Applicability
1. These regulations shall be applicable to the areas under Development Plan within the
jurisdiction of Thane Municipal Corporation sanctioned under the provisions of the
Maharashtra Regional and Town Planning Act, 1966 (hereinafter referred to as “the
said Act”).
2. If the ITP falls within the jurisdiction of more than one authority then in such cases
Government can issue directives at the time of Locational Clearance or at any time
regarding which authority will give permission and supervise the project subject to
terms and conditions as may be specified.
Requirement of Site
1. Any suitable area having area of 40 hectare (100 Acres) or more at one place. The area
shall be one, contiguous, unbroken and uninterrupted.
2. If the Integrated Township area is more than 200 Ha., it can be segregated as long as
each parcel is more than 40 Ha. and is located within a radius of 5 kms. Provided that
the land use mix is maintained in each parcel.
3. The area shall have an access by means of an existing, or proposed road having
minimum width of 18 mt.
Ownership of Land
1. The project proponent shall have the ownership of all the land parcels under project.
(Explanation - for this clause, ownership includes rights accrued vide one or more
registered Development Agreement or Power of Attorney (PoA) for such development
and disposal, on behalf of land owner/owners).
Permission and Declaration of Project by State Government
1. The Project Proponent shall apply to the State Government for obtaining permission
and declaration of such project to be a “Integrated Township Project”. .
2. Every such permission and declaration shall remain in force for a period of two years,
if not applied for Letter of Intent thereafter it shall lapse.
3. Such lapse shall not bar any subsequent application for fresh proposal.
4. The Director of Town Planning, Maharashtra State, on the request of Project
Proponent, by notification in the Official Gazette, may grant to add or delete any area,
not exceeding 50% of the total area under Locational Clearance, subject to condition
that the remaining area shall not be less than 40 Hect.The permissible FSI and other
parameters shall increase or decrease accordingly.
Letter Of Intent by the Collector
1. The Project Proponent shall apply to the Collector for obtaining the Letter of Intent for
such project.
2. The Collector shall verify and satisfy himself that Ownership and Development Rights
of all the lands under project are with the Project Proponent before issuing the Letter
of Intent.
Planning Considerations
1. Permissibility in respect of Zoning
● For the areas falling in zones, other than residential, commercial as per the sanctioned
Development Plan the Project Proponent shall have to pay a premium for permitting project
in such zones at the rates prescribed below.
Permissibility in respect of Zoning
1. Afforestation Zone, Hill Top & Hill Slope Zone as shown on 15%
Development Plan.
1. Garden and Park 5% of Master Layout Area.(out of Out of this at least 1000 sq. mt.
this 50% area may be allowed on area shall be kept open for
Hill Top Hill Slope Zone, Buffer Town Plaza/Town Square, at
Zone of ESZ and within HFL) one place and remaining area
shall be kept open and may be
allowed to be proposed at
suitable places. Major public
amenities / activities shall be
cluster around this area.
Mandatory Town-Level Amenities - Area and FSI Allocations
2. Play Grounds 7.5% of Master Layout Area (may Maximum 10% of area under
be allowed in Buffer Zone of ESZ Play Ground which may
having slope less than 1: 5) accommodate indoor games,
stadiums and allied users only.
Community Health Care Facilities
2. For Master Layout area upto & 1000 sq. m. 10000 sq.m
inclusive of 200 Ha.
3. For Master Layout area more than To be increased proportionately with increase in
200 Ha. Master Layout area and be proposed at one or more
locations, as per requirements.
Public Utilities
S.No Particulars Minimum Area Required Minimum Built-up Area required
1. Fire Brigade 3000 sq.m. or as prescribed by As per recommendations of the Director
Station the Director of Fire Services, of Fire Services, Maharashtra State/Chief
Maharashtra State/ Chief fire fire Officer of the Thane Municipal
Officer of the Thane Municipal Corporation.
Corporation.
The Project Proponent must submit an application to the Municipal Commissioner for an
Occupancy Certificate for buildings in a project, in whole or in part. This application must
include all relevant documents as well as a coloured Google Earth/Bhuvan/Drone survey
image.
General Stipulations
● The Project Proponent shall complete the development of basic infrastructure and
amenities to the satisfaction of the Municipal Commissioner, either for the entire
project or in phases. Amenity Space, inclusive housing as otherwise required by
Development Plan regulations, if any.
● The Project Proponent shall plant indigenous trees at the rate of at least 150 trees per
ha. and maintain it properly.
● It shall be mandatory for the Project Proponent to provide appropriate width of road as
per existing width or as per easement rights to the land not owned by the project
proponent which is surrounded by the Township Area.
Special Concessions
Land designated for non-agricultural (N.A.) use is to be considered N.A. Under the
provisions of the Maharashtra Land Revenue Code, 1966, no separate permission is
required. The amount of non agricultural assessment for the land under the Integrated
Township Project shall be exempted to the extent of 50% of the normal rate. The amount of
Development Charges exempted under sub-section (3) of Section 124F of the said Act shall
be 50%. Exemption from royalty on minor minerals is also available under the Maharashtra
Minor Mineral Extraction (Development and Regulation) Rules.
Transition Policy
A Part Occupancy Certificate (LC) is issued to a building or site for a Special Township
Project that has already received location clearance and/or a LOI. If the project proponent
wishes to develop the township in accordance with these regulations, he may apply for a
Letter of Intent or Master Layout Plan.
Appeal
Anyone aggrieved by an order passed under prevailing bylaws may within forty days from
the date of communication of the order, prefer an appeal to the Director of Town Planning,
Maharashtra State, Pune. The appeal shall be decided within 60 days.