•Create the following (E.P.

S)

Test Company

Saudi Arabia Egypt

Industrial Residential Residential


Industrial
Projects Projects Projects
Projects

Jeddah Al-Khobar Riyadh Sharm


Cairo Alex
El-Sheikh

Project of Riyadh Project of Cairo


Residence Residence
Building (EPS)
1-Click enterprise tab in the menu bar and select
the enterprise project structure.
Building (EPS)
2- click add on the command bar to add new EPS.
Building (EPS)
3- use the arrow tabs to optimize the new EPS in
the hierarchy.
Building (EPS)
4- add nodes and completely EPS.
Organizational break down structure (OBS)

OBS element are assigned as responsible


manager for work within an EPS elements,
project, Work break down structure.
Genral Manager
(Eng/Atef)

Manager for Saudi Arabia Projects


Manager for Egypt projects (Eng/Ahmed)
(Eng/Mohamed)

Manager of Industerial Manager of Residential Manager of Industeria Manager of Residential


Projects (Eng/Abdallah) Projects (Eng/alaa) Projects (Eng/Ayman) Projects (Eng/Ashraf)

Manager of Manager of Manager of Manager of


Manager of Alex Manager of
Jeddah Area Al-Khobar Area Riyadh Area Cairo Area Area (Eng/Waleed) Sharm El-Sheikh Area
(Eng/mahmoud) (Eng/yasser) (Eng/Hassan)
(Eng/Moustafa) (Eng/Adel)

Manager of Project Manager of Project Manager of Project


Riyadh Residence Riyadh Residence Riyadh Residence
(Eng/Islam) (Eng/Hany) (Eng/Islam
Building (OBS)
1-Click enterprise tab in the menu bar and select
the OBS.
Building (OBS)
2- click add on the command bar to add new OBS, and use
arrows to optimize the new OBS in the hierarchy.
Building (OBS)
3- click the enterprise tab in the menu bar and select the
enterprise project structure and select the responsible manger
for EPS.
calendars.
Calendar is used for scheduling activities, and activity
type determines whether the activity uses the calendar
of the assigned resource or activity calendar.
Types of calendars.
1- Global: contains calendars that can be used by all
projects, available for all resources and activities.

2- Project: contains separate pool of calendars for each


project in the EPS, available for current project only.

3- Resource: contains separate calendar for each


resource.
Creating Calendar.
1-Click enterprise tab in the menu bar and select Calendars.
Creating Calendar.
2-Cick add to add new calendar in global window, and select
calendar to copy from then rename it.
Creating Calendar.
3-Cick Modify button then work week button, and nonwork
button to adjust working days.
Creating Calendar.
4-Select project window, then click add, then select the
calendar of project and rename it with the project name.