by each plan will be used 124.582,91, while case 1 is the MHP plan with the
to calculate the benefits obtained during the one year smallest cost of $ 107.339,97.
the MHP operates.
2. Cash In Flow
3.3 Cost and Benefit of Different Case The cost of goods sold (COGS) of electrical energy
used is the cost of electric power sales based on off-
1. Cost Flow grid management, which is $ 0,048. Thus, the price per
The construction of the micro-hydropower plant in the kWh is obtained as follows:
Poreng River and the Jamintoro River is estimated to
cost money, which can be seen in the following Table 4. Cash In Flow
detailed information: Case
COGS E CIF
($/kWh) (kWh) ($)
Table 3. Investment Costs 1 0,048 321303,84 15.428,22
CF0 Tax 10% CF 2 0,048 343457,928 16.492,01
Case 3 0,048 613652,688 29.466,09
($) ($) ($)
4 0,048 645251,112 30.983,38
1 97.581,79 9.758,17 107.339,97
2 99.331,99 9.933,19 109.265,19
3 113.257,19 11.325,72 124.582,91 From the results in table 4, case 1 can generate annual
4 112.215,93 11.221,59 123.437,52 profit of $ 15.428,22; case 2 for $ 16.492,01; case 3
for $ 29.466; and in case 4, it made a profit of $
30.983,38. The calculation of profit per year shows
that case 4 has the most advantage compared to other incurred by present value, which is negative. Equation
cases. (7) is used to find out how many BCR values are
generated in each case that has been designed in table
3. Annual Cash In Flow 7 below:
For the approach to determining the Annual Cash In
Flow, expenditures consist of operational costs, Table 7. Benefit-Cost Ratio
maintenance, and taxes, which are assumed to be 10% Cost Benefit
Case BCR Feasibility
of total annual revenue. Annual cash in flow can be ($) ($)
calculated using equation (5) in table 5 as follows: 1 130.482,31 231,423.35 1,77 Feasible
2 134.003,21 247.380,12 1,85 Feasible
Table 5. Annual Cash In Flow 3 168.782,06 441.991,48 2,62 Feasible
Maintenance 4 169.912,58 464.750,66 2,74 Feasible
Annual Cash
CIF and
Case In Flow
($) Operation The calculations in table 7 show that the investment
($)
($)
funds used in these four cases are smaller than the
1 15.428,22 1.542,82 13.885,40
2 16.492,01 1.649,20 14.842,81
benefits, so that the value of the benefit-cost ratio
3 29.466,09 2.946,61 26.519,49 (BCR) in case 1 is 1,77, case 2 is 1,85, case 3 of 2,62
4 30.983,38 3.098,34 27.885,04 and case 4 of 2,74. This value can be interpreted that
the MHP project implemented according to the present
Based on table 5, it can be seen that after calculating value is feasible to be developed.
the annual cash in flow, it is found that the case that
produces the most net profit is case 4 using a turgo 3. Internal Rate of Return (IRR)
turbine at the location of the Jamintoro river. Case 4 The internal rate of return (IRR) is the internal interest
resulted in a net profit of $ 27.885,04. The results of rate that shows the project's ability to generate profits.
the four cases will then be analyzed based on the The basis of the IRR value is the same as the interest
feasibility of the NPV, BCR, and IRR. rate, which makes the NPV value equal to zero. If the
IRR is greater than the current interest rate, the project
3.4 Feasibility of Financial is viable. Equation (8) is used to analyze the feasibility
based on the IRR, which can be seen in Table 8 below:
1. Net Present Value
Net present value (NPV) is defined as the present Table 8. Internal Rate of Return
value of the net income that will be obtained in the Annual Cash In Flow IRR
Case Feasibility
($) (%)
future if the money is valued now. The operational
1 13.885,40 9,73% Feasible
length of the MHP is assumed to be 15 years. By using
2 14.842,81 10,59% Feasible
equation (6), the feasibility analysis based on the NPV 3 26.519,49 19,89% Feasible
in the four cases can be seen in Table 6 below: 4 27.885,04 21,36% Feasible
Table 6. Net Present Value The calculation results in Table 8 show that the IRR
Annual Cash In
Cas NPV values of the four cases were 9,73%, 10,59%, 19,89%,
Flow Feasibility
e
($)
($) and 21,36%, respectively. By looking at the value of
1 13.885,40 49.777,45 Feasible the IRR, it means that the project can generate profits.
2 14.842,81 58.685,56 Feasible Therefore, the project can be said to be economically
3 26.519,49 175.492,96 Feasible feasible.
