1 Open MDT call Integration to perform HC and Backup CV for Site

Call Integration to perform HC and Backup CV for Site

2 Install 2nd SUBRACK


3 Insert 2nd DUW into the expansion (still powered down)
4 Switch �ON� and Format Secondary DUW (NO CABLES CONNECTED). After Format
Switch�OFF� again
5 Do the cabling as shown in the Layout
6 Run the modify script to add the 2nd DUW to the RBS (switch on 2nd DUW if you
see
�waiting for start up of board� in the Modify-Wizzard

Note: If script loading is taking too much time (more than 10 mins) you
need to switch �OFF� and the switch �ON� again the Secondary DUW
and observe if the script loading will continue

7 If already finished with script loading, check the status of the 2nd DUW with
EMAS (needs to be enabled)
8 Check the status of the 2nd DUW with MOSHELL using �cab�
With the command �cab� you see that the 2nd DUW is in synch status. (Need to
restart cabinet if 2nd DUW is not showing on moshell)
9 Wait until the synch status of the 2nd DUW is �StandbyReady�

10 Verify with Integration Team for the Status of 2nd DUW


Create a CV (Ex. After_DUW_sync )
11 Start upgrading to R3M02
12 Export and Delete the Configuration.
13 Load the Cabinet and Site with 3rd Carrier Configuration