Exercise 2
Setting up Resources
2019-2020
Contents of this document are based on material in Microsoft Project 2016: Step-by-Step by C. Chatfield and T. Johnson
1
For use by ME4103 only. Not for distribution.
Note: Depending on how the date format of your PC is set up, the date shown in the figures in this
document may appear different from what you see on your PC, e.g., Tue 06-02-18 instead of Tue
06/02/18.
File template required in this exercise is provided on LumiNUS. Please download a copy to the
local PC and use it for this exercise.
2
For use by ME4103 only. Not for distribution.
1. On the View tab, in the Resource Views group, click Resource Sheet to display the layout
shown below.
3
For use by ME4103 only. Not for distribution.
2) On the Resource tab, in the Insert group, click Add Resources, then click Work
Resource.
Project inserts a new row with the name <New Resource> in the Resource Name
column, and renumbers the subsequent resources.
3) With <New Resource> selected, enter Jun Cao and then press the Enter key.
4) Repeat 2) and 3) to enter the names shown in the figure below. When you finish
entering all the names, the task list should appear as shown below.
4
For use by ME4103 only. Not for distribution.
After customizing the Max Units values for the two resources, the Resource Sheet
should appear as shown below.
5
For use by ME4103 only. Not for distribution.
1. Enter the following pay rates in the Standard (Std.) Rate field.
1) On the View tab, in the Resource Views group, click Resource Sheet.
2) In the Resource Sheet view, click the Std. Rate column for Jun Cao, and enter
42.00/hour.
3) Repeat 1) and 2) but enter, in Std. Rate column, 1100/week for Sharon Salacaria,
2700/week for Toby Nixon, 55/hour for Zac Woodall, and 45/hour for Copyeditors. Do
not change the entry in the Std. Rate column for Toni Poe because he is the book
author.
6
For use by ME4103 only. Not for distribution.
The Resource Sheet should appear as shown below after pay rates are entered.
1. Make January 26, 2018 a nonworking time calendar exception for Toby Nixon. Name the
exception Toby attending a conference.
1) Click on Toby Nixon under the Resource Name column. On the Project tab, in the
Properties group, click Change Working Time.
The dialog box as shown below should appear. Note that the calendar year and month
displayed may be different from that shown in the figure below.
7
For use by ME4103 only. Not for distribution.
2) In the cell For calendar (at the top of the dialog box), select Toby Nixon (if it is not
already shown). On the Exceptions tab, click the first cell in the Name column and enter
Toby attending a conference. Set the value for “Start” as January 26 2018 and the value
for “Finish” also as January 26 2018.
3) Double click on the text Toby attending a conference (under the Name column in the
Change Working Time dialog box) to bring up the Details for ‘Toby attending a
conference’ dialog box. Select the radio button for Nonworking.
4) Click OK in the Details for ‘Toby attending a conference’ dialog box, and click OK in the
Change Working Time dialog box.
8
For use by ME4103 only. Not for distribution.
2. For Jun Cao, change the default work week to a “4-by-10” weekly work schedule (that is, 4
days per week, 10 hours per day Monday through Thursday, with Friday off). On the days
that Jun Cao works, she will work from 8:00 AM to 7:00 PM with the noon hour off for lunch.
1) On the Project tab, in the Properties group, click Change Working Time.
2) Select Jun Cao in the For calendar cell. Note that the calendar year and month displayed
may be different from those shown in the figure below.
5) A Details for ‘[Default]’ dialog box appears. Under Selected Day(s), select Monday
through Thursday (using the Shift-Click combination).
9
For use by ME4103 only. Not for distribution.
6) To set working times that differ from the base calendar, click the Set day(s) to these
specific working times radio button. In the From and To columns, enter the working
times as shown in the figure below – note the “7:00 PM” in the To column. Click OK to
exit each dialog box.
7) To set Friday as a non-working day for Jun Cao, return to the Details for ‘[Default]’
dialog box. Select Friday under the Select day(s) heading, and select the Set days to non-
working time radio box.
10
For use by ME4103 only. Not for distribution.
2) In the Resource Sheet view, click the (empty) cell under Copyeditors in the Resource
Name column.
3) On the Resource tab, in the Insert group, click Add Resources, then click Cost Resource.
Project inserts a row for the new cost resource, with the name: <New Resource>.
11
For use by ME4103 only. Not for distribution.
4) With <New Resource > selected, enter Travel then press the Enter key. The cost
resources should appear as shown in the Resource Sheet below.
4) In the Notes box, enter Toby worked on launch campaigns for Toni Poe’s previous two
books.
12
For use by ME4103 only. Not for distribution.
2. Use the Resource Form to add this note for Sharon Salavaria: Sharon’s standard pay rate is
adjusted for her half-time work schedule.
1) On the View tab, in the Resource Views group, click Resource Sheet.
2) On the Resource tab, in the Properties group, click the Details button.
Click Sharon Salavaria in the Resource Name column. The Resource Form displayed in
the lower pane appears as shown below.
3) Click anywhere in the Resource Form view. This switch Windows’ focus to the Resource
Form pane. The label of the Format tab (as part of the main menu at the top of the
overall Project window) changes to Resource Form Tools.
13
For use by ME4103 only. Not for distribution.
5) Enter “Sharon’s standard pay rate is adjusted for her half-time work schedule.” in the
note box.
The two methods (for entering notes in the project plan) described above are essentially equivalent.
Use the “Save As” option to save a copy of the Project file that you have been working on for this
exercise. Make sure to use your Student Number as the file name, i.e.,
XXXXXXXXX.mpp
Upload the saved file into the folder Exercise 2 submission under the “Files” section of the ME4103
module page on LumiNUS.