4 27.885,04 192.089,97 Feasible
3.5 Sensitivity analysis
Based on the results of the calculation with the
prevailing interest rate in Indonesia, namely 3,75%, Sensitivity analysis is an analysis conducted to
the NPV value in case 1 is $ 49.777,45; case 2 for $ determine the effect of changes in production
58.685,56; case 3 for $ 175.492,96; and case 4 for $ parameters on changes in the performance of the
192.089,97. If viewed with the NPV parameter, the production system in generating profits. Sensitivity is
four cases are feasible to be implemented for 15 years analyzed based on different parameters, namely
because they produce a value of more than 0. changes in interest rates, age changes, and discharge
changes. The results of the sensitivity analysis will be
2. Benefit-Cost Ratio (BCR) shown in Tables 9, 10, 11, and Figure 1 as follows:
The benefit-cost ratio (BCR) is defined as the ratio of
present value net income, which is positive with costs
$300,000
$200,000
Net Present Value
$100,000
$-
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
$-100,000
$-200,000
Year
Table 10. Sensitivity analysis based on changes in Poreng River flow rate
Net Present Value
Head Discharge min.
Case Turbine Discharge (0,89 m3/s) Discharge (0,69 m3/s) Discharge (0,49 m3/s)
(m) (m3/s)
($) ($) ($)
1 Crossflow 5,54 49.777,45 13.518,29 -21.513,09 0,613
2 Kaplan 5,54 58.685,56 19.928,12 -17.519,22 0,584
Table 11. Sensitivity analysis based on changes in Jamintoro River flow rate
Net Present Value
Head Discharge min.
Case Turbine Discharge (0,158 m3/s) Discharge (0,098 m3/s) Discharge = 0,038 m3/s
(m) (m3/s)
($) ($) ($)
1 Pelton 59,19 175.492,96 58.678,54 -53.522,35 0,066
2 Turgo 59,19 192.089,97 72.462,65 -47.476,23 0,062
Poreng River
80,000
60,000
Net Present Value ($)
(40,000)
(60,000)
Discharge (m3/s)
Jamintoro River
250,000
Net Present Value ($)
200,000
f(x) = 1993234.28571429 x − 123031.96952381 Pelton
150,000 f(x)
R² = =0.999998344927313
1899604.28571429 x − 127147.762857143
R² = 0.999600228555038 Linear (Pelton)
100,000 Turgo
50,000 Linear (Turgo)
-
0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18
(50,000)
Discharge (m3/s)
From Table 8, it can be seen that the sensitivity to operation of the micro hydro power plant is 5 years
changes in interest rate values, changes in the and the minimum river flow rate is 0,062 m 3/s. Based
maximum interest rate that occurs in each planned case on these results, a MHP plan was chosen in case 4,
are 9,71%; 10,57%; 19,88%; and 21,35%, respectively. which has a head elevation of 59,19 m. This shows
Figure 2 describes the minimum age for a micro- that the head elevation is very important to be used as
hydropower plant based on the four cases carried out an indicator in selecting the MHP location.
with a minimum length of time consecutively ten Several opportunities for the development of
years, nine years, six years, and five years. Tables 10 micro-hydropower plants exist in Indonesia. If the
and 11 show the minimum discharge so that the four MHP design can be appropriately realized, it will give
cases are able to generate profits. The minimum good results in the production and benefits of
discharge required is in case 1 of 0,613 m 3/s; case 2 of renewable energy. The community is expected to pay
0,584 m3/s; case 3 amounting to 0,066 m 3/s; and case 4 attention to the environment, especially forest
of 0,062 m3/s. Figure 3 explains that the ability of maintenance, to protect watersheds that are water
MHP to generate profits is greatly influenced by sources, and forests play a crucial role in supporting
discharge. The greater the river's discharge, the greater the availability of water sources. Supervision and
the energy produced so that the profits obtained from assistance from the technical implementing
the sale of electrical energy will be greater. departments of the Ministry of Energy and Mineral
Based on the three parameters of the sensitivity Resources (ESDM) of the provincial and regional
analysis, it can be concluded that the MHP planning in governments are urgently needed to realize sustainable
case 4 has the best results compared to the three cases MHP development.
that have been designed so that case 4 is the most
appropriate for changes in interest rates, age of MHP References
and river flow discharge.
Harvey, A. et.al. (1993), “Micro-Hydro Design Manual.
