Professional Documents
Culture Documents
Per KM Comparison Conc
Per KM Comparison Conc
I MV Line Construction
5 Heavy angle Ass.( with Guy wire single pole ) ass. - 2,185.61 - - New unit price (with 800dan)
Heavy angle Ass.( with Guy wire double pole ) ass. 1 3,035.76 3,380.00
Class 1,10mt(Earth Backfill with soil) ea - 531.48 3,035.76 3,380.00 11.34
6 T-off Assembly with Guy wire ass. 1,671.40 1,975.61
Class 1,10mt(Earth Backfill with soil) ea 531.48 - -
7 Dead end Ass. with Guy wire (single pole) ass. 1,663.70 1,962.39
Dead end Ass. with Guy wire (double pole) ass. 3,924.78 New unit price (with 800dan)
Load break switch Assembly( with double pole) ass. 3,780.38 New unit price
Autoreclosure Installation( with single pole) ass. 6,815.82 - - - New unit price
MV Construction per km (assuming 100% Class 1) Sub total 26,238.25 35,425.74 35.02
Page 31
TABLE 1A - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 1 - EARTH BACK FILL
II Transformer Erection
Transformer erection with earthing ea 1 4,794.63 7,963.73 4,794.63 7,963.73 66.10
III LV Line Construction Unit Qty per km 2002/03 2006/07 2002/03 2006/07
1 Suspension Assembly ass. 8 1,089.92 1,346.17 8,719.36 10,769.36 23.51
2 Light angle Assembly ass. - -
with Guy wire 3 1,238.91 1,744.11 3,716.73 5,232.33 40.78
3 Heavy angle Assembly ass. - -
with Guy wire 3 1,242.77 1,744.54 3,728.31 5,233.62 40.38
4 2T-off Assembly ass. 1,089.92 1,369.02 - -
5 T-off Assembly ass. - -
with Guy wire 3 1,242.77 1,753.35 3,728.31 5,260.05 41.08
6 Dead end Assembly ass. - -
with Guy wire 3 1,242.77 1,748.07 3,728.31 5,244.21 40.66
7 LV assembly mounted on MV pole ass. 21.79 22.85 - -
8 Arial section swtch set 25.06 20.63 - -
9 Earthing installation set 5 107.04 282.67 535.20 1,413.35 164.08
Page 32
TABLE 1B - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 2 - SELECTED MATERIAL BACK FILL
I MV Line Construction
Class 2,11mt 300dan(Earth Backfill with selected material) (40%,11mt) ea 3 62.00 666.85
3 Light angle Ass. (with Guy wire) ass. 3 1,645.03 1,955.78 18.89
Class 2,10mt 300dan(Earth Backfill with selected material) (60%) ea 2 60.00 576.35 5,117.09 7,686.89
Class 2,11mt 300dan(Earth Backfill with selected material) (40%) ea 1 62.00 666.85
4 Tension tower (Single pole) ass. - 1,479.20 New unit price (with 800dan)
5 Heavy angle Ass.( with Guy wire single pole ) ass. - 2,185.61 - - New unit price (with 800dan)
Heavy angle Ass.( with Guy wire double pole ) ass. 1 3,035.76 3,380.00 11.34
Class 2,10mt(Earth Backfill with selected material) ea 120.00 776.59 3,035.76 3,380.00
6 T-off Assembly with Guy wire ass. 1,671.40 1,975.61 18.20
Class 2,10mt(Earth Backfill with selected material) ea 120.00 776.59 - -
7 Dead end Ass. with Guy wire (single pole) ass. 1,663.70 1,962.39 17.95
Dead end Ass. with Guy wire (double pole) ass. 3,924.78 New unit price (with 800dan)
Section switch (with droup out fuse only) ass. 2,808.70 2,916.63 3.84
Load break switch Assembly( with single pole) ass. 2,210.38 New unit price
Load break switch Assembly( with double pole) ass. 3,780.38 New unit price
Autoreclosure Installation( with single pole) ass. 6,815.82 - - New unit price
MV Construction per km (assuming 100% Class 2) Sub total 26,846.25 37,126.12 38.29
Page 31
TABLE 1B - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 2 - SELECTED MATERIAL BACK FILL
II Transformer Erection
Transformer erection with earthing ea 1 4,794.63 7,963.73 4,794.63 7,963.73 66.10
