Professional Documents
Culture Documents
Chapter 10:
Short-term decision
2
Relevant costs
Outsourcing decision
Further processing
3
Short-term decision
The importance of relevant cost
Select among
different
options
Whether to
do or not to
do something
4
Short-term decision
Definition
In the INCREMENTAL
CASH only AVOIDABLE
FUTURE only
Short-term decision
Relevant cost of labour
Relevant cost of
labour
Labour is fully
Work can be done in Labour is fully employed and no
idle time required further labour is
available
To hire additional
Overtime payment
labour
6
Short-term decision
Relevant cost of labour - Example
Require: What is the relevant cost of the labour hours required for
manufacture of the new product?
7
Short-term decision
Relevant cost of labour - Example
Unskilled – 12,000 hours are required for the project and the
company is prepared to hire more staff to meet this need. The
incremental cash outflow of this decision is (12,000 hours x $8) =
$96,000.
Short-term decision
Relevant cost of labour - Example
The temptation is to see that the same number of skilled
employees are paid before and after being moved to the new
project and therefore the opportunity cost of contribution foregone
from diverting hours away from the existing production of Product
X is the only relevant cost ($24/4 hours = $6 per hour). This is
incorrect.
Short-term decision
Relevant cost of material
In warehouse?
No Yes
Yes
Replacement cost Use regularly?
No
Higher of value in
Scrap/ disposal other use or scrap
value value (If there are
(If no other use) other uses)
10
Short-term decision
Relevant cost of material - Example
Short-term decision
Relevant cost of material - Example
Short-term decision
Relevant cost of material - Example
Short-term decision
Relevant cost of machinery
Cost of machinery
Short-term decision
Relevant cost of machinery - Example
Some years ago, a company bought a piece of machinery for
$300,000. The net book value of the machine is currently $50,000.
The company could spend $100,000 on updating the machine and
the products subsequently made on it could generate a
contribution of $150,000. The machine would be depreciated at
$25,000 per annum. Alternatively, if the machine is not updated,
the company could sell it now for $75,000.
On a relevant cost basis, should the company update and use the
machine or sell it now?
15
Short-term decision
Relevant cost of machinery - Example
Short-term decision
Some types of decision making using relevant cost
2 Outsourcing decision
4 Further processing
17
Short-term decision
Make or buy
Or
Make Buy
Construction company
Or Subcontract the work
should do some work
to another company
with its own employees
Service should be
Or Employ external
carried out by an
organisation
internal department
18
Short-term decision
Make or buy
Make or buy
Scare resources?
No Yes
The relevant costs are the The relevant costs are the
differential costs between differential costs between
the two options the two options
Consider Consider
Quality of bought in
product
Reliability of supplier
Units bought have the lowest
Possibility of becoming
extra variable cost of buying per
dependent on supplier
unit of scarce resource saved by
Likelihood of future price
buying
increases
How to use spare capacity
Confidentiality issues
19
Short-term decision
Make or buy
Resource
is scare? Make Buy
Short-term decision
Outsourcing/Contract manufacturing/Subcontracting.
Operating of internal Or
Use external services
service departments
Advantage
Disadvantages
Superior quality
and efficiency Reliability of
Capital is freed up supplier
Greater capacity Loss of control and
and flexibility to flexibility
cope with changes Effect on existing
in demand workforce
Useful if not
enough work to
keep internal staff
fully occupied
Example
December 2014
A business makes two components which it uses to produce one of
its products. Details are
Component A Component B
Per unit information: $ $
Buy in price 14 17
Material 2 5
Labour 4 6
Variable overheads 6 7
General fixed overheads 4 3
Total absorption cost 16 21
The business wishes to maximise contribution and is considering
whether to continue making the components internally or buy in
from outside.
Which components should the company buy in from outside in
order to maximise its contribution?
A. A only B. B only
Example
December 2014
Which components should the company buy in from outside in
order to maximise its contribution?
A. A only B. B only
Short-term decision
Shut down decision
Or
Shutdown Continue
Consider
Permanent Timing Temporary
Financial Non-financial
Short-term decision
Shut down decision – Example
Short-term decision
Shut down decision – Example
Short-term decision
Shut down decision – Example
Note that the $2m total profit is the same as the profit of $6m from
Production Line A and the loss of $4m from Production Line B as
shown in the table at the start of this example.
If either production line were closed down, fixed costs saved are
25% x $24m = $6m, however the contribution lost from the
products (and contribution looks at cash flows caused by
production) would be either $16m or $10m, which exceed the cash
saved on the fixed costs.
27
Short-term decision
Further processing decision
Raw
material
Product A
Product B (higher
Sell immediately
price than Product A)
Short-term decision
Further processing decision – Example
Short-term decision
Further processing decision – Example
Short-term decision
Further processing decision – Example
Example
December 2016
Jorioz Co makes joint products X and Y. $120,000 joint processing
costs are incurred.
At the split-off point, 10,000 units of X and 9,000 units of Y are
produced, with selling prices of $1.20 for X and $1.50 for Y.
Example
December 2016