4. Conclusion A guide to small-scale water power schemes”.
Intermediate Technology Publications, ISBN 1
The comparison of the 4 cases can provide guidance 85339 103 4.
and illustrate the determination of the optimal MHP Andriani, Y, et al. (2016). “Benefits and Costs Analysis
design based on the availability of discharge and head.
of Micro Hydro Electric Power Generation of
From the analysis used based on NPV, BCR, and IRR
Enim Watershed Tanjung Tiga for Sustainable
in the 15th year with an interest rate of 3.75%, it can
be concluded that the four micro-hydro power plant Development”. In OIDA International Journal of
cases are feasible. But the results show that case 4 is Sustainable Development.
the most profitable design, with a power output of Garg, S. K. (2005). “Irrigation Engineering and
78,84 kW and a cost of $ 123.437,52. Based on the Hydraulic Structures, 19th ed”. Khanna
financial feasibility and sensitivity analysis, case 4 Publishers: New Delhi, India. p. 1175.
yielded a feasibility value based on the NPV is $ Hosseini, S. M. H., Forouzbakhsh, F., Fotouhi, M., and
192.089,97; BCR is 2,74; The IRR is 21,36% and the Vakilian, M. (2008). “Determination of
sensitivity is based on changes in the maximum installation capacity in reservoir hydro-power
interest rate of 21,35%, the minimum length of
plants considering technical, economical and Available online:
reliability indices. Electr. Power Energy Syst”. http://195.251.42.2/cgi-bin/nisehist.sh?
pp. 393–402. [CrossRef]. objtype=xartes (accessed on 16 April 2021).
Hidayah, E., Indarto, and Sri Wahyuni. (2017). NVA. (2016). “Cost Base for Small Hydropower Plants
“Proposed Method to Determine the Potential in Georgia < 13 Megawatt”.
Location of Hydropower Plant: Application at Pratama, A. (2020). “Design of a Micro Hydro Power
Rawatamtu Watershed, East Java”. In Procedia Plant (MHP) in the Jompo Tributary (Rawatamtu
Engineering. Sub-watershed)”.
I. Hussein and N. Raman, (2010). “Reconnaissance Rejekiningrum, P., & Krido S. S. (2015). “Financial
studies of micro hydro potential in Malaysia”. In Feasibility Analysis for Development Of Solar
Proceedings of the International Conference on Power Automatic Irrigation with Disc Irrigation
Energy and Sustainable Development: Issues and System in West Nusa Tenggara”. In Irrigation
Strategies (ESD ’10), pp. 1–10. Journal. pp. 125-136.
IRENA. (2012). “Renewable Energy Technologies: RUPTL PLN. (2019). “Electricity Supply Business
Cost Analysis Series”. In International Renewable Plan”. pp. 1–735.
Energy Agency. Vol. 1. Issue 3/5. Santoso, Muhammad. (2021). “Planning for a Micro
Khan, M.Y. (1999). “Theory & Problems in Financial Hydro Power Plant (PLTMH) in Jamintoro
Management”. Boston: McGraw Hill Higher Village, Sumberbaru Sub-district, Jember
Education. District”.
Krieger, T., Martig, D. S., van den Brink, E., & Berger, Shively, Gerald. (2012). “An Overview of Benefit-Cost
T. (2016). “Working on self-compassion online: A Analysis”.
proof of concept and feasibility study”. Internet
Interventions, 6, 64-70.
Kumar, A., Mohanty, P., Palit, D., and Chaurey, A.
(2009). “Approach for Standardization of Off-
Grid Electrification Projects”. Renewable and
Sustainable Energy Reviews 13 1946-56
Liaquat, A. M., Kalam, M. A., Masjuki, H. H., & Jayed,
M. H. (2010). “Potential emissions reduction in
road transport sector using biofuel in developing
countries”. Atmospheric Environment, 44(32),
3869-3877.
Mbaka, John Gichimu, and Mercy Mwaniki. (2017).
“Small Hydro-Power Plants in Kenya : A Review
of Status , Challenges and Journal of Renewable”.
Journal of Renewable Energy and Environment
3(September 2017): 20–26.
Morales, Sergio et al. (2015). “An Overview of Small
Hydropower Plants in Colombia: Status, Potential,
Barriers and Perspectives”. Renewable and
Sustainable Energy Reviews.
Moten, J. and C. Thron. (2013). “Improvements on
Secant Method for Estimating Internal Rate of
Return, International Journal of Applied
Mathematics and Statistics”. 42:12,
http://www.ceser.in/ceserp/index.php/ijamas/articl
e/view/1929.
Mukherjee, M. & Roy, S. (2017). “Feasibility Studies
and Important Aspect of Project Management”.
International Journal of Advanced Engineering
and Management. Vol. 2. No. 4, pp. 98-100.
Nair, Pratap & Nithiyananthan. (2016). “Feasibility
Analysis Model for Mini Hydropower Plant in
Tioman Island, Malaysia”.
National Information System for Energy, Greece.
Daftar Artikel Terbit& Under Review
di Jurnal/Prosiding sd 24 April 2021
a.n Wiwik Yunarni Widiarti, dkk
Nama Dosen Lain Yang terlibat:
Ririn Endah Badriani
Retno Utami Agung Wiyono
Entin Hidayah
Gusfan Halik