III LV Line Construction Unit Qty per km 2002/03 2006/07 2002/03 2006/07
1 Suspension Assembly ass. 8 1,089.92 1,346.17 8,719.36 10,769.36 23.51
2 Light angle Assembly ass. - -
with Guy wire 3 1,238.91 1,744.11 3,716.73 5,232.33 40.78
3 Heavy angle Assembly ass. - -
with Guy wire 3 1,242.77 1,744.54 3,728.31 5,233.62 40.38
4 2T-off Assembly ass. 1,089.92 1,369.02 - -
5 T-off Assembly ass. - -
with Guy wire 3 1,242.77 1,753.35 3,728.31 5,260.05 41.08
6 Dead end Assembly ass. - -
with Guy wire 3 1,242.77 1,748.07 3,728.31 5,244.21 40.66
7 LV assembly mounted on MV pole ass. 21.79 22.85 - -
8 Arial section swtch set 25.06 20.63 - -
9 Earthing installation set 5 107.04 282.67 535.20 1,413.35 164.08
Page 32
TABLE 1C - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 3 - SOIL- CEMENT MIX
I MV Line Construction
Class 3,11mt 300dan(Soil cement) (40%) ea 1 669.00 1,653.50 6,051.09 10,439.94 72.53
4 Tension tower (Single pole) (pole erection & Accesory mounting) ass. - 1,479.20 New unit price (with 800dan)
Tension tower (double pole) (pole erection & Accesory mounting) ass. 2,808.70 2,890.20 - -
6 T-off Assembly with Guy wire (pole erection & Accesory mounting) ass. 1,671.40 1,975.61
Class 3,10mt(cast) ea 2,540.86 2,785.51 - -
7 Dead end Ass. with Guy wire (single pole)(pole erection & Accesory mou ass. 1,663.70 1,962.39
Dead end Ass. with Guy wire (double pole)(pole erection & Accesory mou ass. 3,924.78 New unit price (with 800dan)
Section switch (with droup out fuse only) ass. 2,808.70 2,916.63
Load break switch Assembly( with single pole) ass. 2,210.38 New unit price
Load break switch Assembly( with double pole) ass. 3,780.38 New unit price
Autoreclosure Installation( with single pole) ass. 6,815.82 - - - New unit price
MV Construction per km (assuming 100% Class 3 ) Sub total 31,593.25 42,765.71 35.36
Page 31
TABLE 1C - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 3 - SOIL- CEMENT MIX
II Transformer Erection
Transformer erection with earthing ea 1 4,794.63 7,963.73 4,794.63 7,963.73 66.10
III LV Line Construction Unit Qty per km 2002/03 2006/07 2002/03 2006/07
1 Suspension Assembly ass. 8 1,089.92 1,346.17 8,719.36 10,769.36 23.51
2 Light angle Assembly ass. - -
with Guy wire 3 1,238.91 1,744.11 3,716.73 5,232.33 40.78
3 Heavy angle Assembly ass. - -
with Guy wire 3 1,242.77 1,744.54 3,728.31 5,233.62 40.38
4 2T-off Assembly ass. 1,089.92 1,369.02 - -
5 T-off Assembly ass. - -
with Guy wire 3 1,242.77 1,753.35 3,728.31 5,260.05 41.08
6 Dead end Assembly ass. - -
with Guy wire 3 1,242.77 1,748.07 3,728.31 5,244.21 40.66
7 LV assembly mounted on MV pole ass. 21.79 22.85 - -
8 Arial section swtch set 25.06 20.63 - -
9 Earthing installation set 5 107.04 282.67 535.20 1,413.35 164.08
LV Construction per km (assuming 100% Class 3 ) Sub total 25,076.01 35,458.80 41.41
Page 32
TABLE 1D - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 3 - Cast in place
I MV Line Construction
Class 3,11mt 300dan(Cast in place) (40%) ea 1 845.48 2,049.78 7,467.03 11,556.72 54.77
4 Tension tower (Single pole) ass. - 1,479.20 New unit price (with 800dan)
5 Heavy angle Ass.( with Guy wire single pole ) ass. - 2,185.61 - - New unit price (with 800dan)
Heavy angle Ass.( with Guy wire double pole ) ass. 1 3,035.76 3,380.00
Class 3,10mt(Cast in place) ea 2,813.70 3,389.19 3,035.76 3,380.00 11.34
6 T-off Assembly with Guy wire ass. 1,671.40 1,975.61
Class 3,10mt(Cast in place) ea 2,813.70 3,389.19 - -
