Project Risk

Management Overview

11.1 Plan 11.3 Perform 11.4 Perform


11.2 Identify Risks
Risk Management Qualitative Risk Analysis Quantitative Risk Analysis
.1 Inputs .1 Inputs .1 Inputs .1 Inputs
.1 Project charter .1 Project management plan .1 Project management plan .1 Project management plan
.2 Project management plan .2 Project documents .2 Project documents .2 Project documents
.3 Project documents .3 Agreements .3 Enterprise environmental .3 Enterprise environmental
.4 Enterprise environmental .4 Procurement factors factors
factors documentation .4 Organizational process .4 Organizational process
.5 Organizational process .5 Enterprise environmental assets assets
assets factors
.2 Tools & Techniques .2 Tools & Techniques
.6 Organizational process
.2 Tools & Techniques .1 Expert judgment .1 Expert judgment
assets
.1 Expert judgment .2 Data gathering .2 Data gathering
.2 Data analysis .2 Tools & Techniques .3 Data analysis .3 Interpersonal and team
.3 Meetings .1 Expert judgment .4 Interpersonal and team skills
.2 Data gathering skills .4 Representations of
.3 Outputs .3 Data analysis .5 Risk categorization uncertainty
.1 Risk management plan .4 Interpersonal and team .6 Data representation .5 Data analysis
skills .7 Meetings
.5 Prompt lists .3 Outputs
.6 Meetings .3 Outputs .1 Project documents
11.5 Plan .1 Project documents updates updates
. 3 Outputs
Risk Responses .1 Risk register
.2 Risk report
1 Inputs
.3 Project documents
.1 Project management plan
.2 Project documents
updates 11.7 Monitor Risks
.3 Enterprise environmental
factors .1 Inputs
.4 Organizational process .1 Project management plan
assets 11.6 Implement .2 Project documents
Risk Responses .3 Work performance data
.2 Tools & Techniques
.4 Work performance reports
.1 Expert judgment .1 Inputs
.2 Data gathering .1 Project management plan .2 Tools & Techniques
.3 Interpersonal and team .2 Project documents .1 Data analysis
skills .3 Organizational process .2 Audits
.4 Strategies for threats assets .3 Meetings
.5 Strategies for opportunities
.2 Tools & Techniques .3 Outputs
.6 Contingent response
.1 Expert judgment .1 Work performance
strategies
.2 Interpersonal and team information
.7 Strategies for overall
skills .2 Change requests
project risk
.3 Project management .3 Project management plan
.8 Data analysis
information system updates
.9 Decision making
.4 Project documents updates
.3 Outputs .3 Outputs .5 Organizational process
.1 Change requests .1 Change requests assets updates
.2 Project management plan .2 Project documents updates
updates
.3 Project documents updates

Figure 11-1. Project Risk Management Overview