Ajman Warehouse Project

Activities Duration Start date Finish date


SUB STRUCTURE
Sub structure 7 23-Oct-19 30-Oct-19
slab on grade 4 30-Oct-19 3-Nov-19
SUPER STRUCTURE
columns 2 4-Nov-19 6-Nov-19
slabs and beams 5 7-Nov-19 12-Nov-19
Parapet and back proping 8 13-Nov-19 21-Nov-19
FINISHING WORK
Block work 5 23-Nov-19 28-Nov-19
Plaster internal & external 8 29-Nov-19 7-Dec-19
Paint 5 8-Dec-19 13-Dec-19
Floor Finishing work 4 14-Dec-19 18-Dec-19
Doors and counters 4 19-Dec-19 23-Dec-19
External paint 8 14-Dec-19 22-Dec-19
EXTERNAL WORK 12 8-Dec-19 20-Dec-19
MEP FIXTURES 25 30-Nov-19 25-Dec-19
Final Touchup and Hand over 5 26-Dec-19 31-Dec-19