7 Dead end Ass. with Guy wire (single pole) ass. 1,663.70 1,962.39
Dead end Ass. with Guy wire (double pole) ass. 3,924.78 New unit price (with 800dan)
Section switch (with droup out fuse only) ass. 2,808.70 2,916.63
Load break switch Assembly( with single pole) ass. 2,210.38 New unit price
Load break switch Assembly( with double pole) ass. 3,780.38 New unit price
Autoreclosure Installation( with single pole) ass. 6,815.82 - - - New unit price
MV Construction per km (assuming 100% Class 3 submerged soil) Sub total 34,679.55 50,118.52 44.52
Page 31
TABLE 1D - Comparision of construction Cost for 3-phase Concrete pole Medium and Low voltage Line construction
Class 3 - Cast in place
II Transformer Erection
Transformer erection with earthing ea 1 4,794.63 7,963.73 4,794.63 7,963.73 66.10
III LV Line Construction Unit Qty per km 2002/03 2006/07 2002/03 2006/07 % Difference
1 Suspension Assembly ass. 8 1,089.92 1,346.17 8,719.36 10,769.36 23.51
2 Light angle Assembly ass. - -
with Guy wire 3 1,238.91 1,744.11 3,716.73 5,232.33 40.78
3 Heavy angle Assembly ass. - -
with Guy wire 3 1,242.77 1,744.54 3,728.31 5,233.62 40.38
4 2T-off Assembly ass. 1,089.92 1,369.02 - -
5 T-off Assembly ass. - -
with Guy wire 3 1,242.77 1,753.35 3,728.31 5,260.05 41.08
6 Dead end Assembly ass. - -
with Guy wire 3 1,242.77 1,748.07 3,728.31 5,244.21 40.66
7 LV assembly mounted on MV pole ass. 21.79 22.85 - -
8 Arial section swtch set 25.06 20.63 - -
9 Earthing installation set 5 107.04 282.67 535.20 1,413.35 164.08
Page 32
TABLE 1G - Comparision of TRANSPORTATION Cost for 3-phase Concrete pole Medium and Low voltage Line
Pole transportation 8/9/10/11 (Transport cost per pole transportation from near by S/S with in Option km) 2,708.12 2981
IV Description Unit Qty per km 2002/03 2006/07 2002/03 2006/07 196746
Page 31
TABLE 1G - Comparision of TRANSPORTATION Cost for 3-phase Concrete pole Medium and Low voltage Line
2002/03 2006/07
Unit Qty per Km Distance from % Difference Remark
Distance from UEAP UEAP store is 1
2002/03 2006/07
Transport & Insurance Cost of LV Distribution Accessories store is 1 KM Accessories KM
materials To Transport from near by UEAP store Transportation Accessories Transportatio Accessories
with 1km assumption per km Transportation per n per km Transportation
I unit per unit
1 Suspension Assembly set 7 0.25 0.25 0.44 0.44 1.75 3.08 76.00
2 L.a assmbly set 3 0.26 0.26 0.48 0.48 0.78 1.44 84.62
3 H.A assembly set 1 0.46 0.46 0.83 0.83 0.46 0.83 80.43
II Transport cost per transformer with accessories set 1 5.14 5.14 6.97 6.97 5.14 6.97 35.60
TABLE 1G - Comparision of TRANSPORTATION Cost for 3-phase Concrete pole Medium and Low voltage Line
2002/03 2006/07
Unit Qty per Km % Difference Remark
2002/03 2006/07
III Transport & Insurance Cost of LV Distribution materials To Transport from near by UEAP store with 1km assumption
1 Suspension Assembly set 8 0.02 0.02 0.050 0.05 0.16 0.40 150.00
2 Light Angle Assembly set 3 0.02 0.02 0.030 0.03 0.06 0.09 50.00
3 Heavy angle assembely set 3 0.02 0.02 0.040 0.04 0.06 0.12 100.00
4 T-off Assembly set 5 0.02 0.02 0.040 0.04 0.10 0.20 100.00
5 dead end Assembly set 3 0.02 0.02 0.040 0.04 0.06 0.12 100.00
6 Earthing accessories set 5 0.09 0.09 0.15 0.15 0.45 0.75 66.67
7 Conductor 0 0 - -
8 ABC cable (3- phase) km 1 5.89 5.89 5.28 5.28 5.89 5.28
IV Description Unit Qty per km 2002/03 Unit price 2006/07 Unit price 2002/03 Total 2006/07 Total
LV line
construction EARTH BACKFILL 25,076.01 35,458.80 41.41