You are on page 1of 4

Production Department

Cement mill & Packing Process Divisio


Cement mill #1 Action plan for Production ma
S/N Activities
Starting Finishing 16-May-22
1 511BM17 1st chamber steel ball discharging 16-May-22 16-May-22
2 Steel ball sorting 16-May-22 20-May-22
3 cleaning both halves of Mill inlet and outlet diaphragm 20-May-22 21-May-22
4 511BF37 & 511BF55 filter bag inspection 17-May-22 21-May-22
5 cement area airslide canvas inspection and replacement 17-May-22 20-May-22
6 Cement silo top diverters 521VV03 ,05 inspection 19-May-22 20-May-22
7 Steel ball charging 21-May-22 22-May-22
8 housekeeping activity 21-May-22 22-May-22
9 511BM17 starting 22-May-22
Department
ng Process Division
or Production maintenance
date
17-May-22 18-May-22 19-May-22 20-May-22 21-May-22 22-May-22
Production Department
Cement mill & Packing Process Division
Cement mill #1 Finding
S/N FINDING
1 511FN57 have vibration and bearing needs replacement
2 MILL Inlet missed lifter plates fixing
3 Central intermediate sieve wornout and needs replacemnt
4 511BF37 Suction duct plate wornout and needs replacement
5 511BF37&55 Pistons and purging system inspections
6 511BE23 Fluid coupling Have oil leakages
7 511BE23 bucket bolts loosen
8 511BE23 & 521BE01BE01 auxillary drive have abnormal sound
9 521VV03 piston needs replacement
10 511BC15 volcanizing point is detaching
11 ALL weight feeders needs calibration
12 511SR29 Fixed vane replacement
Department
M
M
M
M
E&M
M
M
M
E&M
M
E
M

You might also like